CHAPTER 2
Factors: How Time and Interest Affect Money
ENGINEERING ECONOMY, Sixth Edition
by Blank and Tarquin
Mc
GrawHill
Authored by Don Smith, Texas A&M University 2004
![Page 2: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/2.jpg)
2
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
1. Foundations: Overview1. F/P and P/F Factors
2. P/A and A/P Factors
3. F/A and A/F Factors
4. Interpolate Factor Values
5. P/G and A/G Factors
6. Geometric Gradient
7. Calculate i
8. Calculate “n”
9. Spreadsheets
![Page 3: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/3.jpg)
3
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
CHAPTER 2: Section 1
F/P and P/F Factors
![Page 4: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/4.jpg)
4
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.1 Basic Derivations: F/P factor
F/P Factor To find F given P
P0
Fn
n
………….
To Find F given P
Compound forward in time
![Page 5: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/5.jpg)
5
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.1 Derivation by Recursion: F/P factor
F1 = P(1+i)
F2 = F1(1+i)…..but:
F2 = P(1+i)(1+i) = P(1+i)2
F3 =F2(1+i) =P(1+i)2 (1+i) = P(1+i)3
In general:
Fn = P(1+i)n
Fn = P(F/P,i%,n)
![Page 6: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/6.jpg)
6
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.1 Present Worth Factor from F/P
Since Fn = P(1+i)n
We solve for P in terms of FN
P = F{ 1/ (1+i)n} = F(1+i)-n
Thus:P = F(P/F,i%,n) where
(P/F,i%,n) = (1+i)-n
Thus, the two factors are:
1. F = P(1+i)n finds the future worth of P;
2. P = F(1+i)-n finds the present worth from F
![Page 7: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/7.jpg)
7
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.1 P/F factor – discounting back in time
Discounting back from the future
P
Fn
n
………….
P/F factor brings a single future sum back to a specific point in time.
![Page 8: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/8.jpg)
8
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
CHAPTER 2: Section 2
P/A and A/P Factors
![Page 9: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/9.jpg)
9
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.2 Example- F/P Analysis
Example: P= $1,000;n=3;i=10%What is the future value, F?
0 1 2 3P=$1,000
F = ??
i=10%/year
F3 = $1,000[F/P,10%,3] = $1,000[1.10]3
= $1,000[1.3310] = $1,331.00
![Page 10: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/10.jpg)
10
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.2 Example – P/F Analysis
Assume F = $100,000, 9 years from now. What is the present worth of this amount now if i =15%?
0 1 2 3 8 9
…………
F9 =
$100,000
P= ??
i = 15%/yr
P0 = $100,000(P/F, 15%,9) = $100,000(1/(1.15)9)
= $100,000(0.2843) = $28,430 at time t = 0
![Page 11: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/11.jpg)
11
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.2 Uniform Series Present Worth and Capital Recovery Factors
Annuity Cash Flow
$A per period
P = ??
0
………….. n 1 2 3 .. ..
n-1
![Page 12: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/12.jpg)
12
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.2 Uniform Series Present Worth and Capital Recovery Factors
Desire an expression for the present worth – P of a stream of equal, end of period cash flows - A
0 1 2 3 n-1 n
A = given
P = ??
![Page 13: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/13.jpg)
13
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.2 Uniform Series Present Worth and Capital Recovery Factors
Write a Present worth expression
1 2 1
1 1 1 1..
(1 ) (1 ) (1 ) (1 )n nP A
i i i i
Term inside the brackets is a geometric progression.
Mult. This equation by 1/(1+i) to yield a second equation
[1]
![Page 14: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/14.jpg)
14
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.2 Uniform Series Present Worth and Capital Recovery Factors
The second equation
[2]
To isolate an expression for P in terms of A, subtract Eq [1] from Eq. [2]. Note that numerous terms will drop out.
2 3 1
1 1 1 1..
1 (1 ) (1 ) (1 ) (1 )n n
PA
i i i i i
![Page 15: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/15.jpg)
15
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.2 Uniform Series Present Worth and Capital Recovery Factors
Setting up the subtraction
1 2 1
1 1 1 1..
