Environmental Monitoring Report Bi Annual Environmental Monitoring Report January June 2015 AZE: Water Supply and Sanitation Investment Program Tranche 1 and 2 Prepared by AZERSU, Government of Azerbaijan for the Asian Development Bank. This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

Upload: buikhue

Post on 07-Sep-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

Environmental Monitoring Report Bi Annual Environmental Monitoring Report January – June 2015

AZE: Water Supply and Sanitation Investment

Program – Tranche 1 and 2

Prepared by AZERSU, Government of Azerbaijan for the Asian Development Bank.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

Bi-Annual EMR No-5 January 01 - June 30-2015

Bi Annual Environmental Monitoring Report

Period: January01 – June30, 2015

REPUBLIC OF AZERBAIJAN

WATER SUPPLY AND SANITATION INVESTMENT PROGRAM

Tranche 1 Project

Project No. L-42408-ICB-2.01

- COMPLETION OF CONSTRUCTION OF WATER INTAKE FACILITIES AND

REHABILITATION OF PART OF WATER SUPPLY AND SEWERAGE NETWORKS IN

GOYCHAY TOWN – PACKAGE 1

Tranche 2 Projects

Project No. MFF032-T2-ICB-1.01

- COMPLETION OF CONSTRUCTION OF WATER INTAKE FACILITIES AND

REHABILITATION OF WATER SUPPLY AND SEWERAGE NETWORKS IN AGDASH

TOWN

Project No. MFF032-T2-ICB-1.02

- CONSTRUCTION OF WATER INTAKE FACILITIES AND REHABILITATION OF

WATER SUPPLY AND SEWERAGE NETWORKS IN BEYLAGAN TOWN

Project No. MFF032-T2-ICB-1.03

- COMPLETION OF CONSTRUCTION OF WATER INTAKE FACILITIES AND

REHABILITATION OF WATER SUPPLY AND SEWERAGE NETWORKS IN

GOYCHAY TOWN – PACKAGE 2

Prepared by AZERSU, Government of Republic of Azerbaijan for the Asian Development Bank

ABBREVIATIONS

ADB - Asian Development Bank

CSC - Construction Supervision Consultant

EA - Environmental Assessment

EA&OC - Environmental Assessment and Organization Chart

HSE - Health, Safety and Environment

EIA - Environmental Impact Assessment

EMP - Environmental Management Plan

EMS - Environmental and Monitoring Sector

EP - Environmental Protection

HIV/AIDS - Human Immune deficiency virus and Acquired immune Deficiency

syndrome

IBA - Important Bird Areas

IDB - Islamic Development Bank

IUCN - International Union for Control of Nature

LACMA - Law on administrative Control over Municipality Activity

MAC - Maximum Allowable Concentration

MENS - Ministry of Ecology and Natural Resources

MH - Ministry of Health

NGO - Non-governmental Organization

OP - Operation Policy

PIU - Project Implementation Unit

ERV - Environmental Regional Visit

RP - Resettlement Policy

SFF - State Forest Fund

SD - Sexual diseases

STP - Sewage Treatment Plant

TA - Technical Assessment

UNDP - United Nations Development Program

WR - Water Reservoir

WSS - Water Supply and Sanitation

Measurement units

°C - Celsius degree

km - kilometre

km/s - km/hour

km2 - Square kilometre

m - meter

m3 - Cubic meter

mg/l - Milligram per litre

mg∙ekv - Equivalent to milligram

m/san - meter/second

m3/san - cubic meter/second

mm - Millimetre

106m3 - Million cubic meter

mb - Millibar

Table of Contents

I. INTRODUCTION ...................................................................................................... 1

A. Construction works and project progress during 6 months............................................... 2

B. Ecological Management Team ........................................................................................ 3

C. Project organization ......................................................................................................... 4

II. ECOLOGICAL MONITORING.................................................................................. 5

D. Noise ............................................................................................................................... 5

E. Water quality ................................................................................................................... 5

F. Air quality ........................................................................................................................ 6

G. Flora and fauna ............................................................................................................... 6

