eng470 engineering honours thesis...i eng470 engineering honours thesis wind-solar energy...
TRANSCRIPT
i
ENG470 Engineering Honours Thesis
Wind-Solar Energy Integration including Battery Storage at Murdoch University Project Report
Yuvraj Singh
Unit coordinator: Dr. Gareth Lee
Supervisor: Dr. Ali Arefi, Mr. Craig Carter
ii
Declaration
I declare that this thesis is solely my own research and does not contain any content from
any previous studies conducted on the similar topic.
Signed:
Yuvraj Singh
iii
Abstract
This report demonstrates the process involved to identify the most economic renewable
energy generation system for Murdoch University (MU). The most economic renewable
energy generation system that would help in reducing the annual electricity consumption off
the grid for MU. The analysis involved PV System, Wind System, Wind-PV System and Wind-
PV System including the battery storage system. The analysis commenced with the
assessment of the availability of solar and wind resource at the MU. Western Australia gets a
significant amount of solar irradiance throughout the year and it was available to download
from the website of Bureau of Meteorology. The wind speed data were obtained from the
weather station located Murdoch University, which helped to determine the strength and
intensity of wind speed. For the purpose of the analysis, solar irradiance data and wind speed
data for the year 2015 was used for the specific reason, explained further in the report.
Murdoch University electricity consumption in the year 2015 was 22.29 GWh with the
maximum load of 5.78 MW. Mr Andrew Hanning, Energy Manager at MU helped to obtain
the load consumption data of MU. Then analysis followed by the identification of the energy
production potential of solar and wind using the photovoltaics and wind turbines. Microsoft
Excel and Homer, a computer software model helped to calculate the energy production of
photovoltaics and wind turbines. A 2.0 MW PV system was used for the analysis, as the study
conducted by the previous student concluded it to be the maximum size that could be
installed on the rooftop of MU. Wind system included two Enercon E-53 wind turbines each
with 800kW rated capacity. The selection of the wind turbine for the purpose of the analysis
was based on its maximum power output corresponding to the wind speed at MU. Enercon
E-53 was tallest among other wind turbines analyzed to identify to the most suitable wind
turbine for the proposed location at MU. Further, the analysis included the assessment of
reduction in the electricity consumption from the grid, of the MU for the year 2015, by
integrating different renewable energy generation system in the distributed network of MU.
From different combinations of renewable energy systems used for the analysis, the
combination of Wind-PV system produced the significant amount of reduction in the annual
energy consumption from the grid. The annual electricity consumption of MU reduced from
22.29 GWh to 13.31 GWh. Analysis also included the assessment of reduction in the capacity
and network demand charges affected by the decline in the annual electricity consumption
of MU from the grid. The Wind-PV system produced annual savings of $743,144 on the cost
of electricity consumed from the grid by MU and annual savings of $555,242 on the network
demand and capacity charges.
iv
Acknowledgments
I would like to thank my supervisors, Mr. Craig Carter and Dr. Ali Arefi for their continuous
support throughout my project.
I would also like to thank my wife and my parents for supporting me throughout my journey
to become an electrical engineer.
v
Table of Contents 1 Introduction ........................................................................................................................ 1
1.1 Aim .............................................................................................................................. 2
1.2 Murdoch University ..................................................................................................... 3
1.3 Previous Studies .......................................................................................................... 5
1.4 Software Used ............................................................................................................. 6
2 Resource Analysis ............................................................................................................... 7
2.1 Load Analysis ............................................................................................................... 7
2.2 Solar Analysis ............................................................................................................... 8
2.3 Wind Analysis .............................................................................................................. 9
2.4 Site Analysis ............................................................................................................... 12
3 Energy Production ............................................................................................................ 16
3.1 Wind Energy Production ........................................................................................... 16
3.2 Solar Energy Production ............................................................................................ 20
4 Economic Analysis ............................................................................................................ 22
4.1 Grid Only.................................................................................................................... 22
4.2 PV System Analysis .................................................................................................... 23
4.3 Wind System Analysis................................................................................................ 25
4.4 Wind and PV system.................................................................................................. 27
4.5 Wind-PV-Battery Storage System Analysis ............................................................... 28
4.6 Discussion .................................................................................................................. 30
5 Conclusion & Future Studies ............................................................................................ 31
5.1 Conclusion ................................................................................................................. 31
5.2 Future Studies ........................................................................................................... 32
6 References ........................................................................................................................ 33
Appendix 1 ............................................................................................................................... 36
Appendix 2 ............................................................................................................................... 37
Appendix 3 ............................................................................................................................... 46
vi
List of Tables
Table 1: Height above sea level ............................................................................................... 10
Table 2: Annual mean wind speed recorded from anemometer at Murdoch University. ...... 10
Table 3: Long-Term mean wind speed estimated at Jandakot Airport ................................... 11
Table 4: Rated output and hub height of wind turbines used for the analysis ....................... 14
Table 5: Terrain Description (A.L. Rogers, 2009) ..................................................................... 15
Table 6: Energy production calculated for different wind turbines using Power Curve
Polynomial. .............................................................................................................................. 17
Table 7: Total energy production for different wind turbines estimated in Homer ............... 18
Table 8: General specifications of Enercon E-53 ..................................................................... 19
Table 9: Average commercial solar system prices per watt. (Limited, 2017).......................... 21
Table 10: Cost of electricity bought from grid. ........................................................................ 22
Table 11: Annual charges that incorporates grid cost. ............................................................ 23
Table 12: New cost of buying electricity from the grid. .......................................................... 23
Table 13: Cost Summary of the PV system .............................................................................. 23
Table 14: Energy production of the PV-Grid System ............................................................... 24
Table 15: Calculate new capacity and network demand charges ........................................... 25
Table 16: Cost summary of the grid-connected wind system. ................................................ 25
Table 17: Total energy production of the Wind system .......................................................... 26
Table 18: Calculated new capacity and network demand charges. ........................................ 26
Table 19: Cost Summary of the grid-connected Wind and PV system .................................... 27
Table 20: New calculated annual capacity and network charges ............................................ 27
Table 21 General properties of Gildemeister Vanadium Flow Battery.: ................................. 28
Table 22: Cost summary of the Wind-PV-Battery Storage System.......................................... 29
Table 23: New capacity and demand charges ......................................................................... 29
Table 24: Economic analysis of different renewable energy generation systems. ................. 31
vii
List of Figures
Figure 1: Decline in commercial solar prices from year 2014-2017 (Limited, 2017) ................ 2
Figure 2: Murdoch University south street campus .................................................................. 3
Figure 3: Electricity bill breakdown of MU ................................................................................ 4
Figure 4: Electricity bill breakdown (Energy I. , 2015) ............................................................... 4
Figure 5: Annual energy consumption of MU ............................................................................ 7
Figure 6: Comparison between the Off peak and Peak load of MU .......................................... 8
Figure 7: Monthly mean solar irradiance fallen at MU in year 2015......................................... 9
Figure 8: Annual wind speed recorded from anemometer at Murdoch University................ 11
Figure 9: Inter-Annual wind speed variations recorded at Jandakot Airport .......................... 12
Figure 10: Murdoch University south street campus .............................................................. 12
Figure 11: General rule of minimum tower height. (Geoff Stapleton, 2013) .......................... 13
Figure 12: Power curve polynomial. ........................................................................................ 16
Figure 13: Power curve of the wind turbine (Homer Energy, n.d.) ......................................... 17
Figure 14: Capacity factor calculated in Homer ....................................................................... 19
Figure 15: Power curve of Enercon E53 wind turbine. ............................................................ 20
Figure 16: Comparison between the existing grid energy consumption and new grid
consumption ............................................................................................................................ 24
Figure 17: Comparison between the existing grid energy consumption and new grid
consumption ............................................................................................................................ 27
Figure 18: Comparison between the existing grid energy consumption and new grid
consumption ............................................................................................................................ 28
Figure 20: PV system analysed in Homer................................................................................. 37
Figure 21: Cost summary of the PV system calculated in Homer. ........................................... 38
Figure 22: Payback period ........................................................................................................ 38
Figure 23: Electricity Production of PV system. ....................................................................... 39
Figure 24: Cost summary of Wind system. .............................................................................. 40
Figure 25: Payback Period of Wind System. ............................................................................ 40
Figure 26: Energy production of wind system. ........................................................................ 41
Figure 27: Wind-PV system analysed in Homer ....................................................................... 41
Figure 28: Cost summary of Wind-PV system ......................................................................... 42
Figure 29: Payback period ........................................................................................................ 42
Figure 30: Energy production of Wind-PV system ................................................................... 43
Figure 31: Wind-PV-2.48MWh Battery storage system........................................................... 43
Figure 32: Cost summary of Wind-Pv-2.48MWh battery storage system. .............................. 44
Figure 33: Payback period. ....................................................................................................... 44
Figure 34: Energy production of Wind-PV-2.48MWh battery storage system. ...................... 45
viii
Acronyms
MU Murdoch University
PV Photovoltaics
NPC Net Present Cost
DC Direct Current
AC Alternating Current
AEMO Australian Energy Market Operator
MS Microsoft
RET Renewable Energy Target
CMD Contracted Maximum Demand
REGS Renewable Energy Generation Systems
BOM Bureau of Meteorology
1
1 Introduction
Renewable energy is produced using natural resources that constantly replenish and never run out. There is a number of natural resources such as solar energy, Wind energy, Hydropower, Biogas, Ocean energy etc. used to generate electricity. Generating electricity from renewable resources is increasing significantly, which is initiated by different reasons. Carbon emission is one of the reasons contributing towards the growth of electricity generation from renewable resources. The current source of generating electricity in Australia is primarily coal, which emits a large amount of carbon into the atmosphere. The carbon emission level of Australia in 2005 was 605 Mt CO2-e which decreased by 9.1 percent for year to March by 550Mt CO2-e but the quarterly results between 1990 and 2016 shows that emissions from electricity have had the largest growth, dumping 59.5 megatons into the atmosphere, an increase of 49.2 percent (Department of Environment and Energy, 2017).
