environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/formb/tor/pfr/...2018-03-31final...

291
FINAL ENVIRONMENTAL IMPACT ASSESSMENT REPORT OF OF OF OF M/S. SRI BHAGAVAN MINES Extent: 33.029 Ha Sy.No.326/1,386, 529, 530, 531, 534, 535, 536, 537, 538 & 549, Turimerla (V) Sydapuram (M) S.P.S.R Nellore District, A.P PREPARED BY SV ENVIRO LABS & CONSULTANTS H.O:Block-B, B-1, IDA, Autonagar -12, Vishakapatnam Ph: 0891-2755528, Fax: 0891-2755529, E-mail: [email protected] Ph: 9440338628 QCI NABET Accredited& Recognized by MOE&F, New Delhi. September’ 2017

Upload: dotu

Post on 22-Apr-2018

240 views

Category:

Documents


8 download

TRANSCRIPT

  • FINAL ENVIRONMENTAL IMPACT

    ASSESSMENT REPORT

    OFOFOFOF

    M/S. SRI BHAGAVAN MINES

    Extent: 33.029 Ha

    Sy.No.326/1,386, 529, 530, 531, 534, 535, 536, 537, 538 &

    549, Turimerla (V)

    Sydapuram (M)

    S.P.S.R Nellore District, A.P

    PREPARED BY

    SV ENVIRO LABS & CONSULTANTS

    H.O:Block-B, B-1, IDA, Autonagar -12, Vishakapatnam

    Ph: 0891-2755528, Fax: 0891-2755529,

    E-mail: [email protected]

    Ph: 9440338628

    QCI NABET Accredited& Recognized by MOE&F,

    New Delhi.

    September

    2017

  • INDEX

    S.No TITLE PAGE No.

    I Executive Summary

    Chapter -1:- Introduction

    1.0 Purpose of the Project 1-1

    1.1 Details of the project & identification of project proponent 1-2

    1.2 Background information of the project 1-2

    1.3 Brief Description of the project 1-3

    1.3.1 Project Nature, Size and Location 1-3

    1.4 Regulatory compliances & applicable Laws/Regulations 1-6

    1.5 Environmental Parameters In The Study Area 1-6

    1.6 Generic Structure Of EIA Document 1-6

    1.7 Approved Terms of Reference compliance 1-7

    1.8 General Conditions 1-19

    1.9 Post Environment Clearance Monitoring 1-20

    Chapter -2 :-Project Description

    2.1 Description of the Project 2-1

    2.2 Location Details 2-2

    2.2.1 Details about project site 2-2

    2.3 Geology and Exploration 2-7

    2.3.1 Area Geology 2-7

    2.3.2 Geology of this mine 2-7

    2.4 Details of Exploration 2-8

    2.4.1 Method of Mining 2-8

    2.5 Details of Production 2-9

    2.5.1 Yeas wise production for the next five years 2-9

    2.5.2 Year wise production for ensuing five years 2-10

    2.6 List of Mining Machinery 2-11

    2.7 Nature and generation of waste 2-11

    2.8 Conceptual Plan 2-12

    2.9 Mine Development 2-12

    2.10 Mineral Reserves 2-12

    2.11 Life of the Mine 2-14

    2.12 Land Use 2-15

    2.13 Afforestation 2-15

    2.14 Progressive Reclamation Plan 2-16

    2.15 Use of Minerals 2-17

    2.16 Site Services-Utilities 2-17

    Chapter -3:- Analysis of Alternatives

    3.0 General 3-1

    3.1 Alternate Technology 3-1

    3.2 Site Alternatives 3-1

  • Chapter -4:-Description Of The Environment

    4.0 Introduction 4-1

    4.1 Study area 4-1

    4.2 Study Period 4-1

    4.3 Methodology of EIA study 4-1

    4.4 Collection of Baseline Data 4-2

    4.4.1 Micro Meteoreological Data 4-2

    4.4.2 Winds 4-3

    4.5 Air Environment 4-5

    4.5.1 Selection of Sampling Locations 4-5

    4.5.2 Methodology of Sampling and Analysis 4-5

    4.5.3 Frequency of Sampling 4-6

    4.5.4 Description of Sampling Locations 4-8

    4.5.5 Existing Ambeint Air Quality 4-12

    4.6 Water Environment 4-13

    4.6.1 Surface Water and Ground Water Quality Assessment 4-13

    4.6.2 Sampling Techniques 4-14

    4.6.3 Water Sampling Locations 4-16

    4.6.4 Ground Water Quality of the Study Area 4-18

    4.6.5 Surface water quality results 4-21

    4.6.6 Summary of Groundwater quality 4-21

    4.7 Soil Quatliy 4-22

    4.7.1 Selection of Sampling Locations 4-22

    4.7.2 Sampling and Analytical Techniques 4-22

    4.7.3 Details of Soil Sampling Locations 4-23

    4.7.4 Soil Analysis Results in the Study Area 4-25

    4.7.5 Summary of Soil Analysis Data 4-26

    4.7.6 Standard Soil Classification 4-28

    4.8 Noise Enviornment 4-30

    4.8.1 Identification of Sampling Locations 4-30

    4.8.2 Methodology 4-30

    4.8.3 Noise Monitoring Locations 4-31

    4.8.4 Description of Locations 4-31

    4.8.5 Noise Levels in the Study Area 4-33

    4.9 Land Use/Land Cover 4-36

    4.10 Biological Environmentd 4-43

    4.11 Socio Economic Environment 4-61

    Chapter -5:-Anticipated Environmental Impacts & Mitigation Measures

    5.0 Introduction 5-1

    5.1 Air Environment 5-9

    5.1.1 Impact due to transportation 5-9

    5.1.2 Air Quality Mitigation Measures 5-9

    5.2 Water Environment 5-10

  • 5.2.1 Impacts on surface water bodies and control measures 5-10

    5.2.2 Water consumption and waste water generation 5-11

    5.2.3 Rain Water Harvesting 5-12

    5.3 Land Environment 5-13

    5.3.1 Impact due to land degradation 5-13

    5.3.2 Land reclamation control measurs 5-13

    5.3.2.1 Reclamation of land affected due to mining activites 5-13

    5.3.2.2 Soil conservation measures and Top soil management 5-13

    5.3.2.3. Maintenance of road 5-14

    5.3.3 Programme of Afforestation 5-14

    5.3.4 Land Use 5-15

    5.4 Noise Environment 5-15

    5.4.1 Impact due to Noise and Vibration 5-15

    5.4.2 Noise and Vibration Control Measures 5-16

    5.5 Solid waste generation and stacking of wastes 5-17

    5.6 Biological Enviornment 5-17

    5.6.1 Mitigation Measures 5-19

    5.7 Traffic Analysis 5-22

    5.7.1 Impact on road network 5-23

    5.8 Socio-Economic Conditions 5-23

    5.8.1 Impact on socio-economic conditions 5-23

    5.9 Impact on Occupational Health and Safety 5-24

    5.10 Mines Waste Management 5-24

    Chapter -6:-Environmental Monitoring Programme

    6.0 Environmental Monitoring 6-1

    6.1 Monitoring around th mine site 6-1

    6.2 Post project monitoring programme 6-2

    6.2.1 Environmental Monitoring 6-2

    6.3 Monitoring schedule for environmental parameters 6-2

    6.4 Implementation Schedule 6-3

    6.5 Infrastructure for environmental protection & socio economic 6-4

    6.6 Monitoring Equipment and Consumables 6-4

    Chapter -7:-Additional Studies

    7.1 Risk Assessment 7-1

    7.2 Air Environment 7-1

    7.3 Disaster Management Plan 7-3

    7.4 Identificatin of Hazards 7-3

    7.4.1 Filling up the mine pit due to excessive rains 7-3

    7.4.2 Failure of slope in the pit 7-4

    7.4.3 Failure of slope of dump 7-4

    7.4.4 Accidents of heavy machinery 7-4

    7.4.5 Seismic activity 7-4

  • 7.4.6 Surface fire 7-4

    7.5 Safety Preparedness Plan 7-4

    7.6 Training 7-5

    7.7 Implementation of EMP and Montoring System 7-6

    7.7.1 General 7-6

    7.8 Implementation 7-7

    7.9 Activites to be monitored/inspected by EMC 7-7

    7.9.1 Land Erosion 7-7

    7.9.2 Drainage 7-7

    7.9.3 Re-vegetation and green belt development 7-9

    7.9.4 Occupational health 7-9

    Chapter -8:-Project Benefits

    8.0 General 8-1

    8.1 Employment 8-1

    8.2 Occupational health 8-1

    8.3 Improvements in physical and social infrastructure 8-1

    8.3.1 Improvement in the Physical Infrastructure 8-2

    8.3.2 Improvement in the Social Infrastructure 8-2

    8.3.3 Increase in Employment Potential 8-2

    8.3.4 Prevention of Illegal Mining & Contribution to the Exchequer 8-3

    8.3.5 Enhancement of Green Cover 8-3

    8.4 Health 8-3

    Chapter -9:-Environmental Management Plan

    9.0 Introduction 9-1

    9.1 Applicable Regulations 9-2

    9.2 Objectives of Environmental Management Plan 9-4

    9.3 Air Quality Management 9-4

    9.3.1 Controlling Dust Levels 9-5

    9.3.2 Air Pollution Control Measures 9-5

    9.3.3 Controlling of NOx Levels 9-5

    9.4 Water Quality Management 9-6

    9.5 Noise Level Monitoring 9-7

    9.5.1 Parameters 9-8

    9.5.2 Methodology 9-8

    9.5.3 Noise Quality Management 9-8

    9.5.4 Noise Pollution Control 9-8

    9.6 Biological Management 9-8

    9.6.1 Tree Plantation Program 9-9

    9.6.2 Mine Drainage 9-9

    9.7 Soil Management 9-9

    9.8 Proposed Mitigation Measures 9-10

    9.8.1 Land Enviornment 9-10

    9.8.1.1 Land use 9-10

  • 9.8.1.2 Calendar plan 9-11

    9.8.1.3 Mine roads 9-11

    9.8.1.4 Storage and preservation of top soil 9-11

    9.8.1.5 Soil erosion control 9-12

    9.8.1.6 Land restoration 9-12

    9.9 Socio-Economic Environment & Safety 9-13

    9.10 Biological Management Plan 9-13

    9.10.1 Green Belt Development/Afforestation Plan 9-13

    9.10.2 Design of Green Development 9-14

    9.11 Occupational Health and Safety Measures 9-14

    9.12 Public Health Implication, Occupational Health Survey Program

    and First Aid

    9-15

    9.13 Project Cost 9-16

    Chapter -10:-Summary & Conclusion

    10.0 Summary & Conclustion 10-1

    10.1 Recommendation 10-1

    Chapter -11:-Disclosure Of Consultants Engaged

    11.0 Disclosure of Consultants Engaged 11-1

    11.1 Services Offered by SV Enviro 11-1

    11.2 EIA Team 11-2

  • LIST OF TABLES

    TABLE NO. TITLE PAGE NO.

