environmental & social monitoring report · the environmental management plan (emp) and...

17
Environmental & Social Monitoring Report Project Number: 42378-015 Semi-Annual Report December 2017 2966 BAN(SF): Power System Expansion and Efficiency Improvement Investment Program Prepared by the North-west Power Generation Co. Ltd for the Asian Development Bank.

Upload: others

Post on 23-Mar-2020

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

Environmental & Social Monitoring Report

Project Number: 42378-015 Semi-Annual Report December 2017

2966 BAN(SF): Power System Expansion and Efficiency Improvement Investment Program

Prepared by the North-west Power Generation Co. Ltd for the Asian Development Bank.

Page 2: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

This Environmental & Social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 3: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

1

Environmental and Social Safeguard Monitoring Report Semi Annual (July – December, 2017) Report

Upgradation of Khulna 150 MW to 225 MW

Combined Cycle Power Plant Project

at Khalishpur, Khulna.

North-West Power Generation Co. Ltd.

(NWPGCL)

Page 4: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

2

TABLE OF CONTENTS

Page

Abbreviations

3

Executive Summary 4

1.0 Introduction

1.1 Brief Project Description

5

1.2 Project Progress Status and Implementation Schedule

6

2.0 Compliance to National Regulations

2.1 Environmental Conservation Rules 1997

6-8

3.0 Compliance to Environmental Covenants from the ADB Loan Agreement

8-10

4.0 Compliance to Environmental Management Plan

11

5.0 Air, Noise, Water Monitoring Results

11-14

6.0 Conclusion and Recommendations

14

Page 5: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

3

ABBREVIATIONS

ADB Asian Development Bank

APs Affected Persons

BPDB Bangladesh Power Development Board

DoE Department of Environment

EARF Environmental Assessment and Review Framework

ECA Environmental Conservation Act

ECR Environmental Conservation Rules

EIA Environmental Impact Assessment

EMP Environmental Management Plan

EMoP Environmental Monitoring Plan

ECC Environmental Clearance Certificate

IA Implementing Agency

IUCN International Union for Conservation of Nature

IEE Initial Environmental Examination

MoPEMR Ministry of Power, Energy and Mineral Resources

MFF Multi Financing Facility

PD Project Director

PMO

Project Management Office

PMU

Project Management Unit

SPS

Safeguard Policy Statement

Page 6: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

4

Semi Annual Monitoring Report For Upgradation of Khulna 150 MW to 225 MW Combined Cycle Power

Plant Project (CCPP)

(Khalishpur, Khulna)

Period: Semi-Annual (July - December, 2017) Monitoring: Ambient Air, Water & Noise Quality

Executive Summery

Upgradation of Khulna 150 MW Peaking Power Plant to 225 MW Combined Cycle

Power Plant Project is identified by the Government of Bangladesh (GoB) to proper

utilization of Energy. The executing Agency of the project is the Ministry North-West

Power Generation Co. Ltd. and the implementing Agency is the Ministry of Power,

Energy and Mineral Resources (MoPEMR). Financial assistance is given by the Asian

Development Bank (ADB) under the Tranch 1 of Power System Expansion and

Efficiency Improvement Investment Program.

At present, one 150MW Dual Fuel Peaking Power Plant has been established beside

Khulna Power Station (KPS) complex by NWPGCL. Now, NWPGCL intends to add one

75MW Steam Plant using exhaust gas from 150MW dual fuel power plant to convert this

open cycle power plant into combined cycle power plant to be used as base load power

station with the financial assistance from Asian Development Bank (ADB). In order to

convert this peaking power plant into combined cycle power plant, it has been proposed

to add Heat Recovery Steam Generator, Steam Turbine, 75MW Generator, Power

transformer, cooling system, 45 m long Stack etc. with the peaking power plant to be

located in the existing rental power plant area.

The Environmental Management Plan (EMP) and Environmental Monitoring Plan

(EMoP) are the main practical tools employed during the construction phase to provide

the environmental protection measures. The purpose of the environmental management

plan is to set out clearly the required mitigation measures and allocate responsibility for

each, and to provide additional information to assist in planning and implementing the

various activities.

The Impacts and mitigation for this project fall into two distinct categories, based on the

phase in which the mitigation will be provided and the parties who will take necessary

action. For this reason the EMP as well as EMoP for this project is divided into two

parts. These are as follows:

Page 7: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

5

a) Construction Phase EMP

b) Operation Phase EMP

This report mainly addressed relevant environmental issues and their mitigation

measures for the construction stage of the Project as mentioned in the following item.