Australian Government has imposed climate change policies such as The Clean Energy Act legislated in 2011, which established long-term goals to reduce the emission to 80 percent below 2000 levels by 2050 (Climate Change Authority, n.d.). Australian Government has also introduced Renewable Energy Target (RET) in the electricity sector in 2001 to mitigate the emission of carbon into the atmosphere. The RET target was split into two schemes, the Large-scale Renewable Energy Target (LRET) that supports large-scale projects and the Small-scale Renewable Energy Scheme (SRES) that supports the installation of small-scale systems. This scheme creates a financial incentive for the establishment and the growth of the renewable energy power stations. The primary objective of the RET is to source two percent of Australiaβs electricity generation from renewable sources (Austrlalian Government, Clean Energy Regulator, n.d.). A number of business, schools, and organizations have taken the advantage of RET scheme and have or are installing the solar PV systems utilizing their roof space as Australia gets a significant amount of solar energy throughout the year, which has been very advantageous. University of Queensland, St Lucia campus has installed a rooftop (2.3 MW) PV system, one of the largest integrated installation in Australia (University of Queensland, 2017). Charles Sturt University in New South Wales, Wagga Wagga campus installed 1.77 MW rooftop PV system incorporating 6000 PV panels, roughly the equivalent of powering 400 typical Australian Households (Charles Sturt University, 2017). Murdoch University has also taken initiative to take the advantage of RET Scheme to generate electricity onsite from renewable sources. Generating electricity on University campus from renewable sources would offer a reduction in the electricity consumption off the grid that could benefit the savings on the cost of electricity bought from the grid and at the same time would offer the reduction in the carbon emissions. However, there is few number of integrated renewable energy systems that include small-scale wind turbines. Piney Lakes, City of Melville, Perth, Western Australia house the 12kW grid connected integrated system including 5kW wind turbine and 7kW PV system. The system also incorporates a battery storage system to store energy from the renewable resources for use later (City of Melville, 2017). Moreover, the cost of commercial solar prices has reduced over the years in Australia (Australian Energy Resource Assesment, 2009). Energy storage is a rapidly developing sector; battery storage offers the storage of excess electricity generated by renewable resources for use later. Vanadium flow batteries have grown in demand over the years in Australia and offer significant benefits. Vanadium Redox Flow Batteries employ vanadium ions in different oxidation states to store chemical potential energy (Australian Vanadium Limited , 2017). The Vanadium batteries, also
2
referred to as cell cubes come in different sizes. A 100kWh cell cube containerized Vanadium flow battery is deployed in Busselton, Western Australia. The cell cube, installed along with 15kW PV system and provides the benefit of storing the excess energy generated by PV system ( VSun Energy, 2017). Figure 1 shows the decline in the commercial solar prices in Australia from 2014-2017. As a result, generating electricity from renewable energy has increased in Australia over the years which has made Renewable energy sector more competitive and has made available, better and cheaper technologies in the market to generate electricity from the renewable sources.
Figure 1: Decline in commercial solar prices from the year 2014-2017 (Limited, 2017)
1.1 Aim The primary aim of the project is to identify an optimum onsite renewable energy power
generation system for Murdoch University (MU) that can operate in conjunction with the grid.
The specific objectives involved in the project are listed below:
1. The analysis includes analyzing the availability of solar and wind sources at MU.
2. Estimating the energy production of different wind turbines at MU.
3. Analysing the total energy production of the different renewable energy generation
system such as PV, Wind, Wind-PV and Wind-PV-Battery systems.
4. Estimating the reduction in the total energy consumption of MU from the grid that
renewable energy generation systems can offer.
5. Conducting the cost-benefit analysis to identify the most economic renewable energy
generation system.
Calculate the reduction in the capacity and network demand charges with the
inclusion of the renewable energy generation system into the distributed network of
MU.
3
1.2 Murdoch University
Murdoch University South Street Campus is located in the Perth suburb of Murdoch, Western
Australia, 15km south of the Perth and 5km east of Fremantle.
Figure 2: Murdoch University south street campus
Murdoch University has high electricity demand with the maximum peak load of 5.78 MW
satisfied primarily by the electricity supplied by the grid. Due to high-electricity consumption,
the University pays high electricity bills. In addition to the cost of buying electricity from the
grid, Universityβs electricity bill includes a significant amount of capacity and network demand
charges. Figure 3 shows the primary components of electricity bill of MU. Capacity charges
contribute 28 percent of the total electricity bill, which is charged by the Australian Energy
Market Operator (AMEO) based on the maximum annual peak load of the MU. AEMO makes
sure that the required capacity is available throughout the year to serve the annual load
demand of MU. Whereas the network demand charges are, the transportation charges
charged to MU by the Western Power based on the Contracted Maximum Demand (CMD)
under the particular tariff. It contributes 19 percent of the total electricity bill of the MU. The
CMD is expressed in Kilo Volt Amperes (KVA), which comprise of three different charges; fixed
demand charges, variable demand charges and a variable demand length charge calculated
by multiplying the demand length price by the electrical distance to the zone substation by
the CMD. The zone substation is the nearest substation from where the electricity is
transported to serve the electricity consumption of MU.
4
Figure 3: Electricity bill breakdown of MU
According to the infinite energy, Australiaβs solar power systems installers; the network
demand and capacity charges are the dominant components of the electricity bill, which can
be seen in Figure 4 indicating the percentages of different charges that make up the electricity
bill. It shows that charges are higher to transport the electricity via Western Power's
network of poles and wires (38.4%) than it costs to produce the electricity at the power
generation station (33.3%) (Energy I. , 2015). However, the exact contribution of all the
relevant charges would depend upon the individual clientβs electricity consumption.
Figure 4: Electricity bill breakdown (Energy I. , 2015)
Capacity Charge
28%
Network Charge
19%
Energy Charge53%
ELECTRCITY BILL BREAKDOWN
Peak Demand capacity
22%
Energy33%
Renewable Energy Target Costs
4%
Ancillary Services2%
Market Fees1%
Network Charges38%
ELECTRCITY BILL BREAKDOWN
5
1.3 Previous Studies Identifying an optimum renewable generation system for a particular geographical location
depends on various aspects such as availability of renewable sources, reliable technology, and
the existing load demand. Research to obtain an optimum renewable energy system is
undergoing at different places for different reasons. Several previous studies were analyzed
to get an idea of the process involved to identify an optimum renewable energy systems as
follows:
The study conducted by Sami Alhusayni on the Cost-Benefit Analysis of PV and Storage System
with the perspective to install at Murdoch University (MU) provides detail insight of the
process used to analyze the optimum PV system. The analysis primarily performed in HOMER,
to analyze the economic benefit of the PV system. The analysis involved, identification of an
optimum size of the PV system for MU utilizing its rooftop. The analysis concludes that it
would be cost-effective to install 2MW PV system facing North, on the rooftop of the
university campus. Installing the 2MW PV system would offer a significant reduction in the
annual electricity consumption from the grid. However, the analysis does not include a
reduction in the reserve capacity and network demand charges. Potential of installing the
battery storage at the campus disregarded in the analysis due to high prices of the battery
storage systems and as the proposed PV system just have the ability to offset the peak load
demand.
Another research paper presented the strategy used to analyze the optimization of a power
system consisting of wind and solar systems including the battery storage for optimal
matching of supply and demand at a particular location. The study purposed the methodology
to determine the optimal power flow from a battery storage system, the optimal combination
of wind and solar systems for the selected battery storage system and finding the optimal
capacity of battery storage system. The study also demonstrates the benefits of using battery
storage systems in conjunction with the wind and solar systems. The solar photovoltaic
energy system cannot provide reliable power during non-sunny days. Similarly, wind system
cannot satisfy constant load demands due to significant fluctuations in the magnitude of wind
speeds from hour to hour throughout the year. Hence, the output power of wind turbines
fluctuates making the wind power non-dispatchable. Furthermore, they can cause frequency
deviations and power outage particularly when wind power penetration is significant, i.e.,
when there is a large amount of wind power into the distributed network. Therefore, energy
storage systems will be required for each of these systems in order to satisfy the power
demands (Muhammad Khalid, 2015).
6
1.4 Software Used HOMER is an Optimization Model used for simulation purposes of different Renewable Energy Generation Systems (REGS). HOMER models a renewable energy power systemβs physical behavior and its life cycle cost, the total cost of installing and operating the system over its lifespan. HOMER allows the comparison between different design options such as Grid only, PV, Wind, Wind-PV systems including the battery storage system. HOMER performs three principal tasks: simulation, optimization, and sensitivity analysis. In the simulation process, HOMER models the performance of a different renewable energy generation systems configuration, every thirty minutes of the year to determine its technical feasibility and life-cycle cost. However, it can be used to compute the performance of the REGS for the different time intervals as well. In the optimization process, HOMER simulates many different system configurations in search of the one that satisfies the technical constraints at the lowest life-cycle cost. In the sensitivity analysis process, HOMER performs multiple optimizations under a range of input assumptions to gauge the effects of uncertainty or changes in the model inputs. Optimization determines the optimal value of the variables over which the system designer has control such as the mix of components that make up the system and the size or quantity of each. Sensitivity analysis helps assess the effects of uncertainty or changes in the variables over which the designer has no control, such as the average wind speed or the future fuel price.