    Chapter -1:- Introduction

    1.1 Description of Project Proponent 1-2

    Chapter -2 :-Project Description

    2.1 Details about the Project Site 2-2

    2.2 Year wise proposed development & production from opencast

    mining

    2-9

    2.3 Details of machinery 2-11

    2.4 Waste generated in the scheme period 2-11

    2.5 UNFC classification of Reserves & Resources estimation 2-14

    2.6 Existing Land Use Pattern 2-15

    2.7 Proposed Land Use Pattern 2-15

    2.8 Year Wise greenbelt development 2-16

    Chapter -4:-Description Of The Environment

    4.1 Micro Meteorological Data at Site 4-3

    4.2 Techniques and Detectable limits for Ambient Air Quality

    Monitoring

    4-6

    4.3 Location of Ambient Air Quality Monitoring Stations 4-6

    4.4 Summary of Analysis of Ambient Air Quality in the Study

    Area

    4-9

    4.5 Standard Operating Procedures (SOP) For Water Sampling 4-14

    4.6 Analytical Techniques For Water Analysis 4-15

    4.7 Water Sampling Stations 4-16

    4.8 Ground water quality results 4-18

    4.9 Surface Water Quality of the Study Area 4-20

    4.10 Analytical Techniques For Soil Analysis 4-23

    4.11 Soil Sampling Locations 4-23

    4.12 Soil Analysis Results 4-25

    4.13 Noise Monitoring Locations 4-31

    4.14 Noise Levels in the Study Area 4-33

    4.15 Flora enumerated from both Core and Buffer zones of the

    proposed mining

    4-45

    4.16 List of Vertebrate fauna found in the study area 4-55

    4.17 Details of proposed plantation 4-58

    4.18 Selected list of plant species for Greenbelt development 4-60

    4.19 Particulars of the agriculture of Nellore district 4-65

    4.20 Particulars of the participants in primary survey 4-67

    Chapter -5:-Anticipated Environmental Impacts & Mitigation Measures

    5.1 Expected Nature of Impacts 5-1

    5.2 Identified/Predicted Environmental Impacts with & without 5-2

  • Mitigation Measures

    5.3 Green Belt Plan 5-14

    5.4 Existing Land Use Pattern 5-15

    5.5 Noise impact 5-16

    5.6 Suggested trees for greenbelt development 5-21

    Chapter -6:- Environmental Monitoring Programme

    6.1 Monitoring Schedule for Environmental Parameters 6-2

    6.2 Implementation Schedule 6-3

    Chapter -7:-Additional Studies

    7.1 Predicted GLC due to proposed mining project 7.2

    Chapter -9:- Environmental Management Plan

    9.1 EMP costing for the proposed project 9-3

    9.2 Ambient Air Quality Standards 9-4

    9.3 Air Pollution Control Measures 9-5

    9.4 Water Requirement & Waste water generation 9-6

    9.5 Details of Year Wise Tree Plantation Programme 9-14

    Chapter -11:- Disclosure of Consultants

    11.1 List of Experts Involved 11-2

  • LIST OF FIGURES

    FIGURE NO. TITLE PAGE NO.

    Chapter -1 :-Introduction

    1.1 Location map of project site 1-5

    Chapter -2: - Project Description

    2.1 Google map (10km radius) 2-4

    2.2 Topo map of 10km radius 2-5

    2.3 Lease Sketch 2-6

    Chapter -4:-Description Of The Environment

    4.1 Wind Rose Diagram for the month of January 17-

    February17

    4-4

    4.2 Ambient Air Quality Monitoring Location Maps 4-7

    4.3 Water Sampling Locations 4-17

    4.4 Soil Sampling Locations 4-24

    4.5 Noise Monitoring Locations 4-32

    4.6 Flow Chart Of Methodology 4-38

    4.7 Roads & Built up area 4-40

    4.8 Contour Map 4-41

    4.9 Drainage Map 4-42

    Chapter -7:-Additional Studies

    7.1 Predicted GLC by AERMOD 7-2

    7.2 Organizational setup of EMC 7-6

    7.3 Drainage Map 7-8

    Annexures

    Annexure -I ToR Copy

    Annexure -II Mine Lease documents

    Aneexure -III Approved Mining Plan

    Annexure IV Mine drawings

    Annexure-V Violation clearance documents

    Annexure- VI Minutes of Public Hearing

    Annexure - VII NABET Copy

  • CHAPTER I

    INTRODUCTION

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 1

    INTRODUCTION

    1.0 PURPOSE OF THE PROJECT

    M/s. Sri Bhagavan Mines of 33.029Ha for producing Mica, Quartz and Feldspar of

    mining lease area at sy no. 326/1, 328, 529, 530, 531, 534, 535, 536, 537, 538 & 549

    of Turimerla Village, Sydapuram Mandal, S.P.S.R Nellore district, Andhra Pradesh.

    M/s. Sri Bhagavan Mines proposes to obtain Environmental Clearance for the above

    mine from State Expert Appraisal Committee, Andhra Pradesh (SEAC, AP). The

    proposed project is categorized as Category B project as per Environmental Impact

    Assessment (EIA) Notification SO 1533, of 14-09-2006 and subsequent amendment

    notifications.

    Environmental Impact Assessment (EIA) is a process, used to identify the

    Environmental, social and economic impacts of a project prior to decision-making. It

    is a decision making tool, which guides the decision makers in taking appropriate

    decisions for proposed projects. EIA systematically examines both beneficial and

    adverse consequences of the proposed project and ensure that these impacts are taken

    into account during the project development & operational phases.

    The Environmental Impact Assessment report has been prepared in terms of EIA

    notification of the MoEF dated 14-9-2006, as amended on 1st Dec 2009, 4

    th April

    2011and approved ToRs vide Lr. No: SEIAA/AP/AP NLR MIN 05 2016 89 Dt:

    13.07.2016, for seeking Environmental Clearance for mining in the name of Sri

    Bhagavan Mines measuring 33.029 hectares falling under category B. Baseline

    survey of existing Environmental attributes are also conducted which helped in

    evaluating Environmental impacts due to the proposed activities and in formulating a

    scientific Environmental Management Plan (EMP).

    Presentation of TOR has been made before the SEAC, A.P committee and the TOR

    has been issued vide Lr No. SEIAA/AP/AP NLR MIN 05 2016 89 dated 13.07.2016

    which is attached as Annexure -1. As per the TOR, baseline data collected for one

    season i.e., non-monsoon season. The study area comprises of the core zone (lease

    area) and the buffer zone (10 kms around the core zone from the periphery).

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 2

    1.1 DETAILS OF THE PROJECT & IDENTIFICATION OF PROJECT

    PROPONENT

    M/s. Sri Bhagavan Mines, is the applicant for this mining project

    Table: 1.1 Description of Project Proponent

    Address of the

    lessee

    M/s. Sri Bhagavan Mines

    M. G Nagaraju (Lessee)

    3-6-200/401, 4th

    Floor, Arunodaya Apartment, Behind Minerva

    Hotel, Himayath Nagar, Hyderabad - 500029

    Cell No: 9246351239

    Address of Mine Sy. No: 326/1, 328, 529, 530, 534, 535, 536, 537, 538 & 549

    Turimerla Village, Sydapuram Mandal,

    S.P.S. R Nellore District, Andhra Pradesh.

    1.2 Background Information of the Project:

    G. Narayana Setty has applied for grant of mining lease for Quartz, Mica, Feldspar

    mine over an extent of 33.029 hectares which is located in Sy.No.326/1,328,529 to

    531, 534 to 538, & 549 of Tirumerla (V), Sydapuram (M), Nellore Dist., of A.P. got

    grant in favor of Sri. G.Narayana Setty Vide G.O. Ms. No. 201, dt: 18-10-1996 and

    the Mining Lease was executed by ADMG, Nellore, Vide Proc. No. 3852/M2/96, Dt:

    27-02-1997 for a period of 20 years from 27-02-1997 to 26-02-2017 in favor of Sri.

    G.Narayana Setty. After 10 years, the M.L was transferred in favor of M/s. Bhagavan

    Mines and the transferred of Mining Lease was executed by ADMG, Nellore, Vide

    Proc. 3852/M2/96, dt: 01-02-2008 for un-expired of lease portion i.e., up to 26-02-

    2017 in favour of M/s Bhagavan Mines.

    The first mining was approved by IBM vide Lt No. 659(221)/MC/96/NLR, Dt: 20-8-

    1996 under Rule 24 of MCR 1960 to get grant of mining lease.

    After mining lease was transferred in favor of M/s Bhagavan Mines, 1st scheme of

    mining was approved by IBM vide Lt. No. 659/M.S/MC/2007/Hyd, dt: 13-05-2008

    for five years period of 2008-09 to 2012-13.

    2nd

    scheme of mining was approve by Dept Director of Mines and Geology, Guntur

    vide Lt.No. 4572/Ms/NLR/2016, Dt: 25-2-2016 for the period of 2016-17.

