energy planning and approval strategies
DESCRIPTION
Energy Planning and Approval Strategies. Overview. outline. Strategic – BC Hydro Long Term Planning Project level Environmental Assessment Federal - Canadian Integration. BC Hydro – supply gap. BC Hydro - planning. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/1.jpg)
Energy Planning and Approval Strategies
1
![Page 2: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/2.jpg)
Overview
2
![Page 3: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/3.jpg)
outline
Strategic – BC Hydro Long Term Planning
Project level Environmental Assessment
▪ Federal - Canadian Integration
3
![Page 4: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/4.jpg)
BC Hydro – supply gap
4
![Page 5: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/5.jpg)
BC Hydro - planning
Integrated electricity planning - the long-term planning of electricity generation, transmission, and demand-side resources to reliably meet forecast requirements.
2000s - long-term acquisition plan (LTAP) every 4 yrs Needs to be reviewed and approved by BCUC
2010 Clean Energy Act – IRP replaces LTAP Same problem for analysis and decision-
making but different consultation, review, and
approval
5
![Page 6: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/6.jpg)
Utility planning
Planning context, objectivesGross (pre-DSM) demand forecastsResources (supply and DSM) – ID and
measurementDevelop resource portfoliosEvaluate and select resource
portfoliosDevelop action planConsultGet approval 6
![Page 7: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/7.jpg)
2008 LTAP developments
Application submitted to BCUC June 2008 Evidentiary update December 08
Formal hearings in BCUCBCUC decision rejecting plan July
2009 Greenpolicyprof summary
7
![Page 8: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/8.jpg)
BC government response
May 2010: Clean Energy Act passed. New IRP process Removed from BCUC scrutiny
8
![Page 9: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/9.jpg)
Evaluation
What are the consequences of removing BC Hydro planning from BCUC review?
9
![Page 10: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/10.jpg)
10
![Page 11: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/11.jpg)
Policy Objective
11
![Page 12: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/12.jpg)
Conservation first
12
![Page 13: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/13.jpg)
13
![Page 14: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/14.jpg)
14
![Page 15: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/15.jpg)
15
![Page 16: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/16.jpg)
16
![Page 17: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/17.jpg)
outline
Strategic – BC Hydro Long Term Planning
Project level Environmental Assessment
Integration
17
![Page 18: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/18.jpg)
Project level – Environmental Assessment
18
![Page 19: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/19.jpg)
Environmental Assessment
Environmental Assessment as a policy tool – a “procedural policy instrument” Requires analysis and procedure but does not
specify outcome
19
![Page 20: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/20.jpg)
Stages in EA
1. Proposal from proponent2. Screening – is EA required and if so
what kind?3. Scoping – what issues?4. Assessment of the proposal5. Report preparation, submission,
and review6. Decision: recommendation by EA
body, authoritative decision by political body
7. Monitoring and compliance follow-up
20
![Page 21: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/21.jpg)
Designated project list under CEAAhttp://
laws-lois.justice.gc.ca/eng/regulations/SOR-2012-147/index.html
21
![Page 22: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/22.jpg)
Scope of issues, Kinder Morgan pipeline expansion 1. The need for the proposed project.2. The economic feasibility of the proposed project.3. The potential commercial impacts of the proposed project.4. The potential environmental and socio-economic effects of the proposed project, including
any cumulative environmental effects that are likely to result from the project, including those required to be considered by the NEB’s Filing Manual.
5. The potential environmental and socio-economic effects of marine shipping activities that would result from the proposed Project, including the potential effects of accidents or malfunctions that may occur.
6. The appropriateness of the general route and land requirements for the proposed project.7. The suitability of the design of the proposed project.8. The terms and conditions to be included in any approval the Board may issue.9. Potential impacts of the project on Aboriginal interests.10. Potential impacts of the project on landowners and land use.11. Contingency planning for spills, accidents or malfunctions, during construction and
operation of the project.12. Safety and security during construction of the proposed project and operation of the project,
including emergency response planning and third-party damage prevention.The Board does not intend to consider the environmental and socio-economic effects associated with upstream activities, the development of oil sands, or the downstream use of the oil transported by the pipeline.
