environment effects statement...4.3 impact assessment method 21 4.3.1 dewatering drawdown estimates...
TRANSCRIPT
Groundwater impact assessmentEES Technical Report D
Environment Effects StatementJuly 2020
Revision – 11-Jun-2020Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – ABN: N/A
AGL Wholesale Gas Limited and APATransmission Pty Limited11-Jun-2020
Groundwater impactassessmentGas Import Jetty and Pipeline Project EES Technical Report D
Technical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
AECOM
Groundwater impact assessmentGas Import Jetty and Pipeline Project EES Technical Report D
Client: AGL Wholesale Gas Limited and APA Transmission Pty LimitedABN: N/A
Prepared byAECOM Australia Pty LtdLevel 10, Tower Two, 727 Collins Street, Melbourne VIC 3008, AustraliaT +61 3 9653 1234 F +61 3 9654 7117 www.aecom.comABN 20 093 846 925
11-Jun-2020
AECOM in Australia and New Zealand is certified to ISO9001, ISO14001 AS/NZS4801 and OHSAS18001.
© AECOM Australia Pty Ltd (AECOM). All rights reserved.
AECOM has prepared this document for the sole use of the Client and for a specific purpose, each as expressly stated in the document. No otherparty should rely on this document without the prior written consent of AECOM. AECOM undertakes no duty, nor accepts any responsibility, to anythird party who may rely upon or use this document. This document has been prepared based on the Client’s description of its requirements andAECOM’s experience, having regard to assumptions that AECOM can reasonably be expected to make in accordance with sound professionalprinciples. AECOM may also have relied upon information provided by the Client and other third parties to prepare this document, some of whichmay not have been verified. Subject to the above conditions, this document may be transmitted, reproduced or disseminated only in its entirety.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
AECOM
Table of contentsExecutive summary iAbbreviations ivGlossary of terms i1.0 Introduction 1
1.1 Purpose 11.1.1 Why understanding groundwater is important 1
1.2 Project description 21.2.1 Gas Import Jetty Works 21.2.2 Pipeline Works 21.2.3 Construction 21.2.4 Operation and maintenance 31.2.5 Decommissioning 31.2.6 Groundwater considerations in the pipeline design 41.2.7 Groundwater considerations at the Crib Point Receiving Facility 9
1.3 Project Area 101.3.1 Study area 10
2.0 Scoping requirements 122.1 EES evaluation objectives 122.2 Assessment of specific environmental effects 12
3.0 Legislation, policy and guidelines 144.0 Methodology 17
4.1 Existing conditions assessment 174.1.1 Desktop assessment 174.1.2 Field program 17
4.2 Risk assessment method 19Application of mitigation measures 21
4.3 Impact assessment method 214.3.1 Dewatering drawdown estimates 224.3.2 Modification of groundwater flow regime 22
4.4 Assumptions and limitations 234.5 Stakeholder engagement 234.6 Linkage to other technical reports 24
5.0 Existing conditions 255.1 Topography and surface water 255.2 Geology 255.3 Hydrogeology 275.4 Hydraulic conductivity 275.5 Groundwater management 285.6 Groundwater quality and beneficial uses 295.7 Groundwater use 29
5.7.1 Groundwater dependent ecosystems 305.8 Groundwater - surface water interactions 315.9 Summary: hydrogeological conceptual model 32
6.0 Risk assessment 337.0 Impact assessment 37
7.1 Construction 377.1.1 Drawdown estimates from dewatering (relevant to Risk IDs HG1,
HG2, HG3) 377.1.2 Impacts on groundwater levels 387.1.3 Impacts on groundwater quality 417.1.4 Water supply (Risk ID HG6) 427.1.5 Loss of registered bores (Risk ID HG7) 42
7.2 Operation 437.2.1 Preferential flow paths (Risk ID HG9) 437.2.2 Impeded groundwater flow paths due to piles (Risk ID HG10) 44
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
AECOM
8.0 Recommended mitigation measures 459.0 Conclusion 46
9.1 Impact assessment summary 469.2 Residual risk 46
10.0 References 47
Appendix AFigures A
Appendix BTables B
Appendix CField program methodology C
Appendix DBorelogs D
Appendix ERising head tests E
Appendix FDewatering drawdown estimates F
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
iAECOM
Executive summaryThis report assesses potential impacts to groundwater associated with the construction and operationof the proposed Gas Import Jetty and Pipeline Project (the Project).
The Project would establish a gas import jetty and pipeline in Victoria comprising:
· a floating storage and regasification unit (FSRU) at Crib Point Jetty – the Gas Import Jetty Works
· a gas pipeline between Crib Point and Pakenham to connect to the Victorian TransmissionSystem (VTS) east of Pakenham – the Pipeline Works.
The Project would provide an additional supply of natural gas into the south-eastern Australian gasmarket for industrial, commercial and residential customers.
Potential supply gaps in Victoria’s gas market are predicted from 2024. The Project would improveenergy security for industrial, commercial and domestic customers and would increase competition inthe market.
Marine, surface water and contaminated soils, acid sulphate soils and contaminated sedimentstechnical assessments have been prepared to consider other water related impacts.
MethodologyThe groundwater study area includes the proposed pipeline alignment and its options, and a bufferarea of 200 metres either side of the pipeline, being the area where groundwater levels, flow orgroundwater quality could be impacted. The Crib Point Receiving Facility portion of the Gas ImportJetty Works was also assessed as part of this study.
The assessment of existing conditions for groundwater was based on a review of publicly availablegroundwater data and studies, and results of a field program carried out in December 2018 andJanuary 2019. Twenty-six shallow groundwater monitoring bores were installed along the pipelinealignment to characterise the groundwater quality, depth to groundwater and hydraulic conductivity ofthe geology along the pipeline alignment.
Potential impacts on groundwater have been identified by considering the proposed constructionmethods and identifying risks that may impact beneficial uses or groundwater users. Methods tomitigate potential impacts have been developed based on existing construction guidelines andpractices to manage environments surrounding construction sites of similar type and scale.
Existing conditionsThe study area is within the Western Port Basin (the basin). The sediments and volcanic flows of thebasin form a multilayered aquifer system dominated by a Tertiary Age sedimentary sequence, overlainby a relatively thin veneer of Quaternary sediments - including coastal and inland dune deposits,swamp and lake deposits and alluvial deposits. The maximum depth of trench excavations along thepipeline alignment is approximately three metres, but more typically two metres. Thrust bore bell holesmay be up to four metres deep. The geology encountered to this depth during the field program isunconsolidated and includes clay, silt and sand with occasional gravels.
The watertable along the pipeline is generally shallow (less than four metres below ground), butdeeper than the typical open cut trench depth of two metres in most monitoring wells installed alongthe pipeline alignment. Watertable fluctuations of up to 0.5 to two metres are typical in comparableshallow groundwater environments, with water levels shallowest in late winter/early spring anddeepest in late summer/early autumn. Although groundwater levels were measured towards the end ofsummer as part of this study (when levels are likely to be deeper), the impact assessmentconservatively considered a high watertable scenario close to ground surface (that is, within 0.5metre). Groundwater levels have previously been encountered between approximately six and eightmetres below ground surface beneath the western portion of the Crib Point Receiving Facility (wheretrenching and piling is proposed).
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
iiAECOM
Shallow geology is mostly fine grained (clay and clay/silt) with occasional sands and gravelly sands.This is consistent with generally low hydraulic conductivity values in shallow monitoring wells(geometric mean of 0.007 metres per day but up to 0.3 metres per day (measured at one location)).
Moderate to high potential aquatic and terrestrial ecosystems that may rely on groundwater have beenmapped in the study area based on national assessment, particularly in the southern portion of thestudy area. These include watercourses that cross the pipeline alignment and are mapped aspotentially gaining streams (that is, receiving groundwater as baseflow). These potential groundwaterdependent ecosystems (GDEs) were considered as part of the groundwater impact assessment.
There were 69 registered bores within the study area (of which eight were designated as ‘not used’),with 48 being for consumptive use and 21 for monitoring purposes. Four consumptive use bores(stock, stock and domestic, and irrigation) were within 30 metres of trenched pipeline sections andnone were within 60 metres of thrust bore bell holes and HDD tie-in bell holes – conservativelyestimated as the extent of reduced groundwater levels due to dewatering activities.
Impact assessmentPotential impacts identified for the construction phase of the Pipeline Works and Gas Import JettyWorks included:
· reduction in groundwater levels if dewatering activities are required with the subsequent potentialto affect registered bore users, groundwater dependent ecosystems (GDEs) and induce salineintrusion
· groundwater quality impacts from horizontal directional drilling (HDD) drilling muds
· poor quality overland flow entering open trenches
· loss, damage or inaccessibility of registered groundwater bores during construction
· groundwater quality impacts due to the installation of pilings beneath land side portion of the GasImport Jetty Works (at Crib Point Receiving Facility).
The groundwater impact assessment found limited potential for impacts on groundwater levels andflow during the operational phase of the Project. The risk of permanently reduced groundwater levelsdue to the drainage effects of preferential flow paths within the trench was considered.
Overall, construction and operation of the Pipeline Works and the Gas Import Jetty Works presentlimited risks to groundwater due to the shallow depth of trenching and horizontal boring, short durationdewatering activities (where groundwater is intersected) and clay and silt dominated nature of thematerials likely to be encountered. Where dewatering is required, the reductions in groundwater levelsare estimated to be of limited magnitude, lateral extent and duration.
The residual risk of potential impacts on groundwater were identified as being low or very low and itwas concluded that the Project is consistent with the scoping requirements and the draft evaluationobjective with respect to potential impacts on groundwater levels, quality and flow from constructionand operational activities with appropriate mitigation measures in place.
Recommended mitigation measuresThe following mitigation measures are recommended for the Project.
Mitigationmeasure ID Recommended mitigation measures Works area Stage
MM-HG01 Dewatering activities should be limited to twodays or less in trenched sections and HDD tie-inbell holes, and 10 days or less at thrust boresections and thrust bore bell holes, whereverpracticable.
Pipeline Works Construction
MM-HG02 Drilling muds used in horizontal directionaldrilling should be biodegradable and non-toxic,where geotechnical conditions allow.
Pipeline Works Construction
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
iiiAECOM
Mitigationmeasure ID Recommended mitigation measures Works area Stage
MM-HG03 Contractor(s) suitably qualified and experiencedin trenchless installation techniques and pilinginstallation should be used.
Pipeline Worksand Gas ImportJetty Works
Construction
MM-HG04 The duration that trench sections and bell holesare open should be minimised to reduce thepotential for poor quality runoff impactinggroundwater.
Pipeline Works Construction
MM-HG05 Sourcing of groundwater for construction supply(if required) should be in accordance withSection 50 Licence to take and use water of theWater Act 1989.
Pipeline Works Construction
MM-HG06 Through liaison with landholders the location,condition and functionality of potentially affectedbores (due to damage, destruction or loss ofaccess) should be visually confirmed prior toconstruction commencing, and make-goodarrangements should be agreed if required.
Pipeline Works Construction
MM-HG07 Compaction of backfill using excavated material,where practicable, should be carried out toreduce the potential for preferential lateral flowalong the trench
Pipeline Works Operation
MM-HG08 Trench blocks (such as trench/sack breakers)should be installed adjacent to watercourses,wetlands and steep slopes as shown in thestandard drawing (CPT.2373-DWG-L-0106).
Pipeline Works Operation
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
ivAECOM
AbbreviationsAbbreviation DefinitionAGL AGL Wholesale Gas Limited
APA APA Transmission Pty Limited
DELWP Department of Environment, Land, Water and Planning
EE Act Environment Effects Act 1978
EES Environment Effects Statement
EOLSS End of Line Scraper Station
EPBC Act Environment Protection and Biodiversity Conservation Act 1999
FSRU Floating storage and regasification unit
GDE Groundwater dependent ecosystem
GDE Atlas Groundwater Dependent Ecosystems Atlas
GIS Geographic information system
HDD Horizontal directional drilling
KP Kilometre point
KWR WSPA Koo Wee Rup Water Supply Protection Area
LNG Liquefied natural gas
mAHD Metres Australian Height Datum
mbgs Metres below ground surface
mbtoc Metres below top of casing
m/day Metres per day
MLV Mainline valves
MNES Matters of National Environmental Significance
PoHDA Port of Hastings Development Authority
QA Quaternary Aquifer
ROW Right of way
SEPP State Environment Protection Policy
SRW Southern Rural Water
UTAF Upper Tertiary Aquifer - Fluvial
UMTA Upper Mid Tertiary Aquifer
VTS Victorian Transmission System
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
iAECOM
Glossary of termsTerm DefinitionGaining stream A stream that receives groundwater, which adds to its overall flow.
Groundwater dependentecosystem (GDE)
A terrestrial or aquatic ecosystem that requires access to groundwater tomeet all or some of their requirements.
Groundwater users GDEs and users of existing registered bores
Hydraulic conductivity The ease with which a fluid (usually water) can move through porespaces or fractures.
Preferential flowpath The uneven and often rapid movement of water and solutes throughporous media.
Saline intrusion The movement of saline water into a freshwater aquifer, which can leadto contamination of drinking water sources and other consequences.
Subsidence The process by which an area of land sinks to a lower level than the landsurrounding it.
Watertable The surface where the water pressure head is equal to the atmosphericpressure.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
1AECOM
1.0 IntroductionThis report assesses the potential groundwater impacts associated with the construction and operationThe Project would provide an additional supply of natural gas into the south-eastern Australian gasmarket for industrial, commercial and residential customers.
The Australian Energy Market Operator has predicted potential supply gaps in Victoria’s gas marketfrom 2024 (AEMO, 2019). The Project would improve energy security for industrial, commercial anddomestic customers and would increase competition in the market.
The joint proponents of the Project are AGL Wholesale Gas Limited (AGL) and APA Transmission PtyLimited (APA).
The Project would establish a gas import jetty and pipeline comprising:
· a floating storage and regasification unit (FSRU) at Crib Point Jetty – the Gas Import Jetty Works
· a gas pipeline between Crib Point and Pakenham to connect to the Victorian TransmissionSystem (VTS) east of Pakenham – the Pipeline Works.
The Project was referred by AGL and APA to the Victorian Government under the Environment EffectsAct 1978 (Vic) on 13 September 2018 as two separate projects consisting of the Gas Import JettyWorks and Pipeline Works.
On 8 October 2018 the Minister for Planning issued a decision determining that an EnvironmentEffects Statement (EES) was required for the Project due to the potential for a range of significantenvironmental effects.
The Gas Import Jetty Works and the Pipeline Works were also referred to the CommonwealthGovernment under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) asseparate projects.
Each project was designated as a controlled action requiring impact assessment under the EPBC Act.The EES process is the accredited environmental assessment for the controlled action decisionsunder the EPBC Act in accordance with the bilateral agreement between the Commonwealth andVictorian governments.
1.1 PurposeThis report provides a groundwater impact assessment for the EES and sets out mitigation measuresfor potential impacts of the Project. This report will inform the development of an EnvironmentalManagement Framework (EMF) for the Project. The mitigation measures listed in the EMF would beimplemented in the approvals and management plans for the Project.
1.1.1 Why understanding groundwater is importantShallow groundwater is anticipated to be intersected along some sections of the Project duringconstruction activities required for the installation of the pipeline, which could potentially impactgroundwater levels, flow and quality.
It is important to assess whether these activities could impact the beneficial uses of groundwater or,groundwater users in the Project Area. Groundwater users include those people who pump water fromexisting registered groundwater bores, and groundwater dependent ecosystems (GDEs). GDEs arethose ecosystems that require access to groundwater to meet all or some of their water requirementsto maintain the communities of plants and animals and ecological processes they support, andecosystem services they provide1. These can include streams or lakes that groundwater flows into,vegetation with roots that access groundwater or biota living in cave systems.
1 Definition from Ministerial Guidelines for Groundwater Licensing and the Protection of High Value Groundwater DependentEcosystems, dated 13 April 2015.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
2AECOM
This report documents the area of potential groundwater level and groundwater quality impacts thatmay arise from the Project and documents potential risks to groundwater users (including GDEs) andbeneficial uses.
Potential impacts to groundwater quality from the Project are also considered in EES Technical ReportE: Contamination and acid sulfate soils impact assessment.
1.2 Project descriptionThe Project comprises two sets of works: the Gas Import Jetty Works and the Pipeline Works.
AGL would undertake the Gas Import Jetty Works. APA would undertake the Pipeline Works.
1.2.1 Gas Import Jetty WorksThe Gas Import Jetty Works would consist of a liquefied natural gas (LNG) import facility comprising:
· continuous mooring of an FSRU at Berth 2 of the existing Crib Point Jetty to store LNG andregasify LNG into natural gas
· Jetty Infrastructure on the Crib Point Jetty including marine loading arms (MLAs) and gas pipingto transfer the gas from the FSRU to the Crib Point Receiving Facility
· Crib Point Receiving Facility, including metering, odorant injection and nitrogen injection, whichwould be located on land adjacent to the Crib Point Jetty.
The FSRU vessel for the Project would be approximately 300 metres long and 50 metres wide. Itwould have capacity to store 170,000 cubic metres (m3) of LNG. Visiting vessels carrying LNG (LNGcarriers) would berth alongside the FSRU to transfer their LNG to the FSRU, which could take up to 36hours.
The FSRU would store the LNG as a liquid and when required, return LNG back into a gaseous stateby heating the LNG using either seawater or gas-fired boilers (a process known as regasification).
Following regasification, the natural gas would be transferred through gas piping along the jetty fromthe FSRU to the Crib Point Receiving Facility.
The Crib Point Receiving Facility would include treatment facilities to inject odorant and nitrogen (asrequired) into the natural gas to meet VTS gas quality specifications.
1.2.2 Pipeline WorksThe Pipeline Works would comprise a bi-directional gas transmission pipeline to transport gas from theCrib Point Receiving Facility to the VTS east of Pakenham.
The pipeline would be approximately 57 kilometres long with a nominal diameter of 600 millimetres.The pipeline would be buried at a depth of generally 1.2 metres below ground (to the top of the pipe).
The Pipeline Works would also comprise the following facilities:
· the pigging facility at the Crib Point Receiving Facility to enable in-line inspections of the pipelinewith a pipeline inspection gauge (pig)
· the above-ground Pakenham Delivery Facility situated adjacent to the Pakenham East rail depotto monitor and regulate the gas
· the below-ground End of Line Scraper Station (EOLSS) located at the connection point to theVTS, north of the Princes Highway in Pakenham
· two above-ground mainline valves (MLVs) located at different points along the pipeline alignmentto enable isolation of the pipeline in an emergency.
1.2.3 ConstructionThe key construction activities for the Gas Import Jetty Works would include:
· establishment of construction sites including laydown areas
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
3AECOM
· installation of Jetty Infrastructure on the Crib Point Jetty, including MLAs, gas piping mounted tothe jetty, electrical and instrumentation equipment and a firefighting system
· construction of the Crib Point Receiving Facility.
Construction for the Gas Import Jetty Works would take approximately 18 to 27 months, depending onweather conditions.
The key construction activities for the Pipeline Works would include:
· establishment of laydown areas
· construction of the pigging facility at Crib Point Receiving Facility, Pakenham Delivery Facility,two MLVs and the EOLSS
· pipeline construction using construction techniques such as trenching, horizontal directionaldrilling (HDD) or boring, typically within a 30-metre-wide pipeline construction right of way (ROW).
Construction for the Pipeline Works would take approximately 18 to 124 months, depending onweather conditions.
Subject to the staging of the works outlined above, construction for the entire Project is expected totake approximately 18 to 27 months.
1.2.4 Operation and maintenanceWhen commissioned, the FSRU would be operated by an experienced third-party operator. The CribPoint Receiving Facility and associated Jetty Infrastructure would be owned and operated by AGL oran experienced third-party operator. The Pipeline Works would be owned and operated by APA.
The FSRU may leave Western Port during the Project lifetime for activities such as scheduledmaintenance and extreme weather events.
The gas import jetty would initially receive approximately 12 LNG carriers per year with capacity toincrease to approximately 40 LNG carriers per year. The number and frequency of LNG carriersarriving each year would depend on their storage capacity and gas demand.
The Crib Point Receiving Facility is designed to be automated and may be operated unmanned undernormal operating conditions.
An operational easement of generally 15 metres wide would apply to the pipeline alignment. Thepipeline easement would be routinely inspected for any operational or maintenance issues inaccordance with APA procedures.
The pipeline would also be designed and constructed so that pigging could be undertaken to inspectthe integrity of the pipeline as required. Pigging would be undertaken around 10 years afterconstruction and then at a frequency determined by the first inspection.
The Pakenham Delivery Facility is also designed to be automated and operate unmanned undernormal operating conditions.
The EOLSS would be buried with valves contained within concrete pits. The connection to the VTSwould operate unmanned. Excavation of the site to access the EOLSS would be required for thepigging activities.
1.2.5 DecommissioningThe FSRU is proposed to operate for 20 years, although this may be shortened or extended toaddress security and stability of gas supply to south-eastern Australia. When the Project was nolonger required, the FSRU would leave Western Port.
The Jetty Infrastructure installed on the Crib Point Jetty and the Crib Point Receiving Facility would bedecommissioned and removed when no longer required. The Crib Point Jetty would remain as anoperational jetty under the management of the Port of Hastings Development Authority (PoHDA).
The pipeline would have a design life of 60 years. If the Pipeline Works were no longer required, theywould be decommissioned in accordance with Australian Standard AS2885 Pipelines – gas and liquidpetroleum and relevant legislative and approval requirements at the time of decommissioning.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
4AECOM
1.2.6 Groundwater considerations in the pipeline designThe proposed pipeline alignment is shown in blue in Figure 1-1 below. Alternative alignment optionsare shown in orange in the same figure.
Figure 1-1 Project Area
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
5AECOM
ConstructionPipeline installation is expected to occur primarily during summer, wherever practicable, whenephemeral streams are less likely to be flowing and any surface water runoff into open trenches wouldbe reduced. Groundwater levels would typically be at their lowest at this time.
The pipeline would be installed using three techniques: trenching, horizontal directional drilling (HDD),and horizontal boring. These are discussed below.
Trenching:
Trenching is the principal construction method, with 47.43 kilometres of the total 57.76 kilometres (84per cent) of pipeline designed to be installed with this method. In a number of areas with potentiallysensitive features, or for logistical reasons, HDD and boring installation techniques would be used.
The trenching process would involve excavating an open cut trench that would typically be two metresdeep and a minimum of 900 millimetres wide (600 millimetres pipe diameter plus 150 millimetres eachside). The trench width is increased to 1,800 millimetres (600 millimetres pipe diameter plus 600millimetres each side) where in situ concrete slab protection is required above the pipe. Where thetrench crosses unsealed roads, the depth may increase to 2.6 to three metres.
Typically, the time the trench is open (i.e. time between excavation and backfilling) would beminimised, however it is possible that at times the pipeline trench could remain open in the order ofseveral weeks.
Immediately prior to the pipe being installed, the trench would be dewatered to remove the majoritywater, which has collected during the time it has been open. This water may be groundwater,incidental rainwater or a combination of both. It is anticipated that pumping from the trench andinstallation of the pipe would be completed on the same day. However, for the purposes of this impactassessment, a maximum pumping period of two days (48 hours) has been assumed.
Disposal of groundwater pumped out of the trench is discussed in EES Technical Report E:Contamination and acid sulphate soils impact assessment. Wherever possible, the trench would bebackfilled with native material (that is, material removed during trench excavation) following grading toremove rocks and other deleterious material that could damage pipe coating. Packing sands would beused to backfill the trench beneath roads.
Figure 1-2 Construction right of way trenching layout
Horizontal directional drilling (HDD):
HDD would typically be used to install the pipeline beneath major roads, major watercourses and othersensitive features. The construction design involves approximately eight kilometres of the total57 kilometre pipeline length (14 per cent) using HDD methods.
HDD would involve drilling at an angle to a low point in the middle and then back up to an exit point onthe other side of the sensitive feature (road, waterway, vegetation). Entry and exit pits are typically
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
6AECOM
constructed (approximately five metres long, three metres wide and two metres deep) and used asmud pits, therefore not dewatered.
No trenches need to be excavated for this installation method and no dewatering is necessary duringdrilling and pipe installation. After drilling and installation of the pipe along the HDD section, bell holeswould be constructed at the entry and exit points to facilitate joining of the pipe (known as tying-in).These HDD tie-in bell holes would be approximately five metres long, five metres wide, and two andhalf metres deep. These may require short term dewatering if groundwater is intersected. It isanticipated that pumping from the bell hole and tying-in of the pipe would be completed on the sameday. Potential impact on groundwater quality from drilling fluids has been considered.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
7AECOM
Figure 1-3 Typical HDD process
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
8AECOM
Horizontal boring:
Horizontal thrust boring (also known as micro tunnelling) or mini-HDD would be used to install thepipeline at identified road, rail and water crossings. The preference is typically to utilise mini-HDDtechniques at these locations, with horizontal thrust boring used where mini-HDD is deemed to beunsuitable. The drilling methodology would be determined by the contractor.
Thrust boring would involve excavating an entry bell hole approximately 10 metres long, four metreswide, and up to four metres deep. The exit bell hole would typically be seven metres long, four metreswide and up to four metres deep. The boring machine drills horizontally from the entry bell holebeneath the sensitive feature until it reaches the bell hole at the end of the boring section. Thrust borebell holes would need to be dewatered prior to drilling if groundwater has seeped in. It isconservatively assumed that a depth of up to 3.5 metres of water would be present in the bell holesand would require dewatering for up to ten days. The entry and exit bell holes associated with themini-HDD technique are approximately five metres long, five metres wide and two and half metresdeep, with the duration of dewatering activities being less than that of the thrust boring technique.
The impact assessment has assumed that all horizontal boring would be by the thrust boringtechnique. This is a conservative approach given that potential drawdown impacts from dewateringwould be greater for thrust bore bell holes due to the greater footprint, depth and duration of pumpingcompared to mini-HDD.
The construction design involves approximately 1.35 kilometres of the total 57.76 kilometres pipelinelength (two per cent) using horizontal boring or mini-HDD methods.
Figure 1-4 Typical thrust bore site set up
End of line scraper station (EOLSS):
The EOLSS is where the pipeline connects to the VTS, via the Longford Dandenong Pipeline (LDP)and LDP loop line. These works would include hot tap works involving the excavation of large holestypically six metres wide, 10 metres long and up to 3.5 metres deep to allow for welding onto the
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
9AECOM
existing pipeline and drilling into it. Additional excavations would be required to install the buriedpipework, concrete retaining wall, concrete foundations and the large concrete valve pits that enablethe EOLSS to remain buried under normal operation by allowing operation of the valves to beaccessible from the surface. It is unlikely that groundwater would be intersected based on the site’selevation and regional data.
Design/operationTrench breakers:
The design of the pipeline includes the installation of ‘trench breakers’ (also known as trench blocks)across the space between the pipeline and the trench (that is, the annulus). These prevent scour ofthe trench by impeding lateral water flow along the trench annulus, and are installed at intervals insloping terrain and where overbends are required to increase or decrease the elevation of the pipelineover a short distance (such as at MLVs and watercourses).
Trench breakers are installed in a number of ways within the trench void around the pipe which mayinclude sandbags containing sand and dry mix cement compacted under and around the pipe or sandand dry mix cement placed in-situ around the pipe.
Figure 1-5 Typical trench breaker details (see APA drawing CPT.23737-DWG-L-0106 in Appendix A)
Backfill:
Rocks and other deleterious material that could affect the pipe coating are removed to allow re-use ofexcavated material. The fines are used for bedding and padding around the pipe in trenches and bellholes and the remaining material compacted in layers on top of the fines as cover above the pipe.
Hydrostatic testing:
The pipeline would be tested for leaks following installation. This is termed hydrostatic testing andinvolves filling a section of the pipeline with water and then pressurising it. Approximately 15megalitres of water would be used during hydrostatic testing. Following testing, subject to confirmationof the water quality, the water would be released onto adjoining land with appropriate slope, soil andgroundcover characteristics. Water release occurs through a dewatering structure designed to slowthe flow of water.
1.2.7 Groundwater considerations at the Crib Point Receiving FacilityMost construction activities and infrastructure installed at the Gas Import Jetty Works would be aboveground and are not considered as part of the groundwater study.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
10AECOM
Sections of below ground pipeline, including the bored section beneath The Esplanade that starts atthe Crib Point Receiving Facility, are considered part of the pipeline alignment in this groundwaterassessment.
Piling:
The installation of concrete flight auger (CFA) piles beneath the nitrogen tank is proposed at the CribPoint Receiving Facility. The technique involves boring a vertical hole to the required depth usingaugers. Concrete slurry is then pumped through the centre of the augers as they are removed from thehole, thereby backfilling the bored hole with concrete and reducing the potential for hole collapse.
Up to 100 piles, but more likely in the order of 70 piles, are proposed beneath the nitrogen tankmeasuring 25 metres in diameter. The piles would be terminated in competent rock (‘bedrock’) at up to20 metres below ground surface and have a minimum centre-to centre spacing of 2.4 metres(conservatively assuming 100 pile design).
The need for additional piles under the retaining wall or equipment slabs is considered unlikely and notconsidered further.
1.3 Project AreaThe Project Area is situated between Crib Point and Pakenham East in Victoria within the localgovernment areas of Mornington Peninsula Shire, the City of Casey and Cardinia Shire.
The Project Area includes the construction and operation footprints for the Gas Import Jetty Works andthe Pipeline Works. The Project Area also includes the locations of previous pipeline alignment optionsthat were assessed over the course of the EES which are no longer being considered.
The Project Area is detailed in EES Attachment VII Map book. An overview of the Project showing theproposed pipeline alignment and current options is shown in Figure 1-1.
The Gas Import Jetty Works would be located within Western Port at the existing Crib Point Jetty andon land immediately adjacent. The Crib Point Jetty is located within the Port of Hastings and within anarea designated as a wetland of international significance under the Ramsar Convention on Wetlandsof International Importance (the Western Port Ramsar site).
The Pipeline Works would be located on land between the Crib Point Receiving Facility and aconnection point to the VTS east of Pakenham.
The pipeline alignment was selected to minimise impacts on sensitive land uses and where possiblefollows existing pipeline easements.
The pipeline would be located on land used for various purposes including rural residential living, roadcorridors, industry, conservation reserves, hobby farming, horse studs and agriculture. The pipelinewould generally follow the Stony Point rail reserve through Hastings.
Towards Pakenham, the pipeline would cross the Gippsland rail line before reaching the proposedPakenham Delivery Facility adjacent to the Pakenham East rail depot and connecting to the VTS northof the Princes Highway.
1.3.1 Study areaThis groundwater impact assessment includes any intrusive works in the Project Area that mayintersect groundwater, as well as surrounding areas where groundwater levels or groundwater qualitycould be impacted. The groundwater study area includes the pipeline alignment, its options and abuffer area of 200 metres either side of the pipeline, considered sufficient to encompass potentialgroundwater impacts from the Project. The groundwater study area also includes the Crib PointReceiving Facility portion of the Gas Import Jetty Works, where a section of trenching and piling tosupport the facility’s nitrogen storage tank are proposed. The study area is shown in Figure 1-6 below.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
11AECOM
Figure 1-6 Study area
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
12AECOM
2.0 Scoping requirementsThe EES scoping requirements for the Project were issued by the Victorian Minister for Planning inFebruary 2019, and augment the key matters listed in the Minister's decision to require an EES. Thescoping requirements set out the specific matters to be investigated and documented in the EES in thecontext of the Ministerial guidelines for assessment of environmental effects under the EnvironmentEffects Act 1978. The EES is an accredited assessment process for the purposes of the assessmentof the Project under the EPBC Act, and the EES scoping requirements also include matters to beassessed under the EPBC Act.
2.1 EES evaluation objectivesThe following draft evaluation objective is relevant to groundwater and identifies the desired outcomesin the context of potential Project effects. The draft evaluation objectives, as set out in the final scopingrequirements, provide a framework to guide integrated assessment of the environmental effects of theProject. These draft evaluation objectives are to be used in the context of the relevant legislativerequirements set out in Section 3.0.
Draft evaluation objective for groundwater
Water and catchment values – To minimise adverse effects on water (including groundwater,waterway, wetland, estuarine, intertidal and marine) quality and movement particularly as theymight affect the ecological character of the Western Port Ramsar site.
2.2 Assessment of specific environmental effectsThe following extracts from the scoping requirements, issued by the Minister for Planning, are relevantto the draft evaluation objective listed above.Table 2-1 Scoping requirements for the groundwater impact assessment
Aspect Scoping requirement ReferKey issues The potential for adverse effects on the
functions, values and beneficial uses ofgroundwater due to the Project, ongroundwater dependent ecosystems (GDEs)and the ecological character of the WesternPort Ramsar site due to changes ingroundwater levels, behaviour or quality.
The potential for adverse effects on nearbyand downstream water environments due tochanged flow regimes, floodplain storage, run-off rates, water quality changes, or otherwaterway conditions during construction andoperation, in the context of relevant climatechange projections.
Section 7.0 (Impactassessment)
EES Technical Report C:Surface water impactassessment
EES Technical Report E:Contamination and acid sulfatesoils impact assessment
EES Technical Report B:Terrestrial and freshwaterbiodiversity impact assessment
EES Technical Report A: Marinebiodiversity impact assessment
Priorities forcharacterisingthe existingenvironment
Describe marine, estuarine, intertidal andfreshwater waters that could be affected, withrespect to water quality, water behaviour andbeneficial uses.
