Eng Eyad Haddad Construction Project Management1
Construction Project Management
Faculty of Applied Engineering and Urban Planning
Civil Engineering Department
Week 1 Lect 1
2nd Semester 20082009
UP Copyrights 2008
Const
ruct
ion P
roje
ct
Managem
ent
Eng Eyad Haddad
Eng Eyad Haddad Construction Project Management
2
Construction Project Management
AgendaAbout Eyad Haddad
Structure and delivery
Assessment
Ground rules
About Construction Project Management
What makes Construction Project Management important
Mission Statement
Eng Eyad Haddad Construction Project Management
3
Construction Project Management
About Eyad Haddad
Master Degree of Construction Management
Eyad Haddad contact details
Website httpwwwupedups
Email ehadad1977hotmailcom
Room BK008
Office Hours (1100 ndash 930 )الثالثاء( amp 1100 ndash 930 )االحد
Mobile ---
All lecture slides assignments Notes will be posted on the web as can
as possible
Eng Eyad Haddad Construction Project Management
4
Construction Project Management
Structure and delivery
2 lectures per week (90 minutes each)
Students will be expected to attend the lectures
)1100 ndash 930 (الثالثاء) amp 1100 ndash 930(االحد
Students will be expected to have undertaken a
wide range of reading
Eng Eyad Haddad Construction Project Management
5
Construction Project Management
Resources
1048766 The World Wide Web (www)
1048766 Library books
1048766 Magazines and Journals
1048766 Most key documents will be available electronically
Eng Eyad Haddad Construction Project Management
6
Construction Project Management
Assessment1 Coursework Assignment you will be expected to Write
5 assignments this term (- marks)
2 5-quizes (short exams) during the lecture without prior
notice (- marks)
bull Lectures attendance (- marks)
bull Term Project amp Presentation (- marks)
bull Mid-Term exam (20 marks)
bull 2hour final exam (60 marks)
Eng Eyad Haddad Construction Project Management
7
Construction Project Management
Ground rules Coming in late
Disruption of any kind
Donrsquot ask for an extension without good Reason
Individual work only is allowed Group
discussions for concepts and problems
Donrsquot copy previous year work
When confused ask instructor
Academic honesty
Eng Eyad Haddad Construction Project Management
8
Construction Project Management
Ground rules Cont
Cell Phones are strictly prohibited Please
Donrsquot bring your cell to the lecture or
keep it always closed
Eng Eyad Haddad Construction Project Management
9
Construction Project Management
Course Objectives Project stages
Project delivery approaches and contract types
Detailed cost estimation
Planning
Scheduling using Bar charts CPM
Resource scheduling amp Resource leveling
Scheduling of Repetitive Projects
Time-Cost Trade-off Analysis
Cash flow analysis
Project updating and delay analysis
Bidding analysis and pricing policy
Project control techniques
Eng Eyad Haddad Construction Project Management
10
Construction Project ManagementSyllabus
1 INTRODUCTION 11 Construction Industry 12 The Players 13 Categories of Construction Projects 14 Project Manager 15 Project Phases 151 Pre-construction 152 Procurement Phase 153 Construction Phase 154 Closeout
2 CONTRACT STRATEGY 21 Organization Structures 22 Contractual Relationships 23 Construction Contracts 24 Contract Documents 25 Tender Documents 26 Tendering Methods 27 Bid Evaluation
Eng Eyad Haddad Construction Project Management
11
Construction Project Management
Syllabus (Cont)
3 PLANNING AND SCHEDULING
31 Planning
311 Work Breakdown
312 Activity Duration
313 Logical Relationships
314 Overlap
315 Network Representation
32 Scheduling
321 Activity on Arrows )CPM(
322 Activity on Nodes )PDM(
323 Bar Chart
324 Time Scaled Diagram
325 Program Evaluation and Review Techniques )PERT(
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
2
Construction Project Management
AgendaAbout Eyad Haddad
Structure and delivery
Assessment
Ground rules
About Construction Project Management
What makes Construction Project Management important
Mission Statement
