environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/formb/tor/pfr/...2018-03-31final...
TRANSCRIPT
-
FINAL ENVIRONMENTAL IMPACT
ASSESSMENT REPORT
OFOFOFOF
M/S. SRI BHAGAVAN MINES
Extent: 33.029 Ha
Sy.No.326/1,386, 529, 530, 531, 534, 535, 536, 537, 538 &
549, Turimerla (V)
Sydapuram (M)
S.P.S.R Nellore District, A.P
PREPARED BY
SV ENVIRO LABS & CONSULTANTS
H.O:Block-B, B-1, IDA, Autonagar -12, Vishakapatnam
Ph: 0891-2755528, Fax: 0891-2755529,
E-mail: [email protected]
Ph: 9440338628
QCI NABET Accredited& Recognized by MOE&F,
New Delhi.
September
2017
-
INDEX
S.No TITLE PAGE No.
I Executive Summary
Chapter -1:- Introduction
1.0 Purpose of the Project 1-1
1.1 Details of the project & identification of project proponent 1-2
1.2 Background information of the project 1-2
1.3 Brief Description of the project 1-3
1.3.1 Project Nature, Size and Location 1-3
1.4 Regulatory compliances & applicable Laws/Regulations 1-6
1.5 Environmental Parameters In The Study Area 1-6
1.6 Generic Structure Of EIA Document 1-6
1.7 Approved Terms of Reference compliance 1-7
1.8 General Conditions 1-19
1.9 Post Environment Clearance Monitoring 1-20
Chapter -2 :-Project Description
2.1 Description of the Project 2-1
2.2 Location Details 2-2
2.2.1 Details about project site 2-2
2.3 Geology and Exploration 2-7
2.3.1 Area Geology 2-7
2.3.2 Geology of this mine 2-7
2.4 Details of Exploration 2-8
2.4.1 Method of Mining 2-8
2.5 Details of Production 2-9
2.5.1 Yeas wise production for the next five years 2-9
2.5.2 Year wise production for ensuing five years 2-10
2.6 List of Mining Machinery 2-11
2.7 Nature and generation of waste 2-11
2.8 Conceptual Plan 2-12
2.9 Mine Development 2-12
2.10 Mineral Reserves 2-12
2.11 Life of the Mine 2-14
2.12 Land Use 2-15
2.13 Afforestation 2-15
2.14 Progressive Reclamation Plan 2-16
2.15 Use of Minerals 2-17
2.16 Site Services-Utilities 2-17
Chapter -3:- Analysis of Alternatives
3.0 General 3-1
3.1 Alternate Technology 3-1
3.2 Site Alternatives 3-1
-
Chapter -4:-Description Of The Environment
4.0 Introduction 4-1
4.1 Study area 4-1
4.2 Study Period 4-1
4.3 Methodology of EIA study 4-1
4.4 Collection of Baseline Data 4-2
4.4.1 Micro Meteoreological Data 4-2
4.4.2 Winds 4-3
4.5 Air Environment 4-5
4.5.1 Selection of Sampling Locations 4-5
4.5.2 Methodology of Sampling and Analysis 4-5
4.5.3 Frequency of Sampling 4-6
4.5.4 Description of Sampling Locations 4-8
4.5.5 Existing Ambeint Air Quality 4-12
4.6 Water Environment 4-13
4.6.1 Surface Water and Ground Water Quality Assessment 4-13
4.6.2 Sampling Techniques 4-14
4.6.3 Water Sampling Locations 4-16
4.6.4 Ground Water Quality of the Study Area 4-18
4.6.5 Surface water quality results 4-21
4.6.6 Summary of Groundwater quality 4-21
4.7 Soil Quatliy 4-22
4.7.1 Selection of Sampling Locations 4-22
4.7.2 Sampling and Analytical Techniques 4-22
4.7.3 Details of Soil Sampling Locations 4-23
4.7.4 Soil Analysis Results in the Study Area 4-25
4.7.5 Summary of Soil Analysis Data 4-26
4.7.6 Standard Soil Classification 4-28
4.8 Noise Enviornment 4-30
4.8.1 Identification of Sampling Locations 4-30
4.8.2 Methodology 4-30
4.8.3 Noise Monitoring Locations 4-31
4.8.4 Description of Locations 4-31
4.8.5 Noise Levels in the Study Area 4-33
4.9 Land Use/Land Cover 4-36
4.10 Biological Environmentd 4-43
4.11 Socio Economic Environment 4-61
Chapter -5:-Anticipated Environmental Impacts & Mitigation Measures
5.0 Introduction 5-1
5.1 Air Environment 5-9
5.1.1 Impact due to transportation 5-9
5.1.2 Air Quality Mitigation Measures 5-9
5.2 Water Environment 5-10
-
5.2.1 Impacts on surface water bodies and control measures 5-10
5.2.2 Water consumption and waste water generation 5-11
5.2.3 Rain Water Harvesting 5-12
5.3 Land Environment 5-13
5.3.1 Impact due to land degradation 5-13
5.3.2 Land reclamation control measurs 5-13
5.3.2.1 Reclamation of land affected due to mining activites 5-13
5.3.2.2 Soil conservation measures and Top soil management 5-13
5.3.2.3. Maintenance of road 5-14
5.3.3 Programme of Afforestation 5-14
5.3.4 Land Use 5-15
5.4 Noise Environment 5-15
5.4.1 Impact due to Noise and Vibration 5-15
5.4.2 Noise and Vibration Control Measures 5-16
5.5 Solid waste generation and stacking of wastes 5-17
5.6 Biological Enviornment 5-17
5.6.1 Mitigation Measures 5-19
5.7 Traffic Analysis 5-22
5.7.1 Impact on road network 5-23
5.8 Socio-Economic Conditions 5-23
5.8.1 Impact on socio-economic conditions 5-23
5.9 Impact on Occupational Health and Safety 5-24
5.10 Mines Waste Management 5-24
Chapter -6:-Environmental Monitoring Programme
6.0 Environmental Monitoring 6-1
6.1 Monitoring around th mine site 6-1
6.2 Post project monitoring programme 6-2
6.2.1 Environmental Monitoring 6-2
6.3 Monitoring schedule for environmental parameters 6-2
6.4 Implementation Schedule 6-3
6.5 Infrastructure for environmental protection & socio economic 6-4
6.6 Monitoring Equipment and Consumables 6-4
Chapter -7:-Additional Studies
7.1 Risk Assessment 7-1
7.2 Air Environment 7-1
7.3 Disaster Management Plan 7-3
7.4 Identificatin of Hazards 7-3
7.4.1 Filling up the mine pit due to excessive rains 7-3
7.4.2 Failure of slope in the pit 7-4
7.4.3 Failure of slope of dump 7-4
7.4.4 Accidents of heavy machinery 7-4
7.4.5 Seismic activity 7-4
-
7.4.6 Surface fire 7-4
7.5 Safety Preparedness Plan 7-4
7.6 Training 7-5
7.7 Implementation of EMP and Montoring System 7-6
7.7.1 General 7-6
7.8 Implementation 7-7
7.9 Activites to be monitored/inspected by EMC 7-7
7.9.1 Land Erosion 7-7
7.9.2 Drainage 7-7
7.9.3 Re-vegetation and green belt development 7-9
7.9.4 Occupational health 7-9
Chapter -8:-Project Benefits
8.0 General 8-1
8.1 Employment 8-1
8.2 Occupational health 8-1
8.3 Improvements in physical and social infrastructure 8-1
8.3.1 Improvement in the Physical Infrastructure 8-2
8.3.2 Improvement in the Social Infrastructure 8-2
8.3.3 Increase in Employment Potential 8-2
8.3.4 Prevention of Illegal Mining & Contribution to the Exchequer 8-3
8.3.5 Enhancement of Green Cover 8-3
8.4 Health 8-3
Chapter -9:-Environmental Management Plan
9.0 Introduction 9-1
9.1 Applicable Regulations 9-2
9.2 Objectives of Environmental Management Plan 9-4
9.3 Air Quality Management 9-4
9.3.1 Controlling Dust Levels 9-5
9.3.2 Air Pollution Control Measures 9-5
9.3.3 Controlling of NOx Levels 9-5
9.4 Water Quality Management 9-6
9.5 Noise Level Monitoring 9-7
9.5.1 Parameters 9-8
9.5.2 Methodology 9-8
9.5.3 Noise Quality Management 9-8
9.5.4 Noise Pollution Control 9-8
9.6 Biological Management 9-8
9.6.1 Tree Plantation Program 9-9
9.6.2 Mine Drainage 9-9
9.7 Soil Management 9-9
9.8 Proposed Mitigation Measures 9-10
9.8.1 Land Enviornment 9-10
9.8.1.1 Land use 9-10
-
9.8.1.2 Calendar plan 9-11
9.8.1.3 Mine roads 9-11
9.8.1.4 Storage and preservation of top soil 9-11
9.8.1.5 Soil erosion control 9-12
9.8.1.6 Land restoration 9-12
9.9 Socio-Economic Environment & Safety 9-13
9.10 Biological Management Plan 9-13
9.10.1 Green Belt Development/Afforestation Plan 9-13
9.10.2 Design of Green Development 9-14
9.11 Occupational Health and Safety Measures 9-14
9.12 Public Health Implication, Occupational Health Survey Program
and First Aid
9-15
9.13 Project Cost 9-16
Chapter -10:-Summary & Conclusion
10.0 Summary & Conclustion 10-1
10.1 Recommendation 10-1
Chapter -11:-Disclosure Of Consultants Engaged
11.0 Disclosure of Consultants Engaged 11-1
11.1 Services Offered by SV Enviro 11-1
11.2 EIA Team 11-2
-
LIST OF TABLES
TABLE NO. TITLE PAGE NO.