Characterise the local groundwater quality andbehaviour, including the protected beneficialuses and values and identifying any GDEs thatmight be affected by the Project.
Section 5.0 (Existing conditions)
EES Technical Report C:Surface water impactassessment
Technical Report E:Contamination and, acid sulfatesoils impact assessment
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
13AECOM
Aspect Scoping requirement ReferCharacterise the interaction between surfacewater and groundwater within the Project andbroader area.
Detail and evaluate the hydrological/hydro-geological modelling techniques utilised.
Technical Report B: Terrestrialand freshwater biodiversityimpact assessment
Technical Report A: Marinebiodiversity impact assessment
Design andmitigationmeasures
Identify and evaluate aspects of project worksand operations, and proposed designrefinement options or measures, that couldavoid or minimise significant effects on water,waterway or wetland environments.
Describe further potential and proposed designoptions and measures that could avoid orminimise significant effects on beneficial usesof surface water, groundwater anddownstream water environments during theproject’s construction and operation, includingresponse measures for environmentalincidents.
Section 6.0 (Risk assessment)Section 7.0 (Impactassessment)Section 8.0 (Mitigationmeasures)
Technical Report C: Surfacewater impact assessment
Technical Report E:Contamination and acid sulfatesoil impact assessment
Assessment oflikely effects
Identify and evaluate effects of the project andalternatives on groundwater, surface water,waterways and wetlands near the projectworks, including the likely extent, magnitudeand duration (short and long term) of changesto water quality, water level, temperature orflow paths during construction and operation,considering appropriate climate changescenarios and possible cumulative effectsresulting in combination with other existing orproposed projects of actions.
Section 7.0 (Impactassessment)
Technical Report C: Surfacewater impact assessment
Technical Report E:Contamination and acid sulfatesoils impact assessment
Approach tomanageperformance
Describe any further methods that areproposed to manage risks of effects ongroundwater and surface water and catchmentvalues, as well as water quality, to form part ofthe Environmental Management Framework.
Describe any further methods that areproposed to manage risks of effects as a resultof nearby projects impacting on water inflow towater environments and catchment values, aswell as water quality.
Describe and evaluate the approach tomonitoring and the proposed contingencymeasures to be implemented in the event ofadverse residual effects on water quality andcatchment values requiring furthermanagement.
Describe and evaluate the approach tomonitoring and the proposed ongoingmanagement measures to be implemented toavoid adverse residual effects on the WesternPort Ramsar site.
Section 8.0 (Mitigationmeasures)
Technical Report C: Surfacewater impact assessment
Technical Report E:Contamination and acid sulfatesoils impact assessment
Technical Report B: Terrestrialand freshwater biodiversityimpact assessment
Technical Report A: Marinebiodiversity impact assessment
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
14AECOM
In the context of this report, ‘effects’ includes all potential direct, indirect, on-site and off-siteenvironmental impacts resulting from the Project. The description and assessment of effects is notconfined to the immediate area of the Project but also considers the potential of the Project to impacton adjacent or other areas that could be affected, in the context of a systems-based approach.
3.0 Legislation, policy and guidelinesTable 3-1 summarises the relevant legislation that applies to the Project in the context of thisgroundwater impact assessment as well as the implications and required approvals.Table 3-1 Primary environmental legislation and associated information on groundwater
Document Description Implications for the Project Works AreaStateLegislation
EnvironmentEffects Act1978(EnvironmentEffects Act)
The Environment Effects Actprovides a regime whereprojects with potentiallysignificant environmentalimpacts may require thepreparation of an EES forassessment by the Minister forPlanning. An EES may berequired for declared ’publicworks’ or works determined bythe Minister for Planning torequire an EES followingreferral. Where an EES isrequired, the Minister forPlanning will issue scopingrequirements to guidepreparation of the EES.Once the EES is prepared it isplaced on exhibition for publiccomment (typically for 20 to 30days).The Minister for Planning mayappoint an inquiry to assess theimpacts of the project, takinginto account the EES studiesand any public submissions.This can involve a formalhearing.The Minister for Planningsubsequently provides anassessment (typically within 25business days of the inquiryreport being received), havingconsidered the proponent’sresponse, public submissions,EES documents and the inquiryreport. The relevant statutorydecision-makers must considerthe Minister for Planning’sAssessment when decidingwhether to approve the projectand, if so, on what conditions.
On 8 October 2018, theVictorian Minister for Planningdetermined that an EES wasrequired for the Gas ImportJetty Works and Pipeline Works(as a single joint project). InFebruary 2019, the Minister forPlanning issued the scopingrequirements for the Project.The EES has been prepared inaccordance with these scopingrequirements, which require theassessment of a range ofspecific environmental effects.The EES would be placed onpublic exhibition and an inquirywould be appointed to considerthe environmental effects of theprojects. At the conclusion ofthe EES assessment processthe Minister for Planning’sAssessment Report would beprovided to the relevantstatutory decision-makers toinform their decisions whetherto grant approvals for theprojects.
Gas ImportJetty Worksand PipelineWorks
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
15AECOM
Document Description Implications for the Project Works AreaStateLegislation
Water Act1989(Water Act)
The Water Act provides thelegal framework for theintegrated management ofVictoria’s water resources. Themain purpose of the Act is topromote the efficient andequitable use of waterresources and ensure waterresources are conserved andappropriately managed forsustainable use. The Water Actprovides a formal means ofprotecting and enhancingwaterway flow, water qualityand catchment conditions. TheAct applies to the managementof groundwater and imposeslicensing requirements inrelation to the dewatering ofgroundwater.For groundwater in southernVictoria, DELWP has delegatedthis responsibility to SouthernRural Water (includinglicensing).
Bore construction licences wereobtained from Southern RuralWater for the installation ofmonitoring wells as part of theEES assessment process.Preliminary discussionsbetween APA and SouthernRural Water have indicated thatrequirement for an extractionlicence is not anticipated fordewatering works.
PipelineWorks
EnvironmentProtection Act1970(EnvironmentProtectionAct)
The Environment Protection Actprovides a legal framework toprotect the environment inVictoria, including theprotection of air, land and waterfrom pollution. The Act isoutcome oriented, with a basicphilosophy of preventingpollution and environmentaldamage by settingenvironmental qualityobjectives and establishingprograms to meet them.The Environment Protection Actestablishes the EPA Victoria toadminister the Act and anyregulations and orders madeunder the Act, including ordersdeclaring SEPPs.
The Act regulates the dischargeto surface water or groundwaterby a system of licences andWorks Approvals. Anydischarge into a waterway orgroundwater during theconstruction or operation of theProject must be in accordancewith the requirements of theEnvironment Protection Act,including relevant SEPPs
Gas ImportJetty Worksand PipelineWorks
Pipelines Act2005(PipelinesAct)
The Pipelines Act is the primaryAct governing the constructionand operation of pipelines inVictoria. The Pipelines Actcovers ‘high transmission’pipelines for the conveyance ofgas, oil and other substances.
The Project requires a PipelineLicence under the Pipelines Actfor the construction andoperation of the PipelineWorks.Mitigation measures tominimise impacts from pipeline
PipelineWorks
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
16AECOM
Document Description Implications for the Project Works AreaStateLegislation
DELWP and Energy SafeVictoria are responsible foradministering the Act and thePipelines Regulations 2017.
construction on groundwaterwould be incorporated in thePipeline Works ConstructionEnvironment Management Plan(CEMP).
Policy / guidelines / standards
SEPP(Waters)(2018)
SEPPs are subordinate to theEnvironment Protection Act.SEPP (Waters) provides aframework for the protectionand management of waterresources in Victoria, coveringsurface waters, estuarine andmarine waters and groundwateracross the State.SEPP (Waters) aims to protectthe beneficial uses of waterresources, set water qualityindicators and objectives, andestablish rules and obligationsto achieve these objectives..
The EP Act requires that anydischarge to waters must beconsistent with SEPP (Waters).The Project would minimise thepotential impacts ongroundwater quality during theconstruction of the PipelineWorks to ensure that existingbeneficial uses are protectedthrough the Pipeline WorksCEMP. There would be noongoing impacts onceconstruction of the PipelineWorks is completed. TheEnvironmental ManagementPlan (EMP) included in theIncorporated Document in thePlanning Scheme Amendmentrequired for the Gas ImportJetty Works (including theFSRU) would also incorporatemeasures to protect beneficialuses of groundwater.
Gas ImportJetty Worksand PipelineWorks
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
17AECOM
4.0 MethodologyA systematic risk-based approach has been applied to understand the existing environment, potentialimpacts of the Project and how to avoid, minimise or manage the risk of impact.
The following sections outline the method for the groundwater impact assessment.
4.1 Existing conditions assessmentThe purpose of defining existing conditions is to inform the assessment of potential impacts from theProject. The existing conditions are described using both publicly available data and data collectedduring a field program conducted in December 2018 and January 2019. This is described furtherbelow.
4.1.1 Desktop assessmentThe publicly available data sources used in the preparation of this report are summarised in Table 4-1.Table 4-1 Publicly available data sources
Data Source
Hydrology Melbourne Water:https://www.melbournewater.com.au/water/health-and-monitoring/river-health-and-monitoring/westernport-catchmentWaterway Crossing Assessment prepared by Alluvium ConsultingAustralia (Coffey, 2018)
Aquifer units SRW Port Phillip and Western Port Atlas (SRW, 2014)Victorian Aquifer Framework2:https://www.water.vic.gov.au/groundwater/victorias-groundwater-resources/victorian-aquifer-framework
Groundwater levels DELWP Water Management Information System:http://data.water.vic.gov.au/monitoring.htmCrib Point to Pakenham Pipeline Project Desktop Geotechnical andHydrology Study (Coffey, 2018)Department of Environment, Land, Water and Planning (DELWP)database
Groundwater management SRW Koo Wee Rup WSPA (SRW, 2010)
Groundwater salinity Department of Environment, Land, Water and Planning (DELWP)database
Groundwater users DELWP Water Management Information System:http://data.water.vic.gov.au/monitoring.htm
GDEs Bureau of Meteorology: GDE Atlas:http://www.bom.gov.au/water/groundwater/gde/map.shtml
Groundwater - surfacewater interactions
Australian Hydrological Geospatial Fabric Surface HydrologyCatchments datasethttps://www.data.vic.gov.au/data/dataset/groundwater-surface-water-interaction
4.1.2 Field programThe purpose of the field program was to determine if any shallow aquifers are present along theproposed pipeline alignment and, if so, characterise the groundwater quality, depth to groundwaterand hydraulic conductivity of those aquifers.
2 Victorian Aquifer Framework - developed by DSE (now DELWP). May 2012
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
18AECOM
To achieve this, 26 shallow groundwater monitoring bores were installed along the pipeline alignmentin December 2018 and January 2019, with all bores developed and gauged. The monitoring networkwas based on:
· targeted bores:
- in low lying parts of the landscape, typically near surface water courses, where shallowgroundwater associated with alluvial sediments might be expected to be encountered
- at sites with the potential to contaminate groundwater (discussed in EES Technical Report EContamination and acid sulfate soils impact assessment)
- based on the various mapped surface geology
· infill bores:
- located along the alignment between targeted bores above to provide coverage along thelength of the proposed pipeline.
A selection of wells with enough water column for sampling and aquifer testing were chosen to providespatial coverage along the alignment, and coverage of the differing lithology encountered (i.e. clay,silty clays, sand etc.).
A summary of the groundwater investigation activities completed in the study area is presented inTable 4-2 below.Table 4-2 Field program summary table
Bore ID CPT ID DateDrilled
DateDeveloped
DateAquiferTested
DateSampled
Date Gauged/Surveyed
GW02 CPT000_GW02 10/01/19 16/01/19 - - 30/01/19
GW03 CPT000_GW03 10/01/19 16/01/19 - - 30/01/19
GW04 CPT040_B_GW04 8/01/19 15/01/19 22/01/19 23/1/419 30/01/19
GW05 CPT045_GW05 8/01/19 15/01/19 22/01/19 23/01/19 30/01/19
MW01 CPT006_MW01 6/12/18 12/12/18 21/01/19 25/01/19 30/01/19
MW02 CPT012_MW02 5/12/18 8/12/18 21/01/19 23/01/19 30/01/19
MW03 CPT012_MW03 5/12/18 8/12/18 21/01/19 23/01/19 30/01/19
MW04 CPT015_MW04 5/12/18 8/12/18 - - 30/01/19
MW05 CPT022_MW05 4/12/18 12/12/18 21/01/19 25/01/19 30/01/19
MW06 CPT027_MW06 8/01/19 15/01/19 - - 30/01/19
MW07 CPT040_B_MW07 18/12/18 19/12/18 22/01/19 24/01/19 30/01/19
MW08 CPT000_MW08 10/01/19 16/01/19 22/01/19 - 30/01/19
MW09 CPT051_MW09 17/12/18 19/12/18 22/01/19 23/01/19 30/01/19
MW10 CPT055_MW10 3/12/18 8/12/18 23/01/19 23/01/19 30/01/19
MW11 CPT000_MW11 9/01/19 15/01/19 21/01/19 23/01/19 30/01/19
MW12 CPT064_MW12 7/12/18 12/12/18 - - 30/01/19
MW13 CPT068_MW13 7/12/18 12/12/18 - - 30/01/19
MW14 CPT037_B_MW14 3/12/18 8/12/18 23/01/19 24/01/19 30/01/19
MW15 CPT000_MW15 9/01/19 16/01/19 24/01/19 22/01/19 30/01/19
MW16 CPT000_MW16 9/01/19 15/01/19 - - 30/01/19
MW17 CPT099_MW17 11/01/19 15/01/19 - - 30/01/19
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
19AECOM
Bore ID CPT ID DateDrilled
DateDeveloped
DateAquiferTested
DateSampled
Date Gauged/Surveyed
MW18 CPT107_MW18 4/12/18 8/12/18 - - 30/01/19
MW19 CPT114_MW19 4/12/18 8/12/18 - - 30/01/19
MW21 CPT129_MW21 17/12/18 19/12/18 24/01/19 30/01/19 30/01/19
MW22 CPT134_MW22 6/12/18 8/12/18 24/01/19 30/01/19 30/01/19
MW23 CPT036_C_MW23 18/12/18 19/12/18 - - 30/01/19
Bore locations are included in Figure A1 (Appendix A). Additional details on well construction areprovided in Table B1 (Appendix B) and further information on the field program are provided inAppendix C. Results of the field program have been used to describe existing conditions (see Section5.0).
4.2 Risk assessment methodThe EES scoping requirements for the Project require that a risk-based approach be adopted forassessment of the potential impacts of the Project. A risk assessment was carried out using anapproach that is consistent with Australian/New Zealand Standard AS/NZS ISO 31000:2018 RiskManagement Process.
The risk assessment process provides a method for:
· facilitating a consistent approach to risk assessment across the various specialist studies in theEES
· identifying key Project risks to inform where detailed investigations are required
· ensuring the level of investigation is proportionate to the relative environmental risk
· assessing the effectiveness of proposed mitigation measures and whether additional measuresmay be required.
Risk can be defined as a combination of:
· the magnitude of potential consequences of an event
· the likelihood of the event occurring.
The risk assessment process developed for the Project involved the assignment of consequence andlikelihood ratings which combined to give an overall risk level for each identified risk.
The initial findings of the impact assessment were used to identify and describe cause-and-effectpathways for the Project to determine links between Project activities and their subsequentenvironmental consequences (known as risk pathways). These risk pathways were identifiedconsidering the assets, values and uses requiring protection identified during the existing conditionsassessment.
Assigning consequence of risksIn this risk assessment, the consequences of a risk occurring were assigned using a consequenceguide. Specific consequence categories were developed considering existing conditions in the studyarea. The consequence rating criteria used in the risk assessment specifically for risks relating togroundwater is shown in Table 4-3.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
20AECOM
Table 4-3 Groundwater consequence rating criteria
Level Qualitative description
Negligible Change to groundwater levels, flows or quality that does not result in either:· loss of one or more beneficial uses of groundwater, or· impact to groundwater users.1
Minor Changes to groundwater levels, flows or quality results in either of the following in alocal area (i.e. within the study area):· temporary loss of one or more beneficial uses of groundwater, or· temporary impact to groundwater users.
Moderate Changes to groundwater levels, flows or quality results in either of the following in alocal area (i.e. within the study area):· long-term loss of one or more beneficial uses of groundwater, or· long-term impact to groundwater users.
Major Changes to groundwater levels, flows or quality results in either of the following over awidespread area (i.e. beyond the study area):· long-term loss of one or more beneficial uses of groundwater, or· long-term impact to groundwater users.
Severe Changes to groundwater levels, flows or quality results in either of the following over awidespread area (i.e. beyond the study area):· permanent loss of one or more beneficial uses of groundwater, or· permanent impact to groundwater users.
Note: 1 – Groundwater users refers to GDEs and users of existing registered bores.
Assigning likelihood of risksA likelihood rating for each identified risk pathway was assigned using the guide in Table 4-4 below.The likelihood criteria in the risk assessment range across a scale from ‘almost certain’ where ‘theevent is expected to occur in most circumstances or is planned to occur’ to ‘rare’ where ‘the event mayoccur only in exceptional circumstances.’Table 4-4 Likelihood guide
Level Description
Rare The event may occur only in exceptional circumstances
Unlikely The event could occur but is not expected
Possible The event could occur
Likely The event will probably occur in most circumstances
Almost certain The event is expected to occur in most circumstances or is planned to occur
Risk assessment matrix and risk ratingThe consequence and likelihood were combined to arrive at a risk rating, using the risk assessmentmatrix shown in Table 4-5.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
21AECOM
Table 4-5 Risk assessment matrix
Consequence ratingsNegligible Minor Moderate Major Severe
Likelihoodrating
Rare Very Low Very Low Low Medium Medium
Unlikely Very Low Low Low Medium High
Possible Low Low Medium High High
Likely Low Medium Medium High Very High
Almostcertain Low Medium High Very High Very High
Further information about the risk assessment process and the full risk register for the Project isdetailed in EES Attachment III Environmental risk report.
Application of mitigation measuresAn initial set of mitigation measures have been developed as part of this impact assessment. Thesemitigation measures are based on compliance with legislation and standard requirements that aretypically incorporated into the delivery of infrastructure projects of similar type, scale and complexity.
As the Pipeline Works design, construction methodology and operation strategies were wellprogressed at the commencement of this impact assessment, mitigating measures that were alreadyincorporated in the Pipeline Works design were included as initial mitigation measures.
Initial risk ratings were applied to each identified risk pathway assuming that these initial mitigationmeasures were in place.
Additional mitigation measures were developed where the initial risk ratings were categorised asmedium or higher.
The initial and additional mitigation measures have been incorporated into the Project description anddesign (where relevant) by AGL and APA and included in the EMF to effectively manage theenvironmental performance of the Project during construction and operation. See Chapter 25Environmental Management Framework for further detail on how the mitigation measures areproposed to be implemented.
The risk and impact assessment process is iterative. Potential impacts were reassessed after the riskassessment and after mitigation measures were refined. The level of residual risk was reassessedusing the same methodology to confirm the mitigation measure is effective in mitigating or managingpotential impacts, so the Project is able to satisfy the draft evaluation objectives set out in the EESscoping requirements.
4.3 Impact assessment methodPotential impacts to groundwater (quantity and quality) that could arise from the Project have beenidentified for the Pipeline Works and for piling works at the Crib Point Receiving Facility, both in termsof construction and a design life of approximately 60 years for the Pipeline Works and 20 years for theGas Import Jetty Works.
The impact assessment included consideration of drawdown on the watertable from dewatering oftrenched sections and bell holes associated with horizontal boring, the potential for the pipeline to altergroundwater flows in the long term, and the potential for the installation of piles at the Crib PointReceiving Facility to alter groundwater levels, flow and quality.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
22AECOM
The method for these estimates is discussed in more detail below and potential groundwater risks areprovided in Table 6-1.
4.3.1 Dewatering drawdown estimatesIf groundwater is intersected by sections of open trench and/or thrust bore bell holes, short-termdewatering (i.e. removal of groundwater) may be required prior to pipeline installation. Drawdown ofgroundwater from dewatering the smaller tie-in bell holes for entry and exit points of mini-HDD andHDD has conservatively been assumed to be the same as that of the thrust bore bell holes whichmeans that the highest level of potential impact is being assessed.
Potential groundwater impacts associated with the EOLSS facility are considered in Section 7.0,however, the depth to groundwater is anticipated to be between five and 10 metres (from VisualisingVictoria’s Groundwater (VVG) website3) and not likely to be intersected.
The Theis (1935) analytical solution was used to conservatively estimate the extent of drawdown (i.e.magnitude of groundwater level decline) induced by the short-term dewatering based on twoscenarios:
i. 100 metres section of open cut trench
ii. thrust bore bell hole and HDD tie-in bell holes.
For the 100 metres open cut trench scenario, a line of pumping bores was used to simulate adrawdown of approximately two metres within the trench. This was achieved by varying the pumpingrate of an individual well and the spacing of wells along the trench section. The cumulative drawdownfrom all wells was then considered at varying distances from the trench after two days of pumping. It isnoted that increasing the length of dewatered trench does not affect the estimated maximumdrawdown distances.
A similar approach was used for the thrust bore bell hole scenario. In this case however, a line ofpumping bores was used along both long edges of the bell hole to simulate a drawdown ofapproximately 3.5 metres within a 10 metre (long) by four metre (wide) by four metre (deep) bell hole.Again, individual pumping rates and well spacing were varied and the cumulative drawdowns atvarying distances from the bell hole were considered after ten days of pumping.
The drawdown estimates, and potential impacts associated with drawdown are discussed inSection 7.0.
4.3.2 Modification of groundwater flow regimeThe potential issue of groundwater flow being restricted by the Pipeline Works during operation(resulting in watertable mounding on the up hydraulic gradient side of the pipeline and watertablereduction on the down hydraulic gradient side of the pipeline) was considered. However, this issuewas not considered further in the risk and impact assessments, as it was not considered to be amaterial impact for the following reasons:
· The trench would be approximately two metres deep along much of the pipeline alignment andonly intersect groundwater along some sections.
· Although the 600 millimetres diameter pipe would impede flow, the surrounding trench is to bebackfilled with the excavated material or bedding sand and, as such, shallow groundwater flowcan be expected to continue across the trench without any material effect on groundwaterlevels.
The potential for piles beneath the nitrogen tank at the Crib Point Receiving Facility to cause changesto groundwater levels, flow and quality was considered and is discussed in Section 7.2.2.
The potential for preferential flow along the pipeline (via higher permeability backfill in the trench)causing a permanent reduction in groundwater levels around the pipeline was also considered and isdiscussed in Section 7.2.1.
3 https://www.vvg.org.au/
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
23AECOM
4.4 Assumptions and limitationsAssumptions and limitations relating to this groundwater impact assessment are provided below:
· the construction methodology would be as outlined in Section 1.2.
· the initial mitigation measures outlined in Section 8.0 would be employed as described.
4.5 Stakeholder engagementA program of stakeholder and community engagement has been undertaken to assist with Projectdevelopment (see EES Chapter 26 Stakeholder engagement).
Specific stakeholder engagement undertaken as part of this impact assessment is summarised inTable 4-6.Table 4-6 Groundwater stakeholder engagement
Activity When Key issues discussed Engagement outcomeMeeting with SouthernRural Water(Ringwood Office)
12 Oct 2018 Whether there was arequirement for permits orlicensing to extract waterfrom trenches duringpipeline construction.
Permit to extract water notrequired.
CommunityInformation Sessions(Round 1)
Feb - Mar 2019 Community membersraised concerns aboutimpacts to groundwater inagricultural areas in thenorth section of thealignment.
Potential risks andimpacts to groundwaterfor the entire alignmenthave been considered inSections 6.0, 7.0 and 8.0of this report, and EESTechnical Report E:Contamination and acidsulfate soils impactassessment.
CommunityInformation Sessions(Round 2)
Aug – Sep 2019 Concerns about themaintained pressure ofHDD and pipelineinstallation and its effectson the subsoil.
The risks and potentialimpacts from HDDoperations (includinguncontrolled drilling mudloss) are considered inSections 6.0, 7.1.3 and8.0.
CommunityInformation Sessions(Round 2)
Aug – Sep 2019 Questions on how APAhandles the ground watertable during HDD.
A description of the HDDtechnique is provided inSection 1.2.6, andpotential risks andimpacts from HDD drillingare considered inSections 6.0, 7.0 and 8.0of this report.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
24AECOM
4.6 Linkage to other technical reportsThe groundwater impact assessment should be read in conjunction with other relevant technicalreports forming part of the EES. Other potential impacts relating to biodiversity, surface water andcontamination have been considered in detail in other technical reports.
The outcomes of the groundwater impact assessment were used as inputs to:
· EES Technical Report B: Terrestrial and freshwater biodiversity impact assessment
· EES Technical Report C: Surface impact assessment
· EES Technical Report E Contamination and acid sulfate soils impact assessment
· EES Technical Report O: Agriculture impact assessment.
This report also considered the findings of:
· EES Technical Report A: Marine biodiversity impact assessment
· EES Technical Report B: Terrestrial and freshwater biodiversity impact assessment
· EES Technical Report C: Surface water impact assessment
· EES Technical Report E: Contamination and acid sulfate soils impact assessment
Where relevant to groundwater, other technical reports are considered and referenced.
Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
25AECOM
5.0 Existing conditionsExisting conditions within the study area are discussed below where they are relevant tounderstanding potential impacts to groundwater as a result of the proposed Project.
5.1 Topography and surface waterThe study area is solely located in the Western Port catchment.
The Western Port catchment varies from the hilly regions near the Bunyip State Park and StrzeleckiRanges to the low lying, flat to undulating terrain of the former Koo Wee Rup swamp with surfacewater draining from these topographic highs to Western Port.
The catchment has an area of around 3,700 square kilometres and contains over 2,200 kilometres ofrivers and creeks. Seventeen waterways enter Western Port including major rivers and creeks such asBunyip, Tarago, Cardinia, Yallock, Lang Lang and Bass River networks, all of which discharge directlyinto the Western Port Ramsar site.
Much of the catchment has been modified to support rural and green wedge land use. Historically, theKoo Wee Rup swamp covered large areas in the Western Port hinterland but was drained fordevelopment and has resulted in a number of watercourses in the lower catchment becomingchannelised drains. Although the area contains a mix of land uses, the predominant land use isagriculture consisting of dairying, grazing and horticulture.
The study area includes coastal floodplains in the lower reaches of the catchment where the relief ismostly low lying and generally flat to gently undulating. The ground surface elevation ranges fromapproximately one to two metres above sea level in the southern portion to 10-25 metres above sealevel over the northern portion, where the gently sloping topography grades up to the north.
5.2 GeologyThe site is located within the Western Port Basin (the Basin) which is a relatively shallow, structurallycontrolled sedimentary basin consisting of sediments and volcanic flows. The western side of theBasin coincides with the Clyde Monocline-Tyabb Fault System and the eastern extent is controlled bythe Heath Hill Fault. Basin sediments pinch out to the north against uplifted basement (SRW, 2010),and extend offshore to the south.
The sediments and volcanic flows of the basin form a multilayered aquifer system which is dominatedby a Tertiary Age sedimentary sequence that thickens to approximately 200 metres in the Koo WeeRup area, and pinches out along Basin margins.
The Tertiary Age sediments are overlain by a relatively thin veneer of Quaternary sediments, includingcoastal and inland dune deposits, swamp and lake deposits and alluvial deposits; although thesesediments thicken to between 10 and 50 metres in the Koo Wee Rup area.
The outcropping units in the study area are shown on Figure A1 (Appendix A) and summarised inTable 5-1 below.
The maximum depth of trench excavations along the pipeline alignment would be three metres (atroad crossings), but more typically would be two metres deep. Where thrust boring is required themaximum depth of entry and exit pit bell holes would be up to four metres deep. The geologyencountered to this depth during the field program is all unconsolidated and includes clay, silt andsand with occasional gravels. Fill overlies this sediment in places. The bore logs are presented inAppendix D.
Gas
Impo
rt Je
tty a
nd P
ipel
ine
Proj
ect E
nviro
nmen
t Effe
cts
Stat
emen
tTe
chni
cal R
epor
t D: G
roun
dwat
er im
pact
ass
essm
ent
Prep
ared
for –
AG
L W
hole
sale
Gas
Lim
ited
and
APA
Tra
nsm
issi
on P
ty L
imite
d –
6059
2634
26A
ECO
M
Tabl
e 5-
1 W
este
rn P
ort g
eolo
gica
l and
hyd
roge
olog
ical
sum
mar
y
Geo
logi
cal
Uni
tM
ain
Occ
urre
nce
Dep
th to
Aqu
ifer U
nit
Thic
knes
sLi
thol
ogy
Aqu
ifer
Laye
rH
ydro
geol
ogic
alLa
yers
Hyd
roge
olog
ical
Uni
tD
une
Dep
osits
Smal
loc
curre
nces
;C
ranb
ourn
ean
d La
ng L
ang
area
s
Out
crop
ping
Thin
,m
ostly
less
than
6m
Sand
, med
ium
to c
oars
e qu
artz
Upp
erQ
A Q
uate
rnar
yU
ndiff
eren
tiate
dre
cent
sed
imen
ts
Allu
vial
Dep
osits
Long
war
ry to
Dal
mor
eO
utcr
oppi
ngLe
ss th
an7
mC
lay,
san
d an
dgr
avel
Wes
tern
Port
Gro
upTh
roug
hout
Out
crop
tosu
bcro
p fo
r mos
tof
eas
t are
a. U
pto
75
m c
lay
cove
r in
wes
t
20 to
175
mSa
nd, g
rave
l,lim
esto
ne, c
lay,
silt
and
ligni
te
Mid
dle
UTA
F U
pper
Terti
ary
Aqui
fer
(Flu
vial
)
Baxt
er S
ands
tone
(Red
Blu
ffSa
ndst
one)
UM
TA U
pper
Mid
Terti
ary
Aqui
fer
Sher
woo
d &
Yallo
ck F
orm
atio
nO
lder
Volc
anic
sTh
roug
hout
Out
crop
inC
ranb
ourn
e an
dal
ong
Hea
th H
illFa
ult.
Up
to 2
50m
cov
er in
cent
ral B
asin
.
10 to
75
mBa
salt,
bas
altic
clay
Low
erLT
B Lo
wer
Terti
ary
Basa
ltsO
lder
Vol
cani
cs
Chi
lder
sFo
rmat
ion
Mai
noc
curre
nce:
Yallo
ck-
Yann
atha
n-La
ng L
ang
area
10 to
75
m5
to 5
0 m
Sand
and
gra
vel
with
lign
ite b
eds
LTA
Low
erTe
rtiar
y Aq
uife
rC
hild
ers
Form
atio
n
Base
men
tTh
roug
hout
Out
crop
at B
asin
mar
gins
. >40
0 m
in c
entra
l Bas
in
-Si
ltsto
ne,
sand
ston
e,cl
ayst
one
and
gran
ite.
BSE
Mes
ozoi
can
d Pa
laeo
zoic
bedr
ock
Perm
ian
glac
ial
sedi
men
ts, a
llPa
laeo
zoic
base
men
t roc
kN
ote:
hig
hlig
hted
row
s in
dica
te k
ey g
eolo
gica
l uni
ts c
onsi
dere
d re
leva
nt to
the
Pro
ject
.
27Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
5.3 HydrogeologyIn the southern portion of the Pipeline Works area, the outcropping geology is predominantlyQuaternary coastal and inland dune deposits, Quaternary alluvial sediments and outcropping UpperTertiary Red Bluff sandstone where the Quaternary sediments are absent. Groundwater is likely to belimited in lateral and vertical extent within the Quaternary sediments. Where Quaternary sedimentsbecome thinner, the watertable aquifer would be formed by the outcropping to sub-cropping weatheredRed Bluff sandstone.
Further north (from approximately kilometric point KP30), the pipeline turns inland towards Pakenhamand the Pipeline Works area is underlain by a thicker sequence of Quaternary swamp and lakesediments associated with floodplains in the Koo Wee Rup area. Here, sediments are likely to be 10 to50 metres thick and include silty clay, silts and clay lenses. Where saturated, they are likely to be lowyielding and have higher salinity groundwater (SRW, 2014).
The final two kilometres or thereabouts of the pipeline (from KP55.0) is inferred to be underlain byoutcropping basalts of the Older Volcanics Lower Tertiary Basalts aquifer. Groundwater levels areinferred to be from 10 to greater than 20 metres below ground surface (mbgs) in this area. Nomonitoring wells were installed in the basalt.
The key hydrogeological units in the study area are summarised in Table 5-1 above.
Regional groundwater flow is from the Basin margins towards Western Port. The presence of shallowaquitards, surface water features and groundwater extraction locally affect depths to groundwater.
Previous environmental investigations carried out at the Crib Point Receiving Facility have includedthe installation of monitoring wells, with groundwater levels encountered between 6.8 and 7.5 mbgs in1997 (CMPS&F, 1997 – as referenced in Jacobs, 2017). Groundwater level gauging, carried out at fivemonitoring bores in March 2017, encountered groundwater at between 6.11 and 8.35 metres belowtop of casing (mbtoc) in the western portion of the Crib Point Facility. Proposed trenching at thislocation and horizontal boring beneath Woolleys Road and The Esplanade are therefore notanticipated to intersect groundwater.
