Environmental Monitoring Report
This report has been submitted to ADB by the Program Management Unit, Government of Uttarakhand, Dehradun and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Project Number: 40648-033 December 2017 Period: January 2017 – June 2017
IND: Infrastructure Development Investment Program for Tourism - Tranche 2
Submitted by
Program Management Unit, Government of Uttarakhand, Dehradun
p_, ~ ii'~
Govt ot IJtlMekh,m<J
Program Management Unit lnfr,1strudun~ Dnclopmcnt luvestmcnt Prngrnm for Tourism
(,f IW A.\'.1-i.m'.i/ · · Loan ,Vt,. 2833, /11dio)
Government of Uttarakhand Pandit Deondyal Upadhayay Paryatan Bhawan, Nvar ONGC Helipad G.arhi Cantt, Dehradun -248003
f ()I: 91 ·135-2559987, Fax: 91-135-2559988 E-mail: [email protected]
r/t{1Xnlk.!t<1f11/
H<~f:'? b 1.2 /2-10-ADB IDI PT /223/2014-15
To
Date: 16.11.2017
Country Director,
Indian Hesident Mission (INRM),
Plot no -4, San Martin Marg, Chanakyapuri,
New Delhi ll0021, PB No .. 53311 (HPO)
Sub: Loan No. 2833 IND- IDIPT, UI< Revised Submission of Semiannual Safeguard Monitoring Report (Environment}, for January - June, 2017
Hef: PMU's letter no. 5542/2-10-ADB IDIPT/223/2014-15
Hespected Sir,
Please ff nd the revfseci Semiannual Environment Monitoring Hcport for your kind
perusal and approval.
Encl.:- As above
Yours Sincere ly
// J!11 I (11 (!'; -
(Purshottam)
Additional Program Director
,._; K--! i "" '
Semi – Annual Environmental Monitoring Report
Loan No: 2833 IND
Period: January to June 2017
IND: Infrastructure Development Investment Programme for Tourism,
Uttarakhand
(Tranche-II)
Prepared by Dept. of Tourism, Government of Uttarakhand for Asian
Development Bank
November, 2017
This Semi – Annual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
Table of Contents
1. INTRODUCTION ..................................................................................................... 1
2. COMPLIANCE STATUS ......................................................................................... 23
3. COMPLIANCE STATUS WITH NATIONAL/ STATE/ LOCAL STATUTORY
ENVIRONMENTAL REQUIREMENTS ....................................................................... 23
4. COMPLIANCE STATUS WITH THE ENVIRONMENTAL COVENANTS AS STIPULATED
IN THE LOAN AGREEMENT ................................................................................... 25
5. COMPLIANCE STATUS WITH ENVIRONMENT MANAGEMENT AND MONITORING
PLANS AS STIPULATED IN THE ENVIRONMENTAL DOCUMENTATION AS AGREED
WITH ADB ........................................................................................................... 28
6. APPROACH & METHODOLOGY ENGAGED FOR ENVIRONMENTAL MONITORING OF
THE PROJECT ..................................................................................................... 79
7. MONITORING OF ENVIRONMENTAL RECEPTORS/ ATTRIBUTES ............................... 79
8. IMPLEMENTATION OF ENVIRONMENTAL MONITORING PLAN .................................. 80
9. INSTITUTIONAL ARRANGEMENTS ....................................................................... 104
9.1 INSTITUTIONAL ARRANGEMENTS FOR EMP IMPLEMENTATION .............................. 105
10. CONSULTATION DETAILS .................................................................................. 107
11. ANY OTHER ENVIRONMENTAL ASPECTS, IMPACTS OBSERVED DURING
IMPLEMENTATION WHICH WERE NOT COVERED EARLIER .................................... 112
12. DETAILS OF COMPLAINTS RECEIVED FROM PUBLIC AND ACTION TAKEN
THEREOF TO RESOLVE ..................................................................................... 112
13. FOLLOW UP ACTIONS AND CONCLUSIONS .......................................................... 112
List of Table
TABLE 1: PROJECT PROGRESS IN THE REPORTING PERIOD TILL 30TH
JUNE, 2017 ........................................................................................................ 2
TABLE 2: WORK DETAILS AND RISKS FOR SUB PROJECTS .......................... 6
TABLE 3: STATUS OF COMPLIANCE WITH EARF/ADB PROCEDURES* ....... 23
TABLE 4: STATUS OF ENVIRONMENT, FOREST AND OTHER
CLEARANCE ................................................................................................... 24
TABLE 5: STATUS OF COMPLIANCE WITH ENVIRONMENTAL LOAN
COVENANTS ................................................................................................... 26
TABLE 6: EMP IMPLEMENTATION STATUS ..................................................... 28
TABLE 7: EMP MONITORING STATUS CHART ................................................. 33
TABLE 7(I): EMP MONITORING STATUS CHART- ASAN BARRAGE .............. 33
TABLE 7(II): EMP MONITORING STATUS CHART- TIGER FALL AND
LAKHAMANDAL ............................................................................................. 35
TABLE 7(III): EMP MONITORING STATUS CHART- DEOBAN FOREST
REST HOUSE .................................................................................................. 37
TABLE 7 (IV): EMP MONITORING STATUS CHART- DEVELOPMENT OF
ADVENTURE TOURIST CENTRES IN UTTARAKHAND .............................. 39
TABLE 7 (V): EMP MONITORING STATUS CHART- DEVELOPMENT OF
TOURISM INFRASTRUCTURE FOR NORTH CORBETT ENTRY POINT
AT KOTDWARA .............................................................................................. 43
TABLE 7(VI): EMP MONITORING STATUS CHART- SIGNAGES WORKS
IN UTTARAKHAND STATE ........................................................................... 49
TABLE 7(VII): EMP MONITORING STATUS CHART- DEVELOPMENT OF
ADVENTURE TOURIST CENTRE AT TEHRI ................................................. 56
TABLE 7(VIII): EMP MONITORING STATUS CHART - UPGRADATION OF
TOURIST FACILITIES AT TRH PARICHAY ................................................... 63
TABLE 7(IX): EMP MONITORING STATUS CHART - AMELIORATION OF
LAKE NAUKUCHIATAL .................................................................................. 66
TABLE 7(X): EMP MONITORING STATUS CHART - TREK TRAIL FROM
PITHORAGARH TO CHANDAK, PITHORAGARH ........................................ 69
TABLE 7(XI): EMP MONITORING STATUS CHART - VIEW POINT AT
MOSTAMANU TEMPLE, PITHORAGARH ..................................................... 72
TABLE 7(XII): EMP MONITORING STATUS CHART - CONSERVATION OF
PITHORAGARH FORT, PITHORAGARH ....................................................... 74
TABLE 7(XIII): EMP MONITORING STATUS CHART – DEVELOPMENT OF
ADVENTURE CENTRE AT BAUR JALASHAY ............................................. 76
TABLE 8: PARAMETERS AND METHODOLOGY FOR ENVIRONMENTAL
MONITORING .................................................................................................. 79
TABLE 9 (I): IMPLEMENTATION OF ENVIRONMENTAL MONITORING
PLAN- FOR PROJECTS UNDER DSC DEHRADUN ..................................... 80
TABLE 9 (II): IMPLEMENTATION OF ENVIRONMENTAL MONITORING
PLAN- FOR PROJECTS UNDER DSC KOTDWAR ....................................... 91
TABLE 9 (III): IMPLEMENTATION OF ENVIRONMENTAL MONITORING
PLAN- FOR PROJECTS UNDER PIU BHIMTAL ........................................... 96
TABLE 10(I): STAKEHOLDER CONSULTATION DETAILS FOR
PROJECTS UNDER PIU DEHRADUN.......................................................... 107
TABLE 10(II): STAKEHOLDER CONSULTATION DETAILS FOR
PROJECTS UNDER PIU KOTDWAR ........................................................... 109
TABLE 10(III) STAKEHOLDER CONSULTATION DETAILS FOR
PROJECTS UNDER PIU BHIMTAL .............................................................. 111
LIST OF ANNEXURE
ANNEXURE: 1: PHOTO ILLUSTRATION PROJECTS UNDER PIU
DEHRADUN ................................................................................................... 113
ANNEXURE: 2: PHOTO ILLUSTRATION PROJECTS UNDER PIU
KOTDWAR ..................................................................................................... 115
ANNEXURE: 3: PHOTO ILLUSTRATION PROJECTS UNDER PIU
BHIMTAL ....................................................................................................... 117
ANNEXURE: 4: PHOTO ILLUSTRATION OF AWARENESS GENERATION
AND LABOUR WELFARE ACTIVITIES........................................................ 120
ANNEXURE: 5: ATTENDANCE RECORD OF CONSULTATION ACTIVITIES . 123
ANNEXURE: 6: CORRESPONDENCE WITH DISTRICT ADMINISTRATION
REGARDING CHANGE OF PROPOSED LOCATION BATURI –
PANCHESWAR IN CHAMPAWAT TO TANAKPUR CHAMPAWAT ........... 127
1
1. Introduction
Overall Project Description
1. The Infrastructure Development Investment Program for Tourism Financing Facility (the Facility) will develop
and improve basic urban infrastructure and services in the four participating states of Himachal Pradesh, Punjab,
Uttarakhand and Tamil Nadu—to support the tourism sector as a key driver for economic growth. It will focus on:
(i) strengthening connectivity to and among key tourist destinations; (ii) improving basic urban infrastructure and
services, such as water supply, road and public transport, solid waste management and environmental
improvement, at existing and emerging tourist destinations to ensure urban amenities and safety for the visitors,
and protect nature and culture-based attractions. Physical infrastructure investments will be accompanied by: (iii)
capacity building programs for concerned sector agencies and local communities for better management of the
tourist destinations and for more active participation in the tourism-related economic activities, respectively.
2. The proposed Project targets enhanced economic growth and provision of livelihood opportunities for local
communities through tourism infrastructure development with a focus on preservation and development of
natural and cultural heritage and incidental services. The Project supports the state of Uttarakhand to develop
the tourism sector as a key driver for economic growth.
3. The Executing Agency (EA) for the Investment Program is Dept. of Tourism, Govt. of Uttarakhand. The Loan
Agreement and Project Agreement for the IDIPT, Uttarakhand is 2833-IND. Project Implementation Unit have
been established in three towns respectively (Dehradun, Bhimtal and Kotdwar) for implementation of sub-
projects. Design and Supervision Consultants (DSCs), has already been established in three towns for designing
the Infrastructure, managing the tendering of Contractors and supervising construction, and providing support to
the PIUs.
Outputs of the Project
4. The outputs of the Project are as follows:
Component 1: Urban Infrastructure and Service Improvement
� World class infrastructure comprising of gardens, fountains and water sports developed
along the banks of Ganga Canal at Haridwar; (project held in abeyance)
� Tourist facilities at Parichay and Naukuchiyatal Lake upgraded and developed;
� Tourist support infrastructure at Pithoragarh improved;
� Tourist facilities developed at Hanol Temple, Tiger Falls, Deoban, Lakhamandal and Tree
Samadhi (Tree Samadhi component dropped);
� 9 Adventure tourism centers established across the state; and
� North Corbett entry point improved.
Component 2: Improved connectivity
� Walk-way at Asan Barrage; and
� Trek trail connecting Pithoragarh to Chandak.
Component 3: Quality Enhancement of Natural and Cultural Attractions
� Water sports tourism facility developed at Asan Barrage Dehradun;
� Jagjitpur/ Silt ejector canal at Haridwar improved;
2
� Pithoragarh Fort conserved; and
� Naukuchiyatal lake Ameliorated
Component 4: Greater participation by local communities
Component 5: Capacity Development, Community Participation and Project Management
Environment Category
5. The project under IDIPT was categorized as Environment Category “B”, according to ADB’s Safeguard Policy
Statement (2009). All the subprojects under execution have been categorized as category B.
Environment Performance Indicators, if any
6. For effective monitoring, selected environmental parameters have been identified as indicators which may be
qualitatively and quantitatively measured and compared over a period of time in order to assess/ ensure the
compliance to environmental management plans (EMPs). The environmental performance indicators selected
are physical, biological and social characteristics identified as most important in affecting the environment at
critical locations all along the sub project corridors. The parameters identified as performance indicators are:
� Compliance with environmental management and monitoring plan
� Compliance to State/ National environmental regulations.
� Monitoring of ambient air quality, water quality and noise levels and comparison with baseline
environmental quality and State/ National Standards.
Overall project progress, agreed milestones and Implementation schedule
7. Construction status of the sub projects is shown in Table 1.
Table 1: Project Progress in the Reporting Period till 30th June, 2017
SI.
No.
Package Ref No. General
Description
Goods or
Works
Contract
Signing
Date
Name of the Contractor Contract
Value
Contract
period in
months
1 UK/IDIPT/DDN/01 Development of
Tourism
infrastructure
facilities at Asan
Barrage
Dehradun- Lot 1
10.2.2014 M/S Rajendra Kumar
Tripathi, Pratapgarh
INR
3.03 Crores
18 +5
2 UK/IDIPT/DDN/02 Development of
Tourism
infrastructure
facilities at Asan
Barrage
Dehradun- Lot 2
Dropped
3 UK/IDIPT/DDN/03 Development of
Yamuna Circuit
(Tiger Falls &
Lakhamandal
Temple)- Lot 1
9.6.2014 M/S Aradhya Engineers
and Construction & Pvt.
Ltd, Rishikesh
INR
1.84 Crores
18+ 1.5
4 UK/IDIPT/DDN/04 Development of MoU signing Under Force Accounts 0.26 Crores 12 + 11
3
SI.
No.
Package Ref No. General
Description
Goods or
Works
Contract
Signing
Date
Name of the Contractor Contract
Value
Contract
period in
months
Yamuna Circuit
(Deoban)- Lot 2
date
18.9.2014
MoU has been signed
with Forest Dept.
5 UK/IDIPT/DDN/05 Development of
Yamuna Circuit
(HanolMahasu) -
Lot 3
15.5.2014 M/S Dagmo Riba Itanagar INR
8.76Crores
18 +18
Adventure Sports Centre (Goods)
6 UK/IDIPT/DDN/06
B - Lot 1 –P1
Development of
Adventure tourist
Centre
20.05.2017 M/s Rite Equipment
JV Bangalore
Bangalore
INR
8.24 Crore
18
UK/IDIPT/DDN/06
A - Lot 1 –P2 Development of
Adventure tourist
Centre
29.04.2017 M/s Litmus Marine
Innovation Pvt. Ltd.
3, Anurag Business
Centre, Near Amar
Cinema, Chembur,
Mumbai - 400071
INR
8.40 Crore
18
UK/IDIPT/DDN/06
A - Lot 1 –P3 Development of
Adventure tourist
Centre
17.10.2016 M/s R & R Adventure
J/V, 30 Kiran Vihar,
Delhi
30 Kiran Vihar, Delhi
INR
1.97 Crore
18
Adventure Sports Centre (Works)
7 UK/IDIPT/DDN/06-
Lot2 P1
Development of
Adventure
Tourist Centre-
Bageshwar-
Kapkot
30.05.2016 M/s Samir Kumar
Mishra,Badripur,Dehradun
INR
0.58 lakhs
18
UK/IDIPT/DDN/06-
Lot2 P2
Development of
Adventure
Tourist Centre-
Champawat-
Tanakpur1
30.05.2016 M/s Samir Kumar
Mishra,Badripur,Dehradun
INR 0.58
Lacs
18
UK/IDIPT/DDN/06-
Lot2 P2
Development of
Adventure
Tourist Centre-
Pauri
07.06.2016 M/s Kailash Bisht JV with
Laxman Prasad Daya
Bhawan,Agency
chowk,Dehradun
INR 0.56
Lacs
18
8 UK/IDIPT/KOT/01 Development of
North Entry in
Corbett Sub-
project
09.07.2014 M/S Dagmo Riba Itanagar INR
11.31Crores
17+15
9 UK/IDIPT/KOT/02 Signage Sub- 30.12.2014 M/s Reynober SA, Madrid INR 18+7
1 Proposed Location Baturi-Pancheswar in Champawat was changed to Tanakpur-Champawat due to
administrative reasons. Addendum to IEE Development of Adventure Tourist Centres in Uttarakhand is under
process.
4
SI.
No.
Package Ref No. General
Description
Goods or
Works
Contract
Signing
Date
Name of the Contractor Contract
Value
Contract
period in
months
project in
Uttarakhand
Spain in JV with M/s
Prabhatam Advertising
Pvt. Ltd.
47.08 Crores
10 UK/IDIPT/KOT/03-
Lot-1
Adventure
Sports Centre at
Tehri under PIU
Kotdwar - Lot 1
27.01.2015 M/s Litmus Marine
Innovation Pvt. Ltd.,
Mumbai
3.72 Crores 17+6
11 UK/IDIPT/KOT/03-
Lot-2
Adventure
Sports Centre at
Tehri under PIU
Kotdwar - Lot 2
30.12.2014 M/s Sunil Garg& Co. in JV
with M/s Jai Durgey
Trading and Construction
Co.
INR
13.53Crores
17+7
12 UK/IDIPT/KOT/04 Haridwar Ganga
Canal(1.83 M
US$)
Held in abeyance
13 UK/IDIPT/KOT/05 Beautification of
Jagjitpur/Silt
ejector canal at
Haridwar (1.33
M US$)
Held in abeyance
14 UK/IDIPT/BHT/01 Upgradation of
Tourist Facilities
at TRH Parichay
15.5.2014 M/S Dagmo Riba Itanagar INR
4.62Crores
18+13
15 UK/IDIPT/BHT/02 Amelioration of
Lake
Naukuchiatal
26.6.2014 M/S Global Aqua
Treatment Technology
Pvt. Ltd, Rudrapur
INR
13.51 Crores
12+ 3
year O&M
16 UK/IDIPT/BHT/03
Lot 1
Trek Trail from
Pithoragarh to
Chandak
3.6.2014 M/S Soar Valley
Construction & JS
Matiyani, Pithoragarh
INR
0.89 Crores
12+18
17 UK/IDIPT/BHT/03
Lot 2
View Point at
Mostamanu
Temple
3.6.2014 M/S Soar Valley
Construction & JS
Matiyani, Pithoragarh
INR
0.99Crores
12+11
18 UK/IDIPT/BHT/03
Lot 3
Conservation of
Pithoragarh Fort
25.09.2014 M/s Dagmo Riba Itanagar INR 4.55
Crores
12+15
19 UK/IDIPT/BHT/04
Lot-1
Development of
Adventure
Center
BaurJalasaya
Lot-1
30.06.2015 M/s Litmus Marine
Innovation Pvt. Ltd.,
Mumbai
INR
6.13 Crores
17+4
20 UK/IDIPT/BHT/04
Lot-2
Development of
Adventure
Center
06.06.15 M/S Dagmo Riba, Rohini
Delhi
INR
8.17 Crores
17+4
5
SI.
No.
Package Ref No. General
Description
Goods or
Works
Contract
Signing
Date
Name of the Contractor Contract
Value
Contract
period in
months
BaurJalasaya
Lot-2
8. Progress of the work during reporting period is shown in Table 2.
Photographs showing project progress are given in Annexure 1, 2 and 3.
6
Table 2: Work Details and Risks For sub projects
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
UK/IDIPT/DDN/01-
LOT-1
Development of
Tourism
infrastructure
facilities at Asan
Barrage Dehradun-
Lot 1
Shri Rajendra Kumar Tripathy
• Admin. & kitchen block
• Cottages for tourists
• Security Cabin • Dormitory toilet • Open restaurant • Public toilets • Boating Deck • Viewing Deck • Signage • Floating Pontoon • Pathways
• Open sitting with
children Play area
• Landscaping
• Pump Room
• Over Head Water
Tank
• Parking
08.03.14 Handover on 30.04.2016
Completed all activity and handed over to GMVN for Operation and Maintenance
100% No change Appropriate measures has been taken for fulfillment of the objectives
NA
7
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
UK/IDIPT/DDN/03
Development of Yamuna Circuit Lot
1 (Tiger Falls & Lakhamandal
Temple)
M/S Aradhya
Engineers and
Construction & Pvt.
Ltd, Rishikesh
Tiger Fall
• Entrance Arch • Pathways
• Railing • Parking • Informative and
directional Signage • Bridge • External
Electrification • Prefab Toilet • Kiosk and Toilet at
parking lot • changing room and
Kiosk at fall site • sitting benches • Retaining and
Breast Wall with K.C Drains
• Pargola • Welcome Arches
Lakhamandal
• Path way • Parking area • Public Toilet
• Renovation of Entrance gate
09.06.2014 Tigerfall Handover on 4th April 16
and
Lakhamandal handed over on 13th May 16
Finishing work of all activities
100% No change in Tiger Falls Site.