7
2 Resource Analysis
2.1 Load Analysis Two different meters HVMSR1 and HVMSR2 record the total electricity consumption of MU
for each 30-minute time interval. Instead of analyzing the load data from two meters
separately, the combined load data of both meters was used for the analysis. The load data
for the year 2015 used for the analysis was provided by Mr. Andrew Hanning, the energy
manager at MU. Load data for the year 2015 was preferred over the load data for the year
2016 as one of the transformers in the distributed network of MU malfunctioned in 2016 for
some reason, which affected the overall consumption of electricity from the grid. Murdoch
University consumed 22.29 GWh energy from the grid in the year 2015. Figure 5 shows the
annual energy consumption of MU from the grid recorded every 30-minute time interval. It
shows the high-energy consumption during the Feb-March.
Figure 5: Annual energy consumption of MU
Figure 6 shows the comparison between off-peak and peak time load of MU recorded every
30-minute time interval. The peak time of the MU is between 8 am to 10 pm, off-peak, time
is between 10 pm to 8 am from Monday-Friday, and it is off-peak time on Saturday-Sunday.
The maximum peak load of University in recorded in the year 2016 was 5.78 MW with the
base load of 2.5 MW. The maximum load was during Feb-March as it is a time when the
semester starts and surprisingly it was during the off-peak time although the maximum load
consumption is typical during general working hours. University had high electricity
consumption during March, which declined significantly in the following month than
remained consistent throughout the remaining year, shown in figure 6. The University had
44% load factor for the year 2015, the high load factor shows the steady consumption of the
University. Full calculations are shown in Appendix 1.
0
0.5
1
1.5
2
2.5
3
3.5
An
nu
al E
ner
gy C
on
sum
pti
on
(M
Wh
)
Time of the year
Annual Energy Consumption of MU
8
πΏπππ πΉπππ‘ππ =πππ‘ππ πΈπππππ¦ πΆπππ π’πππ‘πππ
ππππ πΏπππ Γ π·ππ¦π Γ 24
Figure 6: Comparison between the Off-peak and Peak load of MU
2.2 Solar Analysis Electricity generation from Photovoltaics (PV) depends upon the total solar energy falling on
the earthβs surface as they convert the solar energy into useful electrical energy. The solar
energy is variable in nature as the amount of solar energy falling on earth surface varies
seasonally and on a daily basis. The average amount of annual solar irradiance that falls in
Perth is around 2000kWh/m2/year (Alhusayni, 2017). As the load data of MU for a year, 2015
was used for the analysis that is why the solar irradiance data of the year 2015 of MU was
taken into consideration for the analysis. Figure 7 shows the annual solar energy fallen at MU
during the year 2015 Monthly mean solar irradiance for the year 2015 fallen on MU is
available to download from Bureau of Metrology (BOM) website (Meteorology, 2018). Solar
energy had high mean value during the summer (September β March) but started to decline
as the weather started to get cooler, between (April-August).
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
30
min
ute
Lo
ad C
on
sum
pti
on
(M
W)
Peak Time Load Vs Off Peak Time LoadPeak Time Load
Off Peak Time LoadPeak Load 5.78MWBase Load 2.5MW
9
Figure 7: Monthly mean solar irradiance fallen at MU in the year 2015
2.3 Wind Analysis In general, the wind is a motion of the air and the Sun is the primary source of the energy
contained in the wind. The airflows from high to low-pressure areas due to variations in the
atmospheric pressure caused by the uneven heating of the earth by the solar radiations. In
Australia, high and low-pressure systems pass from west to east over the continent. In the
warmer months (November β April), low-pressure systems predominate over the continent
and bring cyclones to the topics and southeasterly trade winds and sea breezes to the higher
altitudes. In the cooler months (May β October) high-pressure are predominant and these
bring south-easterly trade winds to the tropics and strong westerly winds to the southern
parts of the continent (Berril, 2004)
Wind resource analysis for this study commenced with an assessment of the availability of
wind speed at the MU. Wind speed data recorded at the weather station located at MU
helped to determine the variability and intensity of the wind speeds at the site. The weather
station on the MU campus records different weather elements and associated parameters
such as wind speed, wind direction, rainfall, solar radiation etc. (Weather Station, 2017). Wind
speed data for the year 2015 recorded at 10-minute intervals was obtained from MU weather
station. MU is 22.260 m above sea level whereas the anemometer used to record the wind
speed data is installed on a hill at 29.952 m above sea level. The height of the anemometer
mast is 10m from its reference height. The proposed location for installing wind turbines is at
the same elevation as MU, which is 22.260 m. Therefore, the effective height of the
anemometer is 17.692 as it includes the additional 7.692m of elevation of the 10m
anemometer mast provided by the hill. Table 1 shows the difference between height above
sea level for proposed site at MU and base of the anemometer mast.
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Sola
r Ir
rad
iacn
e (k
Wh
/m2
/day
Year 2015
Monthly Average Daily Solar Irradiance at Murdoch University
10
Height Above Sea Level (m)
Proposed site of wind turbines at MU 22.26
Base anemometer mast 29.952
Difference 7.692 Table 1: Height above sea level
Annual mean wind speed for the year 2015 recorded from the anemometer at MU was
calculated using the following formula; series of N wind speed observations,ππ, each averaged
over the time interval βπ‘. Wind speed is measured in m/s.
π =
1
πβ ππ
π
π=1
(1)
π = the long-term mean horizontal wind speed (m/s)
π = series of wind speed observations
ππ = horizontal wind speed averaged over the time interval
From the data, the calculated annual mean wind speed is 5.36 m/s at the MU campus shown
in Table 2.
Months Monthly mean wind speed (m/s)
Jan 6.10
Feb 5.60
Mar 5.64
Apr 5.80
May 4.65
Jun 5.00
Jul 4.52
Aug 5.16
Sep 5.23
Oct 5.01
Nov 5.63
Dec 6.02
Annual Mean Wind Speed 5.36 Table 2: Annual mean wind speed recorded from anemometer at Murdoch University.
Figure 8 shows the variations in the monthly mean wind speed data of the year 2015 recorded
from the anemometer at MU, showing the variable nature of the wind energy. It shows that
wind speed recorded between Nov-April was high as compared to other months as it started
to decline in the following months with the wind speed recorded between the May-July being
the lowest.
11
Figure 8: Annual wind speed recorded from anemometer at Murdoch University.
Wind speed data recorded at the nearest Meteorological Bureau weather station located at
Jandakot Airport only 8kms from the MU was also obtained for correlation with the wind
speed data recorded at MU weather station. The long-term mean wind speed at the Jandakot
location calculated using the formula 1 for wind speed data of past 9 years is 4.24m/s, shown
in table 3. The wind speed for Jandakot airport obtained from BOM was recorded at three-
hour intervals. The mean annual wind speed for 2014 and 2015 matches the 9 years mean
wind speed (4.24m/s) recorded at Jandakot Airport that is why wind speed data of the year
2015 recorded at MU weather station used for the analysis as it represents the average windy
year. Statistically, one-year data is generally sufficient to predict the long-term seasonal
mean wind speed. (A.L. Rogers, 2009).
Year Mean Wind Speed (m/s)
2008 4.19 2009 4.33 2010 3.96 2011 4.39 2012 4.21 2013 4.15 2014 4.24 2015 4.24 2016 4.43
Long-Term Mean Wind Speed 4.24 Table 3: Long-Term mean wind speed estimated at Jandakot Airport
Figure 9 shows the inter-annual variations over the time scales greater than one year of wind
data recorded at Jandakot Airport, Weather station.
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Win
d S
pee
d (
m/s
)
Year 2015
Monthly mean wind speed (m/s)
12
Figure 9: Inter-Annual wind speed variations recorded at Jandakot Airport
2.4 Site Analysis In general, the elevated site or open lands where winds are unimpeded by trees and buildings
is preferred as this is where wind turbines generate more energy but the proposed location
to install wind turbines at MU campus is shown in figure 10 highlighted as a red circle has
relatively rough terrain. The proposed location has a large number of Pinus Pinaster and
Eucalyptus marginata. The average height of the Pinus Pinaster and Eucalyptus marginate
trees is 20m but the height of mature Pinus Pinaster and Eucalyptus marginate can be up to
20-35 m tall.
Figure 10: Murdoch University south street campus
3.70
3.80
3.90
4.00
4.10
4.20
4.30
4.40
4.50
2008 2009 2010 2011 2012 2013 2014 2015 2016
Mea
n W
ind
Sp
eed
(m
/s)
Years
13
Turbulence due to rough surfaces around or isolated obstacles such as trees or buildings can
slow down the wind speed. The contour Maps for MU is provided in Appendix 3. Surface
roughness interferes with the smooth flow of the air slowing the wind speed close to the
ground. The influence of this effect decreases with the increasing height, producing the
vertical wind speed profile. The increase in wind speed with height defines the phenomenon
of wind shear. So it is required to install the wind turbines at the purposed location at
sufficient height to access the stronger and less turbulent airflow above the canopy. A general
rule for minimum tower height is that the bottom of the turbine rotor, or blades, should be
at least 10m above the tallest obstruction within 150m or the nearby prevalent tree height.
For trees, this means the mature tree height over the 20β 30-year life of the turbine, not the
current tree height (Geoff Stapleton, 2013).
Effectively, this means the minimum tower height is:
(Height of tallest obstacle within 150m) + (10m buffer) + (length of blade of selected wind system)
Figure 11: General rule of minimum tower height. (Geoff Stapleton, 2013)
10m
14
As explained in wind source analysis, wind speed increase with the increase in height so the
wind speed at a hub height of the wind turbines was calculated to determine wind energy
production of each wind turbine. Table 4 shows the rated output and standard hub height of
the different wind turbines used for analysis.