H. Waste disposal ................................................................................................................ 9

I. Final Monitoring Report ................................................................................................... 6

III. ECOLOGICAL MANAGEMENT ............................................................................... 7

J. Site inspection ................................................................................................................. 7

K. Reporting ......................................................................................................................... 7

L. Non-compliance notices ................................................................................................ 13

M.Reformatory Action Plan ..................................................................................................... 7

N. Recommendations and grievances .................................................................................. 7

APPENDICES

Appendix 1: Monitoring data

Appendix 2: Photographs of the Project Sites

Appendix 3: Grievance records of the towns

List of Tables

Table 1: Project Organization ..................................................................................................... 4

Table 2: Monitoring Table .......................................................................................................... 6

I. INTRODUCTION

1. The Azerbaijan Water Supply and Sanitation Investment Program is being co-financed

by the Government of Azerbaijan and the Asian Development Bank through a multitranche

financing facility (MFF) involving several tranches.

2. Tranche 1 considers completion of construction of water intake facilities and

rehabilitation of part of water supply and sewerage network in Goychaytown.Construction of

remaining part of water supply and sanitation systems and wastewater treatment plant

inGoychay, and WSSsystems and WWTPs in AghdashandBeylagantowns are included into

tranche II, while construction of WSS systems and WWTPs in AghjabediandBalakanis included

into tranche III .

3. Goychay- “Completion of construction of water intake facilities and rehabilitation of

partofwater supply and sewerage networks in Goychay – Package 1” (L-42408-ICB-2.01) and

”Completion of water intake facilities and rehabilitation of water supply and sewerage networks

in Goychay - Package-2” (MFF032‐T2‐ICB‐1.03).The initial contract includes the construction of

water intake facilities – drilling 2 units of artesian wells, laying HDPEtransmission main (4175 m

Ø450 mm), installation of HDPE pipeline (1002 m Ø400 mm), two units of 2000 m3 water

reservoir, checkpoints and lavatory, including polyethylene water distribution network (54 300 m

length with different diameters) with fire hydrants and house connections and construction of

sewerage network from corrugated pipes (49 120 m length ) with manholes and house

connections.Both contracts were awarded to ATINAK Construction and Trading Co. in

November 2011 and September 2012. The construction works for Package 1 commenced on

January 2012, while for Package 2 on November 2012. The initial contract duration forPackage

1 was 540days.The contract duration for Package 1 was extended two times, for 200 days for

the first extension and 150 days for the second extension. The initial contract duration for

Package 2 was 548 days. The contract duration for Package 2 has been extended threetimes,

for 230 daysfor the first extension and 181 days for the second extension and 184 days for the

third extension

4. Agdas-The contract of “Completion of construction of water intake facilities and rehabilitation of water supply and sewerage networks in Agdash town (MFF 032-T2-ICB-1.01)” was awarded to ALKE InşaatSanayiveTicaret A.Ş. in July of 2012. The construction works commenced in November. The initial contract duration was 548 days. The contract duration for

Agdash was extended two times, for 243 daysfor the first extension and 240 days for the

second extension.

The initial contract consists of;

5. Water intake facilities:2 units of artesian wells(Depth: 140m, Diameter: Ø400 mm, also

water pumps),construction of 5 units of wellhead cubicles, installation of power lines and

transformer, construction of steel pipeline (271 m, Ø159x6 ) from water collection site to water

reservoirs field, construction of gravel roads (5,000 m²), construction of new pumps (3 set,

each 45 kW and 150 m³/hour, H=70 m), construction of two units of water reservoirs (each

2,000 m³).

6. Water Supply system:total length: about 134,000 m, pipe diameter: 110 - 400 mm,

length of roads to be reinstated: around 107,000 m², house connections: 7,616 units, fire

hydrants: 594 units, valves: 789 units

7. Valve chambers: 109units, pressure and chlorine measuring points: 5 units, crossings: 5

units.

8. Sewerage network: Total length: app. 121,000 m, pipe diameters: 200 - 800 mm, length

of roads to be reinstated: app. 110,000 m², crossings: 6 units.