Few changes suggested by ASI were incorporated
(Parking was shifted outside the ASI regulated zone)
.
NA
8
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
• Renovation of Public Toilet
• Electrical and solarlights
• Pathway to cave • Welcome Arches
UK/IDIPT/DDN/05
Development of Yamuna Circuit Lot 3 (Hanol Mahasu &
Tree Samadhi**)
M/S Dagmo Riba Itanagar
• Entrance Arch • Road • Dias Platform • Pathways
• Stairs • Heritage Railing • Parking • Drinking Water
Fountain • Informative and
directional Signage • External
Electrification • Kitchen and
Longer • Pre-fab Toilet • Guest House • Retaining and
Breast Wall with K.C Drains
• Welcome Arches
15.05.2014 14.11.2015
Extended upto
20.07.2017
Process for handing
over the project to
Temple Committee is
in process,
Wooden entrance
Gate:- Wooden
carving at entrance
gate work is in
progress.
TRH :- Plastering work completed and Internal finishing such as floor tile, colour washing to be started.
72.00% Snanghat, Kiosk, has been dropped due to land unsuitable for construction
Renovation of existing TRH
Plastering
Flooring
Electrical and sanitation works have been taken up
Works in ASI regulated zone have been completed
No risks envisaged
9
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
UK/IDIPT/DDN/04 Under
Force
Accounts
MoU has
been
signed with
Forest
Dept.
• Landscaping,
Fencing and
plantation
• Renovation of
FRH
• Water Boring
and Water
Supply
• Other facilities(procurement of portable solar lanterns, portable tents, canteen equipments, Binoculars, torch and LPG gas
18.08.2014 17.08.2015
Overhead Tank fitting and supply. Works almost completed, only commissioning of water system not executed.
95% No Appropriate measures has been taken for fulfillment of the objectives
None.
Works completed.
UK/IDIPT/DDN/06 Lot 2 –P-1 (W) Location- Bageshwar-Kapkot
M/s Samir
Kumar
Mishra
Civil work: Staff Residence and Interpretation Centre
30.05.2016 30.11.2017 RCC retaining wall work of third lift work in progress. Work slowed due to continuous heavy rain and cloud burst at Kapkot.
4.00 % No change so far
Work slowed due to late land (17.02.2017) allotment, and continuous heavy rain
Weather disturbances may affect project progress
10
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
UK/IDIPT/DDN/06 Lot 2- P-2 (W)
Location- Champawat-Tanakpur2
M/s Samir
Kumar
Mishra
Civil work: Staff Residence and Interpretation Centre
30.05.2016 30.11.2017 Finishing work such as plastering works in progress and procures other finishing items materials at site such as floor tile, wooden D &W etc.
54.50% Proposed location for the Center in Champawat Baturi-Pancheswar was shifted to Tanakpur in Champawat due to administrative reasons. Addendum to IEE is under process. Correspondence details attached
Annexure 6
Work progress is satisfactory
Appropriate measures has been taken for fulfillment of the objectives
2 Proposed Location Baturi-Pancheswar in Champawat was changed to Tanakpur-Champawat due to administrative reasons. Addendum to IEE Development of Adventure
Tourist Centres in Uttarakhand is under process.
11
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
UK/IDIPT/DDN/06 Lot 2-P-3 (W)
Location- Pauri
M/s Kailash Bisht Jv withLaxman Prasad Daya Bhawan Agences chowk , Pauri.UK
Civil work: Staff Residence and Interpretation Centre
07.06.2016 06.12.2017 Interpretation Center: - Color washing and final finishing work is in progress. Caretaker Room: - Color washing and final finishing work is in progress.
47.00% No change so far
Work progress is slow due to weather condition
Appropriate measures has been taken for fulfillment of the objectives
Weather disturbances may affect project progress
UK/IDIPT/DDN/06 B - Lot 1 –P1 (G)
M/s Rite
Equipment
JV
Bangalore
Supply of goods 20.05.2017 19.11.2017 Work order issued
UK/IDIPT/DDN/06 A - Lot 1 –P2 (G)
M/s Litmus
Marine
Innovation
Pvt. Ltd. ,
Mumbai
Supply of goods 29.04.2017 28.10.2017 Work order issued
UK/IDIPT/DDN/06 A - Lot 1 –P3 (G)
M/s R & R
Adventure
J/V,
Delhi
Supply of goods 17.10.2016 16.04.2017 Supply of goods completed at UTDB office
12
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
Upgradation of Tourist Facilities at TRH Parichay, Naukuchiyatal UK/IDIPT/BHT/01
M/S Dagmo Riba Itanagar
• TRC Restaurant
• TRH Main Building
• LA Works
• Annexe Building
• Dormitory
• Services
• Electrical Work
• Tent Platform
30.07.2014 Extended upto 30-07-2017
A-
Restaurant Building
(82.20%)
Electrical work
(wireing, point, G. I.
box, modular etc. work)
is under progress.
Expose stone masonry
varnish coating work is
under progress.
B- Main Building
(34.96%)
Cleaning of Stone
surface is under
progress.
False Ceiling work is
under progress.
Repairing and Fixing of
wooden purlins (for
roofing) are under
progress.
Repairing and refixing
of wooden beams are
under progress.
Fixing of GI sheet is
under progress.
Lean concrete under
flooring is under
progress.
Anti Termite Treatment
(A. T. T.) work under
63.53% Minor change
as per site
requirement
Appropriate
measures have
been taken for
fulfillment of the
objectives
Not
anticipated,
only in case of
force majeure
13
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
flooring is under
progress.
Fixing of GI Ridge &
Hips work is under
progress.
Cement plaster work is
under progress.
Wooden window
panelled and glazed
shutter making works
are under progress
Toilet brick work is
under progress.
Wooden flooring work
is under progress. x-
Wooden railing work is
under progress.
Ground floor chir wood
false ceiling work is
under progress.
C-L. A. Work
(76.24%) Pathway work is under
Progress.
Local Patal work over
Amphitheater steps is
under progress.
Cafe deck works are
under progress.
Surface preparation
work is under progress
14
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
for landscaping.
Doob grass work is
under progress.
m- R. R. Masonry work
for dry stone pitching is
under progress.
o-Kota Stone fixing in
stair work is under
progress.
p- Gravel path is under
progress.
Annexe
Building (60.82%) Flooring work is under
progress.
Toilet wall & floor tile
fixing work are under
progress.
Door & window fixture
fixing work are under
progress.
E- Dormitory Building (90.14%).
Toilet floor & wall tile
fixing work are under
progress.
UPVC door frame &
panel fixing is under
progress.
Roof painting work is
under progress.
15
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
Expose stone masonry
varnish coating work is
under progress.
F-Services (38.29%)
G-Rehabilitation of
Tent Platform
(98.73%)
Amelioration of Lake Naukuchiatal,
Naukuchiatal UK/IDIPT/BHT/02
M/S Global Aqua
Treatment Technology Pvt. Ltd, Rudrapur
• Construction of Compressor Houses (3 Nos.)
• Supply of Compressors & Aeration System
• Installation & Commissioning
• Operation & Maintenance Bio
manipulation
10-09-2014 O & M upto 21-07-2018
A- Compressor House Complete
B-Supply, Installation of compressors and Aeration system: Complete Bio manipulation and O&M is in progress.
100% O & M and
Biomanipulation work is in progress
No change Appropriate measures have
been taken for fulfillment of the objectives
In case of any
violation of the conditions of Irrigation Dept.
Development of Adventure Tourist Center at BaurJalashay
UK/IDIPT/BHT//04- LOT1 (Goods)
M/s Litmus Marine Innovation Ltd.
Procurement of
Adventure Sports
Equipment for Lot 2
below
06.06.15
05.11.16
Physical
Progress-
87.97%
No change
Appropriate
measures have
been taken for
fulfillment of the
objectives
NA
16
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
Development of Adventure Tourist Center at Baur Jalashay
UK/IDIPT/BHT//04-LOT2
(Works)
M/s Dagmo Riba, Itanagar, Arunachal Pradesh
Construction of
Parking area,
Reception,
Interpretation Center,
Entrance Plaza,
Restaurant Dormitory,
Double bed rooms,
Equipment store
(Boat House), First
aid facility, Staff
Accomodation,
Entertainment area,
Public Convenience,
Watch Tower,
Waterscape, Children
Play area, Floating
jetty
30.06.15
extended upto 31.03.17
(1) Boat House
Restaurant-
Erection of
Column, Earth
filling &
compaction ramp
near activity
ground work in
progress 55%
work completed.
(2) Toilet Block-
Procurement of
material is in
process- 81%
work completed.
(3) Swimming Pool
Area-
Procurement of
material in
process- 71%
work completed.
(4) Main Building-
Plinth, brick
work, earth filling
completed, PCC
work and
Antitermite
treatment in
Physical
Progress-
53.95%
No change so
far
Excessive
rainfall may
raise the water
level of the
reservoir
which may
delay the
works.
Cooperation of
Irrigation
Dept. is
necessary
17
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
progress- 35%
work completed,
(5) Staff Quarter-
Procurement of
door, window,
shutter, roofing &
railing. Iron work
in progress- 75%
work completed.
(6) Pathway- Tile
work in progress,
(7) Landscape work
near swimming
Pool- Grassing
work in internal
court yard and
activity ground,
other places as
ramp preparation
& hedge work in
progress- 45%
work completed.
(8) Internal
electrification
15% completed
& External
Electrification-
Mostly treching
18
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
completed.
(9) Septic tank-
100% work
completed.
Trek Trail from Pithoragarh to Chandak, Pithoragarh UK/IDIPT/BHT/03
Lot 1
M/S Soar Valley Construction & GS Matiyani,
Pithoragarh
• Nature trail • Pilgrim trail • Viewing shelter • Seat walls • Open restaurant • Featured outlook • Planting • Stabilization of
ruins
22-06-2014 completed A-Nature Trail : Complete B-Pilgrim Trail : Complete Site handing over is
under progress.
100% Ruins
stabilization
works have
been
dropped
Appropriate measures have been taken for fulfillment of the objectives
NA
View Point at Mostamanu Temple, Pithoragarh UK/IDIPT/BHT/03 Lot 2
M/S Soar Valley Construction & GS Matiyani, Pithoragarh
• Boundary Wall • Toilet Block • Pathways • Seat Wall Cluster • Services • Viewing shelter • Signage & Dust Bin • Lighting Plan • Shop Platform • Relocated Room • Paving • Ampi theater • Tree Platform
22-06-2014 completed Complete Note: 1- Project is handed over to temple committee.
100% Shop platform works have been dropped due to objection of temple committee.
Appropriate measures have been taken for fulfillment of the objectives
NA
19
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
• Stairway • Shoe Storage
Conservation of Pithoragarh Fort, Pithoragarh UK/IDIPT/BHT/03 Lot 3
M/S Degmo Riba, Itanagar
• Demolition of Buildings
• Landscaping Works • Lighting Plan • Planting Plan • Restoration of Fort
Wall • Restoration of
Tehsil Office • Restoration of
Tehsil Residence • Restoration of SDM
Camp Office • Restoration of
Record Rooms • Signage and Waste
bins
13-10-2014 Extended 31.03.2017
1- Demolition of Buildings (100%) A-Store and Toilet Dismantling work of Kanungo Office, Khatouni building,Tehsil Abhilekhakar has been completed. 2-L.A.Work (25%) 3-Restoration of fort wall (25.77%) Pointing work for inside fort wall is under progress. 4-Restoration of Tehsildar Residence (80%) 5-Restoration of S.D.M. Camp Office (50%) 6-Restoration of Record Room (90%) 7-Restoration of Tehsil Office (6.14%)
59.35% Minor Change as per site requirement
Appropriate measures have been taken for fulfillment of the objectives.
Community support is necessary for the fulfillment of objectives
UK/IDIPT/KOT/01 Development of
M/S DagmoRib
Kotdwara gateway
and destination
09-07-2014 08-12-2015
08-12-2015 (
1- Finishing works on cottages for tourists
89.00% No change anticipated so
Compliance with EMP and
In case there is no compliance
20
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
North Entry in Corbett Sub-project
a, Itanagar connectivity, including
Visitor Information,
Facilitation and
Reception Centre
(384 m2);
Amphitheatre
Complex with toilet
block, food court,
Kitchen, Handicraft
stall (1400 m2);
Cottages for tourists
(4 Nos., 105 m2);
Convention Centre
cum restaurant (292
m2); Staff quarters
(100 m2); Overhead
Reservoir (60 m2);
Entrance Gate with
Security and Booking
counter (30 m2) /
landscaping and
Signage.
Extension has been granted up to August, 31, 2017
under progress
2- Convention Center cum restaurant finishing work under progress
3-Interpretation Center - Construction work is in progress
4- LPG Gas godown works are in progress
5- Landscape, tree plantation and pathway works in progress
6- Internal electrical works in progress
7- Fountain works are in progress
far beyond the granted extension period
monitoring plan are being ensured
with EMP mitigation and monitoring plan during construction and operation. phases
21
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
UK/IDIPT/KOT/02
Signage Sub-
project in
Uttarakhand
M/s Reynober SA, Madrid Spain in JV with M/s Prabhatam Advertising Pvt. Ltd
Signages work in Uttarakhand State
30.12.2014 30-06-2016 (Extension Granted up to March 31, 2017)
1- Signage work in 13 districts is in progress
2- Special signages construction works are in progress
3- Foundation works of 2022 signages completed (98 %
complete)
89% No change anticipated so far
The contractor has been instructed not to leave sites untidy and regular visits to sites are taken up
No risk as minor works for signage erection required
UK/IDIPT/KOT/03-
Lot-2
Adventure Sports Centre at Tehri under PIU Kotdwar - Lot 2
M/s Sunil Garg& Co. in JV with M/s Jai Durgey
Trading and Construction Co.
1-Reception & visitor
facilitation/
information center.
(760 Sqm. Floor
area)
2- Personal
Adventure and
Tourists recreation
facilities
1. House Boats/
Cruise boat
2. Canoeing
3. Kayaking
30.12.2014 30-05-2016 ( Extension Granted up to Apr 30, 2017 )
1- Finishing works of adventure sports Centre completed.
2- Minor repair for building under progress
3- Construction camp
under demolition
4- Landscaping works under progress
100% No change Compliance with EMP and environmental monitoring plan and regular
orientation and training of workforce on safeguards issues
In case there is no compliance with EMP during
operation phases
22
Name & No. of
Package
Name of
the
contractor
Listing of works
under the package
Starting Date(land
clearance) and schedule
date of completion
Type of works
Continued at Present
Progress
in %
Expected
change from
Approved
scope
Fulfillment of
objective Type
of remedial
measures
needed
Key
assumption
and risk affect
attainment the
objective Starting date Date of Completion
4. Zorbing
5. Jet Ski
6. Jet Boating
Angling
UK/IDIPT/KOT/03-
Lot-1
Adventure Sports Centre at Tehri under PIU Kotdwar - Lot 1
M/s Litmus Marine Innovation Pvt. Ltd., Mumbai
Procurement of
equipment and
safety gadgets for
Adventure Sports
Centre
27-01-2015 27-06-2016 ( extension granted up to March 31, 2017)
Major equipments have been procured and are stored at Adventure Sports Centre (W) site
79.98% No change anticipated so far.
Safe use of equipment during operation phase.
Chances of accident occurrence in operation phase if proper
safety measures are not followed by the facility operators and tourists
9. Any other information useful for assessing environmental performance of the project:
No additional information during this period
23
2. Compliance Status
10. Status of Compliance with EARF/ADB Procedures is shown in the following table:
Table 3: Status of Compliance with EARF/ADB Procedures*
Name & No. of Package Environment
Category Status of
preparation of IEE
Status of Approval by ADB
Date of Approval
Further Action needed For
Compliance & Responsibility
UK/IDIPT/DDN/ 01-Lot-1 B Completed and approved
Approved 01.01.2014 Regular monitoring and reporting of the
EMP UK/IDIPT/DDN/ 03 B Completed and
approved Approved 29.04.2014 Regular monitoring
and reporting of the EMP
UK/IDIPT/DDN/04 B Completed and approved
Approved 21.11.2016 Regular monitoring and reporting
UK/IDIPT/DDN/ 05 B Completed and approved
Approved 30.04.2014 Regular monitoring and reporting of the
EMP UK/IDIPT/DDN/ 06-LoT-23
(W) B Completed and
approved Approved 13.11.2014 Regular monitoring
and reporting of the EMP
UK/IDIPT/KOT/ 01 B Completed and approved
Approved 31-03-2014
Regular monitoring and reporting of
EMP UK/IDIPT/KOT /03-Lot-2 B Completed and
approved Approved 31-03-
2014 Regular monitoring
and reporting of EMP
UK/IDIPT/BHT/01
B Completed and approved
Approved 31.01.14 Regular monitoring and reporting of the
EMP UK/IDIPT/BHT/02 B Completed and
approved Approved 31.01.14 Regular monitoring
and reporting of the EMP
UK/IDIPT/BHT/03 Lot 1 B Completed and approved
Approved 29.05.14 Regular monitoring and reporting of the
EMP
UK/IDIPT/BHT/03 Lot 2 B Completed and
approved Approved 20.06.14 Regular monitoring
and reporting of the EMP
UK/IDIPT/BHT/03 Lot 3 B Completed and
approved Approved 29.04.14 Regular monitoring
and reporting of the EMP
UK/IDIPT/BHT/04Lot-2 B Completed and
approved Approved 19.12.14 Regular monitoring
and reporting of the EMP
*Only Works packages reported
3. Compliance Status with National/ State/ Local statutory environmental requirements
11. Status of Compliance with National/ State/ Local statutory environmental requirements is shown in the given table:
3 01 of the locations of the sub project Baturi-Pancheshwar in Champawat was shifted to Tanakpur in
Champawat due to administrative reasons. The addendum to IEE is under process.
24
Table 4: Status of Environment, Forest and other Clearance
Work (Package No.)
Applicable
Legislation/Type
of clearance
Clearance Given
by and date
Subject/I
ssue Remarks/Action needed
UK/IDIPT/DDN/01-LOT-1
Development of Tourism infrastructure facilities at Asan Barrage Dehradun- Lot 1
NOC from forest department
Chief wild Life Warden , Uttarakhand vide letter No 2260/3-6 dated 10th April 2013
Nil
Construction work complete as per conditions of the Clearance from the Chief Wild Life Warden
UK/IDIPT/DDN/03
Development of Yamuna Circuit (Tiger Falls &
Lakhamandal Temple)- Lot 1
NOC from ASI is required for works in the ASI regulated zone of Lakhamandal temple
NOC obtained from ASI on 25.02.2016
Nil Construction work complete as per clearance from ASI
UK/IDIPT/DDN/04
Deovan FRH
Executed by the Forest Dept. under Force Accounts
Nil Work almost complete
UK/IDIPT/DDN/05
Development of Yamuna Circuit (Hanol Mahasu & Tree
Samadhi) - Lot 3
NOC from ASI is required for works in the ASI regulated zone of
Hanol Mahasu temple
NOC Obtained from ASI 0n 25.02.2016
Nil Temple works completed as per conditions of NOC from ASI
UK/IDIPT/DDN/06 Lot 2 P-1
Development of Adventure
Tourist Centre-Kapkot
Nil No Clearance required as construction is being done at
existing land of UTDB
UK/IDIPT/DDN/06 Lot 2 P-24
Development of Adventure Tourist Centre-Tanakpur
Nil No Clearance required as construction is being done at existing land of UTDB
UK/IDIPT/DDN/06 Lot 2 P-3
Development of Adventure Tourist Centre-Pauri
Nil Renovation of existing TRH
No NOC is required
UK/IDIPT/KOT/01
Development of Tourism infrastructure for North Corbett Entry Point at Kotdwar
No environmental and forest
clearance requirement.
Not applicable Nil No action needed
UK/IDIPT/KOT/03-Lot-2
Adventure Sports Centre at Tehri under PIU Kotdwar - Lot
No environmental and forest clearance
Not applicable Nil No action needed
4 01 of the locations of the sub project Baturi-Pancheshwar in Champawat was shifted to Tanakpur in
Champawat due to administrative reasons. The addendum to IEE is under process. The correspondence details
are attached in Annexure 6.
25
Work (Package No.)
Applicable
Legislation/Type
of clearance
Clearance Given
by and date
Subject/I
ssue Remarks/Action needed
2 requirement.
UKIDIPT/BHT/01
Up gradation of Tourist
Facilities at TRH Parichay at
Naukuchiatal
NOC from KMVN MD, KMVN, vide letter no. 3087, dated 08-08-2013
Nil No action needed
UKIDIPT/ BHT/02
Amelioration of Lake
Naukuchiatal at Bhimtal
NOC from Irrigation Dept.