Chapter -1:- Introduction
1.1 Description of Project Proponent 1-2
Chapter -2 :-Project Description
2.1 Details about the Project Site 2-2
2.2 Year wise proposed development & production from opencast
mining
2-9
2.3 Details of machinery 2-11
2.4 Waste generated in the scheme period 2-11
2.5 UNFC classification of Reserves & Resources estimation 2-14
2.6 Existing Land Use Pattern 2-15
2.7 Proposed Land Use Pattern 2-15
2.8 Year Wise greenbelt development 2-16
Chapter -4:-Description Of The Environment
4.1 Micro Meteorological Data at Site 4-3
4.2 Techniques and Detectable limits for Ambient Air Quality
Monitoring
4-6
4.3 Location of Ambient Air Quality Monitoring Stations 4-6
4.4 Summary of Analysis of Ambient Air Quality in the Study
Area
4-9
4.5 Standard Operating Procedures (SOP) For Water Sampling 4-14
4.6 Analytical Techniques For Water Analysis 4-15
4.7 Water Sampling Stations 4-16
4.8 Ground water quality results 4-18
4.9 Surface Water Quality of the Study Area 4-20
4.10 Analytical Techniques For Soil Analysis 4-23
4.11 Soil Sampling Locations 4-23
4.12 Soil Analysis Results 4-25
4.13 Noise Monitoring Locations 4-31
4.14 Noise Levels in the Study Area 4-33
4.15 Flora enumerated from both Core and Buffer zones of the
proposed mining
4-45
4.16 List of Vertebrate fauna found in the study area 4-55
4.17 Details of proposed plantation 4-58
4.18 Selected list of plant species for Greenbelt development 4-60
4.19 Particulars of the agriculture of Nellore district 4-65
4.20 Particulars of the participants in primary survey 4-67
Chapter -5:-Anticipated Environmental Impacts & Mitigation Measures
5.1 Expected Nature of Impacts 5-1
5.2 Identified/Predicted Environmental Impacts with & without 5-2
-
Mitigation Measures
5.3 Green Belt Plan 5-14
5.4 Existing Land Use Pattern 5-15
5.5 Noise impact 5-16
5.6 Suggested trees for greenbelt development 5-21
Chapter -6:- Environmental Monitoring Programme
6.1 Monitoring Schedule for Environmental Parameters 6-2
6.2 Implementation Schedule 6-3
Chapter -7:-Additional Studies
7.1 Predicted GLC due to proposed mining project 7.2
Chapter -9:- Environmental Management Plan
9.1 EMP costing for the proposed project 9-3
9.2 Ambient Air Quality Standards 9-4
9.3 Air Pollution Control Measures 9-5
9.4 Water Requirement & Waste water generation 9-6
9.5 Details of Year Wise Tree Plantation Programme 9-14
Chapter -11:- Disclosure of Consultants
11.1 List of Experts Involved 11-2
-
LIST OF FIGURES
FIGURE NO. TITLE PAGE NO.
Chapter -1 :-Introduction
1.1 Location map of project site 1-5
Chapter -2: - Project Description
2.1 Google map (10km radius) 2-4
2.2 Topo map of 10km radius 2-5
2.3 Lease Sketch 2-6
Chapter -4:-Description Of The Environment
4.1 Wind Rose Diagram for the month of January 17-
February17
4-4
4.2 Ambient Air Quality Monitoring Location Maps 4-7
4.3 Water Sampling Locations 4-17
4.4 Soil Sampling Locations 4-24
4.5 Noise Monitoring Locations 4-32
4.6 Flow Chart Of Methodology 4-38
4.7 Roads & Built up area 4-40
4.8 Contour Map 4-41
4.9 Drainage Map 4-42
Chapter -7:-Additional Studies
7.1 Predicted GLC by AERMOD 7-2
7.2 Organizational setup of EMC 7-6
7.3 Drainage Map 7-8
Annexures
Annexure -I ToR Copy
Annexure -II Mine Lease documents
Aneexure -III Approved Mining Plan
Annexure IV Mine drawings
Annexure-V Violation clearance documents
Annexure- VI Minutes of Public Hearing
Annexure - VII NABET Copy
-
CHAPTER I
INTRODUCTION
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 1
INTRODUCTION
1.0 PURPOSE OF THE PROJECT
M/s. Sri Bhagavan Mines of 33.029Ha for producing Mica, Quartz and Feldspar of
mining lease area at sy no. 326/1, 328, 529, 530, 531, 534, 535, 536, 537, 538 & 549
of Turimerla Village, Sydapuram Mandal, S.P.S.R Nellore district, Andhra Pradesh.
M/s. Sri Bhagavan Mines proposes to obtain Environmental Clearance for the above
mine from State Expert Appraisal Committee, Andhra Pradesh (SEAC, AP). The
proposed project is categorized as Category B project as per Environmental Impact
Assessment (EIA) Notification SO 1533, of 14-09-2006 and subsequent amendment
notifications.
Environmental Impact Assessment (EIA) is a process, used to identify the
Environmental, social and economic impacts of a project prior to decision-making. It
is a decision making tool, which guides the decision makers in taking appropriate
decisions for proposed projects. EIA systematically examines both beneficial and
adverse consequences of the proposed project and ensure that these impacts are taken
into account during the project development & operational phases.
The Environmental Impact Assessment report has been prepared in terms of EIA
notification of the MoEF dated 14-9-2006, as amended on 1st Dec 2009, 4
th April
2011and approved ToRs vide Lr. No: SEIAA/AP/AP NLR MIN 05 2016 89 Dt:
13.07.2016, for seeking Environmental Clearance for mining in the name of Sri
Bhagavan Mines measuring 33.029 hectares falling under category B. Baseline
survey of existing Environmental attributes are also conducted which helped in
evaluating Environmental impacts due to the proposed activities and in formulating a
scientific Environmental Management Plan (EMP).
Presentation of TOR has been made before the SEAC, A.P committee and the TOR
has been issued vide Lr No. SEIAA/AP/AP NLR MIN 05 2016 89 dated 13.07.2016
which is attached as Annexure -1. As per the TOR, baseline data collected for one
season i.e., non-monsoon season. The study area comprises of the core zone (lease
area) and the buffer zone (10 kms around the core zone from the periphery).
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 2
1.1 DETAILS OF THE PROJECT & IDENTIFICATION OF PROJECT
PROPONENT
M/s. Sri Bhagavan Mines, is the applicant for this mining project
Table: 1.1 Description of Project Proponent
Address of the
lessee
M/s. Sri Bhagavan Mines
M. G Nagaraju (Lessee)
3-6-200/401, 4th
Floor, Arunodaya Apartment, Behind Minerva
Hotel, Himayath Nagar, Hyderabad - 500029
Cell No: 9246351239
Address of Mine Sy. No: 326/1, 328, 529, 530, 534, 535, 536, 537, 538 & 549
Turimerla Village, Sydapuram Mandal,
S.P.S. R Nellore District, Andhra Pradesh.
1.2 Background Information of the Project:
G. Narayana Setty has applied for grant of mining lease for Quartz, Mica, Feldspar
mine over an extent of 33.029 hectares which is located in Sy.No.326/1,328,529 to
531, 534 to 538, & 549 of Tirumerla (V), Sydapuram (M), Nellore Dist., of A.P. got
grant in favor of Sri. G.Narayana Setty Vide G.O. Ms. No. 201, dt: 18-10-1996 and
the Mining Lease was executed by ADMG, Nellore, Vide Proc. No. 3852/M2/96, Dt:
27-02-1997 for a period of 20 years from 27-02-1997 to 26-02-2017 in favor of Sri.
G.Narayana Setty. After 10 years, the M.L was transferred in favor of M/s. Bhagavan
Mines and the transferred of Mining Lease was executed by ADMG, Nellore, Vide
Proc. 3852/M2/96, dt: 01-02-2008 for un-expired of lease portion i.e., up to 26-02-
2017 in favour of M/s Bhagavan Mines.
The first mining was approved by IBM vide Lt No. 659(221)/MC/96/NLR, Dt: 20-8-
1996 under Rule 24 of MCR 1960 to get grant of mining lease.
After mining lease was transferred in favor of M/s Bhagavan Mines, 1st scheme of
mining was approved by IBM vide Lt. No. 659/M.S/MC/2007/Hyd, dt: 13-05-2008
for five years period of 2008-09 to 2012-13.
2nd
scheme of mining was approve by Dept Director of Mines and Geology, Guntur
vide Lt.No. 4572/Ms/NLR/2016, Dt: 25-2-2016 for the period of 2016-17.
1st renewal of Quarry lease application was filed by M/s. Sri Bhagavan Mines on
27.10.2015. ADMG, Nellore submitted proposal for grant of 1st renewal of Quarry
lease for Mica, Quartz & Feldspar over an extent of 81.58Ac (33.029Ha) in sy.nos
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 3
326/1, 328, 529, 530, 531, 534, 535, 536, 537, 538 & 549 of Turimerla village,
Sydapuram Mandal, SPSR Nellore Dist in favour of M/s. Bhagavan Mines. As per the
ADM&G, Nellore file no: 5210/P/2015 Dt: 21.10.2016, Assistant Director of Mines
and Geology, Nellore submitted proposals recommending for grant of 1st renewal of
Quarry Lease for Mica, Quartz & Feldspar over an extent of 81.58Acres in sy. nos:
326/1, 328, 529 to 531, 534 to 538 & 549 of Turimerla village, Sydapuram Mandal,
SPSR Nellore District for a further period of 20 years w.e.f 26.02.2017 in favour of
Sri M/s. Sri Bhagavan Mines.