    1st renewal of Quarry lease application was filed by M/s. Sri Bhagavan Mines on

    27.10.2015. ADMG, Nellore submitted proposal for grant of 1st renewal of Quarry

    lease for Mica, Quartz & Feldspar over an extent of 81.58Ac (33.029Ha) in sy.nos

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 3

    326/1, 328, 529, 530, 531, 534, 535, 536, 537, 538 & 549 of Turimerla village,

    Sydapuram Mandal, SPSR Nellore Dist in favour of M/s. Bhagavan Mines. As per the

    ADM&G, Nellore file no: 5210/P/2015 Dt: 21.10.2016, Assistant Director of Mines

    and Geology, Nellore submitted proposals recommending for grant of 1st renewal of

    Quarry Lease for Mica, Quartz & Feldspar over an extent of 81.58Acres in sy. nos:

    326/1, 328, 529 to 531, 534 to 538 & 549 of Turimerla village, Sydapuram Mandal,

    SPSR Nellore District for a further period of 20 years w.e.f 26.02.2017 in favour of

    Sri M/s. Sri Bhagavan Mines.

    M/s. Bhagavan Mines, Mg. Partner: Sri G. Nagaraju is requested by Director of Mines

    and Geology to submit mining plan along with CFE, CFO and EC for grant of 1st

    renewal within period of (6) months from the date of issue of the notice No:

    17454/R3-1/2016 Dt: 05.01.2017. Mining plan was approved by Deputy Director of

    Mines & Geology, Guntur vide Letter No 616/MP/NLR/2017 dated 03.03.2017.

    1.3 BRIEF DESCRIPTION OF THE PROJECT

    As per the approved mining plan (Lr. No: 616/MP/NLR/2017 Dt: 03-03-2017), M/s.

    Sri Bhagavan Mines had a mining lease for Mica, Feldspar & Quartz over an extent of

    33.029 Ha in Sy. No: 326/1, 328, 529, 530, 534, 535, 536, 537, 538 & 549 of

    Turimerla Village, Sydapuram Mandal, S.P.S.R Nellore District, Andhra Pradesh.

    The present proposal is for production of 8000 TPA of Quartz, 20000 TPA of

    Feldspar and 2000 TPA of Mica and the mining activity is carried out by

    Opencast method.

    1.3.1 Project Nature, Size and Location

    Nature

    The proposed project is mining of Mica, Quartz & Feldspar in the lease area of

    33.029Ha of Government waste land. The method of mining is manual open cast for

    the production of Mica, Feldspar and Quartz.

    Size

    The proposed production of mine is 2000 TPA of Mica, 20000 TPA of Feldspar and

    8000 TPA of Quartz. The anticipated life of mine will be 11 years as per targeted

    production and past exploration.

    Location

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 4

    The mining area is located in Turimerla Village of Sydapuram Mandal at SPSR

    Nellore District, Andhra Pradesh. The area is located at a distance of 34 Km from the

    district headquarters.

    The mine lease area falls under the Toposheet No. 57 N/4 bearing Toposheet details.

    Geo-coordinates:

    B.P no Latitude (WGS-84) Longitude (WGS-84)

    BP1 N141741.1 E794252.5

    BP2 N141713.6 E794251.4

    BP3 N141712.6 E794249.8

    BP4 N141710.6 E794247.8

    BP5 N141708.7 E794246.0

    BP6 N141706.2 E794243.7

    BP7 N141701.2 E794239.6

    BP8 N141700.0 E794244.3

    BP9 N141655.0 E794243.0

    BP10 N141648.9 E794240.9

    BP11 N141644.4 E794239.6

    BP12 N141645.0 E794236.0

    BP13 N141642.7 E794235.4

    BP14 N141642.2 E794237.1

    BP15 N141641.9 E794239.2

    BP16 N141641.5 E794241.9

    BP17 N141637.4 E794241.3

    BP18 N141634.8 E794247.5

    BP19 N141641.3 E794252.0

    BP20 N141640.9 E794255.3

    BP21 N141645.2 E794256.2

    BP22 N141650.1 E794255.0

    BP23 N141653.6 E794255.1

    BP24 N141654.2 E794249.6

    BP25 N141700.7 E794248.6

    BP26 N141708.9 E794251.2

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 5

    Accessibility

    Road Link

    The area is connected by BT road- Thummala Talupur Road at 1.91 Km which is

    connected to Nellore-Rapur Road which is at a distance of 5.85 Km from mine lease

    area. State Highway 58 connecting Gudur and Rajampet at 9.70 Km. NH-5 at 18.85

    Km at SE.

    Rail link

    The nearest rail head is Gudur Railway Station at a distance of 20.15 from the mine

    lease area.

    Air link

    The nearest airport facility is available at Tirupathi which is about 73.55 Km away

    from mine.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 6

    Fig: 1.1 Location Map

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 7

    1.4 REGULATORY COMPLIANCES & APPLICABLE LAWS/REGULATIONS

    a) The mining plan for the current mining scheme was approved by Department of

    Mines and Geology vide Letter No. 316/MP/NLR/2017 dated 03.03.2017 for 5

    years from 2017-18 to 2021-22.

    b) There are no legal cases & issues against the project and project proponent related

    with this mine.

    c) There are no National parks/ Sanctuaries notified under Wildlife Protection Act

    within 10km radius.

    1.5 ENVIRONMENTAL PARAMETERS IN THE STUDY AREA

    Collection of Base line data is an Integral aspect of the preparation of Environmental

    Impact Assessment report. Base line data reflects the present status of Environment

    before the initiation of any activity of the proposed project. The possible effects due

    to the proposed mine project are estimated and superimposed on the compiled

    baseline data subsequently to asses Environmental impacts.

    Pre Project Environment assessment was conducted in the study area during January

    2017 to March2017. Studies were under taken to generate base line data of the

    following:-

    1. MICROMETEOROLOGICAL DATA.

    2. AIR QUALITY EXISTING AMBIENT AIR QUALITY.

    3. WATER ANALYSIS - GROUND WATER.

    4. NOISE LEVELS.

    5. FLORA AND FAUNA.

    6. LAND ENVIRONMENT.

    7. LAND USE / LAND COVER.

    8. SOIL CHARACTERISTICS and

    9. SOCIO ECONOMIC STATUS SURROUNDING THE PROJECT SITE.

    1.6 GENERIC STRUCTURE OF EIA DOCUMENT

    In terms of the EIA notification of the MoEF dated 14th September 2006 as amended

    Dec 2009, the generic structure of the EIA document should be as under:

    1. Introduction

    2. Project Description

    3. Description of the Environment

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 8

    4. Anticipated environmental Impact & Mitigation Measures

    5. Analysis of alternatives (Technology and site)

    6. Environmental Monitoring Program

    7. Additional Studies

    8. Project Benefits

    9. Environmental Management Plan

    10. Summary & Conclusion

    11. Disclosure of Consultants engaged

    1.7 APPROVED TERMS OF REFERENCE COMPLIANCE

    ToR Lr. No: SEIAA/AP NLR MIN 05 2016 89 Dt: 13.07.2016

    Sl.

    No.

    TOR Points TOR Compliance/Section No.

    1. Year-wise production details since 1994

    should be given, clearly stating the highest

    production achieved in any one year prior to

    1994. It may also be categorically informed

    whether there had been any increase in

    production after the EIA Notification, 1994

    came into force w.r.t. the highest production

    achieved prior to 1994.

    The first lease was granted vide Letter

    No. G.O.Ms. No.201 dated 18-10-

    1996 in favor of G. Narayana Setty.

    Mining lease was executed by

    ADMG, Nellore vide proc. No.

    3852/M2/96 dt. 27-02-1997 for 20

    years from 27-02-1997 to 26-02-

    2017.

    After 10 years, the M.L was

    transferred in favor of M/s Sri

    Bhagavan Mines vide G.O Ms.

    No.292, dt 07-11-2017 and transfer of

    mining lease was executed by

    ADMG, Nellore v vide Proc. No.

    3852/M2/96, dt:01-02-2008 for an un-

    expired lease period i.e., up to 26-02-

    2017 in favor of M/s Sri Bhagavan

    Mines.

    After transfer, the first mining plan

    was approved by IBM vide Lr No.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 9

    659(221)/MC/96/NLR, Dt: 20-08-

    1996.

    The 1st scheme was approved by IBM

    vide letter No: 659

    /37MS/MC/2007/Hyd Dated:

    13.05.2008, period of 5 years from

    2008-09 to 2012-13.

    1st renewal of Quarry lease

    application was filed by M/s Sri

    Bhagavan Mines on 27-10-2015.

    Director of Mines and Geology

    requested to submit CFE, CFO and

    EC for grant of 1st renewal within 6

    months from the date of issue of the

    notice no. 17454/R3-1/2016, Dt: 05-

    01-2017.

    The second scheme of mining period

    i.e. 2016-17 to 2021-22 was approved

    by Dept. Director of Mines and

    Geology, Guntur vide Lr. No.

    4572/Ms/NLR/2016, Dt: 25-02-2016.

    Year-wise production details since

    2008 are as follows:

    Year Mica Feldspar Quartz

    2008 210.0 3440.915 250.0

    2009 710.0 4932.98 Nil

    2010 954.0 1142.475 Nil

    2011 529.0 Nil Nil

    2012 512.0 Nil Nil

    2013 214.0 150.0 Nil

    2014 316.020 700.0 200.0

    2015

    (only

    January

    month)

    50.0 100.0 Nil

    2. A copy of the document in support of the fact

    that the Proponent is the rightful lessee of the

    mine should be given.

    Lease documents are attached as Annexure

    II and approved mining plan is attached as

    Annexure -III

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 10

    3. All documents including approved mine plan,

    EIA and public hearing should be compatible

    with one another in terms of the mine lease

    area, production levels, waste generation and

    its management and mining technology and

    should be in the name of the lessee.

    While preparing EIA it has been ensured that

    all the documents including approved mine

    plan, EIA are compatible with one another in

    terms of the mine lease area, production

    levels, waste generation and its management,

    mining technology etc and are in the name of

    lessee.