Chief Engineer, (North) vide letter no. D-57, dated 12-02-2013
Asst. Engineer, Jal Sansthan, Nainital, vide letter no3084, dated 25-10-2013
Nil O&M under process.
No action needed
UKIDIPT/ BHT/03/Lot-1
Trek Trail from Pithoragarh to Chandak at Pithoragarh
NOC from Forest Department,
Nagar palika,
Van Panchayat
DFO Pithoragarh vide letter No 2378/12-1 dated 15-02-2014
Executive Officer, Nagar Palika, Pithoragarh, vide letter dated 11-09-
2013
Sarpanch of Vanpanchayat, Bajethi dated 08-01-2014
Nil Works completed. No action needed
UKIDIPT/ BHT/03/Lot-2
Work of View Point in Mostamanu Temple at Pithoragarh
NOC from Mostamanu Temple Committee
Van Panchayat &
Gram Panchayat
Mostmanu Temple Committee, dated 12-09-2013
Vanpanchayat, Bakarkatia dated 17-02-2014
Gram Pradhan,
DhungaBhool, dated 17-02-2014
Nil Works completed. No action needed
UK/IDIPT/BHT/04-LOT-2
(Works)
NOC from Irrigation Dept., Uttarakhand
Irrigation Dept., Uttarakhand on 7th Nov, 2013
Nil Work is being carried out as
per directions of Irrigation Dept.
4. Compliance status with the environmental covenants as stipulated in the Loan Agreement
12. The status of compliance with environmental loan covenants is presented below:
26
Table 5: Status of Compliance with Environmental Loan Covenants
S.
No Covenants Compliance
1. The Borrower and the States shall ensure that the
preparation, design, construction, implementation,
operation and decommissioning of each Subproject and
all Project facilities comply with (a) all applicable laws
and regulations of the Borrower and the States relating
to environment, health, and safety; (b) the Environment
Safeguards; (c) the EAFR; and (d) all measures and
requirements set forth in the respective IEE and EMP,
and any corrective or preventative actions set forth in a
Safeguard Monitoring Report.
Compliance of (a) all applicable laws and regulations
of the Borrower and the States relating to
environment, health, and safety (b) Environment
Safeguards; (c) the EARF; and (d) EMP is being
ensured during sub projects implementation.
Safeguards – Related Provisions in Bidding
Documents and Works Contracts
The States shall ensure that all bidding documents and
contracts for Works contain provisions that require
contractors to:
(a) Comply with the measures and requirement
relevant to the contractor set forth in the IEE, the
EMPs, any RO and any IPP (to the extent they
concern impacts on affected people during
construction), and any corrective or preventative
actions set out in a Safeguard Monitoring Report;
(b) make available a budget for all such environment
and social measures;
(c ) provide the relevant State with a written notice of
any unanticipated environmental, resettlement or
indigenous peoples risks or impacts that arise
during construction, implementation or operation of
the Project that were not considered in the IEE, the
EMP, the or the IPP (if any): and
(d) Fully reinstate pathways, other local infrastructure,
and agricultural land to at least their pre-project
condition upon the completion of construction.
EMPs are made part of the contract agreements of
respective subprojects andare being complied with.
Orientation sessions are being carried out in each
site for better understanding of Safeguards
Compliance by the Contractor
Environmental monitoring and mitigation costs
allocated/ incorporated in contract agreements.
No such environmental impact has been identified so
for that was not considered in the IEE and in the
EMP. (If any such impact arises in future, will be
suitably addressed)
All the areas that if disturbed by construction
activities will be restored to pre-project condition by
the contractors.
Safeguards Monitoring and Reporting
11. The States shall do the following:
(a) Submit semi-annual Safeguards Monitoring
Reports to ADB and disclose relevant information
from such reports to affected persons promptly
upon submission;
(b) if any unanticipated environment and/or social
The seventh semiannual report is submitted herewith.
Subsequent reports will be submitted on time.
In case of any unanticipated environmental risks and
27
S.
No Covenants Compliance
risks and impacts arise during construction,
implementation or operation of the Project that
were not considered in the IEE, the EMP, any RP
or any IPP, promptly inform ADB of the
occurrence of such risks or impacts, with detailed
description of the event and proposed corrective
action plan; and Report any breach of compliance
with the measures and requirements set forth in
the EMP, any IPP promptly after becoming aware
of the breach.
impacts arise, that shall be immediately informed to
ADB with detailed description of the event and
proposed corrective action plan.
Breach will be reported to ADB immediately after
becoming aware of it.
28
5. Compliance Status with Environment Management and Monitoring Plans as stipulated in the
environmental documentation as agreed with ADB
13. The compliance Status with Environment Management and Monitoring Plan is shown in the following table:
Table 6: EMP Implementation Status
S.
No
Sub Project Name EMP Part of
Contract
Documents
EMP being
Implemented
Status of EMP
Implementation
Actions Proposed/
Additional Corrective
Measures Required
(Yes/No) (Yes/ No) (Excellent/
Satisfactory/
Partially
Satisfactory/
Below
Satisfaction)
1. UK/IDIPT/DDN/01-LOT-1
Development of Tourism infrastructure facilities at Asan Barrage Dehradun- Lot 1
Yes Yes Satisfactory. Operation phase monitoring is being done
Proposed activity has been completed and asset handed over to GMVN
2 UK/IDIPT/DDN/03
Development of Yamuna Circuit (Tiger Falls &Lakhamandal Temple)-
Lot 1
Yes Yes Satisfactory. Operation phase monitoring is being done
Proposed activity has been completed and asset handed over to Village committee
3 UK/IDIPT/DDN/05
Development of Yamuna Circuit (Hanol Mahasu & Tree Samadhi) - Lot 3
Yes Yes Satisfactory No additional corrective measures proposed.
4 UK/IDIPT/DDN/04
Deovan FRH
Yes Yes Satisfactory
Project was executed by the
Forest Dept., under Force Accounts
Works 95% complete
5. UK/IDIPT/DDN/06 (Lot-2) P-1
Development of Adventure Centres in Uttarakhand-Kapkot
Yes Yes Partially Satisfactory
Contractor was directed to improve solid waste and sanitation conditions at site
UK/IDIPT/DDN/06 (Lot-2)
P-2 Development of Adventure Centres in Uttarakhand-Tanakpur 5
Yes Yes Satisfactory
5 01 of the locations of the sub project Baturi-Pancheshwat in Champawat was shifted to Tanakpur in
Champawat due to administrative reasons. The addendum to IEE is under process.
29
S.
No
Sub Project Name EMP Part of
Contract
Documents
EMP being
Implemented
Status of EMP
Implementation
Actions Proposed/
Additional Corrective
Measures Required
(Yes/No) (Yes/ No) (Excellent/
Satisfactory/
Partially
Satisfactory/
Below
Satisfaction)
UK/IDIPT/DDN/06 (Lot-2)
P-3Development of Adventure Centres in Uttarakhand-Pauri
Yes Yes Partially Satisfactory
Solid waste management to be improved
6 UK/IDIPT/BHT/01
Upgradation of Tourist Facilities at TRH Parichay, Naukuchiatal
Yes Yes Satisfactory On an average 10 (labourers have been deployed for the construction activities.
Contractors have provided basic safety equipment like safety Hat, safety Boots & first-aid box at site.
Dust bins provided for collection of solid waste materials. Suggested proper solid waste management
Contractor/PIU has been instructed for the safe disposal of construction waste material.
7 UK/IDIPT/BHT/02
Amelioration of Lake
Naukuchiatal, Naukuchiatal
Yes Yes Satisfactory The project is in O&M phase. , Water quality
monitoring and stocking of beneficial fishes is being regularly done by Dept. of Fisheries Pantnagar University and as per monitoring results, physical condition of Naukuchiyatal lake is improving. Lake is found fit for survival of aquatic
ecosystem.
8 UK/IDIPT/BHT/0 3/ lot- 1/CA/03/2014-15 Trek Trail From Pithoragarh to Chandak, Pithoragarh
Yes Yes Satisfactory Project Completed
Facility constructed under the subproject is being efficiently utilized by the community and is under the process of handing
30
S.
No
Sub Project Name EMP Part of
Contract
Documents
EMP being
Implemented
Status of EMP
Implementation
Actions Proposed/
Additional Corrective
Measures Required
(Yes/No) (Yes/ No) (Excellent/
Satisfactory/
Partially
Satisfactory/
Below
Satisfaction)
over to the Pithoragarh Nagar Palika. Accordingly, a joint inspection of the site has been completed on 17th June and issuance of handing over letter along with the signing of MoM is under process.
9 UK/IDIPT/BHT03 /LOT- 2/CA/04/2014-15 View Point at Mostamanu
Temple, Pithoragarh
Yes Yes Satisfactory. Project Completed
The activity under this sub project, officially, has already been handed over
to the Temple Committee for taking care of its operation and maintenance in future. The Temple Committee has submitted that all the construction activities are completed and members are satisfied with the quality of the work.
10 UK/IDIPT/BHT03 /LOT-3 Conservation of Pithoragarh Fort Phase-I
Yes Yes Satisfactory On an average 15 labour have been deployed for the construction activities.
Contractors have provided basic safety equipment like safety Hat, safety Boots & first-aid box at site.
Labour are staying in the existing building of the Fort. Contractor directed to improve housekeeping at site.
11 UK/IDIPT/BHT//04- LOT1
(Goods)
Development of Adventure Tourist Center at Baur Jalashay
Yes Yes Satisfactory On an average 35 local laborers have been deployed for the construction activities. Contractors have provided PPEs, site Safety training is being
31
S.
No
Sub Project Name EMP Part of
Contract
Documents
EMP being
Implemented
Status of EMP
Implementation
Actions Proposed/
Additional Corrective
Measures Required
(Yes/No) (Yes/ No) (Excellent/
Satisfactory/
Partially
Satisfactory/
Below
Satisfaction)
UK/IDIPT/BHT/04-LOT2
(Works)
Development of Adventure Tourist Center at Baur Jalashay
imparted to the laborers and supervisors from time to time. Dust bins provided for collection of solid waste materials. Suggested for proper solid waste management
12 UK/IDIPT/KOT/01
Development of Tourism infrastructure for North Corbett Entry Point at
Kotdwar
Yes Yes Partially Satisfactory
The contractor has been instructed to carry out preparation for landscaping and plantation works as monsoon season is starting from July. The contractor has been instructed to segregate construction waste scattered around site for reutilization and recycle.
13 UK/IDIPT/KOT/02
Signages works in Uttarakhand State
Not applicable as this is category C project and very minor works of signage erection
Mitigation measures being followed.
Satisfactory The contractor has been advised not to leave signage sites and surroundings untidy and carry out proper compaction and not to create inconvenience to road users during the signage erection works. .
14 UK/IDIPT/KOT/03-Lot-2 Development of Adventure Tourist centre at Tehri
Yes Yes Satisfactory The mitigation measures as per EMP are being followed. The contractor has been instructed to utilize maximum waste material in the filling works and landscaping. - The contractor has been instructed to collect construction waste, packing materials scattered all over site. 3- The contractor has been instructed to dismantle construction camp and leave the site tidy.
32
S.
No
Sub Project Name EMP Part of
Contract
Documents
EMP being
Implemented
Status of EMP
Implementation
Actions Proposed/
Additional Corrective
Measures Required
(Yes/No) (Yes/ No) (Excellent/
Satisfactory/
Partially
Satisfactory/
Below
Satisfaction)
4- The contractor has been instructed to carry out environmental monitoring for summer season and submit report.
33
Table 7: EMP Monitoring Status Chart
Table 7(i): EMP Monitoring Status Chart- Asan Barrage
IEE/EMP Component
Environmental issues Responsibility
Actions during Reporting Period Compliance
issues
Corrective actions
UK/IDIPT/DDN/01-LOT-1
Location • Siting of facilities • Lack of sufficient Planning • Impact on archaeological remains • Other
PMU & DSC
1 Construction camp established within project site boundary 2. Layout for the project has been developed considering tourism promotion and tourists requirements. IEE and EMP have been prepared and EMP being complied with 3. No site of archaeological remains in the vicinity 4. None
1- No issue
Not Applicable
Pre-construction activities by
the Contractor
1.Construction Camps 2.Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas (Asan Barrage) 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste mgmt. on site
Contractor & DSC
Pre-construction activities completed before the current reporting period. So this is not applicable
Not Applicable
Not Applicable
Construction 1.Improper stockpiling of construction materials 2. Quarry/ Borrow pit operations 3.Stripping, stocking and preservation of top soil 4. Soil erosion 5.Soil & Water pollution due to fuel and lubricants, construction waste 6.Siltation of water bodies 7.Generation of dust 8.Emission of construction vehicles, Equipment & Machinery 9.Noise from construction equipment 10.Material handling at site 11.Disposal of construction waste/debris 12.Safety measures 13. Risks force majeure 14. Malaria risk 15. Construction Staff causing disruption to migratory birds 16.Clearing of construction camps and restoration
Construction activities completed before the current reporting period. So this is not applicable
Not Applicable
34
Operation 1. Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5.Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities
PMU, UTDB
Project has been handed over to GMVN on April 2016. Project activity
completed on March 2016.
Regular maintenance of sanitary facilities
GMVN is being regularly monitored by the DSC and PIU. No. of dustbins have been increased.
35
Table 7(ii): EMP Monitoring Status Chart- Tiger Fall and Lakhamandal
IEE/EMP
Component
Environmental issues Responsibility Actions during Reporting Period Compliance
issues
Corrective
actions
UK/IDIPT/DDN/03
Location • Siting of facilities • Lack of sufficient Planning • Impact on archaeological
remains • Other
PMU & DSC 1 Construction camp established within project site boundary
2. Layout for the project has been developed considering tourism promotion and tourists requirements. IEE and EMP have been prepared and EMP being complied with 3. No site of archaeological remains in the vicinity 4. None
Not Applicable
Not Applicable
Pre-construction activities by
the
Contractor
1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas (Tiger Fall) 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste mgt on site
Contractor & DSC
Pre-construction activities completed before the current reporting period. So this is not applicable
Not Applicable Not Applicable
Construction 1.Improper stockpiling of construction materials 2. Quarry/ Borrow pit operations 3.Stripping, stocking and preservation of top soil 4. Soil erosion 5.Soil & Water pollution due to fuel and lubricants, construction waste 6.Siltation of water bodies 7.Generation of dust 8.Emission of construction vehicles, Equipment & Machinery 9.Noise from construction equipment 10.Material handling at site 11.Disposal of construction waste/debris 12.Safety measures 13. Risks force majeure 14. Malaria risk 15.Clearing of construction
camps and restoration
Construction activities completed before the current reporting period. So this is not applicable
Not Applicable
36
IEE/EMP
Component
Environmental issues Responsibility Actions during Reporting Period Compliance
issues
Corrective
actions
Operation 1.Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads
onto the existing waste disposal facilities
PMU, UTDB Project handed over to Village committee on April 2016 for Operation and Maintenance.
Project handed over to Temple committee Lakhamandal on dated 13th May ‘2016
In Tiger Falls, after handing over the Project to Village Committee, operation and maintenance of the assets is being done by them successfully
In case of Lakhamandal capacity building of the committee is being continuously done by the NGO and PIU to achieve project objectives
NGO and PIU was instructed to conduct regular sessions on environment awareness and sanitation at Lakhamandal and conduct cleanliness drives at Tiger Falls with the help of community
37
Table 7(iii): EMP Monitoring Status Chart- Deoban Forest Rest House
Sl No
Environmental Issues Mitigation Measures Compliance Issues And Corrective Actions
UK/IDIPT/DDN/04
1. Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created of the surroundings
Activities were carried out in accordance with provisions of Forest Management Plan. Construction stage is over. No residual impacts were observed during the site visits.
Nil
2. 2.1 Selection of materials and
construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations
Construction stage is over. No residual impacts were observed during the site visits.
Nil
2.2 Construction Camps – Location, Selection, Design and Layout
Not Applicable Nil
2.3 Circulation plan during construction in the tourist destinations
Not Applicable Nil
2.4 Site clearance activities, including delineation of construction areas
Not Applicable Nil
2.5 Drinking water availability Not Applicable Nil 2.6 Waste disposal Not Applicable Nil 3. 3.1 Improper stockpiling of
construction materials cause impacts starting from obstruction of drainage, disturbance/ safety hazard to tourists, etc.
Not Applicable Nil
3.2 Quarry / Borrow pits Operations Not Applicable Nil 3.3 Arrangement for Construction
Water Not Applicable Nil
3.4 Soil and Water Pollution due to fuel and lubricants, construction waste Water Pollution from Construction Wastes
Not Applicable Nil
3.5 Generation of Dust Not Applicable Nil 3.6 Emission from Construction
Vehicles, Equipment and Machinery
Not Applicable Nil
3.7 Noise from construction activities and equipment
Not Applicable Nil
3.8 Material Handling at Site Not Applicable Nil 3.9 Disposal of Construction Waste
/ Debris / Cut Material Not Applicable Nil
3.10 Safety Measures During Construction
Not Applicable Nil
3.11 Clearing of Construction of Camps & Restoration
Not Applicable Nil
4. 4.1 Unhygienic condition due to poor
maintenance of sanitation facilities and irregular solid waste collection
The Forest department will carry out maintenance of the toilets, and carry out the regular collection of wastes, and will also ensure that sanitation improvements proposed
Project is complete but not considered 100% due to pending submissions from the Forest Dept. During site visit sanitation facilities and waste
--
--
38
do not result in pollution of groundwater. The transfer of waste will also ensure no spillage and all wastes will be transported to a designated solid waste treatment site.
management were found satisfactory. Also values of different environmental parameters monitored were found much below the permissible levels indicating no residual impacts on environment quality.
39
Table 7 (iv): EMP Monitoring Status Chart- Development of Adventure Tourist Centres in Uttarakhand
IEE/EMP
Compone
nt
Environmental issues Responsibi
lity Actions during Reporting Period
Complianc
e issues
Correctiv
e actions
UK/IDIPT/DDN/06 Lot 2 P-1, P-26 and P-3
Location 1. Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created and the architectural /archaeological character of the surroundings
PMU & DSC
Location planned strategically in due consultation with stakeholders and proper technical assessment by Experts.7
Not Applicable
No action is needed as this stage for the sub
project is over.
Pre-construction activities by the Contractor
1. Layout of components to avoid impacts on the aesthetics of the site 2. Increased storm water runoff from alterations of the site’s natural drainage patterns due to landscaping, excavation works in the periphery of construction of parking lots, and addition of paved surfaces. 3. Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations 4. Integration of energy efficiency and energy conservation programs in design of subproject component
Contractor & DSC
1. Lay out done in consideration of
aesthetics of site.
2. Components have been planned
as per sites natural drainage
patterns.
3. Project is very small in nature and
emphasis is given to local
material and craftsmanship.
4. Energy efficiency shall be
ensured through purchase of
energy efficient electric fixtures
and water saving plumbing
measures, use of local adaptable
and less water requiring plants in
landscaping.
5. Site work and construction of
RCC and RR retaining wall on
work on under progress at
Kapkot.
Not Applicable
Not Applicable
Construction
1. Construction Camps 2.Site clearance activities, including delineation of construction areas 3.Drinking water availability 4. Identification of disposal sites 5. Waste Disposal 6. Improper stockpiling 7.Quarry/ Borrow pit operations 8. Soil erosion 9. Soil & Water pollution due to
Contractor & DSC
1- No construction camps at all 03 sites Kapkot, Tanakpur and Pauri. Labour resides in existing residence on rent. Mostly local labour.
Submission of Environmental
monitoring report for post monsoon
Usage of PPEs at site
The contractor has been instructed
to submit environmental monitoring report
The contractor has been
2- The stage of site clearance and delineation of construction areas is over.
3- Drinking Water Arrangements:
Kapkot
Potable water supplied by contractor
6 01 of the locations of the sub project Bautadi in Champawat was shifted to Tanakpur in Champawat due to
administrative reasons. The addendum to IEE is under process.
7 Owing to administrative reasons, 01 of the proposed location for the sub-project Baturi-Pancheshwar was
shifted to Tanakpur-Champawat. DM’s request letter attached Annexure 6.
40
IEE/EMP
Compone
nt
Environmental issues Responsibi
lity Actions during Reporting Period
Complianc
e issues
Correctiv
e actions
fuel/lubricants 10. Siltation of water bodies 11. Generation of dust 12.Emission from constn
vehicles 13.Noise from constn equipment 14. Material handling at site 15.Disposal of constn waste/debris 16. Safety measures 17. Clearing of Construction of Camps and Restoration
to laborers at Kapkot
Tanakpur
Existing boring water used by laborer for drinking purpose at Tanakpur
Pauri
Potable Drinking water is being made available at construction site by existing jal sansthan supply.
advised to enforce usage of PPEs at site without fail.