(1 ) (1 ) (1 ) (1 )n nP A
i i i i
[1]
[2]
-
1
1 1
1 (1 ) (1 )n
iP Ai i i
= [3]
2 3 4 1
1 1 1 1 1...
(1 ) (1 ) (1 ) (1 ) (1 ) (1 )n n
PA
i i i i i i
![Page 16: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/16.jpg)
16
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.2 Uniform Series Present Worth and Capital Recovery Factors
Simplifying Eq. [3] further
1
1 1
1 (1 ) (1 )n
iP Ai i i
1
11
(1 )nA
Pi i
(1 ) 1 0
(1 )
n
n
iP A for i
i i
![Page 17: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/17.jpg)
17
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.2 Uniform Series Present Worth and Capital Recovery Factors
This expression will convert an annuity cash flow to an equivalent present worth amount one period to the left of the first annuity cash flow.
(1 ) 1 0
(1 )
n
n
iP A for i
i i
/ %, P A i n factor
![Page 18: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/18.jpg)
18
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.2 Capital Recovery Factor A/P, i%, n
Given the P/A factor
(1 ) 1 0
(1 )
n
n
iP A for i
i i
(1 )
(1 ) 1
n
n
i iA P
i
Solve for A in terms of P
Yielding….
A/P,i%,n factor
The present worth point of an annuity cash flow is always one period to the left of the first A amount
![Page 19: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/19.jpg)
19
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
CHAPTER 2: Section 3
F/A and A/F Factors
![Page 20: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/20.jpg)
20
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.3 F/A and A/F Derivations
Annuity Cash Flow
0
………….. N
$A per period
$F
Find $A given the Future amt. - $F
![Page 21: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/21.jpg)
21
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.2.3 Sinking Fund and Series Compound amount factors (A/F and F/A)
Take advantage of what we already haveRecall:
Also:
1
(1 )nP F
i
(1 )
(1 ) 1
n
n
i iA P
i
Substitute “P” and simplify!
![Page 22: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/22.jpg)
22
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.3 A/F Factor
By substitution we see:
Simplifying we have:Which is the (A/F,i%,n) factor
1 (1 )
(1 ) (1 ) 1
n
n n
i iA F
i i
(1 ) 1nA
i
iF
![Page 23: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/23.jpg)
23
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.3 F/A factor from the A/F Factor
Given:
Solve for F in terms of A
(1 ) 1n
iA F
i
)=A
(1 1F
ni
i
![Page 24: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/24.jpg)
24
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.3 F/A and A/F Derivations
Annuity Cash Flow
0
………….. N
$A per period
$F
Find $F given the $A amounts
![Page 25: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/25.jpg)
25
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.3 Example 2.5
Formosa Plastics has major fabrication plants in Texas and Hong Kong. It is desired to know the future worth of $1,000,000 invested at the end of each year for 8 years, starting one year from now. The interest rate is assumed to be 14% per year.
![Page 26: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/26.jpg)
26
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.3 Example 2.5
•A = $1,000,000/yr; n = 8 yrs, i = 14%/yr
•F8 = ??
![Page 27: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/27.jpg)
27
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.3 Example 2.5
Solution:The cash flow diagram shows the annual payments starting at the end of year 1 and ending in the year the future worth is desired. Cash flows are indicated in $1000 units. The F value in 8 years is
F = l000(F/A,14%,8) = 1000( 13.23218) = $13,232.80 = 13.232 million 8 years from now.
![Page 28: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/28.jpg)
28
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.3 Example 2.6
How much money must Carol deposit every year starting, l year from now at 5.5% per year in order to accumulate $6000 seven years from now?
![Page 29: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/29.jpg)
29
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.3 Example 2.6
Solution
The cash How diagram from Carol's perspective fits the A/F factor.
A= $6000 (A/F,5.5%,7) = 6000(0.12096) = $725.76 per yearThe A/F factor Value 0f 0.12096 was computed using the A/F factor formula
![Page 30: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/30.jpg)
30
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
CHAPTER 2: Section 4
Interpolation in Interest Tables
![Page 31: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/31.jpg)
31
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.4 Interpolation of Factors
• All texts on Engineering economy will provide tabulated values of the various interest factors usually at the end of the text in an appendix
• Refer to the back of your text for those tables.
