Environmental Monitoring Report Semi-Annual Report July December, 2017 VIE: Greater Mekong Sub-region Flood And Drought Risk Management and Mitigation Project Prepared by Vietnam Water, Sanitation and Environmental JS Company for the Ministry of Agriculture and Rural Development and the Asian Development Bank

Upload: others

Post on 15-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Environmental Monitoring Report Semi-Annual Report July – December, 2017

VIE: Greater Mekong Sub-region Flood And Drought Risk Management and Mitigation Project Prepared by Vietnam Water, Sanitation and Environmental JS Company for the Ministry of

Agriculture and Rural Development and the Asian Development Bank

Page 2: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

ASIAN

DEVELOPMENT

BANK

MINISTRY OF RURAL

DEVELOPMENT AND

AGRICULTURAL

CENTRAL OFFICE FOR WATER RESOUCES PROJECT – CPO

BIDDING PACKAGE GMS-4.10

INDEPENDENT ENVIRONMENTAL MONITORING CONSULTANT

SECOND SEMI-ANNUAL ENVIRONMENTAL

MONITORING REPORT

GREATER MEKONG SUBREGION FLOOD AND DROUGHT RISK

MANAGEMENT AND MITIGATION PROJECT (ADB-GMS1)

INVESTOR CONSULTING UNIT

CENTRAL PROJECT OFFICE - CPO VIETNAM WATER, SANITATION AND

ENVIRONMENTAL JS COMPANY

Hanoi December, 2017

Page 3: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

CURRENCY EQUIVALENTS

(Up to 16th August, 2013)

Currency unit – Viet Nam Dong (VND)

$1.00 = VND 20.815

ABBREVIATIONS

ADB – Asian Development Bank

PMU – Project Management Unit

BVMT – Environmental protection

CBOs – Community Based Organizations

CEMP – Community Environmental Management Program

CPM – Central Project Management Unit

CPO – Central Project Office

EMP – Environmental Management Plan

GOV – Government

M&E – Monitoring and Evaluation

PPMU – Provincial Project management Unit

PRA – Public Relative Assessment

QLMT – Environmental management

SEMP – Site Environmental Management Program

TN&MT – Natural resources and Environment

TOR – Terms of References

TVGS – Monitoring Consultant

DONRE – Department of Natural Resources and Environment

IEE – Initial Environmental Examination

PMU – Project Management Unit

QCVN – Vietnam National Environmental Standards

UNITS OF MEASUREMENT

ha – Hectare kg – Kilogram km – Kilometer m – Meter t – Ton

NOTES

In this report, "$" refers to US dollars unless otherwise state.

This environmental monitoring report is a document of the borrower. The views

expressed herein do not necessarily represent those of ADB's Board of Directors,

Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any

designation of or reference to a particular territory or geographic area in this document,

the Asian Development Bank does not intend to make any judgments as to the legal or

other status of any territory or area.

Page 4: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

62

CONTENT

1.1. PROJECT BACKGROUND ........................................................................................... 63

1.2. PROJECT IMPLEMENTATION PROGRESS .................................................................... 64

2. INSTITUTIONAL SETUP AND RESPONSIBILITIES FOR EMP IMPLEMENTATION

AND SUPERVISON................................................................................................................. 60 3. COMPLIANCE WITH ENVIRONMENT RELATED PROJECT COVENANTS ............. 61

4. ENVIRONMENTAL MITIGATION MEASURES IMPLEMENTED IN THE REPORTING

PERIOD .................................................................................................................................... 60 5. ENVIRONMENTAL EFFECTS MONITORING ................................................................ 67

5.1. PURPOSE, SAMPLING METHOD AND LOCATION ........................................................ 67

5.2. MONITORING RESULT .............................................................................................. 60

6. PUBLIC CONSULTATION, GRIEVANCE REDRESS MECHANISM ............................ 69

6.1. PUBLIC CONSULTATION AND EMP INFORMATION DISSEMINATION ........................ 69

6. PUBLIC CONSULTATION, GRIEVANCE REDRESS MECHANISM ............................ 69

6.1. PUBLIC CONSULTATION AND EMP INFORMATION DISSEMINATION ........................ 69

6.2. GRIEVANCE REDRESS MECHANISM (GRM) ............................................................ 71

7. INSTITUTIONAL STRENGTHENING AND TRAINING ................................................ 71 8. KEY ENVIRONMENTAL ISSUE ....................................................................................... 72 9. CONCLUSION AND RECOMMENDATION .................................................................... 61

9.1. OVERALL PROGRESS OF IMPLEMENTATION OF ENVIRONMENTAL MANAGEMENT

MEASURES ........................................................................................................... 61

9.2. ACTION RECOMMENDED ......................................................................................... 61

APPENDICES ........................................................................................................................... 60

LIST OF TABLES

Table 1: Project implementation progress ......................................................................... 60

Table 2: Responsibilities of environmental management implementation........................ 60

Table 3: Compliance with environmental related project covenants ................................. 60

Table 4: Environmental protection measures to be performed .......................................... 60

Table 5: Purpose, monitoring locations and analysis parameters ...................................... 68

Table 6: Site Status and Key Issues Identified, Actions Taken, Additional Action

Required for Each Construction Item ................................................................................ 60

LIST OF FIGURES

Figure 1. Implementation organization chart ..................................................................... 60

Figure 2: Sampling map of Go Cong subproject ............................................................... 60

Figure 3: Map of air samples (Ba Rai - Phu An subproject) ............................................. 62

Figure 4: Map of surface water samples (Ba Rai - Phu An subproject) ............................ 62

Figure 5: Map of groundwater samples (Ba Rai - Phu An subproject) ............................. 64

Figure 6: Map of soil samples (Ba Rai - Phu An subproject ............................................. 64

Figure 7: Map of air sampling – Dong Thap Muoi subproject (Plain of Reeds) ............... 65

Figure 8: Map of air sampling – Dong Thap Muoi subproject (Plain of Reeds) ............... 67

Figure 9: Map of surface water sampling - Dong Thap Muoi subproject ......................... 68

Figure 10: Map of ground water sampling – Dong Thap Muoi subproject ....................... 68

Figure 11: Map of mud/soil sampling – Dong Thap Muoi subproject (Plain of Reeds) ... 69

Page 5: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

63

1. INTRODUCTION

1.1. Project background

Greater Mekong flood subregion and drought risk management and mitigation project

(ADB-GMS1) is taken from loans no.2937-VIE (SF) of Asian Development Bank

(ADB). The Agreements was signed from 21 December, 2012 and entered into force on

10 May, 2013.The project includes 04 subprojects located on 02 provinces Tien Giang

and Dong Thap. Construction period of the project expected 03 years. Detail is as

following:

(1) Construction of flood control system in Ba Rai – Phu An region, Tien Giang

province: Construction of 28 medium and small sewers to create a flooding prevention

system protects the safety of people and fruit-growing area for the region between two

channels Ba Rai and Phu An thereby boosting socio-economic sustainable

development for investment area of the project.

(2) Upgrading saline control system of Go Cong region, Tien Giang province:

Construction of 3 new sewers includes Son Quy (B=20m). Nguyen Van Con (B=15m)

and Salisete (B=10m) and 1,9km of embankment connecting 03 existing sewers to

against salt intrusion for Go Cong town and Go Cong freshening area of the project;

(3) Improvement and upgrading irrigation channels and supply irrigation water for

Plain of Reeds include channels and its length: (i) Khang Chien (32,263km),

construction of 20 sluice and culvert system of flood control and drainage,

embankment combining with construction of rural traffic road; (ii) Tan Cong Chi –

Doc Vang Ha (37,370km), construction of 27 new sewers; and (iii) Cai Cai

(19,668km), construction of 5 sewers and 3 bridges which pass over channel.

Embankment and upgrading traffic infrastructure along existing system of channels are

to improve flooding drainage capacity, mitigate the damage of flood caused and

provide irrgation water for Plain of Reeds;

(4) Embankment erosion control in Thuong Thoi Tien Town, Hong Ngu District, Dong

Thap Province: New construction of a ferry terminal in district central and 3.224km of

embankment, which was broken by flood as well as construction of traffic road along

riverbank (7,0m of width with asphalt).

Each subproject includes 04 components:

- Component 1: Enhancing database, information and regional knowledge to

manage floods and droughts. Planning design guidelines for flood and drought

control system and protection works in MeKong Delta region, Cambodia –

Vietnam overflowing flood management;

- Component 2: Improving infrastructure of drainage system;

- Component 3: Strengthening management capacity based on communities;

- Component 4: Project management.

The objective of project is to improve capacity of community to prepare for respond to

and overcomes the risks of flood and drought caused reduces maximum the damages of

prolonged flood and drought to the local economy and society.

Page 6: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

64

The Project will support GoV to carry out structural and non-structural actions for the

preparation and management of disaster risks related to floods and droughts. Floods and

droughts will be mitigated by positive impacts of the project. Strengthening capacity and

improving management process is one of project’s results. Specifically:

- Upgrading irrigation infrastructures include: Dredging, expanding 77km of

channel; reinforce 60km of embankment and rural road; construct regulator

drainage system, traffic bridge; construction of 3.25km embankment to improve

flooding drainage and to ensure safety of people as well as irrigation water source

providing to 185,872ha of agricultural land;

- Enhance community capacity to manage floods and droughts with the activities

focused on some communes in project area;

- Regional cooperation to manage negative issues such as climate change, sea level

rise and border overflowing flood; building design standards of flood and drought

in the Mekong Delta with the cooperation of MRC and the participartion of

Mekong riparian countries.

1.2. Project implementation progress

Page 7: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

60

Table 1: Project implementation progress

No Bidding package

Contractor

selection

period

Implementation

period

Begining of

construction period Construction progress to April/2017

1

Civil package GMS 2.6.

Upgrading saline control system

of Go Cong region, Tien Giang

province

Quater

II/2014-

IV/2014

3 years 23, February 2016

- Construction progress of Nguyen Van Con

sewer: 92% workload.

- Currently, the items are being carried out as

following: Making road on the sluice and

administration building

- Construction progress of Saliset Sluice: 95%

workload. Finishing trial operation of water

circulation

- Currently, the items are being carried out as

following: Making road on the sluice and

administration building

- Construction progress of Son Quy sluice: 20%

workload.

- Currently, the items are being carried out as

following: Pouring concrete into holes

2

Civil package GMS 2.7

Construction of flood control

system in Ba Rai – Phu An

region. Tien Giang province

Quater

II/2014-

IV/2014

3 years 6, February 2017

- Construction progress: under construction of 28

sluices

- 04 remaining sluices haven’t been constructed

due to delay in handing over the ground for

contractor

3

Civil package GMS 2.8.

Embankment erosion control in

Thuong Thoi Tien Town, Dong

Thap Province

Quater

II/2014-

IV/2014

3 years 29, December 2015 The construction was completed.

4 Civil package GMS 2.9. Quater 4 years Quater IV/2016 - In association with Petroleum Construction

Page 8: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

61

Improvement and upgrading

irrigation channels and supply

irrigation water for Plain of

Reeds, Dong Thap province

II/2014-

IV/2014

Investment Joint Stock Company and Hong

Truong Limited Company, Bao Chung Joint

Stock Company are carrying out to construct 3

bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3,

dredging Cai Cai channel and pumping mud into

Cell no 1,3,4).