4 Identification of disposal sites Kapkot Kapkot waste stored for land filling Tanakpur In Tanakpur, so far waste is being utilized for filling at site only Pauri Waste disposal in Pauri is done at the designated site in consultation with DSC Engineer and Pauri Nagar Palika. 5. Waste Disposal Not much domestic waste is generated at sites At kapkot waste being disposed in municipality dusbins Waste is stored in dustbins at site and disposed in municipality dustbins at Tanakpur. Waste is stored in dustbins at site and disposed in municipality dustbins at Pauri 6- Stockpiling of construction material is demarcated but is not covered in Tanakpur.
In Pauri, since land constraint is there, material is brought as per demand and not much is stocked.
7-There has been no requirement for borrow pit operations. The sand is being procured from licensed quarries in both sites. There has been no requirement for sub grade in the reporting period. 8- At Kapkot to check soil erosion, retaining wall is under construction No issue of soil erosion at Tanakpur
41
IEE/EMP
Compone
nt
Environmental issues Responsibi
lity Actions during Reporting Period
Complianc
e issues
Correctiv
e actions
site since it is plain land. At Pauri existing DTDO’s office is being renovated, so no issue of soil erosion 9- The fuel and lubricants are being stored in drums and construction machinery is not maintained at site. The fuel is purchased on need basis Hence, there are no chances of water and soil pollution. 10- No water bodies are nearby areas of Kapkot This is not applicable to Tanakpur site, as river is not within impact zone. There is a seasonal (monsoon) water body close to sub project site in Pauri, but works are mainly of renovation. so there is no issue of siltation 11- Contractor has taken a rented room to keep the materials properly at Kapkot. The dust generation due to material handling is being controlled through water sprinkling and covering the stockpiles of raw material in Tanankpur. In Pauri, raw material is brought as per demand and stored in existing building. 12- At Kapkot no heavy machinery is available at this stage. At Tanakpur, the construction vehicle usage at site is not needed except for bringing construction materials at site. The frequency of trucks bringing construction materials is once or twice a week. The other source is emissions from mini Generator set operated intermittently for casting only. At Pauri, there is no generator. The emissions on account of vehicle movement are insignificant. 13- The only noise generated at site is from portable concrete mixer. It is operated intermittently. 14- At kapkot material handling is satisfactory. The material handling at site has not been satisfactory in Tanakpur during reporting period, as workers were not seen using personal protective equipment (PPEs) such as hand gloves, boots, helmets, etc. while handling the
42
IEE/EMP
Compone
nt
Environmental issues Responsibi
lity Actions during Reporting Period
Complianc
e issues
Correctiv
e actions
construction materials. At Pauri, usage is satisfactory.
15- Disposal of construction waste/debris- discussed under sl.no.4 above.
16- Works in the reporting period at kapkot were minor pertaining only to site clearance and construction of retaining wall. Usage of PPEs at tanakpur and Pauri is partially satisfactory. 17-Not applicable.
Operation 1Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities
PMU, UTDB
1-The sub project has not reached Operation phase, so this is not applicable.
Not Applicable
Not applicable
43
Table 7 (v): EMP Monitoring Status Chart- Development of Tourism Infrastructure for North Corbett Entry Point at Kotdwara
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
UK/IDIPT/KOT/01
Location 1. Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created and the architectural /archaeological character of the surroundings
PMU & DSC Not Applicable as this environmental issue pertains to pre construction stage and this stage of sub project is over.
1- No issue
No action is needed as this stage for the sub project is over.
Pre-construction
activities by the Contractor
1. Layout of components to avoid impacts on the aesthetics of the site 2. Increased storm water runoff from alterations of the site’s natural drainage patterns due to landscaping, excavation works in the periphery of construction of parking lots, and addition of paved surfaces. 3. Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations 4. Integration of energy efficiency and energy conservation programs in design of subproject component
Contractor & DSC 1-Not Applicable as this environmental issue pertains to pre construction stage
and this stage of sub project is over.
Not Applicable Not Applicable
2-Not Applicable as this environmental issue pertains to pre construction stage and this stage of sub project is over.
3-Not Applicable as this environmental issue pertains to pre construction stage and this stage of sub project is over.
4-Not Applicable as
this environmental issue pertains to pre construction stage and this stage of sub project is over.
44
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
Construction 1. Construction Camps 2.Site clearance activities, including delineation of construction areas 3.Drinking water availability 4. Identification of disposal sites 5. Waste Disposal 6. Improper stockpiling 7.Quarry/ Borrow pit operations 8. Soil erosion 9. Soil & Water pollution due to fuel/lubricants 10. Siltation of water bodies 11. Generation of dust 12.Emission from constn vehicles 13.Noise from constn equipment 14. Material handling at site 15.Disposal of constn waste/debris 16. Safety
Contractor & DSC 1-The project is in finishing stage. The construction camp has been demolished. At the site landscaping and tree plantation works are to be taken up in the coming monsoon season. The contractor has been instructed to prepare for plantation works.
1-Usage of PPEs during material handling
2 Environmental monitoring report submission for summer season.
3-Usage of PPEs at site .
4-Usage of discarded construction waste for fill
works.
5- Stabilization of side slopes at water bodies
6- Demarcation
of excavated areas with caution tapes.
1- The contractor has been instructed to enforce usage of PPEs.
2 The contractor has been instructed to carry out
environmental monitoring as early as possible for summer season.
3- Contractor has been instructed to submit details
for side slopes protection at water bodies.
4- The contractor has been instructed to utilize remaining
2- The stage of site clearance and delineation of construction areas is over during pre construction phase so this is not applicable
3- Potable Drinking water is being made available at construction site by the contractor for all the construction work force.
45
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
measures 17. Clearing of Construction of Camps and Restoration
4- The contractor was instructed to identify location for waste disposal. It has been decided later that construction waste and debris will be utilised for filling works at the Gas Godown, water body under development. Most of the construction waste has already been utilized in filling. Remaining waste has been stored at an isolated location at site and will be utilised in fill works at water bodies.
construction waste in fill works.
5- The contractor has been instructed to put caution tape around all excavated areas at site.
5- Waste disposal has been explained at sl.no.4 6-Stockpiling of construction material is not much now because project is in finishing
stage. The construction material stockpiling is now under the semi finished buildings of
subproject.
7-There has been no requirement for borrow pit operations. The sand is being procured from licensed quarries. There has been no requirement for sub grade in the reporting period. 8- The soil erosion issue may come up at water body location as this is under development.
46
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
The contractor has been advised to stabilize the side slopes with proper compaction and shrubs plantation. 9- The fuel and lubricants are being stored in drums and construction machinery is not maintained at site. The fuel is purchased on need basis from the petrol pumps at Kotdwara. Hence, there are no chances of water and soil pollution. 10- There is no water body close to sub project site, so there is no issue of siltation. This environmental issue is not applicable to Kotdwara site. 11- The dust generation due to material handling is being controlled through water sprinkling and storing materials in the semi finished building of the sub project. Since site is ready for landscaping so dust generation chances are minimum. 12-The construction vehicle usage at site is not needed except for bringing construction materials at site. Most of construction materials and finished items such as tiles, Granite slabs, cement bags, etc. have already been transported to the site. The other
47
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
source is emissions from DG set operated intermittently for concrete mixer. This DG set is maintained properly. The emissions on account of vehicle movement are insignificant. 13- The only noise generated at site is from portable concrete mixer. It is operated intermittently. The construction workers were not seen using personal protective equipment (PPEs). The construction activities are not taken up during night time. 14- The material handling at site has not been satisfactory, during reporting period, as workers not seen are using personal protective equipment (PPEs) such as hand gloves, boots, helmets, etc. while handling the construction materials. 15- Disposal of construction waste/debris- discussed under sl.no.4 above. 16- The safety measures such as usage of PPEs, fencingof excavated sites for water bodies, and trenches for laying of electrical cables with caution tapes,
48
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
etc. have not been seen at sites during various visits.
17- The construction camp has been demolished and the site is restored to original form.
Operation 1Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities
PMU, UTDB 1-The sub project has not reached
Operation phase, so this is not applicable.
Not Applicable Not applicable
49
Table 7(vi): EMP Monitoring Status Chart- Signages works in Uttarakhand State
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
UK/IDIPT/KOT/02- Signage Works in Uttarakhand
Location 1. Siting of facilities 2 Lack of sufficient planning 3.Impact on archaeological remains 4. Other
PMU & Line Agency
1-The locations have been finalised by the signage expert in consultation with tourism department and other relevant stakeholders. This has been done during DPR preparation. So this is not applicable.
Not Applicable as this stage in the sub project is over.
Not Applicable
2- The planning for locations of various signage works has been done after due consideration of tourism potential in the state in the DPR phase. This is not applicable for reporting period.
3- No impacts on archeological remains has been identified so far.
4- No other unforeseen issue related to signage has been encountered so far.
Design & pre construction
impacts
1. Impact on sensitive areas 2. Slope stability related issues 3. Increased storm water runoff 4. Impact on ground water quality 5. Impact on aesthetic appeal 6. Integration of energy
DSC & PIU 1- This stage in the sub project is over, however, no impact on sensitive areas, as all signage works are within the existing RoW of NH/SH/MDR. This is a pre construction environmental issue, hence not applicable for the reporting period.
Not Applicable as this stage is over for the sub project.
Not Applicable
2- The signages works require very less area (<5 m2) for foundation so no
50
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
conservation slope stability related issue faced in the sub project. This is a pre construction environmental issue, hence not applicable for the reporting period. 3- No issue related to storm water runoff in signage works as these have been planned either in already existing RoW of Roads or fully developed land owned by the Government in urban areas of Uttarakhand state. This is a pre construction environmental issue, hence not applicable for the reporting period. 4- No impact on ground water quality due to erection of tourism signages. This is a pre construction environmental issue, hence not applicable for the reporting period. 5-The impacts on aesthetic appeal were not identified during design and pre construction issue. This is a pre construction environmental issue, hence not applicable for the reporting period. 6- The signage works are along the roads and no specific lighting/ electrification around these has been planned. So
51
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
this is not applicable. This is a pre construction environmental issue, hence not applicable for the reporting period.
Pre-construction
activities by the Contractor
1.Construction Camps 2. Defining of construction/work areas on ground for activities within 200m of the boundaries of the protected areas 3. Circulation plan during construction 4. Site clearance activities 5. Drinking water availability 6. Identification of disposal sites 7. Waste management on sub- project sites
Contractor & DSC 1-The signage works do not require construction camp establishment so this is not applicable.
Not applicable as this stage is over for the sub project.
Not Applicable
2- The signage locations are well within the existing RoW of roads and these have been planned sufficiently away >200m from the archaeological sites. 3- No specific circulation plan required for signage construction works. 4- Site clearance activities not needed as the works are within the existing RoW and the works are very small in nature. 5- The construction crew moves with all construction materials and signage components and stays in hotels in urban areas so drinking water availability is not an issue. 6-The waste generation at individual sites is insignificant as small works for foundation of signage are carried out. So there is no issue of waste disposal. 7- This is not applicable as team
52
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
working on signage works is not leaving any waste at signage site.
Construction impacts
1. Improper stockpiling 2.Quarry/ Borrow pit operations 3.Stripping, stocking & preservation of top soil 4.Soil erosion 5. Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9. Noise from constn equipment 10. Material handling at site 11. Disposal of constn waste/debris 12. Safety measures 13. Risks force majeure 14. Malaria risk 15. Chance archaeological finds 16.Religious structures 17. Construction Staff causing disruption to migratory birds
Contractor 1- Stockpiling of construction materials is not
required in signage works.
1- At some locations where signage works
have been completed, some left over construction material was
seen and at some locations compaction around foundation and on side slopes of road was not done properly. This may result in soil erosion.
1- The contractor has been
instructed to compact the base around foundation properly and
not to leave any discarded materials or excavated earth.
2- The signage works are small in nature and do not require quarry and
borrow pit operations.
3- The signage works are being taken up in an area (<5 m2) within the RoW of road, so top soil generation is insignificant. Any small quantity generated is used in filling works after
completion of foundation works.
4-No soil erosion issue has been there till now in the erection of signages.
5- There is no
storage of fuel and lubricant at location of signage works. The construction crew is moving in a truck so issue of water and soil pollution due to fuel and lubricants is not there.
6- No issue of siltation into water
bodies as works at individual sites are very small in nature.
53
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
7-Dust generation issue is not there. While doing foundation works material handling is manual by the workers.
8-The only construction vehicle used is truck carrying cement, sand and sigange foundation components of steel. Hence no issue of emissions from construction vehicle. The truck being used has pollution under control certificate.
9-No noise generation issue as no construction equipment are being used. The construction material is mixed manually by the construction crew.
10-The material handling at signage site is proper. The construction crew uses gloves, shoes, etc. while handling materials at site.
11- There is no generation of construction waste/debris at individual sites of signanges. No specific plan is required for disposal of construction waste/debris. At some sites, discarded
54
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
construction waste was seen.
12-The construction crew is using PPE while working at sites. This has been observed during site visits.
13- No risk force Majeure during reporting period.
14-No malarial risks identified as there is no impoundment of water at the individual sites of
signage works. These being within RoW of roads, which is well drained.
15-No chance finds encountered during reporting period. Hence no action required.
16-No impacts on religious structures, during the reporting
period, as signage works locations are away from the religious structures. The sub project will have positive impact as it will ease accessibility to pilgrims to the locations of religious structures.
17-The construction
crew is not staying at site, so no risk to migratory birds.
55
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
O & M impacts 1. Environmental conditions 2.Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities
PMU, Contractor & DSC
The sub project has not reached operation stage as signage works are in progress so this is not applicable.
Not applicable Not Applicable
56
Table 7(vii): EMP Monitoring Status Chart- Development of Adventure Tourist Centre at Tehri
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
UK/IDIPT/KOT/03-Lot-2
Location impacts
1. Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created and the architectural /archaeological character of the surroundings.
PMU & Line Agency
1-No actions as the location of sub project finalized considering all aspects of long term sustainability and protection of assets. This is a pre construction environmental
issue, hence not applicable for the reporting period.
No issue related to location finalisation. This stage in the sub project is over, so not applicable.
None as this stage is over.
Design & pre construction
impacts
1. Layout of components to avoid impacts on the aesthetics of the site 2. Increased storm water runoff from alterations of the site’s natural drainage patterns due to landscaping, excavation works in the periphery of construction of parking lots, and addition of paved surfaces. 3. Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations 4. Integration of energy efficiency and energy conservation programs in design of subproject
DSC & PIU 1- No action as layout of sub project finalized during early stage of sub project implementation. This is a pre construction environmental issue, hence not applicable for the reporting period.
This stage of the project is over, so this is not applicable
Not Applicable
2- No such issue encountered during pre construction stage as sub project site is on slope having quick drainage to Tehri lake. This is a pre construction environmental issue, hence not applicable for the reporting period. 3- The selection of materials and construction technologies already finalized during pre construction stage, so no action required during reporting period.
57
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
component 5. Slope Stability related issues
4- The energy efficiency and energy conservation measures considered during project design, so no action required during reporting period as this a design phase issue. Lighting system of building utilizes LED lights. 5- The necessary slope protection works through retaining wall have been taken up as part of sub project component in the pre- construction phase. The retaining wall works have been completed, so no action during reporting period.
Pre-construction
activities by the Contractor
1. Construction Camps 2.Site clearance activities, including delineation of construction areas 3.Circulation plan during construction in the tourist destinations 4.Drinking water availability
Contractor & DSC 1-Construction camp has been established near sub project site. The DSC has monitored sanitation, drinking water facilities, etc. at the construction camp. Now the subproject
construction works have been completed, the construction camp is empty. This is a pre construction environmental issue, hence not applicable for the reporting period.
No issues as this stage of project is over. Hence not applicable.
Not Applicable
2- Site clearance activities over during
pre construction stage, hence this is not applicable for the reporting period.
58
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
3- The construction of sub project did not have any impact on movement tourists during the reporting period.
4-The drinking water
has been made available to the construction work force during the reporting period. The drinking water for the camp is sourced through water tankers. This is being monitored by the DSC team during the reporting period.
Construction impacts
1. Waste Disposal 2. Improper stockpiling 3.Quarry/ Borrow pit operations 4. Soil erosion 5. Soil & Water pollution due to fuel/lubricants 6. Siltation of water bodies 7. Generation of dust 8.Emission from construction vehicles 9.Noise from construction equipment 10. Material handling at site 11.Disposal of construction waste/debris 12. Safety measures 13. Clearing of Construction of Camps and Restoration
Contractor 1-Since the project is at completion stage, most of the construction waste has already been utilized in filling works. During the site visits, waste material in the form of Scattered shuttering material, cement bags, packing polythene wastes, leftover sand and tiles were seen.
1- Use of personal protective equipment to be enforced to the entire construction crew.
2- The
contractor is in the process of dismantling of construction. The camp site to be reinstated to original form.
3- Segregation of scattered construction waste and
identification of waste disposal site.
4- Completion of environmental monitoring for summer
1- The contractor has been advised to enforce usage of PPEs for the entire work force in maintenance works being taken up.
2- The contractor has been advised to dismantle the remaining portion of camp and not to leave any construction camp demolition waste at site. The camp site has to be left in its original form. 3- The
2- Now the construction works are complete so no stockpiling of construction
materials is required.
3- During the construction phase, contractor was obtaining sand for construction works from the licensed
59
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
quarries only. Borrow area operations were not required to be operated.
season. contractor has been advised to collect and segregate construction waste such as shuttering materials, steel bars, cement bags, etc. This waste needs to be collected and disposed off to leave the site surroundings tidy. 4- The contractor has been advised to submit the monitoring report for summer season.
4- In order to avoid soil erosion
protection works in the form retaining wall have been taken up in the beginning phase of the project. The retaining wall construction works have been completed before this reporting period. There has been no issue of soil erosion during the reporting period.
5- The fuel for construction works is not stored at site. It is purchased on need basis from the petrol pumps. Now, there is no requirement of storage of lubricants as construction works for the project are over. Hence no issue of soil and water pollution of Tehri Lake on account of fuel and lubricants.
6- The construction material storage
requirements in the project are over as works have been completed. Now there are no excavation works requirements also. Hence there is no issue of siltation in
60
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
Tehri Lake on account project activities.
7-The generation of dust has been controlled through water sprinkling
during the reporting period. The storage of cement in shed and storage of construction materials (prone to airborne due to winds) for the maintenance of building was observed in inside one portion of building completed. The dust generation is minimal as finishing works of project are also completed.
8- The emissions from construction vehicles were controlled through regular maintenance during the reporting period. Now construction materials transportation to site is not required. Hence vehicular emissions are not there on account of construction
activities.
9-Now since construction works for the subproject are completed, so there is no issue of noise generation from the project.
61
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
10-The material handling at site is is not required except for some minor repairs of subproject project building completed. Although, the contractor has procured personal protective equipment such as helmets, Gloves, safety shoes, etc. some of the construction
workers were seen not using these PPEs during the reporting period.
11- Disposal of construction waste/Debris- This has already been discussed under sl.no.1
12- The safety measures such as usage of PPEs, fencing of excavated sites with tapes, and proper storage of steel bars, etc. has been observed partially satisfactory during the reporting period. The site engineers of DSC although regularly instruct for this. 13- The sub project construction works are completed and
almost all workers are also demobilised, so contractor has dismantled part construction camp. The contractor needs to demolish
62
IEE/EMP
Component
Environmental
issues Responsibility
Actions during
Reporting Period
Compliance
issues
Corrective
actions
the remaining portion of construction camp and reinstate the construction camp to original form. The DSC environmental expert has instructed to identify site for camp demolition waste and to reinstate camp site to original form. This activity will be monitored in the next few months
after the reporting period.
O & M impacts 1. Environmental conditions 2. Uncontrolled tourism 3. Management of the toilet blocks 4. Adequate drainage 5. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection 6. Increased waste loads onto the existing waste disposal facilities 7. Operation of Motor boats
PMU, Contractor & DSC
The sub project construction works are not yet completed, hence this is not applicable.
Not Applicable Not Applicable
63
Table 7(viii): EMP Monitoring Status Chart - Upgradation of Tourist Facilities at TRH Parichay
IEE/EMP Components
Environmental Issues Responsibility Action during Reporting period
Compliance Issues
Corrective Actions
UK/IDIPT/BHT/01 Location impacts
Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created and the architectural character of the surroundings.
PMU & Line Agency
The project site is existing Tourist
Rest House
No issue Not applicabl
e
Design & pre construction impacts
1. Increased storm water runoff from alterations of the site‘s natural drainage patterns due to additional structures in TRH complex and landscaping works in the area and on lake edge.
