environmental seminar: managing environmental issues in construction projects

23
Environmental seminar: Managing environmental issues in construction projects Presented by: Karen Groulx 23 April 2015 Dentons Canada LLP

Upload: dentons

Post on 15-Jul-2015

128 views

Category:

Environment


0 download

TRANSCRIPT

Environmental seminar:

Managing environmental issues in

construction projects

Presented by: Karen Groulx

23 April 2015

Dentons Canada LLP

Fact pattern: what should happen

• Shoebox retains Geotech consultant

to prepare soils report, incorporated

into Tender Documents

• Tender Documents provided to

BossCo

• Soils report alerts BossCo about

PAHs and metals

• BossCo incorporates necessary

remediation work into bid

• BossCo – Digger subcontract

accounts for remediation

Shoebox

BossCo

Digger

23 April 2015

2

Fact pattern: what went wrong - missing information

• Developer must disclose all relevant information about site conditions

• If tender documents exclude information:

• Withheld information may give rise to contractual liability - extras and delays

• Developer/consultant may be liable for negligent misrepresentation

• GC may be held contributorily negligent for failing to inquire or investigate

23 April 2015

3

What can happen?

Consider 2 cases:

• Brown and Huston Ltd. v York (Borough), 1983 CarswellOnt 743 (ONHC),

confirmed by 1985 OJ No 211 (ONCA)

• Advice Pipelines Ltd. v Mississauga Golf and Country Club Ltd., 1989 CLD 723

(ONHC)

4

23 April 2015

Brown and Huston Ltd. v York (Borough)

Facts

• Brown successfully tendered to

construct an underground pumping

station for the City.

• Tender docs prepared by Fenco, omitted

soils report and some information about

ground water levels.

• Brown chose construction method that

proved to be inappropriate in light of the

actual ground water level encountered.

• Brown sued City and Fenco for

negligent misrepresentation.

The City of York (owner)

FencoConsultants (consultant)

Geocon(soils)

Peto MacCallum(soils)

Brown and Huston Ltd. (GC)

23 April 2015

5

Brown and Huston Ltd. v York (Borough)

Held

• Fenco liable for 75%; Brown for

25%.

• Negligent misrepresentation

elements established.

• Brown not aware of the existence of

the water table due to insufficient

information in tender documents.

• Brown contributorily negligent due to

failure to make inquiries at the bid

stage, as required pursuant to

contract with City.

The City of York (owner)

FencoConsultants (consultant)

Geocon(soils)

Peto MacCallum(soils)

Brown and Huston Ltd. (GC)

23 April 2015

6

Advice Pipeline Ltd. v Mississauga Golf Club Ltd.

Facts

• Plaintiff contracted with Defendant City to construct footbridge abutments

• Incorrect information provided by City to bidders in tender documents

• No mention of existing soils reports

• No mention of conservation authority reports

• Water elevation indicated 15ft of land above water line (actual site conditions –

river flooded)

• According to tender documents Plaintiff concluded that earth berm

sufficient to keep abutments dry

• During construction berm collapsed and Plaintiff forced to rebuild using

other methods

• Plaintiff alleged negligent misrepresentation

• City argued that Plaintiff failed to inquire or investigate

23 April 2015

7

Advice Pipeline Ltd. v Mississauga Golf Club Ltd.

Held

• Plaintiff awarded full damages

• Plaintiff under no obligation to investigate or verify information provided

by the City

• City made negligent omissions in tender documents

• Tender documents interpreted against the City (as the drafter)

23 April 2015

8

Lessons from Brown and Advice

• Contractor’s duty to investigate:

• In both cases, contract required GC to satisfy itself by personal examination as

to the local conditions or that it accepted the risk of not doing so.

• Provisions interpreted strictly against the owner.

• Contractor’s duty to inquire:

• In Brown, incorrect information in tender documents should have given rise to

inquiry by contractor.

• In Advice, information about the water level was precise and appeared

accurate and so there was no duty to inquire.

“…there is nothing in the practice of the trade which leads me to conclude that the plaintiff

would investigate the information supplied by the defendant to verify its accuracy.” (para 77)

23 April 2015

9

Fact Pattern: What likely went wrong

• Shoebox had no knowledge of hydro-carbons and metals in soil

• How does Shoebox protect itself from potential liability?