9. Beylagan-The initial contract includes construction of water intake facilities – drilling 5

artesian wells, pumping systems, construction ofsteeltransmissionmain, laboratory, water

reservoirs, administrative building, workshop, checkpoints, lavatory, including water distribution

network 70905 m in length with fire hydrants and house connections and construction of

sewerage network from corrugated pipes 78828 m in length with manholes and house

connections. The contract was awarded by TTS Construction & Ludwig Pfieffer GmbH Co JV in

August 2012. The construction works commenced on November 2012.The initial contract

duration was 548 days. The contract duration for Beylagan was extended two times, for 243

daysfor the first extension and 365 days for the second extension.

10. This ecological monitoring report was prepared based on data for the months of

JanuarytoJune, 2015.

11. Ecological Impact Monitoring is performed according to Ecological Management Plan

prepared by Project Implementation Unit. The environmental impacts during construction are

indicated below:

1. Excavation

2. Land replacement

3. Pipe installation

4. Backfilling and compaction

5. Installation of asphalt/concrete roads

6. Road protection and other works

12. The following are monitored during project implementation:

1. Noise

2. Water quality

3. Air quality

4. Flora-fauna

5. Waste disposal

A. Construction activity and project progress during last six months

13. In Goychay–During last six months(January 01 – June 30), in “Tranche 1 project –

Completion of construction of water intake facilities and rehabilitation of part of water supply and

sewerage networksinGoychay – Package 1, the contractorhascompleted all works

andtemporary acceptance has been realized.

“Tranche 2 project – Completion of construction of water intake facilities and

rehabilitationofwater supply and sewerage networksinGoychay– Package 2” commencedonNovember 13, 2012, the works started in January of 2013. The contractor has

installed water lines Ø160 mm and Ø110 mm connected by valves, hydrants and fittings. In

addition, sewerage line with different diameters was installed. The works have beencompleted

around 95%.

14. InAghdash–Works in water and sewerage networks have been continued. The scope of the

contract has been changed and reduced by cancelling the middle part of the city

Water Network – excavation works, pipe lying, backfilling, and installation of fittings have been

continued. House connections have been constructed in parallel to pipe lying. During this period

the installation of water meters have been increased.

Sewerage network–excavation works, pipe lying, backfilling, and construction of inspection

manholes have been continued. House connections have been constructed in parallel to pipe

lying.

15. In Beylaqan–Works in water intake area, water and sewerage networks have been

continued in accordance with new approved projects.

Water intake area - The Contractor has mostly completed the water intake facilities such as

water wells, piping between water wells, water intake structure, 500 m3 two reservoirs and

pump station. The transmission main has already been completed and it is also connected to

the existing reservoirs. By rehabilitating the reservoirs and by constructing a new pump station

and installation new pumps into the pump station, water has pumped to the new network. By

this way the project objective has been realized.

Water network - excavation works, pipe lying, backfilling, and installation of fittings have been

continued. House connections have been constructed in parallel to pipe lying.During this period

the installation of water meters have been increased.

Sewerage network– excavation works, pipe lying, backfilling, and construction of inspection

manholes have been continued. House connections have been constructed in parallel to pipe

lying in sewerage network.

B. Ecological Management Team

16. Construction Specialist and Site Inspectors of Consultant assist Mr Abbas Əliyev, the

ecological expert of Azersu JSC, to perform monitoring of Ecological Management Plan.

The below mentioned are fulfilled by Ecological Management Team:

Inform contract parties, site workers, inspectors and other related personnel on

Ecological Management Plan;

Attend the site daily to control ecological process emerged during construction;

Review and implement Ecological Management Plan;

Inform contract parties about implemented works in order to solve the problems

raised during monitoring

C. Project organization

17. The Project Organization for above mentioned contracts are shown in the following

Table1.

Table 1: Project Organization

Project Employer Contractor Engineer

Goychay P1

L-42408-ICB-

2.01

Azersu JSC Atinak A.S. AYKO-ART-NKUK

Aghdash

MFF032-T2-ICB-

1.01

Azersu JSC AlkeInsaatSanayiveTicaret

A.S.