DSC & PIU Impacts considered and
measures integrated in
design
No issue Not applicabl
e
2. Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations 3. Integration of energy efficiency and energy conservation programs in design of subproject components
Pre-construction activities by the contractor
1. Circulation plan during construction in the tourist destinations
Contractor & DSC
Circulation plan made
No issue
2. Site clearance activities, including delineation of construction areas
Site clearance done by contractor
3. Drinking water availability and water arrangement
Drinking water is available at site 500m away (Hand Pump) is being used by the labour
4. Identification of sites for disposal of construction and demolition work Designated site for
waste Disposal by the local municipality is being used for dumping of the domestic waste
Construction impacts
1. Improper stockpiling of construction materials cause impacts starting
Contractor Construction Material Properly stockpiled and
No issue
I
64
IEE/EMP Components
Environmental Issues Responsibility Action during Reporting period
Compliance Issues
Corrective Actions
from obstruction of drainage, disturbance/ safety hazard to tourists, etc.
brought as per demand
2. Stripping, stocking and preservation of top soil
Demolished waste and excavated material from working site and use/ disposal of the same as per Mitigation measures in EMP
No issue
3. Soil Erosion 3. Construction is being done in place of existing structures as per EMP there is no issue of soil erosion.
No issue
4. Soil and Water Pollution due to fuel and lubricants, construction waste
4. Since no major equipment is being used at site storage is not required. Fuel is being carried as per requirement
No issue
5. Siltation of water bodies due to spillage of construction and demolition wastes
5. Construction waste is being used for ground filling and remaining is being disposed as per EMP
No issue
6. Generation of Dust 6. Water sprinkling is being done regularly at construction site and construction material is being carried by covered truck.
No issue
7.Emission from construction vehicles, equipment and machinery
7. Only Vibrators and one concrete mixer is being used. No Major vehicles / equipments are present at site.
No issue
8. Noise from construction equipment
8. Only Vibrators and one concrete mixer is being used. No Major
No issue
I
65
IEE/EMP Components
Environmental Issues Responsibility Action during Reporting period
Compliance Issues
Corrective Actions
vehicles / equipments are present at site.
9. Material Handling at Site 9.Proper Material handling is being done for storage and disposal as per EMP
No issue
10. Disposal of Construction Waste/ Debris
10. Demolished waste and excavated material are stocked at working site. There is need to dispose of this material
Proper Disposal of demolition waste
Contractor/PIU have been instructed for the same
11. Safety Measures During Construction
11. Using Personal Protective Equipment like helmets and shoes are being used by workers. Warning tape has been provided around the Construction site
11. Other cautionary signage need to be provide
11. Contractor has been instructed to provide other cautionary signage at Construction Sites
12. Risk caused by Force Majeure
12. NA
13. Malaria Risk 13. Precaution being taken as per EMP
No issue
O&M impacts 1.Environmental Conditions
PMU, Contractor & DSC
Not Yet Started
2. Adequate drainage of site area 3. Increased waste loads onto the existing waste disposal facilities (that are non conformant to the Government requirements for SWM)
I
66
Table 7(ix): EMP Monitoring Status Chart - Amelioration of Lake Naukuchiatal
IEE/EMP Compon
ents
Environmental Issues Responsibility
Action during Reporting period
Compliance Issues
Corrective Actions
UK/IDIPT/BHT/02 Location impacts
1. Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created and the architectural character of the surroundings.
PMU & Line Agency
The project scope involves aeration and bio-manipulation of the lake, for which locations for compressor have been chosen after technical examination and feasibility assessment.
No issue Not applicable
2.Impact on archaeological remains No Archeological
remains exist at the site Design & pre construction impacts
1. Slope stability related issues
DSC & PIU Impacts considered and measures integrated in the design
No issue as this stage is over
Not applicable
2. Increased storm water runoff from alterations of the site‘s natural drainage patterns due to excavation works in the periphery of the lake and addition of paved surfaces. 3. Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations 4. Integration of energy efficiency and energy conservation programs in design of subproject components
Pre-construction activities by the contractor
1. Circulation plan during construction in the tourist destinations
Contractor & DSC
No issue as this stage is over
Not applicable
1. Site clearance activities, including delineation of construction areas 2. Drinking water availability and water arrangement 3. Identification of disposal sites
Construction impacts
1. Improper stockpiling of construction materials cause impacts starting from obstruction of drainage, disturbance/ safety hazard to tourists, etc.
Contractor No issue, since construction activity completed
Not applicable
2. Soil Erosion
67
IEE/EMP Compon
ents
Environmental Issues Responsibility
Action during Reporting period
Compliance Issues
Corrective Actions
3. Soil and Water Pollution due to fuel and lubricants, construction waste 4. Siltation of water bodies due to spillage of construction wastes 5. Generation of Dust 6. Emission from Construction Vehicles, Equipment and Machinery 7. Noise from construction Equipments 8. Material Handling at Site
9. Impacts due to operation of construction equipment 10. Disposal of Construction Waste/ Debris / Cut Material/weeds 11. Safety Measures During Construction 12. Risk caused by Force Majeure 13. Malaria Risk
O & M impacts
Environmental Conditions
PMU, Contractor & DSC
The Dissolved Oxygen (DO) Temperature, pH TDS Transparency are being recorded regularly by the contractor as well as by the GB Pant Univ. The present Dissolved oxygen level is 0.34 to 8.55 mg/l on surface while, Transparency level ranged between 1.24 to 1.60 meter. Similarly, temperature varied between 23.0 oC to 23.6oC. The pH value was 7.60 to 8.65. The environmental condition is improving gradually. Fingerlings of mahsheer, Rohu, catla & silver carp are being regularly introduced in the lake for biomanipulation.
Algal growth in lake. Mortality of stocked fingerlings
Manual cleaning process should be regularly carried out. Contractor. Mortality needs to be checked.
Management of the toilet blocks
No toilet block available. One Toilet need to be provide at each compressor
PIU need to take action for the construction of the toilet
68
IEE/EMP Compon
ents
Environmental Issues Responsibility
Action during Reporting period
Compliance Issues
Corrective Actions
house after discussion with LDA
Unhygenic condition due to poor maintenance of sanitation facilities and irregular solid waste collection
No major sanitation facility required.
One Toilet need to be provide at each compressor house Litter bin needs to be provided
Contractor has been instructed to provide One Toilet and Litter bin at each compressor house
Increased waste loads onto the existing waste disposal facilities
Insignificant waste load envisaged due to only one employee required for operation at a time on each pump house.
No issue
69
Table 7(x): EMP Monitoring Status Chart - Trek Trail from Pithoragarh to Chandak, Pithoragarh
IEE/EMP Components
Environmental Issues
Responsibility Action during
Reporting period Compliance
Issues Corrective Measures
UK/IDIPT/BHT/03 - Lot 1
Location impacts
1. Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created and the architectural character of the surroundings.
PMU & Line Agency Not applicable No issue as this stage is
over
Not applicable
Design & pre construction impacts
1. Increased storm water runoff from alterations of the site‘s natural drainage patterns due to additional structures and landscaping works in the area.
DSC & PIU Not applicable No issue as this stage is
over
Not applicable
2. Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations 3. Integration of energy efficiency and energy conservation programs in design of subproject components 4. Slope stability related issues 5. In areas of shallow water table, ensure that the septic tanks developed, do not impact the ground water quality
Pre-construction activities by
1. Circulation plan during construction in the
Contractor & DSC Not applicable No issue as this stage is
over
Not applicable
70
IEE/EMP Components
Environmental Issues
Responsibility Action during
Reporting period Compliance
Issues Corrective Measures
the contractor
tourist destinations 2. Site clearance activities, including delineation of construction areas
Not applicable
3. Drinking water availability and water arrangement
Not applicable
4. Identification of sites for disposal of construction and demolition work
Not applicable
Construction impacts
1. Improper stockpiling of construction materials cause impacts starting from obstruction of drainage, disturbance/ safety hazard to tourists, etc.
Contractor Not applicable No issue as this stage is
over
2. Soil Erosion 3. Soil and Water Pollution due to fuel and lubricants, construction waste 4. Siltation of water bodies due to spillage of construction and demolition wastes
5. Generation of Dust
6. Emission from construction vehicles, equipment and machinery
7. Noise from construction equipment
8. Material Handling at Site 9. Disposal of Construction Waste/ Debris / Cut Material 11.Safety Not applicable
71
IEE/EMP Components
Environmental Issues
Responsibility Action during
Reporting period Compliance
Issues Corrective Measures
Measures During Construction 12. Risk caused by Force Majeure 13. Malaria Risk
O & M impacts
1. Environmental Conditions
PMU, Contractor & DSC
Precaution being taken as per the EMP
No issue
2. Adequate drainage of site area
Precaution has been taken during construction.
No issue
3. Increased waste loads onto the existing waste disposal facilities (that are non-conformant to the Government requirements for SWM)
Increased waste loads not envisaged. Dustbin along the trek trail and proper disposal of solid waste have been suggested
Proper disposal of solid waste
Waste bin needs to
be provided along the trek trail
72
Table 7(xi): EMP Monitoring Status Chart - View Point at Mostamanu Temple, Pithoragarh
IEE/EMP Components
Environmental Issues Responsibility Action during Reporting period
Compliance Issues
Corrective Actions
UK/IDIPT/BHT/03 - Lot 2
Location impacts
1. Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets created and the architectural character of the surroundings.
PMU & Line Agency
Not applicable No issue as this stage is
over
Not applicable
Design & pre construction impacts
1. Increased storm water runoff from alterations of the site‘s natural drainage patterns due to additional structures and landscaping works in the area.
DSC & PIU Not applicable No issue as this stage is
over
Not applicable
2. Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations 3. Integration of energy efficiency and energy conservation programs in design of subproject components 4. Slope stability related issues 5. In areas of shallow water table, ensure that the septic tanks developed, do not impact the ground water quality
Pre-construction activities by the contractor
1. Circulation plan during construction in the tourist destinations
Contractor & DSC
Not applicable No issue as this stage is
over
Not applicable
2. Site clearance activities, including delineation of construction areas 3. Drinking water availability and water arrangement 4. Identification of sites for disposal of construction and demolition work
Construction impacts
1. Improper stockpiling of construction materials cause impacts starting from obstruction of drainage, disturbance/ safety hazard to tourists, etc.
Contractor No issue as this stage
is over
2. Stripping, stocking and preservation of top soil
3. Soil Erosion 4. Soil and Water Pollution due to fuel and lubricants,
73
IEE/EMP Components
Environmental Issues Responsibility Action during Reporting period
Compliance Issues
Corrective Actions
construction waste 5. Siltation of water bodies due to spillage of construction and demolition wastes
6. Generation of Dust 7. Emission from construction vehicles, equipment and machinery
8. Noise from construction equipment
9. Material Handling at Site 10. Disposal of Construction Waste/ Debris / Cut Material
11.Safety Measures During Construction
12. Risk caused by Force Majeure
13. Malaria Risk O & M impacts
1. Environmental Conditions PMU and Temple Committee
Precaution being taken as per the EMP
No issue
2. Increased waste loads onto the existing waste disposal facilities
Regular Solid waste generation is very less.
However on local
festival, solid waste
increase, for which extra bins need to be provided.
Extra Waste bin needs to
be provided in
temple compound.
3. Unhygienic condition due to poor maintenance of sanitation facilities and irregular solid waste collection
Dustbin have been suggested and management committee members has been oriented for proper solid waste management
Proper disposal of solid waste
Collected west in
Dust bin needs to
be transported
at Municipal dumping
site regularly
74
Table 7(xii): EMP Monitoring Status Chart - Conservation of Pithoragarh Fort, Pithoragarh
IEE/EMP Components
Environmental Issues Responsibility Action during Reporting period
Compliance Issues
Corrective Actions
UK/IDIPT/BHT/03 - Lot 3
Location impacts
1. Lack of sufficient planning to assure long term sustainability of the improvements and ensure protection of the assets
created and the architectural character of the surroundings.
PMU & Line Agency
The project site is existing at Pithoragarh Fort Complex
No issue
Not applicable
Design & pre construction impacts
1. Increased storm water runoff from alterations of the site‘s natural drainage patterns due to additional structures and landscaping works in the area.
DSC & PIU Impacts considered and measures integrated in the design
No issue
Not applicable
2.Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations
3.Integration of energy efficiency and energy conservation programs in design of subproject components
Pre-construction activities by the contractor
1.Circulation plan during construction in the tourist Destinations
Contractor & DSC
Circulation plan made No issue
Not applicable
2.Site clearance activities, including delineation of construction areas
Site clearance done by contractor
3.Drinking water availability and water arrangement
Municipal water is being used by the labour
4.Identification of sites for disposal of construction and demolition waste
Construction/demolition waste is being disposed at designated site identified by PIU
Construction impacts
1.Improper stockpiling of construction materials cause impacts starting from obstruction of drainage, disturbance/ safety hazard
to tourists, etc.
Contractor 1. Construction Material Properly stockpiled.
No issue
2.Stripping, stocking and preservation of top soil
2.Demolished waste and excavated material from working site and use / disposal of the same as per Mitigation measures in EMP
No issue
3.Soil Erosion 3.Construction is being done in place of existing
No issue
75
IEE/EMP Components
Environmental Issues Responsibility Action during Reporting period
Compliance Issues
Corrective Actions
structures as per EMP
4.Soil and Water Pollution due to fuel and lubricants, construction waste
4. Since no major equipment is being used at site storage of Fuel is not required. Fuel is being carried as per requirement
Testing of water quality
Contractor has been instructed to get regular testing of air water and noise as per EMP
5.Generation of Dust 5. Water sprinkling is being done regularly at construction sites and construction material is being carried by covered truck.
Testing of ambient air quality
6.Emission from
construction vehicles, equipment and machinery
6. No major equipment/ machinery is being used at site .
Testing of ambient air quality
7.Noise from construction equipment
7. No Major equipments/ machinery are being used at site no noised generation is envisaged.
Testing of ambient noise quality
8.Material Handling at Site 8.Proper Material handling is being done for storage and disposal as per EMP
No issue
9.Disposal of Construction Waste/ Debris / Cut
Material
9. Demolished waste and excavated material from working site and use / disposal of the same as per Mitigation measures in EMP
No issue
10.Safety Measures During Construction
10. Using Personal Protective Equipment like helmets and gum boot are being used by workers
No issue
11.Risk caused by Force Majeure
11.NA
12.Malaria Risk 12. Precaution being taken as per EMP
No issue
O & M impacts
1.Environmental Conditions PMU, Contractor & DSC
Not yet started
2.Adequate drainage of site area
76
Table 7(xiii): EMP Monitoring Status Chart – Development of Adventure Centre at Baur Jalashay
IEE/EMP Components
Environmental Issues
Responsibility Action during Reporting period
Compliance Issues
Corrective Actions
UK/IDIPT/BHT/04-LOT-2 (Works)
Location impacts 1. Siting of facilities PMU & DSC Integrated in design, all care has been taken to plan activities in accordance with Irrigation Dept. norms.
No Issue NA 2. Lack of sufficient
Planning 3. Lay out of
Components to avoid impacts in site aesthetics
4. Slope stability related issues
4.Slope stability issue is not much as site is plain land
No Issue NA
5. Increased storm water runoff
5. The storm water runoff from the project is diverted to the reservoir through drainage system of project.
No Issue NA
Design & pre construction impacts
1. Increased storm water runoff from alterations of the site‘s natural drainage patterns due to additional structures and landscaping works in the area.
DSC & PIU Pre No issue Not applicable
2.Selection of materials and construction technologies, if not carefully chosen, will adversely impact the aesthetic appeal of the destinations 3.Integration of energy efficiency and energy conservation programs in design of subproject components
Pre-construction activities by the contractor
1. Construction Camps
Pre-construction activities are over. Construction camps are established in vacant space near the site and provided with sanitation and potable drinking water through the existing bore well/ tube well. Waste material due to site clearance and construction activity was stored and kept aside for utilization in later phase of
No Issue NA
2. Sanitation facilities at camps
3. Circulation plan during construction
4. Site clearance activities
5. Drinking water availability
6. Identification of disposal sites
7. Waste mgt on site
77
IEE/EMP Components
Environmental Issues
Responsibility Action during Reporting period
Compliance Issues
Corrective Actions
construction. Construction impacts
1. Improper stockpiling of construction materials
1. Stockpiling has been done in designated places with barricade and signage.
No issue NA
2. Quarry/ Borrow pit operations
2. The contractor is obtaining sand and sub grade from the licensed quarries. The borrow earth requirement is not there at present in the project.
3. Stripping, stocking and preservation of top soil.
3. Top soil has been stored in designated places for later use in landscaping.
4. Soil erosion 4. No cutting or steep slope issues involved in the project. Small excavations are protected with steel sheets or wooden boards
5. Water pollution due to fuel and lubricants, construction waste
5. The fuel and lubricants are not stored at site and are purchased from market as per need.
6. Siltation of water bodies
6. No disposal done in the water body
7. Generation of dust 7. Generation of dust is on account of material handling at site. Necessary dust suppression measures such as water sprinkling are followed
8. Emission of construction vehicles, Equipment & Machinery
8. Materials carrying vehicle are covered- reducing dust hazard & Water sprinkling at construction site for arresting dust
9. Noise from construction equipment
9. Only vehicles with PUC certificate allowed at the construction site
10. Material handling at site
10. Proper Material handling is being done for storage and disposal as per EMP
11. Disposal of construction waste/debris
11. Disposal of the construction waste as per Mitigation
78
IEE/EMP Components
Environmental Issues
Responsibility Action during Reporting period
Compliance Issues
Corrective Actions
measures in EMP 12. Safety measures
during Contractor. 12. Using Personal
Protective Equipment like helmets and gum boot are being used by workers.
First Aid Box is available at working site. Orientation on Health & Safety of workers, given. Engaged all workforces from nearby village.
13. Construction Staff causing disruption to migratory birds
13. Staff oriented on the sensitivity of area wrt birds (work site is quite away from reservoir so as to impact birds.)
14. Clearing of construction camps and restoration
14. Since work is in progress. Restoration of site will be start after completion of the work.
O & M impacts Environmental Conditions Uncontrolled tourism flow Operation and management of Water Sports Activity
PMU, UTDB Not reached Operation phase
NA
1. Operation of Motor Boats
2. Demarcation and Flagging
3. Zonation of risky, shallow and sensitive areas
4. Health and Safety risks
79
6. Approach & Methodology engaged for environmental monitoring of the project
5. Continuous monitoring of EMP implementation is being carried out by DSC, PIU and PMU.
6. Concerned staff of DSC and PIU visit the construction sites and report to Team Leader DSC and PMC about
issues/ problems related to environmental non-compliance. Necessary directions, in case of non-compliance are
being issued to the contractors on the site and through letters about the procedures to resolve the
problems/issues or requirements. The Safeguards Staff of DSC conduct regular site visits to monitor the
implementation of safeguards measures on sites. In the reporting period PMU organized orientation program for
all technical persons of PMU, PIU, DSC, PMC and Contractors and plans to organize more such programs in
future.
7. Monitoring of environmental receptors/ attributes
Monitoring basis
7. Monitoring for the implementation of Environmental Monitoring Plan/Management Plan is required to be done
to check if any adverse impact is being caused by the construction activities. The monitoring of these variables is
to be carried out in construction sites within 100 m impact zone of the sub project.
8. The monitoring of environmental variables is to be carried out as per the agreed Environmental Monitoring
Plan.
Type of environmental receptor/ attribute to be monitored
9. The environmental attributes to be monitored include the air, noise and water quality parameters at the
construction sites in sub project sites. The air quality parameters monitored include RSPM (PM10), SO2 and NO2.
The water quality parameters include temperature, pH, electrical conductivity (EC), dissolved oxygen (DO),
biochemical oxygen demand (BOD), total suspended solids (TSS), total dissolved solids (TDS) and turbidity. In
case of noise the day time Leq values are monitored.
Methods of monitoring and equipment used
10. The following standard methodology is being used for monitoring
Table 8: Parameters and Methodology for Environmental Monitoring
Parameter Methodology
RSPM (PM10) High Volume Sampler method (attached with cyclone)/ Respirable Dust samplers.
SO2 Modified West and Gaeke Method
NO2 Jacob &Hochheiser Modified (Sodium Arsenite) Method.
Noise Level Direct Reading Sound Level Meter.
Temperature Digital/Mercury Thermometer Method.
pH Electrometric Method.
EC Electrometric Method.
DO Winkle’s Method Using Azide Modification
BOD5 Five Days BOD as per APHA 2005
TDS Digital Meter Method.
