environmental & social monitoring report · the environmental management plan (emp) and...
TRANSCRIPT
Environmental & Social Monitoring Report
Project Number: 42378-015 Semi-Annual Report December 2017
2966 BAN(SF): Power System Expansion and Efficiency Improvement Investment Program
Prepared by the North-west Power Generation Co. Ltd for the Asian Development Bank.
This Environmental & Social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
1
Environmental and Social Safeguard Monitoring Report Semi Annual (July – December, 2017) Report
Upgradation of Khulna 150 MW to 225 MW
Combined Cycle Power Plant Project
at Khalishpur, Khulna.
North-West Power Generation Co. Ltd.
(NWPGCL)
2
TABLE OF CONTENTS
Page
Abbreviations
3
Executive Summary 4
1.0 Introduction
1.1 Brief Project Description
5
1.2 Project Progress Status and Implementation Schedule
6
2.0 Compliance to National Regulations
2.1 Environmental Conservation Rules 1997
6-8
3.0 Compliance to Environmental Covenants from the ADB Loan Agreement
8-10
4.0 Compliance to Environmental Management Plan
11
5.0 Air, Noise, Water Monitoring Results
11-14
6.0 Conclusion and Recommendations
14
3
ABBREVIATIONS
ADB Asian Development Bank
APs Affected Persons
BPDB Bangladesh Power Development Board
DoE Department of Environment
EARF Environmental Assessment and Review Framework
ECA Environmental Conservation Act
ECR Environmental Conservation Rules
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EMoP Environmental Monitoring Plan
ECC Environmental Clearance Certificate
IA Implementing Agency
IUCN International Union for Conservation of Nature
IEE Initial Environmental Examination
MoPEMR Ministry of Power, Energy and Mineral Resources
MFF Multi Financing Facility
PD Project Director
PMO
Project Management Office
PMU
Project Management Unit
SPS
Safeguard Policy Statement
4
Semi Annual Monitoring Report For Upgradation of Khulna 150 MW to 225 MW Combined Cycle Power
Plant Project (CCPP)
(Khalishpur, Khulna)
Period: Semi-Annual (July - December, 2017) Monitoring: Ambient Air, Water & Noise Quality
Executive Summery
Upgradation of Khulna 150 MW Peaking Power Plant to 225 MW Combined Cycle
Power Plant Project is identified by the Government of Bangladesh (GoB) to proper
utilization of Energy. The executing Agency of the project is the Ministry North-West
Power Generation Co. Ltd. and the implementing Agency is the Ministry of Power,
Energy and Mineral Resources (MoPEMR). Financial assistance is given by the Asian
Development Bank (ADB) under the Tranch 1 of Power System Expansion and
Efficiency Improvement Investment Program.
At present, one 150MW Dual Fuel Peaking Power Plant has been established beside
Khulna Power Station (KPS) complex by NWPGCL. Now, NWPGCL intends to add one
75MW Steam Plant using exhaust gas from 150MW dual fuel power plant to convert this
open cycle power plant into combined cycle power plant to be used as base load power
station with the financial assistance from Asian Development Bank (ADB). In order to
convert this peaking power plant into combined cycle power plant, it has been proposed
to add Heat Recovery Steam Generator, Steam Turbine, 75MW Generator, Power
transformer, cooling system, 45 m long Stack etc. with the peaking power plant to be
located in the existing rental power plant area.
The Environmental Management Plan (EMP) and Environmental Monitoring Plan
(EMoP) are the main practical tools employed during the construction phase to provide
the environmental protection measures. The purpose of the environmental management
plan is to set out clearly the required mitigation measures and allocate responsibility for
each, and to provide additional information to assist in planning and implementing the
various activities.
The Impacts and mitigation for this project fall into two distinct categories, based on the
phase in which the mitigation will be provided and the parties who will take necessary
action. For this reason the EMP as well as EMoP for this project is divided into two
parts. These are as follows:
5
a) Construction Phase EMP
b) Operation Phase EMP
This report mainly addressed relevant environmental issues and their mitigation
measures for the construction stage of the Project as mentioned in the following item.
Summary of the Environmental compliance during the period of July to December,
2017.