    4. All corner coordinates of the mine lease area,

    superimposed on a High Resolution

    Imagery/topo sheet should be provided. Such

    an Imagery of the proposed area should

    clearly show the land use and other ecological

    features of the study area (core and buffer

    zone).

    All the corner coordinates of mine lease are

    has been marked/superimposed on toposheet.

    10 km radius Topo map of 1:50,000 scale of

    the proposed project location with all the

    corner coordinates of the mine lease area is

    given in Chapter 2; Fig. 2.2.

    Corner co-ordinates are superimposed on

    High resolution Google earth imagery is

    given in Chapter-2 under Fig 2.1.

    5. Information should be provided in Survey of

    India Topo sheet in 1:50000 scale indicating

    geological map of the area, geomorphology of

    land forms of the area, existing minerals and

    mining history of the area, important water

    bodies, streams and rivers and soil

    characteristics.

    The area is located in Survey of India

    Toposheet no: 57N/11 shown in chapter -2

    under fig no: 2.2

    6. Details about the land proposed for mining

    activities should be given with information as

    to whether mining conforms to the land use

    policy of the state: land diversion for mining

    should have approval from state land use

    board or the concerned authority.

    The land of mining is located at sy.no: 326/1,

    328, 529, 530, 531, 534, 535, 536, 537, 538

    & 549 of Turimerla Village, Sydapuram

    Mandal, SPSR Nellore Dt. The land is

    Government waste land comprising of

    33.029Ha. The Detailed land use of core zone

    is given in chapter -2 under table no: 2.7

    7. It should be clearly stated whether the

    proponent company has a well laid down

    Environment Policy approved by its Board of

    Directors? If so, it may be spelt out in the EIA

    The project proponent is committed to

    environmental safeguard and sustainable

    development. Environmental Monitoring Cell

    shall be established for reporting

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 11

    report with description of the prescribed

    operating process/procedures to bring into

    focus any infringement/deviation/violation of

    the environmental or forest norms/conditions?

    The hierarchical system or administrative

    order of the Company to deal with the

    environmental issues and for ensuring

    compliance with the EC conditions may also

    be given. The system of reporting of non-

    compliances / violations of environmental

    norms to the Board of Directors of the

    Company and/or shareholders or stakeholders

    at large may also be detailed in the EIA

    report.

    environmental issues. The Environmental

    policy is as follows:

    Prevent Environmental pollution by

    continual improvement in

    environmental performance of the

    Environmental Management Plan

    Comply with all the environmental

    legislations, regulations under the

    EIA Notification 2006 & subsequent

    amendments.

    Promote environmental awareness

    amongst employees, local

    communities and interested parties

    through proactive communication and

    training.

    Training to employees in terms of

    Safety, Health & Environment

    8. Issues relating to Mine Safety, including

    subsidence study in case of underground

    mining and slope study in case of open cast

    mining, blasting study etc. should be detailed.

    The proposed safeguard measures in each

    case should also be provided.

    The method of mining is opencast method

    with the help of jackhammer drilling and

    blasting.

    Safety related issues in detailed explained in

    Chapter-7 under section: 7.5.

    9. The study area will comprise of 10 km zone

    around the mine lease from lease periphery

    and the data contained in the EIA such as

    waste generation etc should be for the life of

    the mine / lease period.

    The study area is taken as 10km radius

    around the proposed mine.

    Every year about 3952m3 of mineral waste

    will be generated on an average and about

    19761m3 of mineral waste will be generated

    during this plan period.

    10. Land use of the study area delineating forest

    area, agricultural land, grazing land, wildlife

    sanctuary, national park, migratory routes of

    fauna, water bodies, human settlements and

    other ecological features should be indicated.

    Land use/Land cover is exclusively detailed

    in section 4.9 of Chapter-4 and their impacts

    are mentioned in chapter -5.

    Land use plan of plan of mine lease area is

    mentioned in chapter -2 under table no: 2.7

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 12

    Land use plan of the mine lease area should

    be prepared to encompass preoperational,

    operational and post operational phases and

    submitted. Impact, if any, of change of land

    use should be given.

    11. Details of the land for any Over Burden

    Dumps outside the mine lease, such as extent

    of land area, distance from mine lease, its

    land use, R&R issues, if any, should be given.

    OB Dump area is 10400 m2

    within the mine

    lease area. No R& R issues.

    12. A Certificate from the Competent Authority

    in the State Forest Department should be

    provided, confirming the involvement of

    forest land, if any, in the project area. In the

    event of any contrary claim by the Project

    Proponent regarding the status of forests, the

    site may be inspected by the State Forest

    Department along with the Regional Office of

    the Ministry to ascertain the status of forests,

    based on which, the Certificate in this regard

    as mentioned above be issued. In all such

    cases, it would be desirable for representative

    of the State Forest Department to assist the

    Expert Appraisal Committees.

    There is no forest land involved in the

    proposed mine lease area. Hence, clearance

    from State forest department is not

    applicable.

    13. Status of forestry clearance for the broken up

    area and virgin forestland involved in the

    Project including deposition of net present

    value (NPV) and compensatory afforestation

    (CA) should be indicated. A copy of the

    forestry clearance should also be furnished.

    There is no forest land involved in the

    proposed mine lease area.

    Hence forest clearance is not required.

    14. Implementation status of recognition of forest

    rights under the Scheduled Tribes and other

    Traditional Forest Dwellers (Recognition of

    Forest Rights) Act, 2006 should be indicated.

    Not Applicable

    15. The vegetation in the RF / PF areas in the Ecological Studies in Reserve forest is

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 13

    study area, with necessary details, should be

    given.

    mentioned in Chapter-4, under section

    Biological Environment.

    16. A study shall be got done to ascertain the

    impact of the Mining Project on wildlife of

    the study area and details furnished. Impact of

    the project on the wildlife in the surrounding

    and any other protected area and accordingly

    detailed mitigative measures required, should

    be worked out with cost implications and

    submitted.

    There is no wildlife sanctuary within the

    study area. Details of fauna existing within

    the study area are given in Chapter -4 under

    section 4.10.

    Anticipated impact of mining on the same

    along with suggested mitigation measures are

    incorporated in Chapter -5.

    17. Location of National Parks, Sanctuaries,

    Biosphere Reserves, Wildlife Corridors,

    Tiger/Elephant Reserves/(existing as well as

    proposed), if any, within 10 km of the mine

    lease should be clearly indicated, supported

    by a location map duly authenticated by Chief

    Wildlife Warden. Necessary clearance, as

    may be applicable to such projects due to

    proximity of the ecologically sensitive areas

    as mentioned above, should be obtained from

    the State Wildlife Department/Chief Wildlife

    Warden under the Wildlife (Protection) Act,

    1972 and copy furnished.

    There are no notified Sanctuaries, National

    Parks, Biosphere Reserves, and Wildlife

    corridors present within 10 km of the mine

    lease area.

    18. A detailed biological study of the study area

    [core zone and buffer zone (10 km radius of

    the periphery of the mine lease)] shall be

    carried out. Details of flora and fauna, duly

    authenticated, separately for core and buffer

    zone should be furnished based on such

    primary field survey, clearly indicating the

    Schedule of the fauna present. In case of any

    schedule-I fauna found in the study area, the

    necessary plan for their conservation should

    be prepared in consultation with State Forest

    Detailed Biological study in core zone and

    buffer zone is enclosed in Chapter -4 under

    section 4.10. No Schedule I Fauna is found

    and hence no conservation plan is prepared as

    either core or buffer zone are not ecologically

    sensitive.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 14

    and Wildlife Department and details

    furnished. Necessary allocation of funds for

    implementing the same should be made as

    part of the project cost. The Conservation

    Plan for Schedule-I species shall be approved

    by the Chief Wildlife Warden of the State

    Government.

    19. Proximity to Areas declared as Critically

    Polluted or the Project areas likely to come

    under the Aravali Range, (attracting court

    restrictions for mining operations), should

    also be indicated and where so required,

    clearance certifications from the prescribed

    Authorities, such as the SPCB or State

    Mining Dept. Should be secured and

    furnished to the effect that the proposed

    mining activities could be considered.

    The proposed project does not fall within

    10km radius of any Critically polluted area

    and also it does not come under the Aravali

    Range.

    20. Similarly, for coastal Projects, A CRZ map

    duly authenticated by one of the authorized

    agencies demarcating LTL. HTL, CRZ area,

    location of the mine lease w.r.t CRZ, coastal

    features such as mangroves, if any, should be

    furnished. (Note: The Mining Projects falling

    under CRZ would also need to obtain

    approval of the concerned Coastal Zone

    Management Authority).

    Not applicable as the project does not fall in

    the CRZ area.

    21. R&R Plan/compensation details for the

    Project Affected People (PAP) should be

    furnished. While preparing the R&R Plan, the

    relevant State/National Rehabilitation &

    Resettlement Policy should be kept in view.

    In respect of SCs/STs and other weaker

    sections of the society in the study area, a

    need based sample survey, family-wise,

    As per the Socio-Economic Survey, no R&R

    plan is envisaged; as there is no habitation

    within proposed mining area hence no

    displacement of people is envisaged from

    their respective areas due to proposed mining

    project.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 15

    should be undertaken to assess their

    requirements, and action programmes

    prepared and submitted accordingly,

    integrating the sectoral programmes of line

    departments of the State Government. It may

    be clearly brought out whether the village

    located in the mine lease area will be shifted

    or not. The issues relating to shifting of

    Village including their R&R and socio-

    economic aspects should be discussed in the

    report.

    22. One season (non-monsoon) primary baseline

    data on ambient air quality (PM10, SO2 and

    NOx), water quality, noise level, soil and

    flora and fauna shall be collected and the

    AAQ and other data so compiled presented

    date-wise in the EIA and EMP Report. Site-

    specific meteorological data should also be

    collected. The location of the monitoring

    stations should be such as to represent whole

    of the study area and justified keeping in view

    the pre-dominant downwind direction and

    location of sensitive receptors. There should

    be at least one monitoring station within 500

    m of the mine lease in the pre-dominant

    downwind direction. The mineralogical

    composition of PM10, particularly for free

    silica, should be given.