Depth to water was measured in January 2019 at all 26 monitoring wells installed as part of the EESgroundwater investigations. At four of the 26 wells the water level was below the base of the well andthe wells were recorded as being dry. That is, water levels were at least four metres below ground(MW04, MW23, MW17, MW19). Seven of the 26 wells had water levels shallower than two metresbelow ground, which is the typical base of open cut trenched sections. These wells are GW05, MW02,MW05, MW09, MW10, MW21, and MW22. A further five wells had water levels between two and threemetres below ground (GW04, MW07, MW13, MW14, MW15).
See Table B2 (Appendix B) and Figure A1 (Appendix A) for depths to groundwater.
There are no long-term water level data available from the bores installed and therefore, the seasonalwater level fluctuations have not been measured. However, it is typical in shallow, near shore aquifersto have seasonal fluctuations typically in the order of 0.5 metres, but in some instances up to twometres. Water levels tend to be shallowest in late winter and spring and deepest in late summer.Longer term fluctuations also occur due to changes in climate (e.g. drought periods).
The implications of the hydrogeological conditions described above are discussed in Section 7.0.
5.4 Hydraulic conductivityHydraulic conductivity is a measure of how quickly groundwater can flow through the sub-surface. It ishigher in a porous aquifer like sands and lower in fine-grained, clay dominant aquifers. If hydraulicconductivity is very low, the unit is often referred to as an aquitard rather than an aquifer.
Aquifer testing was undertaken in selected bores along the pipeline alignment in order to estimate thehydraulic conductivity, as described in Section 4.1.2. The results are summarised in Table 5-2 below,the slug testing methodology is described in Appendix C, and outputs provided in Appendix E.
28Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
The results show the hydraulic conductivity ranged from 2.6x10-4 to 3.2x10-1 metres per day with ageometric mean of 7.2x10-3 metres per day (8 x10-6 centimetres per second). This broadly classifiesthe aquifer tested and to be intersected by the pipeline as a clay or silty clay (Fetter, 2000).
The implications of the hydraulic conductivity described above are discussed in Section 7.0.Table 5-2 Summary of hydraulic conductivity estimates
Well ID Date Geology at screen Hydraulic conductivity (m/day)
GW04 22/01/2019 SAND 9.7E-03
GW05 22/01/2019 Clayey SAND 1.6E-02
MW05 21/01/2019 CLAY and SILT 1.4E-02
MW07 22/01/2019 CLAY/Sandy CLAY/Gravelly CLAY 2.6E-04
MW08 22/01/2019 Sandy CLAY 2.5E-03
MW09 22/01/2019Sandy CLAY/Clayey SAND
6.6E-02
MW09 22/01/2019 8.9E-02
MW10 23/01/2019Sandy CLAY
2.6E-01**
MW10 23/01/2019 3.2E-01
MW11 21/01/2019 CLAY 1.8E-03
MW14 23/01/2019 CLAY 2.8E-03
MW15 24/01/2019 CLAY 3.7E-03
MW21 24/01/2019 CLAY 2.0E-03
MW22 24/01/2019 CLAY 7.1E-03
Minimum 2.6E-04Maximum 3.2E-01Geometric Mean 7.2E-03Notes:** - Falling head test resultTests were completed on MW01, MW02 and MW03 but no results were determined due to insufficient displacement.The Butler method was used to select appropriate time period for all wells except MW15 (see Appendix C).
5.5 Groundwater managementThe central and northern portion of the proposed pipeline alignment falls within the Koo Wee RupWater Supply Protection Area (KWR WSPA), as shown in Figure A1 (Appendix A). The remainder islocated within the general Unincorporated Area.
The KWR WSPA consists of seven sub-zones and includes a Coastal Buffer area. Although no verticallimit has been placed on the depth of the KWR WSPA, it is predominantly applied to the groundwaterresource in the Western Port Group which would not be intersected during construction of the pipeline.
The KWR WSPA is managed via a Groundwater Management Plan (SRW, 2010), which documentsall local management rules including rules on trade, metering, groundwater monitoring, licenses andconsultation. A Permissible Consumptive Volume of 12,915 megalitres per year currently applies tothe KWR WSPA. While no restrictions are placed on current licence holders, no new licences wouldbe issued except for those specified in prescription of the Groundwater Management Plan.
The Unincorporated Area has no groundwater management plans or local restrictions.
It is anticipated that a permit to extract groundwater for trench dewatering during pipeline constructionwould not be required based on discussions between APA and SRW (see Table 4-6).
29Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
Water would likely be required for the pipeline construction, including for dust suppression andhydrostatic testing of the pipeline. If this water is sourced from groundwater within the KWR WSPA,then a temporary entitlement may need to be purchased from an existing licence holder as the KWRWSPA is fully allocated.
5.6 Groundwater quality and beneficial usesThe aquifer yield (a reflection of its permeability) and salinity (usually measured as total dissolvedsolids in milligrams per litre) of groundwater in the Quaternary sediments of the Upper Aquifer isknown to be highly variable, which reflects the heterogeneity of the soil type (clay, clayey silts/sands),aquifer thickness, and depth to groundwater.
Groundwater salinity was measured in 14 monitoring wells along the pipeline alignment, as describedin Section 4.1.2. The salinity, measured as total dissolved solids (TDS), ranged from 1,253 milligramsper litre at MW07 to 16,414 milligrams per litre at MW11 with an average of 6,334 milligrams per litre.
Previous environmental investigations carried out at the Crib Point Receiving Facility (part of the GasImport Jetty Works area) have indicated a TDS range of 302 to 3,760 mg/L; with an average TDS of1,621.5 mg/L (Jacobs, 2017). This is broadly consistent with regional mapping that indicates a TDSrange of 1,000 and 3,000 mg/L beneath the Crib Point Receiving Facility.
Regional TDS mapping and monitoring well data are presented on Figure A2 (Appendix A) and inTable B3 (Appendix B).
The State Environment Protection Policy (SEPP) (Waters), provides a framework to ‘protect andimprove the quality of Victoria’s waters having regard to the principles of environment protection setout in the Environment Protection Act 1970’. Groundwater segments are classified based onbackground total dissolved solids. Protected beneficial uses are provided for each segment, andgroundwater quality indicators and objectives are established to protect each beneficial use.
Groundwater across the Pipeline and Gas Import Jetty Works area is assumed as Segment B (1,201-3,100 milligrams per litre) based on salinity monitoring well data and regional mapping. The SegmentB beneficial uses to be protected include:
· water dependent ecosystems and species
· agriculture and irrigation (irrigation)
· agriculture and irrigation (stock watering)
· industrial and commercial
· water-based recreation (primary contact recreation)
· traditional owner cultural values
· cultural and spiritual values
· buildings and structures
· geothermal properties.
The implications of the groundwater quality and beneficial uses described above are discussed inSection 7.
5.7 Groundwater useThere are 69 registered groundwater bores in the study area, that is, within 200 metres of the pipelinealignment and options4 (not including the 26 monitoring wells installed as part of the EES groundwaterinvestigations). This includes eight bores designated with a status of ‘not used’. The total depth of the69 registered bores ranges from 5.4 metres below ground to 114.3 metres below ground.
4 Bore search undertaken on 10 January 2019, using the Water Measurement Information System maintained by theDepartment of Environment, Land, Water and Planning.
30Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
There is no information available on the aquifer screened by these bores. However, based on thedepths, most are likely screening the Quaternary (QA), Upper Tertiary (UTAF), and Upper Mid Tertiary(UMTA) Aquifers, as highlighted in Table 5-1.
Overall, 48 bores have been identified as being for consumptive purposes, which includes domestic,stock, irrigation, and unknown purposes. The number of bores in each category is summarised inTable 5-3 below.
Table 5-3 Registered groundwater bores in the study area
UseBores within 200 m ofthe pipeline alignmentand alternative options
Monitoring/observation usesObservation 5
Observation, groundwater investigation 1
Observation, State Observation Network 2
Groundwater investigation 10
Observation, State Observation Network, groundwater investigation 3
TOTAL – monitoring/observation 21Consumptive usesDomestic (including one bore with status ‘not used’) 3
Stock and domestic 18
Irrigation (including one bore with status ‘not used’) 3
Stock 15
Stock, domestic, irrigation 1
Unknown (including six bores with status ‘not used’) 8
TOTAL - consumptive uses 48
Potential impacts on consumptive use bores are discussed in Section 7.1.2.
5.7.1 Groundwater dependent ecosystemsThe Groundwater Dependent Ecosystems Atlas (GDE Atlas) was developed as a national dataset ofAustralian GDEs (http://www.bom.gov.au/water/groundwater/gde/map.shtml).
The Atlas contains information about:
· aquatic ecosystems that rely on the groundwater that discharges to the surface, including rivers,springs and wetlands
· terrestrial ecosystems that rely on the subsurface presence of groundwater, including vegetation
· subterranean ecosystems that live in caves and underground aquifers5.
The mapping is from two broad sources:
· national assessment: national scale assessment based on available geographic informationsystem (GIS) data and a set of rules that describe the potential for groundwater and ecosystemsto interact
5 The GDE Atlas does not contain information regarding subterranean GDESs for Victoria but is not considered relevant to thisstudy based on the geological formations intersected by the Project’s shallow construction activities.
31Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
· regional studies: more detailed assessment by state and/or regional agencies using field work,satellite imagery or application of conceptual models.
It is important to note that the identification of potential GDEs in the Atlas does not confirm that aparticular ecosystem is groundwater dependent.
Aquatic GDEsThe pipeline alignment intersects 11 watercourses designated as high potential GDEs through nationalassessment: Warringine Creek, Olivers Creek, Kings Creek, Watson Creek, Langwarrin Creek,Rutherford Creek, Western Outfall Creek, Cardinia Creek, Lower Gum Scrub Creek, Deep Creek andToomuc Creek. It is noted that the Western Port Ramsar site encompasses the last kilometre or so ofWatson Creek where it discharges into Western Port.
Between Crib Point (KP01) and the Pearcedale area (KP30), coastal wetlands described as semi-permanent saline and salt meadow wetlands that are classified as known GDEs (regional study) arewithin one to two kilometres of the pipeline alignment. Between KP19 and KP20, these GDEs fallwithin the study area (approximately 200 metres from the pipeline alignment). A number of high tomoderate potential aquatic GDEs (regional study) described as coastal wetlands/saltmarsh are alsowithin the study area. Between the Crib Point Receiving Facility and Hastings, some coastal saltmarsh(identified as potential aquatic GDEs from the GDE Atlas) are located within the Western Port Ramsarsite.
North of the Pearcedale area, the pipeline alignment turns northeast away from coastal GDEs andtowards Pakenham.
The location of potential GDEs is presented in Figure A3 (Appendix A).
Possible impacts to potential aquatic GDEs are discussed in Section 7.0.
Terrestrial GDEsThere are numerous moderate to high potential terrestrial GDEs (national assessment) that arecrossed by the pipeline alignment, particularly in the southern portion of the Pipeline Works areabetween Crib Point and the Pearcedale area. High potential terrestrial GDEs (national Assessment)are also mapped as being adjacent to the Crib Point Receiving Facility (part of the Gas Import Jettyworks). The potential GDEs include woodland, coastal saltmarsh, swamp scrub and salt meadows.Between the Crib Point Receiving Facility and Hastings, some coastal saltmarsh (identified aspotential terrestrial GDEs from the GDE Atlas) are located within the Western Port Ramsar site.
The location of potential GDEs is presented in Figure A3 (Appendix A).
Possible impacts to potential terrestrial GDEs are discussed in Section 7.0.
5.8 Groundwater - surface water interactionsSome watercourses and waterbodies receive groundwater discharge (termed ‘gaining’). A gainingwatercourse is typically perennial meaning that it flows even during low rainfall periods. However, anephemeral watercourse can also be gaining for short periods following a rainfall event and then dry up.Some watercourse and waterbodies act as recharge sources to groundwater (termed ‘losing’).Watercourses can change from gaining to losing over time and over short distances.
Where a watercourse is identified in the GDE Atlas as a potential GDE, this means that it is potentiallya gaining watercourse, that is, relying on groundwater to some extent. This includes the followingwatercourses that cross the pipeline alignment: Warringine Creek, Olivers Creek, Kings Creek,Watson Creek, Langwarrin Creek, Rutherford Creek, Western Outfall Creek, Cardinia Creek, LowerGum Scrub Creek, Deep Creek, and Toomuc Creek.
National mapping of major streams is available through the Australian Hydrological Geospatial FabricSurface Hydrology Catchments dataset. The available data is presented in Figure A3 (Appendix A)and shows that Toomuc Creek, which crosses the pipeline at approximately KP41, is a gainingwatercourse. This is consistent with the GDE Atlas mapping described above.
32Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
5.9 Summary: hydrogeological conceptual modelThe watertable in the study area is generally shallow (less than four metres below ground) and liesmostly within Quaternary sediments and Tertiary Red Bluff Sandstone. The water levels in mostmonitoring wells installed along the pipeline alignment are deeper than the depth of the pipeline trench(typically two metres). There is no Project specific monitoring data available on seasonal groundwaterlevel fluctuations. However, fluctuations of up to 0.5 to two metres are typical in comparable shallowgroundwater environments. Water levels tend to be shallowest in late winter and spring and deepest inlate summer. It is noted that the impact assessment conservatively assumes that the watertable iswithin 0.5 metres of ground surface during construction (Section 7.0).
Drilling along the pipeline alignment shows the shallow geology is mostly fine grained (clay andclay/silt) with occasional sands and gravelly sands. The hydraulic conductivity measured in shallowmonitoring wells is generally low (geometric mean of 0.007 metres per day) but up to 0.3 metres perday.
There are numerous potential aquatic and terrestrial ecosystems that may rely on groundwater,particularly in the southern portion of the study area. Groundwater may also discharge into streams.
There are 43 bores registered for consumptive uses (including irrigation, stock and domestic) withinthe study area (that is, within 200 metres of the pipeline).
The implications of the hydrogeological data presented in this section are discussed in Section 7.0,addressing potential impacts of the Project on groundwater.
33Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
6.0 Risk assessmentAn assessment of hydrogeology risks posed by the Project was undertaken in accordance with themethod described in Section 4.2. The initial and residual groundwater risks associated with the Projectare summarised in Table 6-1.
The initial risk ratings presented below consider an initial set of mitigation measures (where relevant),which are based on compliance with legislation and standard requirements that are typicallyincorporated into the delivery of infrastructure projects of similar type, scale and complexity. Riskratings were applied to each of the identified risk pathways assuming that these mitigation measureswere in place.
Except for the potential for damage or loss of registered bores during construction which was identifiedas a medium risk, all other initial risk ratings relating to groundwater were determined to be very low orlow with initial mitigation measures in place. With the inclusion of a number of additional mitigationmeasures, the subsequent residual risk ratings were determined to be low or very low.
34G
as Im
port
Jetty
and
Pip
elin
e Pr
ojec
t Env
ironm
ent E
ffect
s St
atem
ent
Tech
nica
l Rep
ort D
: Gro
undw
ater
impa
ct a
sses
smen
t
Prep
ared
for –
AG
L W
hole
sale
Gas
Lim
ited
and
APA
Tra
nsm
issi
on P
ty L
imite
d –
6059
2634
Tabl
e 6-
1 H
ydro
geol
ogy
risks
Ris
kID
Wor
ksar
eaR
isk
nam
eR
isk
path
way
Initi
al m
itiga
tion
mea
sure
Initi
al ri
skA
dditi
onal
miti
gatio
n m
easu
reR
esid
ual r
isk
CL
Ris
kC
LR
isk
Con
stru
ctio
nH
G1
Pipe
line
Wor
ksG
roun
dwat
erus
ers
Dew
ater
ing
redu
ces
grou
ndw
ater
leve
ls a
tre
gist
ered
grou
ndw
ater
bor
es.
No
initi
al m
itiga
tion
mea
sure
s id
entif
ied.
Minor
Possible
Low
MM
–HG
01D
ewat
erin
g ac
tiviti
essh
ould
be
limite
d in
dura
tion
Negligible
Unlikely
Very low
HG
2Pi
pelin
eW
orks
Pote
ntia
l GD
Es
Dew
ater
ing
redu
ces
grou
ndw
ater
leve
ls a
tpo
tent
ial G
DEs
and
/or
wat
erco
urse
s.
No
initi
al m
itiga
tion
mea
sure
s id
entif
ied.
Minor
Possible
Low
MM
-HG
01D
ewat
erin
g ac
tiviti
essh
ould
be
limite
d in
dura
tion
Minor
Unlikely
Low
HG
3Pi
pelin
eW
orks
Salin
e in
trusi
on
Dew
ater
ing
redu
ces
grou
ndw
ater
leve
lsca
usin
g sa
line
intru
sion
.
No
initi
al m
itiga
tion
mea
sure
s id
entif
ied.
Minor
Unlikely
Low
MM
-HG
01D
ewat
erin
g ac
tiviti
essh
ould
be
limite
d in
dura
tion
Minor
Rare
Very low
HG
4Pi
pelin
eW
orks
Dril
ling
mud
Unc
ontro
lled
loss
of
drilli
ng m
uds
durin
gtre
nchl
ess
inst
alla
tion,
whi
ch a
ffect
sgr
ound
wat
er q
ualit
y.
MM
-HG
03U
se c
ontra
ctor
(s)
suita
bly
qual
ified
and
expe
rienc
ed.
Minor
Unlikely
Low
MM
- HG
02D
rillin
g m
uds
used
inho
rizon
tal d
irect
iona
ldr
illing
sho
uld
bebi
odeg
rada
ble
and
non-
toxi
c, w
here
geot
echn
ical
cond
ition
s al
low
Minor
Rare
Very low
35G
as Im
port
Jetty
and
Pip
elin
e Pr
ojec
t Env
ironm
ent E
ffect
s St
atem
ent
Tech
nica
l Rep
ort D
: Gro
undw
ater
impa
ct a
sses
smen
t
Prep
ared
for –
AG
L W
hole
sale
Gas
Lim
ited
and
APA
Tra
nsm
issi
on P
ty L
imite
d –
6059
2634
Ris
kID
Wor
ksar
eaR
isk
nam
eR
isk
path
way
Initi
al m
itiga
tion
mea
sure
Initi
al ri
skA
dditi
onal
miti
gatio
n m
easu
reR
esid
ual r
isk
CL
Ris
kC
LR
isk
HG
5Pi
pelin
eW
orks
Ove
rland
flow
togr
ound
wat
erPo
or q
ualit
y ov
erla
ndflo
w e
nter
ing
grou
ndw
ater
via
tren
chor
bel
l hol
es.
No
initi
al m
itiga
tion
mea
sure
s id
entif
ied.
Minor
Possible
Low
Tren
ched
wat
erco
urse
cros
sing
s sh
ould
be
cons
truct
ed d
urin
g no
or lo
w fl
ow c
ondi
tions
as p
er E
ES T
echn
ical
Rep
ort C
:Sur
face
wat
er im
pact
asse
ssm
ent.
MM
-HG
04M
inim
ise
the
time
that
trenc
h se
ctio
ns a
ndbe
ll ho
les
are
open
Minor
Rare
Very low
HG
6Pi
pelin
eW
orks
Wat
er s
uppl
yIf
grou
ndw
ater
use
dfo
r con
stru
ctio
n ph
ase
- dra
wdo
wn
from
wat
ersu
pply
redu
ces
grou
ndw
ater
leve
ls a
tgr
ound
wat
er u
sers
(incl
. pot
entia
l GD
Esan
d re
gist
ered
bor
es).
MM
-HG
05So
urci
ng o
f gro
undw
ater
for c
onst
ruct
ion
supp
ly (i
fre
quire
d) s
houl
d be
inac
cord
ance
with
rele
vant
legi
slat
ion.
Negligible
Rare
Very low
No
addi
tiona
lm
itiga
tion
mea
sure
sid
entif
ied.
Negligible
Rare
Very low
HG
7Pi
pelin
eW
orks
Loss
of
regi
ster
ed b
ores
Reg
iste
red
bore
sbe
com
e da
mag
ed, l
ost
(des
troye
d) o
rin
acce
ssib
le th
ereb
yim
pact
ing
bore
use
r.
No
initi
al m
itiga
tion
mea
sure
s id
entif
ied.
Moderate
Likely
Medium
MM
-HG
06Vi
sual
con
firm
atio
n of
loca
tion
of p
oten
tially
impa
cted
bor
es p
rior t
oco
nstru
ctio
n an
dm
ake-
good
arra
ngem
ents
.
Minor
Rare
Very low
36G
as Im
port
Jetty
and
Pip
elin
e Pr
ojec
t Env
ironm
ent E
ffect
s St
atem
ent
Tech
nica
l Rep
ort D
: Gro
undw
ater
impa
ct a
sses
smen
t
Prep
ared
for –
AG
L W
hole
sale
Gas
Lim
ited
and
APA
Tra
nsm
issi
on P
ty L
imite
d –
6059
2634
Ris
kID
Wor
ksar
eaR
isk
nam
eR
isk
path
way
Initi
al m
itiga
tion
mea
sure
Initi
al ri
skA
dditi
onal
miti
gatio
n m
easu
reR
esid
ual r
isk
CL
Ris
kC
LR
isk
HG
8G
asIm
port
Jetty
Wor
ks
Aqui
fer
inte
rcon
nect
ion
Aqui
fers
inte
rcon
nect
ed d
urin
gau
gerin
g fo
r pilin
gin
stal
latio
n th
atad
vers
ely
impa
cts
grou
ndw
ater
qua
lity
inon
e or
mor
e aq
uife
rs.
MM
-HG
03U
se c
ontra
ctor
(s)
suita
bly
qual
ified
and
expe
rienc
ed
Minor
Unlikely
Low
No
addi
tiona
lm
itiga
tion
mea
sure
sid
entif
ied.
Minor
Unlikely
Low
Ope
ratio
nH
G9
Pipe
line
Wor
ksPr
efer
entia
l flo
wpa
ths
Tren
ched
sec
tions
of
pipe
line
crea
te a
pref
eren
tial f
low
path
resu
lting
in c
hang
edgr
ound
wat
er fl
owpa
ttern
s an
d/or
leve
lsan
d co
ntam
inan
tm
igra
tion.
MM
-HG
07C
ompa
ctio
n of
bac
kfill
usin
g ex
cava
ted
mat
eria
lM
M-H
G08
Use
of t
renc
h bl
ocks
adja
cent
tow
ater
cour
ses,
wet
land
san
d st
eepe
r ter
rain
Moderate
Unlikely
Low
No
addi
tiona
lm
itiga
tion
mea
sure
sid
entif
ied.
Moderate
Unlikely
Low
HG
10
Gas
Impo
rtJe
ttyW
orks
Pile
sPi
les
inst
alle
d be
neat
hni
troge
n ta
nk im
pedi
nggr
ound
wat
er fl
ow th
atad
vers
ely
effe
cts
grou
ndw
ater
use
rs.
No
initi
al m
itiga
tion
mea
sure
s id
entif
ied.
Negligible
Unlikely
Very low
No
addi
tiona
lm
itiga
tion
mea
sure
sid
entif
ied.
Negligible
Unlikely
Very low
37Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
7.0 Impact assessmentThis section of the report provides more detail on the potential groundwater impacts that wereidentified in the risk assessment outlined in Section 6.0. The groundwater impacts are associated withthe construction and operation of the Project, and draw on data presented in Section 5.0, dealing withexisting conditions. Impacts associated with contamination and acid sulfate soils are discussed in EESTechnical Report E: Contamination and acid sulfate soils impact assessment.
Section 8.0 provides details on the mitigation measures outlined in the risk assessment that wouldmanage potential impacts.
7.1 ConstructionThe potential groundwater impacts during the construction and installation phases of the PipelineWorks and the Gas Import Jetty Works are listed below and assessed in the following sections:
· reduction of groundwater levels (drawdown) from dewatering activities that:
- impact water levels in nearby bores
- affect groundwater availability to GDEs
- affect creek/river base flow
- cause subsidence
- cause saline intrusion.
· overland flow impacting groundwater quality, via trenches that are open
· change in groundwater quality from use of HDD drilling fluids
· water supply for dust suppression and hydrostatic (pressure) testing of the pipeline
· loss, damage or inaccessibility of registered bores during construction
· interconnection of aquifers with different groundwater quality and protected beneficial uses duringpiling installation at the Crib Point Receiving Facility.
7.1.1 Drawdown estimates from dewatering (relevant to Risk IDs HG1, HG2, HG3)The impact assessment is based on the estimated maximum drawdown that may occur because ofconstruction dewatering if shallow groundwater was encountered during construction. The method toestimate this drawdown is described in Section 4.3.1, which is a Theis analytical solution using anumber of conservative input assumptions.
A summary of the estimates of drawdown on the watertable are provided in Table 7-1 and furtherdetails are included in Appendix F.Table 7-1 Summary of drawdown estimates
ScenarioMaximum Drawdown (m)
at 10 m fromexcavation
at 25 m fromexcavation
at 60 m fromexcavation
Open trench intersecting 2 metres ofwater
0.79 0.09 -
Thrust bore bell hole or HDD tie-in bellhole intersecting 3.5 metres of water
1.81 0.78 0.10
The approach is considered a reasonable estimate of the maximum drawdown for the followingreasons:
38Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
· The assumption of a one per cent storage coefficient used in the unconfined aquifer scenario,which is considered a highly conservative value for the type of clayey dominant materials to beencountered. A higher value of storage coefficient would result in lesser drawdown impacts.
· The assumption of 0.3 metres per day (m/day) hydraulic conductivity, which is the upper end ofthe values estimated from site-specific rising head tests (discussed in Section 5.4).
· The assumed depths of water in the trench scenario (two metres) and bell hole (3.5 metres) are aconservative estimate of anticipated conditions, based on measured groundwater levels along thealignment (measured at end-January 2019).
· As part of the construction schedule, the duration of dewatering is anticipated to be less than twodays at trenched sections and HDD tie-in bell holes, and less than 10 days at thrust bore bellholes. Typically, the volume of water in the open trench or bell hole would be removed and thepipeline installed within one day and before additional dewatering is required.
The potential implications of these drawdown estimates on registered bore users, potential GDEs andsaline intrusion are discussed in the following sections.
7.1.2 Impacts on groundwater levelsRegistered groundwater bore users (Risk ID HG1)Dewatering of the trench and bell holes (thrust bore and HDD tie-in locations) has the potential totemporarily reduce groundwater levels and reduce the available drawdown in nearby groundwaterbores.
Typically, dewatering of excavations is avoided or minimised as much as practicable to reduce the riskof destabilising the trench and bell holes, and to reduce the volume of discharged water to bemanaged. Impacts to groundwater levels and flow would therefore likely be temporary and limited inmagnitude and extent; based on the predominantly low permeability soils (silts and clays), shallowdepth of excavations and short-term dewatering activities.
A reasonable worst case scenario of a high watertable, with dewatering limited to two days (fortrenching) and ten days (thrust bore and HDD bell holes) provided an estimate for the extent andmagnitude of water level reduction away from the excavation (sometimes called the cone ofdepression). The maximum extent of drawdown has been estimated following the method described inSection 4.1.2. The results are attached as Appendix H. The results suggest that drawdown wouldextend up to 30 metres from the trenched pipeline sections and around 60 metres from bell holes(thrust bore and HDD tie-in locations), even under the ‘worst case’6 scenario.
There are four bores within 30 metres of trenched sections of the pipeline alignment that areregistered for consumptive use. Location and construction information for these four bores issummarised in Table 7-2. The locations of these bores are shown in Figure A3 (Appendix A).
There are no bores registered for consumptive use within 60 metres of thrust bore bell holes or HDDtie-in bell holes. It is noted that bore WRK992476 is located in the north western portion of the CribPoint Receiving Facility, approximately 55 metres from the proposed entry and exit bell holes of thethrust bore proposed beneath The Esplanade roadway. The WMIS database status of the bore is ‘notused’ and its purpose/use is stated as unknown. Given the ‘not used’ status and likely intended use asa monitoring bore, this it is not considered a ‘consumptive bore’ for the purposes of the riskassessment.
6 Assuming the highest hydraulic conductivity value measured (0.3 metres per day), and two days of dewatering to the base ofthe trench (2 metres deep) or ten days of dewatering to the base of thrust bore pits (four metres deep). See Appendix H forfurther details.
39Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
Table 7-2 Consumptive use bores that could be impacted by dewatering
Bore ID Use Easting NorthingBoredepth
(mbgs)
Distancefrom
pipeline(m)
Distancefrom
options(m)
ClosestKP
WRK070589 Stock anddomestic 362119 5775733 26 33 20 KP 38.8
91465 Stock 355463.2 5772286 15.2 145 23 KP 30.5
121049 Irrigation 345413.2 5765624 47.8 0 NA KP 16.7
142356 Irrigation 345413.2 5765324 42.6 6 NA KP 16.4
The closest groundwater monitoring wells to bore WRK070589 are MW17 (965 m to the southwest)and MW18 (1.8 km to the northeast). Monitoring well MW17 was recorded as being dry (that is, thedepth to water was greater than four metres below ground), and the depth to water was measured as3.92 metres below ground surface (mbgs) at MW18. Therefore, the trench is unlikely to intersectgroundwater in this area during construction, and there should be no need to dewater near boreWRK070589. Based on this, no adverse impact on groundwater availability is anticipated for this user.
The closest monitoring well to bore 91465 is MW15 (300 m to the northeast), where a water level of2.24 mbgs was measured. Based on the pipeline trench depth of two metres, it is anticipated thatconstruction dewatering would not be required in that location, and no adverse impact on groundwateravailability is anticipated for this groundwater user. If groundwater levels are higher duringconstruction, and are intersected by open trenching, the conservative estimate of a 30 metredrawdown extent (based on two metres of water in the trench) means that adverse impacts ongroundwater availability for this user would still not be anticipated.
Bore 121049 (at 47.8 metres deep) and bore 142356 (at 42.6 metres deep) are both relatively deepbores and unlikely to be impacted by dewatering of shallow trench sections (if it were required). Theclosest monitoring well to these bores is MW08, located 135 m northeast of bore 121049 and 430metres northeast of bore 142356. The depth to water at MW08 was measured at 3.5 mbgs. Groundelevations at bores 112049 and 142356 are approximately 2.5 metres higher than at MW08, andtherefore groundwater levels at these locations are anticipated to be several metres below the base oftrench – generally assumed to be two mbgs. The need for dewatering is unlikely, and adverse impactson groundwater availability are not anticipated for this groundwater user. The potential for loss,damage or lack of access to these bores during construction is considered in Section 7.1.5.
Overall, the risk of adversely impacting registered bores due to dewatering of trenched sections, thrustbore bell holes and HDD tie-in bell holes is considered to be very low. Limiting the dewatering durationwhere practicable to do so would limit the cone of depression and the potential for effects ongroundwater to significantly impact on groundwater users (including at groundwater bores).
Depth to groundwater beneath the EOLSS facility is estimated to be five to 10 metres on VisualisingVictoria’s Groundwater (VVG) website7. Groundwater is not anticipated to be intersected given thatEOLSS excavations would be up to 3.5 metres deep only. The nearest registered groundwater bore(ID 84052) is approximately 200 metres southwest of the facility, where the ground surface elevation(approximately 41 mAHD) is below the base of the proposed EOLSS excavation (estimated to be47 mAHD). Therefore, any reduction in groundwater levels from dewatering of the EOLSS (if required)would not impact on the groundwater availability from the bore.
Groundwater dependent ecosystems and watercourses (Risk ID HG2)Dewatering of the trench, HDD tie-in bell holes and thrust bore pits has the potential to temporarilyreduce water levels beneath terrestrial GDEs that transpire groundwater, or to temporarily reducegroundwater inflows into gaining streams.
Typically, dewatering of excavations is avoided or minimised as much as practicable to reduce the riskof destabilising the trench and bell holes, and to reduce the volume of discharged water to be
7 https://www.vvg.org.au/
40Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
managed. Impacts to groundwater levels and flow would therefore likely be temporary and limited inmagnitude and extent; based on the predominantly low permeability soils (silts and clays), shallowdepth of excavations and short-term dewatering activities.
A reasonable worst case scenario of a high watertable, with dewatering limited to two days (fortrenching) and ten days (thrust bore and HDD bell holes) provided an estimate for the extent andmagnitude of water level reduction away from the excavation (sometimes called the cone ofdepression). The drawdown due to dewatering would only extend up to around 30 metres fromtrenched pipeline sections and up to around 60 metres from thrust bore bell holes and HDD tie-in bellholes, even under the ‘reasonable worst case’ scenario described in Section 4.3.1.
Eleven watercourses that cross the pipeline alignment have been identified as high potential aquaticGDEs from national assessment (that is, gaining streams). Information collected on these streams issummarised in Table 7-3, based on Table 5-1 in EES Technical Report C: Surface water impactassessment.