M/s. Bhagavan Mines, Mg. Partner: Sri G. Nagaraju is requested by Director of Mines
and Geology to submit mining plan along with CFE, CFO and EC for grant of 1st
renewal within period of (6) months from the date of issue of the notice No:
17454/R3-1/2016 Dt: 05.01.2017. Mining plan was approved by Deputy Director of
Mines & Geology, Guntur vide Letter No 616/MP/NLR/2017 dated 03.03.2017.
1.3 BRIEF DESCRIPTION OF THE PROJECT
As per the approved mining plan (Lr. No: 616/MP/NLR/2017 Dt: 03-03-2017), M/s.
Sri Bhagavan Mines had a mining lease for Mica, Feldspar & Quartz over an extent of
33.029 Ha in Sy. No: 326/1, 328, 529, 530, 534, 535, 536, 537, 538 & 549 of
Turimerla Village, Sydapuram Mandal, S.P.S.R Nellore District, Andhra Pradesh.
The present proposal is for production of 8000 TPA of Quartz, 20000 TPA of
Feldspar and 2000 TPA of Mica and the mining activity is carried out by
Opencast method.
1.3.1 Project Nature, Size and Location
Nature
The proposed project is mining of Mica, Quartz & Feldspar in the lease area of
33.029Ha of Government waste land. The method of mining is manual open cast for
the production of Mica, Feldspar and Quartz.
Size
The proposed production of mine is 2000 TPA of Mica, 20000 TPA of Feldspar and
8000 TPA of Quartz. The anticipated life of mine will be 11 years as per targeted
production and past exploration.
Location
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 4
The mining area is located in Turimerla Village of Sydapuram Mandal at SPSR
Nellore District, Andhra Pradesh. The area is located at a distance of 34 Km from the
district headquarters.
The mine lease area falls under the Toposheet No. 57 N/4 bearing Toposheet details.
Geo-coordinates:
B.P no Latitude (WGS-84) Longitude (WGS-84)
BP1 N141741.1 E794252.5
BP2 N141713.6 E794251.4
BP3 N141712.6 E794249.8
BP4 N141710.6 E794247.8
BP5 N141708.7 E794246.0
BP6 N141706.2 E794243.7
BP7 N141701.2 E794239.6
BP8 N141700.0 E794244.3
BP9 N141655.0 E794243.0
BP10 N141648.9 E794240.9
BP11 N141644.4 E794239.6
BP12 N141645.0 E794236.0
BP13 N141642.7 E794235.4
BP14 N141642.2 E794237.1
BP15 N141641.9 E794239.2
BP16 N141641.5 E794241.9
BP17 N141637.4 E794241.3
BP18 N141634.8 E794247.5
BP19 N141641.3 E794252.0
BP20 N141640.9 E794255.3
BP21 N141645.2 E794256.2
BP22 N141650.1 E794255.0
BP23 N141653.6 E794255.1
BP24 N141654.2 E794249.6
BP25 N141700.7 E794248.6
BP26 N141708.9 E794251.2
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 5
Accessibility
Road Link
The area is connected by BT road- Thummala Talupur Road at 1.91 Km which is
connected to Nellore-Rapur Road which is at a distance of 5.85 Km from mine lease
area. State Highway 58 connecting Gudur and Rajampet at 9.70 Km. NH-5 at 18.85
Km at SE.
Rail link
The nearest rail head is Gudur Railway Station at a distance of 20.15 from the mine
lease area.
Air link
The nearest airport facility is available at Tirupathi which is about 73.55 Km away
from mine.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 6
Fig: 1.1 Location Map
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 7
1.4 REGULATORY COMPLIANCES & APPLICABLE LAWS/REGULATIONS
a) The mining plan for the current mining scheme was approved by Department of
Mines and Geology vide Letter No. 316/MP/NLR/2017 dated 03.03.2017 for 5
years from 2017-18 to 2021-22.
b) There are no legal cases & issues against the project and project proponent related
with this mine.
c) There are no National parks/ Sanctuaries notified under Wildlife Protection Act
within 10km radius.
1.5 ENVIRONMENTAL PARAMETERS IN THE STUDY AREA
Collection of Base line data is an Integral aspect of the preparation of Environmental
Impact Assessment report. Base line data reflects the present status of Environment
before the initiation of any activity of the proposed project. The possible effects due
to the proposed mine project are estimated and superimposed on the compiled
baseline data subsequently to asses Environmental impacts.
Pre Project Environment assessment was conducted in the study area during January
2017 to March2017. Studies were under taken to generate base line data of the
following:-
1. MICROMETEOROLOGICAL DATA.
2. AIR QUALITY EXISTING AMBIENT AIR QUALITY.
3. WATER ANALYSIS - GROUND WATER.
4. NOISE LEVELS.
5. FLORA AND FAUNA.
6. LAND ENVIRONMENT.
7. LAND USE / LAND COVER.
8. SOIL CHARACTERISTICS and
9. SOCIO ECONOMIC STATUS SURROUNDING THE PROJECT SITE.
1.6 GENERIC STRUCTURE OF EIA DOCUMENT
In terms of the EIA notification of the MoEF dated 14th September 2006 as amended
Dec 2009, the generic structure of the EIA document should be as under:
1. Introduction
2. Project Description
3. Description of the Environment
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 8
4. Anticipated environmental Impact & Mitigation Measures
5. Analysis of alternatives (Technology and site)
6. Environmental Monitoring Program
7. Additional Studies
8. Project Benefits
9. Environmental Management Plan
10. Summary & Conclusion
11. Disclosure of Consultants engaged
1.7 APPROVED TERMS OF REFERENCE COMPLIANCE
ToR Lr. No: SEIAA/AP NLR MIN 05 2016 89 Dt: 13.07.2016
Sl.
No.
TOR Points TOR Compliance/Section No.
1. Year-wise production details since 1994
should be given, clearly stating the highest
production achieved in any one year prior to
1994. It may also be categorically informed
whether there had been any increase in
production after the EIA Notification, 1994
came into force w.r.t. the highest production
achieved prior to 1994.
The first lease was granted vide Letter
No. G.O.Ms. No.201 dated 18-10-
1996 in favor of G. Narayana Setty.
Mining lease was executed by
ADMG, Nellore vide proc. No.
3852/M2/96 dt. 27-02-1997 for 20
years from 27-02-1997 to 26-02-
2017.
After 10 years, the M.L was
transferred in favor of M/s Sri
Bhagavan Mines vide G.O Ms.
No.292, dt 07-11-2017 and transfer of
mining lease was executed by
ADMG, Nellore v vide Proc. No.
3852/M2/96, dt:01-02-2008 for an un-
expired lease period i.e., up to 26-02-
2017 in favor of M/s Sri Bhagavan
Mines.
After transfer, the first mining plan
was approved by IBM vide Lr No.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 9
659(221)/MC/96/NLR, Dt: 20-08-
1996.
The 1st scheme was approved by IBM
vide letter No: 659
/37MS/MC/2007/Hyd Dated:
13.05.2008, period of 5 years from
2008-09 to 2012-13.
1st renewal of Quarry lease
application was filed by M/s Sri
Bhagavan Mines on 27-10-2015.
Director of Mines and Geology
requested to submit CFE, CFO and
EC for grant of 1st renewal within 6
months from the date of issue of the
notice no. 17454/R3-1/2016, Dt: 05-
01-2017.
The second scheme of mining period
i.e. 2016-17 to 2021-22 was approved
by Dept. Director of Mines and
Geology, Guntur vide Lr. No.
4572/Ms/NLR/2016, Dt: 25-02-2016.
Year-wise production details since
2008 are as follows:
Year Mica Feldspar Quartz
2008 210.0 3440.915 250.0
2009 710.0 4932.98 Nil
2010 954.0 1142.475 Nil
2011 529.0 Nil Nil
2012 512.0 Nil Nil
2013 214.0 150.0 Nil
2014 316.020 700.0 200.0
2015
(only
January
month)
50.0 100.0 Nil
2. A copy of the document in support of the fact
that the Proponent is the rightful lessee of the
mine should be given.
Lease documents are attached as Annexure
II and approved mining plan is attached as
Annexure -III
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 10
3. All documents including approved mine plan,
EIA and public hearing should be compatible
with one another in terms of the mine lease
area, production levels, waste generation and
its management and mining technology and
should be in the name of the lessee.
While preparing EIA it has been ensured that
all the documents including approved mine
plan, EIA are compatible with one another in
terms of the mine lease area, production
levels, waste generation and its management,
mining technology etc and are in the name of
lessee.
4. All corner coordinates of the mine lease area,
superimposed on a High Resolution
Imagery/topo sheet should be provided. Such
an Imagery of the proposed area should
clearly show the land use and other ecological
features of the study area (core and buffer
zone).
All the corner coordinates of mine lease are
has been marked/superimposed on toposheet.
10 km radius Topo map of 1:50,000 scale of
the proposed project location with all the
corner coordinates of the mine lease area is
given in Chapter 2; Fig. 2.2.