Wind Turbines Rated Output (kW) Hub Height (m)
EO25 25 30
Norvento nED100 100 36
Vergnet 32-m 275 32
Vergnet 55-m 275 55
Wind Flow 45 500 38
EW DW 54 900 50 Enercon E53 800 73
Vestas V82 1,650 70 Table 4: Rated output and hub height of wind turbines used for the analysis
There are two different mathematical models or laws generally used to predict the variation
in the wind speed with elevation above the ground, Logarithmic Law, and Power Law. For
purpose of this report, Logarithmic Law (Log Law) is used to calculate mean wind speed over
the MU at different hub heights of the wind turbines, as follows:
πβπ’π = πππππ βln (
πβπ’π
ππ)
ln (πππππ
ππ)
(2)
πβπ’π = the wind speed at hub height of the wind turbine (m/s)
πππππ = the wind speed at anemometer height (m/s)
πβπ’π = the hub height of the wind turbine (m)
πππππ= anemometer height (m)
ππ = the surface roughness length (m)
ln (β¦ ) = the natural logarithm
The proposed location to install wind turbines as mentioned in the site analysis is surrounded
by a large number of trees so a surface roughness length of Z0=250 mm was taken into
consideration. The approximate surface roughness lengths for various terrain types are
shown in table 5.
15
Terrain Description Zo(mm)
Very Smooth, ice or mud 0.01
Calm open Sea 0.2
Blown Sea 0.5
Snow Surface 3
Lawn Grass 8
Rough pasture 10
Fallow field 30
Crops 50
Few Trees 100
Many Trees, hedges, few buildings 250
Forest and woodlands 500
Suburbs 1500
Centers of cities with tall buildings 3000 Table 5: Terrain Description (A.L. Rogers, 2009)
In comparison to the Log law, the power law represents a simple model for the vertical wind
speed profile.
πβπ’π
πππππ= (
πβπ’π
πππππ)
πΌ
(3)
πβπ’π = the wind speed at hub height of the wind turbine (m/s)
πππππ = the wind speed at anemometer height (m/s)
πβπ’π = the hub height of the wind turbine (m) = the range given in table 4
πππππ= anemometer height (m) = 17.692 m
πΌ = the power law exponent
The value of the power law exponent depends upon the parameter such as elevation, time of
the day, season, and nature of the terrain, wind speed, temperature and various thermal and
mechanical mixing parameters. So due to the complexity of the power law to determine the
exact power law exponent, the Logarithmic law was used to determine the wind speed at
different hub heights.
16
3 Energy Production
3.1 Wind Energy Production The kinetic energy of the wind determines the power and the energy in the wind. The power
in the wind largely depends on the cube of the wind speed (Berril, 2004). The specific wind
power defined as follows:
π0 = 0.5 Γ π Γ π£3
π0 = the specific wind power (W/m2)
π = the density of air (kg/m3). The density of air is around 1.225kg/m3 at sea level
π£ = the velocity of the air (m/s)
For a given area, such as the swept area by a wind turbine, the power in the wind is simply:
π = ππ Γ π΄
Where
P = the power in the wind, (W)
π0 = specific wind power, (W/m2)
π΄ = the capture area, (m2)
Energy production of the different wind turbines shown in Table 4 was analyzed to identify
the most suitable wind turbine corresponding to the wind speed at MU. The Power Curve
Polynomial spreadsheet was used to calculate the energy production of all the different wind
turbines. It was used in one of the renewable energy units during the study course to calculate
the energy production of a particular unit. Figure 11 shows the Power Curve Polynomial fit of
the particular wind turbine. However, each wind turbine used for the analysis had different
power curve based on its rated capacity.
Figure 12: Power curve polynomial.
y = -1.2332x6 + 94.622x5 - 2743.9x4 + 37981x3 -261006x2 + 903584x - 1E+06
RΒ² = 1
0
100000
200000
300000
400000
500000
600000
700000
800000
0 5 10 15 20
Win
d T
urb
ine P
ow
er
Ou
tpu
t (k
W)
Wind Speed (m/s)
Power Curve (3 to 14m/sec)
Series1
17
The energy production of different wind turbines was calculated using the Power Curve Polynomial spreadsheet is shown in table 6:
Wind Turbines Rated Output (kW) Mean Output (kW) Energy Production (kWh)
EO25 25.0 7.9 69,389
Norvento nED100 100.0 38.9 340,913
Vergnet 32-m 275.0 67.5 590,924
Vergnet 55-m 275.0 86.9 761,348
Wind Flow 45 500.0 138.7 1,215,021
EW DW 54 900.0 281.6 2,466,456
Enercon E53 800.0 321.8 2,819,372
Vestas V82 1,650.0 630.4 5,522,679 Table 6: Energy production calculated for different wind turbines using Power Curve Polynomial.
At the same time, Homer a computer model was used to calculating the energy production
of each wind turbine listed in table 4. Homer refers to the wind turbine's power curve to
calculate the expected power output from the wind turbine at that wind speed under
standard conditions of temperature and pressure. In figure 12, the red dotted line indicates
the hub-height wind speed, and the blue dotted line indicates the wind turbine power output.
If the wind speed at the turbine hub height is not within the range defined in the power curve,
the turbine will produce no power. This follows the assumption that wind turbines produce
no power at wind speeds below the minimum cut-off or above the maximum cut out wind
speeds (Homer Energy, n.d.).
Figure 13: Power curve of the wind turbine (Homer Energy, n.d.)
Later Homer applies the density correction formula to estimate the wind turbine, power
output. Power curves typically specify wind turbine performance under conditions of
standard temperature and pressure (STP). To adjust to actual conditions, HOMER multiplies
the power value predicted by the power curve by the air density ratio, according to equation
4.
18
ππππΊ = (π
ππ) Γ ππππΊ,πππ (4)
ππππΊ = the wind turbine power output (kW)
ππππΊ,πππ = the wind turbine power output at standard temperature and pressure (kW)
π = the actual air density (kg/m3)
ππ = the air density at standard temperature and pressure (1.225kg/m3)
Table 7 shows the total energy production calculated in Homer, it is less than the total energy
production calculated using Power Curve Polynomial by 1%. The difference is due to density
correction method followed by the Homer to calculate the wind energy production.
Wind Turbines Rated Output (kW) Mean Output (kW) Energy Production (kWh)
EO25 25.0 7.8 68,078.0
Norvento nED100 100.0 38.5 337,169.0
Vergnet 32-m 275.0 66.3 580,576.0
Vergnet 55-m 275.0 86.1 754,291.0
Wind Flow 45 500.0 137.0 1,198,052.0
EW DW 54 900.0 279.0 2,441,500.0
Enercon E-53 800.0 318.0 2,785,680.0
Vestas V82 1,650.0 619.0 5,423,698.0 Table 7: Total energy production for different wind turbines estimated in Homer
The wind energy production calculated in Homer used for the analysis purposes as it is based
on the actual air density, standard temperature, and pressure. Wind turbine with the highest
capacity factor had an advantage over the other wind turbines as it produced highest average
output against the wind speed at the MU. Few wind turbines produced high capacity factors
such as Norvento nED100, Enercon E-53, and Vestas V82. Norvento nED100 is only 100kW
wind turbine and more than 10 wind turbines are required to match the energy production
of other wind turbines with high rated output and it would require more land for the
installation so that is why Norvento nED100 excluded from the consideration. Vestas V82 did
not produce required capacity factor in comparison to its rated output so Vestas V82 was not
taken into consideration. Enercon E-53 had the advantage over the other wind turbines
because of its highest capacity factor, as it would be required in low number to produce the
energy production. Any structure above 30 meters or more above the ground within 30 km
of the aerodrome must be notified to Royal Australian Air Force (RAAF) as they maintain all
the database of tall structures in the country. Enercon E-53 being a 73 m tall it is also required
to notify Civil Aviation Security Authorities (CASA) as it is likely to create an obstacle for
aviation services at Jandakot Airport.
19
The following formula used to calculate the capacity factor of different wind turbines.
πΆππππππ‘π¦ πΉπππ‘ππ =
π΄π£πππππ πππ€ππ πππππππ‘ππ ππ¦ π€πππ π‘π’ππππππ
π ππ‘ππ πππ€ππ ππ π‘βπ π€πππ π‘π’ππππππ (5)
Figure 14 shows the comparison between capacity factors of different wind turbines
calculated in Homer.
Figure 14: Capacity factor calculated in Homer
Enercon E53 with the rated capacity of 800kW had the highest capacity factor among the
other wind turbines with respect to the energy production, corresponding to the annual
wind speed at the site. The following table shows the general specifications of the Enercon
E53 including its calculated annual energy production as well its capacity factor.
General Specifications
Hub Height (m) 73
Rated Output (kW) 800
Number of Blades 3
Rotor Diameter (m) 53
Swept Area m2 2,198
Total Energy Production (kWh/yr) 2,785,680
Capacity Factor (%) 40% Table 8: General specifications of Enercon E-53
31
%
38
.5%
24
%
31
%
27
% 31
.00
% 39
.8%
37
.5%
1 2 3 4 5 6 7 8
PER
CEN
TAG
E O
F C
AP
AC
ITY
FAC
TOR
WIND TURBINES
CAPACITY FACTOR
Capacity Factor Homer
20
Figure 15: Power curve of Enercon E53 wind turbine.