Of the potentially gaining streams listed in Table 7-3, trenching is only proposed at Olivers Creek andWestern Outfall Creek, neither of which have been identified as having intact vegetation. Anyreduction in groundwater levels from trench dewatering would be temporary in nature (less than aweek) and limited in extent (less than 0.8 metres at ten metres from the trench - conservativelyassuming two metres drawdown at the trench). HDD is proposed at all potentially gaining streams withintact vegetation identified. For HDD the potential for drawdown effects are associated with dewateringat HDD tie-in bell-holes. Any reduction in groundwater levels from dewatering would be temporary innature (less than 2 days) and limited in extent (less than 0.1 metres at 25 metres - conservativelyassuming two metres of drawdown at the HDD tie-in bell hole).Table 7-3 Watercourse assessment summary for gaining streams
Watercourse name Crossing ID Natural orConstructed Vegetation Pipeline installation
methodWarringine Creek 2 Natural Intact HDD
Kings Creek 3 Natural Intact HDD
Olivers Creek 6 Natural Cleared Trench
Watson Creek 10 Natural Intact HDD
Langwarrin Creek 12 Natural Intact HDD
Rutherford Creek 28 Constructed Cleared HDD
Western Outfall Creek 29 Constructed Cleared Trench
Cardinia Creek 46 Constructed Cleared HDD
Lower Gum ScrubCreek
49 Constructed Cleared HDD
Toomuc Creek 50 Constructed Cleared HDD
Deep Creek 51 Constructed Cleared HDD
There are other potential terrestrial GDEs within the estimated extents of drawdown associated withtrenching and bell holes (including within the construction ROW) where groundwater levels may bereduced due to short-term dewatering activities (see Figure A3, Appendix A). It is noted that thepotential aquatic and terrestrial GDEs that fall within the Western Port Ramsar site, between the CribPoint Receiving Facility and Hastings, are beyond the potential dewatering impact zone estimated inSection 7.1.1.
The BOM GDE Atlas also identifies low to moderate potential terrestrial GDEs (swampy woodland)more than 200 metres east and west of the EOLSS. As discussed above, groundwater is notanticipated to be intersected by EOLSS excavations, and further, the base of the EOLSS excavation(estimated to be 47 mAHD) is above the ground surface of these potential GDEs. Therefore, they
41Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
would not be impacted by any reduction in groundwater levels from dewatering of the EOLSS (ifrequired).
Potential impacts on aquatic and/or terrestrial GDEs from reduced groundwater levels (if any) wouldbe temporary in nature and of limited lateral extent, and the potential risk to GDEs is considered to below. Limiting the dewatering duration, where practicable to do so, would limit the cone of depressionand the potential for effects on groundwater to significantly impact on groundwater users (includingGDEs).
Potential impacts on GDEs are also discussed in EES Technical Report B: Terrestrial and freshwaterbiodiversity impact assessment.
Saline intrusion (Risk ID HG3)In coastal areas, fresher (less saline) groundwater, sometimes known as the ‘freshwater lens’, sits ontop of saline groundwater. This saline groundwater is in connection with seawater and is sometimescalled the salt wedge.
Pumping significant volumes of groundwater in coastal areas can produce long-term reductions ingroundwater levels in the fresher water, such that upward flow from the underlying salt wedge occurs.This can then increase salinity within the freshwater lens and may impact on groundwater boresand/or GDEs.
The pipeline alignment is within around 150 metres of Western Port (at MW10) in some places andtherefore the potential for saline intrusion has been considered.
As a rule of thumb, for every metre of freshwater lens thickness above sea level (or metres AustralianHeight Datum (mAHD)), the freshwater lens extends 40 metres below sea level - due to the density offreshwater compared to that of seawater8. Along the pipeline closest to the coast this would equate toa freshwater lens approximately 30 metres thick (based on groundwater elevations of 0.89 mAHD atMW10 and 0.69 mAHD at MW11). As discussed in Section 7.1.1, construction dewatering activities fortrench sections and bell holes would lead to localised, small scale (up to 0.1 metres at 60 metres fromexcavation) and temporary reductions in groundwater levels due to the shallow depth of dewatering(typically less than three metres) and short-term duration of dewatering events (up to ten days).Therefore, adverse impacts to groundwater users due to induced lateral flow from the coast (at least150 metres away) or upward flow from the underlying salt wedge (at a depth of approximately 30metres) are not anticipated. The overall risk is considered to be very low.
7.1.3 Impacts on groundwater qualityDrilling muds (Risk ID HG4)Drilling mud would be used to install the pipeline where HDD is used. If the drilling mud containscontaminants, this could potentially impact groundwater quality and beneficial uses surrounding HDDlocations.
The uncontrolled loss event of drilling muds is considered unlikely, and any impacts would bemanaged and localised, when a suitably qualified and experienced HDD contractor is used. Thepotential effects on groundwater quality could be further reduced if non-toxic and biodegradable drillingmuds are used where possible. The primary clay used for drilling mud is bentonite (sodiummontmorillonite), a non-toxic, naturally occurring mineral clay, which is added to fresh water toproduce a ‘mud’
Therefore, drilling muds to be used in the Pipeline Works should be biodegradable and non-toxicwhere geotechnically practicable, and a suitably qualified and experienced contractor would supervisethe HDD sections. Therefore, the risk of drilling muds impacting groundwater quality is considered tobe very low.
8 Based on the Ghyben-Herzberg relation.
42Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
Overland flow to groundwater (Risk ID HG5)If there is a significant rainfall event while trench sections or bell holes are open (prior to backfilling)runoff could flow into the excavation. This runoff water could be of low quality (such as having elevatednutrient concentrations) and potentially infiltrate into groundwater near the trench. The highestpotential for this to occur is at or near trench crossing of waterways where greater surface water flowwould be expected due to drainage patterns, and there is potential for higher hydraulic conductivitysediments associated with the waterway.
Trenched water crossings should be installed during no flow or low flow conditions wherever possible,when there is typically less overland flow anticipated. If overland flow enters the trench, impacts ongroundwater quality would be limited. This is due to the predominantly clay dominant soils in thePipeline Works area, and therefore limited ability for runoff via the trench to move laterally into thesurrounding groundwater prior to the trench being dewatered following such an event.
The potential to impact groundwater quality from this already low risk event can be further reduced byminimising the duration for which excavations remain open. Overall, the risk is considered to be verylow.
Interconnection of aquifers during piling (Risk ID HG8)During augering of the piling hole, and prior to the placement of concrete slurry for piling as part of theGas Import Jetty Works, there is the potential to interconnect aquifers with different water qualityleading to the loss of beneficial uses or effecting groundwater users in one or more aquifers.
Regional geology indicates that the Crib Point Receiving Facility is underlain by Baxter Sandstone ofthe upper tertiary aquifer, which is typically greater than 20 metres thick (see Table 5-1). Overlyingalluvial sediments (if present) would be thin and of limited saturated thickness. The potential formultiple aquifers being intersected across the 20-metre depth of piling is considered unlikely, and thevariability of groundwater quality is not anticipated to be material in terms of beneficial uses. Further,the interconnection of aquifers (if any) would be of short duration - being limited to the time taken todrill up to 20-metres deep and pump in concrete slurry.
Overall, the risk of interconnecting aquifers and impacting groundwater quality such that beneficialuses and/or groundwater users are affected in one or more aquifers is considered to be low.
7.1.4 Water supply (Risk ID HG6)Water would likely be required during the pipeline construction phase, including for dust suppressionand hydrostatic (pressure) testing of the pipeline. If this water is sourced from groundwater within theKWR WSPA, then a temporary entitlement may need to be purchased from an existing licence holderas the WSPA is fully allocated.
All relevant legislation and policy requirements regarding sourcing of water for construction supplywould be adhered to. The risk of a groundwater supply for the Project adversely impactinggroundwater users is considered very low.
7.1.5 Loss of registered bores (Risk ID HG7)Registered bores within, or near, the construction footprints of the alignment or alignment options havethe potential to be damaged, lost (i.e. destroyed), or to become inaccessible during construction. Asummary of registered bores within thirty metres of the alignment or alignment options is provided inTable 7-4. Access to other registered bores outside the ROW may also be temporarily affected duringconstruction if access is prevented or made more difficult.
Table 7-4 Registered bores within ROW (based on mapped locations)
Bore ID Use Easting NorthingDistance from
pipeline(m)
Distancefrom
options (m)Closest KP
WRK070589 Stock anddomestic 362119 5775733 33 20 KP 38.8
91465 Stock 355463.2 5772286 145 23 KP 30.5
43Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
Bore ID Use Easting NorthingDistance from
pipeline(m)
Distancefrom
options (m)Closest KP
109673 Groundwaterinvestigation 353883.2 5771474 2 297 KP28.7
112085 Groundwaterinvestigation 343493.2 5754464 22 NA KP 1.0
112086 Groundwaterinvestigation 343833.2 5754444 29 NA KP 0.6
121049 Irrigation 345413.2 5765624 0 NA KP 16.7
142356 Irrigation 345413.2 5765324 6 NA KP 16.4
Following detailed design, the location of registered bores relative to the ROW could be visuallyconfirmed on site. Prior to construction, the potential for impacts to existing bores (for exampledamage or loss of access) could then be confirmed in consultation with the landowner.
In instances where a landholder bore is deemed to be impacted by the Project, consultation canfacilitate agreement between AGL and APA and landholder.
7.2 OperationThe risk assessment presented in Section 6.0 identified one potential operational risk pathway fromthe Project, being a change in groundwater flow from intersection of backfill material. This potentialimpact is discussed in the following section.
7.2.1 Preferential flow paths (Risk ID HG9)If the hydraulic conductivity (a property of soils and rocks that describes the ease with which a fluidcan move through pore spaces or fractures) of backfill material surrounding the pipe is higher than thesurrounding undisturbed soils, this could create a preferential flow path (where groundwater flowsfaster through the backfill material than in surrounding material). There is a risk that this could create adrainage-like feature that may result in a permanent reduction in groundwater level along the pipelinealignment, most significantly where the trench intersects alluvial sediments at water crossings therebyallowing preferential flow along the trench to discharge into the potentially higher conductivity alluvialchannel sediments.
The consequence of this occurring is that there may be a permanent reduction in groundwater levelsthat could impact groundwater dependent ecosystems close to the pipeline alignment and/or reducegroundwater discharge to gaining streams crossing the pipeline. It could also provide a pathway forcontaminant migration, which is discussed in EES Technical Report E: Contamination and acid sulfatesoils impact assessment. A preferential pathway becomes more significant where the trench backfill iscoarse grained as water is more readily able to move through this medium, or where the fall of thetrench is steep and there is a point of discharge out of the trench - for example where the trenchintersects alluvial sediments beneath a watercourse.
The preferred construction methodology for the pipeline trench is to backfill with the excavated nativematerial after being screened to keep rocks and other deleterious material away from the pipe coatingto avoid defects which would lead to corrosion. The fines are used for bedding and padding and theremainder is backfilled on top of the fines and compacted in layers. This could result in a change inhydraulic conductivity immediately surrounding the pipe. Packing sands, which would have a higherhydraulic conductivity, would only be used to backfill short sections of the trench, for example beneathroads. Backfill, whether excavated or imported, should be placed and compacted such that thepermeability is similar to the unexcavated material (as per AS/NZS 2885.19).
To manage the potential impact of a preferential flow path being established along the pipeline trench,trench breakers (that is, lower permeability material backfilled around the pipeline) should be installed
9 Australian Standards/New Zealand Standards 2885.1:2018. Pipelines – Gas and Liquid Petroleum. Ddesign and Construction.
44Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
in sections of trench where the pipe has a steeper fall and at overbends – which includes at trenchedwatercourse crossings.
The use of native material to backfill the trench in most locations and the shallow fall of the trenchalong much of the alignment would reduce the likelihood of a significantly higher hydraulic conductivitysurrounding the pipeline. The use of trench breakers at trenched waterway crossings would alsoreduce preferential flow by impeding preferential flow out of the trench at these locations and reducethe likelihood of impact to gaining streams that cross the pipeline alignment.
7.2.2 Impeded groundwater flow paths due to piles (Risk ID HG10)Groundwater flow could be impeded by the presence of piles at the Crib Point Receiving Facilityleading to changes in groundwater levels and groundwater flow direction. This could potentially resultin impacts such as the reduction of groundwater flow to GDEs, exposure of acid sulfate soils downhydraulic gradient of piles (due to groundwater level decreases) and raising saline/brackishgroundwater into the soil zone.
The magnitude of changes to the groundwater regime depends on several factors, including the extentto which the aquifer perpendicular to groundwater flow has been impeded by the piles. If it isconservatively assumed that 100 piles are required beneath the nitrogen tank, the centre-to-centrespacing of the 600 mm diameter piles would be 2.4 metres. This would equate to approximately 40 percent (or 10 metres) of the 25-metre wide section of aquifer beneath the nitrogen tank being impededby piles. If the width of aquifer perpendicular to groundwater flow is considered for the Crib PointReceiving Facility (i.e. approximately 120 metres) the piles would block the equivalent of nine per centof the aquifer through which groundwater flow is occurring (from west to east). It is thereforeanticipated that groundwater would flow around the piled section and/or through the spacing betweenthe piles with negligible effect on groundwater levels and flow.
Overall, the risk of piling beneath the nitrogen tank adversely impacting groundwater levels, flow orquality is considered to be very low.
45Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
8.0 Recommended mitigation measuresThis section outlines the recommended mitigation measures for groundwater identified as a result ofthe risk and impact assessment.
The recommended mitigation measures listed in Table 8-1 combine the initial and additional mitigationmeasures applied during the risk assessment to arrive at recommended mitigation measures for thedesign, construction and operation of the Gas Import Jetty Works and the Pipeline Works.
In the course of finalising this technical report, consultation was undertaken with AGL and APA andother members of the team (designers, contractors and other specialists) so that the recommendedmitigation measures would be achievable and compatible with those proposed by other specialists.
The recommended mitigation measures have been refined as a result of these discussions and shouldbe incorporated into the EMF, which would be implemented as described in Chapter 25 EnvironmentalManagement Framework through the Project approvals to effectively manage the environmentalperformance of the Project.
In addition to the groundwater mitigation measures recommended in Table 8-1, mitigation measures toavoid, minimise and mitigate impacts to groundwater are also recommended as per:
· EES Technical Report C: Surface water impact assessment (MM-SW03).Table 8-1 Recommended mitigation measures
Mitigationmeasure ID Recommended mitigation measures Works area Stage
MM-HG01 Dewatering activities should be limited to two daysor less in trenched sections and HDD tie-in bellholes, and 10 days or less at thrust bore sectionsand thrust bore bell holes, wherever practicable.
Pipeline Works Construction
MM-HG02 Drilling muds used in horizontal directional drillingshould be biodegradable and non-toxic, wheregeotechnical conditions allow.
Pipeline Works Construction
MM-HG03 Contractor(s) suitably qualified and experienced intrenchless installation techniques and pilinginstallation should be used.
Pipeline Worksand Gas ImportJetty Works
Construction
MM-HG04 The duration that trench sections and bell holesare open should be minimised to reduce thepotential for poor quality runoff impactinggroundwater.
Pipeline Works Construction
MM-HG05 Sourcing of groundwater for construction supply (ifrequired) should be in accordance with Section 50Licence to take and use water of the Water Act1989.
Pipeline Works Construction
MM-HG06 Through liaison with landholders, the location,condition and functionality of potentially affectedbores (due to damage, destruction or loss ofaccess) should be visually confirmed prior toconstruction commencing and make-goodarrangements should be agreed if required.
Pipeline Works Construction
MM-HG07 Compaction of backfill using excavated material,where practicable, should be carried out to reducethe potential for preferential lateral flow along thetrench.
Pipeline Works Operation
MM-HG08 Trench blocks (such as trench/sack breakers)should be installed adjacent to watercourses,wetlands and steep slopes as shown in thestandard drawing (CPT.2373-DWG-L-0106).
Pipeline Works Operation
46Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
9.0 ConclusionThis groundwater impact assessment has been undertaken to determine the potential impacts of theProject on groundwater levels, flow and quality, and to identify recommended management andmitigation options where appropriate in order to reduce risks of the Project.
Potential impacts on groundwater quality from the Project are considered in EES Technical Report E:Contamination and acid sulfate soils impact assessment.
9.1 Impact assessment summaryPotential impacts on groundwater levels, flow and quality within the groundwater study area wereidentified for construction and operational phases. The potential for loss, damage or inaccessibility ofregistered bores during construction of the pipeline was also considered.
For the Pipeline Works several potential construction impacts were related to the reduction ingroundwater levels if dewatering activities are required with the subsequent potential to affectregistered bore users, GDEs and induce saline intrusion. The other potential groundwater impactswere related to potential groundwater quality impacts from HDD drilling muds, poor quality overlandflow entering open trenches. For the Gas Import Jetty Works the potential interconnection of aquifersduring auger drilling for piling was considered.
The groundwater impact assessment found limited potential for impacts on groundwater levels andflow during the operational phase of the Project. For the Pipeline Works the risk of permanentlyreduced groundwater levels due to the drainage effects of preferential flow paths within the trench wasconsidered. For the Gas Import Jetty Works the potential changes in groundwater levels and flow dueto the installation of piles at the Crib Point Receiving Facility were considered.
Overall, construction and operation of the Pipeline Works present limited risks to groundwater due tothe shallow depth of trenching and horizontal boring, the short duration of dewatering activities (wheregroundwater is intersected) and clay and silt dominated nature of the materials likely to beencountered. Where dewatering is required the reductions in groundwater levels are estimated to beof limited magnitude, lateral extent and duration.
Risks to groundwater from piling as part of the Gas Import Jetty Works (at the Crib Point ReceivingFacility) were also considered to be low to very low due to the relatively small piling footprint, spacingof pilings and short duration auger drilling.
9.2 Residual riskThe risk of potential impacts on groundwater were identified as being low or very low, and it wasconcluded that the Project is consistent with the scoping requirements and the draft evaluationobjective with respect to potential impacts on groundwater levels, quality and flow from constructionand operational activities with mitigation measures that are commonly applied and have proveneffective in major construction projects in place. Additional mitigation measures were applied to anumber of risks to further reduce the already moderate to low initial risk ratings.
47Gas Import Jetty and Pipeline Project Environment Effects StatementTechnical Report D: Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
10.0 ReferencesAEMO (2019). Gas Statement of Opportunities: For eastern and south-eastern Australia, March 2019.
Alluvium Consulting Australia (2018). Hydrology and Scour Study Report. Appendix B of: CoffeyServices Australia Pty Ltd (2018) Crib Point to Pakenham Pipeline Project Desktop Geotechnical andHydrology Study. Report for APA Group. 6 April 2018.
CMPS&F (1997). Environmental Site Assessment Works Port of Hastings. CMPS&F Pty Ltd,Melbourne.
Coffey Services Australia Pty Ltd (2018). Crib Point to Pakenham Pipeline Project DesktopGeotechnical and Hydrology Study. Report for APA Group. 6 April 2018.
Jacobs (2017). Factual Report: Baseline Environmental Contamination Investigation. Prepared for Portof Hastings Authority. 1 June 2017.
Fetter, C.W. (2000). Applied Hydrogeology. 4th Ed. Pearson, November 26, 2000.
Southern Rural Water (SRW) (2010). Groundwater Management Plan Koo Wee Rup Water SupplyProtection Area. 4 August 2010.
Southern Rural Water (SRW) (2014). Port Phillip and Western Port Groundwater Atlas. July 2014.
State Environment Protection Policy (SEPP) (Waters) (2018) October 2018.
Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
AECOM
AAppendix AFigures
! <! <
! <
! <
! <
! <! <! <
! <
! <
! <
! <
! <
! <
! <
! <
! <
! <
! <
! <
! <
! <
! <
! <
! <
! <
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!( !( !( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
Qm1
Qd1
Qd1Qd
1Qd
1
Qd1
Ox
Qd1
Qd1
Nbr
SmSm
Sm
Nb
Qy
Nbr
Nbr
Qdl1
Nb
Qb
Qdl1
Qd1
Nbr
Sm
Qd1
Qd1
SmOc
Nuo
Nbr
Qc1
Qdl1
G264
Qc1
-Put
Qm1
Qm1
Qg
Ksw
Qm1
Qm1
Qa1
Sm
Sm
-Put
Qc1
Qd1
Qb
Qg
Qb
-PumQdl1
Qdl1
Qdl1
Nbr
Qb
Sm
Qb
Sm
Qd1
Qd1
Nbr
Sm
Nbr
Qdl1
Nb
SmSm
Nuo
Qm1
Qd1
Qg
Nbr
Qd1
Qg
Qa1
Qa1
Qd1
Qg
-Put
Qa1
Qm1
Qm1
Sm
Nbr
G239
G239
Qd1
Sm
Nb
Nb
Nb
G239
G239
Qg
Ox
Qd1
Qd1
Qb
Qg
Qb
Qd1
Qg
Nbr
Nuo
Nuo
Qm1
Qm1
Qdl1Qm
1
G239
Qc1
Qb
-Put
Nb
Qd1
Qdl1
Nbr
Nbr
Nbr
Qd1
QbQd
l1
Ox Ox
Qd1
Qd1
Qd1
Qd1
Qa1
Nbr
Nbr
Nb
Sm Qg
G239
Qd1
Qd1
Sm
Qa1
Qd1
Sm
Qd1
Qd1
Qdl1
Qd1
Qd1
Sxa
Qd1
Qg
Qd1
Qd1
Qa2
Nuo
Nb
Sm
Qa2
Sm
Sm
Qa1
Qdl1
Nbr
Qd1
Qg
Qb
Qd1
Sm
Qa1
Qa1
Qdl1
Nbr
Nbr
Nbr
Nuo
Qdl1
Oc
Qm1
G239
Qm1
Qm1
Qd1
Sm
Qc1
Sm
Nbr
-Put
Sm Sm
Nb
Qa1
Qd1
Qm1
Oc Ox
Qd1
Qd1
Qd1
Qb
Sm
Qd1
Qd1
Sm
Nuo
Qd1
-Put
Nbr
Qa2
QbSm
Nbr
Nbr
Nbr
Sm
Qb
Qb
GW02
(3.78
)GW
03(3
.29)
GW04
(2.45
)
GW05
(1.74
)
MW01
(3.80
)MW
02(1
.52)
MW03
(3.54
)
MW04
(DRY
)
MW05
(1.41
)
MW06
(3.31
)
MW07
(2.60
)MW08
(3.53
)MW
09(1
.62)
MW10
(1.99
)
MW11
(3.05
)
MW12
(3.23
)MW
13(2
.22)
MW14
(2.23
)MW15
(2.24
)
MW16
(4.00
)
MW17
(DRY
)
MW18
(3.92
)
MW19
(DRY
)
MW21
(1.15
)
MW22
(1.09
)
MW23
(DRY
)
KP56
KP54
KP50
KP46
KP45
KP41
KP49
KP38KP
40KP
37
KP52
KP44
KP42
KP36KP
39
KP34
KP33
KP29
KP53
KP24
KP23
KP21
KP17
KP27
KP51
KP16
KP30
KP14
KP55
KP13
KP12
KP19
KP11
KP9
KP8
KP7KP
6
KP25
KP10
KP5
KP31
KP43
KP15
KP18
KP4
KP22
KP26
KP47
KP3
KP28
KP32
KP1
KP2
KP20
KP48
KP35
MLV 2
-La
nd ar
ea
Crib
Point
Rece
iving F
acilit
y
MLV 1
Pake
nham
Eas
tDe
livery
Facil
ity
MLV 2
EOLS
S
02,0
004,0
006,0
00me
tres´
1:125
,000
(whe
n prin
ted at
A3)
A3 si
ze
AECOM does not warrant the accuracy or completeness of information displayed in this map and any person using it does so at their own risk. AECOM shall bear no responsibility or liability for any errors, faults, defects, or omissions in the information.
www.
aeco
m.co
m
PROJ
ECT I
D
LAST
MODIF
IEDCR
EATE
D BY
605828
11 sa
m.schr
oder
sam.s
chrode
r 22 M
AY 20
20
LEGE
ND!(
Kilom
etre P
oint (K
P)Pip
eline
Align
ment
Optio
ns! <
Grou
ndwa
ter w
ells (
water
leve
l in m
bgs,
30Ja
nuary
2019
)Ko
oWee
Rup W
ater S
upply
Prote
ction
Area
Brigh
ton G
roup(
Nb): g
eneri
cMu
rrindin
di Su
pergr
oup(
Sm): g
eneri
cMu
rrindin
di Su
pergr
oup(
Sm): h
ornfel
sRe
d Bluf
f San
dston
e (Nb
r): ge
neric
Thorp
dale
Volca
nic G
roup (
-Put)
: Gen
eric
alluv
ium an
d coll
uvium
( Qb):
gene
ricall
uvium
( Qa1
): gen
eric
coas
tal du
ne de
posit
s (Qd
l1): g
eneri
cco
astal
lago
on de
posit
s (Qg
): gen
eric
collu
vium(
Qc1
): gen
eric
inlan
d dun
e dep
osits
(Qd1
): gen
eric
swam
p and
lake
depo
sits (
Qm1):
gene
ric
Coord
inate S
ystem
: GDA
1994
MGA Z
one 55
Grou
ndwa
ter Im
pact
Asse
ssme
ntGa
s Imp
ort Je
tty an
d Pipe
line P
rojec
tEn
viron
ment
Effec
ts St
ateme
nt
Map D
ocume
nt: (\\a
umel1
fp001\
Projec
ts\605X
\60592
634\90
0_CAD
_GIS\
920_G
IS\02_
Maps\
GIS_M
XDs\M
XD_T
ECH_
SINGL
E\Grou
ndwate
r\FA1
_Geol
ogy_t.m
xd)
A1Figur
eAG
L/APL
Geolo
gy, g
roun
dwate
r well
s, an
dwa
ter le
vels
Wes
tern
Por
t
! <
! <
! <
! <! <
! <
! <
! <
! <
! <
! <
! <
! <
! <
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!( !( !( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
DEVO
NME
ADOW
SFIVEW
AYS
CLYD
E NOR
THCR
ANBO
URNE
CRIB
POIN
T
DALM
ORE E
AST
CALD
ERME
ADE
CANN
ONS C
REEK
CHEL
SEA
HEIG
HTS
BITTE
RN
BEAC
ONSF
IELD
BANG
HOLM
E
BAXT
ER
FREN
CH IS
LAND
CRAN
BOUR
NENO
RTH
SOME
RVILL
E
TOOR
ADIN
TYAB
B
PATT
ERSO
NLA
KES
HAST
INGS
JAM
JERR
UP
LANG
WARR
IN
CARD
INIA
DALM
ORE
OFFIC
ER SO
UTH
BOTA
NIC
RIDG
E
LANG
WARR
INSO
UTH
SAND
HURS
T
CRAN
BOUR
NEEA
ST
CRAN
BOUR
NESO
UTH
CRAN
BOUR
NE W
EST
CARR
UM D
OWNS
NAR
NAR
GOON
PEAR
CEDA
LE
YALL
OCK
BLIN
DBIG
HT
WARN
EET
SKYE
RYTH
DALE
NARR
EWA
RREN
SOUT
H
PAKE
NHAM
PAKE
NHAM
SOUT
H
MONO
MEITH
LYND
HURS
T
KOO
WEE R
UP
KOO
WEE
RUP N
ORTH
LANG
LANG
KARI
NGAL
BAYL
ES
FRAN
KSTO
NNO
RTH
SOUTH
GIPPS
LAND
HIGHWAY
PRINC
ESHI
GHWA
Y
SOUT
HGIPP
SLAN
DHI
GHWA
Y
MOOROODUC HIGHWAY
SOUTH GIPP
SLAND HIGH
WAY
PRIN
CES H
IGHW
AY
SOUTH GIPPSLAND HIGHWAY
DANDENONG-HASTINGSROAD
BASS HIGHWAY
DANDENONG-HASTINGS ROAD
BASSHIGHWAYSOUTH GIPPSLAND HIGHWAY
DANDENONG-HASTINGS ROAD
CLYDE-FIVEWAYSROAD
SEAFO
R DRO
AD
CLYDE ROAD
THOM
PSON
S ROA
D
CRAN
BOUR
NE-FR
ANKS
TONRO
AD
BAXT
ER-TO
ORAD
INR O
A D
KOO WEE RUP ROAD
STONY POINT ROAD
COOLART ROAD
BALL
ARTO
ROA
DCR
ANBO
URNE
ROAD
THOM
PSON
ROA
D Stony Point Line
Morin
gton
Tourist
Railw
ay
Bairn
sdale
Line
Leongatha Line
Franks
ton Lin
e
Dand
enon
g-Leo
ngath
a
GW04
5591GW
0554
99
MW01
5922
MW02
2613
MW03
2864
MW05
5577
MW07
1253
MW09
1273
6MW
1036
90
MW11
1641
4
MW14
5207
MW15
4885
MW21
5473
MW22
1095
3
KP56
KP54
KP50
KP46
KP45
KP41
KP49
KP38
KP40
KP37
KP52
KP44
KP42
KP36KP
39KP
34KP
33
KP29
KP53
KP24 KP
23KP
21
KP17
KP27
KP51
KP16
KP30
KP14
KP55
KP13
KP12
KP19
KP11
KP9
KP8
KP7
KP6
KP25
KP10
KP5
KP31
KP43
KP15
KP18
KP4
KP22
KP26
KP47
KP3
KP28
KP32
KP1KP
2
KP20
KP48
KP35
MLV 2
-La
nd ar
ea
Crib
Point
Rece
iving F
acilit
y
MLV 1
Pake
nham
Eas
tDe
livery
Facil
ity
MLV 2
EOLS
S
02,0
004,0
006,0
00me
tres´
1:125
,000
(whe
n prin
ted at
A3)
A3 si
ze
AECOM does not warrant the accuracy or completeness of information displayed in this map and any person using it does so at their own risk. AECOM shall bear no responsibility or liability for any errors, faults, defects, or omissions in the information.
www.
aeco
m.co
m
PROJ
ECT I
D
LAST
MODIF
IEDCR
EATE
D BY
605828
11 sa
m.schr
oder
sam.s
chrode
r 22 M
AY 20
20
LEGE
ND!(
Kilom
etre P
oint (K
P)Pip
eline
Align
ment
Optio
ns! <
Samp
led gr
ound
water
well
sGr
ound
water
Salin
ity< 1
000 m
g/L TD
S10
00-30
00 m
g/L TD
S30
00-70
00 m
g/L TD
S
Coord
inate S
ystem
: GDA
1994
MGA Z
one 55
Map D
ocume
nt: (\\a
umel1
fp001\
Projec
ts\605X
\60592
634\90
0_CAD
_GIS\
920_G
IS\02_
Maps\
GIS_M
XDs\M
XD_T
ECH_
SINGL
E\Grou
ndwate
r\FA2
_Salin
ity_t.m
xd)
A2Figur
e
Grou
ndwa
ter Sa
linity
Wes
tern
Por
t
Grou
ndwa
ter Im
pact
Asse
ssme
ntGa
s Imp
ort Je
tty an
d Pipe
line P
rojec
tEn
viron
ment
Effec
ts St
ateme
nt
AGL/A
PL
1420
Total
Diss
olved
Solid
s (mg
/L)
! >
! >! >
! >
!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!( !(
!(
!(
!( !( !( !(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
!(
WRK0
7058
9
1423
5612
1049
9146
5
KP56
KP54 KP
50
KP46
KP45
KP41
KP49
KP38
KP40
KP37
KP52
KP44
KP42
KP36KP
39KP
34KP
33
KP29
KP53
KP24
KP23
KP21
KP17
KP27
KP51
KP16
KP30
KP14
KP55
KP13
KP12
KP19
KP11
KP9
KP8
KP7
KP6
KP25
KP10
KP5
KP31
KP43
KP15
KP18
KP4
KP22
KP26
KP47
KP3
KP28KP
32
KP1
KP2
KP20
KP48
KP35
01,0
002,0
003,0
004,0
005,0
00me
tres´
1:125
,000
(whe
n prin
ted at
A3)
A3 si
ze
AECOM does not warrant the accuracy or completeness of information displayed in this map and any person using it does so at their own risk. AECOM shall bear no responsibility or liability for any errors, faults, defects, or omissions in the information.
www.
aeco
m.co
m
PROJ
ECT I
D
LAST
MODIF
IEDCR
EATE
D BY
605828
11 sa
m.schr
oder
sam.s
chrode
r 22 M
AY 20
20
LEGE
ND!(
Kilom
etre P
oint (K
P)! >
Cons
umpti
ve us
e bore
s with
in 30
m of
pipe
line
Grou
ndwa
ter - s
urfac
e wate
rint
eracti
ons
Gaini
ngNe
utral/
Losin
gUn
class
ified
Aqua
tic G
DEs
Know
n GDE
(regio
nal s
tudies
)Hig
h pote
ntial
GDE (
region
al stu
dies)
Mode
rate p
otenti
al GD
E (reg
ional
studie
s)Un
class
ified p
otenti
al GD
E (reg
ional
studie
s)Hig
h pote
ntial
GDE (
natio
nal a
sses
smen
t)Mo
derat
e pote
ntial
GDE (
natio
nal
asse
ssme
nt)Te
rrestr
ial G
DEs
High p
otenti
al GD
E (na
tiona
l ass
essm
ent)
Mode
rate p
otenti
al GD
E (na
tiona
las
sess
ment)
Low
poten
tial G
DE (n
ation
al as
sess
ment)
Pipeli
neAli
gnme
nt Op
tions
Align
ment
and o
ption
s 200
m bu
ffer
Coord
inate S
ystem
: GDA
1994
MGA Z
one 55
Grou
ndwa
ter Im
pact
Asse
ssme
ntGa
s Imp
ort Je
tty an
d Pipe
line P
rojec
tEn
viron
ment
Effec
ts St
ateme
ntMa
p Docu
ment:
(\\aum
el1fp0
01\Pro
jects\6
05X\60
592634
\900_C
AD_G
IS\920
_GIS\
02_Ma
ps\GIS
_MXD
s\MXD
_TEC
H_SIN
GLE\G
roundw
ater\F
A3_U
sers_v
10_001
.mxd)
A3Figur
eAG
L/APL
Grou
ndwa
ter us
ers
Wes
tern
Por
t
Data
sourc
e: Gr
ound
water
Dep
ende
nt Ec
osys
tems A
tlas
http:/
/www
.bom.
gov.a
u/wate
r/grou
ndwa
ter/gd
e/map
.shtm
l
Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
AECOM
BAppendix BTables
Clie
nt N
ame:
AG
L W
hole
sale
Gas
Ltd
and
APA
Tra
nsm
issi
on P
ty L
tdPr
ojec
t Nam
e: G
IJPP
EES
Gro
undw
ater
Tec
hnic
al R
epor
t
Tabl
e B
1. W
ell C
onst
ruct
ion
and
Dev
elop
men
t Rec
ord
CPT
IDBo
re ID
Dat
e D
rille
dEa
stin
gN
orth
ing
TOC
(mAH
D)
Gro
und
Surfa
ceEl
evat
ion
(mAH
D)
Hol
eD
iam
eter
(mm
)
Dril
led
Dep
th(m
bgs)
Scre
enIn
terv
al(m
bgs)
Scre
ened
Inte
rval
Form
atio
n
Dat
eD
evel
oped
SWL
(mbt
oc)
Volu
me
Rem
ove
d (L
)
Tem
pera
ture
(ºC
)
Dis
solv
edO
xyge
n(m
g/L)
Elec
trica
lC
ondu
ctiv
ity(µ
S/cm
)pH
Red
oxFi
eld
(mV)
Tota
lD
isso
lved
Solid
s(T
DS)
¹ ²
Red
oxPo
tent
ial
(Eh)
³C
omm
ent
CPT
006_
MW
01M
W01
6/12
/18
3433
40.8
5257
5452
6.40
97.