- Huyen Minh company are constructing Cell

no.2 and Bau Lut bridge

Workload carried out is as following:

- Completed casting concrete pile of Long Son

Ngoc and Ca Chap 3 bridge (under construction

of spans)

The volumn of Cell no 1 reaches about 95%

The volumn of Cell no 2 reaches about 95%

The volumn of Cell no 3 reaches about 95%

Currently, cell no.4 hasn’t carried out the

construction activities

Page 9: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

60

2. INSTITUTIONAL SETUP AND RESPONSIBILITIES FOR EMP

IMPLEMENTATION AND SUPERVISON

Institutional responsibilities for environmental management

Figure 1. Implementation organization chart

Task, function of agencies/organizations:

Table 2: Responsibilities of environmental management implementation No Agencies Responsibilities of environmental management

implementation

1 CPO/CPMU Taking responsibilities for management, monitoring, supervision

and preparation of environmental monitoring reports to submit

ADB every 6 months.

Mobilize an independent environmental monitoring consultant

during project implementation process to monitor EMP’s

implementation.

2 PPMU To be responsible for implementing all of environmental

protection activities in the environmental management plan of the

sub-projects (EMP) in the preparation stages of pre-construction

and construction.

Assign environmental staff to supervise environmental protection

activities of contractors as well as CSC’s monitoring activities

Coordinating with local authorities to resolve complaints (if any).

Prepare periodic reports to submit CPMU about implementing

project plan and environmental management plan of sub-project.

3 Construction

contractor

Prepare “Site environmental management plan for construction

area of contractor" to meet the requirements for environmental

management of sub-project. This plan must be approved by the

project owner before proceeding construction.

Perform tasks that defined in the Site Environmental

Management Plan, effectively caring out mitigation measures

ADB CPMU

PPMU

Environmental staff

Contractor CMC Community

IEMC

DONRE

Page 10: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

61

No Agencies Responsibilities of environmental management

implementation

during construction and other issues relating to the

environmental management plan of sub-project.

Reporting to local authorities and PPMU if occurring the

environmental accidents and coordinating with relevant parties

and stakeholders to resolve it.

Resolve complaints relating to the construction and operation of

the workers.

4 Construction

Supervision

Consultant

Support PMU for the implementation of daily environmental

management plan approved by ADB in contractor’s construction

process

Periodically making the temporary reports on implementation of

EMP at the site including the improved proposals for Contractor’s

synthesis to submit to PPMU

5 Independent

environmental

monitoring

consultant of

project

Strengthen management capacity and environmental monitoring

for contractors thoughout EMP guideline and training class.

Checking, supervise the compliance of contractors with

environmental mitigation measures mentioned in the approved

EMP/EIA

Sampling, analysis and environmental quality assessment to

evaluate project’s influence level to the environment

Prepare periodic reports on implementing environmental

safeguard for subproject as required

6 Local community Residential communities have right and responsibility supervising

activities in the construction process to ensure rights and their

safety policies are protected adequately as well as mitigation

measures are implemented effectively by contractor and PMU. In

case of unexpected problems, they will report to CSC/PMU/CPC.

3. COMPLIANCE WITH ENVIRONMENT RELATED PROJECT COVENANTS

Page 11: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

60

Table 3: Compliance with environmental related project covenants Implemen

tation

condition

of the

sub-

projects

Environmental covenants

Communit

y

monitoring

UXO Environment Related to bidding document and

contracts

Grievance

redress

mechanism

Set up

monitoring

activities

basing on

community

Removi

ng

unexplo

ded

ordinace

s (UXO)

Complianc

e with

Vietnam

laws and

regulations

on

environme

nt, safety

and health

Complian

ce with

environm

ental

safety

Compliance

with mitigation

measures and

requirements

mentioned in

IEE and EMP

and other

preventing

measures,

which involved

monitoring

report

Priority to

implemena

tion of

ADB

policies if

there are

differences

between

ADB

policies

and

Vietnam

laws/regul

ations

ADB policies

will be applied

if there are

diffrences arised

between ADB

policies and

Vietnam law,

regulations

Contractor

must

comply

with

requiremen

ts and

mitigation

measures

mentioned

in IEE,

EMP and

other

preventing

measures,

which

involved

monitoring

report

Forecast

unforeseen

environmental

risks in IEE, EMP

Restate road,

infrastructure in

case it is damaged

by construction

activities,

transport before

completing the

project

Recover

roads and

infrastructu

re before

completing

the project

in case it is

damaged

Set up

grievance

redress

mechanism

(GRM)

Page 12: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

61

GMS 2.6.

Upgrading

saline

control

system of Go

Cong region,

Tien Giang

province

Non-

complied1

Being

complie

d

Being

complied

Being

complied

Partly

complied2

Being

complied

– Being

complied

No unforeseen

environmental

risks arised

Not yet

due,

because

Son Quy

sluice is

under

constructio

n

Being

complied

GMS 2.7.

Construction

of flood

control

system in Ba

Rai – Phu

An region,

Tien Giang

province

No

monitoring

activities

carried out

because

Interdisciplin

ary inspection

teams are

performing

cross-

checking3

Being

complie

d

Being

complied

Being

complied

Partly

complied

Being

complied

– Being

complied

No unforeseen

environmental

risks arised

To prepare

detours for

civil traffic

Being

complied

GMS 2.8.

Embankment

erosion

control in

Thuong Thoi

Tien Town,

Dong Thap

Province

Done

Done Done Done Done Done Done Done

Done Done Done

1 In first period of the project, community-based monitoring was set up, however, due to its poor supervision, community-based monitoring has been suspended and now replaced

by Interdisciplinary inspection teams 2 In the monitoring phase, IEMC team found that contractor and CSCs didn’t perform environmental mitigation measures such as sparying water to reduce dust on the

transportation routes as well as cleaning up transportation vehicles. Besides, environmental mitigation measures, which mentioned in EMP report, were performed poorly by

contractors 3 Similar to civil package GMS 2.6, IEMC team asked Tien Giang PPMU and community-based organizations to supervise construction activities tightly in order to ensure

affected people’s benefit and quickly repair incidents (if any)

Page 13: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

62

GMS 2.9.

Improvemen

t and

upgrading

irrigation

channels and

supply

irrigation

water for

Plain of

Reeds

Being

complied

Being

complie

d

Being

complied

Partly

complied

Non-complied

at Cell no.24

Being

complied

Complied Complied

No unforeseen

environmental

risks arised

Not yet

due,

because it

is under

constructio

n

Being

complied

4 Details will be shown at Table 6, civil package GMS 2.9 – Cell no.2

Page 14: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

60

4. ENVIRONMENTAL MITIGATION MEASURES IMPLEMENTED IN THE

REPORTING PERIOD

4.1. Monitoring method

In order to assess compliance with environmental protection measures of contractors,

IEMC has carried out monitoring methods as following:

Field survey: In monitoring phases of quarter III, IEMC had carried out field survey (5

November – 14 November, 2017) for each construction site in order to observe and

record compliance with environmental protection measures of contractors.

Composition of site survey included: IEMC team, PPMU’s environmental staff, CSC and

site leader of the civil package. Details of site survey are as follow:

- 6 November, 2017: Meeting with Tien Giang PPMU and conducting the site survey of

civil package GMS 2.6 – Go Cong subproject.

- 7-9 November, 2017: Conducting the site survey of civil package GMS 2.7 – Ba Rai-

Phu An subproject

- 10 November, 2017: Meeting with Dong Thap PPMU

- 11 November, 2017: Conducting the site survey of civil package GMS 2.8 – Thuong

Thoi Tien subproject

- 12-13 November, 2017: Conducting the site survey of cilvil package GMS 2.9 – Cai Cai

channel subproject

CSC monitoring: For each bidding package, IEMC has set up an environmental

monitoring form according to EMP provided for CSC. CSCs have responsibility to carry

out environmental protection measures everyday basing on environmental monitoring

form and synthesize it in monthly reports. In periodically monitoring phases, IEMC will

review those monthly reports to assess compliance with environmental protection

measures of construction contractor.

Community consultation: Recording people’s reflection on environmental issues at

construction site as well as environmental sanitation safeguards of contractors during

construction.

4.2. Environmental protection measures to be performed

IEMC has synthesized Table 4 according to environmental protection measures proposed

by EMP and compliance with environmental mitigation measures of contractors based

on CSC’s monthly environmental monitoring reports (Environmental monitoring forms

of monthly environmental monitoring reports are presented at Appendix 3 in the report).

Detail of Table 4 is as following:

Table 4: Environmental protection measures to be performed

No

Environmental

protection

measures

The implementaion of Environmental protection measures at the

subprojects

GMS 2.6.

Upgrading saline

control system of

Go Cong region,

Tien Giang

GMS 2.7.

Construction of

flood control

system in Ba Rai –

Phu An region,

GMS 2.8.

Embankment

erosion control

in Thuong Thoi

Tien Town,

GMS 2.9.

Improvement and

upgrading

irrigation

channels and

Page 15: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

61

province Tien Giang

province

Dong Thap

Province

supply irrigation

water for Plain of

Reeds

1 Removing UXO Being complied

Unexploded

ordnance has

been already

removed by

professional unit

before

commencement

of construction

Being complied

Unexploded

ordnance has been

already removed by

professional unit

before

commencement of

construction

Done Being complied

Unexploded

ordnance has

been already

removed by

professional unit

before

commencement

of construction

2 Diclosure of

RAP, EMP5

Done Done Done Done

3 Prepare onsite

environmental

mangement plan

Being complied

On site

environmental

mangement plans

prepared by

contractors have

been submitted to

CSC before

commencement

of construction

Not yet due

On site

environmental

mangement plans

prepared by

contractors have

been submitted to

CSC before

commencement of

construction

Done Being complied

Onsite

environmental

mangement plans

prepared by

contractors have

been submitted to

CSC before

commencement

of construction

4 Disposal site of

excavating

soil/dredging

mud

The amount of

excavated

soil/mud of Go

Cong and Saliset

sluice has been

used for restating

surface road as

well as making

sluice box body

The amount of

soil/mud will be

placed on site and

reuse for restating

surface road and

making sluice box

body. However,

contractors have not

carried out

environmental

protection measures

for the mud

disposal site as

mentioned in EMP

report. IEMC team

has remided

contractors and

PPMU’s

environmental staff

to carry out

environmental

protection

measures. Budget

for environmental

Done Disposal site has

been prepared

according to the

agreement with

local

Vetiver grass was

planted around

embankment of

disposal site

5 PPMU has completed sending RAP and EMP reports to commune/ward PCs in the project area. For EMP report,

contractors have saved one copy on site office in order to facilitate the implementation of environmental mitigation