The wind turbine produced highest capacity factor than other wind turbines. The cut in wind
speed of the turbine is 3m/s, the speed at which the turbine starts to rotate and generate
power. The amount of electrical power generated by wind turbines depends upon the wind
speed at a particular site as the wind speed increases the level of electrical power generated
by wind turbine start to rise as well. The following figure shows the Power Curve of the
Enercon E-53 indicating its electrical power output at different wind speeds. The wind turbine
produces its maximum rated output power at the wind speed of 14m/s also referred as rated
output wind speed. As the wind speed increases above its rated output wind speed, it
enforces pressure on the wind turbine blades. At a wind speed of 28-34m/s, a cutout wind
speed, the braking system becomes active to prevent any damages to the wind turbine (Wind
Power Program, n.d.). Enercon E-53 has upwind rotor with active pitch control. The gearless
drive concept combined with an efficiently streamlined rotor blade design, E-53 offers better
performance and reliability. The innovative aerodynamic design of ENERCON rotor blades
promises extraction of maximum power from the wind. The rotor blades have low noise
emissions and minimal structural loads that ensure an optimal yield in the widest variety of
weather conditions (Enercon, 2018).
3.2 Solar Energy Production Homer a computer software model helped to calculate the energy produced by the 2 MW PV
system over the year 2015. The previous student conducted a study to find an optimum PV
system and concluded that 2MW PV is the maximum size of PV system that can be installed
on the rooftop of MU so that is why 2MW PV system was taken into consideration. Total
energy calculated for 2MW PV system in Homer was 3.34 GWh.
The selection of the solar panels for the purpose of this project solely based on the market
price of solar panels not on the type of technology, as there are different types of solar panels
-
100
200
300
400
500
600
700
800
900
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Pow
er O
utp
ut
(kW
)
Wind Speed (m/s)
Enercon E53 Power Curve
21
available in the market using different technologies. The price of the solar panels declined
over the past years due to growth in the technology and the growing demand of generating
power at households or at a commercial level. In 2016, 68 new commercial solar projects
commissioned in Australia adding capacity of 23MW to the existing total capacity. Table 9
shows average commercial solar system prices per watt for different cities in Australia. All
prices in the tables below include incentives available through the federal Renewable Energy
Target as well as GST, but do not incorporate installation cost, meter installation fees or
additional costs such as ground-mounting, grid protection or grid connection studies (Limited,
2017). For the purpose of this project as MU based in Perth, the average price $1.17 of solar
panels used for the analysis.
Average 10kW 30kW 50kW 100kW
Adelaide, SA $1.22 $1.34 $1.22 $1.18 $1.13
Brisbane, QLD $1.24 $1.33 $1.23 $1.23 $1.16
Canberra, ACT $1.16 $1.35 $1.22 $1.08 $0.99
Hobart, TAS $1.25 $1.44 $1.25 $1.20 $1.12
Melbourne, VIC $1.28 $1.44 $1.28 $1.25 $1.17
Sydney, NSW $1.16 $1.24 $1.18 $1.13 $1.09
Perth, WA $1.17 $1.24 $1.07 $1.25 $1.14
Average $1.22 $1.34 $1.21 $1.19 $1.12 Table 9: Average commercial solar system prices per watt. (Limited, 2017)
22
4 Economic Analysis An economic analysis conducted to identify an optimum onsite renewable power generation
system for the lifetime of 20 years. Apart from generating power onsite from PV, the analysis
include the contribution of wind turbines and the battery storage. Analysis conducted with
the combination of Homer and excel spreadsheets helped to determine the reduction in the
electrical consumption from the grid with the integration of renewable resources in the
distributed network. Reduction in the electrical consumption from the grid decreased the
maximum demand of the load offering the savings in the network demand and capacity
charges. Different scenarios were analyzed for the purpose of the analysis. The disadvantage
of using Homer is the option to add network demand and capacity charges into the grid cost
is not available. So the capacity and network demand charges were added to the cost of
buying electricity for each scenario using excel spreadsheets.
4.1 Grid Only Homer-calculated the total cost of electricity bought from the grid based on the amount of
total energy purchased from the grid, 22.28 GWh, during the year 2015. Utility company
charges the University for the use of energy based on the time of the use. Homer calculated
the cost of electricity purchased from the grid based on the peak and off-peak rates specified
for the different time of the day. The report does not include the documentation of the rates
charged by the utility company to MU due to confidentiality. Total annual cost of energy
consumed by MU Homer is $1.785 million. The NPC calculated by Homer is the present value
of all the costs the system incurs over its lifetime, minus the present value of all the revenue
it earns over its lifetime. The replacement and capital costs of the system are zero as there is
no initial investment required. Table 10 shows the total cost of buying electricity for 20 years
which fell under the operations and maintenance cost (O&M).The total cost of buying
electricity from the grid calculated by Homer does not include any additional charges such as
network demand and capacity charges as Homer does not have any input to include these
charges.
Component Capital ($ ) Replacement ($) O&M ($) Total ($)
Grid $0 $0 $35,060,349 $35,060,349
System $0 $0 $35,060,349 $35,060,349 Table 10: Cost of electricity bought from the grid.
The network demand and capacity charges cost around $1 million per annum to MU; table 11
shows the description of all the associated existing charges, charged along the cost of buying
electricity from the grid including the total amount of charges for 20 years lifetime.
Type of Charge Value
Existing Capacity Charge ($/kVA) 927,987
Existing Network Charge (time of use) ($/kVA) 613,102
Supply Charge 7,469
AEMO Fees and LFAS Charges 99,686
Total 1,648,245
GST 115,377
Grand Total 1,763,622
23
Grand Total for 20 years 35,272,433 Table 11: Annual charges that incorporate grid cost.
After the inclusion of all the charges into the grid cost calculated by Homer the cost
increased to $70.3 million, shown in table 12.
Component Capital ($ ) Replacement ($) O&M ($) Total ($)
Grid $0 $0 $70,332,782 $70,332,782
System $0 $0 $70,332,782 $70,332,782 Table 12: The new cost of buying electricity from the grid.
4.2 PV System Analysis The previous study conducted by Sami Alhusayni on the βCost-Benefit Analysis of PV and
Storage Installation at Murdoch Universityβ concluded that it would be cost-effective to install
(2MW) rooftop PV system facing north at the University campus (Alhusayni, 2017). However,
economic analysis did not include the calculation of new network demand and capacity
charges. The same system was used for this analysis to estimate the savings on new network
demand and capacity charges. Homer simulation is shown in Appendix 2.
Component Capital ($ ) Replacement ($) O&M ($) Salvage ($) Total ($)
Grid $100,000 $0 $14,765,128 $0 $14,865,128
Inverter $277,778 $128,665 $1,432 $0 $407,874
PV System $2,340,000 $0 $202,254 ($85,819) $2,456,435
System $2,717,778 $128,665 $14,968,814 ($85,819) $17,729,437 Table 13: Cost Summary of the PV system
The initial cost of the PV system is $2.7 million calculated in Homer, shown in table 13. Homer
a computer software model calculated NPC of the system based on the costs associated with
each component that contributed towards the initial capital cost and the total NPC of the
system. There is an additional cost added to the grid NPC by the Homer, a capital cost, used
as grid interconnection charge, a one-time fee charged by the utility for allowing a power system
to connect to the grid. HOMER does not apply this fee to grid-only systems, but rather to grid-
connected systems that include some other generation source (Energy H. , Grid Inrerconnection
charge, n.d.). Homer also calculated the salvage value of the PV system ($85,819), a value that
is remaining in a PV system at the end of the project lifetime. The project lifetime is 20 years
whereas the PV system has 25 years of a lifetime so Homer deducted that salvage value from
the total NPC of the PV system. HOMER assumes linear depreciation of components, meaning
that the salvage value of a component is directly proportional to its remaining life. It also
assumes that the salvage value depends on the replacement cost rather than the initial capital
cost. (Energy H. , Homer Pro 3.10- Salvage Value, n.d.). With the inclusion of PV, system into
the distributed network the peak load reduced from 5.78MW to 4.79MW. Figure 15 shows
the comparison between the existing and new load.
24
Figure 16: Comparison between the existing grid energy consumption and new grid consumption
The electricity consumption from the grid reduced to 19 GWh from 22.29 GWh as PV system
generated 3,341,202 kWh energy over the 20 years lifetime. Table 14 shows the energy
production estimated by Homer for the PV system. The payback time for the PV system
calculated in Homer is 11.48 years. Homer calculated payback time by calculating the period
in which the cumulative cash flow difference between the grid only system and the PV system
switched from negative to positive. The payback is an indication of how long it would take to
recover the difference in investment costs between the current system and the base case
system (Energy H. , Homer Pro Version 3.7, User Manual, Year 2016).
Production kWh/Yr %
AC Primary Load 22,280,768 100
PV System 3,341,202 14.9
Grid Purchases 19,018,685 85.1
Total 22,359,887 100 Table 14: Energy production of the PV-Grid System
Table 15 shows the calculated new capacity and network demand charges. It also includes additional charges such as supply charge, AEMOO feed and LMFAS charges including the GST on the total price. The PV system produced annual savings of $278,671 on network demand and capacity charges, the PV system produced annual savings of $276,504 on the energy purchased from the grid by MU. The PV system produced the total annual savings of $555,176.
-1000
0
1000
2000
3000
4000
5000
6000
7000En
ergy
Co
nsu
mp
ti (
kWh
)
Time of the Year
Existing grid cosumption Vs New grid consumption
Measured Load
New Load
25
Type of Charge Value
New Capacity Charge ($/kVA) 780,312
New Network Charge (time of use) ($/kVA) 500,337
Supply Charge 7,469
AEMO Fees and LFAS Charges 99,686
Total 1,387,804
GST 97,146
Grand Total 1,484,950
Grand Total for 20 years 29,699,001 Table 15: Calculate new capacity and network demand charges
As mentioned above the Homer does not have the option to input capacity and network
demand charges into the grid cost so the new payback period of the PV system inclusive of
network demand and capacity charges was calculated using the excel spreadsheet. After
including all the capacity and demand charges into to the cost of the electricity purchased
from the grid for PV and Grid Only system. The payback period changed significantly from
11.47 years to 4.89 years. Payback period calculated by using equation 6.