Environmental Mitigation Measures
Compliance Status
Environmental Monitoring program To be prepared as per EIA Report
1.0 Introduction 1.1 Brief Project Description
Power System Expansion and Efficiency Improvement Investment Program is
intended to finance a series of investments via Multi-tranche Financing Facility
(MFF) of Asian Development Bank (ADB). Tranche 1 consist of several
developments projects in Generation, Transmission and Distribution sectors,
including Upgradation of Khulna 150 MW Peaking Power Plant to 225MW
Combined Cycle Power Plant Project.
Upgradation of Khulna 150 MW Peaking Power Plant to 225 MW Combined Cycle
Power Plant Project is identified by the Government of Bangladesh (GoB) to
proper utilization of Energy and reduce the exhaust temperature to release the
atmosphere. The executing Agency of the project is the North-West Power
Generation Co. Ltd. and the implementing Agency is Ministry of Power, Energy
and Mineral Resources (MoPEMR).
Upgradation of Khulna 150 MW Peaking Power Plant to 225MW Combined
Cycle Power Plant has been established in the same Khulna 150 MW Peaking
Power Plant area and Agreeko 40MW Rental Power Plant area by adding 75MW
steam plant with the Khulna150MW Peaking Power Plant. The Khulna 150MW
Peaking Power Plant is already constructed within the existing Goalpara (Khulna
Power Station) complex of BPDB, about 5 KM West of Khulna city. In Goalpara,
there are already several power plants e.g. 110 MW Steam, 60 MW Steam, a 110
MW Independent Power Plant (IPP), KPCL and 40MW Rental Power Plant. The
major components of the plant consisted of a Simple Cycle Gas Turbine with
Generator, Control Room, 132/11kV Power Transformer, 132 KV Switch yard,
Liquid Fuel System, Natural Gas Fuel System, Lubricating System, Cooling
System, Water Treatment Plant, Effluent Treatment Plant and other associated
6
accessories. The Gas Turbine is initially operate with High Speed Diesel and
then with natural gas if natural gas will be available. In order to convert this
peaking power plant into combined cycle power plant, it has been proposed to add
Heat Recovery Steam Generator, Steam Turbine, 75MW Generator, Power
transformer, cooling system, 45 m long stack etc. with the peaking power plant to
be located in the existing rental power plant area.
1.2 Project Progress Status and Implementation Schedule
A. Progress Status
The updated status of Upgradation of Khulna 150 MW PPP to 225 MW CCPP
Project from July, 2017 to December, 2017 is given below in Table:
Sl. No.
Work Description Status
1. Civil Works: Piling works and superstructure/foundation works for all structures.
Piling works 100% completed. Super structure/foundation works 100% completed
2. Mechanical and Electrical Facilities Consist of -Erection of HRSG, Steam Turbine, Generator, Cooling Tower, CW Pump House and all other BOP Equipments/Components of Power Plant. -Electrical and I&C works with commissioning
-Erection of HRSG 100% - Erection of Steam Turbine, Generator are100% in progress. -Electrical and I&C works completed.
3. Consultancy Services Engineering Consultancy and construction supervision of the Project
-Design works of the project has been completed 100%
2.0 Compliance to National Regulations
The key environment, health & safety and social legislations that are applicable to
the Upgradation of Khulna 150 MW Peaking Power Plant to 225 MW Combined
Cycle Power Plant Project being considered includes:
Environment Aspect
1. Bangladesh Environmental Conservation Act (1995) and amendments 2. Bangladesh Environmental Conservation rules (1997) and amendments