80
Parameter Methodology
TSS Gravimetry (Filtration and Drying at 105oc)
Turbidity Nephelo Turbidity Method.
8. Implementation of Environmental Monitoring Plan
PIU wise implementation of Environmental Monitoring Plan for sub projects is shown in tables 9
Table 9 (i): Implementation of Environmental Monitoring Plan- For Projects under DSC Dehradun
Component
Periods of
monitorin
g
Parameters/Pol
lutants Standard
Base line
status
Monitoring
result during
project
Implementation
Remarks
UK/IDIPT-III/DDN/01 Development of Tourism Infrastructure Facilities at Asan Barrage
(Operation stage monitoring)
Noise (near
main gate of
project site)
02.03.17 -
03.03.17
Sound Level Leq. dB(A)
Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time
Lmax -48.9(Day), 38.1 (Night) dB(A)
Lmin – 36.4(Day), 31.4(Night) dB(A)
Leq –
40.8(Day), 33.2(Night) dB(A)
CPBC limit for silence Zone db(A)-50.0 (Day), 40.0 (Night)
Within permissible limits
Noise (near
back side
of project
site)
02.03.17 -
03.03.17
Sound Level Leq. dB(A)
Noise Standards for 55 dB( A) for Day Time and
45 dB( A) for Night Time
Lmax -47.3(Day), 39.4 (Night) dB(A)
Lmin – 36.8(Day), 32.3(Night) dB(A)
Leq – 42.8(Day), 35.7(Night) dB(A)
CPBC limit for
Within permissible limits
81
Component
Periods of
monitorin
g
Parameters/Pol
lutants Standard
Base line
status
Monitoring
result during
project
Implementation
Remarks
silence Zone db(A)-50.0 (Day), 40.0 (Night)
Ambient Air
Quality
(near back
side of
project site)
02.03.17-
03.03.17
Particulate Matter (PM10), µg/m3
100 66.74
Within permissible limits
Particulate Matter (PM2.5),
µg/m3
60 39.32
Sulphur Dioxide (So2). µg/m3
80 13.56
Nitrogen Dioxide (No2) µg/m3
80 21.10
Carbon
Monoxide (Co), mg/m3
4 0.49
Ambient Air
Quality
(near main
gate of
project site)
02.03.17-
03.03.17
Particulate Matter (PM10), µg/m3
100 68.18
Particulate Matter (PM2.5), µg/m3
60 38.20
Sulphur Dioxide (So2). µg/m3
80 09.56
Nitrogen Dioxide (No2) µg/m3 80 22.33
82
Component
Periods of
monitorin
g
Parameters/Pol
lutants Standard
Base line
status
Monitoring
result during
project
Implementation
Remarks
Carbon Monoxide (Co), mg/m3
4 0.45
Water
Quality
(drinking
water( tap
water )
canteen
area)
02.03.17
PH (at 25°C)
Colour
Turbidity
Odour
Taste
Total Hardness as CaCo3
Calcium as Ca
Alkalinty as CaCo3
Chloride as CI
Magnesium as Mg
Total Dissolved Solids
Iron as Fe
Copper as Cu
Total Coliform
E. Coli
CPCB Standards for Surface water bodies and Drinking Water
Standards for Potable water
7.40
<5
BDL
Agreeable
Agreeable
193.21
62.34
234.15
51.45
9.15
290.0
0.14
<0.05
<2/100ml
Absent
Within permissible limits
Water
Quality
(lake of
Asan
Barrage)
02.03.17
PH (at 25°C)
Colour
Turbidity
Total Hardness
as CaCo3
Calcium as Ca
Alkalinty as CaCo3
Chloride as CI
Magnesium as
CPCB Standards for Surface water bodies
7.72
<5
BDL
134.12
45.10
169.88
14.30
5.24
Within permissible limits
83
Component
Periods of
monitorin
g
Parameters/Pol
lutants Standard
Base line
status
Monitoring
result during
project
Implementation
Remarks
Mg
Sulfate
Nitrate
Flouride
Sodium as Na
Potassium as K
TKN as N
Total Phosphorous
COD
Phenolic Compound
Iron as Fe
Boron
Sodium Absorption ratio
Free Ammonia as N
Dissolved Oxygen
BOD(3 days at 27)
Zinc as Zn
Arsenic as As
Mercury as Hg
Total dissolved Solids
44.23
1.36
0.65
12.45
24.65
1.97
0.32
10
<.002
0.18
0.11
1.23
0.82
4.10
5.40
0.21
<0.012
<0.002
270.00
UK/IDIPT/DDN/03 Development of Yamuna Circuit Tiger fall (Operation stage monitoring)
Noise (near 04.03.17 - Sound Level Leq. Noise Lmax -
84
Component
Periods of
monitorin
g
Parameters/Pol
lutants Standard
Base line
status
Monitoring
result during
project
Implementation
Remarks
Tiger fall
parking)
05.03.17 dB(A) Standards for 55 dB( A) for Day Time and 45 dB( A) for Night Time
52.5(Day), 42.7 (Night) dB(A)
Lmin – 40.2(Day), 36.4(Night) dB(A)
Leq – 46.6(Day), 39.5(Night) dB(A)
CPBC limit for residential Zone db(A)-55.0 (Day), 45.0 (Night)
Within permissible limits
Noise (near
Track trail)
04.03.17 -
05.03.17 Sound Level Leq. dB(A)
Noise Standards for 55 dB( A) for Day Time and
45 dB( A) for Night Time
Lmax -54.2(Day), 45.6 (Night) dB(A)
Lmin –
43.5(Day), 34.4(Night) dB(A)
Leq – 47.3(Day), 39.5(Night) dB(A)
CPBC limit for residential Zone db(A)-55.0 (Day), 45.0
(Night)
Within permissible limits
85
Component
Periods of
monitorin
g
Parameters/Pol
lutants Standard
Base line
status
Monitoring
result during
project
Implementation
Remarks
Ambient Air
Quality
(Track trail)
04.03.17 –
05.03.17
Particulate Matter (PM10), µg/m3
Particulate Matter (PM2.5), µg/m3
Sulphur Dioxide (So2). µg/m3
Nitrogen Dioxide (No2) µg/m3
Carbon Monoxide (Co), mg/m3
100
60
80
80
4
63.50
38.66
10.27
19.77
0.48
Within permissible limits
Ambient Air
Quality
(near
parking
site)
04.03.17 –
05.03.17 Particulate Matter (PM10), µg/m3
Particulate Matter (PM2.5), µg/m3
Sulphur Dioxide (SO2). µg/m3
Nitrogen Dioxide (N O2) µg/m3
Carbon Monoxide (Co), mg/m3
100
60
80
80
4
57.39
29.23
08.56
17.33
0.41
Within permissible limits
Water
Quality
(canteen
area)
04/03/17
PH (at 25°C)
Colour
Turbidity
Odour
Ground water IS 10500-2012
7.45
<5
BDL
Agreeable
Within permissible limits
86
Component
Periods of
monitorin
g
Parameters/Pol
lutants Standard
Base line
status
Monitoring
result during
project
Implementation
Remarks
Taste
Total Hardness as CaCo3
Calcium as Ca
Alkalinty as CaCo3
Chloride as CI
Magnesium as Mg
Total Dissolved Solids
Iron as Fe
Copper as Cu
Total Coliform
E. Coli
Agreeable
193.21
54.45
121.00
15.45
26.32
310.56
0.14
<0.05
<2/100ml
Absent
UK/IDIPT-III/DDN/03 Lakhamandal Temple (Operation stage monitoring)
Noise
(surroundi
ng area of
the
Temple,
Lakhamna
dal)
08.03.17
-
09.03.17
Sound Level
Leq. dB(A)
Noise
Standards
for 55
dB( A) for
Day Time
and 45 dB(
A) for Night
Time
Lmax -52.5(Day), 43.2 (Night) dB(A)
Lmin – 44.3(Day), 34.9(Night) dB(A)
Leq – 48.2(Day), 37.7(Night) dB(A)
CPBC limit for residential Zone db(A)-55.0 (Day),
Within permissible
limits
87
45.0 (Night)
Noise
(Near
village,
Lakhama
ndal)
08.03.17
-
09.03.17
Sound Level
Leq. dB(A)
Noise
Standards
for 55
dB( A) for
Day Time
and 45 dB(
A) for Night
Time
Lmax -50.7(Day), 44.6 (Night) dB(A)
Lmin –
42.2(Day), 32.8(Night) dB(A)
Leq – 45.9(Day),
37.4(Night) dB(A)
CPBC limit for residential Zone db(A)-
55.0 (Day), 45.0 (Night)
Within permissible
limits
Ambient
Air
Quality
(near
Lakhama
ndal
Temple)
08.03.17
-
09.03.17
Particulate Matter (PM10), µg/m3
Particulate Matter (PM2.5), µg/m3
Sulphur Dioxide (So2). µg/m3
Nitrogen Dioxide (No2) µg/m3
Carbon Monoxide (Co), mg/m3
100
60
80
80
4
62.20
32.14
8.26
18.30
0.36
Within permissible
limits
88
Ambient
Air
Quality
(near
parking
site)
08.03.17 -
09.03.17
Particulate
Matter (PM10), µg/m3
Particulate Matter (PM2.5), µg/m3
Sulphur Dioxide (SO2). µg/m3
Nitrogen Dioxide (N O2) µg/m3
Carbon Monoxide (Co), µg/m3
100
60
80
80
4
64.25
37.40
10.20
19.50
0.44
Within permissible limits
Water
Quality
(Near
Temple
Lakhamand
al)
08/03/17
PH (at 25°C)
Colour
Turbidity
Odour
Taste
Total Hardness
as CaCo3
Calcium as Ca
Alkalinty as
CaCo3
Chloride as CI
Magnesium as
Mg
Total Dissolved
Solids
Iron as Fe
Copper as Cu
Total Coliform
E. Coli
Ground
water IS
10500-
2012
7.46
<5
BDL
Agreeable
Agreeable
210.42
65.18
245.46
20.45
11.61
320.00
0.19
<0.05
<2/100ml
Absent
Within permissible
limits
89
UK/IDIPT/DDN/04 Development of Yamuna Circuit Deoban FRH (Operation stage monitoring)
Noise
Near main
gate of
FRH,
Deoban
7/03/2017
Sound Level Lmax, Lmin. dB(A)
Noise Standards for 50.00 dB( A) for Day Time and 40.00 dB( A) for Night Time (Silence Zone)
- Lmax -46.5 (Day), 38.3 (Night) dB(A)
Lmin – 36.2(Day), 29.7 (Night) dB(A)
Leq -42.4 (Day), 34.7 (Night) dB(A)
Values are well within permissible level
Air Quality
(Near main
gate of
FRH)
06/03/2017 - 07/03/2017
SO2, NOX, CO ,
PM10 and PM2.5
NAAQS
Standards
-
Industrial, Residential,
Rural and other Areas
Particulate Matter < 10 micron
100 µg/m3
64.40 µg/m3 All parameters of ambient air quality are well within the limits
Particulate Matter < 2.5 micron
60µg/m3
- 41.50 µg/m3
Sulphur dioxide,(SO2 )
80 µg/m3
7.40 µg/m3
Nitrogen dioxide(NO2)
80 µg/m3
16.25 µg/m3
Carbon Monoxide (CO)
04 mg/m3
for 08 hrs
0.54 mg/m3
Water
Quality
(Near
Kitchen
area)
(07/03/17) Drinking Water
Tap
CPCB Drinking Water
Standards for Potable water
1. pH-7.36
2. Colour<5
3. Turbidity –BDL
4. Odour-
Agreeable
5. Taste-
Agreeable
6. Total
Hardness -
174.26
7. Calcium as Ca
-58.45
8. Total Alkalinity
-193.56
90
9. Chloride-18.21
10. Magnesium -
6.90
11. Total
Dissolved
solid-254.00
12. Iron as Fe-
0.11
13. Copper as Cu
-<0.05
14. Total Coliform
-<2/1000ml
15. E.coli-Absent
91
Table 9 (ii): Implementation of Environmental Monitoring Plan- For Projects under DSC Kotdwar
Componen
t
Periods of
monitorin
g
Parameters/Pollutant
s Standard
Base
line
status
Monitoring
result during
project
Implementatio
n
Remarks
UK/IDIPT/KOT/01 Development of Tourism Infrastructure For North Corbett Entry Point at Kotdwara
Noise Winter
season
Sound Level Leq. dB(A) Noise
Standards
for 65
dB( A) for
Day Time
and 55 dB(
A) for Night
Time at
camp site
as site is in
urban and
commercial
area and 75
dB ( A) for
Day at
Constructio
n site and
70 dB( A) in
Night Time
at
Constructio
n site
Leq
(Day) =
59.00
dB (A)
Winter
season
1- At
construction
site
Leq ( Day ) =
50.40 dB ( A)
Leq (Night)
=41.1 dB(A)
Leq ( Min)
=39.8
Leq (Max)
=58.0 dB(A)
Construction
camp
demolished so
no
construction
camp data
The
measured
values are
well within
the limits
at sub
project site
Air Quality Winter
Season
SO2, NOX, CO , PM10
and PM2.5
NAAQS
Standards
Industrial,
Residential,
Rural and other
Areas
Particulate Matter < 10
micron
100 µg/m3
76.30
µg/m3
88.2 µg/m3 (at
construction
activity area of
project site )
Monitored
ambient air
quality is
well within
the
stipulated
limits at
sub project
site
Particulate Matter < 2.5
micron
Sulphur dioxide,(SO2 )
Nitrogen dioxide(NO2)
60µg/m3
80 µg/m3
80 µg/m3
02 mg/m3
52.80 µg/m3 14.50 µg/m3 11.70 µg/m3
46.80 µg/m3
(at construction
activity area of
project site)
22.0 µg/m3 (at
construction
activity area of
project site)
26.1 µg/m3(at
construction
activity area of
project site)
92
Componen
t
Periods of
monitorin
g
Parameters/Pollutant
s Standard
Base
line
status
Monitoring
result during
project
Implementatio
n
Remarks
Carbon Monoxide (CO)
for 08 hrs BDL
0.70 mg/m3
(at construction
activity area of
project site)
Water
Quality
Winter
Season
Parameters specified
for Drinking water in
IS: 10500
1- Drinking Water at
Camp and
Construction site
Drinking
Water
Standards
specified in
IS: 10500
1-
Colour-= <5 Hazen Unit
2- Odour= Agreeabl
e
3-pH= 7.3
4- Total Hardness as
CaCO3= 166 mg/l
5- TDS= 376 mg/l
6- BOD= no test done
7- Total Coliform=
Not detected
8- E-Coli=
Not detected
9- Iron as Fe =Nil
mg/l
10- Chloride as Cl= 69 mg/l
11- Fluoride
as F = 0.74 mg/l
1- Colour-= <1
Hazen Unit
2- Odour=
Agreeable
3-pH= 7.2
4- Total
Hardness as
CaCO3= 220
mg/l
5- TDS= 346
mg/l
6- BOD= no
test done
7- Total
Coliform= Not
detected
8- Iron as Fe
<0.1 mg/l
9- Chloride as
Cl= 30 mg/l
11- Fluoride as
F < 0.20 mg/l
All
parameter
s in the
drinking
water
sample
are well
within
Drinking
Water
standards.
93
Componen
t
Periods of
monitorin
g
Parameters/Pollutant
s Standard
Base
line
status
Monitoring
result during
project
Implementatio
n
Remarks
UK/IDIPT/KOT/03-Lot-2 Development of Adventure Tourist Centre at Tehri
Noise Winter
season
Sound Level Leq. dB(A) Noise
Standards
for 55
dB( A) for
Day Time
and 45 dB(
A) for Night
Time
Winter
season
1- At
Completed
Building of
subproject
Leq ( Day ) =
51.7 dB ( A)
Leq (Night)
=41.9 dB(A)
Leq ( Min)
=40.1
Leq (Max)
=60.40 dB(A)
Construction
camp
demolished so
no
construction
camp data
The
measured
values are
well within
the limits
at sub
project site
Air Quality Winter
Season
SO2, NOX, CO , PM10
and PM2.5
NAAQS
Standards
-
Industrial,
Residential,
Rural and other
Areas
Monitored
ambient air
quality is
well within
the
stipulated
limits at
sub project
site
Particulate Matter < 10
micron
100
- 79.9 µg/m3 (at
construction
activity area of
project site )
Particulate Matter < 2.5
micron
Sulphur dioxide,(So2 )
Nitrogen dioxide(NO2)
60µg/m3
80 µg/m3
80 µg/m3
02 mg/m3
-
-
-
38.9 µg/m3 (at
construction
activity area of
project site)
14.4 µg/m3 (at
construction
activity area of
project site)
22.0 µg/m3(at
construction
activity area of
project site)
94
Componen
t
Periods of
monitorin
g
Parameters/Pollutant
s Standard
Base
line
status
Monitoring
result during
project
Implementatio
n
Remarks
Carbon Monoxide (CO)
for 08 hrs
-
0.30 mg/m3
(at construction
activity area of
project site)
Water
Quality
Winter
Season
As specified in IS:
10500 -2012 (
Drinking water
standards)
1- Ground Water at
Subproject site
2 Tehri Lake Water
near Subproject site
As
specified in
IS: 10500-
2012 for
drinking
water
CPCB
Standards
-
-
1- Colour-= <1
Hazen Unit
2- Odour=
Agreeable
3-pH= 7.58
4- Total
Hardness as
CaCO3= 280
mg/l
5- TDS= 314
mg/l
6- BOD= no
test done
7- Total
Coliform= Not
detected
8- Iron as Fe
<0.1 mg/l
9- Chloride as
Cl= 40 mg/l
11- Fluoride as
F < 0.20 mg/l
1-PH=7.3
2- Dissolved
Oxygen =6 mg/l
3- BOD (3 Days
at 27 oC)=
< 1mg/l
All
parameter
s in the
drinking
water
sample
are well
within
Drinking
Water
standards.