πππ¦ππππ ππππππ =
πΌπππ‘πππ πΆππππ‘ππ πΆππ π‘
πΆπ’πππ’πππ‘ππ£π πππ β ππππ€ ππππππππππ (6)
4.3 Wind System Analysis
Two Enercon E-53 wind turbines with the total capacity of 1.6 MW taken into the
consideration for the analysis. The initial capital cost estimated in Homer is $3.3 million. The
total NPC $17.03 million estimated by the Homer for the grid-connected wind system for 20
years lifetime of the project shown in table 16. In comparison to the PV system, the NPC of
the grid-connected wind system is low as the Inverter used in the grid-connected PV system
excluded in this scenario as wind turbines produce AC power and directly connects to the AC
bus. However, the initial cost of setting up the wind system is higher than PV system because
of the high capital cost of the wind turbines. The capital cost of the wind turbines does not
include any installation and cabling cost. The calculated cost of wind turbines is the
multiplication of the rated capacity of the wind turbines and the price $2/watt, the price of
wind turbines calculated using equation 7. The operations and maintenance cost of the wind
turbines considered is 2% of the total cost of the wind turbine.
ππππ ππ’πππππ πππππ = ππππ ππ’πππππ π ππ‘ππ πΆππππππ‘π¦ π $2/πππ‘π‘ (7)
Components Capital ($) Replacement($) O&M($) Total ($)
Enercon E-53 [800kW] $3,200,000 $0 $628,361 $3,828,361
Grid $100,000 $0 $13,100,209 $13,200,209
System $3,300,000 $0 $13,728,571 $17,028,571 Table 16: Cost summary of the grid-connected wind system.
Table 18 shows the total energy production of the wind system, In comparison to the PV
system; wind turbines produced more energy over the 20 years lifetime reducing the total
electricity consumption from the grid.
26
Production kWh/Yr %
Enercon E-53 [800kW] 5,594,568 25.1
Grid Purchases 16,691,625 74.9
Total 22,286,194 100 Table 17: Total energy production of the Wind system
Payback time of the wind system calculated in Homer is 8.52 years. After the inclusion of the
capacity and network demand charges into the cost of electricity purchased from the grid the
payback period of the wind system reduced to 4.26 years. Calculated new capacity and
network demand charges based on the new energy consumption shown in table 20.
Types of Charges Value
New Capacity Charge ($/kVA) 691,253
New Network Charge (time of use) ($/kVA) 539,436
Supply Charge 7,469
AMEO Fees and LFAS Charges 99,686
Total 1,337,844
GST 93,649
Grand Total 1,431,493
Grand Total for 20 years 28,629,870 Table 18: Calculated new capacity and network demand charges.
Although the wind system made a significant reduction in the electricity consumption from
the grid the maximum load demand did not change much. Some days of the year with no wind
or very low wind, wind turbines produced zero energy production thereby load demand
during certain days of the year remained high, that explains the intermittency of the wind.
The wind system reduced the overall capacity charges due to reduction in the total energy
consumption from the grid as during the certain times of the year; the wind turbines produced
excess electricity. The Wind system produced savings of $332,158 on network demand and
capacity charges and produced savings of $442,956 on the cost of electricity bought from the
grid. The annual net savings produced by the Wind system is $775,124. The wind system
produced 681kWh excess electricity annually. The penetration of excess power produced by
the wind in the distributed network can cause the power outages. Having a battery storage
system in conjunction with the wind system would store all the excess energy generated by
the wind system.
27
Figure 17: Comparison between the existing grid energy consumption and new grid consumption
4.4 Wind and PV system The analysis includes the combination of two Enercon E53 wind turbines 1.6MW and 2MW
PV system. The following table shows all the associated costs of each component contributing
towards total NPC of the system estimated by Homer. An initial investment of the Wind and
PV system requires $6.6 million as it includes the cost of wind turbines and PV panels.
Component Capital ($ ) Replacement ($) O&M ($) Salvage ($) Total ($)
Enercon E-53 [800kW] $3,200,000 $0 $628,361 $0 $3,828,361
Grid $100,000 $0 $10,576,721 $0 $10,676,721
Inverter $260,417 $120,623 $1,342 $0 $382,382
PV system $2,340,000 $0 $202,254 ($85,819) $3,156,435
System $6,600,417 $120,623 $11,408,678 ($85,819) $18,043,899 Table 19: Cost Summary of the grid-connected Wind and PV system
Homer calculated 9.8 years as the payback time of the Wind and PV system whereas the new
payback period calculated in excel inclusive of network demand and capacity charges were
5.28 years.
Types of charges Value
New Capacity Charge ($/kVA) $ 581,719
New Network Charge (time of use) ($/kVA) $ 440,451
Supply Charge $ 7,469
AMEO Fees and LFAS Charges $ 99,686
Total $ 1,129,326
GST $ 79,053
Grand Total $ 1,208,379 Table 20: New calculated annual capacity and network charges
The combination of Wind and PV system resulted in significant reduction in the capacity and
network demand charges. The system produced the annual savings of $695,345 on the cost
of electricity bought from the grid. The system also produced annual savings of 555,242 on
1500200025003000350040004500500055006000
1/0
1/2
01
5
22
/01
/20
15
12
/02
/20
15
5/0
3/2
01
5
26
/03
/20
15
16
/04
/20
15
7/0
5/2
01
5
28
/05
/20
15
18
/06
/20
15
9/0
7/2
01
5
30
/07
/20
15
20
/08
/20
15
10
/09
/20
15
1/1
0/2
01
5
22
/10
/20
15
12
/11
/20
15
3/1
2/2
01
5
24
/12
/20
15
Ener
gy C
on
sum
pti
on
(kW
h)
Time of the year
Existing energy consumption Vs NEW energy cosnumption
2015 MeasuredLoad (kW)
New Load Profile (kW)
28
network demand and capacity charges. Figure 21 shows the changes in the existing grid load,
the peak load demand changed from 5.78 MW to 4.22 MW. During certain times of the year,
the system generated excess electricity, a total of 256.95MWh/yr. The excess electricity can
be exported back to the grid or a battery storage could be used to store the excess electricity
for further load reduction that would even save on capacity and network demand charges.
Figure 18: Comparison between the existing grid energy consumption and new grid consumption
4.5 Wind-PV-Battery Storage System Analysis The Gildemeister Vanadium redox flow battery used for the analysis has a nominal capacity
of 2.48 MWh and can potentially supply the maximum power of 300 kW continuously for 8
hours or all at once in one hour. The purpose of using the battery storage system is to store
the excess electricity generated by the renewables resources onsite that would benefit by
shaving off the peak load demand to some extent and would save on excessive network
demand and capacity charges. The general properties of the battery storage system used for
analysis, shown in table 21.
General Properties
Nominal capacity (V) 700
Nominal Capacity (kWh) 2480
Nominal Capacity (Ah) 3540
Round Trip Efficiency (%) 70
Maximum Charge Current (A) 291
Maximum Discharge Current (A) 441 Table 21 General properties of Gildemeister Vanadium Flow Battery.:
-2000
-1000
0
1000
2000
3000
4000
5000
6000
7000
Time of the year
Ener
gy C
on
sum
pti
on
(kW
h)
Existing grid consconsumption Vs New grid consumption
2015 Measured Load New Load
29
Table 24 shows the cost summary of Wind-PV-Battery Storage system that does not include
capacity and network demand charges added to the cost of electricity bought from the grid.
Employing a battery storage into the Wind-PV system increased the initial cost of the Wind-
PV system to $7.19 million.
Component Capital ($ ) Replacement ($) O&M ($) Salvage ($) Total ($)
Enercon E-53 [800kW] $3,200,000 $0 $628,361 $0 $3,828,361
Gildemeister Battery Storage $1,736,000 $0 $170,724 $0 $1,906,443
Grid $100,000 $0 $10,565,152 $0 $10,665,152
Inverter $260,416 $120,623 $1,253 $0 $382,382
PV North $2,340,000 $0 $202,254 ($85,819) $2,456,435
System $7,636,416 $120,623 $13,101,835 ($85,819) $20,773,056 Table 22: Cost summary of the Wind-PV-Battery Storage System
The calculated capital cost of the vanadium flow batteries, based on their current price in the
market, which is around $700/kWh. Formula 8 used to calculate the total price of the battery
shown below; full calculation is shown in Appendix 1
πππ‘ππ πππππ ππ π΅ππ = ππ ππ π΅ππ Γ πππππ ππ π‘βπ πππ‘π‘πππ¦($ ππβ)β (8)
π΅ππ = π΅ππ‘π‘πππ¦ ππ‘πππππ ππ¦π π‘ππ
The Wind-PV system including the 2.48 MWh battery storage system was analyzed in Homer
and MS Excel. The system modeled in MS excel is based on the assumptions, it was assumed
that the battery storage system would be used only once in a day. As mentioned above, the
battery storage has the capacity to deliver 300kW continuously for 8hours or all at once in 1
hour. So from every dayβs load of the Wind-PV system, 300kW subtracted to obtain the new
load of the system. Deducting 300kW from the load profile of wind-PV system did not produce
significant changes in the load demand. After adding the battery storage into Wind-PV
system, new capacity and demand charges calculated, shown in table 23.
Types of charges Value
New Capacity Charge ($/kVA) 580,469
New Network Charge (time of use) ($/kVA) 417,084
Supply Charge 7,469
AEMO Fees and LFAS Charges 99,686
Total 1,104,708
GST 77,330
Grand Total 1,182,038
Table 23: New capacity and demand charges
30
The Wind-PV system generated 279 MWh excess energy over the period of one year at the
average of 704kWh per day that assumed of being used to charge the battery storage
system every day. The formula used to calculate energy generated per day by Wind-PV
system as follows; full calculation shown in Appendix 1.
