Engineers Without Borders-USA2008 International Conference
![Page 2: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/2.jpg)
University of Minnesota Chapter
Solar-Powered Well Pump and Water Tower
Amponsah, Ghana
Spring ’06 to Summer ‘07
![Page 3: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/3.jpg)
Agenda
• Community Needs
• Site Visit
• Design
• Implementation
• Challenges
![Page 4: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/4.jpg)
Community Needs
600+ students & villagers w/o clean water
Pit latrines w/o wash station
Result:Lost time in class due to diarrheal illnessGender inequality from fetching waterRare but still present: Guinea Worm
![Page 5: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/5.jpg)
Site Visit - Summer 2006
![Page 6: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/6.jpg)
VillageAbove-ground water tower
Grundfos submersible
pump
M/F sanitary toilets
Hand washing station
Biomass compost pens
Soccer field / P.E. field
Irrigated farmland for school crops
main school building
main school building
drying slab for crops and bricks
drying slab for crops and bricks
secondary
classrooms
secondary
classrooms
Control Boxw
ater line
water line
water line
Solar panel array
water faucet
water faucet
Design Layout
![Page 7: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/7.jpg)
Pump
• Grundfos SQFlex-1111GPM 30-300 VDC / 90-240 VACMultiple Protections
![Page 8: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/8.jpg)
Solar Array
8 Panel Array
BP 3115J, 115 W
12 V, 7 A Nominal
![Page 9: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/9.jpg)
Implementation- Summer 2007
![Page 10: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/10.jpg)
Raising the Water Tank
![Page 11: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/11.jpg)
Implementation
![Page 12: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/12.jpg)
Perfect or Far From?
Major Challenges:Major Challenges:
1 Transport1 Transport2 Wrong Tower2 Wrong Tower3 Incorrect Schematics3 Incorrect Schematics4 Well Log Inaccurate4 Well Log Inaccurate
![Page 13: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/13.jpg)
Challenge 1: Shipping
![Page 14: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/14.jpg)
Challenge 2: TowerChallenge 2: Tower
Main structure after our modificationsStructure present
when team arrived
10 ft10 ft
10 ft10 ft
10 ft10 ft
Seal Welds
Added Cross-Bracing
Added Footings w/ Rebar
![Page 15: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/15.jpg)
Max exposure to the sunAbove jungle canopyReduced potential of theft
• 6500 L Polytank (10L/person /day)
Challenge 2: TowerChallenge 2: Tower
![Page 16: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/16.jpg)
Challenge 2: TowerChallenge 2: Tower
![Page 17: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/17.jpg)
Designs are often modified in the field -- previous structural/failure analysis is no longer accurateDesign failures occur despite the strength of your materials
3D FVM study of 80 fps (59 mph) wind gust directed towards the lofted edge of the solar panel assembly - to be coupled with structural analysis to determine strains on mounting brackets.
necessary to prevent necessary to prevent catastrophic accidentscatastrophic accidents
Retroactive Design AnalysisRetroactive Design Analysis
Failure analysis can direct Failure analysis can direct your in-country collaborator’s your in-country collaborator’s attention to features prone to attention to features prone to failure failure
![Page 18: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/18.jpg)
Challenge 3: Incorrect SchematicsChallenge 3: Incorrect Schematics
2 Parallel 4-Panel Banks 8 Panels in Series
Result: 125 Watts in full cloud cover
Result: Random pumpshut-off in 50% sunlight
48 V 96 V
48V @ 14 A = 672 watts 96V @ 7 A = 672 watts
![Page 19: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/19.jpg)
Challenge 4: Well PerformanceChallenge 4: Well Performance
Valve to limit well outputPump Duty Cycle:
5 Gpm Lockout Lockout Lockout
2 Gpm
We had to limit well output due to incorrect well log
( = pumping, =Low Well Alarm)
Time
![Page 20: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/20.jpg)
Concluding Remarks
![Page 21: Engineers Without Borders-USA 2008 International Conference](https://reader035.vdocuments.net/reader035/viewer/2022062217/56649de65503460f94ade5db/html5/thumbnails/21.jpg)