engineering project management · 2015-03-22 · 1. work breakdown structure (wbs) wbs is a...

16
Pusan National University Ph.D. Young-Min, Kyoung Engineering Project Management ▶ Subject : Project Planning – Overview

Upload: others

Post on 12-Aug-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

Pusan National University

Ph.D. Young-Min, Kyoung

Engineering Project Management

▶ Subject : Project Planning – Overview ◀

Page 2: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

Project Management Process

2015-03-22 2

WBS (Work

Breakdown

Structure)

Network

Diagram

CPM

- Schedule

- Critical Path

- Completion

time, etc

Time

management

Risk

management

1

2

3

Choosing the project

Planning the project

Initiation Execution

Monitoring & Control

(10/22, W)

(11/17, M)

(11/10, M)

Closing the project

Deliverables Lessons learned

Today’s contents

Cost management

Page 3: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

1. Work Breakdown Structure (WBS)

WBS

is a deliverable-oriented decomposition of a project into smaller components

can be used

to represent the structure of a product, or

to make a service plan of a project

and provides the necessary framework for the succeeding cost estimate, resource allocation, and time management, etc.

2015-03-22 3

Page 4: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

1. Work Breakdown Structure (WBS)

Procedure

decompose the project into work elements

we call these elements or their groups as “activities”.

also called “tasks” or “work packages”

two approaches

Top-down approach

Bottom-up approach

estimate the duration of each activity

“duration” means the time required to complete an activity

determine the precedence relationship between activities

2015-03-22 4

Page 5: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

1. Work Breakdown Structure (WBS)

2015-03-22 5

Comparison of Top-down approach and Bottom-up approach

A project

Work Elements

난방·환기·공기조절장치

(수도·가스의) 배관 공사

굴착; (기초공사의) 땅파기

철골구조물 설치

들보

벽돌 공사

Page 6: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

1. Work Breakdown Structure (WBS)

2015-03-22 6

Camping Example(▲) : Top-Down approach

Camping Example(▶) : Bottom-Up approach

spoon

chopsticks

burner

Kocher

lantern

tent

aspirin

match

map

sleeping bag

hammer

so many others …

Camping

Group 1 Group 2 …

?

… …

Level n

Level n-1

cooking equipment

food & drink

sleeping equipment

emergency medicines

Camping

sleeping bag

mosquito killer

air pillow

Level 1

Level 2

Level 0

Page 7: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

1. Work Breakdown Structure (WBS)

Representation methods of WBS

2015-03-22 7

▼ Tree type

▼ List type

Page 8: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

1. Work Breakdown Structure (WBS)

Example of WBS

2015-03-22 8

cf. calculation of duration

◀ List typed WBS

Page 9: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

2. Gantt Chart / Network Diagram

Gantt Chart

2015-03-22 9

start

required information :

detailed list of tasks (← WBS)

duration of each task

relationships between the tasks

finish

※ prepare a pencil, ruler and grid sheets

Page 10: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

2. Gantt Chart / Network Diagram

Two types of Network Diagrams

2015-03-22 10

1 2 3 A B

Arrow Diagram

Activity

A

Activity

B

Event

1 Event

2 Event

3

A B

Precedence Diagram

Activity

A

Activity

B

선행관계 (precedence relationship)

AOA Diagram (Activity On Arrow)

AON Diagram (Activity On Node)

화살도형법 (ADM: Arrow Diagramming Method)

선후행관계도법 (PDM: Precedence Diagramming Method)

Page 11: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

2. Gantt Chart / Network Diagram

Representation of Networks

2015-03-22 11

A B

A precedes B

A

B

C

B, C : independent activities A precedes B and C

C

A

B

A, B : independent activities A, B precede C

A

B

C

D

A, B : independent activities C, D : independent activities A and B precede C and D

A

B

C

E

D F

Exceptional Case

Page 12: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

2. Gantt Chart / Network Diagram

Example

2015-03-22 12

A

B

D

C

E

F G

H

Page 13: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

3. Critical Path Method(CPM)

Project Scheduling

EST and ECT : Forward Calculation Method

LST and LCT : Backward Calculation Method

2015-03-22 13

3

Page 14: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

3. Critical Path Method(CPM)

EST, ECT Calculation

2015-03-22 14

A

B

D

C

E

F G

H

0 2

2 5

2 4

5 9

5 7

9 10 10 15

15 18

Page 15: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

3. Critical Path Method(CPM)

LST, LCT Calculation

2015-03-22 15

A

B

D

C

E

F G

H

0

0

2

2

2

2

5

5

2

5

4

7

5

5

9

9

5

7

7

9

9

9

10

10

10

10

15

15

15

15

18

18

Page 16: Engineering Project Management · 2015-03-22 · 1. Work Breakdown Structure (WBS) WBS is a deliverable-oriented decomposition of a project into smaller components can be used to

3. Critical Path Method(CPM)

Critical Path, Critical Activities, and Project Completion Time

The project manager should have consideration on ?

Which activities are loose ?

The critical activity may change to slack activity.

2015-03-22 16

A

B

D

C

E

F G

H

0

0

2

2

2

2

5

5

2

5

4

7

5

5

9

9

5

7

7

9

9

9

10

10

10

10

15

15

15

15

18

18