environmental management pl~n - world...
TRANSCRIPT
ENVIRONMENTAL MANAGEMENT P L ~ N
E1467v 14
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
SECTION VI : ENVIRONMENTAL MANAGEMENT PLAN
Tiaong-Lucena City Section
The purpose of the Environment Management Plan is to enhance the beneficial impacts and to lessen effects of adverse impacts. The EMP sekes as guide to ensure proper implementation of mitigating measures. Failure to do so may result in the cancellation of the ECC and project maybe stopped with a cease and desist order. The impact and corresponding mitigation measures are presented below.
1. PRE- I Hiring of Local Labor Force CONSTRUCTION
Fuel, oil and bitumen spillage. m 2. CONSTRUCTION
PHASE
DPWH and Contractor will prioritized the people residing in the area for the construction labor force.
Noise, smoke and dust
.
Equipment shall be in good running condition. I I Minimize he1 and oil spillage from vehicles and equipment.
Observe good work practice. I I
DPWH,LGU's concerned contractors.
DPWH Contractor
The cost of hiring of local labor force will be borne by contractor.
Remove all excavated materials immediately, to be deposited at approved location.
Equipment shall be in good running condition. -
Minimize stock piling of materials.. I 1 I
DPWH Contrator and DENR
1 I I i
SECTION V1: ENVIRONMENTAL MANAGEMENT PLAN Tiaong-Lucena City Section
DPWH Contractor deposited at approved location.
e- l
ENVXRONMENTAL ACTION PLAN - Pagbilao to Camarines Bdry Section Work on Pavement. (pothole patching,scaline;.block replacement. and AC-overlay and road markings).
Possible Hazards Action to be taken Requirements in Verification of by Contractor Bidding Document Resident Engineer
Fuel, oil and Minimize fuel and Condition of Verify that vehicles bitumen spillage oil spillage from Contract, Special and equipment are
vehicles and Provisions, Clause in good running equipment. XXX. condition. Equipment shall be Verify that works in good running are in accordance condition. with Specifications. Observe good work practice.
Fire hazard. Observe safe work Condition of Verify that works procedure. Contract, Special are in accordance
Provisions, Clause with Specifications. XXX.
Flushing of solids Remove all Condition of Verify that by surface water. excavated materials Contract, Special excavated materials
immediately, to be Provisions, Clause are deposited at deposited at XXX. approved location. approved location.
Temporary Minimize Condition of Verify that stockpiling of stockpiling of Contract, Special appropriate warning materials on materials. Provisions, Clause device are in place. pavement. Place appropriate xxx.
warning devices. Partly interruption Place appropriate Condition of Verify that of traffic. warning device. Contract, Special appropriate warning
Control traffic. Provisions, Clause device are in place. XXX.
Noise, smoke and Equipment shall be Condition of Verify that works dust during in good running Contract, Special are in accordance construction. condition. Provisions, Clause with Specifications.
Remove all XXX.
excavated materials I
immediately, to be deposited at approved locat ion. Minimize ?e stockpiling of materials.
B
C
DPWH -Environmental Impact Assessment Project Office 17
Work on shoulders, (patching of holes and devression. grading and regravelling).
DPWH - Environmental Impact Assessment Project Office 18
Possible Hazards
Fuel and oil spillage
Flushing of solids by surface water.
Temporary stockpiling of materials on and/or pavement.
Partly interruption 'of traffic.
Noise, smoke and dust during construction.
Action to be taken by Contractor Minimize fuel and oil spillage from vehicles and equipment. Equipment shall be in good running condition. Observe good work practice. Remove all excavated materials immediately, to be deposited at approved location. Minimize stockpiling of materials. Place appropriate warning devices. Place appropriate warning device. Control traffic.
Equipment shall be in good runni~lg condition. Remove all excavated materials immediately, to be deposited at approved location. Minimize stockpiling of materials.
Requirements in Bidding Document Condition of Contract, Special Provisions, Clause XXX.
Condition of Contract, Special Provisions, Clause '
XXX.
Condition of Contract, Special Provisions, Clause xxx.
Condition of Contract, Special Provisions, Clause XXX. Condition of Contract, Special Provisions, Clause xxx.
Verification of Resident Engineer Verify that vehicles and equipment are in good running condition. Verify that works are in accordance with Specifications.
Verif~~that excavated materials are deposited at approved location.
Verify that appropriate warning device are in place.
Verify that appropriate warning device are in place.
Verify that works are in accordance with Specifications.
I
Work on Drainage, clear in^ and clean in^ of drainacre facilities. minor repair of facilities. construction of line canal and re-establishment).
-
DPWH - Environmental Impact Assessment Project Office 19
Possible Hazards
Fuel and oil spillage.
Flushing of solids by surface water.
Temporary stockpiling of materials on and/ or pavement.
Partly interruption of traffic.
Noise, smoke and dust during construction.
Action to be taken by Contractor Minimize fuel and oil spillage from vehicles and equipment. Equipment shall be in good running condition, Observe good work practice. Remove all excavated materials immediately, to be deposited at approved location. Minimize stockpiling of materials. Place appropriate warning devices. Place appropriate warning device. Control traffic.
Equipment shall be in good running condition. Remove all excavated materials immediately, to be deposited at approved location. Minimize stockpiling of materials. Observe good work practice.
Requirements in Bidding Document Condition of Contract, Special Provisions, Clause XXX.
Condition of Contract, Special Provisions, Clause xxx.
Condition of Contract, Special Provisions, Clause xxx.
Condition of Contract, Special Provisions, Clause XXX.