Corner co-ordinates are superimposed on
High resolution Google earth imagery is
given in Chapter-2 under Fig 2.1.
5. Information should be provided in Survey of
India Topo sheet in 1:50000 scale indicating
geological map of the area, geomorphology of
land forms of the area, existing minerals and
mining history of the area, important water
bodies, streams and rivers and soil
characteristics.
The area is located in Survey of India
Toposheet no: 57N/11 shown in chapter -2
under fig no: 2.2
6. Details about the land proposed for mining
activities should be given with information as
to whether mining conforms to the land use
policy of the state: land diversion for mining
should have approval from state land use
board or the concerned authority.
The land of mining is located at sy.no: 326/1,
328, 529, 530, 531, 534, 535, 536, 537, 538
& 549 of Turimerla Village, Sydapuram
Mandal, SPSR Nellore Dt. The land is
Government waste land comprising of
33.029Ha. The Detailed land use of core zone
is given in chapter -2 under table no: 2.7
7. It should be clearly stated whether the
proponent company has a well laid down
Environment Policy approved by its Board of
Directors? If so, it may be spelt out in the EIA
The project proponent is committed to
environmental safeguard and sustainable
development. Environmental Monitoring Cell
shall be established for reporting
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 11
report with description of the prescribed
operating process/procedures to bring into
focus any infringement/deviation/violation of
the environmental or forest norms/conditions?
The hierarchical system or administrative
order of the Company to deal with the
environmental issues and for ensuring
compliance with the EC conditions may also
be given. The system of reporting of non-
compliances / violations of environmental
norms to the Board of Directors of the
Company and/or shareholders or stakeholders
at large may also be detailed in the EIA
report.
environmental issues. The Environmental
policy is as follows:
Prevent Environmental pollution by
continual improvement in
environmental performance of the
Environmental Management Plan
Comply with all the environmental
legislations, regulations under the
EIA Notification 2006 & subsequent
amendments.
Promote environmental awareness
amongst employees, local
communities and interested parties
through proactive communication and
training.
Training to employees in terms of
Safety, Health & Environment
8. Issues relating to Mine Safety, including
subsidence study in case of underground
mining and slope study in case of open cast
mining, blasting study etc. should be detailed.
The proposed safeguard measures in each
case should also be provided.
The method of mining is opencast method
with the help of jackhammer drilling and
blasting.
Safety related issues in detailed explained in
Chapter-7 under section: 7.5.
9. The study area will comprise of 10 km zone
around the mine lease from lease periphery
and the data contained in the EIA such as
waste generation etc should be for the life of
the mine / lease period.
The study area is taken as 10km radius
around the proposed mine.
Every year about 3952m3 of mineral waste
will be generated on an average and about
19761m3 of mineral waste will be generated
during this plan period.
10. Land use of the study area delineating forest
area, agricultural land, grazing land, wildlife
sanctuary, national park, migratory routes of
fauna, water bodies, human settlements and
other ecological features should be indicated.
Land use/Land cover is exclusively detailed
in section 4.9 of Chapter-4 and their impacts
are mentioned in chapter -5.
Land use plan of plan of mine lease area is
mentioned in chapter -2 under table no: 2.7
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 12
Land use plan of the mine lease area should
be prepared to encompass preoperational,
operational and post operational phases and
submitted. Impact, if any, of change of land
use should be given.
11. Details of the land for any Over Burden
Dumps outside the mine lease, such as extent
of land area, distance from mine lease, its
land use, R&R issues, if any, should be given.
OB Dump area is 10400 m2
within the mine
lease area. No R& R issues.
12. A Certificate from the Competent Authority
in the State Forest Department should be
provided, confirming the involvement of
forest land, if any, in the project area. In the
event of any contrary claim by the Project
Proponent regarding the status of forests, the
site may be inspected by the State Forest
Department along with the Regional Office of
the Ministry to ascertain the status of forests,
based on which, the Certificate in this regard
as mentioned above be issued. In all such
cases, it would be desirable for representative
of the State Forest Department to assist the
Expert Appraisal Committees.
There is no forest land involved in the
proposed mine lease area. Hence, clearance
from State forest department is not
applicable.
13. Status of forestry clearance for the broken up
area and virgin forestland involved in the
Project including deposition of net present
value (NPV) and compensatory afforestation
(CA) should be indicated. A copy of the
forestry clearance should also be furnished.
There is no forest land involved in the
proposed mine lease area.
Hence forest clearance is not required.
14. Implementation status of recognition of forest
rights under the Scheduled Tribes and other
Traditional Forest Dwellers (Recognition of
Forest Rights) Act, 2006 should be indicated.
Not Applicable
15. The vegetation in the RF / PF areas in the Ecological Studies in Reserve forest is
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 13
study area, with necessary details, should be
given.
mentioned in Chapter-4, under section
Biological Environment.
16. A study shall be got done to ascertain the
impact of the Mining Project on wildlife of
the study area and details furnished. Impact of
the project on the wildlife in the surrounding
and any other protected area and accordingly
detailed mitigative measures required, should
be worked out with cost implications and
submitted.
There is no wildlife sanctuary within the
study area. Details of fauna existing within
the study area are given in Chapter -4 under
section 4.10.
Anticipated impact of mining on the same
along with suggested mitigation measures are
incorporated in Chapter -5.
17. Location of National Parks, Sanctuaries,
Biosphere Reserves, Wildlife Corridors,
Tiger/Elephant Reserves/(existing as well as
proposed), if any, within 10 km of the mine
lease should be clearly indicated, supported
by a location map duly authenticated by Chief
Wildlife Warden. Necessary clearance, as
may be applicable to such projects due to
proximity of the ecologically sensitive areas
as mentioned above, should be obtained from
the State Wildlife Department/Chief Wildlife
Warden under the Wildlife (Protection) Act,
1972 and copy furnished.
There are no notified Sanctuaries, National
Parks, Biosphere Reserves, and Wildlife
corridors present within 10 km of the mine
lease area.
18. A detailed biological study of the study area
[core zone and buffer zone (10 km radius of
the periphery of the mine lease)] shall be
carried out. Details of flora and fauna, duly
authenticated, separately for core and buffer
zone should be furnished based on such
primary field survey, clearly indicating the
Schedule of the fauna present. In case of any
schedule-I fauna found in the study area, the
necessary plan for their conservation should
be prepared in consultation with State Forest
Detailed Biological study in core zone and
buffer zone is enclosed in Chapter -4 under
section 4.10. No Schedule I Fauna is found
and hence no conservation plan is prepared as
either core or buffer zone are not ecologically
sensitive.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 14
and Wildlife Department and details
furnished. Necessary allocation of funds for
implementing the same should be made as
part of the project cost. The Conservation
Plan for Schedule-I species shall be approved
by the Chief Wildlife Warden of the State
Government.
19. Proximity to Areas declared as Critically
Polluted or the Project areas likely to come
under the Aravali Range, (attracting court
restrictions for mining operations), should
also be indicated and where so required,
clearance certifications from the prescribed
Authorities, such as the SPCB or State
Mining Dept. Should be secured and
furnished to the effect that the proposed
mining activities could be considered.
The proposed project does not fall within
10km radius of any Critically polluted area
and also it does not come under the Aravali
Range.
20. Similarly, for coastal Projects, A CRZ map
duly authenticated by one of the authorized
agencies demarcating LTL. HTL, CRZ area,
location of the mine lease w.r.t CRZ, coastal
features such as mangroves, if any, should be
furnished. (Note: The Mining Projects falling
under CRZ would also need to obtain
approval of the concerned Coastal Zone
Management Authority).
Not applicable as the project does not fall in
the CRZ area.
21. R&R Plan/compensation details for the
Project Affected People (PAP) should be
furnished. While preparing the R&R Plan, the
relevant State/National Rehabilitation &
Resettlement Policy should be kept in view.
In respect of SCs/STs and other weaker
sections of the society in the study area, a
need based sample survey, family-wise,
As per the Socio-Economic Survey, no R&R
plan is envisaged; as there is no habitation
within proposed mining area hence no
displacement of people is envisaged from
their respective areas due to proposed mining
project.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 15
should be undertaken to assess their
requirements, and action programmes
prepared and submitted accordingly,
integrating the sectoral programmes of line
departments of the State Government. It may
be clearly brought out whether the village
located in the mine lease area will be shifted
or not. The issues relating to shifting of
Village including their R&R and socio-
economic aspects should be discussed in the
report.
22. One season (non-monsoon) primary baseline
data on ambient air quality (PM10, SO2 and
NOx), water quality, noise level, soil and
flora and fauna shall be collected and the
AAQ and other data so compiled presented
date-wise in the EIA and EMP Report. Site-
specific meteorological data should also be
collected. The location of the monitoring
stations should be such as to represent whole
of the study area and justified keeping in view
the pre-dominant downwind direction and
location of sensitive receptors. There should
be at least one monitoring station within 500
m of the mine lease in the pre-dominant
downwind direction. The mineralogical
composition of PM10, particularly for free
silica, should be given.
Baseline data was collected during the month
of January2017 to March2017 and the
results are given in Chapter- 4 Description
of Environment.
23. Air quality modeling should be carried out for
prediction of impact of the project on the air
quality of the area. It should also take into
account the impact of movement of vehicles
for transportation of mineral. The details of
the model used and input parameters used for
Prediction of impacts on air Environment has
been carried out employing mathematical
model by using AERMOD was done and
mentioned in Chapter -7.