measures

Page 16: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

62

protection measures

included in contract

for each

construction item

5 Training labor

safety

Being complied

Contractor carried

out training labor

safety for workers

before

commencement

of construction

Being complied

Contractor carried

out training labor

safety for workers

before

commencement of

construction

Done Being complied

Contractor carried

out training labor

safety for workers

before

commencement

of construction

6 First-aid kit Being complied

First-aid kits in

worker’s camps

have been

equipped fully by

contractor

Partly complied

First-aid kits in

worker’s camps

have been equipped

fully by contractor

However, the

quantity of

medicine and

medical instruments

isn’t enough

Done Partly complied

First-aid kits in

worker’s camps

have been

equipped fully by

contractor

However, the

quantity of

medicine and

medical

instruments isn’t

enough

7 Provide labor

protective

equipment

Partly complied

Gloves, boots and

clothes have been

equipped by

contractor on site

However,

workers rarely

use them

Partly complied

Gloves, boots and

clothes have been

equipped by

contractor on site

However, workers

rarely use them

Done Partly complied

Gloves, boots and

clothes have been

equipped by

contractor on site

However,

workers rarely

use them

8 Increasing

people’s

awareness on

HIV/AIDS6

Being complied

Being complied Done Being complied

9 Provide clean

water, toilets,

trash bins

Being complied

Toilets and trash

bins have been

set up on site

Clean water is

bought from

water supply

facilities or

households

Being complied

Toilets and trash

bins have been set

up on site

Clean water is

bought from water

supply facilities or

households

Done Being complied

Toilets and trash

bins have been

set up on site

Clean water is

bought from

water supply

facilities or

households

10 Using available Being complied Being complied Done Being complied

6 IEMC team will update site images in contractor’s environmental safety document in the upcoming monitoring

phase

Page 17: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

63

borrow pits

Construction

material from

available borrow

pits have been

bought and

transported to

construction area

of subproject

works

Construction

material from

available borrow

pits have been

bought and

transported to

construction area of

subproject works

Construction

material from

available borrow

pits have been

bought and

transported to

construction area

of subproject

works

11 Do not encroach

on natural forest

No natural forest

located in

construction area

No natural forest

located in

construction area

Done No natural forest

located in

construction area

12 Set up drainage

system on site

Being complied

Contractor has set

up drainage ditch

on site

Being complied

Contractor has set

up drainage ditch

on site

Done Being complied

Contractor has set

up drainage ditch

on site

13 Watering to

reduce dust

Non-complied

Contractor did not

spray water to

reduce dust

during monitoring

phase of quarter

IV

Non-complied

Contractor did not

spray water to

reduce dust during

monitoring phase of

quarter IV

Done Non-complied

Contractor did not

spray water to

reduce dust

during monitoring

phase of quarter

IV

14 Cover up

transport

vehicles

Partly complied

Material transport

vehicles have

been covered up

during

transportation

Partly complied

Material transport

vehicles have been

covered up during

transportation

Done Partly complied

Material transport

vehicles have

been covered up

during

transportation

15 Register

machineries

Partly complied

Contractor has

made the

registration of

construction

machineries in

environmental

safety documents.

However, these

machinery have

been changed by

other machinery

without the

registration or no

longer valid

registry

Partly complied

Contractor has

made the

registration of

construction

machineries in

environmental

safety documents.

However, these

machinery have

been changed by

other machinery

without the

registration or no

longer valid registry

Done Partly complied

Contractor has

made the

registration of

construction

machineries in

environmental

safety documents.

However, these

machinery have

been changed by

other machinery

without the

registration or no

longer valid

registry

16 Driving vehicles

on the right

speed

Being complied

Contractor has

Being complied

Contractor has

Done Being complied

Contractor has

Page 18: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

64

carried out the

speed controlling

for each driver,

who workes on

civil package,

through courses

of labor safety

training

- In fact, it is hard

to supervise

drivers on route.

This is a

limitation of

contractor

because of not

enough budget to

install GPS

equipment for

each

transportation

vehicles

carried out the

speed controlling

for each driver, who

workes on civil

package, through

courses of labor

safety training

- In fact, it is hard

to supervise drivers

on route. This is a

limitation of

contractor because

of not enough

budget to install

GPS equipment for

each transportation

vehicles

carried out the

speed controll for

each driver, who

workes on civil

package, through

courses of labor

safety training

- In fact, it is hard

to supervise

drivers on route.

This is a

limitation of

contractor

because of not

enough budget to

install GPS

equipment for

each

transportation

vehicles

17 Set up fence

around

construction site

Being complied

Corrugated sheet

fence has been set

up around

construction site

Partly complied

- Fence has been set

up but it were fairly

sketchy, it may

cause risks of

accident for traffic

participants near

construction site

Done Not implementd

No fence set up

around

construction site

18 Install

construction

signs and

warning lights

near

construction area

Partly complied

Constructions

signs and warning

lights have been

set up at

construction area

Partly complied

Construction signs

and warning light

have been set up

but it was fairly

sketchy

construction signs

and warning lights

at some

construction sites

were not installed

Done Being complied

Constructions

signs and warning

lights have been

set up at

construction area

19 Install

construction

signs

Being complied

Constructions

signs have been

set up at area of

contruction site

and near

construction site

Partly complied

Construction signs

have been set up

but it was fairly

sketchy

Some construction

signs missing or

unseen due to trees

at construction site

Done Being complied

Constructions

signs have been

set up at area of

contruction site

and near

construction site

20 Install speed Being complied Being complied Done Being complied

Page 19: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

65

limit signs and

waring signs as

well as

forbidden signs

Seed limit signs

have been set up

at deserted road.

However, when

the project almost

finished, IEMC

found that

contractor is no

longer pays

attention to

setting up speed

limit signs at

construction site

Forbidden signs

have been set up

at the area of only

authorized

persons allow

Seed limit signs

have been set up at

deserted road

Forbidden signs

have been set up at

the area of only

authorized persons

allow

Seed limit signs

have been set up

at deserted road

Forbidden signs

have been set up

at the area of only

authorized

persons allow

21 Mitigate

construction

activties in

nighttime and

resting hours

Being complied

No night-time

construction

activities arised

Being complied

No night-time

construction

activities arised

Done Being complied

No night-time

construction

activities arised

22 Set up access

roads

Complied

There are no

influences to the

movement of

people

Being complied

Prepare a temporary

road during

construction of

bridge passing over

channel

Done Being complied

There are no

influences to the

movement of

people

23 Restate traffic

roads if it is

damaged by

construction

activties,

transport

Not implemented

yet (because the

project is under

construction

process)

Not implemented

yet (because the

project is under

construction

process)

Done Being complied

(Traffic road has

been restated after

installing culvert

pipeline)

24 Annouce to

community for

the interruption

of services

Being complied

No services

interrupted

Being complied

No services

interrupted

Done Being complied

No services

interrupted

25 Provide barells

to containt oil

waste

Being complied

- Do not store it

on site

Empty barrels

have been stored

in the warehouse

- Barrels have

been provided for

workers in order

to containt oil

waste

Being complied

- Barrels have been

provided for

workers in order to

containt oil waste

Done Being complied

- Barrels have

been provided for

workers in order

to containt oil

waste

- Setting up

concrete ground

to prevent oil

leaking off

26 Do not discharge Being complied Being complied Done Being complied

Page 20: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

66

domestic

wastewater into

channels, canals

Already set up

toilets/septic

tanks on site

Already set up

toilets/septic tanks

on site

Hire people’s

housing

27 Ensure camp’s

sanitary

condition

Being complied

Toilets and trash

bins have been

set up on site

Being complied

Toilets and trash

bins have been set

up near camps

Done

Being complied

Toilets and trash

bins have been

set up on site

28 Gather

construction

materials away

riverbank or

fenced it up

Being complied

Solid waste,

construction

materials have

been gathered

away riverbank or

fenced it up

Being complied

Solid waste,

construction

materials have been

gathered away

riverbank or fenced

it up

Done Being complied

Solid waste,

construction

materials have

been gathered

away away

riverbank or

fenced it up

29 Set up

sedimentation

ponds of

drainage system

Non complied Non complied Done Non complied

30 Do not discharge

wet concrete into

channels, canals

Being complied

Contractor

reminded workers

for illegally

discharging wet

concrete into

channel, canals

Being complied

Contractor

reminded workers

for illegally

discharging wet

concrete into

channel, canals

Done Being complied

Contractor

reminded workers

for illegally

discharging wet

concrete into

channel, canals

31 Clean up

construction site

at the end of the

day

Being complied

Activities such as

collecting solid

waste, assigning

person to clean up

construction have

been performed

Being complied

Activities such as

collecting solid

waste, assigning

person to clean up

construction have

been performed

Done Being complied

Activities such as

collecting solid

waste, assigning

person to clean up

construction have

been performed

32 Clean up

transport

vehicles

Non-complied

There is no

vehicle cleaning

station set up on

site

Non-complied

There is no vehicle

cleaning station set

up on site

Done Non-complied

There is no

vehicle cleaning

station set up on

site

33 Set up grievance

redress

mechainsm

Being complied Done Being complied

but not good

34 Publicize

people’s

complaints

Being complied

Have not any

complaints

Being complied

People’s complaints

at construction area

of Thong Luu

sewer have been

resolved

Done Being complied

Identified cause.

People’s

complaints at

construction area

of Cell no.3 have

Page 21: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

67

satisfactorily been resolved

satisfactorily

Remark:

On site, the environmental protection measures in general have been implemented

relatively enough such as daily cleaning up the site, performing labour safety measures

(construction signs, first-aid box on site…). Besides, construction activities of contractor

don’t cause negative impacts to surrounding residential areas – contractor doesn’t

perform construction activities at nighttime and almost no machines with large noise.

- For the bidding package GMS – 2.6: Basically, contractor in charge of the

construction of Nguyen Van Con sewer, Saliset sewer and Son Quy sewer has

carried out well environmental protection measures on site. However, vehicle

washing station has not yet been set up on site.