πΈπππππ¦ πππ πππ¦
=πππ‘ππ πΈπππππ¦ πππππππ‘ππ ππ¦ π‘βπ ππππ/ππ π π¦π π‘ππ ππ£ππ π‘βπ π¦πππ
ππ’ππππ ππ π·ππ¦π ππ π ππππ
(9)
πΈπππππ¦ ππππ’ππππ πππ π‘βπ ππππ = ππΆ β πΈπππππ¦ πππ πππ¦ (10)
ππΆ β πππππππ πππππππ‘π¦ ππ π΅ππ‘π‘πππ¦ ππ‘πππππ ππ¦π π‘ππ
However, the nominal capacity of the storage system is 2480kWh and the energy generated
by the Wind-PV system was 704kWh so another assumption made, to charge the remaining
capacity of the battery storage system from the energy bought straight from the grid during
the off-peak time. The cost of charging the battery storage off grid calculated was $117 per
day accumulated to $42751 per year. Formula 11 used to calculate the cost to charge the
battery. The system produced annual savings of $695,779 on the cost of electricity bought
from the grid but the cost to charge the battery storage system was deducted from the
savings on the cost of electricity bought from the grid, which reduced to $653,027. The system
also produced the savings of $586,329 on capacity and network demand charges. The system
produced annual net savings of $1.25 million. Payback time calculated in Homer is 17.51 years
whereas payback time after including all the charges reduced to 6.51 years.
πΆππ π‘ π‘π πβππππ π‘βπ πππ‘π‘πππ¦= πΈπππππ¦ ππππ’ππππ πππ ππππ Γ πππ ππππ ππππ π ππ‘ππ
(11)
In Homer, Cycle charging method used to charge the battery storage system. Cycle charging
uses the renewable resources to meet the load and any surplus energy charges the battery.
The simulation performed in Homer for Wind-PV system including the 2.48MWh battery
storage system shown in Appendix 2.
4.6 Discussion To satisfy the objective of this project different renewable resources were analyzed to identify
an optimum grid connected onsite renewable generation system for MU. The analysis of PV
system, Wind System, and Wind- PV system conducted to identify their electricity generation
capacity in order to reduce the electricity consumption of MU from the grid. The analysis of
each system also included the reduction in the capacity and network demand charges due to
a decrease in the total electricity consumption from the grid. Table 24 shows the comparison
between the economics of different renewable generation systems. The Wind-PV system with
the 2.5MWh battery storage system produced more savings on the network demand and
capacity charges. The Wind-PV-Battery Storage system has high initial cost the system as the
31
cost of the battery storage system adds the significant amount of value to the total cost of
the system. The algorithm used to control the battery system for this scenario was assumptive
but a smart battery management system in place would store the electricity and discharge
the battery storage as required. However, the battery storage system would require more
charging and discharge in order to reduce the maximum electricity consumption from the
grid, which would affect the lifetime of battery storage system. The (2MW) PV system has
lowest initial capital cost among other systems and offers a decent amount of reduction in
the network demand and capacity charges with the payback time of only 4.9 years. The Wind-
PV system offered the maximum reduction in the annual savings on all the charges, having a
battery storage system with smart battery management system can offer more savings.
System Capacity
(MW) Initial
Investment Total 20 years
Savings
Net 20 years Savings
Payback Period (Years)
PV 2 $2,717,778 11,103,526 8,385,748 4.90
Wind 1.6 $3,300,000 15,502,494 12,202,494 4.26
Wind-PV 3.6 $5,900,417 25,011,763 19,111,346 4.72
Wind-PV-2.5MWh Battery 3.6 $7,619,056 25,547,267 17,928,211 6.74 Table 24: Economic analysis of different renewable energy generation systems.
5 Conclusion & Future Studies
5.1 Conclusion Generating electricity from renewable energy generation systems (REGS) on campus would
provide savings on the cost of electricity bought from the grid and at the same time would
provide savings on the network demand and capacity charges. In order to achieve that
different REGS such as PV system, Wind system and the combination of PV and Wind and
Battery Storage systems were anal. It was required to obtain an optimum system that could
offer a significant amount of benefits of generating electricity on campus. A maximum of 2
MW PV system can be installed on the rooftop of MU and it would not produce sufficient
energy to meet the peak load demand of the MU. In order to meet the maximum load
demand, it is required to have an alternative form of renewable energy system for generating
electricity on campus. It was identified that having wind turbines along with solar panels
would offer a significant amount of reduction in the total savings on the cost of electricity
bought from the grid and savings on the network demand and capacity charges. Generating
electricity from wind turbines on campus required analysis of the wind speed at the campus.
Annual mean wind speed calculated at MU was 5.36m/s. further, the estimation of wind
energy production by different wind turbines was analyzed. The selection of the wind turbines
was based on the capacity of the wind turbines. Enercon E-53 wind turbine was chosen for
the analysis of this study. A combination of wind and solar panels offered a significant amount
of savings in the capacity and network demand charges and the cost of electricity bought from
the grid. The benefit of having a battery storage system was analyzed with the combination
of Wind-PV system. However, having a battery storage in conjunction with Wind-PV system
increased the payback of time of the system as the battery storage system adds the value to
the initial cost of the system.
32
5.2 Future Studies The system requires a study on the advanced battery model that can be used to control the
flow of energy from the battery storage to meet the required load demand. Two Enercon E-
53 wind turbines were analyzed in this study to identify the amount of reduction in the
existing electricity consumption of MU that it could offer. Further studies may include
assessment of more than two wind turbines at the campus as it may offer high amount
reduction in the existing electricity consumption of MU. However, Enercon E-53 wind turbines
are 73 m tall so it is required to contact CASA to discuss MUβs plan of installing wind turbines
at the University campus. So further studies may include the assessment of wind turbines
other than Enercon E-53 as the wind turbine height may cause disruptions in the project plans.
The system requires bigger battery size that could offer a constant supply of maximum power
for long hours during a day to meet the maximum electricity demand.
33
6 References Clean Energy Australia. (2016). Clean Energy Australia Report 2016. ACT: Complete Colour
Printing.
Murdoch University. (2017). Perth Campus. Retrieved from www.Murdoch.edu.au:
http://www.murdoch.edu.au/life-at-murdoch/perth-campus
Solar Choice. (2017). Solar Choice. Retrieved from www.Solarchoice.net.au:
https://www.solarchoice.net.au/blog/battery-storage-throughput-not-battery-cycle-
life
VSun Energy. (2017). VRB Installation Case Studies. Retrieved from
www.vsunenergy.com.au: https://www.vsunenergy.com.au/case-studies/busselton-
western-australia/
A.L. Rogers, J. M. (2009). Wind Energy Explained. West Sussex: John Wiley & Sons Ltd.
Alhusayni, S. (2017). Cost Benefit Analysis of PV and Storage Installtion at Murdoch
University. Perth.
Australian Energy Resource Assesment. (2009). Solar Energy. Australian Energy Resource.
Australian Government, Department of Foreign Affairs and Trade. (2017-2018). Climate
Change. Retrieved from WWW.dfat.gov.au: http://dfat.gov.au/international-
relations/themes/climate-change/Pages/australias-climate-action.aspx
Australian Vanadium Limited . (2017). Vanadium batteries. Retrieved from
www.australianvanadium.com.au: http://australianvanadium.com.au/vanadium-
batteries/
Austrlalian Government, Clean Energy Regulator. (n.d.). Renewable Energy Target. Retrieved
January 22, 2017, from http://www.cleanenergyregulator.gov.au/RET/About-the-
Renewable-Energy-Target/History-of-the-scheme
Berril, T. (2004). Wind Energy Conversion Systems-Resource Book. Brisbane: Renewable
Energy Centre.
Charles Sturt University. (2017). Wagga Wagga Solar PV Installation. Retrieved from
www.csu.edu.au:
https://www.csu.edu.au/division/facilitiesm/projects/details/wagga/ww-solar-pv-
photovoltaic-installation
City of Melville. (2017). Power . Retrieved from www.melvillecity.com.au:
http://www.melvillecity.com.au/environment-and-waste/piney-
lakes/about/building-technology/power
34
Clean Energy Council Australia. (2015). Clean Energy Austrlaia Report. ACT: Complete Colour
Printing.
Climate Change Authority. (n.d.). Australia's policies on climate change. Retrieved January
22, 2017, from http://climatechangeauthority.gov.au/reviews/targets-and-progress-
review/part-b
Department of Environment and Energy. (2017). Quarterly Update of Australiaβs National
Greenhouse Gas Inventory. Canberra: Commonwealth of Austrlaia.
Enercon, E. F. (2018, January 27). Enercon E-53. Retrieved from www.enercon.de:
https://www.enercon.de/en/products/ep-1/e-53/
Energy, H. (n.d.). Grid Inrerconnection charge. Retrieved from www.homerenergy.com:
https://www.homerenergy.com/support/docs/3.10/grid_interconnection_charge.ht
ml
Energy, H. (n.d.). Homer Pro 3.10- Salvage Value. Retrieved from www.homerenergy.com:
https://www.homerenergy.com/support/docs/3.10/salvage_value.html
Energy, H. (Year 2016). Homer Pro Version 3.7, User Manual. Boulder: Homer Energy .
Energy, I. (2015, February 12). WA Electrcity Tariifs Explained. Retrieved from
www.infiniteenergy.com.au: https://www.infiniteenergy.com.au/electricity-tariff-
makeup-perth-wa
Geoff Stapleton, G. M. (2013). Australia's Guide to Environmentally Sustianable Homes.