375
6.59
413
04.
11
- 4SI
LT12
/12/
184.
113
418
.06.
263
576.
296.
941
3221
8.5
Hig
h Tu
rbid
ity, B
row
n, N
ood
our
CPT
012_
MW
02M
W02
5/12
/18
3414
35.8
4357
5641
2.40
35.
231
5.34
813
04.
11
- 4C
LAY
8/12
/18
1.25
518
16.6
5.7
3830
6.62
28.7
2490
241.
3H
igh
Turb
idity
, Bro
wn,
No
odou
r
CPT
012_
MW
03M
W03
5/12
/18
3414
13.1
5057
5702
1.94
73.
408
3.52
213
04.
11
- 4SI
LT8/
12/1
83.
655
1.3
16.7
7.1
3214
7.26
16.0
2089
228.
6H
igh
Turb
idity
, Bro
wn,
No
odou
rC
PT01
5_M
W04
MW
045/
12/1
834
1436
.683
5757
533.
111
7.99
28.
135
130
4.2
1 - 4
CLA
Y8/
12/1
8D
ry-
--
--
--
-D
ry, N
o od
our
CPT
000_
GW
02G
W02
10/0
1/19
3413
06.1
4757
5902
6.38
513
.574
13.6
7413
04.
01
- 4C
LAY
16/0
1/19
3.85
0-
--
--
--
-N
ot e
noug
h w
ater
to d
evel
op,
No
odou
r
CPT
000_
GW
03G
W03
10/0
1/19
3411
96.4
7057
5936
1.41
07.
636
7.75
313
04.
11
- 4C
LAY
16/0
1/19
3.65
01
18.7
3.2
5920
6.88
67.6
3848
278.
7M
oder
ate
Turb
idity
, Bro
wn,
No
odou
r
CPT
022_
MW
05M
W05
4/12
/18
3411
86.2
2057
5981
5.64
26.
791
6.89
913
04.
41
- 4C
LAY
12/1
2/18
0.82
924
16.2
5.5
7500
6.64
-15.
248
7519
7.7
Hig
h Tu
rbid
ity, L
ight
bro
wn-
Gre
y, N
o od
our
CPT
027_
MW
06M
W06
8/01
/19
3415
90.5
8157
6114
4.67
16.
772
6.01
613
04.
71
- 4C
LAY
15/0
1/19
4.60
50.
319
.16.
446
466.
9295
.030
2030
5.8
Low
Tur
bidi
ty, B
row
n, N
ood
our
CPT
036_
C_M
W23
MW
2318
/12/
1837
2239
.934
5784
161.
856
Tabl
e14
.860
130
4.0
1 - 4
Silty
SAN
D19
/12/
18D
ry-
--
--
--
-D
ry, N
o od
our
CPT
040_
B_M
W07
MW
0718
/12/
1834
3971
.134
5763
584.
910
11.5
7510
.974
130
4.1
1 - 4
CLA
Y19
/12/
184.
012
316
.57.
519
367.
6132
.612
5824
5.3
Hig
h tu
rbid
ity, b
row
n, n
ood
our
CPT
040_
B_G
W04
GW
048/
01/1
934
4249
.838
5763
633.
725
10.8
1210
.122
130
4.1
1 - 4
SAN
D15
/01/
193.
052
1218
.42.
884
036.
4470
.454
6228
1.7
Low
Tur
bidi
ty, B
row
n, N
ood
our
CPT
045_
GW
05G
W05
8/01
/19
3446
42.4
7957
6391
7.06
28.
601
7.86
713
04.
11
- 4C
laye
y SA
ND
15/0
1/19
2.29
515
17.4
3.1
8290
6.49
43.2
5389
255.
2Lo
w T
urbi
dity
, Lig
ht G
rey,
No
odou
r
CPT
000_
MW
08M
W08
10/0
1/19
3454
37.2
0657
6575
6.09
18.
382
8.50
913
04.
11
- 4C
LAY
16/0
1/19
3.21
24
17.8
4.2
2184
6.74
43.3
1420
255.
0M
oder
ate
Turb
idity
, Bro
wn,
No
odou
r
CPT
051_
MW
09M
W09
17/1
2/18
3461
59.7
5357
6625
2.23
93.
203
3.34
113
04.
11
- 4Sa
ndy
CLA
Y19
/12/
181.
458
1916
.65.
319
333
6.54
-4.6
1256
620
8.0
Hig
h Tu
rbid
ity, B
row
n/gr
ey,
No
odou
r
CPT
055_
MW
10M
W10
3/12
/18
3465
55.6
0557
6738
7.90
52.
708
2.80
913
04.
11
- 4Sa
ndy
CLA
Y8/
12/1
81.
529
2516
.02.
658
377.
00-5
3.0
3794
160.
1H
igh
Turb
idity
, Bro
wn,
No
odou
r
CPT
000_
MW
11M
W11
9/01
/19
3469
24.7
1857
6888
7.44
63.
530
3.64
513
04.
11
- 4C
LAY
15/0
1/19
2.89
74.
517
.44.
721
438
6.71
91.3
1393
530
3.3
Low
Tur
bidi
ty, B
row
n, N
ood
our
CPT
064_
MW
12M
W12
7/12
/18
3499
88.2
8957
7018
7.54
44.
367
3.60
713
04.
11
- 4C
LAY
12/1
2/18
4.38
51.
515
.36.
158
066.
8144
.837
7425
8.4
Hig
h Tu
rbid
ity, B
row
n, N
ood
our
CPT
068_
MW
13M
W13
7/12
/18
3520
28.0
1757
7084
6.48
85.
323
4.62
213
04.
11
- 4SI
LT12
/12/
182.
978
916
.17.
713
598
6.73
42.6
8839
255.
6H
igh
Turb
idity
, Bro
wn
- gre
y,N
o od
our
CPT
037_
B_M
W14
MW
143/
12/1
834
3397
.460
5762
421.
683
4.87
64.
116
130
4.2
1 - 4
CLA
Y8/
12/1
82.
616
1116
.56.
574
286.
8461
.548
2827
4.2
Hig
h Tu
rbid
ity, B
row
n, N
ood
our
CPT
000_
MW
15M
W15
9/01
/19
3541
66.7
5757
7153
3.62
13.
578
3.67
513
04.
11
- 4C
LAY
16/0
1/19
1.97
512
16.8
2.0
6698
6.63
36.1
4354
248.
6H
igh
Turb
idity
, Lig
ht B
row
n,N
o od
our
CPT
000_
MW
16M
W16
9/01
/19
3552
09.9
9157
7212
7.11
23.
805
3.94
813
04.
11
- 4C
LAY
15/0
1/19
Dry
--
--
--
--
Dry
, No
odou
rC
PT09
9_M
W17
MW
1711
/01/
1935
7520
.644
5774
095.
463
2.89
52.
941
130
4.1
1 - 4
CLA
Y15
/01/
19D
ry-
--
--
--
-D
ry, N
o od
our
CPT
107_
MW
18M
W18
4/12
/18
3611
97.4
4657
7544
8.92
63.
925
3.00
913
04.
11
- 4C
LAY
8/12
/18
4.62
80.
517
.06.
112
747.
6028
.782
824
1.0
Hig
h Tu
rbid
ity, B
row
n, N
ood
our
CPT
114_
MW
19M
W19
4/12
/18
3638
62.3
2857
7600
3.26
54.
911
4.16
213
06.
01
- 4C
LAY
8/12
/18
4.47
01
17.8
6.5
1337
7.74
13.7
869
225.
4H
igh
Turb
idity
, Bro
wn,
No
odou
r
CPT
129_
MW
21M
W21
17/1
2/18
3661
61.1
4357
7784
3.27
617
.626
17.7
1613
04.
11
- 4C
LAY
19/1
2/18
0.50
119
16.2
7.6
8179
7.14
42.2
5316
255.
1H
igh
Turb
idity
, Bro
wn/
grey
,N
o od
our
CPT
134_
MW
22M
W22
6/12
/18
3707
81.2
3657
8268
3.12
123
.902
24.0
0113
04.
11
- 4C
LAY
8/12
/18
0.41
321
16.5
6.4
1565
66.
5252
.310
176
265.
0Lo
w T
urbi
dity
, Bro
wn
incr
easi
ng to
hig
h tu
rbid
ity,
brow
n, n
o od
our.
Not
esm
AHD
= m
etre
s ab
ove
Aust
ralia
n H
eigh
t Dat
umm
bgs
= m
etre
s be
low
gro
und
surfa
ceTO
C =
Top
of C
asin
gm
m =
milli
met
res
* All w
ells
cons
truct
ed w
ith 5
0 m
m N
D u
PVC
cas
ing
and
scre
enL
= Li
tres
ppm
= p
arts
per
milli
onuS
/cm
= m
icro
siem
ens
per c
entim
etre
mg/
L =
milli
gram
s pe
r litr
em
V =
milli
volts
oC =
deg
rees
Cel
sius
(1) T
DS
= To
tal D
issol
ved
Solid
s(2
) TD
S ap
prox
imat
ed a
s El
ectri
cal C
ondu
ctivi
ty x
0.6
5(3
) Cor
rect
ed R
edox
Pot
entia
l = F
ield
Red
ox P
oten
tial +
(224
.98
- 0.7
443*
Tem
pera
ture
) (R
edox
pot
entia
l con
verte
d fro
m A
g/Ag
Cl e
lect
rode
to H
2 el
ectro
de)
Bor
e D
evel
opm
ent
Bor
e C
onst
ruct
ion
Rev
isio
n 01
10
Jan
uary
201
9P:
\605
X\60
5926
34\4
00_T
ECH
\435
_Gro
undw
ater
\Tab
les\
Tabl
es 1
- 3
GIJ
PP G
roun
dwat
er_1
.xls
xPa
ge 1
of 1
Prin
t Dat
e: 1
1/06
/202
0
Cli
ent
Nam
e:
AG
L W
ho
lesa
le G
as L
td a
nd
AP
A T
ran
smis
sio
n P
ty L
tdP
roje
ct N
ame:
G
IJP
P E
ES
Gro
un
dw
ater
Tec
hn
ical
Rep
ort
Tab
le B
2. G
rou
nd
wat
er G
aug
ing
CP
T ID
Wel
l ID
Dat
eT
op o
f C
asin
g E
leva
tion
(mA
HD
)
Tot
al D
epth
(m
bTO
C)
Tot
al D
epth
(m
bgs)
Dep
th to
Wat
er
(mbT
OC
)D
epth
to W
ater
(m
bgs)
Gro
undw
ater
E
leva
tion
(mA
HD
)
PID
(ppm
)C
omm
ents
CP
T0
06_M
W01
MW
0130
/01/
197.
375
4.8
74.
14.
58
3.8
02.
800.
0G
ood
Con
ditio
n, n
o o
dour
, stic
k up
CP
T0
12_M
W02
MW
0230
/01/
195.
231
3.8
84.
01.
41
1.5
23.
830.
0G
ood
Con
ditio
n, n
o o
dour
, flu
sh g
atic
CP
T0
12_M
W03
MW
0330
/01/
193.
408
3.8
74.
03.
43
3.5
4-0
.02
0.0
Go
od C
ondi
tion
, no
odo
ur, f
lush
ga
ticC
PT
015
_MW
04M
W04
30/0
1/19
7.99
24
.02
4.2
DR
Y (
>4.
02)
--
0.0
Dry
, Go
od C
ondi
tion
, 1 m
etre
insi
de fe
nce
, stic
k up
CP
T0
00_G
W02
GW
0230
/01/
1913
.57
44.
04.
13.
68
3.7
89.
890.
0G
ood
Con
ditio
n, n
o o
dour
, flu
sh g
atic
CP
T0
00_G
W03
GW
0330
/01/
197.
636
3.9
4.1
3.1
73.
29
4.46
0.0
Go
od C
ondi
tion
, no
odo
ur, f
lush
ga
ticC
PT
022
_MW
05M
W05
30/0
1/19
6.79
14
.00
4.1
1.3
01.
41
5.49
0.0
Go
od C
ondi
tion
, no
odo
ur, f
lush
ga
ticC
PT
027
_MW
06M
W06
30/0
1/19
6.77
24
.82
4.1
4.0
63.
31
2.71
0.0
Go
od C
ondi
tion
, no
odo
ur, s
tick
upC
PT
036
_C_
MW
23M
W23
30/0
1/19
15.4
63
4.8
64.
3D
RY
(>
4.6
8)-
-0
.0D
ry, G
ood
Con
ditio
n, s
tick
up
CP
T0
40_B
_MW
07M
W07
30/0
1/19
11.5
75
4.7
04.
13.
20
2.6
08.
380.
0G
ood
Con
ditio
n, n
o o
dour
, stic
k up
CP
T0
40_B
_GW
04G
W04
30/0
1/19
10.8
12
4.8
74.
23.
14
2.4
57.
680.
0G
ood
Con
ditio
n, n
o o
dour
, stic
k up
CP
T0
45_G
W05
GW
0530
/01/
198.
601
4.8
14.
12.
48
1.7
46.
120.
0G
ood
Con
ditio
n, n
o o
dour
, stic
k up
CP
T0
00_M
W08
MW
0830
/01/
198.
382
3.9
04.
03.
40
3.5
34.
980.
0G
ood
Con
ditio
n, n
o o
dour
, flu
sh g
atic
CP
T0
51_M
W09
MW
0930
/01/
193.
203
3.9
64.
11.
48
1.6
21.
720.
0G
ood
Con
ditio
n, n
o o
dour
, flu
sh g
atic
CP
T0
55_M
W10
MW
1030
/01/
192.
708
3.9
84.
11.
89
1.9
90.
820.
0G
ood
Con
ditio
n, n
o o
dour
, flu
sh g
atic
CP
T0
00_M
W11
MW
1130
/01/
193.
530
4.0
04.
12.
94
3.0
50.
590.
0G
ood
Con
ditio
n, n
o o
dour
, flu
sh g
atic
CP
T0
64_M
W12
MW
1230
/01/
194.
367
4.8
54.
13.
99
3.2
30.
380.
0G
ood
Con
ditio
n, n
o o
dour
, stic
k up
CP
T0
68_M
W13
MW
1330
/01/
195.
323
4.7
44.
02.
92
2.2
22.
400.
0G
ood
Con
ditio
n, n
o o
dour
, stic
k up
CP
T0
37_B
_MW
14M
W14
30/0
1/19
4.87
64
.81
4.1
2.9
92.
23
1.89
0.0
Go
od C
ondi
tion
, no
odo
ur, s
tick
upC
PT
000
_MW
15M
W15
30/0
1/19
3.57
84
.00
4.1
2.1
42.
24
1.44
0.0
Go
od C
ondi
tion
, no
odo
ur, f
lush
ga
ticC
PT
000
_MW
16M
W16
30/0
1/19
3.80
54
.00
4.1
3.8
54.
00
-0.0
50
.0G
ood
Con
ditio
n, n
o o
dour
, flu
sh g
atic
CP
T0
99_M
W17
MW
1730
/01/
192.
895
3.9
64.
0D
RY
(>
3.9
6)-
-0
.0D
ry, G
ood
Con
ditio
n, f
lush
ga
ticC
PT
107
_MW
18M
W18
30/0
1/19
3.92
54
.88
4.0
4.8
33.
92
-0.9
10
.0N
o w
ell c
ap, s
tick
up w
obb
ly d
ue
to c
ows
rubb
ing
aga
inst
.C
PT
114
_MW
19M
W19
30/0
1/19
4.91
14
.78
4.0
DR
Y (
>4.
78)
--
0.0
Dry
, Go
od C
ondi
tion
, stic
k u
pC
PT
129
_MW
21M
W21
30/0
1/19
17.6
26
3.7
83.
91.
06
1.1
516
.57
0.0
Goo
d C
ondi
tion
, no
odo
ur, f
lush
ga
ticC
PT
134
_MW
22M
W22
30/0
1/19
23.9
02
3.9
74.
11.
00
1.0
922
.91
0.0
Goo
d C
ondi
tion
, no
odo
ur, f
lush
ga
tic
No
tes
mA
HD
= m
etre
s a
bove
Au
stra
lian
He
igh
t Dat
um
mb
gs =
me
tres
bel
ow g
rou
nd s
urf
ace
mb
TO
C =
met
res
bel
ow
Top
of C
asin
gT
OC
= T
op o
f Cas
ing
L =
Litr
espp
m =
pa
rts
per
mill
ion
uS/c
m =
mic
rosi
em
ens
pe
r ce
ntim
etr
em
g/L
= m
illig
ram
s p
er li
tre
mV
= m
illiv
olts
oC =
de
gre
es C
els
ius
"-"
- no
t cal
cula
ted
Loca
tion
whe
re w
ater
tabl
e at
or
abov
e ba
se o
f 2
m tr
ench
Rev
isio
n 01
1
0 Ja
nuar
y 20
19
P:\
605X
\605
9263
4\40
0_T
EC
H\4
35_G
roun
dwat
er\T
able
s\T
able
s 1
- 3
GIJ
PP
Gro
und
wat
er_1
.xls
xP
age
1 o
f 1
Pri
nt D
ate:
14
/10
/201
9
Clie
nt N
ame:
AG
L W
hole
sale
Gas
Ltd
and
APA
Tra
nsm
issi
on P
ty L
tdPr
ojec
t Nam
e: G
IJPP
EES
Gro
undw
ater
Tec
hnic
al R
epor
t
Tabl
e B
3. G
roun
dwat
er S
ampl
ing
Fiel
d Pa
ram
eter
s
CPT
IDBo
re ID
Dat
eVo
lum
eR
emov
ed (L
)Te
mpe
ratu
re(º
C)
Dis
solv
edO
xyge
n (m
g/L)
Elec
trica
lC
ondu
ctiv
ity(µ
S/cm
)pH
Red
ox F
ield
(mV)
Tota
l Dis
solv
edSo
lids
(TD
S) ¹
²R
edox
Pot
entia
l(E
h) ³
Com
men
ts
CPT
006_
MW
01M
W01
25/0
1/19
1.0
18.2
000.
6391
116.
2842
.259
2225
3.6
Gra
b sa
mpl
e; o
nly
enou
gh w
ater
for T
DS
- Bai
ler;
nood
our,
brow
n, h
igh
turb
idity
, no
shee
n.C
PT01
2_M
W02
MW
0223
/01/
196.
318
.500
0.36
4020
6.09
84.7
2613
295.
9C
lear
, no
odou
r, no
turb
idity
or s
heen
.C
PT01
2_M
W03
MW
0323
/01/
193.
916
.800
0.38
4406
6.67
58.1
2864
270.
6Li
ght b
row
n, n
o od
our,
low
turb
idity
, no
shee
n.C
PT02
2_M
W05
MW
0525
/01/
1913
.717
.800
0.52
8580
6.13
53.5
5577
265.
2C
lear
, no
odou
r.C
PT04
0_B_
MW
07M
W07
24/0
1/19
10.1
17.3
000.
5119
277.
3426
.412
5323
8.5
Ligh
t bro
wn,
no
odou
r, cl
ear.
CPT
040_
B_G
W04
GW
0423
/1/4
199.
018
.300
1.30
8601
6.04
123.
955
9133
5.3
Cle
ar, n
o od
our.
CPT
045_
GW
05G
W05
23/0
1/19
5.8
17.4
001.
3684
606.
1917
0.1
5499
382.
1Li
ght b
row
nish
whi
te, n
o od
our,
low
turb
idity
.C
PT05
1_M
W09
MW
0923
/01/
1921
.517
.700
0.27
1959
46.
3818
.512
736
230.
3Li
ght b
row
n, n
o od
our,
clea
r.C
PT05
5_M
W10
MW
1023
/01/
192.
418
.900
0.25
5677
6.82
-17
3690
193.
9C
lear
, no
odou
r.
CPT
000_
MW
11M
W11
23/0
1/19
3.0
17.1
002.
0325
252
--
1641
4-
pH n
ot s
ampl
ing/
redo
x ch
angi
ng, L
ight
bro
wn,
no
odou
r,cl
ear.
CPT
037_
B_M
W14
MW
1424
/01/
194.
117
.900
0.23
8010
5.96
6952
0728
0.7
Ligh
t bro
wn,
no
turb
idity
, no
odou
r.C
PT00
0_M
W15
MW
1522
/01/
197.
217
.000
2.89
7515
--
4885
-pH
not
sam
plin
g/re
dox
chan
ging
, cle
ar, n
o od
our.
CPT
129_
MW
21M
W21
30/0
1/19
5.2
17.8
003.
1484
206.
811
2.6
5473
324.
3Li
ght b
row
n, lo
w tu
rbid
ity, n
o od
our.
CPT
134_
MW
22M
W22
30/0
1/19
6.9
19.3
001.
9216
850
6.2
118.
110
953
328.
7Li
ght b
row
n, n
o od
our,
clea
r, no
she
en.
Not
es(1
) TD
S =
Tota
l Dis
solv
ed S
olid
s(2
) TD
S ap
prox
imat
ed a
s El
ectri
cal C
ondu
ctiv
ity x
0.6
5(3
) Cor
rect
ed R
edox
Pot
entia
l = F
ield
Red
ox P
oten
tial +
(224
.98
- 0.7
443*
Tem
pera
ture
) (R
edox
pot
entia
l con
verte
d fro
m A
g/Ag
Cl e
lect
rode
to H
2 el
ectro
de)
L =
Litre
spp
m =
par
ts p
er m
illion
uS/c
m =
mic
rosi
emen
s pe
r cen
timet
rem
g/L
= m
illigr
ams
per l
itre
mV
= m
illivo
ltsoC
= d
egre
es C
elsi
usTO
C =
Top
of C
asin
g"-
" - n
ot m
easu
red
due
to in
cons
itenc
ies
in th
e th
e m
easu
rem
ent d
evic
e
Rev
isio
n 01
10
Jan
uary
201
9P:
\605
X\60
5926
34\4
00_T
ECH
\435
_Gro
undw
ater
\Tab
les\
Tabl
es 1
- 3
GIJ
PP G
roun
dwat
er_1
.xls
xPa
ge 1
of 1
Prin
t Dat
e: 2
8/02
/201
9
Table B4Groundwater Analytical ResultsGIJPPAGL Wholesale Gas Limited and APA Transmission Pty Limited - Crib Point to Pakenham
MW01 MW02 MW03 MW07 GW04 MW09 MW10 MW11 MW14 MW15 MW21 MW22CPT006_MW01 CPT012_MW02 CPT012_MW03 CPT022W_MW05CPT022W_MW05CPT022W_MW05CPT040B_MW07CPT040B_MW04 CPT045_MW05 CPT045_MW05 CPT045_MW05 CPT051_MW09 CPT055_MW10 CPT000_MW11 CPT037B_MW14 CPT000_MW15 CPT129_MW21 CPT134_MW2225/01/2019 23/01/2019 23/01/2019 25/01/2019 25/01/2019 25/01/2019 24/01/2019 24/01/2019 23/01/2019 23/01/2019 23/01/2019 23/01/2019 23/01/2019 23/01/2019 24/01/2019 23/01/2019 30/01/2019 30/01/2019Primary Primary Primary Primary Duplicate Triplicate Primary Primary Primary Duplicate Triplicate Primary Primary Primary Primary Primary Primary PrimaryEM1901029 EM1900976 EM1900976 EM1901029 EM1901029 637748 EM1900976 EM1900976 EM1900976 EM1900976 637750 EM1900976 EM1900976 EM1900976 EM1900976 EM1900976 EM1901225 EM1901225
Analyte Unit LORCalculated TDS (from Electrica
Total Dissolved Solids (Calc.) mg/L 1 4730 2670 2850 5100 5320 - 884 5560 5280 5280 - 13,800 4090 18,700 4600 4500 5210 10,800EW_LEED_MA_1523
Perfluoro-n-hexadecanoic acid µg/L 0.005 - - - - - - - <0.005 <0.005 <0.005 - - - - - - - -Per- and Polyfluoroalkyl Subst
Perfluorobutanoic acid µg/L 0.01 - - - - - - - <0.01 <0.01 <0.01 0.008 - - - - - - -Sum of PFAS µg/L 0.002 - - - - - - - <0.002 0.11 0.115 0.13 - - - - - - -Sum of PFAS (WA DER List) µg/L 0.002 - - - - - - - <0.002 0.101 0.106 0.124 - - - - - - -10:2 FTS µg/L 0.005 - - - - - - - <0.005 <0.005 <0.005 <0.001 - - - - - - -MeFOSAA µg/L 0.002 - - - - - - - <0.002 <0.002 <0.002 <0.005 - - - - - - -EtFOSAA µg/L 0.002 - - - - - - - <0.002 <0.002 <0.002 <0.005 - - - - - - -
Perfluoroalkane Sulfonic Acids (PFSA)PFBS µg/L 0.002 - - - - - - - <0.002 0.035 0.033 0.029#1 - - - - - - -PFPeS µg/L 0.002 - - - - - - - <0.002 0.009 0.009 0.006#1 - - - - - - -PFHpS µg/L 0.002 - - - - - - - <0.002 <0.002 <0.002 <0.001 - - - - - - -PFHxS µg/L 0.002 - - - - - - - <0.002 0.025 0.024 0.037#1 - - - - - - -PFOS µg/L 0.002 - - - - - - - <0.002 <0.002 <0.002 0.002#1 - - - - - - -
Perfluoroalkyl Sulfonic Acids (PFSA)Perfluorodecane sulfonic acid (PFDS) µg/L 0.002 - - - - - - - <0.002 <0.002 <0.002 <0.001 - - - - - - -
PFASN-MeFOSE (24448-09-7) ug/L 0.005 - - - - - - - <0.005 <0.005 <0.005 <0.005 - - - - - - -
Physio-Chemical ParametersTotal Dissolved Solids mg/L 10 4000 2000 5000 - 2410 2640 - - 6300 1120 5620 5050 5140 5900 14,300 3780 21,400 4750 4870 - -pH (Lab) pH Units 0.01 6-8.5 6-8.5 6.5-8.5 7.38 6.67 7.06 7.11 7.19 - 7.42 6.31 6.5 6.48 7.9 6.56 6.92 6.67 6.86 6.54 7.31 7.08
Total Petroleum HydrocarbonsC6-C9 fraction µg/L 20 - <20 <20 <20 <20 - - <20 <20 <20 <20 <20 <20 <20 <20 <20 <20 <20C10-C14 fraction µg/L 50 - <50 <50 <50 <50 - - <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50C15-C28 fraction µg/L 100 - <100 <100 <100 <100 - - <100 <100 <100 <100 <100 <100 <100 <100 <100 <100 <100C29-C36 fraction µg/L 50 - <50 <50 <50 <50 - - <50 <50 <50 <100 <50 <50 <50 <50 <50 <50 <50C10-C36 fraction (sum) µg/L 50 - <50 <50 <50 <50 - - <50 <50 <50 <100 <50 <50 <50 <50 <50 <50 <50
Total Recoverable HydrocarbonsC6-C10 fraction µg/L 20 - <20 <20 <20 <20 - - <20 <20 <20 <20 <20 <20 <20 <20 <20 <20 <20C6-C10 fraction (minus BTEX)(F1) µg/L 20 - <20 <20 <20 <20 - - <20 <20 <20 <20 <20 <20 <20 <20 <20 <20 <20>C10-C16 fraction µg/L 100 - <100 <100 <100 <100 - - <100 <100 <100 <50 <100 <100 <100 <100 <100 <100 <100>C10-C16 (minus Naphthalene)(F2) µg/L 100 - <100 <100 <100 <100 - - <100 <100 <100 <50 <100 <100 <100 <100 <100 <100 <100>C16-C34 fraction µg/L 100 - <100 <100 <100 <100 - - <100 <100 <100 <100 <100 <100 <100 <100 <100 <100 <100>C34-C40 fraction µg/L 100 - <100 <100 <100 <100 - - <100 <100 <100 <100 <100 <100 <100 <100 <100 <100 <100>C10-C40 fraction (sum) µg/L 100 - <100 <100 <100 <100 - - <100 <100 <100 <100 <100 <100 <100 <100 <100 <100 <100
Monocyclic Aromatic HydrocarbonsBenzene µg/L 1 1 1 1 500 10#2 - <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1 <1Toluene µg/L 2 800 800 800 8000#2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Ethylbenzene µg/L 2 300 300 300 3000#2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2m&p-Xylene µg/L 2 - <2 <2 <2 <2 <2 <2 <2 <2 <2 <2 <2 <2 <2 <2 <2 <2 <2o-Xylene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Total Xylenes µg/L 2 600 600 600 6000#2 - <2 <2 <2 <2 <3 - <2 <2 <2 <3 <2 <2 <2 <2 <2 <2 <2Styrene µg/L 5 30 30 30 300#2 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5Isopropylbenzene µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5n-butylbenzene µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <5n-propylbenzene µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <5p-isopropyltoluene µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <5sec-butylbenzene µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <5tert-butylbenzene µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <51,2,4-trimethylbenzene µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <51,3,5-trimethylbenzene µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5Total MAH µg/L 3 - - - - - <3 - - - - <3 - - - - - - -Total BTEX µg/L 1 - <1 <1 <1 <1 - - <1 <1 <1 - <1 <1 <1 <1 <1 <1 <1
NaphthaleneNaphthalene (VOC) µg/L 5 50 - <5 <5 <5 <5 - - <5 <5 <5 - <5 <5 <5 <5 <5 <5 <5
Polynuclear Aromatic HydrocarbonsNaphthalene µg/L 2 50 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <22-Methylnaphthalene µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <21-Chloronaphthalene µg/L 5 - - - - - <5 - - - - <5 - - - - - - -2-Chloronaphthalene µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Acenaphthylene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Acenaphthene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Anthracene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Fluorene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Phenanthrene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Fluoranthene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Benz(a)anthracene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Benzo(k)fluoranthene µg/L 1 - - - - - <1 - - - - <1 - - - - - - -Benzo(b&j)fluoranthene µg/L 1 - - - - - <1 - - - - <1 - - - - - - -Benzo(b+j) & Benzo(k)fluoranthene µg/L 4 - <4 <4 <4 <4 - <4 <4 <4 <4 - <4 <4 <4 <4 <4 <4 <4N-2-Fluorenyl Acetamide µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <27,12-Dimethylbenz(a)anthracene µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Benzo(a)pyrene µg/L 2 0.01 0.01 0.01 0.1#2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Chrysene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Pyrene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <23-Methylcholanthrene µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Benzo(g,h,i)perylene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Dibenz(a,h)anthracene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Indeno(1,2,3-cd)pyrene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <2Dibenz(a,j)acridine µg/L 5 - - - - - <5 - - - - <5 - - - - - - -Sum of PAHs µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2
Phenolic CompoundsPhenol µg/L 2 270 - <2 <2 <2 <2 <3 <2 <2 <2 <2 <3 <2 <2 <2 <2 <2 <2 <22-Chlorophenol µg/L 2 300 300 300 3000#2 - <2 <2 <2 <2 <3 <2 <2 <2 <2 <3 <2 <2 <2 <2 <2 <2 <22-Methylphenol (o-Cresol) µg/L 2 - <2 <2 <2 <2 <3 <2 <2 <2 <2 <3 <2 <2 <2 <2 <2 <2 <23&4-Methylphenol (m&p-Cresol) µg/L 4 - <4 <4 <4 <4 <6 <4 <4 <4 <4 <6 <4 <4 <4 <4 <4 <4 <42-Nitrophenol µg/L 2 - <2 <2 <2 <2 <10 <2 <2 <2 <2 <10 <2 <2 <2 <2 <2 <2 <22,4-Dichlorophenol µg/L 2 200 200 200 2000#2 - <2 <2 <2 <2 <3 <2 <2 <2 <2 <3 <2 <2 <2 <2 <2 <2 <22,4-Dimethylphenol µg/L 2 - <2 <2 <2 <2 <3 <2 <2 <2 <2 <3 <2 <2 <2 <2 <2 <2 <22,6-Dichlorophenol µg/L 2 - <2 <2 <2 <2 <3 <2 <2 <2 <2 <3 <2 <2 <2 <2 <2 <2 <24-Chloro-3-methylphenol µg/L 2 - <2 <2 <2 <2 <10 <2 <2 <2 <2 <10 <2 <2 <2 <2 <2 <2 <22,4,6-Trichlorophenol µg/L 2 20 20 20 200#2 - <2 <2 <2 <2 <10 <2 <2 <2 <2 <10 <2 <2 <2 <2 <2 <2 <22,4,5-Trichlorophenol µg/L 2 - <2 <2 <2 <2 <10 <2 <2 <2 <2 <10 <2 <2 <2 <2 <2 <2 <24,6-Dinitro-2-methylphenol µg/L 30 - - - - - <30 - - - - <30 - - - - - - -Pentachlorophenol µg/L 4 10 10 10 11 100#2 - <4 <4 <4 <4 <10 <4 <4 <4 <4 <10 <4 <4 <4 <4 <4 <4 <42,3,4,6-Tetrachlorophenol µg/L 10 - - - - - <10 - - - - <10 - - - - - - -2,4-Dinitrophenol µg/L 30 - - - - - <30 - - - - <30 - - - - - - -4-Nitrophenol µg/L 30 - - - - - <30 - - - - <30 - - - - - - -
MetalsAluminium (Filtered) mg/L 0.01 5 20 5 5 5 - 0.01 0.02 0.02 0.01 0.08 0.08 <0.01 <0.01 <0.01 <0.05 <0.01 0.02 <0.01 0.03 <0.01 0.02 0.01Arsenic (Filtered) mg/L 0.001 0.1 2 0.5 0.5 0.5 0.1#2 - 0.005 0.006 0.004 0.004 0.007 0.005 0.001 0.001 0.001 0.004 0.012 0.011 0.003 0.007 0.001 0.002 0.001Cadmium (Filtered) mg/L 0.0001 0.01 0.05 0.01 0.01 0.01 0.0007 0.02#2 - <0.0001 <0.0001 <0.0001 <0.0001 0.0009 <0.0001 <0.0001 <0.0001 <0.0001 0.0003 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001Chromium (Filtered) mg/L 0.001 0.1 1 1 1 1 0.5#2 - <0.001 <0.001 <0.001 <0.001 0.009 <0.001 <0.001 <0.001 <0.001 0.003 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001Chromium (hexavalent) ug/L 10 50 50 50 0.14 500#2 - - - <10 <10 <5 - - - - <5 - - - - - <10 <10Chromium (hexavalent) (Filtered) ug/L 10 50 50 50 0.14 500#2 - <10 <10 - - - <10 <10 <10 <10 - <10 <10 <10 <10 <10 - -Copper (Filtered) mg/L 0.001 0.2 5 1 0.4 0.4 0.0003 20#2 - <0.001 0.001 <0.001 <0.001 0.008 <0.001 0.004 0.002 0.002 0.004 <0.001 <0.001 0.009 0.002 0.001 0.006 0.001Iron (Filtered) mg/L 0.05 0.2 10 - 1 0.33 1.7 1.95 1.9 0.07 1.02 <0.05 <0.05 0.05 3.59 3.02 0.26 0.74 <0.05 <0.05 <0.05Lead (Filtered) mg/L 0.001 2 5 0.1 0.1 0.1 0.0022 0.1#2 - <0.001 <0.001 <0.001 <0.001 0.008 <0.001 <0.001 <0.001 <0.001 0.002 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001 <0.001Mercury (Filtered) mg/L 0.0001 0.002 0.002 0.002 0.002 0.002 0.0001 0.01#2 - <0.0001 <0.0001 <0.0001 <0.0001 0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001 <0.0001Nickel (Filtered) mg/L 0.001 0.2 2 1 1 1 0.007 0.2#2 - 0.008 0.005 0.005 0.005 0.013 0.002 0.019 0.003 0.003 0.005 0.008 0.004 0.009 0.004 0.012 0.003 0.004Selenium (Filtered) ug/L 10 20 50 20 20 20 100#2 - <10 <10 <10 <10 9 <10 <10 <10 <10 4 <10 <10 <10 <10 <10 <10 <10Zinc (Filtered) mg/L 0.005 2 5 20 20 20 0.007 - 0.061 0.179 0.042 0.047 0.051 0.014 0.114 0.036 0.042 0.042 0.054 0.029 0.072 0.044 0.093 0.164 0.021
MW05 GW05LocationCPT LocationSample DateSample Type
Lab Report No.ANZECC 2000 -LivestockWatering(Sheep)
NHMRC 2008 -Guidelines forManaging Risksin RecreationalWaters
StandardsAustralia -AS2159 2009Buildings andStructures
ANZECC 2000 -Irrigation LTV
ANZECC 2000 -Irrigation STV
ANZECC 2000 -LivestockWatering (Beefcattle)
ANZECC 2000 -LivestockWatering(poultry)
ANZECC 2000 -Maintenance ofEcosystemsMarine Water99%
AECOM Australia Pty Ltd Page 1 of 3 P:\605X\60592634\400_TECH\435_Groundwater\Tables\Table B4 Groundwater Analytical Results_criteria_Marine Only_20190228.xlsm , 28/02/2019