- For the bidding package ICB GSM -2.7: Construction of flood control system in

Ba Rai – Phu An region, Tien Giang province. It is necessary to strengthen

measures as sparying water to reduce dust and installing more traffic signs as well

as setting up fence at deep pits on construction site

- For the bidding package ICB GSM - 2.8: Thuong Thoi Tien embankment:

construction has been already completed

- For the bidding package ICB GSM - 2.9, “Improvement and upgrading irrigation

channels and supply irrigation water for Plain of Reeds”, in monitoring phase of

quarter IV, IEMC team found that the construction of cell 2 is not match in

comparison with the original design even the contractor has been reminded by

IEMC in the previous monitoring phase. The contractor has cooperated with local

authority to satisfactorily resolve people’s complaints at Cell no.3

5. ENVIRONMENTAL EFFECTS MONITORING

5.1. Purpose, sampling method and location

a. Sampling method of surface water sample

Sampling method of surface water sample bases on Vietnam standards (TCVN) and

International Organization for Standardization (ISO), as following:

- TCVN 6663-1:2011 (ISO 5667-2:2006): Sampling technique

- TCVN 6663-3:2003 (ISO 5667-3:1985): Storage and analysis of sample

- TCVN 5994:1995 (ISO 5667-4:1987): Sampling at natural and artificial lakes

- TCVN 6663-6:2008 (ISO 5667-5:2005): Sampling at channel/canal, stream

Some parameters of surface water sample are directly analyzed at field such as pH,

Salinity, Electricial conductivity, DO. Surface water samples are taken, stored in bottles

and brought to the laboratory for the analysis of remaining parameter.

b. Sampling method of ground water sample

Sampling method of ground water sample bases on Vietnam standards (TCVN) and

International Organization for Standardization (ISO), as following:

- TCVN 6663-1:2011 (ISO 5667-1:2006): Plans program and sampling technique

- TCVN 6663-3:2008 (ISO 5667-3:2003): Storage and analysis of sample

Page 22: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

68

- TCVN 6663-11:2011 (ISO 5667-11:2009): Ground water sampling

Some parameters of groundwater sample are directly analyzed at field such as pH,

Hardness, salinity,TSS, DO. Groundwater samples are taken, stored in bottles and

brought to the laboratory for the analysis of remaining parameter.

c. Sampling method of air sample

Sampling method of air sample bases on Vietnam standards (TCVN) and International

Organization for Standardization (ISO), as following:

- TCVN 7726:2007 (ISO 10498:2004): Measurement, analysis and sampling of SO2

parameter on the field

- TCVN 5972:1995 (ISO 8186:1989): Measurement, analysis and sampling of CO

parameter on the field TCVN 5067:1995: Measurement, analysis and sampling of

TSP parameter on the field

- TCVN 6137:2009 (ISO 6768:1998): Measurement, analysis and sampling of NO2

parameter on the field

- TCVN 7878-1:2008 (ISO 1996-1:2003): Basic parameters and assessment methods

- TCVN 7878-2:2008 (ISO 1996-2:2003): Determination of sound pressure level and

assessment methods

Some parameters of air samples are directly analyzed at field such as Dust, Noise,

vibration.

d. Sampling method of mud/soil

- TCVN 5297:1995 (ISO 1996-2:2003): General technique requirements of mud/soil

sampling

- TCVN 7538-2:2005 (ISO 10381-2:2002): Technique of mud/soil sampling

- TCVN 6647:2007 (ISO 11464:2006): Preliminary treatment of mud/soil samples for

chemical and physical analysis

Soil/mud samples all are taken, stored in specialized plastic bags and brought to the

laboratory for the analysis.

Purpose, monitoring locations and analysis parameters are presented in the following

table:

Table 5: Purpose, monitoring locations and analysis parameters

Page 23: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

60

No Environment

al factor

Monitoring location Parameter Basis and sampling purpose

I GMS 2.6. Upgrading saline control system of Go Cong region, Tien Giang province

Air 3 sampling locations:

K 1: On Highway 50, at the bridge passing over Son

Quy ditch (10°24'08"N 106°39'415"E)

K 2: On internal road, in front of Nguyen Van Con

sewer (10°20'42"N 106°39'39"E)

K3: On the embankment construction area of

Salisete sewer and existing road (10°21'55"N

106°40'34"E)

Dust, Noise,

vibration, SO2,

NO2, CO

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

Proposed air sampling locations based on

characteristics are near construction site of

drainage culverts, transport routes and residential

area

Air sampling is to assess how influence level of

construction activities affect air environment and

the efficiency of contractor’s mitigation measures

Surface water 4 sampling locations:

M1: On Vam Giong- Go Cong ditch, faraway

100m of distance from Nguyen Van Con sewer to

the Go Cong town (10°21'14.4"N 106°39'03"E)

M2: On Son Quy ditch, faraway 100m of distance

from Son Quy sewer to the Go Cong sewer

(10°23'01"N 106°40'01"E)

M3: On Salieste channel, faraway 100m of distance

from Salisete sewer to the Go Cong town

(10°21'07"N 106°41'09"E)

M4: On Van Rong – Go Cong ditch, at Long Chanh

bridge (10°21'35"N 106°40'35"E)

pH, Salinity,

Electricial

conductivity, DO,

BOD5, COD, NH4+

; NO2- ; NO3

- PO43-,

Zn, Pb, Hg,

Coliform , Oil and

grease

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

Sampling locations near construction site of

drainage culverts, transport routes and near people

housing

Groundwater 3 sampling locations:

N1: At Mr.Nguyen Van Tai’s hom, new market

village, Long Hoa commune, Go Cong town

(Nguyen Van Con sewer) (10°21'33"N

106°39'82"E)

pH, Hardness,

salinity,TSS, DO,

COD, NH4-N,

NO2-N, NO3-N,

Cl-, Fe, Zn, As,

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

Groundwater sampling is to determine how

Page 24: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

61

N2: At Ms.Truong Thi Thoi’s home, village 3, ward

5, road 862, Go Cong town (Salisete sewer)

(10°21'44"N 106°41'22"E)

N3: At Mr.Tran Thanh Hoa’s home, Hoang Gia

village, Long Hung commune, Go Cong town (Son

Quy sewer) (10°23'41"N 106°40'66"E)

Ecoli, Coliform. influence levels of construction activties affect

groundwaterquality

Soil/mud 3 sampling locations:

Đ1: On Vam Giong- Go Cong ditch, construction

area of Nguyen Van Con sewer (10°21'14.0"N

106°39'06"E)

Đ2: On Son Quy ditch, construction area of Son

Quy sewer (10°23'15"N 106°40'24"E)

Đ3: On Salisete channel, construction area of

Salisete sewer (10°21'17"N 106°41'09"E)

pHkcl, pHH2O, total

soluble salt, mobile

Al, Total N, Total

P, Zn, Pb, As, Cd

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO.

During construction, it is necessary to gather

dredging mud from channels on construction site.

Afterthat, the amount of dredging mud will be

made use of leveling. Soil/mud sampling is to

assess quality of soil/mud and its influence to the

ambient environment during gathering on

construction site

II GMS 2.7: Construction of flood control system in Ba Rai – Phu An region, Tien Giang province

Air 4 sampling locations:

- K1: Giong Tre 1 sewer (10°19'52.9"N

106°03'16.6"E)

- K2: Thong Luu sewer (10°22'12"N

106°03'16.0"E)

- K3. Cai La sewer (10°19'51.1"N 106°03'29"E)

- K4: Ong Ban sewer (10°22'44.0"N

106°05'07.1"E)

Dust, Noise,

vibration, SO2,

NO2, CO

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

Sampling locations are near the construction area,

in order to access air environment status before

construction.

Surface water 7 sampling locations:

Ba Gon sewer (10°20'16.8"N 106°04'51.1"E)

M 2: Rach Giong sewer (10°23'27.2"N

106°03'18.1"E)

pH, Salinity,

Electricial

conductivity, DO,

BOD5, COD, NH4+

; NO2- ; NO3

- PO43-,

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO.

Page 25: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

62

M 3: Ca Nua sewer (10°23'12.1"N 106°05'43.5"E)

M 4. Cai la sewer (10°19'50.0"N 106°03'29.9"E)

M 5: Giong Tre 2 sewer (10°19'52.9"N

106°03'16.6."E)

M 6: Hai Hue sewer (10°19'57.9"N 106°04'45.2"E)

M 7: Khang Chien sewer (10°19'31.4"N

106°04'16.4"E)

Zn, Pb, Hg,

Coliform , Oil and

grease

Sampling locations are near the construction area,

in order to access air environment status before

construction.

Groundwater 4 sampling locations:

N1: At Mr.Cao The Duong’s home, Hoi Xuan

commune (10°19'56.7"N 106°04'44.9"E)

N2: At Mr. Tran Ba Loc’s home, village 6, Phu An

commune (Rach Giong sewer) (10°23'28"N

106°03'20.3"E)

N3: At Mrs. Huynh Thi Nhi’s home, village 1, Cam

Son commune (10°22'48.9"N 106°04'21.6"E)

N4: At Mrs.Tran Thi Dao’s home, village Hiep Phu,

Hiep Duc commune (Cai La sewer) (10°19'46.9"N

106°03'28.0"E)

pH, Hardness,

salinity,TSS, DO,

COD, NH4-N,

NO2-N, NO3-N,

Cl-, Fe, Zn, As,

Ecoli, Coliform.

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

Groundwater sampling is to determine the status of

groundwater quality before implementation, by

dint of that, examing how influence levels of

construction activities to groundwater quality in the

contruction area.

Soil/mud 4 sampling locations:

Đ1: Cai La sewer (10°19'51"N 106°03'29"E)

Đ2:Giong Tre 1 sewer (10°19'52.9"N

106°03'16.6"E)

Đ3: Thong Luu sewer (10°22'12"N

106°03'16.0"E)

Đ4: Rach Giong sewer , village 1, Phu An

commune (10°23'27"N 106°03'19"E)

pHkcl, pHH2O, total

soluble salt, Al,

Total N, Total P,

Zn, Pb, As, Cd

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO.

During construction, it is necessary to gather

dredging mud from channels on construction site.

Afterthat, the amount of dredging mud will be

made use of leveling. Soil/mud sampling is to

assess quality of soil/mud and its influence to the

ambient environment during gathering on

construction site

III GMS 2.8. Embankment erosion control in Thuong Thoi Tien Town, Hong Ngu Commune, Dong Thap Province

Air 3 sampling location: Dust, Noise, The number of samples, sampling locations,

Page 26: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

63

K1: First point of embankment system at Thuong

Phuoc 2 commune, Hong Ngu district

(10°48'50.9"N 105°13'45.8"E)

K2: Tan Chau ferry l, Thuong Thoi Tien commune

(10°48'10.5"N 105°14'55.2"E)

K3: Final point of embankment system, Thuong

Thoi Tien Commune (10°48'22.1"N 105°10’.4"E)

vibration, SO2,

NO2, CO

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

Proposed air sampling locations based on

characteristics are near construction site of

drainage culverts, transport routes and residential

area

Air sampling is to assess how influence level of

construction activities affect air environment and

the efficiency of contractor’s mitigation measures

Surface water 4 sampling location:

- M1: First point of embankment system, Thuong

Phuoc commune, Hong Ngu

district(10°48'55.7"N105°13'49.9"E)

- M2: Ngang wharf - Thuong Phuoc commune,

Hong Ngu district (10°48'45"N 105°14'10"E)

- M3: Tan Chau ferry terminal – Thuong Thoi Tien

commune (10°48'24"N 105°14'53")

- M4: Final point of embankment system - Thuong

Thoi Tien commune (10°48'24"N 105°15'10"E)

pH, Salinity,

Electricial

conductivity, DO,

BOD5, COD, NH4+

; NO2- ; NO3

- PO43-,

Zn, Pb, Hg,

Coliform , Oil and

grease

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

Sampling locations near construction site of

drainage culverts, transport routes and near people

housing

Sampling locations are along the embankment and

are to assess how influence level of construction

activities affect air environment and the efficiency

of contractor’s mitigation measures

Groundwater 2 sampling location:

N1: Drilling well at Mr.Nguyen Van Dung. Village

3, Thuong Phuoc 2 commune, Ngang wharf,

Thuong Thoi Tien town (10°48'46.0"N

105°14'08"E)

N2: Drilling well at Mr. Nguyen Van Chuc –

Thuong Thoi Tien commune, Hong Ngu district

(10°48'36.3"N 105°14'54"E)

pH, Hardness,

salinity,TSS, DO,

COD, NH4-N,

NO2-N, NO3-N,

Cl-, Fe, Zn, As,

Ecoli, Coliform.