Wind rose map showing pre-dominant wind
direction has been carried out and the results
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 16
modeling should be provided. The air quality
contours may be shown on a location map
clearly indicating the location of the site,
location of sensitive receptors, if any, and the
habitation. The wind roses showing pre-
dominant wind direction may also be
indicated on the map.
are given in Chapter-4 under fig no: 4.1
24. The water requirement for the Project, its
availability and source should be furnished. A
detailed water balance should also be
provided. Fresh water requirement for the
Project should be indicated.
Around 12.5 KLD of water will be required
for the proposed project. Accumulated water
in the mined out pits will be used for
sprinkling and greenbelt development and
drinking water will be sourced from nearby
village through water tankers.
25. Necessary clearance from the Competent
Authority for drawl of requisite quantity of
water for the Project should be provided.
As the source of water is through water
tankers and such ground water clearance is
not required.
26. Description of water conservation measures
proposed to be adopted in the Project should
be given. Details of rainwater harvesting
proposed in the Project, if any, should be
provided.
The rain water collected in the pits after spell
of rain will be used for plantation and dust
suppression. At the end of life of mine,
excavated area will be used as rain water pit.
27. Impact of the project on the water quality,
both surface and groundwater should be
assessed and necessary safeguard measures, if
any required, should be provided.
The depth of aquifer is at a depth of 30m and
static water level is at 6-7m during rainy
season and will go down upto 9-9.5m from
bgl.
The mine workings are located at higher
levels and proposed workings go to a depth
of 18m, no ground or surface water is going
to be accumulated in working pits.
However, rainwater accumulated in working
pits will be pumped out to garland drains &
silting tank
28. Based on actual monitored data, it may
clearly be shown whether working will
Mining will not intersect ground water table
which will be carried out upto 18m and water
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 17
intersect groundwater. Necessary data and
documentation in this regard may be
provided. In case the working will intersect
groundwater table, a detailed Hydro
Geological Study should be undertaken and
Report furnished. Necessary permission from
Central Ground Water Authority for working
below ground water and for pumping of
ground water should also be obtained and
copy furnished.
depth is 30m.
29. Details of any stream, seasonal or otherwise,
passing through the lease area and
modification / diversion proposed, if any, and
the impact of the same on the hydrology
should be brought out.
There are no perennial water bodies inside
the mine area. Only small nala passing
towards SE. Buffer zone delineated as per
norms.
The subject area is elevated on Northern side
and sloping towards SE. The storm water will
be diverted to Rain water harvesting and any
surplus during rains will lead to seasonal
nala. The upstream area is only plantation
area and hence no diversion is required.
30. Information on site elevation, working depth,
groundwater table etc. Should be provided
both in AMSL and bgl. A schematic diagram
may also be provided for the same.
Site Elevation is 37mts AMSL, Working
depth is 18m. Ground water depth is 30m.
31. A time bound Progressive Greenbelt
Development Plan shall be prepared in a
tabular form (indicating the linear and
quantitative coverage, plant species and time
frame) and submitted, keeping in mind, the
same will have to be executed up front on
commencement of the project.
Year Area proposed
for plantation
Plants
proposed
2017-18 0.0600Ha 150Nos
2018-19 0.0600Ha 150Nos
2019-20 0.0600Ha 150Nos
2020-21 0.0600Ha 150Nos
2021-22 0.0600Ha 150Nos
Total 0.3000Ha 7500
plants
32. Impact on local transport infrastructure due to
the Project should be indicated. Projected
Existing traffic density at road connecting
from Utukur to Malichedu is 120 PCU/hr and
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 18
increase in truck traffic as a result of the
Project in the present road network (including
those outside the Project area) should be
worked out, indicating whether it is capable
of handling the incremental load.
Arrangement for improving the infrastructure,
if contemplated (including action to be taken
by other agencies such as State Government)
should be covered.
proposed traffic from mine site is 60PCU/hr.
So, total traffic density on the mineral
transportation road will be 170PCU/hr. As
the carrying capacity of the road is
1800PCU/hr, the proposed increase in traffic
density will not cause significant impact on
the traffic since the connecting road and
nearby State Highway is capable of handling
this increase in traffic density.
33. Details of the onsite shelter and facilities to be
provided to the mine workers should be
included in the EIA report.
Temporary rest shelter shall be constructed
during mining operation. For transportation
of mineral product, roads around the mining
area will be strengthened.
34. Conceptual post mining land use and
Reclamation and Restoration of mined out
areas (with plans and with adequate number
of sections) should be given in the EIA report.
An effective program of land restoration will
be drawn and implemented to bring back the
status to as near the pre mining conditions as
possible.
A greenbelt development along the
periphery of the lease area will be
taken up
The excavated area will be used as
rainwater harvesting pit
35. Occupational Health impacts of the Project
should be anticipated and the proposed
preventive measures spelt out in detail.
Details of pre-placement medical examination
and periodical medical examination schedules
should be incorporated in the EMP.
Occupational Health & safety measures,
details of periodical medical examination are
enclosed in Chapter -9 under section 9.7.4.
36. Public health implications of the Project and
related activities for the population in the
impact zone should be systematically
evaluated and the proposed remedial
measures should be detailed along with
budgetary allocations.
Public health implication of the proposed
project is evaluated systematically and
enclosed in Chapter -9 under section 9.11.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 19
37. Measures of socio economic significance and
influence to the local community proposed to
be provided by the Project Proponent should
be indicated. As far as possible, quantitative
dimensions may be given with time frames
for implementation.
At the maximum production level the project
will contribute to the extent of Rs.
5Lakh/annum towards the District Mineral
Foundation (DMF) fund which will be
primarily utilized for the improvement of
infrastructure of villages. Besides this, the
project proponent has earmarked 2% of
project cost for additional CSR activities.
38. Detailed environmental management plan to
mitigate the environmental impacts which,
should inter-alia include the impacts of
change of land use, loss of agricultural and
grazing land, if any, occupational health
impacts besides other impacts specific to the
proposed Project.
Detailed Environmental Management Plan
and cost implication for EMP is mentioned in
Chapter -9
39. Public hearing points raised and commitment
of the project proponent on the same along
with time bound action plan to implement the
same should be provided and also
incorporated in the final EIA/EMP Report of
the Project.
Public hearing was conducted on and the
minutes are enclosed as Annexure -VI
40. Details of litigation pending against the
project, if any, with direction /order passed by
any Court of Law against the project should
be given.
No litigation pending.
There was a violation of EIA notification
case which has been cleared vide CC No:
147/2016 and the documents are enclosed as
Annexure -V
41. The cost of the project (capital cost and
recurring cost) as well as the cost towards
implementation of EMP should clearly be
spelt out.
Total project cost is Rs.80Lakhs and cost
towards EMP is Rs. 27.53 Lakhs for 5 years
and detailed in Chapter-9 with capital and
recurring cost.
42. A disaster management plan shall be prepared
and included in the EMP/EIA Report.
Disaster Management Plan for the report has
been prepared and same has been included in
Chapter -7 Additional studies under section
7.2
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 20
43. Benefits of the project if the project is
implemented should be spelt out. The benefits
of the Project shall clearly indicate
environmental, social, economic, employment
potential, etc.
Improve physical and social
infrastructure of the area
Generate direct as well as indirect
employment
Greenbelt development
1.8 GENERAL CONDITIONS:
a. All documents to be properly referenced with index and continuous page numbering.
b. Where data are presented in the report especially in tables, the period in which the
data were collected and the sources should be indicated.
c. Project proponent shall enclose all the analysis/ testing reports of water, air, soil, noise
etc. Using the MOEF&CC/NABL accredited laboratories. All the original
analysis/testing reports should be available during appraisal of the project.
d. Where the documents provided are in a language other than English, an English
translation should be provided.
e. The Questionnaire for environmental appraisal of industrial projects as devised earlier
by the Ministry shall also be filled and submitted.
f. While preparing the EIA report, the instructions for the proponents and instructions
for the consultants issued by MoEF vide O.M. No. J-11013/41/2006-IA.II (I) dated 4th
August, 2009, which are available on the website of this Ministry, should also be
followed.
g. Changes, if any made in the basic scope and project parameters (as submitted in
Form-I and the P.F.R for securing the TOR) should be brought to the attention of
MoEF with reasons for such changes and permission should be sought, as the TOR
may also have to be altered. Post Public Hearing changes in structure and content of
the draft EIA/EMP (other than modifications arising out of the P.H. process) will
entail conducting the PH again with the revised documentation.
h. As per the circular no. J-11011/618/2010-IA.II (I) dt: 30.05.2012, your are requested
to submit certified report of the status of compliance of the conditions stipulated in the
environment clearance for the existing operations of the project by the Regional
Office of Ministry of Environment & Forests, If applicable.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-I
INTRODUCTION
1 - 21
The EIA report should also include following
i Surface plan of the area indicating
contours of main topographic features,
drainage and mining area
Attached as ANNEXURE-IV
ii Surface Geological plan
iii Sections of the mine pit and external
dumps, if any, clearly showing the land
features of the adjoining area.
iv Conceptual plan and section
v Year wise working plan & section
1.9. POST ENVIRONMENT CLEARANCE MONITORING:
The project management will submit a half yearly compliance report in respect of
stipulated prior Environmental Clearance terms and conditions on 1st June and 1
st
December of each calendar year.