22
![Page 23: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/23.jpg)
Should upstream effects of pipelines (expansion of oil sands facilities) be considered in pipeline review EAs?
Should downstream effects of pipelines (refining, combustion in markets) be considered in pipeline review EAs
23
![Page 24: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/24.jpg)
Environmental Assessment – Federal in CanadaCanadian Environmental Assessment Act
Came into force in 1995 Since 1972, governed by cabinet
guidelines applies to anything that requires federal
approval or permit Procedures managed by
Canadian Environmental Assessment Agency, within Environment Canada
Usually, if federal EA no provincial EA 24
![Page 25: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/25.jpg)
CEAA approval standards
(a) where, taking into account the implementation of any mitigation measures that the responsible authority considers appropriate, (i) the project is not likely to cause significant adverse
environmental effects, or(ii) the project is likely to cause significant adverse
environmental effects that can be justified in the circumstances
the responsible authority may exercise any power or perform any duty or function that would permit the project to be carried out in whole or in part
25
![Page 26: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/26.jpg)
26
![Page 27: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/27.jpg)
Enviro Checklist for EA
Sustainability as core objective
Strengthen public participation
Meaningfully engage Aboriginal governments as decision makers
Legal framework for strategic and regional EA
Require comprehensive, regional cumulative effects assessments
Coordinate multiple jurisdictions with highest standards
Transparency Fair, predictable,
accessible Rights over
efficiency
27
![Page 28: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/28.jpg)
EA process criteria
Guided by sustainability principlesParticipatoryTransparent Well-informedCoordinated to avoid jurisdictional
conflicts and overlapsTimely
February 12, 2013 Sustainable Energy Policy 28
There are tradeoffs between these values. Fostering legitimacy while being timely requires adequately resourced processes
![Page 29: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/29.jpg)
Harper’s “responsible resource development” – Spring 2012
Replace CEAA Definition of environmental effect narrowed Participants limited to are “directly affected” or
have, in the review panel’s judgment, “relevant information and expertise”
Time limits Transfer authority to provinces
NEB Act – final decision moved to cabinet Fisheries Act – reduce habitat protection
![Page 30: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/30.jpg)
Bill C-38 and EA process
Sustainable Energy Policy 30
![Page 31: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/31.jpg)
Should EA procedures allow for the approval of projects likely to cause significant adverse environmental effects?
Should EA’s have time limits?
Sustainable Energy Policy 31
![Page 32: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/32.jpg)
Cumulative effects?
“effects that are additive or interactive and result from the recurrence of actions over time. Cumulative impacts are incremental and result when undertakings build on or add to the impacts of previous impacts.”
Consideration required in federal rules, permitted but not required in BC
What is the best way to deal with cumulative effects in project level assessments?
32
![Page 33: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/33.jpg)
Environmental Assessment - conclusion
requires elaborate assessment demonstration of awareness of concerns consideration of environmental impacts
and mitigation measures but project can still be approved if justified By forcing agencies to consider
environmental consequences, environmental assessment is a critical tool, but it does not affect the balance of values decision-makers ultimately apply.
February 12, 2013 Sustainable Energy Policy 33
![Page 34: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/34.jpg)
Overview
34
![Page 35: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/35.jpg)
Institutions for renewable energy expansion – criteria (Jaccard et al)
35
![Page 36: Energy Planning and Approval Strategies](https://reader035.vdocuments.net/reader035/viewer/2022062316/568168ab550346895ddf5081/html5/thumbnails/36.jpg)
Alternatives, consequencesJaccard et alIRP + PROJECT SPECIFIC ASSESSMENT/APPROVALS risks larger than
necessary local environmental effects
Risks less satisfied public
STRATEGIC ASSESSMENT Risks delay in
renewable development (and climate change mitigation)
36
An important tradeoff that needs to be considered in process design