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

Groundwater sampling is to determine how

influence levels of construction activties affect

groundwater quality

Soil/mud 2 sampling location: pHkcl, pHH2O, total The number of samples, sampling locations,

Page 27: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

64

B1: Near material gathering area of the first point of

embankment, Thuong Phuoc 2 commune, Hong

Ngu district (10°48'1"N 105°14'00"E)

B2: Final point of embankment– Thuong Phuoc

Tien commune(10°49'10"N 105°15'00"E)

soluble salt, Al,

Total N, Total P,

Zn, Pb, As, Cd

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

During construction, it is necessary to gather

dredging mud from channels on construction site.

Afterthat, the amount of dredging mud will be

made use of leveling. Soil/mud sampling is to

assess quality of soil/mud and its influence to the

ambient environment during gathering on

construction site

IV GMS 2.9. Improvement and upgrading irrigation channels, and supply irrigation water for Plain of Reeds, Dong Thap province

Air 3 sampling location:

K1: First point of Ca Chap 2 bridge (10°50'58.1"N

105°34'15.6"E)

K2: Wharf of Ngoc Long Son market (first point of

Cai Cai channel) (10°56'22"N 105°30'22"E)

K3: Point cell no 4 Cai Cai channel

(10°50'29.0"N 105°34'50.1"E )

Dust, Noise,

vibration, SO2,

NO2, CO

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

Proposed air sampling locations based on

characteristics are near construction site of

drainage culverts, transport routes and residential

area

Air sampling is to assess how influence level of

construction activities affect air environment and

the efficiency of contractor’s mitigation measures

Surface water 14 sampling location:

M1: Letfside of Khang Chien channel, faraway

100m of distance from Khang Chien bridge to

the downstream (10°50'44"N105°22'22"E) M2: Letfside of Khang Chien channel,faraway

100m of distance from An Binh channel to the

downstream(10°45'1"N 105°25'37"E) M3: Thong Nhat channel, faraway 100m of

pH, Salinity,

Electricial

conductivity, DO,

BOD5, COD, NH4+

; NO2- ; NO3

- PO43-,

Zn, Pb, Hg,

Coliform , Oil and

grease

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

Sampling locations near construction site of

drainage culverts, transport routes and near people

housing

Page 28: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

65

distance from An Phong channel to the

downstream(10°36'45"N 105°29'36"E) M4 Thong Nhat channel connecting to Tan Thanh –

Lo Gach channel (10°50'36"N 105°23'45"E) M5: Thong Nhat channel connecting to An Phong –

Tan Phuoc channel (10°47'13"N 105°26'33"E) M6: Thong Nhat channel connecting to Thanh Binh

– Tam Nong channel (10°39'48"N 105°29'34"E) M7: Tan Cong Chi channel connecting to Thanh

Lap channel (10°50'05"N 105°27'21"E) M8: Tan Cong Chi channel,Tam Nong general

hospital (10°42'30"N 105°34'35"E) M9: Tan Cong Chi channel, the segmentconnecting

to Doc Vang Ha channel (10°37'55"N

105°32'29"E) M10: Rightside of Cai Cai channel,faraway 100m

of distance from Tan Thanh – Lo Gach channel to

the downstream (10°54'22"N 105°31'23"E) M11: Cai Cai channel, the segment connecting to

Hồng Ngự-Vĩnh Hưng channel (10°49'52"N

105°35'22"E) M12: Cai Cai channel, the starting point of Tan

Thanh A bridge(10°51'31"N 105°33'25"E) M13: Cai Cai channel, it is expected for no.1 mud

cell (10°54'45"N 105°32'47"E)

M14: Cai Cai channel, segment under the bridge

across Cai Cai channel, it is expected for no.4 mud

cell (10°50'48"N 105°32'22"E)

Groundwater 8 sampling location:

N1: Pumping station at residential area Phu Lam,

Phu Thanh B commune (intersection of Kinh Ca

pH, Hardness,

salinity,TSS, DO,

COD, NH4-N,

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

Page 29: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

66

No bridge) (10°45'06"N 105°25'39"E) N2: Water supply station no.755, DT844 street, An

Long commune, Tam Nong district (10°40'45"N

105°23'40"E) N3: Mr. Truong Van Xe’s home, village 2, An

Binh B commune, Hong Ngu district (10°48'45"N

105°24'55"E) N4: House no.96, K10, Phu Hiep village, Tam

Nong district, DT843 street, Dong Thap province

(10°45'48"N 105°30'28"E) N5: Mr. An’s home, under footbridge An Phuoc

(10°48'55"N 105°28'26"E) N6: Water supply station, Tra Dam commune, Tan

Cong Sinh district (10°41'45"N 105°34'55"E) N7: At the market near Cai Cai channel, faraway

100m of distance from Tan Thanh – Lo Gach

channel to the downstream (10°54'20"N

105°31'23"E) N8: Near Cai Cai channel, Anh Dung village, Tan

Thanh A commune, Dong Thap province

(10°51'21"N105°33'11"E)

NO2-N, NO3-N,

Cl-, Fe, Zn, As,

Ecoli, Coliform.

contract signed between VIWASE and CPO

Groundwater sampling is to determine how

influence levels of construction activties affect

groundwater quality.

Soil/mud 12 sampling location:

Đ1: Letfside of Khang Chien channel, faraway

100m of distance from Khang Chien bridge to the

downstream (10°50'54"N 105°23'40"E) Đ2: Letfside of Khang Chien channel,faraway

100m of distance from An Binh channel to the

downstream lưu (10°44'18"N 105°25'30"E ). Đ3: Mud cell no 1 of Cai Cai channel

(10°53'49.7"N 105°31'33.0"E)

Đ4: Mud cell no 2 of Cai Cai channel

pHkcl, pHH2O, total

soluble salt, Al,

Total N, Total P,

Zn, Pb, As, Cd

The number of samples, sampling locations,

analysis parameters are based on proposal of EMP

and meet Independent environmental monitoring

contract signed between VIWASE and CPO

During construction, it is necessary to gather

dredging mud from channels on construction site.

Afterthat, the amount of dredging mud will be

made use of leveling. Soil/mud sampling is to

assess quality of soil/mud and its influence to the

ambient environment during gathering on

Page 30: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

67

(10°53'20.6"N 105°32'48.7"E)

Đ5: Mud cell no 3 of Cai Cai channel

(10°51'48.6"N 105°33'18.3"E)

Đ6: Mud cell no 4 of Cai Cai channel

(10°50'05.3"N 105°35'13.8"E)

Đ7: Tan Cong Chi channel connecting to Thanh

Lap channel (10°50'08"N 105°27'21"E ) Đ8: Tan Cong Chi channel,Tam Nong general

hospital (10°40'36"N 105°33'44"E)

Đ9: Tan Cong Chi channel, the segment

coonecting to Doc Vang Ha channel

(10°38'30"N 105°32'25"E)

Đ10: Rightside of Cai Cai channel, far away

100m of distance from Tan Thanh – Lo Gach

channel to the downstream (10°54'20"N

105°31'21"E)

Đ11: Cai Cai channel, the segment connecting

to Hồng Ngự-Vĩnh Hưng channel (10°49'54"N

105°35'42"E)

Đ12: Cai Cai channel, the segment under Tan

Thanh A bridge (10°51'35"N 105°33'23"E)

construction site

Page 31: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

60

5.2. Monitoring result

A. Subproject: “Upgrading saline control system of Go Cong region, Tien Giang

province”

Figure 2: Sampling map of Go Cong subproject

Note:

Air sample Ground sample

Surface water sample Mud/soil sample

➢ Air environment

Air sampling locations are linked with construction sites of culverts: Nguyen Van Con,

Salisete, Son Quy.

Analysis result of air quality shows that air environment basically is in good condition,

particle concentration ranges from 0.11-0.19 mg/l, have not exceeded allowable limits

QCVN05:2013/BTNMT– National technical regulation on ambient air quality (Particle <

0.3 mg/l).

Parameters NOx, SO2 and CO in air environment are in allowable limits QCVN05:2013/

BTNMT.

Virbation in monitoring locations is also in allowable limits of QCVN27:2010/BTNMT.

K1

K2

K3

M1

M2

M3

M4

N1

N2

N3 B1 B2

B3

Page 32: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

61

Noise ranges from 63 to 68dBA. (Noise<70dBA).

The analysis results show that mitigation measures of dust have been carried out fairly

good thereby mitigating negative impacts of dust to ambient air environment. However,

sometimes, gathering construction machineries and equipment had increased noise in

project area but its impact is localized and in the short time.

➢ Surface water quality

Surface water sampling locations are linked with construction sites of culverts: Nguyen

Van Con, Salisete, Son Quy.

Based on analysis result and QCVN08-MT:2015/BTNMT – National technical regulation

on surface water quality, column B1: using for irrigation purpose show that parameter

Coliform exceeds 1,14- 1,96 times allowable limit. The remaining parameters are within

allowable limit. Basically, construction activities have not caused the increase of surface

water pollution on the channel.

➢ Ground water quality

Ground water sampling locations are is to determine how influence levels of construction

activties affect ground water quality.

Based on analysis result of general ground water samples and QCVN 09-

MT:2015/BTNMT – National technical regulation on ground water quality show that:

- pH, hardness, salinity, COD, NH4+, NO2

-,NO3- and heavy metals Fe, Pb, As, Zn,

Pb, Hg of ground water samples are within allowable limits.

- Coliform parameter of samples exceeds allowable limit from 5 to 6.3 times.

- Undergournd water quality is not affected by installing culvert pipeline because

the depth of installed culvert pipeline is insignificant. Nomarly, depth of access to

ground water is about 200m.

➢ Soil environment

Soil sampling locations are linked with construction activities, installation of culverts:

Nguyen Van Con, Salisete and Son Quy.

Analysis result of 03 soil samples will be compared with QCVN03-MT-:2015/BTNMT –

National technical regulation on heavy metal limit. Concentration of some heavy metals

such as Zn, Pb, As, Cd is in allowable limits. Gathering soil/mud does not cause ambient

environmental pollution. However, contractor should be fenced up material gathering

area for environmental sanitation.

B. Subproject: “Construction of flood control system in Ba Rai – Phu An

region. Tien Giang province”

Page 33: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

62

Figure 3: Map of air samples (Ba Rai - Phu An subproject)

➢ Air and noise quality

Air sampling locations are linked with areas, where are going to construct culverts:

Giong Tre 1, Thong Luu, Cai La, and Tham Ron.

The air sampling locations are connected to materials transportation route of Cai Cai

channel construction site, the Plain of Reeds sub- project.

- Contaminants such as NOx, SO2 and CO are in allowable limits of

QCVN05:2013/BTNMT. The current status of air environment is fairly good

because project hasn’t been constructed.

