    System Process DocumentEntering Quality Results in Parent-Child Plans

    Department

    Responsibility/Role

    File Name 27814112.docRevision

    Document Generation Date 19/01/2010 12:21:00

    Date Modified 1/19/2010 12:21:00 PM

    Last Changed by

    Status

    Entering Quality Results in Parent-Child Plans

    Trigger:

    Concept

    You can enter, update, and view parent-child quality results within the forms application or from

    the Quality Workbench user interface. You can enter quality results directly.

    In this topic, you will enter quality results for parent-child collection plans.

    Required Field(s) Comments

    Output - Result(s) Comments

    Additional Information

    Last changed on: 1/19/2010 12:21:00 PM Page 1

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    2/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Procedure

    Step Action

    1. Begin by navigating to the Enter Quality Results page.

    Click the vertical scrollbar.

    Page 2 Last changed on: 1/19/2010 12:21:00 PM

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    3/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    2. Click the Manufacturing and Distribution Manager link.

    Last changed on: 1/19/2010 12:21:00 PM Page 3

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    4/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    3. Click the vertical scrollbar.

    Step Action

    4. Click the Enter Quality Results link.

    Page 4 Last changed on: 1/19/2010 12:21:00 PM

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    5/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    5. Use the Organizationspage to select the appropriate organization.

    Last changed on: 1/19/2010 12:21:00 PM Page 5

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    6/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    6. Click the M1 list item.

    Step Action

    7. Click the OKbutton.

    orPress [Alt+O].

    Page 6 Last changed on: 1/19/2010 12:21:00 PM

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    7/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    8. Use the Enter Quality Results page to enter the name of the parent collection plan

    for which you want to enter quality results.

    Last changed on: 1/19/2010 12:21:00 PM Page 7

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    8/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    9. Click in the Collection Plan field.

    Step Action

    10. Enter the desired information into the Collection Plan field. Enter "IC

    COLLECTION PLAN".

    Page 8 Last changed on: 1/19/2010 12:21:00 PM

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    9/24

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    10/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    12. Use the Results region to enter quality results.

    You must enter data in the collection elements that you defined as mandatory

    during the collection plan set up

    Step Action

    13. Click in the Item field.

    Page 10 Last changed on: 1/19/2010 12:21:00 PM

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    11/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    14. Enter the desired information into the Item field. Enter "IC2323".

    Last changed on: 1/19/2010 12:21:00 PM Page 11

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    12/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    15. Click in the Quantity field.

    Step Action

    16. Enter the desired information into the Quantity field. Enter "10".

    Page 12 Last changed on: 1/19/2010 12:21:00 PM

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    13/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    17. Click in the Sub field.

    Last changed on: 1/19/2010 12:21:00 PM Page 13

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    14/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    18. Enter the desired information into the Sub field. Enter "FGI".

    Step Action

    19. Click the Save button.

    Page 14 Last changed on: 1/19/2010 12:21:00 PM

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    15/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    20. Click the Child Plan list.

    Last changed on: 1/19/2010 12:21:00 PM Page 15

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    16/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    21. Click the IC DISPOSITION PLAN list item.

    Step Action

    22. Click the Enter button.

    Page 16 Last changed on: 1/19/2010 12:21:00 PM

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    17/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    23. Note that the in the Results region, the quality results you entered for the parent

    plan displays in the child plan.

    Enter the quality results of the child plan.

    Last changed on: 1/19/2010 12:21:00 PM Page 17

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    18/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    24. Click in the Disposition Quantity field.

    Step Action

    25. Enter the desired information into the Disposition Quantity field. Enter "5".

    Page 18 Last changed on: 1/19/2010 12:21:00 PM

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    19/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    26. Click in the Disposition field.

    Last changed on: 1/19/2010 12:21:00 PM Page 19

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    20/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    27. Enter the desired information into the Disposition field. Enter "REPAIR".

    Step Action

    28. Click in the Disposition Status field.

    Page 20 Last changed on: 1/19/2010 12:21:00 PM

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    21/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    29. Enter the desired information into the Disposition Status field. Enter

    "PENDING".

    Last changed on: 1/19/2010 12:21:00 PM Page 21

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    22/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    30. Click the Save button.

    Step Action

    31. Click the OKbutton.

    Page 22 Last changed on: 1/19/2010 12:21:00 PM

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    23/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    32. Click the OKbutton.

    orPress [Alt+O].

    Last changed on: 1/19/2010 12:21:00 PM Page 23

  • 8/14/2019 Entering Quality Results in Parent-Child Plans_SPD

    24/24

    System Process DocumentEntering Quality Results in Parent-Child Plans

    Step Action

    33. Click the Close button.

    Step Action

    34. You have completed the Entering Quality Results in Parent-Child Plans procedure.End of Procedure.