Disolved
Oxygen,
pH, BOD
and
coliform
bacteria
parameter
s meet the
CPCB
norm for
surface
water
category A
95
Componen
t
Periods of
monitorin
g
Parameters/Pollutant
s Standard
Base
line
status
Monitoring
result during
project
Implementatio
n
Remarks
4- COD =
<5mg/l
5-Electrical
Conductivity=
305 mg/l
6- Ammonia=
<10 mg/l
7-Coliform =
Absent
96
Table 9 (iii): Implementation of Environmental Monitoring Plan- For Projects under PIU Bhimtal
Component Periods of
monitoring
Parameters/Pollut
ants Standard
Base
line
statu
s
Monitoring result
during project
Implementation
Remarks
UK/IDIPT/BHT/03 Lot1 Trek Trail From Pithoragrah to Chandak(Operation stage monitoring)
Noise (21.03.17-22.03.17)
Sound Level Lmax, Lmin. dB(A)
Noise Standards for 55 dB( A) for Day Time and 45
dB( A) for Night Time (Residential Zone)
- In front of the pump house
Lmax -50.4(Day), 43.6 (Night) dB(A)
Lmin – 38.5(Day), 35.5(Night) dB(A)
Leq – 44.8(Day), 38.7(Night) dB(A)
CPBC limit for residential Zone db(A)-55.0 (Day), 45.0 (Night)
Values are well within permissible level
Noise Summer Season
(21.03.17-22.03.17)
Sound Level Lmax, Lmin. dB(A)
Noise Standards for 55 dB( A) for Day Time and 45 dB( A) for
Night Time (Residential Zone)
Back side of the pump house
Lmax -48.8(Day), 44.4 (Night) dB(A)
Lmin – 40.2(Day), 32.9(Night) dB(A)
Leq – 44.5(Day),
38.2(Night) dB(A)
CPBC limit for residential Zone db(A)-55.0 (Day), 45.0 (Night)
Air Quality
(In front of
the Pump
house)
Summer Season (21.03.17-22.03.17)
SO2, NOX, CO ,
PM10 and PM2.5
NAAQS
Standards
-
Industrial, Residential,
Rural and other Areas
Particulate Matter < 10 micron
100 µg/m3
66.30 µg/m3
97
Component Periods of
monitoring
Parameters/Pollut
ants Standard
Base
line
statu
s
Monitoring result
during project
Implementation
Remarks
Particulate Matter < 2.5 micron
60µg/m3 - 39.45 µg/m3
Sulphur dioxide,(SO2 )
80 µg/m3 12.33 µg/m3
Nitrogen dioxide(NO2)
80 µg/m3
20.77 µg/m3
Carbon Monoxide (CO)
02 mg/m3
for 08 hrs
0.50 mg/m3
Air
Quality-
(Back side
of the
Pump
house)
Summer Season
(21.03.17-22.03.17)
SO2, NOX, CO ,
PM10 and PM2.5
NAAQS
Standards
-
Industrial, Residential,
Rural and other Areas
All parameters of ambient air quality are well within the limits. Particulate Matter <
10 micron 100 µg/m3
69.30 µg/m3
Particulate Matter <
2.5 micron
60µg/m3 - 47.23 µg/m3
Sulphur dioxide,(SO2 )
80 µg/m3 14.23 µg/m3
Nitrogen dioxide(NO2)
80 µg/m3
23.21 µg/m3
Carbon Monoxide (CO)
02 mg/m3
for 08 hrs
0.40 mg/m3
UK/IDIPT/BHT/03 Lot2 Most Manu Temple, Pithoragarh(Operation stage monitoring)
Air Quality
(Main Gate)
Summer Season (19.03.17-20.03.17)
SO2, NOX, CO ,
PM10 and PM2.5
NAAQS
Standards
-
Industrial, Residential,
Rural and other Areas
Particulate Matter < 10 micron
100 µg/m3
58.20 µg/m3 At Near Construction Site
All parameters of ambient air quality are well within the limits
Particulate Matter < 2.5 micron
60µg/m3 - 30.45 µg/m3 At Near Construction Site
Sulphur dioxide,(SO2 )
09.0 µg/m3 At Near Construction Site
98
Component Periods of
monitoring
Parameters/Pollut
ants Standard
Base
line
statu
s
Monitoring result
during project
Implementation
Remarks
80 µg/m3
Nitrogen dioxide(NO2)
80 µg/m3 18.52 µg/m3 At Near Construction Site
Carbon Monoxide (CO)
02 mg/m3
for 08 hrs
0.31 mg/m3 At Near Construction Site
Air Quality
(Back side)
Summer
Season (19.03.17-20.03.17)
SO2, NOX, CO ,
PM10 and PM2.5
NAAQS
Standards
-
Industrial, Residential,
Rural and other Areas
Particulate Matter < 10 micron
100 µg/m3
60.50 µg/m3 At Near Construction Site
All parameters of ambient air quality are well within the limits
Particulate Matter < 2.5 micron
60µg/m3
- 32.42 µg/m3 At Near Construction Site
Sulphur dioxide,(SO2 )
80 µg/m3
9.88 µg/m3 At Near Construction Site
Nitrogen dioxide(NO2)
80 µg/m3
18.40 µg/m3 At Near Construction Site
Carbon Monoxide
(CO)
02 mg/m3
for 08 hrs
0.36 mg/m3 At Near
Construction Site
Noise
(Back Side)
Summer Season (19.03.17-20.03.17)
Sound Level Lmax, Lmin. dB(A)
Noise Standards for 65.00 dB( A) for
Day Time and 55.00 dB( A) for Night Time (Commercial Zone)
- Lmax -51.5(Day), 45.3 (Night) dB(A)
Lmin – 42.6(Day), 35.7 (Night) dB(A)
Leq – 46.4(Day), 40.4 (Night) dB(A)
CPCB limit for residential Zone db(A)-55.0 (Day), 45.0 (Night) dB(A)
Values are well within permissible level
Noise (In
main gate)
Summer Season (19.03.17-20.03.17)
Sound Level Lmax, Lmin. dB(A)
Noise Standards for 65.00 dB( A) for
- Lmax -54.8(Day), 45.5 (Night) dB(A)
Lmin – 43.0 (Day), 36.3(Night) dB(A)
Values are well within permissible level
99
Component Periods of
monitoring
Parameters/Pollut
ants Standard
Base
line
statu
s
Monitoring result
during project
Implementation
Remarks
Day Time and 55.00 dB( A) for Night Time (Commercial Zone)
Leq – 48.4(Day), 40.4 (Night) dB(A)
CPCB limit for residential Zone db(A)-55.0 (Day), 45.0 (Night) dB(A)
UK/IDIPT/BHT/01 TRH Parichay
Noise
(site
surroundin
g)
Summer Season
(17.03.17-
18.03.17)
Sound Level Lmax, Lmin. dB(A)
Noise Standards for 65.00 dB( A) for Day Time and 55.00 dB( A) for
Night Time (Commercial Zone)
- At Near Construction Site
Lmax -50.4(Day), 43.6
(Night) dB(A)
Lmin – 38.5(Day), 35.5(Night) dB(A)
Leq – 44.8(Day), 38.7 (Night) dB(A)
CPCB limit for residential Zone db(A)-55.0 (Day), 45.0 (Night) dB(A)
Values are well within permissible level
Noise
(Back side
of the
Pump
house)
Summer Season
(17.03.17-18.03.17)
Sound Level Lmax, Lmin. dB(A)
Noise Standards for
65.00 dB( A) for Day Time and 55.00 dB( A) for Night Time (Commercial Zone)
- At Near Construction Site
Lmax -48.8.4(Day), 44.4 (Night) dB(A)
Lmin – 40.2(Day), 32.9(Night) dB(A)
Leq – 44.5(Day), 38.2 (Night) dB(A)
CPCB limit for residential Zone db(A)-55.0 (Day), 45.0 (Night) dB(A)
Values are well within permissible level
Air Quality
(Near main
gate of the
Pump
house)
Summer Season
(17.03.17-18.03.17)
SO2, NOX, CO ,
PM10 and PM2.5
NAAQS
Standards
-
Industrial, Residential,
Rural and other Areas
100
Component Periods of
monitoring
Parameters/Pollut
ants Standard
Base
line
statu
s
Monitoring result
during project
Implementation
Remarks
Particulate Matter < 10 micron
100 µg/m3
66.40 µg/m3 At Near Construction Site
All parameters of ambient air quality are well within the limits
Particulate Matter < 2.5 micron
60µg/m3
- 44.70 µg/m3 At Near Construction Site
Sulphur dioxide,(SO2 )
80 µg/m3 8.48 µg/m3 At Near Construction Site
Nitrogen dioxide(NO2)
80 µg/m3 18.20 µg/m3 At Near Construction Site
Carbon Monoxide (CO)
02 mg/m3
for 08 hrs
0.53 mg/m3 At Near Construction Site
Water
Quality
Summer Season
Drinking Tap
Water Near
Construction Site
CPCB Standards for Surface water bodies and Drinking Water Standards for Potable water
1. pH-7.40
2. Colour <5
3. Turbidity –BDL
4. Odour –
Agreeable
5. Taste –
Agreeable
6. Total Hardness
-193.21
7. Calcium as
Ca- 54.45
8. Alkalinity -
121.20
9. Chloride-15.45
10. Magnesium
and Mg- 26.32
11. Total
Dissolved
Solids –
310.56
12. Iron -0.14
13. Copper<0.05
14. Total Coliform
<2/100ml
15. E-Coli –Absent
All parameters of drinking water are well within the limits of Drinking water specified in IS: 10500
Water
Quality
(17.03.17) Surface water
Naukuchiatal Lake
CPCB Standards
1. pH-7.58
2. Colour<5
101
Component Periods of
monitoring
Parameters/Pollut
ants Standard
Base
line
statu
s
Monitoring result
during project
Implementation
Remarks
for Surface water bodies and Drinking Water Standards for Potable water
3. Turbidity –
BDL(DL-I
NTU)
4. Total
Hardness -
250.20
5. Calcium as Ca
-76.23
6. Total Alkalinity
-270.45
7. Chloride-36.45
8. Magnesium
Hardness -
14.53
9. Sulfate as
SO4- 54.26
10. Nitrate as
NO3-1.82
11. Flouride as F -
0.82
12. Sodium as Na
– 20.45
13. Potassium as
K- 58.26
14. TKN as N-
4.34
15. Total
Phosphorous -
0.78
16. COD-64.10
17. Phenolic
Compound -
<0.002
18. Iron as Fe-
0.48
19. Boron -0.29
20. Sodium
Absorption
ratio -1.90
21. Free Ammonia
as N-0.53
22. Dissolved
Oxygen -8.10
102
Component Periods of
monitoring
Parameters/Pollut
ants Standard
Base
line
statu
s
Monitoring result
during project
Implementation
Remarks
23. BOD(3 days at
27) -17.00
24. Zinc as Zn-
0.42
25. Arsanic as As
-<0.012
26. Mercury as Hg
-<0.002
27. Total
dissolved
Solids -454.00
Water
Quality -
Tap
27.03.17 Drinking Water
Tap
CPCB Standards for Surface
water bodies and Drinking Water Standards for Potable water
1. pH-7.40
2. Colour<5
3. Turbidity –BDL
4. Odour-
Agreeable
5. Taste-
Agreeable
6. Total
Hardness -
193.21
7. Calcium as Ca
-54.45
8. Total Alkalinity
-121.00
9. Chloride-15.45
10. Magnesium -
26.32
11. Total
Dissolved
solid-310.56
12. Iron as Fe-
0.14
13. Copper as Cu
-<0.05
14. Total Coliform
-<2/1000ml
15. E.coli-Absent
103
Average variation in Physico- chemical parameters of Lake Naukuchiyatal
PHYSICO-CHEMICAL PARAMETERS OF WATER OF LAKE NAUKUCHIYATAL
Parameters April , 2017 May , 2017 June , 2017
Ist
fortnight
IInd
fortnight
Ist
fortnight
IInd
fortnight
Ist
fortnight
IInd
fortnight
Atm. Tem. (°C) 20.5 22.5 23.25 21.95 25.00 25.60
Water temp. (°C)
Surface 20.14 20.58 21.70 22.51 24.39 25.41
8 m depth 18.38 19.35 21.01 22.34 24.08 24.93
16 m depth 18.33 19.20 20.81 22.21 24.01 24.75
24 m depth 18.30 19.10 20.73 21.98 23.97 24.64
32 m depth 18.30 19.00 20.60 21.74 23.87 24.51
Transparency (cm) 177.5 180 159.60 133.60 141.53 132.60
TDS (mg/l) 80.6 81 87.00 85.90 82.73 82.80
Conductivity (µS/cm) 238 242 239.6 249.2 261.4 260.9
DO (mg/l)
Surface 11.04 10.83 10.71 10.62 10.02 9.43
8 m depth 10.88 10.76 10.56 10.08 9.58 8.83
16 m depth 10.61 10.36 9.92 9.78 9.17 8.52
24 m depth 10.10 9.90 9.55 9.01 8.40 7.80
32 m depth 2.98 3.03 3.51 2.86 2.53 2.39
Turbidity (NTU) 13.75 12.00 15.25 15.25 13.00 15.17
pH 8.57 7.50 7.84 8.49 7.95 8.17
Free CO2 (mg/l) 1.55 1.70 1.99 2.15 2.45 2.63
Total Alkalinity (mg/l) 136.0 135.0 129.7 136.0 137.3 136.1
Total hardness (mg/l) 152 156.00 155.50 165.00 - -
Iron (mg/l) 0.32 0.32 0.33 0.42 0.40 0.36
Chloride (mg/l) - - - - - -
Silica (mg/l) 5.00 5.00 5.00 5.00 5.00 5.00
Nitrate (mg/l) 1.78 1.78 1.78 1.79 1.77 1.73
Phosphate (mg/l) 0.002 0.00 0.00 0.01 0.01 0.00
Heavy Metal Analysis: Lake Naukuchiyatal
Metals Concentrations(µg/l)
S.NO Site 2 Site 4
1. Lead ( Pb) 0.077 0.081
2. Cadmium ( Cd) 0.000 0.000
3. Zinc ( Zn) 0.020 0.000
4. Copper ( Cu) 0.000 0.0001
104
Soil Analysis
S.No. Parameters Values
1. Sand (%) 8
2. Silt (%) 20
3. Clay (%) 72
4. pH 7.9
5. Nitrogen (mg/100g soil) 10
6. Phosphorous(mg/100g soil) 5
7. Organic carbon (%) 1.95
Note:- � ** Value based on result of the report (Mar to June 2017) submitted by Pantnagar University.
9. Institutional Arrangements
Program Management
11. The Government of Uttarakhand through Department of Tourism (DOT) is the Executing Agency (EA). The
EA (i) assumes overall responsibility for the execution of the Project and reporting; (ii) engage adequate
permanent or fixed-term staff to implement the Project; (iii) setup a state-level project management unit (PMU)
and project implementation units (PIU); (iv) provide overall strategic guidance on technical supervision and
project execution; and (v) ensure overall compliance with the loan covenants.
12. The implementing agency (IA) is the Uttarakhand Tourism Development Board (UTDB). The IA’s
responsibilities include (i) project planning and budgeting; (ii) day-to-day assistance, supervision and guidance
for the project implementation units and their consultants; (iii) review subprojects for due diligence requirements
and approve subproject proposals; (iv) bidding, evaluation and contract award; (v) managing and disbursing
funds; (vi) review compliance with loan covenants, contract specifications, work plans and quality control; and
(vii) consolidate and submit progress reports, finance and accounting / audit reports, and matters requiring higher
level decision to state-level empowered committee (SLEC) and ADB.
13. A State-level empowered committee (SLEC) has been established in Uttarakhand, chaired by state’s Chief
Secretary, with Principal Secretary/Secretary of the Department of Tourism as member secretary and comprised
of secretaries from relevant line departments. The SLEC have been empowered to take all decisions on behalf of
the State and will (i) act as a policy making body, (ii) provide overall advice and guidance to the State’s executing
agency and PMU, and (iii) accord all approvals under the Project.
14. Dept. of Tourism (DoT) has established a PMU, headed by a full-time program director (PD), and consisting
of personnel drawn from relevant line departments and market. Project Management Unit (PMU) is established in
Dehradun for the overall project management. The PMU is the nodal agency for overall management of all
program activities and will be responsible for: (i) project planning and budgeting; (ii) providing day-to-day
assistance, supervision and guidance for the PIUs and their consultants; (iii) reviewing subprojects to satisfy
ADB’s due diligence requirements and approving subproject proposals submitted by PIU and line departments;
(iv) bidding, evaluation and contract award; (v) managing and disbursing funds; (vi) reviewing compliance with
loan covenants, contract specifications, work plans and quality control; (vii) consolidating and submitting
progress reports, finance and accounting/audit reports, and matters requiring higher-level decision, to the SLEC
and ADB. The PMU will be supported by a team of consultants.
105
15. The sub-project is being implemented by the Project Implementation Unit (PIU) of IA, i.e. UTDB, comprising
of personnel drawn from relevant line departments and outside of government and headed by a Project manager.
03 Project Implementation Units (PIU) have been established for each of the three circuits namely Bhimtal,
Dehradun and Kotdwar. The PIUs are responsible for: (i) prioritizing and preparing subproject proposals; (ii)
providing day-to-day assistance, supervision and guidance to the design and supervision consultants; (iii)
conducting detailed assessments and surveys including public consultation and input from stakeholders; (iv)
preparing detailed designs, specifications, schedule of quantity, bidding documents, and related documentation;
(v) implementing civil works and related activities; (vi) reporting to PMU; (vii) preparing regular progress reports
for the SLEC, the executing agency and ADB through PMU; and (viii) supervising construction, conducting
quality control, approving progress payments to contractors; and (ix) maintaining records and accounts on an up-
to-date basis and making these available to ADB, its missions, or auditors for inspection.
16. The Project Management Consultant (PMC) has been engaged to provide support to the PMU in overall
planning, risk management, implementation, monitoring and evaluation of projects under the Investment
Program. The PMC also assists the PMU and PIUs in meeting the relevant requirements of ADB, Government of
Uttarakhand, and Government of India for project implementation. The PMC reports and works under the overall
guidance of the PMU. The scope of services of the PMC includes but not necessarily be limited to: (i) planning,
reporting, and communication; (ii) establishment of procedures and systems; (iii) review and preparation of plans,
manuals and reports; (iv) overall Investment Program management, monitoring and implementation of PPMS;
and (v) social, environmental, archaeological, occupational health and safety, community participation and
gender action compliance monitoring.
17. The Design and Supervision Consultants (DSC) have been engaged to provide all necessary support to and
coordination with the EA, IAs, PMU and any other consultants engaged by the authorities to achieve the desired
outcomes of the Investment Program. The DSC reports to and work under the overall guidance of the PIUs. The
scope of services of the DSC includes but not necessarily be limited to: (i) surveys, verification of feasibility
studies and base maps; (ii) project planning and management support to the PIU; (iii) finalization of design
criteria, preparation of manuals, guidelines and systems; (iv) preparation of detailed design and bid documents;
(v) construction management and contract administration; (vi) environmental, social, archaeological, cultural
heritage, community participation and gender action compliance monitoring; and (vii) capacity building of the
service providers for operational sustainability.
9.1 Institutional Arrangements For EMP Implementation
18. The institutional arrangements specify the arrangements for the implementation of environmental provisions
of the entire project.
Project Management Unit (PMU)
19. A Safeguards Specialist (SGS) is positioned in the PMU, who is responsible for overall implementation of the
environmental safeguard provisions. To look into the matters of forest coordination, a Forest Conservation
Specialist is also placed in the PMU.
Project Management Consultant (PMC) and Design and Supervision Consultants (DSC)
20. Project Management Consultants (PMC) and Design and Supervision Consultants (DSC) have been
recruited to provide assistance to the PMU and PIUs respectively in project implementation. Within the PMC
team an Environment Safeguards Specialist is positioned to provide overall direction for management of
environmental issues, and technical support to the PMU including implementation of the environmental
requirements according to ADB requirements, and assist in monitoring impacts and mitigation measures
106
associated with sub-projects. Towards addressing the environmental issues in the project components during
design and implementation, the DSC includes provisions for inputs of Safeguards Specialist Environment.
21. The Safeguards Specialist of the DSC team is responsible for preparation of the Environmental Assessment
documents in line with the Environment Assessment Review Framework (EARF) and supervises the
implementation of the EMP provisions in the various sub-projects.
22. DSC Safeguard Specialist is placed in each of the three DSCs to support environmental management
functions including updating sub-project IEEs in respect to environmental management plans in compliance with
the ADB Safeguard Policy Statement, national and state level environmental policies, rules and regulations,
assisting in preparing IEEs, and assist in monitoring impacts and mitigation measures associated with sub-
projects. He is required to include mitigation measures in designs where appropriate, and to specify other
measures in construction contracts. In addition to addressing the issues related to environmental management in
the project, the DSC Specialist plays a central role in ensuring capability building on Environmental Management
of the PMU/PIU, Contractor and Line Departments.
23. Contractors are required by their contracts to implement all specified mitigation, monitoring, and reporting
assigned to contractors as presented in sub-project IEE. Contractors have appointed Environment and Safety
Officers for implementation of environment and occupational safety provisions at site.
24. Environmental monitoring is being undertaken by the PMU supported by the Safeguards Specialist of DSCs
and PMC
25. Contact Details of Safeguards Team is given below:
Unit Name Mobilized
Since
Phone E-mail
PMU
Ms. Anjali
Semwal
April, 2013 8191995004 [email protected]
PMC Mr. Navin
Handa
Mr. Ardhendu
Mitra
July 2016 –
Till date
July 2013 –
Sep, 2015
+91-
9599510994
PMC requested for replacement of
Expert
DSC
Dehradun
Mr. Ranjan
Mallick
Mr. Abhay
Srivastava
January,
2014 – Till
date
April, 2013 –
June, 2013
+91-
94382000113
DSC
Kotdwar
Mr.
Shreeniwas
October,
2013
+91
9811224458
107
Verma
DSC
Bhimtal
Dr. A.K.
Sharma
Dr. Aman
Sharma
July -
2015 to Till
Date
March -
2013 to May
2015
09799242184
09811487830
10. Consultation Details
26. Public consultations and environment awareness has been carried out in all sub project sites. The same has
been detailed in table 10. Pictures of Consultation and Attendance records have been provided in Annexure 4
&5.
Table 10(i): Stakeholder Consultation Details For Projects under PIU Dehradun Sl. No.
Sub Project Name and Location
Date Members Present
Issues Discussed Outcome
1 Development of Tourism
infrastructure facilities at Asan
Barrage Dehradun- Lot 1
UK/IDIPT/DDN/01
23.05.2017 20 - Proper Management of Sanitation facilities at site. Resort Manager was instructed to increase the number of dustbins at site - Discussion held with Resort Manager, about the newly created facilities in the resort. He pointed certain problems like seepage, etc. Tourists present there were asked about the facilities and their experience.
ADB visited to the site on 23rd May 2017 and the O&M was praised by the team. The Tourists were satisfied from the project. The shortcomings pointed out by the Resort Manager was brought to the attention of PIU and sorted out. The DSC support engineer explained the importance of maintaining the provided facilities in the resort.
2 Development of Yamuna Circuit (Tiger Falls & Lakhamandal Temple)- Lot 1
UK/IDIPT/DDN/03
09.04.2017
12 Meeting with Tiger Fall Committee
DSC staff explain about proper management project sites and its environment The Committee shared its experience of running the project and needed some suggestions. .