![Page 32: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/32.jpg)
32
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.4 Interpolation of Factors
• Typical Format for Tabulated Interest Tables
![Page 33: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/33.jpg)
33
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.4 Interpolation (Estimation Process)
• At times, a set of interest tables may not have the exact interest factor needed for an analysis
• One may be forced to interpolate between two tabulated values
• Linear Interpolation is not exact because:
• The functional relationships of the interest factors are non-linear functions
• Hence from 2-5% error may be present with interpolation.
![Page 34: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/34.jpg)
34
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.4 An Example
• Assume you need the value of the A/P factor for i = 7.3% and n = 10 years.
• 7.3% is most likely not a tabulated value in most interest tables
• So, one must work with i = 7% and i = 8% for n fixed at 10
• Proceed as follows:
![Page 35: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/35.jpg)
35
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.4 Basic Setup for Interpolation
•Work with the following basic relationships
![Page 36: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/36.jpg)
36
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2. 4 i = 7.3% using the A/P factor
• For 7% we would observe:
COMPOUND PRESENT SINKING COMPOUND CAPITAL
N AMT. FACTOR WORTH FUND AMOUNT RECOVERY
F/P P/F A/F F/A A/P
10 1.9672 0.5083 0.0724 13.8164 0.14238
A/P,7%,10) = 0.14238
![Page 37: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/37.jpg)
37
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2. 4 i = 7.3% using the A/P factor
• For i = 8% we observe:
COMPOUND PRESENT SINKING COMPOUND CAPITAL
N AMT. FACTOR WORTH FUND AMOUNT RECOVERY
F/P P/F A/F F/A A/P
10 2.1589 0.4632 0.0690 14.4866 0.14903
(A/P,8%,10) = 0.14903
![Page 38: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/38.jpg)
38
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2. 4 Estimating for i = 7.3%
• Form the following relationships
![Page 39: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/39.jpg)
39
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.4 Final Estimated Factor Value
• Observe for i increasing from 7% to 8% the A/P factors also increases.
• One then adds the estimated increment to the 7% known value to yield:
![Page 40: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/40.jpg)
40
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.4. The Exact Value for 7.3%
• Using a previously programmed spreadsheet model the exact value for 7.3% is:
![Page 41: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/41.jpg)
41
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
CHAPTER 2 Section 5
P/G and A/G Factors
![Page 42: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/42.jpg)
42
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Arithmetic Gradient Factors
• In applications, the annuity cash flow pattern is not the only type of pattern encountered
•Two other types of end of period patterns are common
•The Linear or arithmetic gradient
•The geometric (% per period) gradient
•This section presents the Arithmetic Gradient
![Page 43: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/43.jpg)
43
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Arithmetic Gradient Factors
• An arithmetic (linear) Gradient is a cash flow series that either increases or decreases by a constant amount over n time periods.
•A linear gradient is always comprised of TWO components:
![Page 44: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/44.jpg)
44
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Arithmetic Gradient Factors
•The Two Components are:
•The Gradient component
•The base annuity component
•The objective is to find a closed form expression for the Present Worth of an arithmetic gradient
![Page 45: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/45.jpg)
45
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Linear Gradient Example
Assume the following:
0 1 2 3 n-1 N
A1+G
A1+2G
A1+(n-2)G
A1+(n-1)G
This represents a positive, increasing arithmetic gradient
![Page 46: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/46.jpg)
46
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Example: Linear Gradient
• Typical Negative, Increasing Gradient: G=$50
The Base Annuity= $1500
![Page 47: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/47.jpg)
47
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Example: Linear Gradient
• Desire to find the Present Worth of this cash flow
The Base Annuity= $1500
![Page 48: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/48.jpg)
48
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Arithmetic Gradient Factors
• The “G” amount is the constant arithmetic change from one time period to the next.
•The “G” amount may be positive or negative!
•The present worth point is always one time period to the left of the first cash flow in the series or,
•Two periods to the left of the first gradient cash flow!
![Page 49: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/49.jpg)
49
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.2.5 Derivation: Gradient Component Only
Focus Only on the gradient Component
G
+2G
(n-2)G
(n-1)G
0 1 2 3 n-1 N
“0” G
Removed Base annuity
![Page 50: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/50.jpg)
50
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Present Worth Point…
The Present worth point of a linear gradient is always: 2 periods to the left of the “1G” point or,
1 period to the left of the very first cash flow in the gradient series.