Retrieved from www.yourhome.gov.au: http://www.yourhome.gov.au/energy/wind-
systems
Hayden, E. (2013). Introduction to Microgrids. Virginia: Securicon.
Homer Energy. (n.d.). Calculating Hub Height Wind Speed. Retrieved from
www.homerenergy.com:
https://www.homerenergy.com/support/docs/3.10/how_homer_calculates_wind_t
urbine_power_output.html
Limited, S. C. (2017). Current solar power system prices: Residential and Commercial.
Retrieved from www.solarchoice.net.au: https://www.solarchoice.net.au/blog/solar-
power-system-prices
Mark Robinson, Y. S. (2016). Energy Audit of Building 340 Murdoch University. Perth.
Meteorology, B. o. (2018, Jan 27). Daily Global Solar Exposure. Retrieved from
http://www.bom.gov.au:
http://www.bom.gov.au/jsp/ncc/cdio/weatherData/av?p_nccObsCode=193&p_displ
ay_type=dailyDataFile&p_startYear=&p_c=&p_stn_num=009187
Muhammad Khalid, A. V. (2015). Optimization of a Power System Consisting of Wind and
Solar Power Plants and Battery Energy Storage for Optimal Matching of Supply and
Demand. IEEE Conference on Control Applications (CCA), 739-743.
35
Statics, A. B. (2017). Consumer Prices Index, Australia. Retrieved from Australian Bureau of
Statics:
http://www.abs.gov.au/AUSSTATS/[email protected]/Previousproducts/6401.0Feature%20A
rticle2Mar%202017?opendocument&tabname=Summary&prodno=6401.0&issue=M
ar%202017&num=&view=
Storage, G. E. (n.d.). Optimal use of microgrids. Gildemeister Energy Solutions, 3.
University of Queensland. (2017). St Lucia. Retrieved from www.uq.edu.au:
https://www.uq.edu.au/solarenergy/pv-array/st-lucia
Weather Station, M. U. (2017). About Murdoch's Met Station. Retrieved from
wwwmet.murdoch.edu.au: http://wwwmet.murdoch.edu.au/about
Wind Power Program. (n.d.). Wind turbine power ouput variation with steady wind speed.
Retrieved from www.wind-power-program.com: http://www.wind-power-
program.com/turbine_characteristics.htm
36
Appendix 1 Load Factor:
πΏπππ πΉπππ‘ππ =πππ‘ππ πΈπππππ¦ πΆπππ π’πππ‘πππ
ππππ πΏπππ Γ π·ππ¦π Γ 24
πΏπππ πΉπππ‘ππ =22291355ππβ
5780ππ Γ 365 Γ 24= 44%
Total Energy generated by Wind-PV system over the period of one day:
πΈπππππ¦ πππ πππ¦ =πππ‘ππ πΈπππππ¦ πππππππ‘ππ ππ¦ π‘βπ ππππ/ππ π π¦π π‘ππ ππ£ππ π‘βπ π¦πππ
ππ’ππππ ππ π·ππ¦π ππ π ππππ
πΈπππππ¦ πππ πππ¦ =256952ππβ
365= 704ππβ
Energy required charging the battery:
πΈπππππ¦ ππππ’ππππ πππ π‘βπ ππππ = ππΆ β πΈπππππ¦ πππ πππ¦
πΈπππππ¦ ππππ’ππππ πππ π‘βπ ππππ = 2480ππβ β 704ππβ = 1776ππβ
ππΆ- πππππππ πππππππ‘π¦ ππ π΅ππ‘π‘πππ¦ ππ‘πππππ ππ¦π π‘ππ
Cost to charge the battery off the grid:
πΆππ π‘ π‘π πβππππ π‘βπ πππ‘π‘πππ¦ = πΈπππππ¦ ππππ’ππππ πππ ππππ Γ πππ ππππ ππππ π ππ‘ππ
Total cost of 300kW BSS:
πππ‘ππ πππππ ππ π΅ππ = ππ ππ π΅ππ Γ πππππ ππ π‘βπ πππ‘π‘πππ¦($ ππβ)β
πππ‘ππ πππππ ππ π΅ππ = 2480 Γ 700 = $1,736,000
π΅ππ = π΅ππ‘π‘πππ¦ ππ‘πππππ ππ¦π π‘ππ
π΅ππ‘π‘πππ¦ πππππ = $700/ππβ
Total cost of 1MW BSS:
πππ‘ππ πππππ ππ π΅ππ = ππ ππ π΅ππ Γ πππππ ππ π‘βπ πππ‘π‘πππ¦($ ππβ)β
πππ‘ππ πππππ ππ π΅ππ = 5000 Γ 700 = $3,500,000
Payback period of PV system:
πππ¦ππππ ππππππ =πΌπππ‘πππ πΆππππ‘ππ πΆππ π‘
πΆπ’πππ’πππ‘ππ£π πππ β ππππ€ ππππππππππ
πππ¦ππππ ππππππ =$2.7πππππππ
$555,176= 4.89 π¦ππππ
37
Payback period of Wind system:
πππ¦ππππ ππππππ =$3.3πππππππ
$442,996= 4.26 π¦ππππ
Payback period of Wind PV system:
πππ¦ππππ ππππππ =$6.6πππππππ
$695,345= 5.28 π¦ππππ
Payback period of Wind PV-300kWh battery storage system:
πππ¦ππππ ππππππ =$8.9πππππππ
$695,779= 6.51 π¦ππππ
Appendix 2 PV System
Figure 19: PV system analyzed in Homer
38
Figure 20: Cost summary of the PV system calculated in Homer.
Figure 21: Payback period
39
Figure 22: Electricity Production of PV system.
Wind system
40
Figure 23: Cost summary of Wind system.
Figure 24: Payback Period of Wind System.
41
Figure 25: Energy production of the wind system.
Wind-PV system
Figure 26: Wind-PV system analyzed in Homer
42
Figure 27: Cost summary of Wind-PV system
Figure 28: Payback period
43
Figure 29: Energy production of Wind-PV system
Wind-PV-2.48MWh battery storage system
Figure 30: Wind-PV-2.48MWh Battery storage system
44
Figure 31: Cost summary of Wind-Pv-2.48MWh battery storage system.
Figure 32: Payback period.
45
Figure 33: Energy production of Wind-PV-2.48MWh battery storage system.
46
Appendix 3
MU Biodiversity Management Plan
16
2
12
7
15
17
8
17
4
6
51
11
19
20
23
9
22
1310
18
3
25
14
24
26
21
1
3
42
8
5
16
13
7
15
6
9
10
1711
14
12
ErMp
Ppcc
Ppcc
Ppcc
EmBaAfXpSl
Pl
Ppcc ErMpAf
Ppcc
ErNfBl
Ppcc
CcPg
Ppcc
CcPg
EmBaAfXp
Ppcc
MpAfLsp
PpLl
Ppcc
CcEmXp
CcBa
PpLl
CcEmXp
Xp
Pl
Cc
Ppcc
CcEmXp
ErMpAc
CcPg
Ppcc
ErMpAc
PpCcCp
ErMpAc
CcBa
Tt
EmBaAfXp
Pl
LaGr
CcBa
Pp
EmBaAfXpSl
ErNfBl
CcPg
EmBaAfXp
ErMpAc
Cc
EmBaAfXpSl
EgPl
Cc
PpCcCp
EmBaAfXp
CcEmXp
ErMpAc
Afpg
389000 389500 390000 39050064
5050
064
5100
064
5150
0
GDA 1994 MGA Zone 50
MURDOCH UNIVERSITYBIODIVERSITY MANAGEMENT PLAN
VEGETATION COMMUNITIES
1:6,500SC AL E @ A3
A U T H O R : R D C H E C K E D : J N D AT E : J U N 2 0 1 2 P R O J E C T N O : 2 7 5 3 - 11
0 100 200 300 400 500 m
CLIENT: MURDOCH UNIVERSITY
LegendStudy areaCurrent ReservesPotential Reserves
Vegetation Communitites
ErMpAcEucalytpus rudis subsp. rudis and Melaleuca preissianaOpen Woodland over Adenanthos cygnorum, Xanthorrhoeapreissii, Chamelaucium uncinatum and weeds
Afpg Allocasuarina fraseriana open woodland over planted gardensCc Corymbia calophylla open woodlandCcBa
CcEmXp Corymbia calophylla and Eucalyptus marginata overXanthorrhoea preissii open shrubland
CcPg Corymbia calophylla open woodland over planted gardens
EmBaAfXpEucalyptus marginata, Banksia littoralis and Allocasuarinafraseriana woodland over Xanthorrhoea preissii shrubland and weeds
EmBaAfXpSlEucalyptus marginata, Banksia littoralis and Allocasuarinafraseriana woodland over Xanthorrhoea preissiiandStrilingia latifolia shrubland
ErMp Eucalyptus rudis and Melaleuca preissiana woodland overTypha sp. and Scirpus sp. sedgeland
ErMpAf Eucalyptus rudis and Melaleuca preissiana over planted gardens
ErNfBl Eucalyptus rudis and Banksia littoralis open woodland overNuytsia floribunda open shrubland
LaGr
MpAfLsp Melaleuca preissiana open woodland over Astartea aff. fasicularisshrubland over Lepidosperma sp. sedgeland
Pp Pinus pinaster woodland
PpCcCp Pinus pinaster and Corymbia calophylla woodland with scatteredCallitris preissii
PpLl Pinus pinaster woodland over Leptospermum laevigatum open scrub
Ppcc Pinus pinaster woodland with scattered Corymbia calophyllaTt Leptospermum laevigatum closed scrubXp Xylomelum occidentale scattered treesEgPl Eucalyptus gomphocephala open woodland over planted gardensPl Planted
MAP 10Aerial imagery supplied by NearMap (2012)