-
CHAPTER II
PROJECT DESCRIPTION
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 1
2.1 DESCRIPTION OF THE PROJECT
First Mining lease was granted to mine mica, quartz and Feldspar over an extent of
81.58Acres (33.029Ha) in Sy. No: 326/1, 328, 529, 530, 531, 534, 535, 536, 537, 538
& 549 of Turimerla Village, Sydapuram Mandal, S.P.S.R Nellore District, Andhra
Pradesh in favour of Sri G. Narayana Setty vide G.O Ms. No: 201 Dt: 18.10.1996.
The Mining Lease was executed by ADMG, Nellore, Vide Proc. No. 3852/M2/96, Dt:
27-02-1997 for a period of 20 years from 27-02-1997 to 26-02-2017 in favor of Sri.
G.NarayanaSetty. After 10 years, the M.L was transferred in favor of M/s. Bhagavan
Mines Vide G.O. Ms. No. 292, dt: 7-11-2007 and the transferred of Mining Lease was
executed by ADMG, Nellore, Vide Proc. 3852/M2/96, dt: 01-02-2008 for un-expired
of lease portion i.e., up to 26-02-2017 in favour of M/s Bhagavan Mines.
The first mining was approved by IBM vide Lt No. 659(221)/MC/96/NLR, Dt: 20-8-
1996 under Rule 24 of MCR 1960 to get grant of mining lease.
After mining lease was transferred in favor of M/s Bhagavan Mines, 1st scheme of
mining was approved by IBM vide Lt. No. 659/M.S/MC/2007/Hyd, dt: 13-05-2008
for five years period of 2008-09 to 2012-13.
2nd
scheme of mining was approve by Dept Director of Mines and Geology, Guntur
vide Lt.No. 4572/Ms/NLR/2016, Dt: 25-2-2016 for the period of 2016-17.
1st renewal of Quarry lease application was filed by M/s. Sri Bhagavan Mines on
27.10.2015. ADMG, Nellore submitted proposal for grant of 1st renewal of Quarry
lease for Mica, Quartz & Feldspar over an extent of 81.58Ac (33.029Ha) in sy.nos
326/A, 328, 529, 530, 531, 534, 535, 536, 537, 538 & 549 of Turimerla village,
Sydapuram Mandal, SPSR Nellore Dist in four of M/s. Bhagavan Mines.
M/s. Bhagavan Mines, Mg. Partner: Sri G. Nagaraju is requested by Director of Mines
and Geology to submit mining plan along with CFE, CFO and EC for grant of 1st
renewal within period of (6) months from the date of issue of the notice No:
17454/R3-1/2016 Dt: 05.01.2017.
The present proposal is for production of 8000 TPA of Quartz, 20000 TPA of
Feldspar and 2000 TPA of Mica and the mining activity is carried out by
Opencast method.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 2
2.2 LOCATION DETAILS
The mining area is located in Turimerla Village of Sydapuram Mandal at SPSR
Nellore District, Andhra Pradesh. The area is located at a distance of 33 Km from the
district headquarters. The mine lease area falls under the
Toposheet No. : 57 N/11
Latitude : N141741.1to N141708.9
Longitude : E794252.5to E794251.2
The nearest railway station is Gudur which is at 22 km from the mine lease area. The
nearest airport is Tirupathi Airport at 95 Km from the mining site.
2.2.1 Details about Project Site
Table: 2.1 Details about the Project Site
Nature of the project Sri Bhagavan Mines
Extent 33.029Ha
Capacity 8000 TPA of Quartz, 20000 TPA of Feldspar and 2000
TPA of Mica
Location of the project
District & State S.P.S.R Nellore District, A.P.
Mandal Sydapuram
Village Turimerla
Latitude N141741.1to N141708.9
Longitude E794252.5to E794251.2
General climatic conditions
Maximum Temperature 46.70C
Minimum Temperature 14.00C
Annual average rain fall 1042 mm
Relative Humidity 64-79%
General location details
Nearest Village Orupali (under Turimeral Gramapanchayati) within
0.20km from the mining site
Nearest city Nellore at 33 km from the mining site.
District headquarters Nellore at 33 km from the mining site.
Nearest railway station Gudur Railway station at 20.15 km from the mining
site.
Nearest Airport Tirupathi Airport at 73.55 km from the mine site.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 3
Archaeological/Historically
important site
None within 10 km radius
Infrastructure Facilities Hospitals and schools are present in Syadapuram.
Sanctuaries/National parks None within 10 km radius.
Nearest RF/PF Podalakur Reserved Forest 7.0Km
Tummalatalupur RF 1.78Km
Munagapadu RF 3.0Km
Tatipalli RF 7.45km
Chaganam RF 4.07km
Utukur RF 4.35km
Griddaluru RF 8.34km
Saidapuram RF 8.06km
Biradavolu RF 9.54km
Turimerla RF 0.80Km
Duggunta RF 7.72km
Nearest Water Bodies Kandleru River- 4.0Km
Maleru River 5.52Km
Penna River -0.27Km
Surrounding Mines Seetharama Mining Company 10.37Ha
Meenakshi Sundaram Mica Mines -24.09Ha
Seetharama Mining Company -53.60Ha
Pattabirama Mining Company 11.22Ha
SreeKalyana Rama Company -116.42Ha
Kalyana Rama Mica mines -1.574Ha
Sree KSR & Company -28.03Ha
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 4
Fig. 2.1 Google map (10 km radius)
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 5
Fig. 2.2 Topomap of 10 km radius
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER
PROJECT DESCRIPTION
CHAPTER-2
PROJECT DESCRIPTION
2 - 6
Fig. 2.3Lease
Sketch
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 7
2.3 GEOLOGY AND EXPLORATION
2.3.1 Area Geology
Two distinct litho-units constitute the subject area. They are (1) Schist and (2) Pegmatite.
Out of these two litho units, the Pegmatite is occurring as concealed lens below m soil
&morum and it is trapped between the Biotite Schist as hanging & footwalls. This is
normally found deeply penetrated vertically keeping the limited width & strike length. In
this area pegmatite is formed as two parallel bodies. The first vein exposed in pit-1, pit-3
and pit-4 over a length of 167m and to a width of to an average width of 30m in NW-SE
strike direction dipping towards SW with 65. The 2nd
parallel pegmatite veins is exposed
in pit-2 over a length of 145m and to a width of 20m. Even tough pegmatite veins are
covered by the soil, these veins are well exposed in four working pits to as a maximum
thickness of 20m in between the RLS of 300-280m in pit-1 and it is continuing further
depth from pit bottom. It is observed from pits that the pegmatite is rich in Potash
Feldspar associated with glassy Quartz and mica. The lease area is covered by the soil
around the working pits on the surface and the contact of pegmatite with schist is clearly
seen from the working pits.
2.3.2 Geology of this mine:
The main pegmatite had been worked from the open quarry.
Mineralogy of the mine:
Feldspar:
The Feldspar is gray in colour& greasy luster. It is having multiple joints and concoidal
fracture. In pegmatite, the recovery of Feldspar is found to be about 50%.
Mineralogical, the Pegmatite is having soda feldspar.
Quartz:
The physical quality of the Quartz in pegmatite is dull white and semi glassy in nature
and having concoidal fracture. It is having glassy luster. In pegmatite,the recovery of
Quartz is found to be about 10%.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 8
Mica:
The mica is available in the form of books and small intercalated minerals in the
pegmatite. The mica is having greasy luster and brittle and flaky in nature. In pegmatite,
the recovery of crude Mica is found to be about 8%. Mineralogical, the pegmatite is
having muscovite mica with clear cleavages and in crisscross form.
In this mine only mica is considered as economically valued mineral, remaining material
is considered as waste.
2.4 DETAILS OF EXPLORATION
In approved mining scheme, it is proposed to drill 23 (PBH -1 to PBH-23) vertical, DTH
boreholes to a depth of 20m to 30m depend up on the mineral availability at less than
50m grid interval in mineral zone during the year 2016-17.
The pit no: 2 is developed and established pegmatite vein over length of 144m and to a
width of 22m during previous year and no exploration was taken up in the year 2016-17.
2.4.1 Method of Mining
Mine operations are carried out by simple open cast method using jackhammer drilling
and blasting. The blasted ROM will be loaded into tippers by the excavator and the
loaded ROM is transported to the crushing and screening plan, located in the lease area
on Southern side for separation minerals of Quartz, Feldspar and Mica from Pegmatite
ROM. The segregated minerals will be loaded into hired trucks and the same will be
transported to the user industries. So, the minerals are feasible in present market. It is a
working mine and the previous mine workings show that the mining of this area is
economically viable.
The mine workings were carried out from four pits during previous years by open cast
benching method on two pegmatite bodies by semi-mechanized method by using an
excavator, jackhammer drilling and blasting and tippers of 10t capacities. The safe
benches were excavated to a height of 3m to 6m in country rock directly with the help of
excavator without drilling and blasting. The benches were developed along and across
the strike direction (N-S & E-W) of the pegmatite and the safe benches were developed
in foot wall and hanging wall side by keeping the bench which more than the bench
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 9
height. The excavated waste rock (schist) was loaded into tippers and shifted to the O.B
dump yard. Since the Pegmatite is hard in nature, the excavations of the minerals were
carried out by open cast method with the help of an excavator into tippers of 10T
capacity and the same is shifted to the crushing and screening plan, located in the lease
area on Southern side. From ROM, minerals of Quartz, Feldspar and Mica were
segregated by screening hand picking. This method of mining will be continued in
ensuing lease period.