AYKO-ART-NKUK

Beylagan

MFF032-T2-ICB-

1.02

Azersu JSC TTSInsaat MMC and

Ludwig Pfeiffer JV

AYKO-ART-NKUK

Goychay P2

(MFF 032-T2-

ICB-1.03)

Azersu ASC Atinak A.S. AYKO-ART-NKUK

II. ECOLOGICAL MONITORING

18. In order to assess environmental impacts during construction works in Aghdash,

Goychay and Beylagan, site visits were conducted at different times to the areas with ongoing

construction-installation works. The monitoring revealed that the construction of water supply

and sewer systems in the downtown were accompanied by massive excavation of land. The

contractor plans work phases and takes necessary measures to manage excavated material

since it impedes normal movement of local people and vehicles.

19. Machinery with disturbing noise is applied at minimum. Dusty materials and other

wastes from construction are prevented through temporary fences and covers. In order to

prevent pollution of the downtown, the excavated materials are transported more through

alternative secondary roads, which are not considered the central streets of the town, rather

than the main roads of the town. There are not any cultural premises and archaeological

monuments in the project area. If the cultural and historical areas are spotted in the project

area in the future, appropriate measures will be taken with regard to the Environmental

Management Plan (EMP).

20. The contractors noted down to consider the health of contract parties, environment of

the construction site; manage noise and wastes; public grievance.

D. Noise

21. The contractors minimized the noise from construction works. All construction works

were carried out during unrestricted hours (09.00 to 18.00), excluding weekends and general

holidays. All heavy vehicles and mechanical equipment used for the purpose of the works

were fitted with exhaust silencers. No diesel heavy construction equipment is kept running idle

for more than five minutes. Special consideration have been provided to protect workers from

harmful and long exposures to noise from construction machinery such as wearing of earmuffs

for operators. The use of vehicles and mechanical equipment resulting in noise and vibration

is minimized in densely populated areas. There is no complaint about noise but it should be

kept under strict control.Listed grievances are connected with other issues.However,

residential buildings were damaged in Beylagan as a result of noise-vibration. By this way,

conducted regular monitoring of pollution should be kept under strict control.

E. Water quality

22. No construction works are conducted around any river side. The executed works were

apart from water resources and there was no pollution.All the works were implemented

considering minimization of sediment in water basin, prevention of wreckage, trees, natural

wastes, oil, diesel and hazardoussubstancesto enter the water basins.

23. Stable construction materials and damaged parts were covered to avoid loss and flow of

material. Storage sites are located at 200 m from water basins.

24. Natural drainage models were under control to minimize sludge disposal into rivers and

water basins as a result of construction. Construction works are nearly conducted in parallel to

existing system. Since existing water pipelines are very old, there are many accidents on

existing line during excavation works and they are eliminated in a very short period by the

Contractor. Accordingly, the water quality gets worse.

F. Air quality

25. Naturally, some wastes, dust from excavation and harmful gases from fuel used by

machinery affect air quality during construction. The construction site is watered especially in

hot and dry weather in order to prevent the dust. Temporary fence and covers are installed to

prevent spread of dusty materials and other wastes from construction. This method is applied

to minimize the dust. Speed limit for heavy construction vehicles was limited at 30 km/hour. All

the excavation, uploading/unloading works have been stopped when wind velocity is more

than 12 km/hour. All construction works were executed in such a way that will minimize if not

totally eliminate the spreading of dust or any inconvenience and nuisance to nearby

communities.

G. Flora and fauna

26. The environmental damage is almost minimized in this stage of construction.

H. Waste disposal

27. All solid wastes were properly packaged and disposed at the designated dumpsite of the

town. This site was determined by MENR. Waste containers were placed in every construction

site and camps. These containers are collected and disposed on a daily basis.

I. Final Monitoring Report

28. The Table 2 was prepared based on monthly report of Contractors of Trench 2. P1

project 'n Trench 1 is expired a year ago.