DO NOT FORGET THIS!
![Page 51: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/51.jpg)
51
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Present Worth Point…
0 1 2 3 4 5 6 7
$100$200
$300
$400
$500
$600
$700
X
The Present Worth Point of the Gradient
![Page 52: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/52.jpg)
52
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Gradient Component
$0
$100$200
$300
$400
$500
$600
X
The Present Worth Point of the Gradient
0 1 2 3 4 5 6 7
•The Gradient Component
![Page 53: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/53.jpg)
53
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Present Worth Point…
0 1 2 3 4 5 6 7
Base Annuity – A = $100
X
The Present Worth Point of the Gradient
•PW of the Base Annuity is at t = 0
•PWBASE Annuity=$100(P/A,i%,7)
![Page 54: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/54.jpg)
54
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Present Worth: Linear Gradient
The present worth of a linear gradient is the present worth of the two components: 1. The Present Worth of the Gradient
Component and, 2. The Present Worth of the Base
Annuity flow Requires 2 separate calculations!
![Page 55: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/55.jpg)
55
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Present Worth: Gradient Component
The PW of the Base Annuity is simply the Base Annuity –A{P/A, i%, n} factorWhat is needed is a present worth expression for the gradient component cash flow.We need to derive a closed form expression for the gradient component.
![Page 56: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/56.jpg)
56
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Present Worth: Gradient Component
General CF Diagram – Gradient Part Only
0 1 2 3 4 ……….. n-1 n
1G2G
3G(n-2)G
(n-1)G
0G
We want the PW at time t = 0 (2 periods to the left of 1G)
![Page 57: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/57.jpg)
57
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 To Begin- Derivation of P/G,i%,n
Next Step:
Factor out G and re-write as …..
( / , %,2) 2 ( / , %,3) ...
[(n-2)G](P/F,i%,n-1) + [(n-1)G](P/F,i%,n)
P G P F i G P F i
![Page 58: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/58.jpg)
58
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Factoring G out…. P/G factor
P/F,i%,2 P/F,i%,P=G ( )+2( ) +...(3 P/F,in-1)( %,n)
What is inside of the { }’s?
![Page 59: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/59.jpg)
59
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Replace (P/F’s) with closed-form
2 3 n-1 n
1 2 n-2 n-1P=G ...
(1+i) (1+i) (1+i) (1+i)
Multiply both sides by (1+i)
[1]
![Page 60: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/60.jpg)
60
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Mult. Both Sides By (n+1)…..
11 2 n-2 n-1
1 2 n-2 n-1P(1+i) =G ...
(1+i) (1+i) (1+i) (1+i)
[2]
•We have 2 equations [1] and [2].
•Next, subtract [1] from [2] and work with the resultant equation.
![Page 61: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/61.jpg)
61
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2 3 n-1 n
1 2 n-2 n-1P=G ...
(1+i) (1+i) (1+i) (1+i)
2.5 Subtracting [1] from [2]…..
11 2 n-2 n-1
1 2 n-2 n-1P(1+i) =G ...
(1+i) (1+i) (1+i) (1+i)
-
(1 ) 1
(1 ) (1 )
n
n n
i n
i i
GP
ii
![Page 62: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/62.jpg)
62
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 The P/G factor for i and N
( / , %, )P G i N factor
(1 ) 1
(1 ) (1 )
n
n n
i n
i i
GP
ii
![Page 63: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/63.jpg)
63
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Further Simplification on P/G
2
(1 ) 1( / , %, )
(1 )
N
N
i iNP G i N
i i
Remember, the present worth point of any linear gradient is 2 periods to the left of the 1-G cash flow or, 1 period to the left of the “0-G” cash flow.
P=G(P/G,i,n)
![Page 64: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/64.jpg)
64
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Extension – The A/G factor
Some authors also include the derivation of the A/G factor.A/G converts a linear gradient to an equivalent annuity cash flow.Remember, at this point one is only working with gradient componentThere still remains the annuity component that you must also handle separately!