    Baseline data was collected during the month

    of January2017 to March2017 and the

    results are given in Chapter- 4 Description

    of Environment.

    23. Air quality modeling should be carried out for

    prediction of impact of the project on the air

    quality of the area. It should also take into

    account the impact of movement of vehicles

    for transportation of mineral. The details of

    the model used and input parameters used for

    Prediction of impacts on air Environment has

    been carried out employing mathematical

    model by using AERMOD was done and

    mentioned in Chapter -7.

    Wind rose map showing pre-dominant wind

    direction has been carried out and the results

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 16

    modeling should be provided. The air quality

    contours may be shown on a location map

    clearly indicating the location of the site,

    location of sensitive receptors, if any, and the

    habitation. The wind roses showing pre-

    dominant wind direction may also be

    indicated on the map.

    are given in Chapter-4 under fig no: 4.1

    24. The water requirement for the Project, its

    availability and source should be furnished. A

    detailed water balance should also be

    provided. Fresh water requirement for the

    Project should be indicated.

    Around 12.5 KLD of water will be required

    for the proposed project. Accumulated water

    in the mined out pits will be used for

    sprinkling and greenbelt development and

    drinking water will be sourced from nearby

    village through water tankers.

    25. Necessary clearance from the Competent

    Authority for drawl of requisite quantity of

    water for the Project should be provided.

    As the source of water is through water

    tankers and such ground water clearance is

    not required.

    26. Description of water conservation measures

    proposed to be adopted in the Project should

    be given. Details of rainwater harvesting

    proposed in the Project, if any, should be

    provided.

    The rain water collected in the pits after spell

    of rain will be used for plantation and dust

    suppression. At the end of life of mine,

    excavated area will be used as rain water pit.

    27. Impact of the project on the water quality,

    both surface and groundwater should be

    assessed and necessary safeguard measures, if

    any required, should be provided.

    The depth of aquifer is at a depth of 30m and

    static water level is at 6-7m during rainy

    season and will go down upto 9-9.5m from

    bgl.

    The mine workings are located at higher

    levels and proposed workings go to a depth

    of 18m, no ground or surface water is going

    to be accumulated in working pits.

    However, rainwater accumulated in working

    pits will be pumped out to garland drains &

    silting tank

    28. Based on actual monitored data, it may

    clearly be shown whether working will

    Mining will not intersect ground water table

    which will be carried out upto 18m and water

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 17

    intersect groundwater. Necessary data and

    documentation in this regard may be

    provided. In case the working will intersect

    groundwater table, a detailed Hydro

    Geological Study should be undertaken and

    Report furnished. Necessary permission from

    Central Ground Water Authority for working

    below ground water and for pumping of

    ground water should also be obtained and

    copy furnished.

    depth is 30m.

    29. Details of any stream, seasonal or otherwise,

    passing through the lease area and

    modification / diversion proposed, if any, and

    the impact of the same on the hydrology

    should be brought out.

    There are no perennial water bodies inside

    the mine area. Only small nala passing

    towards SE. Buffer zone delineated as per

    norms.

    The subject area is elevated on Northern side

    and sloping towards SE. The storm water will

    be diverted to Rain water harvesting and any

    surplus during rains will lead to seasonal

    nala. The upstream area is only plantation

    area and hence no diversion is required.

    30. Information on site elevation, working depth,

    groundwater table etc. Should be provided

    both in AMSL and bgl. A schematic diagram

    may also be provided for the same.

    Site Elevation is 37mts AMSL, Working

    depth is 18m. Ground water depth is 30m.

    31. A time bound Progressive Greenbelt

    Development Plan shall be prepared in a

    tabular form (indicating the linear and

    quantitative coverage, plant species and time

    frame) and submitted, keeping in mind, the

    same will have to be executed up front on

    commencement of the project.

    Year Area proposed

    for plantation

    Plants

    proposed

    2017-18 0.0600Ha 150Nos

    2018-19 0.0600Ha 150Nos

    2019-20 0.0600Ha 150Nos

    2020-21 0.0600Ha 150Nos

    2021-22 0.0600Ha 150Nos

    Total 0.3000Ha 7500

    plants

    32. Impact on local transport infrastructure due to

    the Project should be indicated. Projected

    Existing traffic density at road connecting

    from Utukur to Malichedu is 120 PCU/hr and

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 18

    increase in truck traffic as a result of the

    Project in the present road network (including

    those outside the Project area) should be

    worked out, indicating whether it is capable

    of handling the incremental load.

    Arrangement for improving the infrastructure,

    if contemplated (including action to be taken

    by other agencies such as State Government)

    should be covered.

    proposed traffic from mine site is 60PCU/hr.

    So, total traffic density on the mineral

    transportation road will be 170PCU/hr. As

    the carrying capacity of the road is

    1800PCU/hr, the proposed increase in traffic

    density will not cause significant impact on

    the traffic since the connecting road and

    nearby State Highway is capable of handling

    this increase in traffic density.

    33. Details of the onsite shelter and facilities to be

    provided to the mine workers should be

    included in the EIA report.

    Temporary rest shelter shall be constructed

    during mining operation. For transportation

    of mineral product, roads around the mining

    area will be strengthened.

    34. Conceptual post mining land use and

    Reclamation and Restoration of mined out

    areas (with plans and with adequate number

    of sections) should be given in the EIA report.

    An effective program of land restoration will

    be drawn and implemented to bring back the

    status to as near the pre mining conditions as

    possible.

    A greenbelt development along the

    periphery of the lease area will be

    taken up

    The excavated area will be used as

    rainwater harvesting pit

    35. Occupational Health impacts of the Project

    should be anticipated and the proposed

    preventive measures spelt out in detail.

    Details of pre-placement medical examination

    and periodical medical examination schedules

    should be incorporated in the EMP.

    Occupational Health & safety measures,

    details of periodical medical examination are

    enclosed in Chapter -9 under section 9.7.4.

    36. Public health implications of the Project and

    related activities for the population in the

    impact zone should be systematically

    evaluated and the proposed remedial

    measures should be detailed along with

    budgetary allocations.

    Public health implication of the proposed

    project is evaluated systematically and

    enclosed in Chapter -9 under section 9.11.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 19

    37. Measures of socio economic significance and

    influence to the local community proposed to

    be provided by the Project Proponent should

    be indicated. As far as possible, quantitative

    dimensions may be given with time frames

    for implementation.

    At the maximum production level the project

    will contribute to the extent of Rs.

    5Lakh/annum towards the District Mineral

    Foundation (DMF) fund which will be

    primarily utilized for the improvement of

    infrastructure of villages. Besides this, the

    project proponent has earmarked 2% of

    project cost for additional CSR activities.

    38. Detailed environmental management plan to

    mitigate the environmental impacts which,

    should inter-alia include the impacts of

    change of land use, loss of agricultural and

    grazing land, if any, occupational health

    impacts besides other impacts specific to the

    proposed Project.

    Detailed Environmental Management Plan

    and cost implication for EMP is mentioned in

    Chapter -9

    39. Public hearing points raised and commitment

    of the project proponent on the same along

    with time bound action plan to implement the

    same should be provided and also

    incorporated in the final EIA/EMP Report of

    the Project.

    Public hearing was conducted on and the

    minutes are enclosed as Annexure -VI

    40. Details of litigation pending against the

    project, if any, with direction /order passed by

    any Court of Law against the project should

    be given.

    No litigation pending.

    There was a violation of EIA notification

    case which has been cleared vide CC No:

    147/2016 and the documents are enclosed as

    Annexure -V

    41. The cost of the project (capital cost and

    recurring cost) as well as the cost towards

    implementation of EMP should clearly be

    spelt out.

    Total project cost is Rs.80Lakhs and cost

    towards EMP is Rs. 27.53 Lakhs for 5 years

    and detailed in Chapter-9 with capital and

    recurring cost.

    42. A disaster management plan shall be prepared

    and included in the EMP/EIA Report.

    Disaster Management Plan for the report has

    been prepared and same has been included in

    Chapter -7 Additional studies under section

    7.2

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 20

    43. Benefits of the project if the project is

    implemented should be spelt out. The benefits

    of the Project shall clearly indicate

    environmental, social, economic, employment

    potential, etc.

    Improve physical and social

    infrastructure of the area

    Generate direct as well as indirect

    employment

    Greenbelt development

    1.8 GENERAL CONDITIONS:

    a. All documents to be properly referenced with index and continuous page numbering.

    b. Where data are presented in the report especially in tables, the period in which the

    data were collected and the sources should be indicated.

    c. Project proponent shall enclose all the analysis/ testing reports of water, air, soil, noise

    etc. Using the MOEF&CC/NABL accredited laboratories. All the original

    analysis/testing reports should be available during appraisal of the project.

    d. Where the documents provided are in a language other than English, an English

    translation should be provided.

    e. The Questionnaire for environmental appraisal of industrial projects as devised earlier

    by the Ministry shall also be filled and submitted.

    f. While preparing the EIA report, the instructions for the proponents and instructions

    for the consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II (I) dated 4th

    August, 2009, which are available on the website of this Ministry, should also be

    followed.

    g. Changes, if any made in the basic scope and project parameters (as submitted in

    Form-I and the P.F.R for securing the TOR) should be brought to the attention of

    MoEF with reasons for such changes and permission should be sought, as the TOR

    may also have to be altered. Post Public Hearing changes in structure and content of

    the draft EIA/EMP (other than modifications arising out of the P.H. process) will

    entail conducting the PH again with the revised documentation.

    h. As per the circular no. J-11011/618/2010-IA.II (I) dt: 30.05.2012, your are requested

    to submit certified report of the status of compliance of the conditions stipulated in the

    environment clearance for the existing operations of the project by the Regional

    Office of Ministry of Environment & Forests, If applicable.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-I

    INTRODUCTION

    1 - 21

    The EIA report should also include following

    i Surface plan of the area indicating

    contours of main topographic features,

    drainage and mining area

    Attached as ANNEXURE-IV

    ii Surface Geological plan

    iii Sections of the mine pit and external

    dumps, if any, clearly showing the land

    features of the adjoining area.

    iv Conceptual plan and section

    v Year wise working plan & section

    1.9. POST ENVIRONMENT CLEARANCE MONITORING:

    The project management will submit a half yearly compliance report in respect of

    stipulated prior Environmental Clearance terms and conditions on 1st June and 1

    st

    December of each calendar year.