Summary of the Environmental compliance during the period of July to December,

2017.

Environmental Mitigation Measures

Compliance Status

Environmental Monitoring program To be prepared as per EIA Report

1.0 Introduction 1.1 Brief Project Description

Power System Expansion and Efficiency Improvement Investment Program is

intended to finance a series of investments via Multi-tranche Financing Facility

(MFF) of Asian Development Bank (ADB). Tranche 1 consist of several

developments projects in Generation, Transmission and Distribution sectors,

including Upgradation of Khulna 150 MW Peaking Power Plant to 225MW

Combined Cycle Power Plant Project.

Upgradation of Khulna 150 MW Peaking Power Plant to 225 MW Combined Cycle

Power Plant Project is identified by the Government of Bangladesh (GoB) to

proper utilization of Energy and reduce the exhaust temperature to release the

atmosphere. The executing Agency of the project is the North-West Power

Generation Co. Ltd. and the implementing Agency is Ministry of Power, Energy

and Mineral Resources (MoPEMR).

Upgradation of Khulna 150 MW Peaking Power Plant to 225MW Combined

Cycle Power Plant has been established in the same Khulna 150 MW Peaking

Power Plant area and Agreeko 40MW Rental Power Plant area by adding 75MW

steam plant with the Khulna150MW Peaking Power Plant. The Khulna 150MW

Peaking Power Plant is already constructed within the existing Goalpara (Khulna

Power Station) complex of BPDB, about 5 KM West of Khulna city. In Goalpara,

there are already several power plants e.g. 110 MW Steam, 60 MW Steam, a 110

MW Independent Power Plant (IPP), KPCL and 40MW Rental Power Plant. The

major components of the plant consisted of a Simple Cycle Gas Turbine with

Generator, Control Room, 132/11kV Power Transformer, 132 KV Switch yard,

Liquid Fuel System, Natural Gas Fuel System, Lubricating System, Cooling

System, Water Treatment Plant, Effluent Treatment Plant and other associated

Page 8: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

6

accessories. The Gas Turbine is initially operate with High Speed Diesel and

then with natural gas if natural gas will be available. In order to convert this

peaking power plant into combined cycle power plant, it has been proposed to add

Heat Recovery Steam Generator, Steam Turbine, 75MW Generator, Power

transformer, cooling system, 45 m long stack etc. with the peaking power plant to

be located in the existing rental power plant area.

1.2 Project Progress Status and Implementation Schedule

A. Progress Status

The updated status of Upgradation of Khulna 150 MW PPP to 225 MW CCPP

Project from July, 2017 to December, 2017 is given below in Table:

Sl. No.

Work Description Status

1. Civil Works: Piling works and superstructure/foundation works for all structures.

Piling works 100% completed. Super structure/foundation works 100% completed

2. Mechanical and Electrical Facilities Consist of -Erection of HRSG, Steam Turbine, Generator, Cooling Tower, CW Pump House and all other BOP Equipments/Components of Power Plant. -Electrical and I&C works with commissioning

-Erection of HRSG 100% - Erection of Steam Turbine, Generator are100% in progress. -Electrical and I&C works completed.

3. Consultancy Services Engineering Consultancy and construction supervision of the Project

-Design works of the project has been completed 100%

2.0 Compliance to National Regulations

The key environment, health & safety and social legislations that are applicable to

the Upgradation of Khulna 150 MW Peaking Power Plant to 225 MW Combined

Cycle Power Plant Project being considered includes:

Environment Aspect

1. Bangladesh Environmental Conservation Act (1995) and amendments 2. Bangladesh Environmental Conservation rules (1997) and amendments

