A ‘New Model’ for English Heritage

Caroline Crewe-ReadHead of Corporate Projects and Programmes

Historic England

28 January 2016

Page 3: English heritage new model apm event 28 january 2016

Outline Background Drivers for change Change programme Approach Key lessons Role of stakeholders

Page 4: English heritage new model apm event 28 january 2016

English Heritage: a brief history

Page 5: English heritage new model apm event 28 january 2016

English Heritage: a brief history

1882 & 1913: Ancient Monuments Acts 1930s growth in the collection to 273 sites Division of responsibility with the National Trust 1970s: 5.5 million visitors to sites in England 1983: collection transferred to the Historic Buildings and

Monuments Collection for England (English Heritage)

Page 6: English heritage new model apm event 28 january 2016

English Heritage: its role

England’s heritageResearchPlanningListing Heritage at RiskAdvice to Government

National Heritage Collection420 sites and monumentsPublic accessInterpretationEducation

Page 7: English heritage new model apm event 28 january 2016
Page 8: English heritage new model apm event 28 january 2016
Page 9: English heritage new model apm event 28 january 2016
Page 10: English heritage new model apm event 28 january 2016
Page 11: English heritage new model apm event 28 january 2016
Page 12: English heritage new model apm event 28 january 2016
Page 13: English heritage new model apm event 28 january 2016
Page 14: English heritage new model apm event 28 january 2016
Page 15: English heritage new model apm event 28 january 2016
Page 16: English heritage new model apm event 28 january 2016
Page 17: English heritage new model apm event 28 january 2016

The ‘New Model’: background

Drivers for change:2010 Government Spending ReviewConservation backlog across sites and propertiesBarriers – internal and externalPrecedents set

Page 18: English heritage new model apm event 28 january 2016

The ‘New Model’: concept

New governance model:

Charity operating under the name of English Heritage to care for the National Heritage CollectionHistoric Buildings and Monuments Commission for England to continue to deliver heritage protection and planning services under the name Historic England

Page 19: English heritage new model apm event 28 january 2016

Historic Building and Monuments Commission for England

Secretary of State, DCMS

English Heritage Trust(independent charity)

National Heritage Collection Planning, Protection, Government Advice,

Conservation and Archive Services

Shared Services

Operating asHistoric England

Property Licence & Operating AgreementShared Services Agreement

Funding Agreement

Page 20: English heritage new model apm event 28 january 2016

The ‘New Model’: concept

Government investment:

One off lump sum of £80m to invest in repairs and enhancements to the National Heritage Collection

• Addressing priority conservation defects• Investment in improved facilities and interpretation

Page 21: English heritage new model apm event 28 january 2016
Page 22: English heritage new model apm event 28 january 2016

The ‘New Model’: benefits-led vision For English Heritage:

• Name and brand retained• Conservation backlog addressed• Capital investment in properties• Greater freedoms attained• Longer term planning and self-

sufficiency within 8 years

Page 23: English heritage new model apm event 28 january 2016

The ‘New Model’: benefits-led vision

For Historic England:• Clear focus and purpose and new brand identity• Increased engagement opportunities with general public• More responsive service to owners and developers• Unchanged statutory duties and responsibilities• Sites in National Heritage Collection remain in public ownership

Page 24: English heritage new model apm event 28 january 2016

Overarching timescales

2013-15 Implementation

2015-23Benefits realization

Page 25: English heritage new model apm event 28 january 2016

Implementation: Success Criteria

To split English Heritage into two organisations To establish a charity to take management of the

National Heritage Collection and take receipt of £80 Government investment

To establish a new identity for the remaining functions

Page 26: English heritage new model apm event 28 january 2016

Governance and Approach

Co-directed change Ultimate responsibility for success lay with

DCMS Responsibility for implementation and benefits

realization lay with Commission

Page 27: English heritage new model apm event 28 january 2016

New Model Programme Board

CharityProjectBoard

EH CEO and Executive Board

Head of Programme

Delivery

Historic EnglandProjectBoard

EH Chairman plusCommission

representation

Executive Board

DCMS / EH Programme Board

EH CEO and Executive Board

DCMS SRO

DCMS Directors and Project Team

DCMS / EH ‘project team’

EB Members

EH Head of Programme

Delivery

EH Head of Programme

DeliveryDCMS Project Team

English Heritage DCMS

EH CEOEB members

EH staffProject Managers

Commission Ministers

Page 28: English heritage new model apm event 28 january 2016
Page 29: English heritage new model apm event 28 january 2016

Our story: key milestones

2012: Outline Business Case developed

June 2013: £80m Government funding announced

September 2013: New Model programme team in place

Page 30: English heritage new model apm event 28 january 2016

Our story: key milestones

December 2013: Consultation launched by DCMS

June 2014: Approval of Full Business Case by HM Treasury

August 2014: Ministerial approval

Page 31: English heritage new model apm event 28 january 2016

Our story: key milestones

October 2014: Government approval published

December 2014: Legal agreement signed

April 2015: separation of English Heritage into Historic England and the English Heritage Trust

Page 32: English heritage new model apm event 28 january 2016

Stakeholder Engagement

“Leading change means actively engaging stakeholders”Managing Successful Programmes (MSP®)

Page 33: English heritage new model apm event 28 january 2016

Stakeholders: identification and analysis

Workshops held within English Heritage and DCMS

Interest and influence grid

Stakeholder management plan

Communications plan

Page 34: English heritage new model apm event 28 january 2016

Influence and interest grid

Page 35: English heritage new model apm event 28 january 2016

Vision and Leadership

Early engagement with key stakeholders

Clear vision for the totality of the change

Confident leadership throughout journey

Page 36: English heritage new model apm event 28 january 2016

Consultation

Nature of change required formal and informal consultation

Page 37: English heritage new model apm event 28 january 2016

Schedule

Page 38: English heritage new model apm event 28 january 2016

Risk Management

Page 39: English heritage new model apm event 28 january 2016

Shared Deliverables

Consultation document Full Business Case approval Contractual Framework Settlement Letters Successful Launch

Page 40: English heritage new model apm event 28 january 2016

Business Case Approval

Page 41: English heritage new model apm event 28 january 2016

Assurance

Internal Audit

Major Projects Authority (MPA)

Government Internal Audit Agency (GIAA)

Page 42: English heritage new model apm event 28 january 2016

Internal stakeholders

Page 43: English heritage new model apm event 28 january 2016

Closing Remarks

Page 44: English heritage new model apm event 28 january 2016

Thank you for listening