  • CHAPTER II

    PROJECT DESCRIPTION

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 1

    2.1 DESCRIPTION OF THE PROJECT

    First Mining lease was granted to mine mica, quartz and Feldspar over an extent of

    81.58Acres (33.029Ha) in Sy. No: 326/1, 328, 529, 530, 531, 534, 535, 536, 537, 538

    & 549 of Turimerla Village, Sydapuram Mandal, S.P.S.R Nellore District, Andhra

    Pradesh in favour of Sri G. Narayana Setty vide G.O Ms. No: 201 Dt: 18.10.1996.

    The Mining Lease was executed by ADMG, Nellore, Vide Proc. No. 3852/M2/96, Dt:

    27-02-1997 for a period of 20 years from 27-02-1997 to 26-02-2017 in favor of Sri.

    G.NarayanaSetty. After 10 years, the M.L was transferred in favor of M/s. Bhagavan

    Mines Vide G.O. Ms. No. 292, dt: 7-11-2007 and the transferred of Mining Lease was

    executed by ADMG, Nellore, Vide Proc. 3852/M2/96, dt: 01-02-2008 for un-expired

    of lease portion i.e., up to 26-02-2017 in favour of M/s Bhagavan Mines.

    The first mining was approved by IBM vide Lt No. 659(221)/MC/96/NLR, Dt: 20-8-

    1996 under Rule 24 of MCR 1960 to get grant of mining lease.

    After mining lease was transferred in favor of M/s Bhagavan Mines, 1st scheme of

    mining was approved by IBM vide Lt. No. 659/M.S/MC/2007/Hyd, dt: 13-05-2008

    for five years period of 2008-09 to 2012-13.

    2nd

    scheme of mining was approve by Dept Director of Mines and Geology, Guntur

    vide Lt.No. 4572/Ms/NLR/2016, Dt: 25-2-2016 for the period of 2016-17.

    1st renewal of Quarry lease application was filed by M/s. Sri Bhagavan Mines on

    27.10.2015. ADMG, Nellore submitted proposal for grant of 1st renewal of Quarry

    lease for Mica, Quartz & Feldspar over an extent of 81.58Ac (33.029Ha) in sy.nos

    326/A, 328, 529, 530, 531, 534, 535, 536, 537, 538 & 549 of Turimerla village,

    Sydapuram Mandal, SPSR Nellore Dist in four of M/s. Bhagavan Mines.

    M/s. Bhagavan Mines, Mg. Partner: Sri G. Nagaraju is requested by Director of Mines

    and Geology to submit mining plan along with CFE, CFO and EC for grant of 1st

    renewal within period of (6) months from the date of issue of the notice No:

    17454/R3-1/2016 Dt: 05.01.2017.

    The present proposal is for production of 8000 TPA of Quartz, 20000 TPA of

    Feldspar and 2000 TPA of Mica and the mining activity is carried out by

    Opencast method.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 2

    2.2 LOCATION DETAILS

    The mining area is located in Turimerla Village of Sydapuram Mandal at SPSR

    Nellore District, Andhra Pradesh. The area is located at a distance of 33 Km from the

    district headquarters. The mine lease area falls under the

    Toposheet No. : 57 N/11

    Latitude : N141741.1to N141708.9

    Longitude : E794252.5to E794251.2

    The nearest railway station is Gudur which is at 22 km from the mine lease area. The

    nearest airport is Tirupathi Airport at 95 Km from the mining site.

    2.2.1 Details about Project Site

    Table: 2.1 Details about the Project Site

    Nature of the project Sri Bhagavan Mines

    Extent 33.029Ha

    Capacity 8000 TPA of Quartz, 20000 TPA of Feldspar and 2000

    TPA of Mica

    Location of the project

    District & State S.P.S.R Nellore District, A.P.

    Mandal Sydapuram

    Village Turimerla

    Latitude N141741.1to N141708.9

    Longitude E794252.5to E794251.2

    General climatic conditions

    Maximum Temperature 46.70C

    Minimum Temperature 14.00C

    Annual average rain fall 1042 mm

    Relative Humidity 64-79%

    General location details

    Nearest Village Orupali (under Turimeral Gramapanchayati) within

    0.20km from the mining site

    Nearest city Nellore at 33 km from the mining site.

    District headquarters Nellore at 33 km from the mining site.

    Nearest railway station Gudur Railway station at 20.15 km from the mining

    site.

    Nearest Airport Tirupathi Airport at 73.55 km from the mine site.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 3

    Archaeological/Historically

    important site

    None within 10 km radius

    Infrastructure Facilities Hospitals and schools are present in Syadapuram.

    Sanctuaries/National parks None within 10 km radius.

    Nearest RF/PF Podalakur Reserved Forest 7.0Km

    Tummalatalupur RF 1.78Km

    Munagapadu RF 3.0Km

    Tatipalli RF 7.45km

    Chaganam RF 4.07km

    Utukur RF 4.35km

    Griddaluru RF 8.34km

    Saidapuram RF 8.06km

    Biradavolu RF 9.54km

    Turimerla RF 0.80Km

    Duggunta RF 7.72km

    Nearest Water Bodies Kandleru River- 4.0Km

    Maleru River 5.52Km

    Penna River -0.27Km

    Surrounding Mines Seetharama Mining Company 10.37Ha

    Meenakshi Sundaram Mica Mines -24.09Ha

    Seetharama Mining Company -53.60Ha

    Pattabirama Mining Company 11.22Ha

    SreeKalyana Rama Company -116.42Ha

    Kalyana Rama Mica mines -1.574Ha

    Sree KSR & Company -28.03Ha

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 4

    Fig. 2.1 Google map (10 km radius)

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 5

    Fig. 2.2 Topomap of 10 km radius

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER

    PROJECT DESCRIPTION

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 6

    Fig. 2.3Lease

    Sketch

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 7

    2.3 GEOLOGY AND EXPLORATION

    2.3.1 Area Geology

    Two distinct litho-units constitute the subject area. They are (1) Schist and (2) Pegmatite.

    Out of these two litho units, the Pegmatite is occurring as concealed lens below m soil

    &morum and it is trapped between the Biotite Schist as hanging & footwalls. This is

    normally found deeply penetrated vertically keeping the limited width & strike length. In

    this area pegmatite is formed as two parallel bodies. The first vein exposed in pit-1, pit-3

    and pit-4 over a length of 167m and to a width of to an average width of 30m in NW-SE

    strike direction dipping towards SW with 65. The 2nd

    parallel pegmatite veins is exposed

    in pit-2 over a length of 145m and to a width of 20m. Even tough pegmatite veins are

    covered by the soil, these veins are well exposed in four working pits to as a maximum

    thickness of 20m in between the RLS of 300-280m in pit-1 and it is continuing further

    depth from pit bottom. It is observed from pits that the pegmatite is rich in Potash

    Feldspar associated with glassy Quartz and mica. The lease area is covered by the soil

    around the working pits on the surface and the contact of pegmatite with schist is clearly

    seen from the working pits.

    2.3.2 Geology of this mine:

    The main pegmatite had been worked from the open quarry.

    Mineralogy of the mine:

    Feldspar:

    The Feldspar is gray in colour& greasy luster. It is having multiple joints and concoidal

    fracture. In pegmatite, the recovery of Feldspar is found to be about 50%.

    Mineralogical, the Pegmatite is having soda feldspar.

    Quartz:

    The physical quality of the Quartz in pegmatite is dull white and semi glassy in nature

    and having concoidal fracture. It is having glassy luster. In pegmatite,the recovery of

    Quartz is found to be about 10%.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 8

    Mica:

    The mica is available in the form of books and small intercalated minerals in the

    pegmatite. The mica is having greasy luster and brittle and flaky in nature. In pegmatite,

    the recovery of crude Mica is found to be about 8%. Mineralogical, the pegmatite is

    having muscovite mica with clear cleavages and in crisscross form.

    In this mine only mica is considered as economically valued mineral, remaining material

    is considered as waste.

    2.4 DETAILS OF EXPLORATION

    In approved mining scheme, it is proposed to drill 23 (PBH -1 to PBH-23) vertical, DTH

    boreholes to a depth of 20m to 30m depend up on the mineral availability at less than

    50m grid interval in mineral zone during the year 2016-17.

    The pit no: 2 is developed and established pegmatite vein over length of 144m and to a

    width of 22m during previous year and no exploration was taken up in the year 2016-17.

    2.4.1 Method of Mining

    Mine operations are carried out by simple open cast method using jackhammer drilling

    and blasting. The blasted ROM will be loaded into tippers by the excavator and the

    loaded ROM is transported to the crushing and screening plan, located in the lease area

    on Southern side for separation minerals of Quartz, Feldspar and Mica from Pegmatite

    ROM. The segregated minerals will be loaded into hired trucks and the same will be

    transported to the user industries. So, the minerals are feasible in present market. It is a

    working mine and the previous mine workings show that the mining of this area is

    economically viable.

    The mine workings were carried out from four pits during previous years by open cast

    benching method on two pegmatite bodies by semi-mechanized method by using an

    excavator, jackhammer drilling and blasting and tippers of 10t capacities. The safe

    benches were excavated to a height of 3m to 6m in country rock directly with the help of

    excavator without drilling and blasting. The benches were developed along and across

    the strike direction (N-S & E-W) of the pegmatite and the safe benches were developed

    in foot wall and hanging wall side by keeping the bench which more than the bench

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 9

    height. The excavated waste rock (schist) was loaded into tippers and shifted to the O.B

    dump yard. Since the Pegmatite is hard in nature, the excavations of the minerals were

    carried out by open cast method with the help of an excavator into tippers of 10T

    capacity and the same is shifted to the crushing and screening plan, located in the lease

    area on Southern side. From ROM, minerals of Quartz, Feldspar and Mica were

    segregated by screening hand picking. This method of mining will be continued in

    ensuing lease period.