3. Wildlife (Protection & Safety) Act, 2012

Page 9: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

7

4. The Forest Act, 1927 and amendment

5. The Protection and Conservation of Fish Act, 1950 and amendment

6. Protection and Conservation of Fish Rules, 1985

7. Bangladesh Water Act, 2013

8. Bangladesh Energy Regulatory Commission Act, 2013 and amendment

9. The Building and Construction Act, 1952

10. The Vehicle Act, 1927

11. The Motor Vehicle Ordinance Act, 1983 and amendment

12. Environment Court Act, 2000 and amendment

13. The Ground Water Management Ordinance, 1985

14. Natural Water Bodies protection Act, 2000

15. The Embankment and Drainage Act, 1952

Health and Safety Aspect

1. Fatal Accidents Act, 1855

2. The Factories Act, 1965

3. Fire Prevention and extinguish Act, 2003

4. Fire Service Ordinance Act, 1959

5. The Building Construction Act, 1952 and amendments

6. The Boiler Act ,1923

7. The Boiler Rules, 1961

8. The Electricity Act, 1910

9. The Electricity, Rules, 1937

10. The Petroleum Act, 1934

Page 10: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

8

Social Aspect

1. The Acquisition and Requisition of Immovable Property Ordinance, 1982

2. Bangladesh Labour Act, 2006 and amendment.

3. Children’s Act, 2013 (Act No. 24 of 2013)

4. The Antiquities Act, 1968

3.0 Compliance to Environmental Covenants from the ADB Loan Agreement

Schedule Para No.

Point Description Remarks

5 2

(a)

The Borrower shall ensure, of cause NWPGCL or PGCB to ensure, that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with all applicable laws and regulations of the Borrower relating to environment, health, and safety;

For the construction phase NWPGCL already Complied applicable laws and regulations of environment, health, and safety.

5 2

(b)

The Borrower shall ensure, or cause NWPGCL or PGCB to ensure, that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with the Environment Safeguards;

For the construction phase NWPGCL already Complied the Environment Safeguards.

5 2

(c)

The Borrower shall ensure, or cause NWPGCL or PGCB to ensure, that the preparation, design, construction, implementation, operation and decommissioning of the

For the construction phase already Complied

Page 11: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

9

Project and all Project facilities comply with the EARF;

5 2

(d)

The Borrower shall ensure, or cause NWPGCL or PGCB to ensure, that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with all measures and requirements set forth in the respective IEE and EMP, and any corrective or preventive actions set forth in a Safeguards Monitoring Report.

For the construction phase already Complied

5 7

(a)

The Borrower shall ensure, or cause the Project Executing Agency to ensure, that all bidding documents and contracts for Works contain provisions that require contractors to:

For the construction phase already Complied

comply with the measures and requirements relevant to the contractor set forth in the IEE, the RP and any small ethnic community peoples plan (to the extent they concern impacts on affected people during construction), and any corrective or preventive actions set out in a Safeguards Monitoring Report;

5 7 (b)

Make available a budget for all such environment and social measures;

Yes

5 7

(c)

Provide the Borrower with a written notice of any unanticipated environmental, resettlement or small ethnic community peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the

Not Applicable

Page 12: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

10

EMP, the RP or any small ethnic community peoples plan;

5 7

(d)

Adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and

Yes

5 7

(e)

Fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.

-

5 8

The Borrower shall do the following, or shall cause NWPGCL or PGCB to do the following:

-

5 8

(a)

Submit semi annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission;

Submission of semi annual Safeguards Monitoring Report to ADB is ongoing.

5 8

(b)

If any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the project that were not considered in the IEE, the EMP or the RP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and

For the construction phase already Complied

5 8

(c)

Report any actual or potential breach of compliance with the measures and requirements set forth in the EMP or the RP promptly after becoming aware of the breach.

--

Page 13: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

11

4.0 Compliance to Environmental Management Plan

The Environmental impacts and mitigation for this project fall into two categories,

based on the phase in which the mitigation will be provided and the parties who will

take the necessary action. These are as follows:

1. Construction Phase EMP

2. Operation Phase EMP

Since at present this project is in construction stage, special issues of EMP and relevant environmental issues and their mitigation measures for construction stage of the project are being carried out and addressed in this report.

Based on the Environmental Management Plan, the Compliance Status on Environmental Issues in Upgradation of Khulna 150 MW PPP to 225 MW CCPP Project for Construction is given below in the Table.

4.1 Major environmental activities of the project

Major Environmental Activities of the project which will be during construction period are given below:

I. Influx of workers II. Transportation of equipment, materials and personnel; storage of materials III. Construction activities, including operation of construction equipment

It is noted that this power plant already produced power to national grid from 26

June, 2016. For this reason the above mention activities already completed but

project period was June, 2017 and Loan closing June, 2018.

5.0 Safeguards Monitoring Results and Unanticipated Impacts

Environmental Monitoring Schedule

The Individual environmental monitoring measures are identified in the EIA and in

the EMP of EIA report and relate primarily to those activities in which there are

measurable environmental emissions (air quality, water quality and noise, etc).

These activities are drawn together in the Environmental Monitoring Plan (EMoP),

which describes in detail the purpose of each monitoring activity and the

methodology to be employed (including the approach, parameters to be measured,

survey locations, frequency and other information).