Eng Eyad Haddad Construction Project Management
3
Construction Project Management
About Eyad Haddad
Master Degree of Construction Management
Eyad Haddad contact details
Website httpwwwupedups
Email ehadad1977hotmailcom
Room BK008
Office Hours (1100 ndash 930 )الثالثاء( amp 1100 ndash 930 )االحد
Mobile ---
All lecture slides assignments Notes will be posted on the web as can
as possible
Eng Eyad Haddad Construction Project Management
4
Construction Project Management
Structure and delivery
2 lectures per week (90 minutes each)
Students will be expected to attend the lectures
)1100 ndash 930 (الثالثاء) amp 1100 ndash 930(االحد
Students will be expected to have undertaken a
wide range of reading
Eng Eyad Haddad Construction Project Management
5
Construction Project Management
Resources
1048766 The World Wide Web (www)
1048766 Library books
1048766 Magazines and Journals
1048766 Most key documents will be available electronically
Eng Eyad Haddad Construction Project Management
6
Construction Project Management
Assessment1 Coursework Assignment you will be expected to Write
5 assignments this term (- marks)
2 5-quizes (short exams) during the lecture without prior
notice (- marks)
bull Lectures attendance (- marks)
bull Term Project amp Presentation (- marks)
bull Mid-Term exam (20 marks)
bull 2hour final exam (60 marks)
Eng Eyad Haddad Construction Project Management
7
Construction Project Management
Ground rules Coming in late
Disruption of any kind
Donrsquot ask for an extension without good Reason
Individual work only is allowed Group
discussions for concepts and problems
Donrsquot copy previous year work
When confused ask instructor
Academic honesty
Eng Eyad Haddad Construction Project Management
8
Construction Project Management
Ground rules Cont
Cell Phones are strictly prohibited Please
Donrsquot bring your cell to the lecture or
keep it always closed
Eng Eyad Haddad Construction Project Management
9
Construction Project Management
Course Objectives Project stages
Project delivery approaches and contract types
Detailed cost estimation
Planning
Scheduling using Bar charts CPM
Resource scheduling amp Resource leveling
Scheduling of Repetitive Projects
Time-Cost Trade-off Analysis
Cash flow analysis
Project updating and delay analysis
Bidding analysis and pricing policy
Project control techniques
Eng Eyad Haddad Construction Project Management
10
Construction Project ManagementSyllabus
1 INTRODUCTION 11 Construction Industry 12 The Players 13 Categories of Construction Projects 14 Project Manager 15 Project Phases 151 Pre-construction 152 Procurement Phase 153 Construction Phase 154 Closeout
2 CONTRACT STRATEGY 21 Organization Structures 22 Contractual Relationships 23 Construction Contracts 24 Contract Documents 25 Tender Documents 26 Tendering Methods 27 Bid Evaluation
Eng Eyad Haddad Construction Project Management
11
Construction Project Management
Syllabus (Cont)
3 PLANNING AND SCHEDULING
31 Planning
311 Work Breakdown
312 Activity Duration
313 Logical Relationships
314 Overlap
315 Network Representation
32 Scheduling
321 Activity on Arrows )CPM(
322 Activity on Nodes )PDM(
323 Bar Chart
324 Time Scaled Diagram
325 Program Evaluation and Review Techniques )PERT(
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
3
Construction Project Management
About Eyad Haddad
Master Degree of Construction Management
Eyad Haddad contact details
Website httpwwwupedups
Email ehadad1977hotmailcom
Room BK008
Office Hours (1100 ndash 930 )الثالثاء( amp 1100 ndash 930 )االحد
Mobile ---
All lecture slides assignments Notes will be posted on the web as can
as possible
Eng Eyad Haddad Construction Project Management
4
Construction Project Management
Structure and delivery
2 lectures per week (90 minutes each)
Students will be expected to attend the lectures
)1100 ndash 930 (الثالثاء) amp 1100 ndash 930(االحد
Students will be expected to have undertaken a
wide range of reading
Eng Eyad Haddad Construction Project Management
5
Construction Project Management
Resources
1048766 The World Wide Web (www)