    2.5 DETAILS OF PRODUCTION

    2.5.1 Year wise production for the next five years

    Table 2.2-Year wise proposed development and production from opencast mining:

    Year Pit no Total

    Excavati

    on (m3)

    Top

    soil/OB

    (m3)

    ROM (m3) Mineral Production (t) From ROM @2.5 BD

    Mineral

    (m3) @

    75%

    M.

    Reject

    (m3) @25%

    Quartz

    @20% Feldspar

    @ 50% Mica

    @5%

    2017-18 Pit -2 17376 Nil 11457 3819 7638 19095 1910

    2018-19 Pit -1 18780 Nil 11745 3915 7830 19575 1958

    2019-20 Pit 2 23304 Nil 11700 3900 7800 19500 1950

    2020-21 Pit 1 17430 Nil 12375 4125 8250 20625 2062

    2021-22 Pit - 3 23928 Nil 12006 4002 8004 20010 2001

    100818 59283 19761 39522 98805 9881

    Year wise development in ensuing five years (2017-18 to 2021-22):

    The workings were carried out from four working pits by excavating two to three benches

    to a height of 6m by excavating side burden. Since the minerals are occurring as a vein in

    between the country rock, the safe benches were be developed in side burden by

    excavating top benches in schist to a height of 6m each, before going for mineral

    production. In this plan period, the development will be carried out from pit-1, pit-2 and

    pit-3 as year wise details are furnished below:

    Year 2017-18: In this year,the development will be carried out on western side of the pit-

    2 by advancing the existing 2nd

    bench towards west in country rock over an extent of

    350m2 and to a thickness of 6m between the RLS of 294-288m and obtained about

    2100m3 of waste in this year.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 10

    Year 2018-19: In this year, the development will be carried out on western side of the

    pit-1 by advancing the existing two western side benches (1st& 2

    nd) towards west in

    country rock over an extent of 384-264m2 and to a thickness of 6m each between the

    RLS of 298-294m & 294-288m and obtained about 3120m3 of waste rock in this year.

    Year 2019-20: In this year, the development will be carried out on western side of the pit

    -2 by developing three benches in country rock on western over an extent of 560, 422 &

    302m2 and to a thickness of 6m each between the RLS of 300-294, 294-288m and

    obtained about 7704m3 of waste rock in this year.

    Year 2020-21: In this year, the development will be carried out on eastern side of the pit-

    1 by developing the bottom bench towards east in country rock over an extent of 155m2

    and to a thickness of 6m between the RLS of 288-282m and obtained about 930m3 of

    waste rock in this year.

    Year 2021-22: In this year, the development will be carried out around the pit-3 by

    developing the three benches in country rock over an extent of 600, 570 & 150m2 and to

    a thickness of 6m each between the RLS of 298-292, 292-286 and 286-280 and obtained

    about 7920m3 of waste rock in this year.

    2.5.2 Year wise production for ensuing five years (2017-18 to 2021-22):

    It is proposed to raise about 8,000t of quartz, 20,000t of Feldspar and 2000t of Mica per

    year in this plan period. The working will be carried out around the existing pit -1, pit-2

    & pit-3 by excavating one to three benches of 6m height each in mineral zone. The

    minerals will be excavated with the help of jackhammer drilling and blasting and the

    blaster ROM will be separated as quartz, Feldpsar& Mica by crushing & screening.

    Year 2017-18: In this year, about the production of 7638t Quartz, 19095t Feldspar, 1910t

    Mica & 3819m3 of mineral waste will be obtained by excavating the mineral from 2nd

    bench of pit-2 over an extent of 2546m2 between the RLS of 294-288m.

    Year 2018-19: In this year, the production of 7830t Quartz, 19575t Feldspar, 1958t Mica

    & 3915m3 of mineral waste will be obtained by excavating the 3rd

    benches from bottom

    of the pit -2 in mineral zone, over an extent of 2600m2 between the RLS of 288-282m.

    Year 2019-20: In this year, the production of 7800t Quartz, 19500t Feldspar, 1950t Mica

    & 3900m3 of mineral waste will be obtained by excavating the 3rd benches from bottom

    of the Pit-2 in mineral zone, over an extent of 2600m2 between the RLS of 288-282m.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 11

    Year 2020-21: In this year, the production of 8250t Quartz, 19500t Feldspar, 2062t Mica

    & 4125m3 of mineral waste will be obtained by advancing the 3rd

    benches of Pit-1

    towards east over an extent of 2750m2 between the RLS of 288-282m in mineral zone.

    Year 2021-22: In this year, the production of 8004 t Quartz, 20010t Feldspar, 2001 t

    Mica & 4002m3 of mineral waste will be obtained by excavating 2nd

    & 3rd

    benches of Pit-

    3 over an extent of 1556m2 & 1112m2 between the RLS of 292-286m and 286-280m in

    mineral zone.

    2.6 List of Mining Machinery

    Table: 2.3 Details of Machinery

    S.No Name of Machinerys Capacity Numbers

    1 Excavator 200Lc 1 no

    2 Tractor cum Trolley or tippers 4/10 tones 3 nos

    3 Jackhammer drills 32mm dia 3nos

    4 Water Tanker 2000 Lts 1 No

    2.7 Nature and generation of waste:

    About 25% of the production is going to be generated as mineral wastes consisting of

    intermix with Quartz, Feldspar & Mica. In every year about 3952m3 of mineral waste will

    be generated on an average and about 19761m3 of mineral waste will be generated during

    this plan period. In addition to the mineral waste about 21774m3 of side burden will be

    generated during five years plan period. The quantities of year wise waste generation

    particulars are furnished in below table: 2.4. It is proposed to stack the waste over an extent

    of 2080m2 and to a height of 6m on southern side of the lease area in each year. In these five

    years plan period, the proposed waste dumps will cover an extent of 10400m2.

    Table: 2.4Waste Generated in the Scheme Period

    Year Total Waste(m3)

    2017-18 3819

    2018-19 3915

    2019-20 3900

    2020-21 4125

    2021-22 4002

    Total 19761

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 12

    Dump Management:

    The waste dump will be stabilized with retaining wall by erecting a stone wall around toe

    of the dump on southern sides to a height of 6m. The surface water from waste dumps

    will be diverted into series of separate pits and the final pit water will be send to

    outside/mined out areas for recharge.

    2.8 CONCEPTUAL PLAN

    For any mine conceptual mining plan amounts to, fore-seeing in totality and planning for

    mining and related activities throughout its life span, till such time all the usable ore

    minerals are exhausted to the economical limits and lease area is reclaimed to the extent

    possible. Apart from physico-chemical and mineralogical parameters which form primary

    basis for compilation of conceptual mine plan, several other factors such as grade of sub

    grade ores, marketability and the norms laid down by the Government agencies from time

    to time do play important roles. With, ever increasing and changing needs of humanity,

    coupled with technological advancements, sub grade ores of the date become marketable

    ores in future.

    Therefore, preparation of ideal conceptual mine plan for any mine is difficult and such

    plan period prepared, remains acceptable only under given circumstances. It cannot be

    overlooked that, any such plan undergoes amendments and revisions in the course of

    progressive stages of exploration and exploitation. It is always borne in mind to bring

    back near natural shape to the area and its economic value is elevated. It is further

    ensured that, there is positive contribution to the environment and socio-economic

    development of the region.

    2.9 MINE DEVELOPMENT: For winning of Feldspar, Quartz & Mica, the over burden and side burden must be

    removed as a part of development. The removed waste will be dumped in a

    predetermined area within mine lease area. The waste dumps will be covered by

    afforestation in future.

    2.10 MINERAL RESERVES:

    The Pegmatite, which is consisting of Quartz, Feldspar and Mica is well exposed to a

    thickness of 20m from the surface i.e., upto 280m RL in working pits. It is also noticed

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 13

    from working pits, that the mineralization of pegmatite is continuing further depth from

    pit bottom. Based on the data, collected from working pits, the geological sections were

    prepared across the formation and these cross sectional area used for estimation of

    reserves by sectional method. The mineral reserves were established on UNFC guidelines

    and mine plan approved by the IBM.

    The tonnage factor of 2.5 is taken for Quartz & Feldspar and Mica. The calculations of

    reserves areas given below:

    Category

    & Pit no

    Section Influence

    Distance

    (m)

    Pegmatite

    Sectional

    area (m2)

    Volume

    of

    Pegmatite

    (m3)

    Reserves in tonne

    (@2.5t/m3)

    M.

    Waste

    Quartz

    @20%

    Feldspar

    @50%

    Mica

    @5%

    @25%

    (m3)

    G1 (P-3) A-A 50 252 12600 6300 15750 1575 3150

    G1 (P-3) B-B 40 299 11960 5980 14950 1495 2990

    G1 (P-3) C-C 55 282 15510 7755 19387.5 1938.75 3878

    G1 (P-1) D-D 24 524 12576 6288 15720 1572 3144

    G1 (P-1) E-E 40 311 12440 6220 15550 1555 3110

    G1 (P-1) F-F 31 332 10292 5146 12865 1286.5 2573

    G1 (P-2) G-G 25 0 0 0 0 0 0

    G1 (P-2) H-H 31 168 5208 2604 6510 651 1302

    G1 (P-4) I-I 16 252 4032 2016 5040 504 1008

    Total 42,309 1,05,773 10,577 21155

    G2 (P-3) A-A 50 160 8000 4000 10000 1000 2000

    G2 (P-3) B-B 40 214 8560 4280 10700 1070 2140

    G2 (P-3) C-C 55 230 12650 6325 15812.5 1581.25 3163

    G2 (P-1) D-D 24 562 13488 6744 16860 1686 3372

    G2 (P-1) E-E 40 490 19600 9800 24500 2450 4900

    G2 (P-1) F-F 31 376 11656 5828 14570 1457 2914

    G2 (P-2) G-G 25 165 4125 2062.5 5156.25 515.625 1031

    G2 (P-2) H-H 31 188 5828 2914 7285 728.5 1457

    G2 (P-4) I-I 16 144 2304 1152 2880 288 576

    Total 43106 107764 10776 21553

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 14

    Total Reserves of Quartz 85415 tonnes

    Total Reserves Feldspar 213537 tonnes

    Total reserves of Mica 21353 tonnes

    Total Mineral waste generation 42708m3

    Non-Mineable Reserves: Since the mineral is well deposited within the lease area and

    the safe benches will be formed in the country rock within the lease area without losing

    any mineral deposit. So the minerals estimated in above table are mineable reserves and

    there are no chances for blocking the mineral in 7.5m barrier and under final pit slopes.