• Shoebox provides BossCo opportunity to inspect site and satisfy itself as

to conditions

• Opportunity to inspect must be reasonable

• Must provide access to conduct necessary testing

• Parties use CCDC2 contract provisions addressing unknown site

conditions

• General Conditions may be amended by Supplementary Conditions

23 April 2015

10

It is all about Risk Allocation

• A contract which fails to provide equitable risk sharing may lead to

additional disputes

“There is no doubt that this contract, drawn as it was to protect taxpayers,

attempted to limit the liability of the City to such an extent that one would expect

that not even the ordered rotation of the seasons could be reasonably anticipated

by the contractor. The problem with contracts such as these is that they are so

rigid and so restricting that the parties tend to amend them by their actions during

the course of the contract.”

Colautti Construction Ltd. v Ottawa (City) (1984), 46 OR (2d) 236 (CA) at 242

23 April 2015

11

The importance of construction contracts

23 April 2015

12

• Given the importance of construction contracts, it is surprising that the

parties often place so little time and emphasis on these important

documents which can serve to limit the source of most of their liability

exposure.

Standard Construction Risks

23 April 2015

13

• errors and/or omissions in the contract documents - scope of

work issues

• geotechnical and other unanticipated site conditions

• changes in contract scope

• delays/scheduling issues

• deficient work

• insolvent contractors and/or subcontractors

• adverse weather conditions

• force majeure events

• negligent construction and/or design work

Unanticipated/Unknown Site Conditions

23 April 2015

14

• When is it appropriate for risk to be shared?

• Who has best knowledge of project site?

• What studies have been performed?

• What information is available at the time of contract formation?

• Does the contractor have an obligation and/or opportunity to inspect?

• What is the nature of project?

• Typically, the contractor will allocate risk of design errors to the owner,

who retained the architect and therefore is in a better position to

address and minimize these losses.

Unanticipated/Unknown Site Conditions

23 April 2015

15

CCDC 2-2008 – GC 6.4 – Concealed or Unknown Conditions

• If either party discovers “subsurface or otherwise concealed

conditions” that existed prior to the commencement of the work

or physical conditions that are materially different than what

would be expected and are not contemplated by the Contract

Documents:

• Obligation to give notice to the other party before the conditions are disturbed

and within five working days.

• If there are conditions that differ materially and impact cost or

time, a Change Order or Change Directive will be issued.

• If there is no material difference, the Consultant will provide a

report explaining same.

Unanticipated/Unknown Site Conditions

23 April 2015

16

Alternative Language seen in Customized Contracts

• Inspection of site

• Review of contract documents, geotechnical and other reports

• Opportunity to ask questions at pre-construction meetings

• Contractor assumes responsibility for all risk associated with

unanticipated conditions

When Problem Discovered: What does the contract say?

• General Conditions of CCDC2 Stipulated Price Contract

• GC9.2: Toxic and Hazardous Substances9.2.2: Prior to the Contractor commencing the Work, the Owner shall:

.1 take all reasonable steps to determine whether Toxic or Hazardous Substances are present at the Place of the

Work; and

.2 provide the Consultant and the Contractor with a written list of any such substances that are known to exist and

their locations.

9.2.4: Unless the Contract expressly provides otherwise, the Owner shall be responsible for taking all

necessary steps, in accordance with applicable legislation in force at the Place of the Work, to dispose

of, store or otherwise render harmless, Toxic or Hazardous Substances which are present at the Place

of the Work prior to the Contractor commencing the Work.

9.2.7: If the Owner and the Contractor agree or if the expert referred to in paragraph 9.2.6 determines

that the Toxic or Hazardous substances were not brought onto the Place of Work by the Contractor,

the Owner shall promptly, at the Owner's own expense:

(1) take all steps as required under paragraph 9.2.4;

(2) reimburse the Contractor for the cost all of steps taken pursuant to 9.2.5

(3) extend the Contract Time for such reasonable time as the Consultant may recommend in consultation with the

Contractor and the expert referred to in 9.2.6. and reimburse the Contractor for reasonable costs incurred as a result

of the delay.