Table 2: Monitoring Table for the projects in Trench 2

Months (2015)

January

February

March April May June

Noise Under control

Under control

Under control

Under control

Under control

Under control

Water quality Satisfactory Satisfactory Satisfactory N/A N/A Satisfactory

Air quality Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory Satisfactory

Flora-fauna Protected Protected Protected Protected Protected Protected

Waste disposal Checked Checked Checked Checked Checked Checked

Public grievance

Health and safety N/A N/A

III. ECOLOGICAL MANAGEMENT

J. Site inspection

29. Official ecological inspectors of Project Implementation unit conducted daily site visits. In

addition, the consultants’ site inspectors were on site to observe safeguard measures. PMO’s environmental manager paid weekly visits to the construction site.

The names of Environmental specialists of each Contractor are;

Goychay, ATINAK, ElnurCaferov

Agdas, ALKE, Alay Azizov

Beylagan, TTS Ins., Amin Mammadov

K. Reporting

30. Contractors submitted monthly reports to the PMO describing their environmental

monitoring activities and health and safety management.

L. Non-compliance notices

31. Not any non-compliance notice has been issued in the project. The environmental team

of “ATINAK” and “AlkeInsaatSanayiveTicaret A.S” Companies of Turkey and “TTŞ İnşaat MMC And Ludwig Pfeiffer” company of Azerbaijan has not changed. The team is very well trained in preventing or minimizing environmental impacts and how to implement them according to their

management plan. They have not been warned for anything.

M. Reformatory Activity Plan

32. No reformatory activity has been performed during the report period, 2014.

N. Recommendations and grievances

33. During the reporting period, grievance letters of IlhamImanovand the other resident

IbrahimovMammadYunisoglu that live in R.Akhundov street,108 in Beylagan were received

by the construction company. Private residential buildings belonging to ImanovIlham and

IbrahimovMammadwere looked at and cracks were identified in the walls of their houses as

a result of the vibration during the construction. In order to calculate the damage to

IlhamImanovMaharramoglu who lives in R.Akhundov street,108 in Beylagan, the

Construction company applied toMinistry's State Agency for Construction Safety Control and

received opinions and recommendations. According to the recommendations the problems

will be solved soon.

10 people have been registered on the complaint in Goychay. The complaints mainly dealt

with not installation of sewer lines and meters and the coverage of roads with asphalt where

the work has done. One issue is resolved, others are expected to be resolved in the near

future.

39 complaints were registered in Agdash in connection with the non-provision of water with

line and elimination of sewage manholes and investigations were conducted at ways of

solving problems and most were resolved in short period, others are expected to be

eliminated.

Bi-Annual EMR No-5 January 01 - June 30-2015

APPENDICES

Appendix 1: Monitoring Data For All Cities :Goychay, Agdash and Beylegan

№ Site Issue Recommended Implemented Note 1

Con

str

uction

site

Use of health-care items (protective glasses, gloves, cloth, shoes, helmet)

Availability of health-care matters in construction site

Health-care items to be provided by the contractor to the workers

Satisfactory

Temporary sites and signals for construction works

Information boards. Warning alarms, identification signs and other important signs should be provided along the pipe

Information boards and warning signals are to be installed during the construction

Satisfactory

Dust Watering the site in order to avoid the dust during vehicle and facility movement; Limiting the speed Covering the completed roads with asphalt

Though the site is watered regularly, there is dust problem in hot and dry weather in the areas not covered with asphalt; The speed is limited at 30 km/hour

Non Satisfactory(1)

Noise contamination

Minimization of noise from vehicle and facilities; Minimization of total construction noise

Use of noise eliminators for heavy vehicle and machinery; Construction activity creating much noise is minimized.

Satisfactory

Water pollution Provision of sediment syphons for erosion control

Barriers and siphons shall be installed in the places shown by Official Ecological Control

Satisfactory

Solid waste Provision of closed (with cap) waste boxes to the construction site; Dispose construction waste to determined site

Waste boxes were provided to each construction site; The waste is transported to the site determined MENR

Satisfactory

2

Con

str

uction

ca

mp

Water quality Provision of water tap in bathroom, lavatory, kitchen and canteen

Reservoir, bathroom, lavatory, kitchen, canteen are supplied with taps.