Table B4Groundwater Analytical ResultsGIJPPAGL Wholesale Gas Limited and APA Transmission Pty Limited - Crib Point to Pakenham
MW01 MW02 MW03 MW07 GW04 MW09 MW10 MW11 MW14 MW15 MW21 MW22CPT006_MW01 CPT012_MW02 CPT012_MW03 CPT022W_MW05CPT022W_MW05CPT022W_MW05CPT040B_MW07CPT040B_MW04 CPT045_MW05 CPT045_MW05 CPT045_MW05 CPT051_MW09 CPT055_MW10 CPT000_MW11 CPT037B_MW14 CPT000_MW15 CPT129_MW21 CPT134_MW2225/01/2019 23/01/2019 23/01/2019 25/01/2019 25/01/2019 25/01/2019 24/01/2019 24/01/2019 23/01/2019 23/01/2019 23/01/2019 23/01/2019 23/01/2019 23/01/2019 24/01/2019 23/01/2019 30/01/2019 30/01/2019Primary Primary Primary Primary Duplicate Triplicate Primary Primary Primary Duplicate Triplicate Primary Primary Primary Primary Primary Primary PrimaryEM1901029 EM1900976 EM1900976 EM1901029 EM1901029 637748 EM1900976 EM1900976 EM1900976 EM1900976 637750 EM1900976 EM1900976 EM1900976 EM1900976 EM1900976 EM1901225 EM1901225
Analyte Unit LOR
MW05 GW05LocationCPT LocationSample DateSample Type
Lab Report No.ANZECC 2000 -LivestockWatering(Sheep)
NHMRC 2008 -Guidelines forManaging Risksin RecreationalWaters
StandardsAustralia -AS2159 2009Buildings andStructures
ANZECC 2000 -Irrigation LTV
ANZECC 2000 -Irrigation STV
ANZECC 2000 -LivestockWatering (Beefcattle)
ANZECC 2000 -LivestockWatering(poultry)
ANZECC 2000 -Maintenance ofEcosystemsMarine Water99%
Halogenated Aromatic CompoundsBenzyl chloride µg/L 5 - - - - - <5 - - - - <5 - - - - - - -Bromobenzene µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5Chlorobenzene µg/L 5 300 300 300 3000#2 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <52-Chlorotoluene µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <54-Chlorotoluene µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <51,2-Dichlorobenzene µg/L 2 1500 1500 1500 15000#2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <21,3-Dichlorobenzene µg/L 2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <21,4-Dichlorobenzene µg/L 2 40 40 40 400#2 - <2 <2 <2 <2 <1 <2 <2 <2 <2 <1 <2 <2 <2 <2 <2 <2 <21,2,3,4-Tetrachlorobenzene µg/L 5 - - - - - <5 - - - - <5 - - - - - - -1,2,3,5-Tetrachlorobenzene µg/L 5 - - - - - <5 - - - - <5 - - - - - - -1,2,4,5-Tetrachlorobenzene µg/L 5 - - - - - <5 - - - - <5 - - - - - - -1,2,3-Trichlorobenzene µg/L 5 - <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <51,2,4-Trichlorobenzene µg/L 2 20 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <21,3,5-Trichlorobenzene µg/L 5 - - - - - <5 - - - - <5 - - - - - - -
Halogenated Aliphatic CompoundsBromochloromethane µg/L 1 - - - - - <1 - - - - <1 - - - - - - -Allyl chloride µg/L 1 - - - - - <1 - - - - <1 - - - - - - -Dichlorodifluoromethane (Freon 12) µg/L 50 - <50 <50 <50 <50 <1 <50 <50 <50 <50 <1 <50 <50 <50 <50 <50 <50 <50Chloromethane µg/L 50 - <50 <50 <50 <50 <1 <50 <50 <50 <50 <1 <50 <50 <50 <50 <50 <50 <50Vinyl chloride µg/L 50 0.3 0.3 0.3 3#2 - <50 <50 <50 <50 <1 <50 <50 <50 <50 <1 <50 <50 <50 <50 <50 <50 <50Bromomethane µg/L 50 1#3 1#3 10#2 - <50 <50 <50 <50 <1 <50 <50 <50 <50 <1 <50 <50 <50 <50 <50 <50 <50Chloroethane µg/L 50 - <50 <50 <50 <50 <1 <50 <50 <50 <50 <1 <50 <50 <50 <50 <50 <50 <50Trichlorofluoromethane (Freon 11) µg/L 50 - <50 <50 <50 <50 <1 <50 <50 <50 <50 <1 <50 <50 <50 <50 <50 <50 <501,1-Dichloroethene µg/L 5 30 30 30 300#2 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5Iodomethane µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <51,1-Dichloroethane µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5cis-1,2-Dichloroethene µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5trans-1,2-Dichloroethene µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <51,1,1-Trichloroethane µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <51,1-Dichloropropene µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <5Carbon Tetrachloride µg/L 5 3 3 3 30#2 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <51,2-Dichloroethane µg/L 5 3 3 3 30#2 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5Trichloroethene µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5Dibromomethane µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <51,1,2-Trichloroethane µg/L 5 140 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <51,3-Dichloropropane µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5Tetrachloroethene µg/L 5 50 50 50 500#2 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <51,1,1,2-Tetrachloroethane µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5trans-1,4-Dichloro-2-butene µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <5cis-1,4-Dichloro-2-butene µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <51,1,2,2-Tetrachloroethane µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <51,2,3-Trichloropropane µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5Dichloromethane µg/L 1 4 4 4 40#2 - - - - - <1 - - - - <1 - - - - - - -Pentachloroethane µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <51,2-Dibromo-3-chloropropane µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <5Hexachlorobutadiene µg/L 2 0.7 0.7 0.7 7#2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2
Fumigants1,2-Dibromoethane (EDB) µg/L 5 1#3 1#3 10#2 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <51,2-Dichloropropane µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <52,2-Dichloropropane µg/L 5 - <5 <5 <5 <5 - <5 <5 <5 <5 - <5 <5 <5 <5 <5 <5 <5cis-1,3-Dichloropropene µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5trans-1,3-Dichloropropene µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5
TrihalomethanesBromodichloromethane µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5Bromoform µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5Chloroform µg/L 5 - <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5 <5Dibromochloromethane µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5
Physico-Chemical ParametersElectrical conductivity (lab) µS/cm 1 7280 4110 4380 7850 8190 - 1360 8550 8130 8120 8300 21,300 6290 28,800 7080 6930 8010 16,600
AlkalinityBicarbonate Alkalinity as CaCO3 mg/L 1 264 267 312 292 292 300 318 156 240 240 260 217 442 596 355 212 321 307Carbonate Alkalinity as CaCO3 mg/L 1 <1 <1 <1 <1 <1 <10 <1 <1 <1 <1 <10 <1 <1 <1 <1 <1 <1 <1Hydroxide Alkalinity as CaCO3 mg/L 1 <1 <1 <1 <1 <1 - <1 <1 <1 <1 - <1 <1 <1 <1 <1 <1 <1Total Alkalinity as CaCO3 mg/L 1 264 267 312 292 292 300 318 156 240 240 260 217 442 596 355 212 321 307Hardness as CaCO3 mg/L 5 - - - - - 1200 - - - - 1000 - - - - - - -Hardness as CaCO3 (Filtered) mg/L 1 804 470 530 1140 1130 - 65 754 957 1140 - 4530 143 6500 633 1360 1040 2240
NutrientsAmmonia (as N) mg/L 0.01 0.5 0.02 0.09 0.06 0.17 0.15 0.12 0.06 0.04 0.24 0.24 0.21 0.5 0.1 0.31 0.17 0.05 0.13 0.2Nitrate (as N) mg/L 0.01 90.3 90.3 90.3 0.04 <0.01 0.03 0.05 0.06 <0.02 0.02 0.02 0.02 0.01 <0.02 <0.01 <0.01 0.03 0.02 0.01 0.11 0.08Nitrite (as N) mg/L 0.01 9.12 9.12 9.12 <0.01 <0.01 <0.01 <0.01 <0.01 <0.02 <0.01 <0.01 <0.01 <0.01 <0.02 <0.01 <0.01 <0.01 <0.01 <0.01 0.01 0.01Total Kjeldahl Nitrogen mg/L 0.1 0.8 0.3 0.7 0.3 0.3 <0.2 1.4 1.2 1.2 0.8 0.8 0.9 0.3 1 0.5 0.5 1 0.3Total Nitrogen (as N) mg/L 0.1 5 25-125 0.8 0.3 0.7 0.4 0.4 <0.2 1.4 1.2 1.2 0.8 0.8 0.9 0.3 1 0.5 0.5 1.1 0.4Reactive Phosphorus (as P) mg/L 0.01 <0.01 <0.01 0.01 <0.01 <0.01 0.01 <0.01 <0.01 <0.01 <0.01 0.01 <0.01 <0.01 0.01 <0.01 <0.01 0.02 <0.01Total Phosphate (as P) mg/L 0.01 - - - - - 0.02 - - - - <0.01 - - - - - - -Total Phosphorus mg/L 0.01 0.05 0.8-12 0.48 0.12 0.19 0.07 0.09 - 0.45 0.4 0.26 0.26 - 0.33 0.09 0.39 0.11 0.17 0.41 0.09
Major IonsChloride mg/L 1 6000 2960 1190 1270 2950 2890 2600 280 3070 2800 3100 2700 7590 1670 10,300 2640 2300 2830 6120Calcium mg/L 1 1000 1000 1000 134 81 72 133 129 170 16 68 98 128 120 809 11 1270 72 199 83 146Fluoride mg/L 0.1 1 2 2 2 2 15#2 0.1 0.1 0.2 0.2 0.2 - 0.7 <0.1 0.1 0.1 <0.5 0.4 0.7 0.3 0.2 0.2 0.5 0.2Sodium Adsorption Ratio (Filtered) - 0.01 23 12.2 12.2 15.3 15.2 - 14.4 22.5 17.7 16 - 19.4 43.7 21.5 22.1 10.8 16.2 23.7Magnesium mg/L 1 114 65 85 197 197 190 6 142 173 200 170 610 28 809 110 211 202 456Potassium mg/L 1 <1 <1 4 <1 <1 <5 <1 <1 <1 3 <5 <2#2 41 <2#2 <1 <1 4 2Sodium mg/L 1 1500 609 645 1190 1180 1200 266 1420 1260 1240 1200 3000 1200 3990 1280 917 1200 2580Sulphate (as SO4-) mg/L 5 1000 1000 1000 5000 1000 - - - - - 130 - - - - 130 - - - - - - -Total Anions meq/L 0.01 97.2 41.4 44.3 91.7 90 - 16.1 94.8 86.4 94.9 - 244 65.4 327 85.6 80.6 89.1 186Total Cations meq/L 0.01 81.3 35.9 38.7 74.6 74 - 12.9 76.8 73.9 76.9 - 221 56.1 304 68.3 67.2 73.1 157Sulfate as SO4 - Turbidimetric (Filtered) mg/L 1 1000 1000 1000 5000 1000 404 122 106 128 129 - 88 244 124 126 - 1220 452 1170 193 554 139 333Ionic Balance % 0.01 8.89 7.19 6.65 10.3 9.79 - 11.1 10.4 7.75 10.5 - 4.9 7.62 3.7 11.2 9.11 9.91 8.35
Oxygenated Compounds2-Propanone (Acetone) µg/L 1 - - - - - <1 - - - - <1 - - - - - - -Vinyl acetate µg/L 50 - <50 <50 <50 <50 - <50 <50 <50 <50 - <50 <50 <50 <50 <50 <50 <502-Butanone (MEK) µg/L 50 - <50 <50 <50 <50 <1 <50 <50 <50 <50 <1 <50 <50 <50 <50 <50 <50 <502-hexanone (MBK) µg/L 50 - <50 <50 <50 <50 - <50 <50 <50 <50 - <50 <50 <50 <50 <50 <50 <504-Methyl-2-pentanone (MIBK) µg/L 50 - <50 <50 <50 <50 <1 <50 <50 <50 <50 <1 <50 <50 <50 <50 <50 <50 <50
Sulfonated CompoundsCarbon disulfide µg/L 5 - <5 <5 <5 <5 <1 <5 <5 <5 <5 <1 <5 <5 <5 <5 <5 <5 <5
Phthalate EstersButyl benzyl phthalate µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Diethyl phthalate µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Dimethyl phthalate µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Di-n-butyl phthalate µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Di-n-octyl phthalate µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Bis(2-ethylhexyl)phthalate µg/L 10 10 10 10 100#2 - <10 <10 <10 <10 <5 <10 <10 <10 <10 <5 <10 <10 <10 <10 <10 <10 <10
NitrosaminesDiphenylamine µg/L 5 - - - - - <5 - - - - <5 - - - - - - -Methapyrilene µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2N-Nitrosodibutylamine µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2N-Nitrosodiethylamine µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2N-Nitrosodiphenyl & Diphenylamine µg/L 4 - <4 <4 <4 <4 - <4 <4 <4 <4 - <4 <4 <4 <4 <4 <4 <4N-Nitrosodipropylamine µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2N-Nitrosomethylethylamine µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2N-Nitrosomorpholine µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2N-Nitrosopiperidine µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2N-Nitrosopyrrolidine µg/L 4 - <4 <4 <4 <4 - <4 <4 <4 <4 - <4 <4 <4 <4 <4 <4 <4
AECOM Australia Pty Ltd Page 2 of 3 P:\605X\60592634\400_TECH\435_Groundwater\Tables\Table B4 Groundwater Analytical Results_criteria_Marine Only_20190228.xlsm , 28/02/2019
Table B4Groundwater Analytical ResultsGIJPPAGL Wholesale Gas Limited and APA Transmission Pty Limited - Crib Point to Pakenham
MW01 MW02 MW03 MW07 GW04 MW09 MW10 MW11 MW14 MW15 MW21 MW22CPT006_MW01 CPT012_MW02 CPT012_MW03 CPT022W_MW05CPT022W_MW05CPT022W_MW05CPT040B_MW07CPT040B_MW04 CPT045_MW05 CPT045_MW05 CPT045_MW05 CPT051_MW09 CPT055_MW10 CPT000_MW11 CPT037B_MW14 CPT000_MW15 CPT129_MW21 CPT134_MW2225/01/2019 23/01/2019 23/01/2019 25/01/2019 25/01/2019 25/01/2019 24/01/2019 24/01/2019 23/01/2019 23/01/2019 23/01/2019 23/01/2019 23/01/2019 23/01/2019 24/01/2019 23/01/2019 30/01/2019 30/01/2019Primary Primary Primary Primary Duplicate Triplicate Primary Primary Primary Duplicate Triplicate Primary Primary Primary Primary Primary Primary PrimaryEM1901029 EM1900976 EM1900976 EM1901029 EM1901029 637748 EM1900976 EM1900976 EM1900976 EM1900976 637750 EM1900976 EM1900976 EM1900976 EM1900976 EM1900976 EM1901225 EM1901225
Analyte Unit LOR
MW05 GW05LocationCPT LocationSample DateSample Type
Lab Report No.ANZECC 2000 -LivestockWatering(Sheep)
NHMRC 2008 -Guidelines forManaging Risksin RecreationalWaters
StandardsAustralia -AS2159 2009Buildings andStructures
ANZECC 2000 -Irrigation LTV
ANZECC 2000 -Irrigation STV
ANZECC 2000 -LivestockWatering (Beefcattle)
ANZECC 2000 -LivestockWatering(poultry)
ANZECC 2000 -Maintenance ofEcosystemsMarine Water99%
Nitroaromatics and Ketones1,3,5-Trinitrobenzene µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <21-Naphthylamine µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <22,4-Dinitrotoluene µg/L 4 - <4 <4 <4 <4 <5 <4 <4 <4 <4 <5 <4 <4 <4 <4 <4 <4 <42,6-Dinitrotoluene µg/L 4 - <4 <4 <4 <4 <5 <4 <4 <4 <4 <5 <4 <4 <4 <4 <4 <4 <42-Naphthylamine µg/L 5 - - - - - <5 - - - - <5 - - - - - - -2-Picoline µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <24-Aminobiphenyl µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <24-Nitroquinoline-N-oxide µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <25-Nitro-o-toluidine µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Acetophenone µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Azobenzene µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Chlorobenzilate µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Dimethylaminoazobenzene µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Isophorone µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Nitrobenzene µg/L 2 - <2 <2 <2 <2 <50 <2 <2 <2 <2 <50 <2 <2 <2 <2 <2 <2 <2Pentachloronitrobenzene µg/L 2 30#3 30#3 300#2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Phenacetin µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Pronamide µg/L 2 70#3 70#3 700#2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2
Haloethers4-Bromophenyl phenyl ether µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Bis(2-chloroisopropyl)ether µg/L 5 - - - - - <5 - - - - <5 - - - - - - -Bis(2-chloroethyl) ether µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Bis(2-chloroethoxy) methane µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <24-Chlorophenyl phenyl ether µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2
Chlorinated HydrocarbonsHexachlorocyclopentadiene µg/L 10 - <10 <10 <10 <10 <5 <10 <10 <10 <10 <5 <10 <10 <10 <10 <10 <10 <10Hexachloroethane µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Hexachloropropene µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Pentachlorobenzene µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Chlorinated hydrocarbons (sum) µg/L 5 - - - - - <5 - - - - <5 - - - - - - -Other chlorinated hydrocarbons (sum) µg/L 5 - - - - - <5 - - - - <5 - - - - - - -
Organochlorine Pesticides (OC)Aldrin µg/L 2 0.3 0.3 0.3 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Dieldrin µg/L 2 0.3 0.3 0.3 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Aldrin + Dieldrin µg/L 4 0.3#3 0.3#3 3#2 - <4 <4 <4 <4 - <4 <4 <4 <4 - <4 <4 <4 <4 <4 <4 <4a-BHC µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2b-BHC µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2d-BHC µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2g-BHC (Lindane) µg/L 2 20 20 20 100#2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2DDD µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2DDE µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2DDT µg/L 4 20 20 20 90#2 - <4 <4 <4 <4 <5 <4 <4 <4 <4 <5 <4 <4 <4 <4 <4 <4 <4DDT+DDE+DDD µg/L 4 - <4 <4 <4 <4 - <4 <4 <4 <4 - <4 <4 <4 <4 <4 <4 <4Endosulfan 1 µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Endosulfan 2 µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Endosulfan sulfate µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Endrin µg/L 2 0.004 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Endrin aldehyde µg/L 5 - - - - - <5 - - - - <5 - - - - - - -Endrin ketone µg/L 5 - - - - - <5 - - - - <5 - - - - - - -Heptachlor µg/L 2 0.3 0.3 0.3 3#2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Heptachlor epoxide µg/L 2 0.3 0.3 0.3 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Hexachlorobenzene (HCB) µg/L 4 - <4 <4 <4 <4 <5 <4 <4 <4 <4 <5 <4 <4 <4 <4 <4 <4 <4Methoxychlor µg/L 5 300 300 300 - - - - - <5 - - - - <5 - - - - - - -
Organophosphorus Pesticides (OP)Chlorfenvinphos µg/L 2 5 5 5 20#2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Chlorpyrifos µg/L 2 10 10 10 0.0005 100#2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Chlorpyrifos-methyl µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Diazinon µg/L 2 3 3 3 40#2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Dichlorvos µg/L 2 1 1 1 50#2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Dimethoate µg/L 2 50 50 50 70#2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Ethion µg/L 2 3 3 3 40#2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Fenthion µg/L 2 7#3 7#3 70#2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Malathion µg/L 2 70#3 70#3 700#2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Pirimphos-ethyl µg/L 2 0.5 0.5 0.5 5#2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Prothiofos µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2
Benzidine3,3-Dichlorobenzidine µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2
Surfactants6:2 FTS µg/L 0.005 - - - - - - - <0.005 <0.005 <0.005 <0.005 - - - - - - -PFOA µg/L 0.002 - - - - - - - <0.002 0.008 0.007 0.008#1 - - - - - - -
Anilines2-Nitroaniline µg/L 4 - <4 <4 <4 <4 <5 <4 <4 <4 <4 <5 <4 <4 <4 <4 <4 <4 <43-Nitroaniline µg/L 4 - <4 <4 <4 <4 - <4 <4 <4 <4 - <4 <4 <4 <4 <4 <4 <44-Chloroaniline µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <24-Nitroaniline µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Aniline µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Carbazole µg/L 2 - <2 <2 <2 <2 - <2 <2 <2 <2 - <2 <2 <2 <2 <2 <2 <2Dibenzofuran µg/L 2 - <2 <2 <2 <2 <5 <2 <2 <2 <2 <5 <2 <2 <2 <2 <2 <2 <2Trifluralin µg/L 5 50 50 50 900#2 - - - - - <5 - - - - <5 - - - - - - -
FieldpH (Field) pH Units 6-8.5 6-8.5 6.5-8.5 6.28 6.09 6.67 6.13 - - 7.34 6.04 6.19 - - 6.38 6.82 - 5.96 - 6.8 6.2Temperature °C 18.2 18.5 16.8 17.8 - - 17.3 18.3 17.4 - - 17.7 18.9 17.1 17.9 17 17.8 19.3Electrical conductivity (field) µS/cm 9111 4020 4406 8580 - - 1927 8601 8460 - - 19,594 5677 25,252 8010 7515 8420 16,850TDS (Field) mg/L 5922 2613 2864 5577 - - 1253 5591 5499 - - 12,736 3690 16,414 5207 4885 5473 10953DO mg/L 0.63 0.36 0.38 0.52 - - 0.51 1.3 1.36 - - 0.27 0.25 2.03 0.23 2.89 3.14 1.92Redox Potential (Field) mV 42.2 84.7 58.1 53.5 - - 26.4 123.9 170.1 - - 18.5 -17 - 69 - 112.6 118.1Redox Potential (Corrected) mV 254 296 271 265 - - 239 335 382 - - 230 194 - 281 - 324 329
Organic4:2 FTS ug/L 0.005 - - - - - - - <0.005 <0.005 <0.005 <0.001 - - - - - - -PFPeA ug/L 0.002 - - - - - - - <0.002 0.007 0.011 0.01#1 - - - - - - -Sum (PFHxS + PFOS) ug/L 0.002 - - - - - - - <0.002 0.025 0.024 0.039 - - - - - - -Sum of enHealth PFAS (PFHxS + PFOS + PFOA)* ug/L 0.001 - - - - - - - - - - 0.047 - - - - - - -Sum of US EPA PFAS (PFOS + PFOA)* ug/L 0.001 - - - - - - - - - - 0.01 - - - - - - -
Perfluorinated Compounds (PFCs)8:2 FTS µg/L 0.005 - - - - - - - <0.005 <0.005 <0.005 <0.001 - - - - - - -N-Me-FOSA µg/L 0.005 - - - - - - - <0.005 <0.005 <0.005 <0.005 - - - - - - -FOSA µg/L 0.002 - - - - - - - <0.002 <0.002 <0.002 <0.005 - - - - - - -PFTeDA µg/L 0.005 - - - - - - - <0.005 <0.005 <0.005 <0.001 - - - - - - -PFTrDA µg/L 0.002 - - - - - - - <0.002 <0.002 <0.002 <0.001 - - - - - - -N-Et-FOSA µg/L 0.005 - - - - - - - <0.005 <0.005 <0.005 <0.005 - - - - - - -PFDcA µg/L 0.002 - - - - - - - <0.002 <0.002 <0.002 <0.001 - - - - - - -PFHpA µg/L 0.002 - - - - - - - <0.002 0.008 0.008 0.006#1 - - - - - - -PFHxA µg/L 0.002 - - - - - - - <0.002 0.018 0.023 0.024#1 - - - - - - -N-Et-FOSE µg/L 0.005 - - - - - - - <0.005 <0.005 <0.005 <0.005 - - - - - - -PFDoA µg/L 0.002 - - - - - - - <0.002 <0.002 <0.002 <0.001 - - - - - - -PFNA µg/L 0.002 - - - - - - - <0.002 <0.002 <0.002 <0.001 - - - - - - -PFUnA µg/L 0.002 - - - - - - - <0.002 <0.002 <0.002 <0.001 - - - - - - -
Env Stds Comments
Data Comments
#1:Interim Guideline#2:ADWG x10 (March 2015)#3:NHMRC 2011 Health
#1 Quantification of linear and branched isomers has been conducted as a single total response using the relative response factor for the corresponding linear/branched standard.#2 Reported Analyte LOR is higher than Requested Analyte LOR
AECOM Australia Pty Ltd Page 3 of 3 P:\605X\60592634\400_TECH\435_Groundwater\Tables\Table B4 Groundwater Analytical Results_criteria_Marine Only_20190228.xlsm , 28/02/2019
Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
AECOM
CAppendix CField programmethodology
1
Field Program and Data Analysis Methodology
Groundwater monitoring well installation The groundwater monitoring well installation methodology is summarised in Table 1 below. The locations of the groundwater monitoring wells are shown on Figure A1 (Appendix A). Table 1 Groundwater monitoring well installation methodology
Activity Details Service location Service location was undertaken by the following contractors:
• QEST Environmental between 29 November 2018 and 4 December 2018 • JULS Projects from between 8 January 2019 and 10 January 2019.
Drilling method All locations were cleared and drilled by Southwestern Drilling between 3 December 2018 and 11 January 2019. The monitoring well locations were cleared using non-destructive drilling to a minimum of 1.5 meters below ground level, and drilling was then advanced using solid stem augers to the target depth.
Soil logging Bore logs and monitoring well construction is presented in Appendix C. Monitoring Bore construction
All monitoring bores were drilled to a depth of 4 meters below ground level. Wells were installed using nominal 50 millimetre diameter Class 18 PVC casing and were screened with machine-slotted (0.5 millimetre slot) PVC across the water table between 1 and 4 meters below ground level. A sand filter pack (8/16 inch washed quartz sand) was installed in the bore annulus across the screen and at least 0.1 meters above the top of the screen. Above this, a bentonite seal was installed and hydrated to 0.1 meter below the surface. The annulus was then grouted to surface level and either a flush gatic (14 in total) or stick-up monument (12 in total) was installed.
Well development Post installation, the groundwater monitoring wells were developed by purging three bore volumes or until dry with a dedicated disposable bailer. All wells were developed within one week of installation.
Well survey All monitoring bores were surveyed on 30 January 2019. Survey data is presented in Table B1 (Appendix B).
Groundwater gauging and sampling The groundwater gauging and sampling methodology is summarised in Table 2 below. Table 2 Groundwater gauging and sampling methodology
Activity Details Groundwater gauging
All groundwater wells (26 locations) were gauged using an oil-water interface meter for depth to groundwater and total depth on 30 January 2019. The groundwater gauging data is presented in Table B2 (Appendix B).
Groundwater sampling dates
A total of 14 wells were sampled between 23 January 2019 and 30 January 2019. Groundwater sampling was conducted in wells GW04, GW05, MW01-MW03, MW05, MW07, MW09-MW11, MW14, MW15, MW21, and MW22. The remaining wells did not have sufficient water column to collect a sample.