➢ Surface quality

Figure 4: Map of surface water samples (Ba Rai - Phu An subproject)

K1

K2

K3

K4

Page 34: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

63

Surface water sampling locations are linked with areas, where are going to construct

culverts: Giong Tre, Rach Giong, Thong Luu, Cai La, Thay Thanh, Tham Ron and Lo

Lang

The air sampling locations are connecting to materials transportation route of Cai Cai

channel construction site, the Plain of Reeds sub- project.

Based on QCVN08-MT:2015/BTNMT - column A2 - National Technical Standards on

surface water quality used for domestic water supply but appropriately applied treatment

technology, shows that:

- pH ranges from 6.4 to 7.8 and in allowable limit of QCVN08-MT:2015/BTNMT,

column A2

- Parameter Dissolve oxygen (DO) of M1, M2, M5, M6 and M7 does not achieve

allowable limit of QCVN08-MT:2015/BTNMT.

- BOD5 parameter of some surface water samples M1, M2, M5, M6 and M7 exceeds

allowable limits from 1.26 to 2.35 times according to QCVN08-MT:2015/BTNMT,

column A2.

- COD parameter some surface water samples M1, M2, M5, M6 and M7 exceeds

allowable limit from 1.19 to 1.36 times according to QCVN08-MT:2015/BTNMT,

column A2

- NO2- parameter of surface water samples M1, M2, M5 and M6 exceeds allowable limit

from 5 to 8 times according to QCVN08-MT:2015/BTNMT, column A2

- Parameters NH4+, NO3-, Pb, Hg, Zn, As are in allowable limits of QCVN08-

MT:2015/BTNMT. Currently, the project has not been constructed so there are no

construction activities affecting surface water quality. Surface water pollution could be

arised by daily activities of local people through littering and discharging domestic

wastewater into the channel.

The results of analysis show that there is not much different compared to the current state

of water environment before construction. That also means the construction activities of

the project do not increase pollution to the water environment, and the constractor

performed the mitigation measures well.

➢ Ground water quality

Page 35: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

64

Figure 5: Map of groundwater samples (Ba Rai - Phu An subproject)

Ground water sampling locations are is to determine how influence levels of construction

activties will affect ground water quality.

Analysis results show that most parameters are within allowable limit of QCVN09-

MT:2015/BTNMT, however, parameter Coliform exceeds allowable limit from 3,3 to 6,7

times.

➢ Soil quality

Figure 6: Map of soil samples (Ba Rai - Phu An subproject

Soil sampling locations are linked with areas, where are going to construct culverts:

Giong Tre, Cai La, Tham Ron and Giach Rong.

Soil sampling locations Đ10, Đ11, Đ12 are associated with dredging activities of Cai Cai

channel. The remaining soil sampling will be related to dredging activities of the

channels including: Thong Nhat, Tan Cong Chanh anh Khang Chien.

Page 36: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

65

Concentration of Cu, Zn, Pb, As and Cd achieves allowable limit of QCVN03-

MT:2015/BTNMT– National technical regulations on heavy metal limit in soil.

C. Subproject “Embankment erosion control in Thuong Thoi Tien Town. Hong Ngu

District, Dong Thap Province”

Figure 7: Map of air sampling – Dong Thap Muoi subproject (Plain of Reeds)

Note:

Air sample Groundwater sample

Surface sample Soil/mud sample

➢ Air environment

Air sampling locations are linked with material transport routes, construction area of Cai

Cai channel, the Plain of Reeds subproject.

Analysis results show that air environmental quality in project area is good, all

parameters represent air environment and vibration in construction area of project

achieve allowable limit QCVN05:013/BTNMT– National technical regulation on noise,

QCVN 26:2010/BTNMT National Technical Regulation on noise and

QCVN27:2010/BTNMT– National technical regulation on vibration.

The analysis results show that mitigation measures of dust, noise have been carried out

well thereby mitigating negative impacts of dust, noise to the air environment.

➢ Surface water quality

Air sampling locations are linked with construction area of Thuong Thoi Tien

embankment and road (along Tien riverbank).

K1

K2

K3

M1

M2

M3

M4

B1

B2

N1

N2

Page 37: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

66

Surface water quality along embankment system applied QCVN08-MT:2015/BTNMT –

National technical regulation surface water (column A2: should apply appropriate

techiques before using for living purpose and water supply) at 04 monitoring locations:

first point of embankment system (M1)., Ngang wharf (M2), Tan Chau ferry terminal

(M3) and final point of embankment system (M4). Specifically:

Parameters such pH, heavy metal, oil and grease are in allowabe limit according to

QCVN08-MT:2015/BTNMT. Tien river water along construction area has signs of a

slight organic pollution with parameter COD at 04 sampling locations exceeds QCVN

from 1.01 to 1.12 times. BOD5 of samples M1, M2, M3 exceeds QCVN08-

MT:2015/BTNMT column A2 from 1.01 to 1.18 times. Water source in those places has

signs of microbiological pollutiom. Parameter Coliform in ¾ the number of samples

exceeds QCVN from 1.1 to 2.2 times. Analysis results show that surface water resource

is polluted by organic matters. Organic pollution is arised by daily acitivities of people

along Tan Chau ferry, Ngang wharf not completely caused by construction activities. The

analysis results aslo show that there is no significant decrease of concentration of

pollutants compared to which mentioned in Quarter IV, 2017.

➢ Ground water quality

Soil sampling locations are linked with construction area of Thuong Thoi Tien

embankment and road (along Tien riverbank)

Based on analysis result and QCVN03-MT:2015/BTNMT – National technical regulation

on heavy metal limit in soil shows that:

Concentration of some heavy metals such as Zn, Pb, As, Cd is not exceed and in

allowable limits. Gathering construction materials wouldn’t cause the increase of soil

environment pollution.

➢ Soil environment

Soil sampling locations Đ10, Đ11, Đ12 are linked with dredging activities of Cai Cai

channel. Remaining soil sampling locations are going to link with dredging activities of

channels: Thong Nhat, Tan Cong Chanh and Khang Chien.

Analysis result shows that all parameters analyzed achieve allowable limit QCVN 03-

MT:2015/BTNMT – National technical regulation on heavy metal limit in soil. Gathering

dredging mud at disposal site on construction site does not cause ambient environmental

pollution

D. Subproject: “Improvement and upgrading irrigation channels and supply

irrigation water for Plain of Reeds”

➢ Air environment

Page 38: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

67

Figure 8: Map of air sampling – Dong Thap Muoi subproject (Plain of Reeds)

Air sampling locations are linked with material transport routes, construction area of Cai

Cai channel, the Plain of Reeds subproject.

Analysis results show that air environmental quality in project area is good, all

parameters represent air environment and vibration in construction area of project

achieve allowable limit QCVN05:013/BTNMT– National technical regulation on noise,

QCVN 26:2010/BTNMT National Technical Regulation on noise and

QCVN27:2010/BTNMT– National technical regulation on vibration. The analysis results

show that mitigation measures of dust, noise have been carried out well thereby

mitigating negative impacts of dust, noise to the air environment.

➢ Surface water quality

K1

K3

K2

Page 39: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

68

Figure 9: Map of surface water sampling - Dong Thap Muoi subproject (Plain of

Reeds)

Air sampling locations are linked with material transport routes, construction area of Cai

Cai channel, the Plain of Reeds subproject.

Analysis results show that, surface water samples of 4 channels have polluted by

microorganisms, demand of biological oxygen also exceeds allowable limits according to

QCVN08-MT:2015/BTNMT National technical regulation surface water, column A2:

should apply appropriate techiques before using for living purpose and water supply.

Parameters such as heavy metal, oil and grease, NH4+ are within allowable limits

according to QCVN08-MT:2015/BTNMT, column A2.

Parameter NO2- of samples M6, M9 and M11 exceeds allowable limit from 1,12 to 4

times according to QCVN08-MT:2015/BTNMT, column A2.

Parameter BOD5 of the samples M1, M5, M6, M7, M8, M9, M10, M11, M12, M13 and

M14 exceeds allowable limit from 1.01 to 1.18 times according to QCVN08-

MT:2015/BTNMT, column A2.

Parameter PO43- of the samples M1, M2, M4, M8, M9 and M11 exceeds allowable limit

from 1.25 to 1.65 times according to QCVN08-MT:2015/BTNMT, column A2.

Parameter Coliform of the samples M1, M2, M3, M4, M5, M6, M7, M8, M10, M11,

M12 and M14 exceeds allowable limit from 1,09 to 3,1 times according to QCVN08-

MT:2015/BTNMT, column A2.

Surface water pollution could be arised by daily activities of people along channels such

as discharging domestic wastewater, waterway traffic activities. However, there is no a

significant change on water quality of channel before construction. It can be understood

as mitigation measures of surface water pollution have been carried out fairly good by

contractor.

➢ Ground water quality

Figure 10: Map of ground water sampling – Dong Thap Muoi subproject (Plain of

Reeds)

Page 40: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

69

Ground water sampling locations are is to determine how influence levels of construction

activties affect ground water quality.

Analysis result of groundwater of 08 drilling wells shows that groundwater quality is

polluted by parameter Coliform, which exceeds allowable limit from 1.3 to 2.33 times

according to QCVN09-MT:2015/BTNMT – National technical regulation on

groundwater quality. Parameter COD exceeds allowable limit from 1.1 to 3.75 times.

➢ Soil environment

Figure 11: Map of mud/soil sampling – Dong Thap Muoi subproject (Plain of Reeds)

Soil sampling locations Đ10, Đ11, Đ12 are linked with dredging activities of Cai Cai

channel. Remaining soil sampling locations are going to link with dredging activities of

channels: Thong Nhat, Tan Cong Chanh and Khang Chien.

Analysis result shows that all parameters analyzed achieve allowable limit QCVN 03-

MT:2015/BTNMT – National technical regulation on heavy metal limit in soil. Gathering

dredging mud at disposal site on construction site does not cause ambient environmental

pollution

6. PUBLIC CONSULTATION, GRIEVANCE REDRESS MECHANISM

6.1. Public consultation and EMP information dissemination

Public consultation and EMP information dissemination for each subporject has been

carried out for 10/July – 23/October/2013.

During on-site monitoring period, independent environmental monitoring consultant

(IEMC) also consults some opinion on environmental issues of people in project

construction process

6. PUBLIC CONSULTATION, GRIEVANCE REDRESS MECHANISM

6.1. Public consultation and EMP information dissemination

Public consultation and EMP information dissemination for each subporject has been

carried out for 6/November – 13/November/2017.

Page 41: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

70

During on-site monitoring period, independent environmental monitoring consultant

(IEMC) also consults some opinion on environmental issues of people in project

construction process

No Project People’s opinion Mitigation measure

1 Upgrading saline

control system of

Go Cong region,

Tien Giang

province

Nguyen Van Con sewer

Spraying water to reduce dust has

been performed well by

construction contractor

CSC, PMU should

supervise tightly

environmental

sanitation ensuring of

contractors

Son Quy sewer

During the last time, contractor

mainly carried out pile driving,

number of transport vehiles is

decreased so it doesn’t affect too

much people’s living activities

Saliset sewer

Currently, construction site of

Saliset sewer is under rainy season

therefore, dust arised by

construction activities isn’t much

- Workers complied with

regulations set up by contractor

2 Construction of

flood control

system in Ba Rai

– Phu An region,

Tien Giang

province

- Local people are welcome and

willing to support project.