3. Development of Yamuna Circuit (Tiger Falls & Lakhamandal Temple)- Lot 1
10.04.2017 10 Meeting with Temple Committee members
DSC staff explain about proper management project sites and its environment The Committee shared its experience of running the
108
UK/IDIPT/DDN/03 project and needed some suggestions
4. Development of Yamuna Circuit
(HanolMahasu) - Lot 3
UK/IDIPT/DDN/05
11.04.2017 14 - Environmental Awareness and safety meeting conducted for labourers, supervisors and DSC,site engineers
The DSC Site Engineer explained about Environmental safety, management and protection to labourer and contractor supervisor and field engineer.
5. Development of Yamuna Circuit
(HanolMahasu) - Lot 3
UK/IDIPT/DDN/05
24.03.2017 11 Meeting with Temple Committee members
DSC staff explain about proper management project sites and its environment The Committee shared its experience of running the project and needed some suggestions
6. Development of Yamuna Circuit
(HanolMahasu) - Lot 3
UK/IDIPT/DDN/05
25.03.2017 18 Meeting with Temple Committee members
Elaborate discussion was held on proper management of project sites and its environment .
7 UK/IDIPT/DDN/06
-Lot2 P1
Development of
Adventure Tourist
Centre-Kapkot
15.04.2017 12 Environmental Awareness and safety meeting conducted for labourers, supervisors and DSC,site engineers
The DSC site Engineer
explained about
Environmental safety,
management and protection
to labourer and contractor
supervisor and field
engineer
8 UK/IDIPT/DDN/06
-Lot2 P1
Development of
Adventure Tourist
Centre-Kapkot
30.05.2017 10 Environmental Awareness and safety meeting conducted for labourers, supervisors and DSC,site engineers
The DSC site Engineer
explained about
Environmental safety,
management and protection
to labourer and contractor
supervisor and field
engineer
9 UK/IDIPT/DDN/06
-Lot2 P2
Development of
Adventure Tourist
Centre-Tanakpur
25.03.2017 13 Environmental Awareness and safety meeting conducted for labourers,
The DSC site Engineer explained about Environmental safety, management and protection to labourer and contractor supervisor and field engineer
11 UK/IDIPT/DDN/06-Lot2 P3
Development of Adventure Tourist
Centre-Pauri
03.05.2017 20 Environmental Awareness and safety meeting conducted for labourers,
The DSC site Engineer explained about Environmental safety, management and protection to labourer and contractor supervisor and field engineer
109
Table 10(ii): Stakeholder Consultation Details For Projects under PIU Kotdwar
Sl.
No.
Activity
/Event at a
glance
Date Total
Participant Male Female Discussion/Suggestions
1 UTDB Office, Dehardun
20.02.2017 and 21-02-2017
35 30 5 Workshop on Environment and Social Safeguards Regarding Implementation of Social and Environment Mitigation and Monitoring and Reporting System. In this workshop EMP implementation and lessons learnt were discussed. On social issues Gender Action plan and Resettlement Plan implementation were discussed. The queries of contractors and PIU staff on environmental and social safeguards were addressed.
2 UTDB Office, Dehradun
28.04.2017 10 10 - Meeting with APD-PMU, TL-DSC Regarding Progress and impacts of Signage Sub-Project. Environmental impacts, if any, were also discussed.
3 Development of North Entry in Corbett Sub-project
19/05/2017
19 19 0 Workers safety during construction like PPEs and safe handling of construction materials, were discussed. The workers were sensitized on advantage of PPE usage. The cleanliness, sanitation, drinking water facilities etc., at the construction camp were satisfactory. The workers are also happy with these facilities including other facilities like use of cooking gas, bathing facilities, etc. During consultation it was also discussed regarding the wages for categories of labour, it was learned that the labourers are getting wages as per Government Prescribed rates. The contractor was advised to conduct monitoring for summer season and to carry out enumeration of trees at site. The contractor was advised to make preparation for plantation of shrubs and trees at site as monsoon season will start late June.
4 UTDB Office, Dehardun
25.05.2017 12 10 2 Consultation with ADB Mission and APD-PMU, DSC, PIU Regarding Progress Review including environmental and social safeguard of Tranche-2, Tranche-3 projects.
110
Sl.
No.
Activity
/Event at a
glance
Date Total
Participant Male Female Discussion/Suggestions
5 UTDB Office, Dehardun
22.06.2017 7 6 1 Consultation meeting was held to sort out the issue regarding installation of new 3 phase power supply connection at North Entry in Corbett, Kotdwar Project – Participant in meeting GM-GMVN, Dpt.GM-GMVN, Nodal Officer- PMU, PM-PIU, TL-DSC, and Electrical Engineer- DSC.
111
Table 10(iii) Stakeholder Consultation Details For Projects under PIU Bhimtal
S. No.
Name of Sub Project
Location Date of Consultation
Issues Discussed
Member Present Outcome
1. 1. Amelioration of Lake Naukuchiyatal
2. Upgradation of
Tourist Facilities at TRH Parichay
Boat house Naukuchiyatal At TRH Parichay
22/02/2017 Discussion with the labourers and representative of the contractor regarding safety measures. Discussion with the local masses and representative of Nav Chalak Kalyan Samiti
Dr. A. K. Sharma Dr. K. K. Gaur Contractor Representative Local Masses and Chairman of Nav Chalak Kalyan Samiti
Nav Chalak Kalyan Samiti was concerned about cleanliness of the lake
2. 1. Amelioration of Lake Naukuchiyatal
2. Upgradation of Tourist Facilities at TRH Parichay
Boat house Naukuchiyatal At TRH Parichay
22/05/2017 Discussion with local persons and representatives of Nav Chalak Kalyan Samiti.
Dr. A. K. Sharma Dr. K. K. Gaur representatives of Nav Chalak Kalyan Samiti and locak mass
Water quality parameters were discussed with Nav Chalak Kalyan Samiti
3. 1. Amelioration of Lake Naukuchiyatal
2. Upgradation of Tourist Facilities at TRH Parichay
Bhimtal 19/06/2017 Discussion with PIU and local masses to known their present status about these two sub projects.
Dr. A. K. Sharma Dr. K. K. Gaur Contractor Representative Local Masses Representatives of “Nav Chalak Kalyan Samiti”
Public was sensitized about aeration project and visible benefits on lake
4. 1. Work of View Point at Mostamanu Temple
2. Trek Trail from Pithoragarh to Chandak
3. Conservation of Pithoragarh Fort Phase-I
Pithoragarh 21/06/2017 Discussion with the local masses & representative of regarding present status of work under the sub projects & labourers problems.
Dr. A. K. Sharma Dr. K. K. Gaur Contractor Representative Labourers
Temple Committee members were sensitized about proper maintenance of facilities like toilets in the temple complex. The general public was sensitized about maintenance of the trek
112
11. Any other environmental aspects, impacts observed during implementation which were not
covered earlier
27. No such impact observed during the reporting period.
28. Reluctance on the part of contractors was repeatedly observed for conducting environmental monitoring and
compliance of environmental safeguards. A decision was taken by PMU to get monitoring conducted by DSC’s
after giving adequate notices and information to the contractor while deducting the same from contractor’s
invoice to prevent further non-compliance of the Environment Monitoring Plan. Along with on -site training
programs by DSC Experts, PMU plans to organize regular orientation session on safeguards for the contractors
and Technical team of the PIU, DSC, PMC and PMU. A Two days training workshop on Gender mainstreaming,
Environment-Social Safeguards was organized by the PMU for contractors. (Report Annex ) Along with on -site
training programs by DSC Experts, PMU plans to organize regular orientation session on safeguards for the
contractors and Technical team of the PIU, DSC, PMC and PMU.
12. Details of Complaints received from public and action taken thereof to resolve
29. One complaint was raised by the local community regarding emergence of aquatic weeds during the
reporting period. The Community was briefed that it was due to the process of aeration that the algae has come
up on the surface of the lake and started floating near the bank towards west and east sides of the lake due to
the wind flow. Public was assured that this is temporary phase. The contractor cleaned the lake manually. The
parameters were also monitored by G. B. Pant University, Pant Nagar. Presently the algae and other aquatic
plants are being removed manually by the contractor and Nav Chalak Kalyan Samiti.
30. The local masses / villagers of village Chanauti and boat owners were found satisfied with the installation of
aeration system under the sub project “Amelioration of Lake Naukuchiyatal” including the cleaning process which
was initiated after their complaint earlier regarding the cleaning and odorless water. More over they were found
satisfied with the quality of visibility of the water present in the lake. It is observed that the present dissolve
oxygen level is increasing and reported as 8.31 to 8.5 milligram/ltr on surface and 0.34 to 7.30 mg/l at bottom.
Further, it is to mention that aeration systems are working properly.
31. No other unforeseen and abnormal adverse environmental impact observed during the reporting period
13. Follow up actions and Conclusions
32. Site supervision will be regularly carried out to ensure that environmental impacts are being adequately
mitigated and to ensure continuation of compliance with statutory regulations as required by laws and agreed
upon EMP. The contractors are being regularly guided and instructed to pay attention to environmental issues
and adhere to the provisions of EMP. Training Programs for engineers, contractors, and project staffs are being
conducted and regular informal onsite orientation for the contractor’s supervisory staff and site engineers and
EMP will be continued.
113
Annexure: 1: Photo Illustration Projects Under PIU Dehradun
1. Hanol Site
Complete Site Asan Barrage Finishing Work of Gate: Hamol
TRH under Renovation Pathway Developed in Hanol
Renovation of Front Elevation of Existing Adventure Tourist centre at Tanakpur
114
DTDO’s office at Pauri
Tanakpur Interpretation Center & Floor
work
Toilet under construction
RCC retaining wall under construction, at Kapkot
View of Renovated Guest house, Deovan
115
Annexure: 2: Photo Illustration Projects Under PIU Kotdwar
1. Development of Tourism Infrastructure for North Corbett Entry Point at Kotdwara.
View of Site under preparation for
landscaping
Landscaping and Passageworks under
development at Site
2. Development of Development of Adventure Tourist Centre at Tehri
View of Finished Building
View of Solar Panels on Roof Top of
Building for Water Heating (Energy
Conservation in Project
3. Signage Works in Uttarakhand
116
View of Signage Type 1 View of Signage type 2
View of Signage Type 3 View of Special Signage installed at Tiger
Fall
117
Annexure: 3: Photo Illustration Projects Under PIU Bhimtal
1. Upgradation of Tourist facility at TRH Parichay, Naukuchiyatal
Landscaping Works near Main Building A view of Café Deck
2. Amelioration of Lake Naukuchiyatal
Discussion with local masses about the quality of
work at Naukuchiatal
Discussions with the President Nav Chalak Kalyan
Samiti at Naukuchiatal
Discussion with the community members Stocking of Fishes in Lake Naukuchiyatal
118
3.Trek Trail at Pithoragarh
A View of Trek trail at Pithoragarh View Point At Trek Trail at Pithoragarh
4.Mostamanu Temple, Pithoragarh
Discussion with Mostamanu Temple Committee
Member
Seat wall cluster at Mostamanu Temple
Local Pataal Paving Path at Mostamanu Temple
Tree Guard at Mostamanu Temple
5. “Conservation of Pithoragarh Fort Phase I, Pithoragarh
119
RR Masonry Work of Craft Center at Pithoragarh A View of PCC of Walkway at Pithoragarh Fort
6. Adventure Tourist Center at Baur Jalashay - Lot 2
Seat wall pavilion Parking ramp near boat house
Landscaping Activity Parking Area ready for tiles
Pictures of Consultation Activity During Reporting Period
- ... .... ' ·' - ....
- -
120
Annexure: 4: Photo Illustration of Awareness Generation and Labour Welfare Activities
Meeting with Manager & GMVN Staff, Asan Barrage Meeting with Hanol Temple Committee
Meeting with Panchayat members At
Lakhamandal
Consultation With Labour: North Entry site Consultation With Labour: Tehri site
121
Labour sensitization on Social and Environmental
Safeguards at Pithoragarh Fort
Discussion with the Secretary, Mostamanu
Temple Committee
Meeting with Local NGOs at Pithoragarh Fort Site Meeting & Field visit by Secretary Tourism at
Almora site
Photographs of Medical Camp Organised at Kotdwar project site
\ mwnildland
11n11mt .... • Program for Tourism-ID I PT /U.K} /,OB 1.oan No.: 2833 IND
"Development of North Entry in Corbett Slb,llroject at Kotdwara"
Medical Health Ca ~ ~ mp " i.,l!tOagmo RIIH, \
122
Public Awareness Program in Lake Naukuchiyatal Subproject Area
123
Annexure: 5: Attendance Record of Consultation Activities
Attendance Sheet
SN
, 2
3
4
r 5
6
7
8
9 ,___ ,o ,, 12
f3
,. 16 r 18
17 ,. 19
29
21
22
23
•• 25
26
SN
27
28
29 ,n
A.
Developmont of North Entry in Corbett at Kotdwar Project (UK/IDIPT- II/KOT/01)
A08 Loan No.: 2833
PUBLIC CONSULTATION
Signature or Partklpants
Dato: I'\ \o s-1 l";f- .
Name Oc:c:upatk»n contact No,
. ,, . ') .s,:c_ L , . SlgnalUN
6 L---,
'>. r.. . - l),$ ~ ~11v·t10 I""-
\Ju .. -, ~~..A - o~co OS<=- lr•tl•• "7.,.L..
' ' l . -I sf .J,,,1 -
1--
\ , . ...,~. 't,_.- - ... - P.,\.
I, 1_,,~e,;f,t.l S,"7'1 C.,.,.,J, I ,.;,i,:, t'~
D. •- £ - • I • , - ~( r,;.,,._ .:iP, C. ' • .t I .I
- t V:::{ r .. ,, (I. ' ~ / '
I ' "I U, /'""""
~LM- ' ,, . . . . , . • J - ~<:::' i? I,, , •. J - J ' ' ' . ~v" \.
' . .. ' ' , / (, r .Lt 141'-Qf-t, 'Yf :'"' _, ~ ,.,._.., I
" = • ...,
,., . . ' - -• 'J I I
' 777': H< . ..,L
I) - .u//:1. • ,, )?;{ hi l:f,fi, J_ I. ' ~ -
.,,_' ' ' .. -~o I P.0 ,_
-r .. ' -· - - ' -r .. ,. ' ' --,~
., , , . .. .. -t.,, :. .
' - . -\ , .. . , =' ,, t' +<C'il '( di
l A .. ' ,,, '
J<D G,,) .,-f:f' .. .
Name Oc:cupation Contact No. Signature
('.,.- '·- I ... J .. --,u-. " c5; - , . ' I•· ' 7//~ {?ftifF< - -,,. ... ,t .. . 1 ,·n
I
Meeting held on 12.04.2017 regarding hand over of toilet block
to the temple committee for trial. If any problem exists, it may
be resolved. Com
Meeting With Temple Committee Members
Meeting held on 12.04.2017 regarding hand over of toilet block
to the temple committee for trial. If any problem exists, it may
be resolved. Committee members suggested tank for toilet
Meeting With Temple Committee Members
Hanol
124
Meeting held on 12.04.2017 regarding hand over of toilet block
to the temple committee for trial. If any problem exists, it may
mittee members suggested tank for toilet
c- .I\J l
"""-""•/ '\ \ G"\~T,;..:;- .
~·--··-·;':>
.J\-'::Y>,,.-. r;;f,J '-------~~-----~-----------------_ · "-·v-vf" s.~,,_,(>
125
Attendance Records of Expert Committee Meeting in Naukuchiyatal sub Project
126
Cleanliness drive was carried out around subproject site of lake Naukuchiyatal by Nav Chalak
Kalyan Samiti in association with other tourism market stakeholders.
~~f ~~ldlH qiTmtf ~(fil~ q4e.1 ~ ,a;flcti it~~ :a&tllil
~ - 11<1 -;;i@lfi ~
mim, 4'l'{f'1111df(1 ff'lflW!Wlil1* tf - .mlm ~l~tim ~ a ~ m :cl~41M'I, . Tfta 1+i\f't4idiH 'Iii~ ~I
'ITll ~ ~ ~ ,t/4i,rl 'II ~ 1li1
~-1R\~~ 11,1 °" m t ~ ~ fqifi'q t lflll!'ll ~ ~ 'g ~ fl'II ~ tfRil!i ~ '1fllfa ~1$ ~ il"ftiftt'!lq;rf ;mmilifflllrt'I ~ ~ 1!ilTl11 ~ "lfQ ~ ¥il-Ol.4llt&i i aiili ;ii ii '1:1@ ~ I;;~' ;;;:;:ii~. m 'Fril .fttf.i111n1(1 11>'1 ~ 1 ~ m 1n ~ ~ ~ . zy!l!, ~ . ~ ~ ~ Wd ffl t~ •. 'Fl ~ m,mi Wlll, ~ ~ ffl w, ~ W111-rn "!"I 1N>ii aifim ~fm'Yirnm,~'lflrl.mm ~If[. 11\Wlmf.tmn ~ I ~ ~ ~ ~ ~ . ~ qn: IJ'li1 ~ ~ ii ~ <fl "1111A f<f.iil 7f!R t ffl1( ~ i "111ft m m ~ tm ~. M;i it;111p~ ~ ~ ~,
127
Annexure: 6: Correspondence with District Administration regarding change of Proposed Location
Baturi –Pancheswar in Champawat to Tanakpur Champawat
Letter from DM, Champawat requesting that the proposed site for Adventure
Center in Champawat “Baturi” is not economically feasible, since the quantity of
water in Saryu river is not available year round. DM requested for change of site
to Tanakpur, which is more suitable for adventure related activities, as there is
sufficient amount of water in river Mahakali for sustaining the project
commercially and there is year round tourist flow in Tanakpur due to Purnagiri
temple, which is visited by lacs of pilgrims/tourists from all over the country.
' ',·
128
Letter from APD, IDIPT, UTDB to District Adventure Sports Officer for
identification of land (approx. 50 sqmt) around Tanakpur, instead of Baturi, as
suggested by District Administration.
-crITTITTiAT ~ ~ q~c~ ~xcFiT R)-q1m ~ ~
(rroiefto#o ~ - f!R -ro 2033, ffelfT}
'3rnxl'(\'1°"5m ovl. of Utta.rakhand l:fO ~ B1Tit<ITTT ~ ~. f'rm 3TTO~O~OWO ~
Uttarakha nd Uimpig ':Hcm,v~r:!
1TiT k, ~- 248003 .
l!iFf: 91-135-2559985, m: s1-135-2s59985
Tftrq):.2..1.9.7f-10 /izo~o~o / (~o~o~o1fioiro) / 179 / 2015-16
xfcIT -if, ~ ~ ~ ~/ ~ ~ ffi,f ~ ~, ~,
,fchm:- uR1lG .)-~/~ ~ cf>'T ~ 1fcFf ffi cfi ~ ~,
~:- 2660 / 2-10-ADB/IDIPT /179/2015-16, Dated 24/6/2015
~.
1804 /2-10-ADB/IDIPT/179/2014-15, Dated 21/11/2014
2776/2-10-ADB/IDIPT/179/2014-15, Dated 27/07/2015
2898 /2-10-ADB/IDIPT/179/2015-16, Dated 22/08/2015
460~ ~ ~-'r.fl'qlc@/2015-16 ~ 2 ~ 2015 ,
~-JIB: [email protected]
ITTfcp: ) ~-5ep.2015
~ ~ ~ * w -if~~ ·*~~~~~ 11 m 3lcl<Rf cfiWIT ~ ¥f % I ~o~o{owo cfi ~ ~ ~. ~ ~ cra-w cf 3Rf ~ cITT<if cfi ~ ~ ~ wfm ~ cnr 1T0<1 wm IJJ!WTT izcf ~ ~ ~ ~;~ ~ ~ ~ ~ ff cfi ~ # ~ ~ cfi ~-wTI
Bero cfi q5,, i:/ ~ ~ cfi 1T5f ~ 08 ~ 2015 ~) &lxT ~ cfi ~ l:lx
~ ~ ~ ~ 3RBr ~ cfi 3ITT,(fIB cfi ITT -if ffi cnr -~ ~ t I .
3Kr:3l1W~!TTP~~cfi~~~cf>'T~~~~cnr (wr:rr 50 qif ~) 'r.fo/f qJX ·3ffi Jllq~i.Jqjcilj-<-llx infc;=r fcrwr cfi -;,fl, ~ 'qJX ~ cfi ~ ~ ~ ~ ~ cnr ~ er ~ qJX ~ cor· ~ ~ ~ cITT ~ ~ cfRFlT ~~,
~: '-'l4xlcfc'lljfil~
~:-
.Q d