    Table: 2.5 UNFC classification of Reserves & Resources estimation:

    Category Code Quantity of Minerals (t)

    Quartz Feldspar Mica

    Total Mineral Resources (A+B) 85415 213537 21353

    A. Mineral Reserves

    1. Proved Mineral Reserve 111 42309 105773 10577

    2. Probable Mineral Reserve 121 & 122 43106 107764 10776

    85415 213537 21353

    B. Remaining Resources

    1. Feasibility Mineral Resources 211 -- -- --

    2. Prefeasibility Mineral Resources 221 & 222 -- -- --

    3. Measured Mineral Resources 331 -- -- --

    4. Indicated Mineral Resources 332 -- -- --

    5. Inferred Mineral Resources 333 -- -- --

    6. Possible Resources 334 -- -- --

    2.11 LIFE OF THE MINE:

    It is proposed to raise about 8000T of Quartz, 20,000Tof Feldspar and 2000T of Mica per

    year on present exploration area.

    Anticipated life of Mine = Updated available reserves

    = 320305 =10.6years

    say 11Years Targeted production per annum 30000

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 15

    2.12 Land use

    The existing land use pattern of the mining area is given below:

    Table: 2.6- Existing Land Use Pattern

    S.No. Description Area is used in

    Hectares

    1 Working pits 1.8480

    2 Waste dump 1.1863

    3 Mineral stock 0.2711

    4 Road 0.5721

    5 Infrastructure 0.1477

    6 Greenbelt 1.2180

    7 Stock yard of ROM 2.7436

    Total 7.9868

    (Source: As per Approved Modified Mining Plan)

    The following additional area is required for mining activity in this plan period.

    Table: 2.7- Proposed Land Use Pattern

    S.No. Description Area is used in

    Hectares

    1 Working pits 0.1894

    2 Waste dump 1.0400

    3 Mineral stock --

    4 Road --

    5 Infrastructure --

    6 Greenbelt 0.3000

    7 Stock yard of ROM --

    8 Retaining wall & G. Drain 0.0320

    Total 1.5614

    2.13 Afforestation

    Plantation will be made over an area of 0.3000 ha as per the approved mining plan.

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 16

    No worked out area is going to be formed in this plan period. However, the green belt

    will be developed along the periphery of the ML area on southern side as detailed as:

    Table: 2.8 Year Wise greenbelt development

    Year Area proposed for plantation Plants proposed for the year

    2017-18 0.0600Ha 150 Nos

    2018-19 0.0600Ha 150 Nos

    2019-20 0.0600Ha 150 Nos

    2020-21 0.0600Ha 150 Nos

    2021-22 0.0600Ha 150 Nos

    Total 0.3000Ha 7500 plants

    2.14 Progressive Reclamation Plan

    As effective program of land restoration will be drawn and implemented to bring back the

    status to as near the pre mining conditions as possible.

    The salient features are as enumerate below:

    Agreen belt development along the periphery of the lease area will be taken up.

    The excavated area will be used as rain water harvesting pit

    The land usage by the end of the five years plan period is detailed below:

    Mining Activity Existing Land used

    patron (Ha)

    Area required for

    1st 5 years (Ha)

    Total area used for

    mining by the end

    of 5 years (Ha)

    Working pits 1.8480 0.1894 2.0374

    Waste dump 1.1863 1.0400 2.2263

    Mineral Stock 0.2711 -- 0.2711

    Road 0.5721 -- 0.5721

    Infrastructure 0.1477 -- 0.1477

    Greenbelt 1.2180 0.3000 1.518

    Stock yard of ROM 2.7436 -- 2.7436

    R.Wall & G. Drain -- 0.0320 0.032

    Total area 7.9868 Ha 1.5614 Ha 9.5482 Ha

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-2

    PROJECT DESCRIPTION

    2 - 17

    2.15 USE OF MINERALS

    The Quartz, Feldspar and Mica of this area are not meant for captive use. The mineral

    Quartz will be sold to the Ferro Alloy Industries, Foundaries, Ceramic and Glass

    Industries. Feldspar will be sold to the ceramic industries and Mica will be sold to the

    insulation manufacturers.

    2.16 Site Services -Utilities

    The site services are already provided by the lessee. Shelter to the workers, first aid

    facilities and toilets will be constructed & water will be provided to the workers in the

    mining area.

    Mine office

    A temporary mine office will be constructed at the mine site.

    Water supply

    Around 12.2 KLD of water will be required for the project activity. Out of which, 1.7

    KLD is required for drinking purpose, 5 KLD and 5.5 KLD for dust suppression and

    green belt respectively and will be made available through water tankers.

    Water is required in the mine for spraying on the roads and working faces to suppress the

    dust and also for use in the garage. Also a small quantity of drinking water is required.

  • CHAPTER III

    ANALYSIS OF

    ALTERNATIVES

  • SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER-3

    ANALYSIS OF ALTERNATIVES

    3- 1

    3.0 GENERAL

    Sri Bhagavan Mines, the proponent has been granted the lease by Government of Andhra

    Pradesh. The land is Govt. waste land. Mine is a site specific in an area of 33.029Ha.

    Mining activities shall be carried out based on local geology and availability of the

    mineral.

    3.1. ALTERNATE TECHNOLOGY:

    M/s. Sri Bhagavan Mines is having experience and progressive outlook in regularly

    updating its technology. The technology adopted by company in mining of Quartz,

    Feldspar, and Mica is very much reliable. The mining activity was proposed to be carried

    out by open cast method with the help of jack hammer drilling and blasting and using an

    excavator & tippers for excavation of the material in approved mining scheme.

    3.2 SITE ALTERNATIVES

    No necessity for the alternative analysis of the technology was observed as the

    technology/process mentioned for mining of the proposed mineral is best suitable.

    The selected site has the following advantages:

    Operational since last long and it is a renewal of mine without addition of mine lease

    area.

    The area chosen for mining activities is not having habitation of any kind.

    The site is well connected by road.

    Easy Availability of labour from nearby villages.

    No alternate sites are selected as the deposit is site specific.

    No necessity for the alternative analysis of the technology was observed as the

    technology mentioned for mining of the proposed project is best suitable.

  • CHAPTER IV

    DESCRIPTION OF ENVIRONMENT

  • [SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER IV

    DESCRIPTION OF

    ENVIRONMENT

    4 - 1

    4.0 INTRODUCTION

    Collection of base line data is an integral aspect of the preparation of Environmental

    Impact Assessment report. Base line data reflects the present status of Environment

    before the initiation of any activity. The possible effects due to the proposed mine

    project are estimated and superimposed on the compiled baseline data subsequently to

    assess Environmental Impacts.

    4.1 STUDY AREA

    Study area covers 10 km radius from proposed mine site located at sy.nos 326/1, 328,

    529, 530, 531, 534, 535, 536, 537, 538 & 549 of Turimerla village, Sydapuram

    Mandal, SPSR Nellore District, Andhra Pradesh.

    4.2 STUDY PERIOD

    The baseline environmental quality represents the background scenario of various

    Environmental components in the study area.

    As part of the Environmental Impact Assessment Study, baseline environmental

    monitoring was carried out for the month of January 2017 to March 2017.

    4.3 METHODOLOGY OF EIA STUDY

    The various steps involved in Environmental Impact Assessment Study of the mine

    site are divided into following phases:

    Identification of significant Environmental parameters and assessing the

    existing status within the impact zone with respect to air, water, noise, soil and

    socio-economic components of Environment. Following studies will be carried

    out:

    MICROMETEOROLOGICAL DATA

    AIR QUALITY EXISTING AMBIENT AIR QUALITY

    WATER ANALYSIS - GROUND WATER-SHALLOW WELLS, DEEPWELLS

    NOISE LEVELS

    FLORA AND FAUNA

    LAND ENVIRONMENT

    LAND USE / LAND COVER

  • [SRI BHAGAVAN MINES

    FINAL EIA REPORT

    CHAPTER IV

    DESCRIPTION OF

    ENVIRONMENT

    4 - 2

    SOIL CHARACTERISTICS and

    SOCIO ECONOMIC STATUS SURROUNDING THE PROJECT SITE.

    Study of various mining activities of the proposed mine to identify the area

    leading to impact/change in Environmental quality.

    Quantification/prediction of impact for the identified activities and to study the

    level of impact on various Environmental components.

    Evaluation of impacts after superimposing the predicted/quantified scenario

    over the baseline scenario.

    Formulation of Environmental Management Plan for implementation in the

    proposed project.

    4.4 COLLECTION OF BASELINE DATA

    4.4.1 MICRO METEOROLOGICAL DATA

    Micrometeorological studies are simultaneously conducted with the Ambient Air

    Quality monitoring. Meteorology plays an important role in the dispersion of

    pollutants. The meteorological data is very useful for interpretation of the base line

    information and for model study of air quality impacts also.

    A temporary meteorological station was installed at project site. The station was

    installed at a height of 4 mts above the ground level in such a way that there are no

    obstructions facilitating flow of wind, wind speed, wind direction, humidity and

    temperature are recorded on hourly basis.

    CLIMATE

    The tropical climate of the region is manifested as hot and humid summer, moderately