Page 14: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

12

Environmental Monitoring Plan for Construction Phase of Khulna 150 MW PPP to

225 MW CCPP is given below:

Table 01: Monitoring Result of SPM, SOx & NOx (July to December, 2017)

SL.

NO

SAMPLING

LOCATION

DATE SPM

3/ mg

SOx

3/ mg

NOx

3/ mg

REMARKS

1 Residential Area

12.07.2017 112 20 23 Result is within limit

North side of

combined cycle

power plant

122 22 25 Result is within limit

2

Residential Area

05.08.2017 112 ND ND Result is within limit

North side of

combined cycle

power plant

112 ND ND Result is within limit

3 Residential Area

21.09.2017

136 ND ND Result is within limit

North side of combined cycle power plant

136 ND ND Result is within limit

4 Residential Area

17.10.2017

121 21 22 Result is within limit

North side of combined cycle power plant

124 20 21 Result is within limit

5 Residential Area

19.11.2017 125 21 20 Result is within limit

North side of combined cycle power plant

126 24 25 Result is within limit

6 Residential Area

18.12.2017 118 20 20 Result is within limit

North side of combined cycle power plant

118 20 21 Result is within limit

Bangladesh

Standard

- 200 80 100

Page 15: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

13

Table 02: Monitoring Result of Underground & Surface Water (July to December,

2017)

Sl. No.

Date: Underground Water

Parameters

Bangladesh Standard

Present value Remarks

1.

10.10.2017

Arsenic (As) 0.05mg/L 0.001mg/L Result is

within limit.

Temperature 20-300C 270 Result is

within limit.

1

10.10.2017

Surface Water

(Industrial)

Quality

parameters

Bangladesh

Standard

Present value Remarks

TSS 150mg/L 115mg/L Result is within limit.

Table 03: Monitoring Result of Noise Level (July to December, 2017)

SL. NO.

SAMPLING LOCATION

DATE TIME NOISE LEVEL (dBa)

REMARKS

1 Plant Area

09.07.2017

10:30 am 61 Result is within limit

2 Residential Area

11:00 am 45 Result is within limit

3 Khulna Bidyut Kendra High School

11:45 am 43 Result is within limit

4 Plant Area 12.08.2017 10:00 am 63

Result is within limit

5 Residential Area

10:30 am 44

Result is within limit

6 Khulna Biddut Kendra High School

11:15 am 42

Result is within limit

7 Plant Area 12.09.2017 10:00 am 63 Result is within limit

8 Residential Area

10:30 am 43 Result is within limit

9 Khulna Biddut Kendra High

11:00 am 44 Result is within limit

Page 16: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

14

School

10 Plant Area 12.10.2017 11:00 am 62 Result is within limit

11 Residential Area

11:30 am 42 Result is within limit

12 Khulna Biddut Kendra High School

12:15 am 42 Result is within limit

13 Plant Area 13.11.2017 10:00 am 64 Result is within limit

14 Residential Area

10:30 am 42 Result is within limit

15 Khulna Biddut Kendra High School

11:15 am 45 Result is within limit

16 Plant Area 17.12.2017 10:00 am 61 Result is within limit

17 Residential Area

10:30 am 44 Result is within limit

18 Khulna Bidyut Kendra High School

11:15 am 44 Result is within limit

Bangladesh Standard For Industrial Area 75(dBa) & Residential Area 55

(dBa) in Day time

Social Issues:

NWPGCL conduct CSR activities at khulna B L. college near the Khulna 225 MW

CCPP area. NWPGCL donated 50 (Fifty) lac taka for established a medical center

of student of khulna B L college from CSR fund (Annex 1).

6.0 CONCLUSION AND RECOMMENDATION

The environmental monitoring report consists of Semiannually environmental

monitoring reporting based on identified parameters in EIA during construction

phase. But this power plant already produced power to national grid from 26

June, 2016. But project period is up to December, 2017. During construction

activities all of the mitigation measures have been taken following ADB

Environmental Safeguard Policy 2009, IFC/World Bank Thermal Power Plant

Guideline 2008 and DoE, Bangladesh guideline and suggestive and

recommended measures in the EIA. Finally it can be concluded that the project

has no detrimental impact for short period on the environment in terms of

ambient air, ambient noise and water during the period from July to December,

2017.

Page 17: Environmental & Social Monitoring Report · The Environmental Management Plan (EMP) and Environmental Monitoring Plan (EMoP) are the main practical tools employed during the construction

15

ANNEX-1