![Page 65: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/65.jpg)
65
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 The A/G Factor
Convert G to an equivalent A
( / , , )( / , , )A G P G i n A P i n
How to do it…………
![Page 66: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/66.jpg)
66
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 A/G factor using A/P with P/G
The results follow…..
(1 ) 1
(1 ) (1 )
n
n n
i n
i i
GP
ii
(A/P,i,n)
(1 )
(1 ) 1
n
n
i i
i
![Page 67: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/67.jpg)
67
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Resultant A/G factor
(A/G,i,n) = 1
(1 ) 1n
nA G
i i
(1 ) 1
(1 ) (1 )
n
n n
i n
i i
GP
ii
(A/P,i,n)
(1 )
(1 ) 1
n
n
i i
i
![Page 68: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/68.jpg)
68
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Gradient Example
• Consider the following cash flow
0 1 2 3 4 5
$100$200
$300$400
$500
Find the present worth if i = 10%/yr; n = 5 yrs
Present Worth Point is here!And the G amt. = $100/period
![Page 69: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/69.jpg)
69
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Gradient Example- Base Annuity
• First, The Base Annuity of $100/period
0 1 2 3 4 5
A = +$100
•PW(10%) of the base annuity = $100(P/A,10%,5)
•PWBase = $100(3.7908)= $379.08
•Not Finished: We need the PW of the gradient component and then add that value to the $379.08 amount
![Page 70: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/70.jpg)
70
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Focus on the Gradient Component
0 1 2 3 4 5
$0$100
$200$300
$400
We desire the PW of the Gradient Component at t = 0
PG@t=0 = G( P/G,10%,5 ) = $100( P/G,10%,5 )
![Page 71: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/71.jpg)
71
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 The Set Up
0 1 2 3 4 5
$0$100
$200$300
$400
PG@t=0 = G(P/G,10%,5) = $100(P/G,10%,5)
G (1 ) 1P=
i (1 ) (1 )
N
N N
i N
i i i
Could substitute n=5, i=10% and G = $100 into the P/G closed form to get the value of the factor.
![Page 72: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/72.jpg)
72
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 PW of the Gradient Component
PG@t=0 = G(P/G,10%,5) = $100(P/G,10%,5)
Calculating or looking up the P/G,10%,5 factor yields the following:Pt=0 = $100(6.8618) = $686.18 for
the gradient PW
P/G,10%,5)
G (1 ) 1P=
i (1 ) (1 )
N
N N
i N
i i i
Sub. G=$100;i=0.10;n=5
6.8618
![Page 73: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/73.jpg)
73
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Gradient Example: Final Result
• PW(10%)Base Annuity = $379.08
•PW(10%)Gradient Component= $686.18
•Total PW(10%) = $379.08 + $686.18
•Equals $1065.26
•Note: The two sums occur at t =0 and can be added together – concept of equivalence
![Page 74: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/74.jpg)
74
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Example Summarized
0 1 2 3 4 5
$100$200
$300$400
$500This Cash Flow…
Is equivalent to $1065.26 at time 0 if the interest rate is 10% per year!
![Page 75: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/75.jpg)
75
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Shifted Gradient Example: i = 10%
• Consider the following Cash Flow
0 1 2 3 4 5 6 7
1. This is a “shifted” negative, decreasing gradient.
2. The PW point in time is at t = 3 (not t = o)
$600$550
$500$450
![Page 76: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/76.jpg)
76
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Shifted Gradient Example
• Consider the following Cash Flow
0 1 2 3 4 5 6 7
$600$550
$500$450
•The PW @ t = 0 requires getting the PW @ t =3;
•Then using the P/F factor move PW3 back to t=0
![Page 77: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/77.jpg)
77
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Shifted Gradient Example
• Consider the following Cash Flow
•The base annuity is a $600 cash flow for 3 time periods
0 1 2 3 4 5 6 7
$600$550
$500$450
![Page 78: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/78.jpg)
78
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Shifted Gradient Example: Base Annuity
• PW of the Base Annuity: 2 Steps
A = -$600
0 1 2 3 4 5 6 7
P3=-600(P/A,10%,4)
P3
P0
P0=P3(P/F,10%,3)
P0= [-600(P/A,10%,4)](P/F,10%,3)3.1699 0.7513
P 0-base annuity = -$1428.93
![Page 79: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/79.jpg)
79
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.5 Shifted Gradient Example: Gradient
• PW of Gradient Component: G = -$50
0 1 2 3 4 5 6 7
P3
P0
P0=P3(P/F,10%,3)
0G1G 2G 3G
P3-Grad = +50(P/G,10%,4)
P0-grad = {+50(P/G,10%,4)}(P/F,10%,3)4.3781 0.7513
=-$164.46
![Page 80: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/80.jpg)
80
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
CHAPTER 2: Section 6
Geometric Gradient
![Page 81: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/81.jpg)
81
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradients
• An arithmetic (linear) gradient changes by a fixed dollar amount each time period.