1048766 Library books
1048766 Magazines and Journals
1048766 Most key documents will be available electronically
Eng Eyad Haddad Construction Project Management
6
Construction Project Management
Assessment1 Coursework Assignment you will be expected to Write
5 assignments this term (- marks)
2 5-quizes (short exams) during the lecture without prior
notice (- marks)
bull Lectures attendance (- marks)
bull Term Project amp Presentation (- marks)
bull Mid-Term exam (20 marks)
bull 2hour final exam (60 marks)
Eng Eyad Haddad Construction Project Management
7
Construction Project Management
Ground rules Coming in late
Disruption of any kind
Donrsquot ask for an extension without good Reason
Individual work only is allowed Group
discussions for concepts and problems
Donrsquot copy previous year work
When confused ask instructor
Academic honesty
Eng Eyad Haddad Construction Project Management
8
Construction Project Management
Ground rules Cont
Cell Phones are strictly prohibited Please
Donrsquot bring your cell to the lecture or
keep it always closed
Eng Eyad Haddad Construction Project Management
9
Construction Project Management
Course Objectives Project stages
Project delivery approaches and contract types
Detailed cost estimation
Planning
Scheduling using Bar charts CPM
Resource scheduling amp Resource leveling
Scheduling of Repetitive Projects
Time-Cost Trade-off Analysis
Cash flow analysis
Project updating and delay analysis
Bidding analysis and pricing policy
Project control techniques
Eng Eyad Haddad Construction Project Management
10
Construction Project ManagementSyllabus
1 INTRODUCTION 11 Construction Industry 12 The Players 13 Categories of Construction Projects 14 Project Manager 15 Project Phases 151 Pre-construction 152 Procurement Phase 153 Construction Phase 154 Closeout
2 CONTRACT STRATEGY 21 Organization Structures 22 Contractual Relationships 23 Construction Contracts 24 Contract Documents 25 Tender Documents 26 Tendering Methods 27 Bid Evaluation
Eng Eyad Haddad Construction Project Management
11
Construction Project Management
Syllabus (Cont)
3 PLANNING AND SCHEDULING
31 Planning
311 Work Breakdown
312 Activity Duration
313 Logical Relationships
314 Overlap
315 Network Representation
32 Scheduling
321 Activity on Arrows )CPM(
322 Activity on Nodes )PDM(
323 Bar Chart
324 Time Scaled Diagram
325 Program Evaluation and Review Techniques )PERT(
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
4
Construction Project Management
Structure and delivery
2 lectures per week (90 minutes each)
Students will be expected to attend the lectures
)1100 ndash 930 (الثالثاء) amp 1100 ndash 930(االحد
Students will be expected to have undertaken a
wide range of reading
Eng Eyad Haddad Construction Project Management
5
Construction Project Management
Resources
1048766 The World Wide Web (www)
1048766 Library books
1048766 Magazines and Journals
1048766 Most key documents will be available electronically
Eng Eyad Haddad Construction Project Management
6
Construction Project Management
Assessment1 Coursework Assignment you will be expected to Write
5 assignments this term (- marks)
2 5-quizes (short exams) during the lecture without prior
notice (- marks)
bull Lectures attendance (- marks)
bull Term Project amp Presentation (- marks)
bull Mid-Term exam (20 marks)
bull 2hour final exam (60 marks)
Eng Eyad Haddad Construction Project Management
7
Construction Project Management
Ground rules Coming in late
Disruption of any kind
Donrsquot ask for an extension without good Reason
Individual work only is allowed Group
discussions for concepts and problems
Donrsquot copy previous year work
When confused ask instructor
Academic honesty
Eng Eyad Haddad Construction Project Management
8
Construction Project Management
Ground rules Cont
Cell Phones are strictly prohibited Please
Donrsquot bring your cell to the lecture or
keep it always closed
Eng Eyad Haddad Construction Project Management
9
Construction Project Management
Course Objectives Project stages
Project delivery approaches and contract types