23 April 2015

17

When Problem Discovered: What do the specs say?

Specifications: Site Work, Demolition and Removal (sample):

• Section 3.3 - DISPOSAL OF CONTAMINATED EARTH

Scope of Work

.1 In the event of contaminated soil being found, the scope of work for the above item shall include all

work required to load contaminated earth and transport it to a licensed land facility, in accordance

OPSS180 and applicable Provincial Regulations

.2 Tested positive contaminated soils must be removed offsite and disposed at an approved landfill.

Basis of payment

.1 Contractor to provide 3 quotes to the Consultant for disposal of contaminated soil to an approved

facility. Payment will be made under the Inspection and Testing cash allowance and only the consultant

can award the disposal Work to the appropriate sub-contractor.

• Section 3.4 GEOTECHNICAL & ENVIRONMENTAL TESTING

Scope of Work

.1 Geotechnical, soils, granular, asphalt and concrete and environmental (soils contamination and

groundwater) testing shall be carried out by the geotechnical, consultant selected by the Consultant.

.2 Any on-site soils encountered by the Contractor that are suspected as being contaminated shall be

brought to the attention of the Consultant for testing, prior to its removal from the site.

Basis of Payment

.1 Contractor to provide 3 quotes for Geotechnical and Environmental Testing Work to Consultant. The

Consultant shall determine the approved quotation.

23 April 2015

18

When Problem Discovered: Provide Written Notice

• Failure to provide notice of delay or claims for extras may preclude GC

from recovering additional compensation

• Technicore Underground Inc. v Toronto (City), 2012 ONCA 597

• The City of Toronto (the “City”) entered into a contract with Clearway

Construction Inc. (“Clearway”) to construct a water main.

• Clearway subcontracted the underground tunneling to Technicore Underground

Inc. (“Technicore”).

• Large water main burst, flooding the tunnel and delaying the project.

• Technicore claimed against Clearway for damages arising from the flood, and

Clearway claimed against the City for indemnity and its own costs.

• Held: Clearway claim barred due to the operation of a contractual notice

provision requiring claims to be filed “no later than 30 days after completion of

the work affected by the situation.”

23 April 2015

19

…Provide Written Notice

• Waiver of Written Notice provision nearly impossible to establish

• Saskatchewan River Bungalows Ltd. v Maritime Life Assurance Co.,

[1994] 2 SCR 490:

• The Party alleging waiver must furnish evidence that the party allegedly waiving

the contractual term: (a) had full knowledge of its rights, and (b) demonstrated

an unequivocal and conscious intention to abandon them.

• Evidence of a conscious intention to abandon the notice requirement:

Colautti Construction Ltd. v Ottawa (City of), 1984 CanLII 1969 (ONCA)

• The contractor billed the owner for extras and the owner paid them, despite the

absence of written authorization as required under the contract.

23 April 2015

20

Limiting Liability

23 April 2015

21

Sample Clause

• The Contractor declares that in tendering for the work, and in entering into this

Contract, he has either investigated for himself the character of the Work to be

done and all local conditions, including the location of any utility which can be

determined from the records or other information available at the office of any

person, partnership, corporation, including a municipal corporation and any

board or commission thereof having jurisdiction or control over the utility, that

might affect this tender or his acceptance of the Work, or that, not having so

investigated, and accept as hereinafter provided, he is willing to assume and

does hereby assume, all risk of conditions now existing or existing in the course

of the Work which might or could make the Work, or any items thereof more

expensive in character, or onerous to fulfill, than was contemplated or known

when the tender was made or the Contract signed.

Exclusion Clause

• Developer protection from delay

• Wide scope exclusion clause

• Example from Perini Pacific Ltd. v Greater Vancouver Sewage and Drainage

District (No 2), [1967] SCR 189:

“…the Contractor shall have no claim or right of action against the Corporation

(respondent) for damages, costs, expenses, loss of profits or otherwise

howsoever… by reason of any delay in fulfillment of the contract… whether or

not such delay may have resulted from anything done or not done by the

Corporation…”

23 April 2015

22

Presented by: Karen Groulx and Alexei Chinkarenko

[email protected]@dentons.com

23 April 2015

23