Groundwater sampling method
Groundwater samples were collected using the following methods: • at well MW10: low flow sampling following the standard procedure (less
than 10 centimetre drawdown in the water column) • at wells MW02, MW03, MW05, MW07, GW04, GW05, MW09, MW11,
MW14, MW15, MW21 and MW22: recharge was too low for low flow
2
Activity Details sampling, so 50% of the well volume was purged with the low flow pump and samples were collected the following day (within 24 hours1) using low flow sampling techniques
• at well MW01: the water column was insufficient to use low flow sampling, so a grab sample was collected using a disposable bailer.
Ex-situ measurements of groundwater field chemistry (pH, electrical conductivity, dissolved oxygen, oxidation reduction potential, and temperature) were collected during low-flow purging. Where samples were collected the following day, in-situ measurements of groundwater field chemistry were collected prior to sampling. Field quality parameters collected during sampling are presented in Table B3 (Appendix B).
Sample preservation
All samples were collected into the appropriately preserved bottles as provided by the laboratory. Samples were stored on ice in a cooler box while on site and in transit to the laboratory for analysis. Samples for dissolved metals were field filtered with a single-use Stericup 0.45 micrometre filter to remove suspended solids and colloids and collected in laboratory-provided sample collection bottles containing acid for stabilisation/preservation.
Sample analysis All primary samples were submitted to Australian Laboratory Services for the following analysis: • dissolved metals • major ions • total dissolved solids • nutrients (nitrate, ammonia, and total phosphorus) • chromium (IV) • total recoverable hydrocarbons • benzene, toluene, ethylbenzene, xylenes and naphthalene • volatile organic compounds and semivolatile organic compounds • per- and poly-fluoroalkyl substances – low level suite (28 analytes) (GW04
and GW05 only). Quality control The following samples were submitted for quality control purposes:
• two duplicate samples, five equipment rinsate blanks, and five trip blanks to Australian Laboratory Services; and
• two inter-laboratory samples (field triplicate) to Eurofins Environment Testing Australia.
Decontamination procedure
The interface probe and low flow pump were washed in Liquinox solution and rinsed with potable water and deionised water between wells. Low flow bladders, low flow tubing and bailers were dedicated for each well.
Disposal of purged groundwater
Purged groundwater collected during sampling was discharged to ground given the minor volumes purged during sampling.
Equipment calibration
The water quality meter used to collect groundwater parameters was calibrated daily prior to sampling.
1 Except at MW21 and MW22 where samples were collected 6 days after purging due to weather constraints on sampling.
3
Aquifer testing The aquifer testing methodology is summarised in Table 3 below. Table 3 Aquifer testing methodology
Activity Details Dates of aquifer testing
Aquifer hydraulic testing (rising head slug tests) was conducted between 21 January 2019 and 25 January 2019. The tests were conducted in groundwater wells MW01-MW03, MW05, MW07, GW04, GW05, MW09-MW11, MW14, MW15, MW21, and MW22, where sufficient water column was available.
Aquifer testing methodology
The slug testing methodology is summarised below: • Depth to groundwater from the top of casing reference point was
measured prior to any disturbance within each of the wells. • An electronic pressure transducer was lowered into the well to monitor
groundwater pressure head at intervals of 10 seconds during testing. • A 35 millimetre diameter bailer of known volume (0.975 litres) was then
lowered into the well, completely submerged where the water column was sufficient and then removed, displacing the water level by approximately 0.5 metres. Where a full bailer was not removed, the bailer volume removed was measured on site and noted.
• Water levels were monitored manually (as well as by transducer) until 90% recovery had occurred (that is, the water level recovered to within 10% of the static water level prior to displacement). Where levels did not recover sufficiently due to site access and timing constraints, pressure transducers were removed after greater than four hours.
• Data from the electronic transducers was compared to manual measurements as part of the data quality assessment.
Tidal influence methodology
Pressure transducers were installed in MW01-MW03 for approximately seven days to determine whether there was potential for tidal influence in the southern portion of the alignment. Tidal influence was not observed in the monitoring wells.
Aquifer testing data analysis
Raw data from the slug tests are presented in Appendix G. The data shows oscillations of the water level during removal of the bailer volume and is considered to exhibit a slight under-damped response. This is reasonable when considering a test well of small diameter within a sandy aquifer. Data was cleaned and processed using AQTESOLV Pro version 4.50, an industry standard program. The Bouwer and Rice Method slug-test analysis method was adopted due to its applicability on partially penetrating, unconfined aquifer systems. The Bower and Rice equation is:
𝐾 =𝑟𝑐
2 ln 𝑅𝑒 𝑅⁄
2𝐿𝑒
1
𝑡ln
𝐻0
𝐻𝑡
(𝑒𝑞𝑢𝑎𝑡𝑖𝑜𝑛 5.91 𝑓𝑟𝑜𝑚 𝐹𝑒𝑡𝑡𝑒𝑟, 2001)
Where: K is hydraulic conductivity rc is the radius of the well casing R is the radius of the gravel envelope Re is the effective radial distance over which the head is dissipated Le is the saturated length of the screen or open section of the well H0 is the drawdown at time t=0 Ht is the drawdown at time t-t T is the time since H-H0 The following assumptions were made: • the geology at all locations was considered a single aquifer unit across the
screened interval of the aquifer
4
Activity Details
• the aquifer thickness was estimated to be the total depth of the monitoring well at each location
• the ratio of vertical to horizontal hydraulic conductivity was 0.1. AQTESOLV output results are provided in Appendix G.
Data Quality The data quality assessment methodology is summarised in Table 4 below. The data validation report is presented in Appendix F. Table 4 Data quality assessment methodology
Activity/Item Details Data quality analysis
Quality assurance and control measures were incorporated into the sampling and analysis work so that the data quality objectives could be achieved and to demonstrate accuracy, precision, comparability, representativeness, and completeness with regard to the data generated.
Data quality indicators
The data quality indicators adopted are based upon data validation guidance documents published by Standards Australia and the National Environment Protection Council. These include the Guide to the Investigation and Sampling of Sites with Potentially Contaminated Soil (AS 4482.1-2005), Schedule B2 Site Characterisation (NEPC 1999, amended 2013) and Schedule B3 Laboratory Analysis of Potentially Contaminated Soils (NEPC 1999, amended 2013). The process involves the checking of analytical procedure compliance and an assessment of the accuracy and precision of analytical data from a range of quality control measurements, generated from both the field sampling and analytical programs. Specific elements that have been checked and assessed for this project include: • preservation and storage of samples upon collection and during transport
to the laboratory • sample holding times • use of appropriate analytical and field sampling procedures • required limits of reporting • frequency of conducting quality control measurements • rinsate, field, and trip blank results • laboratory blank results • field duplicate and triplicate results • laboratory duplicate results • matrix spike results • surrogates spike results • the occurrence of apparently unusual or anomalous results, for example,
laboratory results that appear to be inconsistent with field observations or measurements.
Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
AECOM
DAppendix DBorelogs
0.30
2.80
4.00
CL
CL
CH
CLAY; Light brown, low plasticity, trace rootlets,no odour or staining.
CLAY; Grey with red and orange mottling, low tomedium plasticity, no odour or staining.
From 1.5m no orange mottling.
CLAY; Grey with red mottling, high plasticity,trace medium grained sub-rounded gravel(ironstone), no odour or staining.
Wet from 3.9m.
Borehole terminated at 4.0 mTarget depth reachedTotal Depth: 4.00 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
1.4
1.2
2.4
2.3
3.3
1.9
2.9
3.0
5.9
CPT000_MW02_100119_0.2
CPT000_MW02_100119_0.5
CPT000_MW02_100119_1.0
CPT000_MW02_100119_1.5
CPT000_MW02_100119_2.0
CPT000_MW02_100119_2.5
CPT000_MW02_100119_3.0
CPT000_MW02_100119_3.5
CPT000_MW02_100119_4.0
13.674 m AHD13.574 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0341306
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5759026
0.5 - 4.0
3.583 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
BOREHOLE LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 10 Jan 19
GW02
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.40
0.90
2.00
4.10
FILL
ML
CL
CH
FILL; Gravelly SAND; Brown, fine to mediumgrained sand, poorly sorted, medium to coarsegrained, sub-angular to sub-rounded gravel(construction concrete), trace roots, trace shellfragments, no odour or staining.
SILT; Brown, low plasticity, trace rootlets, noodour or staining.
CLAY; Brown to grey with orange mottling,medium plasticity, trace rootlets, no odour orstaining.
CLAY; Grey with light orange mottling, highplasticity, no odour or staining.
From 2.3m no mottling.
From 3.4m to 3.6m some orange mottling andsome fine to medium grained, sub-angular tosub-rounded red gravel (ironstone).
Wet from 3.9m.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
8.6
7.9
5.4
6.7
2.7
5.9
5.1
6.5
3.8
CPT000_MW03_100119_0.2
CPT000_MW03_100119_0.5
CPT000_MW03_100119_1.0
CPT000_MW03_100119_1.5
CPT000_MW03_100119_2.0
CPT000_MW03_100119_2.5
CPT000_MW03_100119_3.0
CPT000_MW03_100119_3.5
CPT000_MW03_100119_4.0
7.753 m AHD7.636 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0341196
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5759361
0.5 - 4.1
3.056 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
BOREHOLE LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 10 Jan 19
GW03
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.50
1.50
4.10
SW
CLS
SP
SAND; Light brown, fine grained, well sorted,trace rootlets, no odour or staining.
Sandy, Gravelly CLAY; Orange, low plasticity,30% fine to medium grained sand, poorly sorted,20% fine to medium grained gravel (ironstone),no odour or staining.
SAND; Orange with red mottling, fine to mediumgrained sand, poorly sorted, no odour orstaining.
From 2.6m becomes grey to light brown withorange and red mottling.
Wet from 3.0m.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
7.9
106.7
1.0
1.2
0.4
0.4
0.3
0.2
0.4
CPT040_MW04_080119_0.2
CPT040_MW04_080119_0.5
CPT040_MW04_080119_1.0
CPT040_MW04_080119_1.5
CPT040_MW04_080119_2.0
CPT040_MW04_080119_2.5
CPT040_MW04_080119_3.0
CPT040_MW04_080119_3.5
CPT040_MW04_080119_4.0
10.122 m AHD10.812 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0344249
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5763633
0.5 - 4.1
2.445 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
BOREHOLE LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 8 Jan 19
GW04
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.70
1.30
2.60
3.40
3.60
4.10
SP
CLS
SC
SW
CL
SP
SAND; Brown, fine to medium grained, poorlysorted, trace silt, trace rootlets, no odour orstaining.
Sandy CLAY; Grey with brown mottling, lowplasticity, 40% fine to medium grained sand,poorly sorted, no odour or staining.
Clayey SAND; Grey with brown mottling, fine tomedium grained, poorly sorted, 20% clay, noodour or staining.
Wet from 1.7m.
SAND; Grey, medium grained, well sorted, 5 -10% clay, no odour or staining.
CLAY; Grey, medium plasticity, trace finegrained sand, no odour or staining.
SAND; Grey, medium to coarse grained, poorlysorted, 5-10% clay, no odour or staining.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0.1
0
0.1
0.8
1.2
0.8
0.4
0.6
CPT000_MW05_080119_0.2
CPT000_MW05_080119_0.5
CPT000_MW05_080119_1.0
CPT000_MW05_080119_1.5
CPT000_MW05_080119_2.0
CPT000_MW05_080119_2.5
CPT000_MW05_080119_3.0
CPT000_MW05_080119_3.5
CPT000_MW05_080119_4.0
7.867 m AHD8.601 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0344642
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5763917
0.5 - 4.1
1.744 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
BOREHOLE LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 8 Jan 19
GW05
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.30
1.10
3.50
4.10
MLG
MLG
MLG
MLS
Gravelly SILT; Light brown, low plasticity, withfine to medium grained gravel, sub-angular tosub-rounded (ironstone) and 10% fine tomedium grained sand, no odour or staining.
Gravelly SILT; Brown, medium plasticity, withfine to medium grained gravel (ironstone),sub-angular to sub-rounded, no odour orstaining.
Gravelly SILT; Grey with red mottling, mediumplasticity, with fine to medium grained gravel(ironstone), sub-angular to sub-rounded, tracefine grained sand, no odour or staining.
Sandy SILT; Grey with some red mottling,medium plasticity, with 30% medium to coarsegrained quartz sand, no odour or staining.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0
0
0
CPT_MW01_061218_0.2
CPT_MW01_061218_0.5
CPT_MW01_061218_1.0
CPT_MW01_061218_2.0
CPT_MW01_061218_3.0
CPT_MW01_061218_4.0
6.594 m AHD7.375 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0343340
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5754526
0.5 - 4.1
3.799 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 6 Dec 18
MW01
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.50
0.90
2.00
4.10
CLS
CL
CH
CH
Sandy CLAY; Dark brown, low plasticity, with30% fine to medium grained sand, trace finegrained gravel, trace organic matter, tracerootlets, no odour or staining.
CLAY; Grey, low plasticity, with 10% fine tomedium grained sand, poorly sorted, no odouror staining.
CLAY; Grey with orange mottling, high plasticity,trace fine to medium grained sand, tracerootlets, no odour or staining.
From 1.4m orange mottling reducing.
CLAY; Grey, high plasticity, with 15% fine tomedium grained sand, poorly sorted, no odouror staining.Wet from 2.1m.
From 3.0m sand content increased to 25%
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0.1
0
0
CPT_MW02_051218_0.2
CPT_MW02_051218_0.5
CPT_MW02_051218_1.0
CPT_MW02_051218_2.0
CPT_MW02_051218_3.0
CPT_MW02_051218_4.0
5.348 m AHD5.231 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0341435
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5756412
0.5 - 4.1
1.288 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 5 Dec 18
MW02
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.90
2.00
3.50
3.60
4.10
ML
CL-ML
ML
GPS
ML
SILT; Brown, low plasticity, with rootlets, traceorganic matter, trace fine grained sand, noodour or staining.
Clayey SILT; Grey, with brown mottling, mediumplasticity, trace fine grained sand, no odour orstaining.
Wet from 1.9m.
SILT; Grey, medium plasticity, with 10% fine tomedium grained sand, no odour or staining.
From 2.7m Grey with orange mottling.
From 3.2m to 3.4m root system present.
Sandy Gravelly lens; Fine to medium grainedgravel (igneous origin), Sub-rounded torounded, with fine to medium grained sand, siltmatrix, no odour or staining.
SILT; Grey, medium plasticity, with 10% fine tomedium grained sand, no odour or staining.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0
0
0.1
CPT_MW03_051218_0.2
CPT_MW03_051218_0.5
CPT_MW03_051218_1.0
CPT_MW03_051218_2.0
CPT_MW03_051218_3.0
CPT_MW03_051218_4.0
3.522 m AHD3.408 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0341413
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5757021
0.5 - 4.1
3.311 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 5 Dec 18
MW03
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
2.40
4.10
ML
CH
SILT; Brown, low plasticity, no odour or staining.
From 0.9m brown with orange mottling.
From 1.6m orange.
At 2.0 trace fine grained sandstone gravel.From 2.0m to 2.4m highly weathered.At 2.2 trace fine grained sandstone gravel.
CLAY; Grey, high plasticity, no odour or staining.From 2.5m grey with increasing red and orangemottling.
From 3.8m grey.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0
0
0
CPT_MW04_051218_0.2
CPT_MW04_051218_0.5
CPT_MW04_051218_1.0
CPT_MW04_051218_2.0
CPT_MW04_051218_3.0
CPT_MW04_051218_4.0
8.135 m AHD7.992 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0341436
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
SANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5757532
0.5 - 4.1
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 5 Dec 18
MW04
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.80
3.00
4.40
TOPSOIL
CH
TOPSOIL: Sandy SILT; Brown, mediumplasticity, with 20% fine to medium grainedsand, trace rootlets, trace organic fines, noodour or staining.
From 0.5m sand reducing and silt increasing.
CLAY; Grey with some orange mottling, highplasticity, trace fine grained sand, trace rootlets,trace organic fines, no odour or staining.
Wet from 1.5m and increased mottling.
From 1.7m no mottling.
SILT; Grey, medium plasticity, trace fine grainedsands, no odour or staining.
Borehole terminated at 4.4m, target depthreached.Total Depth: 4.40 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0.1
0.1
0
0
0
0
CPT_MW05_041218_0.2
CPT_MW05_041218_0.5
CPT_MW05_041218_1.0
CPT_MW05_041218_2.0
CPT_MW05_041218_3.0
CPT_MW05_041218_4.0
6.899 m AHD6.791 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0341186
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5759815
0.5 - 4.4
1.190 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 4 Dec 18
MW05
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
4.2
4.4
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.20
2.80
4.70
FILL
CL
CH
FILL; Gravelly SAND; Light grey, fine to mediumgrained, poorly sorted, fine to medium grained,sub-angular to sub-rounded igneous gravel, noodour or staining.
CLAY; Dark grey with minor orange mottling,medium plasticity, trace rootlets, no odour orstaining.
From 1.5m increased mottling.
CLAY; Grey, high plasticity, trace fine to mediumgrained sand, trace rootlets, no odour orstaining.
At 3.7m becomes wet.
Borehole terminated at 4.7m, target depthreached.Total Depth: 4.70 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0.6
0.7
0.7
0.7
0.6
0.2
CPT_MW06_080119_0.2
CPT_MW06_080119_0.5
CPT_MW06_080119_1.0
CPT_MW06_080119_2.0
CPT_MW06_080119_3.0
CPT_MW06_080119_4.0
6.016 m AHD6.772 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0341590
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5761144
0.5 - 4.7
3.308 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 8 Jan 19
MW06
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
4.2
4.4
4.6
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.30
0.70
1.50
2.70
3.40
3.80
4.10
CLS
SC
CLS
SC
CH
CLG
GPS
Sandy CLAY; Brown, low plasticity, 30% fine tomedium grained sand, no odour or staining.
Clayey SAND; Light brown, fine to mediumgrained sand, low plasticity clay, trace finegrained, sub-rounded to rounded gravel(igneous), no odour or staining.
Sandy CLAY, Grey with red and orange mottling,medium plasticity, 30% fine to medium grainedsand, poorly sorted, no odour or staining.
Clayey SAND; Orange with red and greymottling, fine to medium grained sand, 20 - 30%low plasticity clay, no odour or staining.
CLAY; Grey, high plasticity, 10% fine to mediumgrained poorly sorted sand, no odour or staining.
Gravelly CLAY; Grey with orange mottling, lowplasticity, fine to medium grained, sub-angular toangular gravel (ironstone) lenses at 3.4 - 3.6 mand 3.7 - 3.8 m, no odour or staining.
Wet from 3.8m.
Sandy CLAY; Grey with orange mottling, highplasticity, 20% fine to medium grained, poorlysorted sand, no odour or staining.Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0
0
0
CPT_MW07_181218_0.2
CPT_MW07_181218_0.5
CPT_MW07_181218_1.0
CPT_MW07_181218_2.0
CPT_MW07_181218_3.4
CPT_MW07_181218_4.0
10.974 m AHD11.575 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0343971
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5763584
0.5 - 4.1
2.599 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 18 Dec 18
MW07
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.20
0.80
1.30
3.00
4.10
FILL
FILL
FILL
CL
CLS
FILL; Gravelly SAND; Dark Brown, fine tomedium grained sand, poorly sorted, fine tomedium grained sub-angular to angular gravel(igneous), trace roots, trace organic matter, noodour or staining.
FILL; SAND; Grey, fine to medium grained sand,poorly sorted, no odour or staining.
FILL; SAND; Light brown to brown, fine tomedium grained sand, poorly sorted, no odouror staining.
At 1.3m broken concrete at base of fill.
CLAY; Grey with orange mottling, 10-15% fine tomedium grained sand, no odour or staining.
Wet from 3.0m.Sandy CLAY; Grey, medium plasticity, 30% fineto coarse grained sand, poorly sorted, trace verycoarse sand, no odour or staining.
At 3.3 - 3.35m red with orange mottling.From 3.4m increases to coarse grained sand.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
5
6.8
9.5
4.4
12.9
13.9
CPT_MW08_100119_0.2
CPT_MW08_100119_0.5
CPT_MW08_100119_1.0
CPT_MW08_100119_2.0
CPT_MW08_100119_3.0
CPT_MW08_100119_4.0
8.509 m AHD8.382 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0345437
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5765756
0.5 - 4.1
3.275 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 10 Jan 19
MW08
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.20
1.90
2.40
3.40
4.10
MLS
CH
CLS
SC
SC
Sandy SILT; Black, low plasticity, 30% fine tomedium grained, poorly sorted sand, tracerootlets, trace organic matter, no odour orstaining.
CLAY; Grey with orange mottling, highplasticity, 10% medium to coarse grained sand,no odour or staining.
Wet from 1.9m.
Sandy CLAY, Grey with orange mottling,medium plasticity, 30 - 40% coarse grainedsand, well sorted, no odour or staining.
Sandy CLAY, Grey, medium plasticity, 30 - 40%fine grained sand, well sorted, no odour orstaining.From 2.5 - 3.0m black, high plasticity withvertical dry streak.
From 3.1 - 3.15m coarse sand.
Clayey SAND; grey, coarse grained, well sorted,20% clay, no odour or staining.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0
0
0
CPT_MW09_171218_0.2
CPT_MW09_171218_0.5
CPT_MW09_171218_1.0
CPT_MW09_171218_2.0
CPT_MW09_171218_3.0
CPT_MW09_171218_4.0
3.341 m AHD3.203 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0346159
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5766252
0.5 - 4.1
1.346 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 17 Dec 18
MW09
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.50
2.50
2.80
4.10
SM
CLS
SP-SC
CLS
Silty SAND; Brown, fine to medium grained sandwith 30-40% silt, trace rootlets, no odour orstaining.
Sandy CLAY; Grey with orange mottling, highplasticity with 20% medium grained sand, noodour or staining.
Wet from 1.6m and sand increases to 30%.
From 2.0m sand reduced back to 20%.
Clayey SAND; Grey, fine to medium grained,poorly sorted, with 30% medium plasticity clay,no odour or staining.
Sandy CLAY; Grey, high plasticity, with 10-20%fine to medium grained sand, no odour orstaining.
From 3.5m red mottling present.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
00
0
0
BH10_031218_0.2
BH10_031218_0.5
BH10_031218_1.0
BH10_031218_2.5
QC100_031218
BH10_031218_3.0
BH10_031218_4.0
2.809 m AHD2.708 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0346555
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5767387
0.5 - 4.1
1.790 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 3 Dec 18
MW10
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.20
0.90
4.10
CL
CL
CH
CLAY; Light brown, low plasticity, trace rootlets,no odour or staining.
CLAY; Brown with orange mottling, mediumplasticity, trace rootlets, no odour or staining.
CLAY; Grey with orange mottling, high plasticity,15% fine to medium grained sand, trace verycoarse grained quartz grains, no odours orstaining.
Wet from 2.1 m.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0.6
0.8
0.5
0.6
0.6
0.6
CPT_MW11_090119_0.2QC101
CPT_MW11_090119_0.5
CPT_MW11_090119_1.0
CPT_MW11_090119_2.0
CPT_MW11_090119_3.0
CPT_MW11_090119_4.0
3.645 m AHD3.530 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0346924
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5768887
0.5 - 4.1
2.823 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 9 Jan 19
MW11
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.90
2.40
4.10
ML
ML
CL-CH
SILT; Brown, low plasticity, with 10% fine tomedium grained sand, trace rootlets, traceorganic matter, trace fine grained roundedgravel, no odour or staining.
SILT; Grey with orange and red mottling,medium plasticity, with trace fine to mediumgrained sand, trace fine grained, rounded gravel(ironstone), no odour or staining.
CLAY; Orange with red mottling, some blackclay throughout, medium plasticity, with 10-15%fine grained sub-angular to sub-rounded gravel(ironstone), no odour or staining.
From 3.0m to 3.2m grey with orange mottling.
From 3.3m to 3.35m medium grained ironstonegravel.
Wet from 3.6m.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0
0
0
CPT_MW12_071218_0.2
CPT_MW12_071218_0.5
CPT_MW12_071218_1.0
CPT_MW12_071218_2.0
CPT_MW12_071218_3.0
CPT_MW12_071218_4.0
3.607 m AHD4.367 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0349988
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5770187
0.5 - 4.1
3.225 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 7 Dec 18
MW12
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
1.00
1.90
4.10
ML
MLS
ML
SILT; Light brown, low plasticity, trace rootlets,trace organic matter, no odour or staining.
From 0.9m orange mottling.
Sandy SILT; Grey with orange mottling, mediumplasticity, with 40% medium to coarse grainedsand, poorly sorted, no odour or staining.
SILT; Light grey with orange mottling, highplasticity, trace fine to medium grained sand, noodour or staining.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0
0
0
CPT_MW13_061218_0.2
CPT_MW13_061218_0.5
CPT_MW13_061218_1.0
CPT_MW13_061218_2.0
CPT_MW13_061218_3.0
CPT_MW13_061218_4.0
4.622 m AHD5.323 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0352027
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5770846
0.5 - 4.1
2.222 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 7 Dec 18
MW13
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.80
4.20
CL-CH
CH
CLAY; Dark Grey, medium plasticity, tracerootlets near the surface, no odour or staining.
CLAY; Dark grey with orange mottling, mediumplasticity, no odour or staining.
Wet from 1.4m.
From 1.7m and fine to medium grained sandlens (30mm), orange, 30-40% silt.From 1.8m dark grey with orange mottling.
From 3.0m dark grey, no mottling.
From 3.3m dark grey with orange mottling.
Borehole terminated at 4.2m, target depthreached.Total Depth: 4.20 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0.1
0.1
0.1
0.1
0.1
0.1
0.1
CPT_BH14_031218_0.2
CPT_BH14_031218_0.5
CPT_BH14_031218_1.0
CPT_BH14_031218_1.5
CPT_BH14_031218_2.0
CPT_BH14_031218_2.5
CPT_BH14_031218_3.0
CPT_BH14_031218_3.5
CPT_BH14_031218_4.0
4.116 m AHD4.876 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0354166
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5771533
0.5 - 4.2
2.130 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 3 Dec 18
MW14
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
4.2
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.20
0.90
3.70
4.10
CLS
CH
CH
CLS
Sandy CLAY; Dark brown, low plasticity, 30%fine to medium grained sand, poorly sorted,trace rootlets, no odour or staining.
CLAY; Black, high plasticity, 10% fine tomedium grained sand, poorly sorted, tracerootlets, no odour or staining.
CLAY; Grey with orange mottling, high plasticity,10% fine to medium grained sand, poorly sorted,trace rootlets, no odour or staining.
From 2.0m sand content increases to 15 -20%.
From 2.2m to 3.2m some black clay.
Wet from 2.5m.
Sandy CLAY; Grey with orange mottling, 30%fine to medium grained sand, poorly sorted, noodour or staining.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0.1
0.1
0.3
0.2
0.1
0.1
CPT_MW15_090119_0.2
CPT_MW15_090119_0.5QC201
CPT_MW15_090119_1.0
CPT_MW15_090119_2.0
CPT_MW15_090119_3.0
CPT_MW15_090119_4.0
3.675 m AHD3.578 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0355209
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5772126
0.5 - 4.1
2.046 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 9 Jan 19
MW15
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.20
0.90
4.10
CL
CL
CH
CLAY; Brown, low plasticity, with roots androotlets, trace fine sand, no odour or staining.
CLAY; Black, medium plasticity, trace finegrained sand, trace rootlets, no odour orstaining.
CLAY; Black, high plasticity, trace fine grainedsand, no odour or staining.
From 2.0m dark grey with orange mottling.
Wet from 2.5m.
From 3.45m to 3.65m some black mottling.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0.6
0.3
0.4
0.3
0.1
0.2
CPT_MW16_090119_0.2
CPT_MW16_090119_0.5
CPT_MW16_090119_1.0
CPT_MW16_090119_2.0
CPT_MW16_090119_3.0
CPT_MW16_090119_4.0
3.948 m AHD3.805 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0357520
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5774095
0.5 - 4.1
3.710 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 9 Jan 19
MW16
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
1.30
4.10
CL
CH
CLAY; Black, low plasticity, trace rootlets, traceorganic matter, no odour or staining.
From 0.2m medium plasticity.
CLAY; Dark grey with brown and light brownmottling, high plasticity, trace rootlets, tracemedium grained sand, no odour or staining.
From 3.8 m increase in brown mottling.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
6.4
10.4
9.6
4.3
7.0
12.7
CPT_MW17_110119_0.2
CPT_MW17_110119_0.5
CPT_MW17_110119_1.0
CPT_MW17_110119_2.0
CPT_MW17_110119_3.0
CPT_MW17_110119_4.0
2.941 m AHD2.895 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0361197
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
SANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5775448
0.5 - 4.1
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 11 Jan 19
MW17
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
4.10
CH CLAY; Black, high plasticity, with 20% roots andorganic matter, no odour or staining.
From 0.5 roots and organic matter reduced to5%.
From 1.3m becoming dark grey with blackmottling.
Wet from 1.8m.
From 2.8m brown.
From 3.3m light grey with black mottling.
From 3.5m light grey with brown mottling.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0.2
0.1
0.3
CPT_MW18_041218_0.2
CPT_MW18_041218_0.5
CPT_MW18_041218_1.0
CPT_MW18_041218_2.0
CPT_MW18_041218_3.0
CPT_MW18_041218_4.0CPT_QC200_041218
3.009 m AHD3.925 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0363862
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5776003
0.5 - 4.1
3.918 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 4 Dec 18
MW18
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.50
1.00
6.00
ML
CH
CH
SILT; Black, medium plasticity, trace finegrained sub-rounded gravel, trace fine grainedsand, trace organic matter, trace rootlets, noodour or staining.
CLAY; Black, high plasticity, trace fine tomedium grained sand, trace rootlets, no odouror staining.
Wet from 0.9m
CLAY; Grey with some brown mottling, highplasticity, no odour or staining.
From 3.0m brown mottling increasing.
From 3.5m trace coarse grained sands.
Borehole terminated at 6.0m, target depthexceeded.
Total Depth: 6.00 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0.9
0.1
0
0
0
CPT_MW19_041218_0.2
CPT_MW19_041218_0.5
CPT_MW19_041218_1.0
CPT_MW19_041218_2.0
CPT_MW19_041218_3.0
CPT_MW19_041218_4.0
4.162 m AHD4.911 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0366161.07
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
SANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5777843.05
0.5 - 6.0
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 4 Dec 18
MW19
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
4.2
4.4
4.6
4.8
5.0
5.2
5.4
5.6
5.8
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
Gravel Packand fallback
0.30
4.10
CL
CH
CLAY; Dark brown, low to medium plasticity,10-20% rootlets and organic matter, no odour orstaining.
CLAY; grey with brown mottling, high plasticity,trace rootlets to 0.5m, no odour or staining.
Wet from 1.2m.
From 2.2m some light green staining.
From 3.1m grey.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0
0
0
CPT_MW21_171218_0.2
CPT_MW21_171218_0.5
CPT_MW21_171218_1.0
CPT_MW21_171218_2.0
CPT_MW21_171218_3.0
CPT_MW21_171218_4.0
17.716 m AHD17.626 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0370781
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5782683
0.5 - 4.1
0.968 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 17 Dec 18
MW21
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.30
0.90
2.80
3.40
4.10
ML
CH
CH
CH
CLG
SILT; Dark brown, low plasticity with 20%organic matter and rootlets, trace fine grainedsand, no odour or staining.
CLAY; Brown, high plasticity, trace organicmatter, trace coarse grained sand, no odour orstaining.
CLAY; Grey with orange mottling, high plasticity,trace coarse grained sand, no odour or staining.
Wet from 1.5m.
From 2.6m to 2.65m - medium to coarse grainedsand, highly weathered.
CLAY; Grey, high plasticity with trace coarsegrained sand, no odour or staining.
At 3.06 small medium to coarse grained sandlens.
Gravelly CLAY; Grey with orange mottling,medium plasticity, with 30% fine to mediumgrained gravel (ironstone), rounded.From 3.6-3.65 highly weathered coarse grainedgravel (ironstone).At 3.78 highly weathered coarse grained gravel.At 3.9 highly weathered coarse grained gravel.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0
0
0
CPT_MW20_061218_0.2
CPT_MW20_061218_0.5
CPT_MW20_061218_1.0
CPT_MW20_061218_2.0
CPT_MW20_061218_3.0
CPT_MW20_061218_4.0
24.001 m AHD23.902 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0372239
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
STABILISED WATER LEVELSANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5784161
0.5 - 4.1
0.896 m BGL
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 6 Dec 18
MW22
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
0.20
0.80
1.40
2.10
2.20
3.90
4.10
SP
SPG
SPG
ML
GW
SM
SP
SAND; Brown, fine to medium grained sand,trace silt, trace organic matter, trace rootlets, noodour or staining.
Gravelly SAND; Grey, fine to medium grained,20% sub-angular to sub-rounded sandstone, noodour or staining.
Gravelly SAND; Brown, fine to medium grained,40% medium to coarse grained, sub-angular tosub-rounded weathered sandstone, no odour orstaining.
SILT; Grey with orange mottling, low plasticitywith trace fine grained, sub-angular tosub-rounded ironstone gravel (ironstone), tracefine to medium grained sand, trace rootlets, noodour or staining.
GRAVEL; Brown, fine to medium grained,sub-angular to sub-rounded gravel (ironstone),trace silt, no odour or staining.
Silty SAND; Grey with orange mottling, fine tomedium grained sand, 30% silt, no odour orstaining.