Detailed cost estimation
Planning
Scheduling using Bar charts CPM
Resource scheduling amp Resource leveling
Scheduling of Repetitive Projects
Time-Cost Trade-off Analysis
Cash flow analysis
Project updating and delay analysis
Bidding analysis and pricing policy
Project control techniques
Eng Eyad Haddad Construction Project Management
10
Construction Project ManagementSyllabus
1 INTRODUCTION 11 Construction Industry 12 The Players 13 Categories of Construction Projects 14 Project Manager 15 Project Phases 151 Pre-construction 152 Procurement Phase 153 Construction Phase 154 Closeout
2 CONTRACT STRATEGY 21 Organization Structures 22 Contractual Relationships 23 Construction Contracts 24 Contract Documents 25 Tender Documents 26 Tendering Methods 27 Bid Evaluation
Eng Eyad Haddad Construction Project Management
11
Construction Project Management
Syllabus (Cont)
3 PLANNING AND SCHEDULING
31 Planning
311 Work Breakdown
312 Activity Duration
313 Logical Relationships
314 Overlap
315 Network Representation
32 Scheduling
321 Activity on Arrows )CPM(
322 Activity on Nodes )PDM(
323 Bar Chart
324 Time Scaled Diagram
325 Program Evaluation and Review Techniques )PERT(
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
5
Construction Project Management
Resources
1048766 The World Wide Web (www)
1048766 Library books
1048766 Magazines and Journals
1048766 Most key documents will be available electronically
Eng Eyad Haddad Construction Project Management
6
Construction Project Management
Assessment1 Coursework Assignment you will be expected to Write
5 assignments this term (- marks)
2 5-quizes (short exams) during the lecture without prior
notice (- marks)
bull Lectures attendance (- marks)
bull Term Project amp Presentation (- marks)
bull Mid-Term exam (20 marks)
bull 2hour final exam (60 marks)
Eng Eyad Haddad Construction Project Management
7
Construction Project Management
Ground rules Coming in late
Disruption of any kind
Donrsquot ask for an extension without good Reason
Individual work only is allowed Group
discussions for concepts and problems
Donrsquot copy previous year work
When confused ask instructor
Academic honesty
Eng Eyad Haddad Construction Project Management
8
Construction Project Management
Ground rules Cont
Cell Phones are strictly prohibited Please
Donrsquot bring your cell to the lecture or
keep it always closed
Eng Eyad Haddad Construction Project Management
9
Construction Project Management
Course Objectives Project stages
Project delivery approaches and contract types
Detailed cost estimation
Planning
Scheduling using Bar charts CPM
Resource scheduling amp Resource leveling
Scheduling of Repetitive Projects
Time-Cost Trade-off Analysis
Cash flow analysis
Project updating and delay analysis
Bidding analysis and pricing policy
Project control techniques
Eng Eyad Haddad Construction Project Management
10
Construction Project ManagementSyllabus
1 INTRODUCTION 11 Construction Industry 12 The Players 13 Categories of Construction Projects 14 Project Manager 15 Project Phases 151 Pre-construction 152 Procurement Phase 153 Construction Phase 154 Closeout
2 CONTRACT STRATEGY 21 Organization Structures 22 Contractual Relationships 23 Construction Contracts 24 Contract Documents 25 Tender Documents 26 Tendering Methods 27 Bid Evaluation
Eng Eyad Haddad Construction Project Management
11
Construction Project Management
Syllabus (Cont)
3 PLANNING AND SCHEDULING
31 Planning
311 Work Breakdown
312 Activity Duration
313 Logical Relationships
314 Overlap
315 Network Representation
32 Scheduling
321 Activity on Arrows )CPM(
322 Activity on Nodes )PDM(
323 Bar Chart
324 Time Scaled Diagram
325 Program Evaluation and Review Techniques )PERT(
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
6
Construction Project Management
Assessment1 Coursework Assignment you will be expected to Write
5 assignments this term (- marks)
2 5-quizes (short exams) during the lecture without prior
notice (- marks)
bull Lectures attendance (- marks)
bull Term Project amp Presentation (- marks)