Satisfactory

Lavatory Provision of lavatory and bathroom with shower system.

Water is available in all the lavatories

Satisfactory

Transportation of sewage waters with septic cranes, its treatment and use for watering mine well

Camp drainage Provision of water drainage bear the ditch far from the camp Prevention of water stagnation in the camp

Water drainage is installed and water is disposed into the ditch. There is no water stagnation in the site

Satisfactory

Solid wastes Placement of waste bins in the camp and modernisation with cap and handles

Each room is provided with waste box When they are full, they are collected and transported.

Satisfactory

Fire-fighting items should be available in the camp and office.

Fire-fighting items which are used in emergency situations shall be visible

Firefighting items shall be visible.

Satisfactory

3

Ma

teria

l re

se

rve

ının

topl

anıld

ığıs

ahə

The dust will pollute the site full of materials

Provision of gravel to earth roads to avoid the dust

The earth is strengthened in the material storage sites. Dust was minimized.

Satisfactory

(1)This issue was solved by consultation with Contractor.

Appendix 2: Photographs of Project Site

Goychay

Reinstatement of the roads

Installation of new pumps

Well No. 4

Reservoirs site No.1

Agdash

Drilling of new well

Existing well

Site visit with the Employer’s staff

Beylagan

Reinstatement of roads

Rehabilitation of existing reservoir

Pumps in new pump station

Appendix 3: Grievance records of the towns Records in Goychay :

№ Date/receiv

ing

grievances

Name/Employe

r’s contact number

Kind of

grievance

Categor

y

Place Situatio

n

waiting-

solved

Organi

zation

s

Further

comments

1 03.05.2015

direct

051 502 60 48 Controllin

g sewer

connectio

ns

Sewer M.Mura

daov

Dalan 2,

h 4

solved

2 06.06.2015

direct

Azadov İl a

050 592 63 95

No sewer Sewer Z.Bunya

dov

waiting

3 12.06.2015

direct

Ma ılov Mahi 050 465 72 69

No sewer

No water

Sewer

and

water

Xaqani

str.

H 2

waiting

4 15.06.2015

direct

Şı ali ev Etiba

050 304 77 22

No sewer

laying

Sewer Potu,

back of

Vusal

market

waiting

5 17.06.2015

direct

Abdullayev

Rüstəm

050 744 50 00

No water

meter

installatio

n

Water Z.Bunya

dov

waiting

6 21.06.2015

direct

İsma ılov Bəxtiyar

050 556 08 77

No

asphalt

laying

Asphalt Kurt

village

waiting solved

7 26.06.2015

direct

İsma ılov Azad

050 343 32 49

No meter Meter Ataturk

7, h 7

waiting

8 01.07.2015

direct

Əliyeva Raida

051 981 61 57

Water

problem

Habibi

str. 22

waiting

Records in Agdash :

№ Name /date The subject of

the grieavance

Address Situation Waiting/solved

1 Qadirov Mehman

01.06.2015

The old sewer

line was

damaged.

Samad

Vurgun,6

The work is

ongoing/

050 343 35 10

Solved

05.06.2015

2 Mammadov Intiqam

01.06.2015

There is no

water

connection.

There is no

sewer and

house

connection

Evez str.,

Opposite the

school

051 746 16 86 Solved

07.06.2015

3 Afandiyev Vidadi

Musayev Bahram

01.06.2015

No house -

water

connection

was given both

of them

Back of the old

hospital

050 314 47 52

050 367 85 75

Solved

07.06.2015

4 Ezmammadov Saffar New house,

but no water

connection.

Ibrahim

Qaradagli str.

051 313 81 00 Solved

07.06.2015

Records in Beylegan :

№ Receiving date By whom The content of the

letter

Who the letter

was addressed to

1 17.04.2015 Ibrahimov Mammad

Yunus

Cracks appeared

in the house

during the

construction of

the sewer line

Pashayev A.

Mamishov S.