Condition of Contract, Special Provisions, Clause XXX.
Verification of Resident Engineer Verify that vehicles and equipment are in good running condition. Verify that works are in accordance with Specifications.
Verify that excavated materials are deposited at approved location.
Verify that appropriate warning device are in place.
Verify that appropriate warning device are in place.
Verify that works are in accordance with Specifications.
I
a 'a
Work on Roadside. (vegetation control and erosion control).,
DPWH - Environmental Impact Assessment Project Office 20
Possible Hazards
Fuel and oil spillage.
Flushing of solids by surface water.
Temporary stockpiling of materials on pavement.
Partly interruption of traffic.
Noise, smoke and dust during construction.
Requirements in Bidding Document Condition of Contract, Special Provisions, Clause XXX.
Condition of Contract, Special Provisions, Clause xxx.
Condition of Contract, Special Provisions, Clause xxx.
Condition of Contract, Special Provisions, Clause XXX.
Condition of Contract, Special Provisions, Clause XXX.
Action to be taken by Contractor Minimize fuel and oil spillage from vehicles and equipment. Equipment shall be in good running condition. Observe good work practice. Remove all excavated materials immediately, to be deposited at approved location. Minimize stockpiling of materials. Place appropriate warning devices. Place appropriate warning device. Control traffic.
Equipment shall be in good running condition. Remove all excavated materials immediately, to be deposited at approved location. Minimize stockpiling of materials.
Verification of Resident Engineer Verify that vehicles and equipment are in good running condition. Verify that works are in accordance with Specifications.
Verify that excavated materials are deposited at approved location.
Verify that appropriate warning device are in place.
Verify that appropriate warning device are in place.
Verify that works are in accordance with Specifications.
I
Possible Hazards Action to be taken Requirements in Verification of by Contractor Bidding Document Resident Engineer
Soap, paint and Observe good work Condition of Verify that works solvent splatter and practice. Contract, Special are in accordance spillage Avoid spillage of Provisions, Clause with Specifications.
paint, soap and XXX.
solvent. Partly interruption Place appropriate Condition of Verify that of traffic. warning devices. Contract, Special appropriate warning
Control traffic. Provisions, Clause devices are in place. XXX.
Possible Hazards Action to be taken Requirements in Verification of by Contractor Bidding Document Resident Engineer
Fuel,oil,soap,paint Observe good work Condition of Verify that works and solvent splatter practice. Contract, Special are in accordance and spillage Avoid pillage of Provisions, Clause with Specifications.
paint, soap and XXX. solvent.
Noise and dust Observe good work Condition of Verify that works during construction. practice. Contract, Special are in accordance
Provisions, Clause with Specifications. XXX.
Partly interruption Place appropriate Condition of Verify that of traffic warning devices. Contract, Special appropriate warning
Control traffic. Provisions, Clause devices are in place. XXX.
4
i DPWH - Environmental Impact Assessment Project Office 2 1
Production of Materials, (Asphalt mix. concrete and agvrenate). :I I
Possible Hazards Action to be taken Requirements in Verification of by Contractor Bidding Document Resident Engineer
Fuel,oil and bitumen Plant and equipment Condition of Verify that vehicles shall be in good Contract, Special and equipment are running condition. Provisions, Clause in good running Minimize xxx. condition. stockpiling of Verify that works materials. are in accordance
with Specifications. Observe safe work Condition of Verify that works procedure. Contract, Special are in accordance
Provisions, Clause with Specifications. XXX.
Flushing of solids Minimize Condition of Verify that by surface water. stockpiling of Contract, Special stockpiles are
materials. Provisions, Clause protected in an Protect stockpiles xxx. appropriate manner. against rain and surface water. Observe good work practice
Noise and dust Equipment shall be Condition of Verify that plant and uction in good running Contract, Special equipment are in
condition. Provisions, Clause good running Minimize xxx. condition. stockpiling of Verify that mixing materials. equipment is in Observe good work accordance with practice Specifications.
Verify that stockpiles are protected in an appropriate manner.
\!
a DPWH - Environmental Impact Assessment Project Office 22
Environmental Monitoring Plan
The Monitoring Plan are intended for the continued observation and evaluation of the mitigated impacts during construction and operation and operation phases. The proponent will closely coordinate with the DENR and the LGUs on the monitoring activities. For a smooth implementation of the project, the proponent will appoint a monitoring team for proper coordination with the DENR and the LGU's.
Project Phase
11. Construction
1 .Pre Construction
Noise Pollution
Issues
Monitor noise Level Monitor the Compliance of Contracts to Mitigation measures
Subject of Monitoring
Equipment Mobilization
Air Pollution Air Pollution Levelldust
Mobilization of equipment prior to construction
Spoil and Monitor wash Construction Management Plan
Remarks/ Measures
Responsibility
Monitor Compliance although effect is only minimal
daytime
DPWH Contractor
Schedule Operation of Equipment at
Air pollution IS Only minimal and temporary But requires
DENR,DPWH
Contractor to Water the Project area if Dusty
Contractor, DPWH, DENR
Designate Contractor
DPWH - Environmental Impact Assessment Project Office 23
\,
. \ 4
DPWH - Environmental Impact Assessment Project Oftice 24
Waste Disposal
Water Quality Effectiveness of Water management measures
to be used in the Project.
Incorporate reuse of waste materials and the used of designated disposal sites in the detailed design.
Estimate the amount and types of spoil and construction waste to be generated by the project. Investigate whether the waste can be reused in the project or by other interested parties.
Only minimal effect