bull Mid-Term exam (20 marks)
bull 2hour final exam (60 marks)
Eng Eyad Haddad Construction Project Management
7
Construction Project Management
Ground rules Coming in late
Disruption of any kind
Donrsquot ask for an extension without good Reason
Individual work only is allowed Group
discussions for concepts and problems
Donrsquot copy previous year work
When confused ask instructor
Academic honesty
Eng Eyad Haddad Construction Project Management
8
Construction Project Management
Ground rules Cont
Cell Phones are strictly prohibited Please
Donrsquot bring your cell to the lecture or
keep it always closed
Eng Eyad Haddad Construction Project Management
9
Construction Project Management
Course Objectives Project stages
Project delivery approaches and contract types
Detailed cost estimation
Planning
Scheduling using Bar charts CPM
Resource scheduling amp Resource leveling
Scheduling of Repetitive Projects
Time-Cost Trade-off Analysis
Cash flow analysis
Project updating and delay analysis
Bidding analysis and pricing policy
Project control techniques
Eng Eyad Haddad Construction Project Management
10
Construction Project ManagementSyllabus
1 INTRODUCTION 11 Construction Industry 12 The Players 13 Categories of Construction Projects 14 Project Manager 15 Project Phases 151 Pre-construction 152 Procurement Phase 153 Construction Phase 154 Closeout
2 CONTRACT STRATEGY 21 Organization Structures 22 Contractual Relationships 23 Construction Contracts 24 Contract Documents 25 Tender Documents 26 Tendering Methods 27 Bid Evaluation
Eng Eyad Haddad Construction Project Management
11
Construction Project Management
Syllabus (Cont)
3 PLANNING AND SCHEDULING
31 Planning
311 Work Breakdown
312 Activity Duration
313 Logical Relationships
314 Overlap
315 Network Representation
32 Scheduling
321 Activity on Arrows )CPM(
322 Activity on Nodes )PDM(
323 Bar Chart
324 Time Scaled Diagram
325 Program Evaluation and Review Techniques )PERT(
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
7
Construction Project Management
Ground rules Coming in late
Disruption of any kind
Donrsquot ask for an extension without good Reason
Individual work only is allowed Group
discussions for concepts and problems
Donrsquot copy previous year work
When confused ask instructor
Academic honesty
Eng Eyad Haddad Construction Project Management
8
Construction Project Management
Ground rules Cont
Cell Phones are strictly prohibited Please
Donrsquot bring your cell to the lecture or
keep it always closed
Eng Eyad Haddad Construction Project Management
9
Construction Project Management
Course Objectives Project stages
Project delivery approaches and contract types
Detailed cost estimation
Planning
Scheduling using Bar charts CPM
Resource scheduling amp Resource leveling
Scheduling of Repetitive Projects
Time-Cost Trade-off Analysis
Cash flow analysis
Project updating and delay analysis
Bidding analysis and pricing policy
Project control techniques
Eng Eyad Haddad Construction Project Management
10
Construction Project ManagementSyllabus
1 INTRODUCTION 11 Construction Industry 12 The Players 13 Categories of Construction Projects 14 Project Manager 15 Project Phases 151 Pre-construction 152 Procurement Phase 153 Construction Phase 154 Closeout
2 CONTRACT STRATEGY 21 Organization Structures 22 Contractual Relationships 23 Construction Contracts 24 Contract Documents 25 Tender Documents 26 Tendering Methods 27 Bid Evaluation
Eng Eyad Haddad Construction Project Management
11
Construction Project Management
Syllabus (Cont)
3 PLANNING AND SCHEDULING
31 Planning
311 Work Breakdown
312 Activity Duration
313 Logical Relationships
314 Overlap
315 Network Representation
32 Scheduling
321 Activity on Arrows )CPM(
322 Activity on Nodes )PDM(
323 Bar Chart
324 Time Scaled Diagram
325 Program Evaluation and Review Techniques )PERT(
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
8
Construction Project Management
Ground rules Cont
Cell Phones are strictly prohibited Please
Donrsquot bring your cell to the lecture or