Construction of river embankment

will improve people’s living

environment as well as landscape

- Fence and warning lights must be

set up on construction site in night-

time in order to ensure people’s

safety

- CSC, PMU should

supervise tightly

environmental

mitigation measures of

the contractor

- Contractor must

repair fence

surrounding

construction site to

ensure people’s safety

3 Improvement and

upgrading

irrigation channels

and supply

irrigation water

for Plain of Reeds

region

Cai Cai channel

- Environmental protection

measures have been carried out well

by contractor. Currently, there

haven’t any environmental issues

affecting people’s life

- Workers complied with

CSC, PMU should

supervise tightly

environmental

sanitation ensuring of

contractors

Page 42: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

71

regulations set up by contractor

6.2. Grievance Redress Mechanism (GRM)

For each subproject, GRM has been already set up to solve people’s complaints.

Specifically:

- On construction site, it has been set up bulletin board with comprehensive information

on subproject, Construction unit, CSC, Investor, Site manager and address, phone

number for Investor communication

- For each subproject, PPMU has already assigned its staff, who always show up on

construction site accompanying with CSC’s staff and Site manager.

- If occurring any complaints, people are able to directly contact with Site manager, CSC

and PMU’s representative through phone number mentioned above. On the other hand,

people can propose their complaints on environmental issues on construction site for

resolving, overcoming and compensation.

- If two parties could not make a deal, people can send their complaints to representative

of Subproject management unit, CSC, Site manager on site or send it to Subproject

management unit’s headquarter. Within one month after receiving complaints, Director

of Subproject management unit will in charge of complaints, apponit staff to reslove

relevant parties including Site manager, representative of Subproject management unit,

CSC and affected people on compensation and overcoming consequences.

- If it is not sastifed, people can pursue their case to the higher level government for

settlement

In 7th monitoring phase 2017, there were some people’s complaints recorded as

following:

1) Bidding package GMS 2.7: Construction of flood control system in Ba Rai –

Phu An region, Tien Giang province

- There are 02 households near construction area of Thong Luu sluice

complained of cracking their housing, however, this issue has already been

addressed by the contractor and no complaints arisen. 2) Bidding package GMS 2.9: Improvement and upgrading irrigation channels,

and supply irrigation water for Plain of Reeds, Dong Thap province

- In construction area of Cell no.3, Thi Son village, Tan Thanh A ward, Tan

Hong district, PMU has received people’s complaints on alum infection in

their paddy farms and aquaculture ponds. On 12 October, 2017, local

authority cooperated with the contractor and affected people for surveying

and identifying causes of the issue. The results show that paddy farms and

aquaculture ponds infected with alumn due to non-regularly checking the

embankment of paddy farm as well as deliberately embankment to change

the flow. Thus, it is considered as not related to the construction unit, the

meeting minutes are attached at Appendix of the report

7. INSTITUTIONAL STRENGTHENING AND TRAINING

Environmental monitoring and training program for CSC and contractors

IEMC found that environmental sanitation issues on construction site have not been

addressed by contactors and CSC and weekly monitoring forms have not updated

Page 43: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

72

regurlarly. For 5 November to 13 November, 2017, IEMC group has visited to

contractor’s head offices to performe training on 3nd environmental monitoring with

participation of Investor, CSC and contractors. The main contents of environmental

monitoring and training class included:

- Representative of PMU’s leader made a speech, introduced about the project,

project’s implementation and progress as well as stated the reason of traning

course.

- Consultant gave environmental monitoring documents to CSC, contractors and

presented the content of environmenta monitoring and training program

- Beside, consultant also guided on how to use environmental monitoring form and

schedule to submit it to PMU

Comments and results obtained:

Consultant explained clearly objectives, contentson environmental protection and

management measures to CSC and contractors as well as remind them to comply with

management measures, environmental protection during project construction phase.

During construction process, contractors and CSCS will coordinate with PMU to control

the implementation of environmental minimization measure tighly and will be

respobsible to overcome environmental issues arise.

PMU’s hot line has provided already to strengthen effectiveness of risk control,

environmental incidents and collects information, environmental pollution issues arising

during project implementation.

8. KEY ENVIRONMENTAL ISSUE

Page 44: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

60

Table 6: Site Status and Key Issues Identified, Actions Taken, Additional Action Required for Each Construction Item

No Items Name of

contractor

Environmental

outstanding

issues

Mitigation

measures

Responsibil

ity should

be carried

out

Period for

overcomin

g

consequen

ces

Status images

I Biding packages GMS – 2.6: Subproject “Upgrading saline control system of Go Cong region. Tien Giang province”

1 Nguyen

Van

Con

sewer

Construction

contractor:

Tien Giang

construction

and investment

JS company

CSC:

Infrastructure

development

and

construction

consulting JS

company

- Workers have

non- regularly

used labor

protective

equipment.

Remind

workers for

using labor

protective

equipment

CSC,

contractor

3 days

Page 45: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

61

2 Salisete

sewer

Construction

contractor:

Tien Giang

construction

and investment

JS company

CSC:

Infrastructure

development

and

construction

consulting JS

company

Transport

vehicles haven’t

been cleaned

before going out

construction site

Set up

vehicle

cleaning

station on site

CSC,

contractor

Immediatel

y

3 Son

Quy

sewer

Construction

contractor:

East Asia

international

corporation

CSC:

Infrastructure

development

and

construction

consulting JS

company

Workers have

not regularly

used labor

protective

equipment.

Remind

workers for

using labor

protective

equipment

CSC,

contractor

3 days

Page 46: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

62

- IEMC team

saw a streak of

spilling oil on

the river near

the crane hull

- Contractor

should set up

floats around

the crane hull

to avoid

spilling oil

CSC,

contractor

One week

II. Bidding package GSM 2.7: the subproject “Construction of flood control system in Ba Rai – Phu An region, Tien Giang province

1 30 June

sewer

Construction

contractor:

Hai Duong

dyke and rural

development

joint stock

company

CSC: Bac Viet

Consulting and

Construction

JSC

No

environmental

outstanding

arisen

- - -

Page 47: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

63

2 Ca

Chat

sewer

Construction

contractor:

Huynh Ngoc

commercial

investment and

construction JS

company

CSC: Bac Viet

Consulting and

Construction

JSC

Completely

finish

construction of

sewer wall.

Worker are

waiting for the

next item

construction to

so no

environmental

issues arisen

Contractor

and CSC

should

continuously

supervise

environmenta

l issues for

the next

construction

activities

CSC,

contractor

Before

implementi

ng the next

construction

activity.

3 Ca Nua

sewer

Construction

contractor:

Hai Duong

dyke and rural

development

joint stock

company

CSC: Center

for scientific

and technical

irrigation

deployment

Completely

address odour

by the

construction of

open-air sewer

and existing

channel

Contractor

should carry

out specific

measures,

especially not

changing oil

on

construction

site

- Covering up

channbel

bank with

nylon

CSC,

contractor

Before

implementi

ng the next

construction

activity.

Page 48: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

64

4 Ong

Ban

sewer

Construction

contractor:

Huynh Ngoc

Trading

Construction

Investment

Joint Stock

Company

CSC: Center

for Scientific

and

Technological

Irrigation

Implementatio

n

Completely

finish

construction of

sewer wall.

Worker are

waiting for the

next item

construction to

so no

environmental

issues arisen

Contractor

and CSC

should

continuously

supervise

environmenta

l issues for

the next

construction

activities

CSC,

contractor

Before

implementi

ng the next

construction

activity.

5 Tham

Rom

sewer

Construction

contractor:

Huynh Ngoc

Trading

Construction

Investment

Joint Stock

Company

CSC: Center

for Scientific

and

Technological

Irrigation

Implementatio

n

- Completed pile

driving

- Contractor has

not implemented

next

construction

activities so no

environmental

issues arisen

Contractor

and CSC

should

continuously

supervise

environmenta

l issues for

the next

construction

activities

CSC,

contractor

Before

implementi

ng the next

construction

activity.

Page 49: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

65

6 Ong

Kham

sewer

Construction

contractor:

Huynh Ngoc

Trading

Construction

Investment

Joint Stock

Company

CSC: Center

for Scientific

and

Technological

Irrigation

Implementatio

n

No vehicle

cleaning station

set up on

construction site

- Set up

vehicle

cleaning

station on site

CSC,

contractor

3 days

7 Thay

Thanh

sewer

Construction

contractor:

Hai Duong

dyke and rural

development

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Cement bags

and oil tanks

must be

collected

appropriately,

do not litter

indiscriminately

on construction

site

Remind

workers for

cleaning up

construction

site at the end

of each day

CSC,

contractor

Before

implementi

ng the next

construction

activity.

Page 50: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

66

8 Ba Gon

sewer

Construction

contractor:

VN Industrial

Group Joint

Stock

Company

CSC: Center

for Scientific

and

Technological

Irrigation

Implementatio

n

Fence has been

set up on site

near traffic road

however, it was

fairly sketchy

Contractor

should set

up

corrugated-

iron sheets

and install

night

lighting

system at

area with

deep pits in

order to

warn traffic

participants

CSC,

contractor

Set up

quickly

9 Hai

Hue

sewer

Construction

contractor:

Huynh Ngoc

Trading

Construction

Investment

Joint Stock

Company

CSC: Center

for Scientific

and

Technological

Irrigation

Implementatio

Fence has not

been set up on

site, especially

at material

gathering areas

It is

necessary to

set up fence

and warning

signs near

traffic road

CSC,

Contractor

Immediatel

y

Page 51: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

67

n

10 Khang

Chien

sewer

Construction

contractor:

Huynh Ngoc

Trading

Construction

Investment

Joint Stock

Company

CSC: Center

for Scientific

and

Technological

Irrigation

Implementatio

n

Contractor has

not set up speed

limit signs and

bulletin board at

the detour near

construction site

Fence up the

area with deep

pits

It is

necessary to

set up two

kinds of sings

CSC,

Contractor

Immediatel

y

11 Cay

Sung

sewer

Construction

contractor:

Hai Duong

dyke and rural

development

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Completed

construction of

Cay Sung

sewer

Prepare to

asphalt the

road on sewer

CSC and

contractor

should

address

environmenta

l sanitation

issues on

construction

site

CSC,

Contractor

Upcoming

time

Page 52: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

68

12

Cai La

sewer

Construction

contractor:

Hai Duong

dyke and rural

development

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Sometime,

workers did not

use labor

protective

equipment

Remind

workers for

using labor

protective

equipment

CSC,

contractor

After

implementi

ng the next

construction

activity.