2.5 DETAILS OF PRODUCTION
2.5.1 Year wise production for the next five years
Table 2.2-Year wise proposed development and production from opencast mining:
Year Pit no Total
Excavati
on (m3)
Top
soil/OB
(m3)
ROM (m3) Mineral Production (t) From ROM @2.5 BD
Mineral
(m3) @
75%
M.
Reject
(m3) @25%
Quartz
@20% Feldspar
@ 50% Mica
@5%
2017-18 Pit -2 17376 Nil 11457 3819 7638 19095 1910
2018-19 Pit -1 18780 Nil 11745 3915 7830 19575 1958
2019-20 Pit 2 23304 Nil 11700 3900 7800 19500 1950
2020-21 Pit 1 17430 Nil 12375 4125 8250 20625 2062
2021-22 Pit - 3 23928 Nil 12006 4002 8004 20010 2001
100818 59283 19761 39522 98805 9881
Year wise development in ensuing five years (2017-18 to 2021-22):
The workings were carried out from four working pits by excavating two to three benches
to a height of 6m by excavating side burden. Since the minerals are occurring as a vein in
between the country rock, the safe benches were be developed in side burden by
excavating top benches in schist to a height of 6m each, before going for mineral
production. In this plan period, the development will be carried out from pit-1, pit-2 and
pit-3 as year wise details are furnished below:
Year 2017-18: In this year,the development will be carried out on western side of the pit-
2 by advancing the existing 2nd
bench towards west in country rock over an extent of
350m2 and to a thickness of 6m between the RLS of 294-288m and obtained about
2100m3 of waste in this year.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 10
Year 2018-19: In this year, the development will be carried out on western side of the
pit-1 by advancing the existing two western side benches (1st& 2
nd) towards west in
country rock over an extent of 384-264m2 and to a thickness of 6m each between the
RLS of 298-294m & 294-288m and obtained about 3120m3 of waste rock in this year.
Year 2019-20: In this year, the development will be carried out on western side of the pit
-2 by developing three benches in country rock on western over an extent of 560, 422 &
302m2 and to a thickness of 6m each between the RLS of 300-294, 294-288m and
obtained about 7704m3 of waste rock in this year.
Year 2020-21: In this year, the development will be carried out on eastern side of the pit-
1 by developing the bottom bench towards east in country rock over an extent of 155m2
and to a thickness of 6m between the RLS of 288-282m and obtained about 930m3 of
waste rock in this year.
Year 2021-22: In this year, the development will be carried out around the pit-3 by
developing the three benches in country rock over an extent of 600, 570 & 150m2 and to
a thickness of 6m each between the RLS of 298-292, 292-286 and 286-280 and obtained
about 7920m3 of waste rock in this year.
2.5.2 Year wise production for ensuing five years (2017-18 to 2021-22):
It is proposed to raise about 8,000t of quartz, 20,000t of Feldspar and 2000t of Mica per
year in this plan period. The working will be carried out around the existing pit -1, pit-2
& pit-3 by excavating one to three benches of 6m height each in mineral zone. The
minerals will be excavated with the help of jackhammer drilling and blasting and the
blaster ROM will be separated as quartz, Feldpsar& Mica by crushing & screening.
Year 2017-18: In this year, about the production of 7638t Quartz, 19095t Feldspar, 1910t
Mica & 3819m3 of mineral waste will be obtained by excavating the mineral from 2nd
bench of pit-2 over an extent of 2546m2 between the RLS of 294-288m.
Year 2018-19: In this year, the production of 7830t Quartz, 19575t Feldspar, 1958t Mica
& 3915m3 of mineral waste will be obtained by excavating the 3rd
benches from bottom
of the pit -2 in mineral zone, over an extent of 2600m2 between the RLS of 288-282m.
Year 2019-20: In this year, the production of 7800t Quartz, 19500t Feldspar, 1950t Mica
& 3900m3 of mineral waste will be obtained by excavating the 3rd benches from bottom
of the Pit-2 in mineral zone, over an extent of 2600m2 between the RLS of 288-282m.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 11
Year 2020-21: In this year, the production of 8250t Quartz, 19500t Feldspar, 2062t Mica
& 4125m3 of mineral waste will be obtained by advancing the 3rd
benches of Pit-1
towards east over an extent of 2750m2 between the RLS of 288-282m in mineral zone.
Year 2021-22: In this year, the production of 8004 t Quartz, 20010t Feldspar, 2001 t
Mica & 4002m3 of mineral waste will be obtained by excavating 2nd
& 3rd
benches of Pit-
3 over an extent of 1556m2 & 1112m2 between the RLS of 292-286m and 286-280m in
mineral zone.
2.6 List of Mining Machinery
Table: 2.3 Details of Machinery
S.No Name of Machinerys Capacity Numbers
1 Excavator 200Lc 1 no
2 Tractor cum Trolley or tippers 4/10 tones 3 nos
3 Jackhammer drills 32mm dia 3nos
4 Water Tanker 2000 Lts 1 No
2.7 Nature and generation of waste:
About 25% of the production is going to be generated as mineral wastes consisting of
intermix with Quartz, Feldspar & Mica. In every year about 3952m3 of mineral waste will
be generated on an average and about 19761m3 of mineral waste will be generated during
this plan period. In addition to the mineral waste about 21774m3 of side burden will be
generated during five years plan period. The quantities of year wise waste generation
particulars are furnished in below table: 2.4. It is proposed to stack the waste over an extent
of 2080m2 and to a height of 6m on southern side of the lease area in each year. In these five
years plan period, the proposed waste dumps will cover an extent of 10400m2.
Table: 2.4Waste Generated in the Scheme Period
Year Total Waste(m3)
2017-18 3819
2018-19 3915
2019-20 3900
2020-21 4125
2021-22 4002
Total 19761
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 12
Dump Management:
The waste dump will be stabilized with retaining wall by erecting a stone wall around toe
of the dump on southern sides to a height of 6m. The surface water from waste dumps
will be diverted into series of separate pits and the final pit water will be send to
outside/mined out areas for recharge.
2.8 CONCEPTUAL PLAN
For any mine conceptual mining plan amounts to, fore-seeing in totality and planning for
mining and related activities throughout its life span, till such time all the usable ore
minerals are exhausted to the economical limits and lease area is reclaimed to the extent
possible. Apart from physico-chemical and mineralogical parameters which form primary
basis for compilation of conceptual mine plan, several other factors such as grade of sub
grade ores, marketability and the norms laid down by the Government agencies from time
to time do play important roles. With, ever increasing and changing needs of humanity,
coupled with technological advancements, sub grade ores of the date become marketable
ores in future.
Therefore, preparation of ideal conceptual mine plan for any mine is difficult and such
plan period prepared, remains acceptable only under given circumstances. It cannot be
overlooked that, any such plan undergoes amendments and revisions in the course of
progressive stages of exploration and exploitation. It is always borne in mind to bring
back near natural shape to the area and its economic value is elevated. It is further
ensured that, there is positive contribution to the environment and socio-economic
development of the region.
2.9 MINE DEVELOPMENT: For winning of Feldspar, Quartz & Mica, the over burden and side burden must be
removed as a part of development. The removed waste will be dumped in a
predetermined area within mine lease area. The waste dumps will be covered by
afforestation in future.
2.10 MINERAL RESERVES:
The Pegmatite, which is consisting of Quartz, Feldspar and Mica is well exposed to a
thickness of 20m from the surface i.e., upto 280m RL in working pits. It is also noticed
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 13
from working pits, that the mineralization of pegmatite is continuing further depth from
pit bottom. Based on the data, collected from working pits, the geological sections were
prepared across the formation and these cross sectional area used for estimation of
reserves by sectional method. The mineral reserves were established on UNFC guidelines
and mine plan approved by the IBM.
The tonnage factor of 2.5 is taken for Quartz & Feldspar and Mica. The calculations of
reserves areas given below:
Category
& Pit no
Section Influence
Distance
(m)
Pegmatite
Sectional
area (m2)
Volume
of
Pegmatite
(m3)
Reserves in tonne
(@2.5t/m3)
M.
Waste
Quartz
@20%
Feldspar
@50%
Mica
@5%
@25%
(m3)
G1 (P-3) A-A 50 252 12600 6300 15750 1575 3150
G1 (P-3) B-B 40 299 11960 5980 14950 1495 2990
G1 (P-3) C-C 55 282 15510 7755 19387.5 1938.75 3878
G1 (P-1) D-D 24 524 12576 6288 15720 1572 3144
G1 (P-1) E-E 40 311 12440 6220 15550 1555 3110
G1 (P-1) F-F 31 332 10292 5146 12865 1286.5 2573
G1 (P-2) G-G 25 0 0 0 0 0 0
G1 (P-2) H-H 31 168 5208 2604 6510 651 1302
G1 (P-4) I-I 16 252 4032 2016 5040 504 1008
Total 42,309 1,05,773 10,577 21155
G2 (P-3) A-A 50 160 8000 4000 10000 1000 2000
G2 (P-3) B-B 40 214 8560 4280 10700 1070 2140
G2 (P-3) C-C 55 230 12650 6325 15812.5 1581.25 3163
G2 (P-1) D-D 24 562 13488 6744 16860 1686 3372
G2 (P-1) E-E 40 490 19600 9800 24500 2450 4900
G2 (P-1) F-F 31 376 11656 5828 14570 1457 2914
G2 (P-2) G-G 25 165 4125 2062.5 5156.25 515.625 1031
G2 (P-2) H-H 31 188 5828 2914 7285 728.5 1457
G2 (P-4) I-I 16 144 2304 1152 2880 288 576
Total 43106 107764 10776 21553
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 14
Total Reserves of Quartz 85415 tonnes
Total Reserves Feldspar 213537 tonnes
Total reserves of Mica 21353 tonnes
Total Mineral waste generation 42708m3
Non-Mineable Reserves: Since the mineral is well deposited within the lease area and
the safe benches will be formed in the country rock within the lease area without losing
any mineral deposit. So the minerals estimated in above table are mineable reserves and
there are no chances for blocking the mineral in 7.5m barrier and under final pit slopes.