keep it always closed
Eng Eyad Haddad Construction Project Management
9
Construction Project Management
Course Objectives Project stages
Project delivery approaches and contract types
Detailed cost estimation
Planning
Scheduling using Bar charts CPM
Resource scheduling amp Resource leveling
Scheduling of Repetitive Projects
Time-Cost Trade-off Analysis
Cash flow analysis
Project updating and delay analysis
Bidding analysis and pricing policy
Project control techniques
Eng Eyad Haddad Construction Project Management
10
Construction Project ManagementSyllabus
1 INTRODUCTION 11 Construction Industry 12 The Players 13 Categories of Construction Projects 14 Project Manager 15 Project Phases 151 Pre-construction 152 Procurement Phase 153 Construction Phase 154 Closeout
2 CONTRACT STRATEGY 21 Organization Structures 22 Contractual Relationships 23 Construction Contracts 24 Contract Documents 25 Tender Documents 26 Tendering Methods 27 Bid Evaluation
Eng Eyad Haddad Construction Project Management
11
Construction Project Management
Syllabus (Cont)
3 PLANNING AND SCHEDULING
31 Planning
311 Work Breakdown
312 Activity Duration
313 Logical Relationships
314 Overlap
315 Network Representation
32 Scheduling
321 Activity on Arrows )CPM(
322 Activity on Nodes )PDM(
323 Bar Chart
324 Time Scaled Diagram
325 Program Evaluation and Review Techniques )PERT(
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
9
Construction Project Management
Course Objectives Project stages
Project delivery approaches and contract types
Detailed cost estimation
Planning
Scheduling using Bar charts CPM
Resource scheduling amp Resource leveling
Scheduling of Repetitive Projects
Time-Cost Trade-off Analysis
Cash flow analysis
Project updating and delay analysis
Bidding analysis and pricing policy
Project control techniques
Eng Eyad Haddad Construction Project Management
10
Construction Project ManagementSyllabus
1 INTRODUCTION 11 Construction Industry 12 The Players 13 Categories of Construction Projects 14 Project Manager 15 Project Phases 151 Pre-construction 152 Procurement Phase 153 Construction Phase 154 Closeout
2 CONTRACT STRATEGY 21 Organization Structures 22 Contractual Relationships 23 Construction Contracts 24 Contract Documents 25 Tender Documents 26 Tendering Methods 27 Bid Evaluation
Eng Eyad Haddad Construction Project Management
11
Construction Project Management
Syllabus (Cont)
3 PLANNING AND SCHEDULING
31 Planning
311 Work Breakdown
312 Activity Duration
313 Logical Relationships
314 Overlap
315 Network Representation
32 Scheduling
321 Activity on Arrows )CPM(
322 Activity on Nodes )PDM(
323 Bar Chart
324 Time Scaled Diagram
325 Program Evaluation and Review Techniques )PERT(
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
10
Construction Project ManagementSyllabus
1 INTRODUCTION 11 Construction Industry 12 The Players 13 Categories of Construction Projects 14 Project Manager 15 Project Phases 151 Pre-construction 152 Procurement Phase 153 Construction Phase 154 Closeout
2 CONTRACT STRATEGY 21 Organization Structures 22 Contractual Relationships 23 Construction Contracts 24 Contract Documents 25 Tender Documents 26 Tendering Methods 27 Bid Evaluation
Eng Eyad Haddad Construction Project Management
11
Construction Project Management
Syllabus (Cont)
3 PLANNING AND SCHEDULING
31 Planning
311 Work Breakdown
312 Activity Duration
313 Logical Relationships
314 Overlap
315 Network Representation
32 Scheduling
321 Activity on Arrows )CPM(
322 Activity on Nodes )PDM(
323 Bar Chart
324 Time Scaled Diagram
325 Program Evaluation and Review Techniques )PERT(
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
11
Construction Project Management
Syllabus (Cont)
3 PLANNING AND SCHEDULING
31 Planning
311 Work Breakdown
312 Activity Duration
313 Logical Relationships
314 Overlap
315 Network Representation
32 Scheduling
321 Activity on Arrows )CPM(
322 Activity on Nodes )PDM(
323 Bar Chart
324 Time Scaled Diagram
325 Program Evaluation and Review Techniques )PERT(
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