•A GEOMETRIC gradient changes by a fixed percentage each time period.
•We define a UNIFORM RATE OF CHANGE (%) for each time period
•Define “g” as the constant rate of change in decimal form by which amounts increase or decrease from one period to the next
![Page 82: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/82.jpg)
82
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradients: Increasing
• Typical Geometric Gradient Profile
•Let A1 = the first cash flow in the series
0 1 2 3 4 …….. n-1 n
A1 A1(1+g)A1(1+g)2
A1(1+g)3
A1(1+g)n-1
![Page 83: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/83.jpg)
83
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradients: Decreasing
• Typical Geometric Gradient Profile
•Let A1 = the first cash flow in the series
A1
A1(1-g)
A1(1-g)2
A1(1-g)3
A1(1-g)n-1
0 1 2 3 4 …….. n-1 n
![Page 84: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/84.jpg)
84
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradients: Derivation
• First Major Point to Remember:
•A1 does NOT define a Base Annuity;
•There is no BASE ANNUITY for a Geometric Gradient!
•The objective is to determine the Present Worth one period to the left of the A1 cash flow point in time
•Remember: The PW point in time is one period to the left of the first cash flow – A1!
![Page 85: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/85.jpg)
85
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradients: Derivation
• For a Geometric Gradient the following parameters are required:
•The interest rate per period – i
•The constant rate of change – g
•No. of time periods – n
•The starting cash flow – A1
![Page 86: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/86.jpg)
86
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradients: Starting
• Pg = The Aj’s time the respective (P/F,i,j) factor
•Write a general present worth relationship to find Pg….
2 11 1 1 1
1 2 3
(1 ) (1 ) (1 )...
(1 ) (1 ) (1 ) (1 )
n
g n
A A g A g A gP
i i i i
Now, factor out the A1 value and rewrite as..
![Page 87: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/87.jpg)
87
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradients
1 2 1
1 2 3
1 (1 ) (1 ) (1 )...
(1 ) (1 ) (1 ) (1 )
n
g n
g g gP A
i i i i
(1)
(1+g)Multuply both sides by to create another equation
(1+i)1 2 1
1 2 3
(1+g) (1+g) 1 (1 ) (1 ) (1 )...
(1+i) (1+i) (1 ) (1 ) (1 ) (1 )
n
g n
g g gP A
i i i i
(2)
Subtract (1) from (2) and the result is…..
![Page 88: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/88.jpg)
88
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradients
1 1
1+g (1 ) 11
1+i (1 ) 1
n
g n
gP A
i i
Solve for Pg and simplify to yield….
1
11
1 g i
n
g
gi
P Ai g
![Page 89: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/89.jpg)
89
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradient P/A factor
• This is the (P/A,g,i,n) factor and is valid if g is not equal to i.
1
11
1 g i
n
g
gi
P Ai g
![Page 90: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/90.jpg)
90
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradient P/A factor
•Note: If g = i we have a division by “0” – undefined.
•For g = i we can derive the closed form PW factor for this special case.
•We substitute i for g into the Pg
relationship to yield:
![Page 91: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/91.jpg)
91
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradient: i = g Case
g 1
1 1 1 1P =A ...
(1+i) (1+i) (1+i) (1+i)
1
(1 )g
nAP
i
For the case i = g
![Page 92: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/92.jpg)
92
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradients: Summary
•Pg = A1(P/A,g,i,n)
1
(1 )g
nAP
i
1
11
1 g i
n
g
g
iP A
i g
g not = to i
Case: g = i
![Page 93: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/93.jpg)
93
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradient: Notes
•The geometric gradient requires knowledge of:
•A1, i, n, and g
•There exist an infinite number of combinations for i, n, and g: Hence one will not find tabulated tables for the (P/A, g,i,n) factor.