Wires and

sockets made

sketchy

CSC should

remind

workers for

carrying out

electricial

safety

measures

CSC Immediatel

y

Page 53: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

69

13 Giong

Tre 2

sewer

Construction

contractor:

Huynh Ngoc

Trading

Construction

Investment

Joint Stock

Company

CSC: Center

for Scientific

and

Technological

Irrigation

Implementatio

n

Speed limit

signs have been

set up on

construction site

near DT864

road

In monitoring

phase, no

environmental

issues arisen

CSC,

Contractor

14 Dong

Sau Ca

Nua

sewer

Construction

contractor:

VNI group JS

company

CSC: Center

for Scientific

and

Technological

Irrigation

Implementatio

n

- It is hard to

access

construction site

- There were

many

households

living around

construction site

however,

contractor didn’t

set up the

retaining wall or

corrugated

sheets to reduce

dust

Contractor

should set up

the retaining

wall or

corrugated-

iron sheets

with 2m of

height

CSC,

Contractor

3 days

Page 54: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

70

15 Bo Keo

sewer

Construction

contractor:

VNI group JS

company

CSC: Center

for Scientific

and

Technological

Irrigation

Implementatio

n

Item has not

performed

construction

activities

- - -

16 Thong

Luu

sewer

Construction

contractor:

40

construction

and investment

joint stock

company

CSC: Bac Viet

Consulting and

Construction

02 households

were cracked its

wall and floor

Contractor

compensated

an amount of

cement to fix

people's

housing's

wall and

floor. It has

no longer

complaints

CSC,

Contractor

Restate

damaged

works after

construction

completed

Page 55: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

71

Under

construction of

road on sewer.

Construction

vehicles should

be cleaned up

before going out

construction site

Set up

vehicle

cleaning

station on site

CSC,

contractor

This issue

has been

reminded

many times

by IEMC

team but

contractor

has not

implemente

d

17 Ap 2

sewer

Construction

contractor:

40

construction

and investment

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Waste soil have

not been

collected

No bulletin

boards set up on

site

Set up

bulletin

boards on site

Gather waste

soil at

designate

area and

fence up for

protecting

and reusing

kind of waste

Not yet due Not yet due

Page 56: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

72

18 Rach

Giong

sewer

Construction

contractor:

40

construction

and investment

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Under

construction of

sewer gate

No

environmental

issues arisen

CSC and

contractor

should

continuousl

y supervise

construction

site

CSC,

contracor

19 Ghenh

Lang

sewer

Construction

contractor:

40

construction

and investment

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Item has been

already

completed

Page 57: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

73

20 Rach

Giong

Ba So

sewer

Construction

contractor:

40

construction

and investment

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Item is being

suspended

construction

activities

In monitoring

phase, no

environmental

issues arisen

CSC and

contractor

should

continuousl

y supervise

item when it

commences

again

CSC,

contracor

After

implementi

ng the next

construction

activity

21 Dap

Chua

sewer

Construction

contractor:

40

construction

and investment

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Fence has been

set up at

construction site

near traffic road

but it was fairly

sketchy

Rebuilding

fence

CSC,

contracor

3 days

Page 58: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

74

22 Cay Me

sewer

Construction

contractor:

40

construction

and investment

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Item is being

suspended

construction

activities

In monitoring

phase, no

environmental

issues arisen

CSC and

contractor

should

continuousl

y supervise

item when it

commences

again

CSC,

contracor

After

implementi

ng the next

construction

activity

23 Giong

Tre 1

sewer

Construction

contractor:

Huynh Ngoc

Trading

Construction

Investment

Joint Stock

Company

CSC: Center

for Scientific

and

Technological

Irrigation

Implementatio

n

Item is being

suspended

construction

activities

In monitoring

phase, no

environmental

issues arisen

CSC and

contractor

should

continuousl

y supervise

item when it

commences

again

CSC,

contracor

After

implementi

ng the next

construction

activity

Page 59: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

75

24 Lo Hoa

Thuong

sewer

Construction

contractor:

VNI group JS

company

CSC: Center

for Scientific

and

Technological

Irrigation

Implementatio

n

No temporary

access road set

up, affect

people’s

movement

Contractor

must set up

temporary

access road

for people

Contractor,

CSC

2 weeks

25 Khach

Minh

sewer

Construction

contractor:

40

construction

and investment

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Item has been

already

completed

- - -

Page 60: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

76

26 Lo

Lang

sewer

Construction

contractor:

40

construction

and investment

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Item is being

suspended

construction

activities

In monitoring

phase, no

environmental

issues arisen

CSC and

contractor

should

continuously

supervise

item when it

commences

again

CSC,

contracor

After

implementi

ng the next

construction

activity

27 Kenh

Dung

sewer

Construction

contractor:

40

construction

and investment

joint stock

company

CSC: Bac Viet

Consulting and

Construction

- Workers did

not use labor

protective

equipment

- No speed limit

signs set up

- No fire

extinguisher

arranged at

workers camps

- Waste oil

hasn’t been

collected as

regulations

mentioned in

EMP

Moving

barrels of

waste oil to

warehouse

CSC,

contracor

Immediatel

y

Page 61: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

77

28 Hai

Lim

sewer

Construction

contractor:

40

construction

and investment

joint stock

company

CSC: Bac Viet

Consulting and

Construction

Item has not

been

implemented

construction

- - -

SIII. Bidding packages ICB GMS – 2.8: Subproject “Embankment erosion control in Thuong Thoi Tien Town. Hong Ngu District. Dong Thap

Province”

(The construction was completed)

IV. GMS 2.9: Improvement and upgrading irrigation channels and supply irrigation water for Plain of Reeds, Dong Thap province

1 Mud

dredgin

g Cai

Cai

channel

into

Cell no

1,3,4

and

constru

cting

Ca

Construction

contractor:

Association

with Bao

Chung JS

company and

Petroleum

Construction

Joint Stock

Company and

Hong Truong

Limited

Lack of fairway

buoy during

construction on

river (Bau Lut

bridge, Ca Chap

2 bridge, Ca

Chap 3 bridge)

Set up

fairway buoy

near

construction

area

Contractor,

CSC

One day for

preparation

Page 62: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

78

Chap 2

bridge

Liability

Company;

CSC:

Infrastructure

development

and

construction

consulting JS

company

Fencing up

disposal site of

soil/mud is

fairly sketchy

Prepare

warning

signs,

reinforce

fence at

disposal site

of soild/mud

Contractor,

CSC

One day for

preparation

Page 63: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

79

2 Mud

dredgin

g the

Cai Cai

channel

into

Cell no

2

Construction

contractor:

CSC:

Infrastructure

development

and

construction

consulting JS

company

Top of

embankment is

lower than

original design

(3m at elevation

+6m)

- Currently,

Huyen Minh

contractor are

using canvas to

cover

embankment

- Adjust top of

embankment to

match with

original design

Rebuild top

of

embankment

in line with

original

design

PMU,

Contractor,

CSC

Carry out

immediately

constructed

discharge gate is

not matched

with the original

design

(discharge water

throughout

pipeline)

Prepare

warning

signs,

reinforce

fence at

disposal site

of soild/mud

Contractor,

CSC

One day for

preparation

Page 64: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

61

9. CONCLUSION AND RECOMMENDATION

9.1. Overall Progress of Implementation of Environmental Management Measures

- The contractors have carried out environmental minimization measures however it

still have had shortcomings. Contractor should follow environmental minimization

measures, which mentioned in environmental management plan (EMP). Environmental

impact assessment and environmental monitoring documents of the Project also were sent

to contractors and CSC thereby strengthening environmental management plan as well as

minimization measures.

- The bidding package GMS 2.6 and 2.7: Contractors and CSC have paid attention

to adjust mitigation measures as menioned in EMP. Contractors have implemented

mitigation measures of dust, however, it is necessary to set up vehicle cleaning

stations on site.

- The bidding package ICB GMS 2.8: Construction almost completed so no

environmental issues arisen in monitoring phase

- The bidding package GMS 2.9: Huyen Minh contractor constructed Cell no.2 not

match with original design. Huyen Minh contractor must quickly implement

corrective measures before conducting next construction activities in order to

ensure communities’ safety as well as preventing the collapse of Cell no.2

- CSC’s periodically environmental monitoring reports have not submitted on

schedule

9.2. Action Recommended

- PMU, CSC and IEMC will continually coordinate construction monitoring and

environmental management. CSC and contractors should follow EMP to carry out

environmental minimization measures on site better.

- Recommends CSC carrying out seriously environmental monioring forms and

submits these forms to the staff of PMU for the preparation of plans to promtly solve

environmental issues as well as incidents.

- Recommends CSC and contractor maintaining and ensuring fully workers’ safety

condition such as camps. labor protective gears. medical kit on site. etc… subproject

PMU should supervise. check and remind contractors to implement those safety

condtions.

- IEMC will conduct environmental monitoring in January, 2018.

Page 65: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

60

APPENDICES

Appendix 1 – Some on-site pictures in environmental monitoring 2017

No Đồng Tháp

Cai Cai Channel

Cell no.1

Cell no.2

Cell no.4

Cell no.3

Cầu Cả Chấp 2

Thuyền nạo vét sông

Long Son Ngoc bridge Bau Lut

Gò Công - Tiền Giang

Nguyen Van Con sewer

Page 66: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

61

Saliset sewer

Sơn Quy sewer

Page 67: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

62

Ba Rài Phú An - Tiền Giang

1 Hai Lim sewer

2 Kênh Đứng sewer

3 Lộ Làng sewer

Page 68: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

63

4 Khách Minh sewer

5 Lộ Hòa Thượng sewer

6 Giồng Tre 1 sewer

7 Cây Me sewer

Page 69: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

64

8 Đập Chùa sewer

9 Cống Rạch Giồng Ba Sở

10 Ghềnh Làng sewer

Page 70: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

65

11 Cống Rạch Giồng

12 Ấp 2 sewer

13 Thông Lưu sewer

14 Bờ Keo sewer

15 Đồng Sau Cả Nứa sewer

Page 71: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

66

16 Giồng Tre 2 sewer

17 Cái Lá sewer

18 Cây Sung sewer

Page 72: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

67

19 Kháng Chiến sewer

20 Hai Huệ sewer

21 Ba Gòn sewer

22 Thầy Thanh sewer

Page 73: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

68

23 Ông Khậm sewer

24 Thâm Rôm sewer

25 Ông Bản sewer

Page 74: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

69

26 Cả Nứa sewer

27 Cả Chát sewer

28 30/6 sewer

Page 75: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

70

Page 76: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

71

Appendix 2 – Analysis result

Page 77: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

72

Appendix 3 – Environmental monitoring form

Page 78: Environmental Monitoring Report€¦ · bridges (Long Son Ngoc, Ca Cap 2, Ca Chap 3, dredging Cai Cai channel and pumping mud into Cell no 1,3,4). - Huyen Minh company are constructing

Bidding packageGMS – 4.10: IEMC Second Semi-Annual Report 2017

Project: Greater Mekong subregion flood and drought risk management and mitigation (ADB-GSM1)

60

Appendix 4 – Circulars on environmental monitoring

- Circular 28/2011/TT-BTNMT regulated on technical process for monitoring ambient air

environment and noisedated 01/August/2011;

- Circular 29/2011/TT-BTNMT regulated on technical process for monitoring continental

surface waterđịa dated 01/August/2011;

-Circular 30/2011/TT –BTNMT regulated on technical process for monitoring groundwater

dated 01/August/2011;

- Circular 33/2011/TT-BTNMT regulated on technical process for monitoring soil dated

01/August/2011;