12
Construction Project Management
Syllabus (Cont)4 RESOURCE MANAGEMENT
41 Objectives42 Resource Scheduling43 Resource Leveling
5 SCHEDULING OF REPETITIVE PROJECTS51 Linear Projects52 Summary Diagrams53 Line of Balance )LOB( Representation
531 Resource-driven Scheduling 532 CPM-LOB Integration 533 Drawing LOB
6 SCHEDULE UPDATING AND DELAYS 61 Scheduling Updating 62 Delays 621 Type of Delays 622 The As-Built Schedule 623 Analysis of Concurrent Delays
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
13
Construction Project Management
Syllabus (Cont)7 CASH FLOW AND FINANCE MANAGEMENT 71 Contract Cash Flow 711 Contract Cost-Expense Curves 712 Cost of Finance 72 Project Cash Flow 721 Profit 722 Payback Period 723 Maximum Capital Lock-up 73 Discounted cash Flow 731 Net Present Value 732 Internal Rate of Return 8 TIME-COST TRADE-OFF 81 Activity Time-Cost Relationship 82 Contract Time-Cost Relationship 83 Optimum Contract Duration
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
14
Construction Project Management
Syllabus (Cont)9 ESTIMATING AND TENDERING
91 Cost Estimating Steps92 Preparation of Method Statement93 Risk Management931 Risk Identification932 Risk Responses94 Estimating Direct Cost941 Unit Rate Estimating942 Operational Estimating95 Estimating Indirect Cost951 Site Overheads952 Head Office Overheads96 Producing Tender Price961 Costs962 Mark-up97 Pricing Policy971 Balanced Bid972 Unbalanced Bid973 Method Related Charg
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
15
Construction Project Management
Syllabus (Cont)
10 COST CONTROL
101 Developing Cost Curves
102 The Earned Value Concept
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
16
Construction Project Management
About Construction Project Management
Syllabus
What makes Construction Project
Management Challenging
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
17
Construction Project Management
Construction Vs Manufacturing
Uncertain demand
More simulation in manufacturing
More data available fewer changes
Process and product is well established
Higher ability to standardize and control
the product
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
18
Construction Project Management
Construction Vs Manufacturing
1048766 One-of a kind Project specific
1048766 Many specialties
1048766 Location weather
1048766 High risk
1048766 Availability of resources
1048766 On time on budget
1048766 Social Political amp Environmental Impact
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
19
Construction Project Management
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
20
Construction Project Management
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
21
Construction Project Management
Software Packages
1048766 Primavera
1048766 Microsoft Project
1048766 Many other software
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
22
Construction Project Management
Mission Statement
The mission is to help organizations achieve
their project objectives of scope quality
budget and schedule within the context of the
natural social and political environment in
which the project is being developed
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
23
Limits of the project
Total pages of the project from 20-30 pages
Font size 12
Title and sub titles is bold
The space between rows is 150
The project must consists of the following items
1 Abstract (05-1) pages
2 Introduction (05 ndash 1) pages
3 Literature review (2 ndash 10) pages
4 Methodology (1 ndash 2) pages
5 Data collection (1 ndash 2) pages
6 Analysis (1 ndash 5) pages
7 Discussion (1 ndash 5) pages
8 Conclusions amp recommendations (1 ndash 5) pages
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-
Eng Eyad Haddad Construction Project Management
24
Questions
- Slide 1
- Slide 2
- Slide 3
- Slide 4
- Slide 5
- Slide 6
- Slide 7
- Slide 8
- Slide 9
- Slide 10
- Slide 11
- Slide 12
- Slide 13
- Slide 14
- Slide 15
- Slide 16
- Slide 17
- Slide 18
- Slide 19
- Slide 20
- Slide 21
- Slide 22
- Slide 23
- Slide 24
-