![Page 94: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/94.jpg)
94
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradient: Notes
•You have to calculated either from the closed form for each problem or apply a pre-programmed spreadsheet model to find the needed factor value
•No spreadsheet built-in function for this factor!
![Page 95: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/95.jpg)
95
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradient: Example
•Assume maintenance costs for a particular activity will be $1700 one year from now.
•Assume an annual increase of 11% per year over a 6-year time period.
![Page 96: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/96.jpg)
96
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradient: Example
•If the interest rate is 8% per year, determine the present worth of the future expenses at time t = 0.
•First, draw a cash flow diagram to represent the model.
![Page 97: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/97.jpg)
97
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradient Example (+g)
•g = +11% per period; A1 = $1700; i = 8%/yr
0 1 2 3 4 5 6 7
$1700 $1700(1.11)1
$1700(1.11)2
$1700(1.11)3
$1700(1.11)5
PW(8%) = ??
![Page 98: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/98.jpg)
98
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Solution
303: Use "g" 667: use f-bar
Geometric Gradients"E" or g or f-bar = 11%
i= 8%N= 7
P/A,g,i,n factor is…… 7.04732
First Amt= 1,700.00$ P. Value = 11,980.44$
• P = $1700(P/A,11%,8%,7)•Need to calculate the P/A factor from the closed-form expression for a geometric gradient.•From a spreadsheet we see:
1
11
1 g i
n
g
g
iP A
i g
![Page 99: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/99.jpg)
99
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradient ( -g )
• Consider the following problem with a negative growth rate – g.
0 1 2 3 4
g = -10%/yr; i = 8%; n = 4
A1 = $1000 $900
$810$729
P0=??
We simply apply a “g” value = -0.10
![Page 100: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/100.jpg)
100
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.6 Geometric Gradient (-g value)
• Evaluate:
1
11
1 g i
n
g
g
iP A
i g
1
11
1 g i
n
g
g
iP A
i g
For a negative g value = -0.10
303: Use "g" 667: use f-bar
Geometric Gradients"E" or g or f-bar = -10%
i= 8%N= 4
P/A,g,i,n factor is…… 2.87637
First Amt= 1,000.00$ P. Value = 2,876.37$
![Page 101: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/101.jpg)
101
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
CHAPTER 2: Section 7
Determination of an Unknown Interest Rate
![Page 102: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/102.jpg)
102
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.7 When the i – rate is unknown
• A class of problems may deal with all of the parameters know except the interest rate.
•For many application-type problems, this can become a difficult task
•Termed, “rate of return analysis”
•In some cases:
•i can easily be determined
•In others, trial and error must be used
![Page 103: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/103.jpg)
103
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.7 Example: i unknown
• Assume on can invest $3000 now in a venture in anticipation of gaining $5,000 in five (5) years.
•If these amounts are accurate, what interest rate equates these two cash flows?
![Page 104: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/104.jpg)
104
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.7 Example: i unknown
• The Cash Flow Diagram is…
0 1 2 3 4 5
$3,000
$5,000
•F = P(1+i)n
•5,000 = 3,000(1+i)5
•(1+i)5 = 5,000/3000 = 1.6667
![Page 105: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/105.jpg)
105
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.7 Example: i unknown
• Solution:
0 1 2 3 4 5
$3,000
$5,000
•(1+i)5 = 5,000/3000 = 1.6667
•(1+i) = 1.66670.20
•i = 1.1076 – 1 = 0.1076 = 10.76%
![Page 106: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/106.jpg)
106
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.7 For “i” unknown
• In general, solving for “i” in a time value formulation is not straight forward.
•More often, one will have to resort to some form of trial and error approach as will be shown in future sections.
•A sample spreadsheet model for this problem follows.