From 3.2m grey with no mottling.
From 3.9m trace silt.
Borehole terminated at 4.1m, target depthreached.Total Depth: 4.10 m
Gatic CoverCement Grout
Bentonite
Stand Pipe
Gravel Pack
2mm SlottedScreen
0
0
0
0
0
0
CPT_MW23_181218_0.2
CPT_MW23_181218_0.5
CPT_MW23_181218_1.0
CPT_MW23_181218_2.0
CPT_MW23_181218_3.0
CPT_MW23_181218_4.0
14.860 m AHD15.463 m AHD
NORTHING
1.0 - 4.0Grab
COMMENTS
TOP OF CASING (TOC)SURFACE ELEVATION
0.0 - 1.0343397
Push Tube followed by Solid Stem Auger
LOGGED BY0.0 - 0.5
GRAVEL PACKSCREENBLANK
SANITARY SEAL/BENTONITE
SAMPLING METHODDRILLING METHOD
EASTING5762421
0.5 - 4.1
CO
NT
AC
TD
EP
TH
WELL DIAGRAM
RE
CO
VE
RY
PID
(p
pm
)
AN
AL
YS
ED
DE
PT
H(m
BG
L)
US
CS
CL
AS
S
LITHOLOGIC DESCRIPTION
SA
MP
LE
NU
MB
ER
GR
AP
HIC
LO
G
MONITORING WELL LOG
DATE
Crib Point to PakenhamGIJPP Groundwater Study
PROJECT NUMBER 18 Dec 18
MW23
60592634
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
2.4
2.6
2.8
3.0
3.2
3.4
3.6
3.8
4.0
LOCATIONPROJECT NAME
PAGE 1 OF 1
AECOM Australia Pty Ltd
Level 11, Tower 2, 727 Collins Street
Docklands, VIC 3008
GIJ
PP
BO
RE
LO
GS
.GP
J 8
/2/1
9
Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
AECOM
EAppendix ERising head tests
Clie
nt N
ame:
AG
L W
hole
sale
Gas
Ltd
and
APA
Tra
nsm
issi
on P
ty L
tdPr
ojec
t Nam
e: G
IJPP
EES
Gro
undw
ater
Tec
hnic
al R
epor
t
Tabl
e E1
. Hyd
raul
ic C
ondu
ctiv
ity S
umm
ary
Tabl
e
CPT
IDW
ell I
DD
ate
Scre
ened
Lith
olog
y Te
sted
Tota
lD
epth
(mbT
OC
)
SWL
(mbT
OC
)
Hei
ght o
f Wat
erC
olum
n(m
)
K - m
id ti
me
(m/d
ay)
K - l
ate
time
(m/d
ay)
K - B
utle
r*(m
/day
)K
- mid
tim
e(m
/sec
)K
- lat
e tim
e(m
/sec
)K
- But
ler*
(m/s
ec)
CPT
022_
MW
05M
W05
21/0
1/20
19C
LAY
and
SILT
4.00
1.14
52.
855
1.4E
-02
3.7E
-03
1.4E
-02
1.7E
-07
4.3E
-08
1.7E
-07
CPT
040_
B_M
W07
MW
0722
/01/
2019
CLA
Y/Sa
ndy
CLA
Y/G
rave
lly C
LAY
4.70
3.08
01.
620
5.8E
-04
2.6E
-04
2.6E
-04
6.7E
-09
3.0E
-09
6.7E
-09
CPT
040_
B__G
W04
GW
0422
/01/
2019
SAN
D4.
873.
114
1.75
69.
7E-0
34.
0E-0
39.
7E-0
31.
1E-0
74.
6E-0
81.
1E-0
7C
PT04
5_G
W05
GW
0522
/01/
2019
Cla
yey
SAN
D4.
812.
415
2.39
51.
6E-0
26.
8E-0
31.
6E-0
21.
9E-0
77.
8E-0
81.
9E-0
7C
PT00
0_M
W08
MW
0822
/01/
2019
Sand
y C
LAY
3.90
3.29
90.
601
2.5E
-03
-2.
5E-0
32.
9E-0
82.
9E-0
8C
PT05
1_M
W09
MW
0922
/01/
2019
3.96
1.37
62.
584
6.6E
-02
3.1E
-02
6.6E
-02
7.6E
-07
3.5E
-07
7.6E
-07
CPT
051_
MW
09M
W09
22/0
1/20
193.
961.
383
2.57
78.
9E-0
27.
5E-0
28.
9E-0
21.
0E-0
68.
7E-0
71.
0E-0
6C
PT05
5_M
W10
MW
10**
23/0
1/20
193.
981.
820
2.16
02.
6E-0
11.
0E-0
12.
6E-0
13.
0E-0
61.
2E-0
63.
0E-0
6C
PT05
5_M
W10
MW
1023
/01/
2019
3.98
1.82
22.
158
3.2E
-01
2.5E
-01
3.2E
-01
3.7E
-06
2.9E
-06
3.7E
-06
CPT
000_
MW
11M
W11
21/0
1/20
19C
LAY
4.00
2.88
01.
120
1.4E
-03
1.8E
-03
1.8E
-03
1.6E
-08
2.1E
-08
CPT
037_
B_M
W14
MW
1423
/01/
2019
CLA
Y4.
812.
922
1.88
82.
8E-0
3-
2.8E
-03
3.3E
-08
3.3E
-08
CPT
000_
MW
15M
W15
24/0
1/20
19C
LAY
4.00
2.11
21.
888
3.7E
-03
2.6E
-03
-4.
3E-0
8-
CPT
129_
MW
21M
W21
24/0
1/20
19C
LAY
3.78
1.05
52.
725
4.6E
-03
2.0E
-03
2.0E
-03
5.4E
-08
2.4E
-08
2.4E
-08
CPT
134_
MW
22M
W22
24/0
1/20
19C
LAY
3.97
0.93
03.
040
7.1E
-03
1.4E
-03
7.1E
-03
8.3E
-08
1.6E
-08
8.3E
-08
Stat
istic
sM
inim
um5.
8E-0
42.
6E-0
42.
6E-0
46.
7E-0
93.
0E-0
96.
7E-0
9M
axim
um3.
2E-0
12.
5E-0
13.
2E-0
13.
7E-0
62.
9E-0
63.
7E-0
6G
eom
etric
Mea
n7.
6E-0
34.
4E-0
37.
2E-0
38.
8E-0
86.
1E-0
89.
0E-0
8Bu
tler*
- K
est
imat
ed a
cros
s Bu
tler's
reco
mm
ende
d he
ad ra
nge
** -
Ris
ing
head
test
s ex
cept
firs
t MW
10 re
sult
bein
g fa
lling
hea
d te
stAn
alys
is -
Bou
wer
-Ric
e U
ncon
fined
NB:
Tes
ts w
ere
com
plet
ed o
n M
W01
, MW
02 a
nd M
W03
- no
resu
lts d
eter
min
ed d
ue to
insu
ffici
ent w
ater
leve
l dis
plac
emen
t for
test
Sand
y C
LAY/
Cla
yey
SAN
D
Sand
y C
LAY
Rev
isio
n 01
10
Jan
uary
201
9P:
\605
X\60
5926
34\6
. Dra
ft D
ocs\
6.1
Rep
orts
\6.1
.2_T
echn
ical
repo
rts\A
pp X
X_G
roun
dwat
er\A
pp G
- R
isin
g H
ead
Test
s C
OM
PLET
E - C
HAN
GE
TO N
EW A
pp E
\Tab
le G
1 G
IJPP
RH
T Su
mm
ary_
v2.x
lsx
Page
1 o
f 1Pr
int D
ate:
26/
04/2
019
0. 2.4E+3 4.8E+3 7.2E+3 9.6E+3 1.2E+40.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW05 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW05 v2.aqtDate: 02/24/19 Time: 07:09:01
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW05Test Date: 21/01/19
AQUIFER DATA
Saturated Thickness: 2.855 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW05)
Initial Displacement: 0.49 m Static Water Column Height: 2.855 mTotal Well Penetration Depth: 2.855 m Screen Length: 2.855 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.003707 m/day y0 = 0.1061 m
0. 2.4E+3 4.8E+3 7.2E+3 9.6E+3 1.2E+40.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW05 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW05 v2.aqtDate: 02/24/19 Time: 07:08:36
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW05Test Date: 21/01/19
AQUIFER DATA
Saturated Thickness: 2.855 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW05)
Initial Displacement: 0.49 m Static Water Column Height: 2.855 mTotal Well Penetration Depth: 2.855 m Screen Length: 2.855 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.01433 m/day y0 = 0.1646 m
0. 2.0E+4 4.0E+4 6.0E+4 8.0E+4 1.0E+50.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW07 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW07 v2.aqtDate: 02/24/19 Time: 07:11:32
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW07Test Date: 22/01/2019
AQUIFER DATA
Saturated Thickness: 1.62 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW07)
Initial Displacement: 0.49 m Static Water Column Height: 1.62 mTotal Well Penetration Depth: 1.62 m Screen Length: 1.62 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.0002552 m/day y0 = 0.1576 m
0. 2.0E+4 4.0E+4 6.0E+4 8.0E+4 1.0E+50.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW07 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW07 v2.aqtDate: 02/24/19 Time: 07:10:59
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW07Test Date: 22/01/2019
AQUIFER DATA
Saturated Thickness: 1.62 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW07)
Initial Displacement: 0.49 m Static Water Column Height: 1.62 mTotal Well Penetration Depth: 1.62 m Screen Length: 1.62 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.0005831 m/day y0 = 0.1737 m
0. 2.0E+3 4.0E+3 6.0E+3 8.0E+3 1.0E+40.01
0.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
GW04 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\GW04 v2.aqtDate: 02/24/19 Time: 12:25:16
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: GW04Test Date: 22/01/19
AQUIFER DATA
Saturated Thickness: 1.756 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (GW04)
Initial Displacement: 0.49 m Static Water Column Height: 1.756 mTotal Well Penetration Depth: 1.756 m Screen Length: 1.756 mCasing Radius: 0.025 m Well Radius: 0.025 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.004005 m/day y0 = 0.1106 m
0. 1.2E+3 2.4E+3 3.6E+3 4.8E+3 6.0E+30.01
0.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
GW04 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\GW04 v2.aqtDate: 02/24/19 Time: 12:22:39
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: GW04Test Date: 22/01/19
AQUIFER DATA
Saturated Thickness: 1.756 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (GW04)
Initial Displacement: 0.49 m Static Water Column Height: 1.756 mTotal Well Penetration Depth: 1.756 m Screen Length: 1.756 mCasing Radius: 0.025 m Well Radius: 0.025 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.009695 m/day y0 = 0.1559 m
0. 2.4E+3 4.8E+3 7.2E+3 9.6E+3 1.2E+40.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
GW05 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\GW05 v2.aqtDate: 02/24/19 Time: 07:07:00
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: GW05Test Date: 22/01/19
AQUIFER DATA
Saturated Thickness: 2.395 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (GW05)
Initial Displacement: 0.49 m Static Water Column Height: 2.395 mTotal Well Penetration Depth: 2.395 m Screen Length: 2.395 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.006755 m/day y0 = 0.1175 m
0. 1.6E+3 3.2E+3 4.8E+3 6.4E+3 8.0E+30.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
GW05 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\GW05 v2.aqtDate: 02/24/19 Time: 07:04:36
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: GW05Test Date: 22/01/19
AQUIFER DATA
Saturated Thickness: 2.395 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (GW05)
Initial Displacement: 0.49 m Static Water Column Height: 2.395 mTotal Well Penetration Depth: 2.395 m Screen Length: 2.395 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.01647 m/day y0 = 0.1628 m
0. 1.2E+4 2.4E+4 3.6E+4 4.8E+4 6.0E+40.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW08 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW08 v2.aqtDate: 02/24/19 Time: 11:39:17
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW8Test Date: 21/01/19
AQUIFER DATA
Saturated Thickness: 0.601 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW08)
Initial Displacement: 0.27 m Static Water Column Height: 0.601 mTotal Well Penetration Depth: 0.601 m Screen Length: 0.601 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.002502 m/day y0 = 0.08958 m
0. 1000. 2.0E+3 3.0E+3 4.0E+3 5.0E+30.01
0.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW09 RISING HEAD TEST 1
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW09_1 v2.aqtDate: 02/24/19 Time: 11:43:46
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW09Test Date: 22/01/19
AQUIFER DATA
Saturated Thickness: 2.584 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW09)
Initial Displacement: 0.49 m Static Water Column Height: 2.584 mTotal Well Penetration Depth: 2.584 m Screen Length: 2.584 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.03057 m/day y0 = 0.1117 m
0. 1000. 2.0E+3 3.0E+3 4.0E+3 5.0E+30.01
0.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW09 RISING HEAD TEST 1
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW09_1 v2.aqtDate: 02/24/19 Time: 11:43:11
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW09Test Date: 22/01/19
AQUIFER DATA
Saturated Thickness: 2.584 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW09)
Initial Displacement: 0.49 m Static Water Column Height: 2.584 mTotal Well Penetration Depth: 2.584 m Screen Length: 2.584 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.06564 m/day y0 = 0.1654 m
0. 800. 1.6E+3 2.4E+3 3.2E+3 4.0E+30.01
0.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW09 RISING HEAD TEST 2
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW09_2 v2.aqtDate: 02/24/19 Time: 11:46:58
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW09Test Date: 22/01/19
AQUIFER DATA
Saturated Thickness: 2.577 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW09)
Initial Displacement: 0.49 m Static Water Column Height: 2.577 mTotal Well Penetration Depth: 2.577 m Screen Length: 2.577 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.07516 m/day y0 = 0.1434 m
0. 800. 1.6E+3 2.4E+3 3.2E+3 4.0E+30.01
0.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW09 RISING HEAD TEST 2
Data Set: C:\Users .AU\Documents\Crib Point\slug tests\Aqtesolv\MW09_2 v2.aqtDate: 02/24/19 Time: 11:46:40
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW09Test Date: 22/01/19
AQUIFER DATA
Saturated Thickness: 2.577 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW09)
Initial Displacement: 0.49 m Static Water Column Height: 2.577 mTotal Well Penetration Depth: 2.577 m Screen Length: 2.577 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.08889 m/day y0 = 0.1709 m
0. 800. 1.6E+3 2.4E+3 3.2E+3 4.0E+30.001
0.01
0.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW10 FALLING HEAD TEST 1
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW10_1 v2.aqtDate: 02/24/19 Time: 11:54:34
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW10Test Date: 23/01/19
AQUIFER DATA
Saturated Thickness: 2.16 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW10)
Initial Displacement: 0.49 m Static Water Column Height: 2.16 mTotal Well Penetration Depth: 2.16 m Screen Length: 2.16 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.1022 m/day y0 = 0.05146 m
0. 800. 1.6E+3 2.4E+3 3.2E+3 4.0E+30.001
0.01
0.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW10 FALLING HEAD TEST 1
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW10_1 v2.aqtDate: 02/24/19 Time: 11:54:06
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW10Test Date: 23/01/19
AQUIFER DATA
Saturated Thickness: 2.16 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW10)
Initial Displacement: 0.49 m Static Water Column Height: 2.16 mTotal Well Penetration Depth: 2.16 m Screen Length: 2.16 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.2626 m/day y0 = 0.1337 m
0. 400. 800. 1.2E+3 1.6E+3 2.0E+31.0E-4
0.001
0.01
0.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW10 FALLING HEAD TEST 2
Data Set: C:\Users .AU\Documents\Crib Point\slug tests\Aqtesolv\MW10_2 v2.aqtDate: 02/24/19 Time: 11:58:11
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW10Test Date: 23/01/19
AQUIFER DATA
Saturated Thickness: 2.158 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW10)
Initial Displacement: 0.49 m Static Water Column Height: 2.158 mTotal Well Penetration Depth: 2.158 m Screen Length: 2.158 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.2495 m/day y0 = 0.1033 m
0. 400. 800. 1.2E+3 1.6E+3 2.0E+31.0E-4
0.001
0.01
0.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW10 RISING HEAD TEST
Data Set: P:\...\ 10_2 v2.aqtDate: 04/26/19 Time: 12:24:41
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW10Test Date: 23/01/19
AQUIFER DATA
Saturated Thickness: 2.158 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW10)
Initial Displacement: 0.49 m Static Water Column Height: 2.158 mTotal Well Penetration Depth: 2.158 m Screen Length: 2.158 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.3173 m/day y0 = 0.1417 m
0. 1.4E+4 2.8E+4 4.2E+4 5.6E+4 7.0E+40.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW11 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW11 v2.aqtDate: 02/24/19 Time: 13:27:27
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW11Test Date: 21/01/19
AQUIFER DATA
Saturated Thickness: 1.12 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW11)
Initial Displacement: 0.25 m Static Water Column Height: 1.12 mTotal Well Penetration Depth: 1.12 m Screen Length: 1.12 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.001847 m/day y0 = 0.1476 m
0. 600. 1.2E+3 1.8E+3 2.4E+3 3.0E+30.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW11 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW11 v2 manual.aqtDate: 02/24/19 Time: 12:52:41
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW11Test Date: 21/01/19
AQUIFER DATA
Saturated Thickness: 1.12 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW11)
Initial Displacement: 0.25 m Static Water Column Height: 1.12 mTotal Well Penetration Depth: 1.12 m Screen Length: 1.12 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.004118 m/day y0 = 0.1124 m
0. 1.6E+4 3.2E+4 4.8E+4 6.4E+4 8.0E+40.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW11 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW11 v2.aqtDate: 02/24/19 Time: 12:01:32
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW11Test Date: 21/01/19
AQUIFER DATA
Saturated Thickness: 1.12 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW11)
Initial Displacement: 0.25 m Static Water Column Height: 1.12 mTotal Well Penetration Depth: 1.12 m Screen Length: 1.12 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.001399 m/day y0 = 0.1272 m
0. 600. 1.2E+3 1.8E+3 2.4E+3 3.0E+30.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW14 RISING HEAD TEST - MANUAL DATA
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW14 manual v2.aqtDate: 02/24/19 Time: 12:04:46
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW14Test Date: 23/01/19
AQUIFER DATA
Saturated Thickness: 1.888 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW14)
Initial Displacement: 0.49 m Static Water Column Height: 1.888 mTotal Well Penetration Depth: 1.888 m Screen Length: 1.888 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.002823 m/day y0 = 0.1465 m
0. 800. 1.6E+3 2.4E+3 3.2E+3 4.0E+30.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW15 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW15 v2.aqtDate: 02/24/19 Time: 12:08:38
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW15Test Date: 24/01/19
AQUIFER DATA
Saturated Thickness: 1.888 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW15)
Initial Displacement: 0.49 m Static Water Column Height: 1.888 mTotal Well Penetration Depth: 1.888 m Screen Length: 1.888 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.002606 m/day y0 = 0.1925 m
0. 800. 1.6E+3 2.4E+3 3.2E+3 4.0E+30.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW15 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW15 v2.aqtDate: 02/24/19 Time: 12:07:47
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW15Test Date: 24/01/19
AQUIFER DATA
Saturated Thickness: 1.888 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW15)
Initial Displacement: 0.49 m Static Water Column Height: 1.888 mTotal Well Penetration Depth: 1.888 m Screen Length: 1.888 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.003729 m/day y0 = 0.1949 m
0. 3.2E+3 6.4E+3 9.6E+3 1.28E+4 1.6E+40.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW21 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW21 v2.aqtDate: 02/24/19 Time: 12:14:21
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW21Test Date: 24/01/19
AQUIFER DATA
Saturated Thickness: 2.725 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW21)
Initial Displacement: 0.49 m Static Water Column Height: 2.725 mTotal Well Penetration Depth: 2.725 m Screen Length: 2.725 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.002045 m/day y0 = 0.1662 m
0. 3.2E+3 6.4E+3 9.6E+3 1.28E+4 1.6E+40.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW21 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW21 v2.aqtDate: 02/24/19 Time: 12:14:01
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW21Test Date: 24/01/19
AQUIFER DATA
Saturated Thickness: 2.725 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW21)
Initial Displacement: 0.49 m Static Water Column Height: 2.725 mTotal Well Penetration Depth: 2.725 m Screen Length: 2.725 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.004633 m/day y0 = 0.1823 m
0. 3.2E+3 6.4E+3 9.6E+3 1.28E+4 1.6E+40.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW22 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW22 v2.aqtDate: 02/24/19 Time: 12:19:45
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW22Test Date: 24/01/2019
AQUIFER DATA
Saturated Thickness: 3.07 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW22)
Initial Displacement: 0.49 m Static Water Column Height: 3.07 mTotal Well Penetration Depth: 3.07 m Screen Length: 3.07 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.001393 m/day y0 = 0.111 m
0. 3.2E+3 6.4E+3 9.6E+3 1.28E+4 1.6E+40.1
1.
Time (sec)
Nor
mal
ized
Hea
d (m
/m)
MW22 RISING HEAD TEST
Data Set: C:\Users\ .AU\Documents\Crib Point\slug tests\Aqtesolv\MW22 v2.aqtDate: 02/24/19 Time: 12:19:19
PROJECT INFORMATION
Company: AECOM Australia Pty LtdClient: APA GroupProject: 60592634Location: Western PortTest Well: MW22Test Date: 24/01/2019
AQUIFER DATA
Saturated Thickness: 3.07 m Anisotropy Ratio (Kz/Kr): 0.1
WELL DATA (MW22)
Initial Displacement: 0.49 m Static Water Column Height: 3.07 mTotal Well Penetration Depth: 3.07 m Screen Length: 3.07 mCasing Radius: 0.025 m Well Radius: 0.075 m
Gravel Pack Porosity: 0.3
SOLUTION
Aquifer Model: Unconfined Solution Method: Bouwer-Rice
K = 0.007139 m/day y0 = 0.1609 m
Groundwater impact assessment
Prepared for – AGL Wholesale Gas Limited and APA Transmission Pty Limited – 60592634
AECOM
FAppendix FDewatering drawdown
estimates
Clie
nt :
APA
Loca
tion
:W
este
rn P
ort
Proj
ect :
GIJ
PP E
ES -
Gro
undw
ater
Stu
dy33
.3bo
res
Cal
cula
te D
raw
dow
n (s
) for
kno
wn
Dis
char
ge (Q
)TH
EIS
Ana
lytic
al S
olut
ion
(The
is, 1
935)
0.6
flow
rate
per
bor
e (L
/sec
)20
.0m
3/da
y (to
tal)
INPU
TSN
OTE
1: E
stim
atin
g 'T
' fro
m s
peci
fic c
apac
ity d
ata
use:
Pum
ping
rate
of w
ell (
m3/
day)
:0.
6[ l
og t
= -2
.31
+0.8
1 lo
g (s
pec
cap)
]0.
23L/
sec
14.
124.
12C
orre
spon
ding
pum
ping
rate
(L/
s):
0.
0069
NO
TE 2
: If u
sing
'T',
divi
de b
y sa
tura
ted
thic
knes
s to
giv
e
Stor
age
coef
ficie
nt (s
) of a
quife
r:0.
01 h
ydra
ulic
con
duct
ivity
(T=k
B)
aqui
fer t
hick
ness
2
Tran
smis
sivi
ty (m
2/da
y):
0.6
NO
TE 3
: Est
imat
es o
f S (c
onse
rvat
ive)
: Unc
onfin
ed=0
.05,
hydr
aulic
con
duct
ivity
0.3
m/d
ay
Tim
e si
nce
pum
ping
sta
rted
(day
s):
2 S
emi=
0.00
5, C
onfin
ed=0
.000
05T
0.6
m2/
day
time
(hrs
)48
.0N
OTE
4: T
o co
nver
t Gal
lons
/min
ute
to li
tres/
sec,
div
ide
by 1
3.2
Volu
me
prod
uced
dur
ing
Test
(KL)
:1.
20N
OTE
5: T
o co
nver
t litr
es/s
ec to
cub
ic m
etre
s/da
y, m
ultip
ly b
y 86
.4
(m3/
hr)
0.03
Spac
ing
3m
Tren
ch le
ngth
100
mN
o. B
ores
per
100
m33
.3
Dis
tanc
e(m
)u
W(u
)D
raw
dow
n(m
)
0.10
2.08
E-05
1.02
E+01
0.81
11
22
33
44
55
66
77
88
99
no. o
f spa
cing
s fro
m c
entre
poi
nt0.
505.
21E-
046.
98E+
000.
563
36
69
912
1215
1518
1821
2124
2427
27di
stan
ce fr
om c
entre
poi
nt (m
)1.
002.
08E-
035.
60E+
000.
45 D
dn1.
03.
23.
26.
16.
19.
19.
112
.012
.015
.015
.018
.018
.021
.021
.024
.024
.027
.027
.02.
008.
33E-
034.
22E+
000.
34D
ista
nce
from
tren
ch c
entre
(m)
11.
90m
0.45
0.26
0.26
0.16
0.16
0.11
0.11
0.07
0.07
0.05
0.05
0.03
0.03
0.02
0.02
0.01
0.01
0.01
0.01
3.00
1.88
E-02
3.42
E+00
0.27
4.00
3.33
E-02
2.86
E+00
0.23
11
22
33
44
55
66
77
88
99
no. o
f spa
cing
s fro
m c
entre
poi
nt5.
005.
21E-
022.
43E+
000.
193
36
69
912
1215
1518
1821
2124
2427
27di
stan
ce fr
om c
entre
poi
nt (m
)6.
007.
50E-
022.
09E+
000.
17 D
dn10
.010
.410
.411
.711
.713
.513
.515
.615
.618
.018
.020
.620
.623
.323
.326
.026
.028
.828
.87.
001.
02E-
011.
80E+
000.
14D
ista
nce
from
tren
ch c
entre
(m)
100.
79m
0.09
0.09
0.09
0.08
0.08
0.06
0.06
0.04
0.04
0.03
0.03
0.02
0.02
0.01
0.01
0.01
0.01
0.01
0.01
8.00
1.33
E-01
1.57
E+00
0.12
9.00
1.69
E-01
1.36
E+00
0.11
11
22
33
44
55
66
77
88
99
no. o
f spa
cing
s fro
m c
entre
poi
nt10
.00
2.08
E-01
1.19
E+00
0.09
33
66
99
1212
1515
1818
2121
2424
2727
dist
ance
from
cen
tre p
oint
(m)
12.0
03.
00E-
019.
06E-
010.
07 D
dn25
.025
.225
.225
.725
.726
.626
.627
.727
.729
.229
.230
.830
.832
.632
.634
.734
.736
.836
.814
.00
4.08
E-01
6.89
E-01
0.05
Dis
tanc
e fro
m tr
ench
cen
tre (m
)25
0.09
m0.
010.
010.
010.
010.
010.
010.
010.
010.
010.
010.
010.
000.
000.
000.
000.
000.
000.
000.
0016
.00
5.33
E-01
5.21
E-01
0.04
18.0
06.
75E-
013.
92E-
010.
0320
.00
8.33
E-01
2.93
E-01
0.02
11
22
33
44
55
66
77
88
99
no. o
f spa
cing
s fro
m c
entre
poi
nt25
.00
1.30
E+00
1.35
E-01
0.01
Ddn
0.1
33
66
99
1212
1515
1818
2121
2424
2727
dist
ance
from
cen
tre p
oint
(m)
In tr
ench
2.29
m0.
810.
270.
270.
170.
170.
110.
110.
070.
070.
050.
050.
030.
030.
020.
020.
010.
010.
010.
01
0.1
2.29
Dis
tanc
e dr
awdo
wn
estim
ates
0
0.5 1
1.5 2
2.5 3
3.5 4
4.5 5
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
Drawdown (m)
Dis
tanc
e (m
)D
ista
nce
vs d
raw
dow
n
AE
CO
M A
ustr
alia
Pty
Ltd
26
/03/
2019
GIJ
PP T
renc
h Th
eis
Dew
ater
ing_
0.3
mpd
.xls
(2 d
ays)
Clie
nt :
APA
Loca
tion
:W
este
rn P
ort
Proj
ect :
GIJ
PP E
ES -
Gro
undw
ater
Stu
dy10
.0bo
res
Cal
cula
te D
raw
dow
n (s
) for
kno
wn
Dis
char
ge (Q
)TH
EIS
Ana
lytic
al S
olut
ion
(The
is, 1
935)
0.5
flow
rate
per
bor
e (c
u.m
/day
)5.
0m
3/da
y (to
tal)
INPU
TSN
OTE
1: E
stim
atin
g 'T
' fro
m s
peci
fic c
apac
ity d
ata
use:
Pum
ping
rate
of w
ell (
m3/
day)
:0.
5[ l
og t
= -2
.31
+0.8
1 lo
g (s
pec
cap)
]0.
06L/
sec
Cor
resp
ondi
ng p
umpi
ng ra
te (
L/s)
:
0.00
58N
OTE
2: I
f usi
ng 'T
', di
vide
by
satu
rate
d th
ickn
ess
to g
ive
Stor
age
coef
ficie
nt (s
) of a
quife
r:0.
01 h
ydra
ulic
con
duct
ivity
(T=k
B)
aqui
fer t
hick
ness
2.5
Tran
smis
sivi
ty (m
2/da
y):
0.75
NO
TE 3
: Est
imat
es o
f S (c
onse
rvat
ive)
: Unc
onfin
ed=0
.05,
hydr
aulic
con
duct
ivity
0.3
m/d
ay
Tim
e si
nce
pum
ping
sta
rted
(day
s):
10 S
emi=
0.00
5, C
onfin
ed=0
.000
05T
0.75
m2/
day
time
(hrs
)24
0.0
NO
TE 4
: To
conv
ert G
allo
ns/m
inut
e to
litre
s/se
c, d
ivid
e by
13.
2
Volu
me
prod
uced
dur
ing
Test
(KL)
:5.
00N
OTE
5: T
o co
nver
t litr
es/s
ec to
cub
ic m
etre
s/da
y, m
ultip
ly b
y 86
.4
(m3/
hr)
0.02
Spac
ing
2m
Tren
ch le
ngth
10m
Tren
ch w
idth
4m
No.
Bor
es p
er 1
00 m
5.0
Dis
tanc
e(m
)u
W(u
)D
raw
dow
n(m
)
0.10
3.33
E-06
1.20
E+01
0.64
11
22
33
11
22
33
no. o
f spa
cing
s fro
m c
entre
poi
nt0.
508.
33E-
058.
82E+
000.
472
24
46
62
24
46
6di
stan
ce fr
om c
entre
poi
nt (m
)1.
003.
33E-
047.
43E+
000.
39D
dn10
.010
.210
.210
.810
.811
.711
.714
.014
.114
.114
.614
.615
.215
.22.
001.
33E-
036.
04E+
000.
32D
ista
nce
from
pit
edge
(m
)10
1.81
m0.
150.
150.
150.
140.
140.
140.
140.
120.
120.
120.
110.
110.
110.
113.
003.
00E-
035.
23E+
000.
284.
005.
33E-
034.
66E+
000.
251
12
23
31
12
23
3no
. of s
paci
ngs
from
cen
tre p
oint
5.00
8.33
E-03
4.22
E+00
0.22
22
44
66
22
44
66
dist
ance
from
cen
tre p
oint
(m)
6.00
1.20
E-02
3.86
E+00
0.20
25.0
25.1
25.1
25.3
25.3
25.7
25.7
29.0
29.1
29.1
29.3
29.3
29.6
29.6
7.00
1.63
E-02
3.55
E+00
0.19
Dis
tanc
e fr
om p
it ed
ge (
m)
250.10
m0.
010.
010.
010.
010.
010.
010.
010.
010.
010.
010.
010.
010.
010.
018.
002.
13E-
023.
29E+
000.
179.
002.
70E-
023.
06E+
000.
161
12
23
3no
. of s
paci
ngs
from
cen
tre p
oint
10.0
03.
33E-
022.
86E+
000.
152
24
46
6di
stan
ce fr
om c
entre
poi
nt (m
)15
.00
7.50
E-02
2.09
E+00
0.11
2.0
2.8
2.8
4.5
4.5
6.3
6.3
20.0
01.
33E-
011.
57E+
000.
08C
entr
e of
pit
23.52
m0.
320.
280.
280.
240.
240.
200.
2025
.00
2.08
E-01
1.19
E+00
0.06
30.0
03.
00E-
019.
06E-
010.
051
12
23
31
12
23
335
.00
4.08
E-01
6.89
E-01
0.04
22
44
66
22
44
66
60.0
01.
20E+
001.
58E-
010.
010.
12.
02.
04.
04.
06.
06.
04.
04.
54.
55.
75.
77.
27.
2A
t eac
h w
ell
3.69
m0.
640.
320.
320.
250.
250.
200.
200.
250.
240.
240.
210.
210.
190.
19
0.1
3.52
Dis
tanc
e dr
awdo
wn
estim
ates
0
0.5 1
1.5 2
2.5 3
3.5 4
4.5 5
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
Drawdown (m)
Dis
tanc
e (m
)D
ista
nce
vs d
raw
dow
n
AE
CO
M A
ustr
alia
Pty
Ltd
27
/05/
2019
GIJ
PP T
hrus
t bor
e pi
t The
is D
ewat
erin
g_0.
3 m
pd -
10 d
ays.
xls
(10
days
hig
h)
www.gasimportprojectvictoria.com.au
General and Gas Import Jetty enquiries1800 039 [email protected] Pipeline enquiries1800 531 [email protected]