Enterprise Resource Planning
Implementing ERP Systems
AAPA Port Operations, Safety & Information Technology Seminar
June 11, 2009
Panel: Jim Eldridge, Steve Rauch, Dave Sleigh
![Page 2: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/2.jpg)
ERP Project Phases
Pre-Implementation
Implementation
Post-production
![Page 3: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/3.jpg)
Pre-Implementation Overview
Project GovernanceEstablishing the Project TeamVendor Selection
![Page 4: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/4.jpg)
Project Governance
Executive SupportManagement Support“Northbound Train”/”Getting on the Bus”Project Team Members
![Page 5: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/5.jpg)
Establishing the Project Team
Executive SponsorProject LeaderRepresentatives from each group impacted
− No implementation without representation− More impact, potentially more
representationVendor representative(s)
![Page 6: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/6.jpg)
Project Charter(At Minimum)
Why are you doing this projectWhat's the expected outcomeWhen is it expectedHow many resources does the team haveWho is on the teamWhere is the project located
![Page 7: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/7.jpg)
Vendor Selection(Among Other Considerations)
Request for Proposal Package− Rules for procurement− When proposals are due− How will the vendor be selected− What is desired− Current environment
![Page 8: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/8.jpg)
Vendor Selection(Among Other Considerations)
Difference between “Can you” and “How do you”Short listGive vendors the scenario you wish to seeAll project team members view the demos
![Page 9: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/9.jpg)
Vendor Selection(Among Other Considerations)
Contract Finalization − How will they be paid− What milestones must be reached, if any, to
be paid− What is the project schedule− Who owns the results− What happens if the project fails
![Page 10: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/10.jpg)
Pre-Implementation
Additional Comments by Panel
![Page 11: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/11.jpg)
Implementation Overview
Project ManagementIntegrator Roles and ResponsibilitiesTraining Configuration, Development, and TestingGo-Live
![Page 12: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/12.jpg)
Project Management
Strong project management skills requiredProject portal
− Schedules and calendars
− Change Requests
− System and project issues
− Go-live checklists
− Documents, links
![Page 13: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/13.jpg)
Integrator Roles and Responsibilities
External project manager - overall project plan and consultantsInternal project lead - assist with plan, gather requirements, obtain user buy-in, coordinate users for acceptance testing, work with development staffLook for strong technical from your vendorConfigurations and Gap analysis
![Page 14: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/14.jpg)
Training
Project leads become Subject Matter ExpertsFunctional users – formal training and prototyping sessionsDevelopment staff must master complex environment as well as functional components
![Page 15: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/15.jpg)
Configuration, Development, and Testing
Use in-house development staff; support after go-liveCycle (development -> unit testing -> “consultant” testing -> end user/acceptance testing -> ready for production -> System testing)Multiple environments: Prototype/Development, Test, ProductionMay be steep learning curve for Tech staffRegular development meetingsDevelopment should include knowledge transfer and documentation
![Page 16: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/16.jpg)
Go-Live
ConversionsDevelopment of go-live checklist with assigned responsibilities and due datesSelect a “Go / No Go” dateConsultants on-board for transition of support, issuesConsider support model during and after go-live
![Page 17: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/17.jpg)
Implementation
Additional Comments by Panel
![Page 18: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/18.jpg)
Post-Production Overview
Post go-live SupportOngoing TrainingMaintenance and SupportPatch Management
![Page 19: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/19.jpg)
Post-production SupportCongratulations!Stabilization and optimization phaseContinual process and system improvementOngoing activitiesHand off process from implementation team to management team
− CRITICAL REVIEW: Implementation Team and Vendor project close out
− Examine and approve implementation close out
![Page 20: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/20.jpg)
Post-production Support
Training for support staff should have already occurredUsers group formationConsistent updates and patching notesService Level agreements established
− Support contracts in place− Accounts established− Communication lines and process
established and understood
![Page 21: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/21.jpg)
Post-production Support
Bug Tracking and Fixing− Communications to audience− Process: Identification of System bug,
customization issue, broken or designed that way
− Migration of enhancements to maintenance and support
![Page 22: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/22.jpg)
Ongoing Training
Technical StaffUser GroupsInternal vs External trainingConsistent CommunicationsTutorials, FAQ’s, Instructional Videos, attendance of user team meetings
![Page 23: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/23.jpg)
Maintenance and SupportSchedules
− Backup schedule− Maintenance windows− Change process for timing of releases
Process change− Core enhancements− Upgrade evaluations− Functional extension planning− Upgrade/enhancement acceptance/handoff
process
![Page 24: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/24.jpg)
Patch Management
Change Management Board (Change process management)Service Desk SupportSubscription or Notification Services from application provider for notification
![Page 25: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/25.jpg)
Post-Production
Additional Comments by Panel
![Page 26: Enterprise Resource Planning System · Enterprise Resource Planning ... Pre-Implementation Implementation Post-production. ... customization issue, broken or designed that way](https://reader031.vdocuments.net/reader031/viewer/2022031906/5b919c3a09d3f215288c11c9/html5/thumbnails/26.jpg)
Audience Q&A