279 Lorne Avenue Stratford, ON Canada N4Z 1H3 Tel: (519) 814-9283 1-833-299-9283 FAX: (519) 814-9288 www.jutzi.com ENERGY ● WATER ● SERVICE COOLING TOWER/CONDENSER TREATMENT SPEC INFORMATION 1) Provide a complete water treatment system for a cooling tower. Supply one Jutzi Water Technologies Cooling Water Package with part #420200200. Use Jutzi Water Technologies for all cooling tower/condenser water treatment. This should include: pretreatment (if required due to water makeup characteristics). Supply sufficient chemicals for initial startup and one month’s operation. The biocide program should be compliant with current Legionella control protocols from the CTI or ASHRAE. 2) Chemical and Test Kit Supply: 2 1. Supply one pail of Jutzi Water Technologies Formula CW 2520 Scale and Corrosion Inhibitor – (20kg), part #420425203 2. Supply one pail Jutzi Water Technologies Formula AA 5445 – alkalinity adjuster (20kg), part #421054452 (if makeup water total alkalinity requires adjustment) 3. Supply one pail of Jutzi Water Technologies Formula MB 3040 – dispersant (22kg), part #420630403 4. Supply one pail of Jutzi Water Technologies Formula MB 3090 – biocide (20kg), part #420630902 5. Supply one Jutzi Water Technologies Cooling Tower / Condenser Water Treatment Manual 6. Supply one Jutzi Water Technologies Test Kit 100 part #424410000 7. Supply one Jutzi Water Technologies TDS/PH Meter part# 424200086 8. Supply sufficient Jutzi Water Technologies Formula MC 6220 – (20kg), part# 421362202 pre-operational cleaner 3) Equipment Supply: Include all accessories required from Jutzi Water Technologies to provide a complete cooling water treatment system fully operational, including: 1. One - Turbine Meter – part #442110216 2. One - Cable with Hall Effect Sensor – part# 442110253 3. One - Advantage Conductivity based controller (with bleed, inhibitor and biocide feed) part# 442601102 with flow switch and conductivity cell 4. One - 3/4” MBV – part# 443104075 5. Four - Injection Pumps – part# 430110021 6. One - PVC Board – part# 449900790 7. Four - PVC L-Brackets – part# 449900798 8. One – Feed Water Pre-Treatment System (Non-Electric) – part# 450201036 4) Pre-operational Cleaning: 1. Ensure that the new cooling tower is properly passivated to prevent “White Rust” in accordance with the manufacturer’s guidelines. 2. Jutzi Water Technologies Formula MC 6220 – (20kg), part# 421362202 pre-operational cleaner should be maintained at 10 gallons per 1000 gallons of system water. Formula MC 6220 should be circulated for 4-8 hours then flushed and drained 2-3 times. The cooling tower

Upload: others

Post on 07-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ENERGY WATER SERVICE · all cooling tower/condenser water treatment. This should include: pretreatment (if required due to water makeup characteristics). Supply sufficient chemicals

279 Lorne Avenue Stratford, ON Canada N4Z 1H3

Tel: (519) 814-9283 1-833-299-9283 FAX: (519) 814-9288 www.jutzi.com

ENERGY ● WATER ● SERVICE

COOLING TOWER/CONDENSER TREATMENT SPEC INFORMATION

1) Provide a complete water treatment system for a cooling tower. Supply one Jutzi Water Technologies Cooling Water Package with part #420200200. Use Jutzi Water Technologies for all cooling tower/condenser water treatment. This should include: pretreatment (if required due to water makeup characteristics). Supply sufficient chemicals for initial startup and one month’s operation. The biocide program should be compliant with current Legionella control protocols from the CTI or ASHRAE.

2) Chemical and Test Kit Supply: 2 1. Supply one pail of Jutzi Water Technologies Formula CW 2520 Scale and Corrosion

Inhibitor – (20kg), part #420425203 2. Supply one pail Jutzi Water Technologies Formula AA 5445 – alkalinity adjuster (20kg),

part #421054452 (if makeup water total alkalinity requires adjustment) 3. Supply one pail of Jutzi Water Technologies Formula MB 3040 – dispersant (22kg),

part #420630403 4. Supply one pail of Jutzi Water Technologies Formula MB 3090 – biocide (20kg),

part #420630902 5. Supply one Jutzi Water Technologies Cooling Tower / Condenser Water Treatment Manual 6. Supply one Jutzi Water Technologies Test Kit 100 part #424410000 7. Supply one Jutzi Water Technologies TDS/PH Meter part# 424200086 8. Supply sufficient Jutzi Water Technologies Formula MC 6220 – (20kg), part# 421362202

pre-operational cleaner 3) Equipment Supply: Include all accessories required from Jutzi Water Technologies to provide a complete cooling

water treatment system fully operational, including: 1. One - Turbine Meter – part #442110216 2. One - Cable with Hall Effect Sensor – part# 442110253 3. One - Advantage Conductivity based controller (with bleed, inhibitor and biocide feed)

part# 442601102 with flow switch and conductivity cell 4. One - 3⁄4” MBV – part# 443104075 5. Four - Injection Pumps – part# 430110021 6. One - PVC Board – part# 449900790 7. Four - PVC L-Brackets – part# 449900798 8. One – Feed Water Pre-Treatment System (Non-Electric) – part# 450201036 4) Pre-operational Cleaning:

1. Ensure that the new cooling tower is properly passivated to prevent “White Rust” in accordance with the manufacturer’s guidelines.

2. Jutzi Water Technologies Formula MC 6220 – (20kg), part# 421362202 pre-operational cleaner should be maintained at 10 gallons per 1000 gallons of system water. Formula MC 6220 should be circulated for 4-8 hours then flushed and drained 2-3 times. The cooling tower

Page 2: ENERGY WATER SERVICE · all cooling tower/condenser water treatment. This should include: pretreatment (if required due to water makeup characteristics). Supply sufficient chemicals

279 Lorne Avenue Stratford, ON Canada N4Z 1H3

Tel: (519) 814-9283 1-833-299-9283 FAX: (519) 814-9288 www.jutzi.com

ENERGY ● WATER ● SERVICE

should be bypassed during the cleaning process. Blowout all low points in the system to remove dirt. System is clean when the system conductivity equals makeup water conductivity, iron levels equal makeup iron and water is clean and clear. Once clean either drain out the piping if it is to be idle or ad Jutzi Water Technologies Formula CW 2520 and biocide.

5) Guarantee the systems provided by Jutzi Water Technologies for one year 6) The first month of service by Jutzi Water Technologies should include the following:

a) initial analysis to optimize correct treatment levels b) initial start-up c) start-up supervision d) personnel training including demonstrations and instructions e) monthly service and consultation f) provision of record forms and log sheets g) laboratory and technical assistance as determined by a Jutzi Water Technologies

representative