Table: 2.5 UNFC classification of Reserves & Resources estimation:
Category Code Quantity of Minerals (t)
Quartz Feldspar Mica
Total Mineral Resources (A+B) 85415 213537 21353
A. Mineral Reserves
1. Proved Mineral Reserve 111 42309 105773 10577
2. Probable Mineral Reserve 121 & 122 43106 107764 10776
85415 213537 21353
B. Remaining Resources
1. Feasibility Mineral Resources 211 -- -- --
2. Prefeasibility Mineral Resources 221 & 222 -- -- --
3. Measured Mineral Resources 331 -- -- --
4. Indicated Mineral Resources 332 -- -- --
5. Inferred Mineral Resources 333 -- -- --
6. Possible Resources 334 -- -- --
2.11 LIFE OF THE MINE:
It is proposed to raise about 8000T of Quartz, 20,000Tof Feldspar and 2000T of Mica per
year on present exploration area.
Anticipated life of Mine = Updated available reserves
= 320305 =10.6years
say 11Years Targeted production per annum 30000
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 15
2.12 Land use
The existing land use pattern of the mining area is given below:
Table: 2.6- Existing Land Use Pattern
S.No. Description Area is used in
Hectares
1 Working pits 1.8480
2 Waste dump 1.1863
3 Mineral stock 0.2711
4 Road 0.5721
5 Infrastructure 0.1477
6 Greenbelt 1.2180
7 Stock yard of ROM 2.7436
Total 7.9868
(Source: As per Approved Modified Mining Plan)
The following additional area is required for mining activity in this plan period.
Table: 2.7- Proposed Land Use Pattern
S.No. Description Area is used in
Hectares
1 Working pits 0.1894
2 Waste dump 1.0400
3 Mineral stock --
4 Road --
5 Infrastructure --
6 Greenbelt 0.3000
7 Stock yard of ROM --
8 Retaining wall & G. Drain 0.0320
Total 1.5614
2.13 Afforestation
Plantation will be made over an area of 0.3000 ha as per the approved mining plan.
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 16
No worked out area is going to be formed in this plan period. However, the green belt
will be developed along the periphery of the ML area on southern side as detailed as:
Table: 2.8 Year Wise greenbelt development
Year Area proposed for plantation Plants proposed for the year
2017-18 0.0600Ha 150 Nos
2018-19 0.0600Ha 150 Nos
2019-20 0.0600Ha 150 Nos
2020-21 0.0600Ha 150 Nos
2021-22 0.0600Ha 150 Nos
Total 0.3000Ha 7500 plants
2.14 Progressive Reclamation Plan
As effective program of land restoration will be drawn and implemented to bring back the
status to as near the pre mining conditions as possible.
The salient features are as enumerate below:
Agreen belt development along the periphery of the lease area will be taken up.
The excavated area will be used as rain water harvesting pit
The land usage by the end of the five years plan period is detailed below:
Mining Activity Existing Land used
patron (Ha)
Area required for
1st 5 years (Ha)
Total area used for
mining by the end
of 5 years (Ha)
Working pits 1.8480 0.1894 2.0374
Waste dump 1.1863 1.0400 2.2263
Mineral Stock 0.2711 -- 0.2711
Road 0.5721 -- 0.5721
Infrastructure 0.1477 -- 0.1477
Greenbelt 1.2180 0.3000 1.518
Stock yard of ROM 2.7436 -- 2.7436
R.Wall & G. Drain -- 0.0320 0.032
Total area 7.9868 Ha 1.5614 Ha 9.5482 Ha
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-2
PROJECT DESCRIPTION
2 - 17
2.15 USE OF MINERALS
The Quartz, Feldspar and Mica of this area are not meant for captive use. The mineral
Quartz will be sold to the Ferro Alloy Industries, Foundaries, Ceramic and Glass
Industries. Feldspar will be sold to the ceramic industries and Mica will be sold to the
insulation manufacturers.
2.16 Site Services -Utilities
The site services are already provided by the lessee. Shelter to the workers, first aid
facilities and toilets will be constructed & water will be provided to the workers in the
mining area.
Mine office
A temporary mine office will be constructed at the mine site.
Water supply
Around 12.2 KLD of water will be required for the project activity. Out of which, 1.7
KLD is required for drinking purpose, 5 KLD and 5.5 KLD for dust suppression and
green belt respectively and will be made available through water tankers.
Water is required in the mine for spraying on the roads and working faces to suppress the
dust and also for use in the garage. Also a small quantity of drinking water is required.
-
CHAPTER III
ANALYSIS OF
ALTERNATIVES
-
SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER-3
ANALYSIS OF ALTERNATIVES
3- 1
3.0 GENERAL
Sri Bhagavan Mines, the proponent has been granted the lease by Government of Andhra
Pradesh. The land is Govt. waste land. Mine is a site specific in an area of 33.029Ha.
Mining activities shall be carried out based on local geology and availability of the
mineral.
3.1. ALTERNATE TECHNOLOGY:
M/s. Sri Bhagavan Mines is having experience and progressive outlook in regularly
updating its technology. The technology adopted by company in mining of Quartz,
Feldspar, and Mica is very much reliable. The mining activity was proposed to be carried
out by open cast method with the help of jack hammer drilling and blasting and using an
excavator & tippers for excavation of the material in approved mining scheme.
3.2 SITE ALTERNATIVES
No necessity for the alternative analysis of the technology was observed as the
technology/process mentioned for mining of the proposed mineral is best suitable.
The selected site has the following advantages:
Operational since last long and it is a renewal of mine without addition of mine lease
area.
The area chosen for mining activities is not having habitation of any kind.
The site is well connected by road.
Easy Availability of labour from nearby villages.
No alternate sites are selected as the deposit is site specific.
No necessity for the alternative analysis of the technology was observed as the
technology mentioned for mining of the proposed project is best suitable.
-
CHAPTER IV
DESCRIPTION OF ENVIRONMENT
-
[SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER IV
DESCRIPTION OF
ENVIRONMENT
4 - 1
4.0 INTRODUCTION
Collection of base line data is an integral aspect of the preparation of Environmental
Impact Assessment report. Base line data reflects the present status of Environment
before the initiation of any activity. The possible effects due to the proposed mine
project are estimated and superimposed on the compiled baseline data subsequently to
assess Environmental Impacts.
4.1 STUDY AREA
Study area covers 10 km radius from proposed mine site located at sy.nos 326/1, 328,
529, 530, 531, 534, 535, 536, 537, 538 & 549 of Turimerla village, Sydapuram
Mandal, SPSR Nellore District, Andhra Pradesh.
4.2 STUDY PERIOD
The baseline environmental quality represents the background scenario of various
Environmental components in the study area.
As part of the Environmental Impact Assessment Study, baseline environmental
monitoring was carried out for the month of January 2017 to March 2017.
4.3 METHODOLOGY OF EIA STUDY
The various steps involved in Environmental Impact Assessment Study of the mine
site are divided into following phases:
Identification of significant Environmental parameters and assessing the
existing status within the impact zone with respect to air, water, noise, soil and
socio-economic components of Environment. Following studies will be carried
out:
MICROMETEOROLOGICAL DATA
AIR QUALITY EXISTING AMBIENT AIR QUALITY
WATER ANALYSIS - GROUND WATER-SHALLOW WELLS, DEEPWELLS
NOISE LEVELS
FLORA AND FAUNA
LAND ENVIRONMENT
LAND USE / LAND COVER
-
[SRI BHAGAVAN MINES
FINAL EIA REPORT
CHAPTER IV
DESCRIPTION OF
ENVIRONMENT
4 - 2
SOIL CHARACTERISTICS and
SOCIO ECONOMIC STATUS SURROUNDING THE PROJECT SITE.
Study of various mining activities of the proposed mine to identify the area
leading to impact/change in Environmental quality.
Quantification/prediction of impact for the identified activities and to study the
level of impact on various Environmental components.
Evaluation of impacts after superimposing the predicted/quantified scenario
over the baseline scenario.
Formulation of Environmental Management Plan for implementation in the
proposed project.
4.4 COLLECTION OF BASELINE DATA
4.4.1 MICRO METEOROLOGICAL DATA
Micrometeorological studies are simultaneously conducted with the Ambient Air
Quality monitoring. Meteorology plays an important role in the dispersion of
pollutants. The meteorological data is very useful for interpretation of the base line
information and for model study of air quality impacts also.
A temporary meteorological station was installed at project site. The station was
installed at a height of 4 mts above the ground level in such a way that there are no
obstructions facilitating flow of wind, wind speed, wind direction, humidity and
temperature are recorded on hourly basis.
CLIMATE
The tropical climate of the region is manifested as hot and humid summer, moderately