![Page 107: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/107.jpg)
107
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.7 Example of the IRR function
=IRR($D7:$D12)
![Page 108: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/108.jpg)
108
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
CHAPTER 2: Section 8
Determination of Unknown Number of Years
![Page 109: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/109.jpg)
109
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.8 Unknown Number of Years
• Some problems require knowing the number of time periods required given the other parameters
•Example:
•How long will it take for $1,000 to double in value if the discount rate is 5% per year?
•Draw the cash flow diagram as….
![Page 110: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/110.jpg)
110
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.8 Unknown Number of Years
0 1 2 . . . . . . ……. n
P = $1,000
Fn = $2000
i = 5%/year; n is unknown!
![Page 111: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/111.jpg)
111
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.8 Unknown Number of Years
• Solving we have…..
0 1 2 . . . . . . ……. n
P = $1,000
Fn = $2000
•Fn=? = 1000(F/P,5%,x): 2000 =
1000(1.05)x
•Solve for “x” in closed form……
![Page 112: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/112.jpg)
112
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.8 Unknown Number of Years
• Solving we have…..
•(1.05)x = 2000/1000
•Xln(1.05) =ln(2.000)
•X = ln(1.05)/ln(2.000)
•X = 0.6931/0.0488 = 14.2057 yrs
•With discrete compounding it will take 15 years to amass $2,000 (have a little more that $2,000)
![Page 113: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/113.jpg)
113
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.8 No. of Years – NPER function
• From Excel one can formulate as:
=NPER(C23,C22,C20,C21)
![Page 114: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/114.jpg)
114
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
CHAPTER 2: Section 9
Spreadsheet Application – Basic Sensitivity Analysis
![Page 115: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/115.jpg)
115
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.9 Basic Sensitivity Analysis
• Sensitivity analysis is a procedure applied to a formulated problem whereby one can assess the impact of each input parameter relating to the output variable.
•Sensitivity analysis is best performed using a spreadsheet model.
•The procedure is to vary the input parameters within certain ranges and observe the change on the output variable.
![Page 116: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/116.jpg)
116
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.9 Basic Sensitivity Analysis
• By proper modeling, one can perform “what-if” analysis on one or more of the input parameters and observe any changes in a targeted output (response) variable
•Commercial add-in packages are available that can be linked to Excel to perform such an analysis
•Specifically: Palisade Corporation’s TopRank Excel add-in is most appropriate.
![Page 117: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/117.jpg)
117
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.9 Basic Sensitivity Analysis
• When you build your own models, devise an approach to permit varying at least one of the input parameters and store the results of each change in the output variable…then plot the results.
•If a small change in one of the input parameters represents a significant change in the output variable then…
•That input variable is “sensitive”
![Page 118: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/118.jpg)
118
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.9 Basic Sensitivity Analysis
• If an input parameter is deemed “sensitive” then some effort should go into the estimation of that parameter
•Because it does influence the response (output) variable.
•Less sensitive input parameters may not have as much effort required to estimate as those input parameters do not have that much impact on the targeted response variable.
![Page 119: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/119.jpg)
119
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
2.9 Basic Sensitivity Analysis
• When you build your own models, devise an approach to permit varying at least one of the input parameters and store the results of each change in the output variable…then plot the results.
•If a small change in one of the input parameters represents a significant change in the output variable then…
•That input variable is “sensitive”
![Page 120: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/120.jpg)
120
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
CHAPTER 2: Summary of Important Points
Mc
GrawHill
![Page 121: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/121.jpg)
121
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
Chapter Summary
• This chapter presents the fundamental time value of money relationships common to most engineering economic analysis calculations
•Derivations have been presented for:
•Present and Future Worth- P/F and F/P
•Annuity Cash flows – P/A, A/P, F/A and A/F
•Gradients – P/G, A,G and P/A,g,i,n
![Page 122: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/122.jpg)
122
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
Chapter Summary
• One must master these basic time value of money relationships in order to proceed with more meaningful analysis that can impact decision making.
•These relationships are important to you professionally and in your personal lives.
•Master these concepts!!!
![Page 123: Engineering Economy Chapter 2x](https://reader035.vdocuments.net/reader035/viewer/2022081413/546a42aeb4af9f9a7f8b4683/html5/thumbnails/123.jpg)
123
Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.
McGrawHill
ENGINEERING ECONOMY, Sixth Edition
Blank and Tarquin
End of Slide Set