3. Wildlife (Protection & Safety) Act, 2012
7
4. The Forest Act, 1927 and amendment
5. The Protection and Conservation of Fish Act, 1950 and amendment
6. Protection and Conservation of Fish Rules, 1985
7. Bangladesh Water Act, 2013
8. Bangladesh Energy Regulatory Commission Act, 2013 and amendment
9. The Building and Construction Act, 1952
10. The Vehicle Act, 1927
11. The Motor Vehicle Ordinance Act, 1983 and amendment
12. Environment Court Act, 2000 and amendment
13. The Ground Water Management Ordinance, 1985
14. Natural Water Bodies protection Act, 2000
15. The Embankment and Drainage Act, 1952
Health and Safety Aspect
1. Fatal Accidents Act, 1855
2. The Factories Act, 1965
3. Fire Prevention and extinguish Act, 2003
4. Fire Service Ordinance Act, 1959
5. The Building Construction Act, 1952 and amendments
6. The Boiler Act ,1923
7. The Boiler Rules, 1961
8. The Electricity Act, 1910
9. The Electricity, Rules, 1937
10. The Petroleum Act, 1934
8
Social Aspect
1. The Acquisition and Requisition of Immovable Property Ordinance, 1982
2. Bangladesh Labour Act, 2006 and amendment.
3. Children’s Act, 2013 (Act No. 24 of 2013)
4. The Antiquities Act, 1968
3.0 Compliance to Environmental Covenants from the ADB Loan Agreement
Schedule Para No.
Point Description Remarks
5 2
(a)
The Borrower shall ensure, of cause NWPGCL or PGCB to ensure, that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with all applicable laws and regulations of the Borrower relating to environment, health, and safety;
For the construction phase NWPGCL already Complied applicable laws and regulations of environment, health, and safety.
5 2
(b)
The Borrower shall ensure, or cause NWPGCL or PGCB to ensure, that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with the Environment Safeguards;
For the construction phase NWPGCL already Complied the Environment Safeguards.
5 2
(c)
The Borrower shall ensure, or cause NWPGCL or PGCB to ensure, that the preparation, design, construction, implementation, operation and decommissioning of the
For the construction phase already Complied
9
Project and all Project facilities comply with the EARF;
5 2
(d)
The Borrower shall ensure, or cause NWPGCL or PGCB to ensure, that the preparation, design, construction, implementation, operation and decommissioning of the Project and all Project facilities comply with all measures and requirements set forth in the respective IEE and EMP, and any corrective or preventive actions set forth in a Safeguards Monitoring Report.
For the construction phase already Complied
5 7
(a)
The Borrower shall ensure, or cause the Project Executing Agency to ensure, that all bidding documents and contracts for Works contain provisions that require contractors to:
For the construction phase already Complied
comply with the measures and requirements relevant to the contractor set forth in the IEE, the RP and any small ethnic community peoples plan (to the extent they concern impacts on affected people during construction), and any corrective or preventive actions set out in a Safeguards Monitoring Report;
5 7 (b)
Make available a budget for all such environment and social measures;
Yes
5 7
(c)
Provide the Borrower with a written notice of any unanticipated environmental, resettlement or small ethnic community peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the
Not Applicable
10
EMP, the RP or any small ethnic community peoples plan;
5 7
(d)
Adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and
Yes
5 7
(e)
Fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.
-
5 8
The Borrower shall do the following, or shall cause NWPGCL or PGCB to do the following:
-
5 8
(a)
Submit semi annual Safeguards Monitoring Reports to ADB and disclose relevant information from such reports to affected persons promptly upon submission;
Submission of semi annual Safeguards Monitoring Report to ADB is ongoing.
5 8
(b)
If any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the project that were not considered in the IEE, the EMP or the RP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and
For the construction phase already Complied
5 8
(c)
Report any actual or potential breach of compliance with the measures and requirements set forth in the EMP or the RP promptly after becoming aware of the breach.
--
11
4.0 Compliance to Environmental Management Plan
The Environmental impacts and mitigation for this project fall into two categories,
based on the phase in which the mitigation will be provided and the parties who will
take the necessary action. These are as follows:
1. Construction Phase EMP
2. Operation Phase EMP
Since at present this project is in construction stage, special issues of EMP and relevant environmental issues and their mitigation measures for construction stage of the project are being carried out and addressed in this report.
Based on the Environmental Management Plan, the Compliance Status on Environmental Issues in Upgradation of Khulna 150 MW PPP to 225 MW CCPP Project for Construction is given below in the Table.
4.1 Major environmental activities of the project
Major Environmental Activities of the project which will be during construction period are given below:
I. Influx of workers II. Transportation of equipment, materials and personnel; storage of materials III. Construction activities, including operation of construction equipment
It is noted that this power plant already produced power to national grid from 26
June, 2016. For this reason the above mention activities already completed but
project period was June, 2017 and Loan closing June, 2018.
5.0 Safeguards Monitoring Results and Unanticipated Impacts
Environmental Monitoring Schedule
The Individual environmental monitoring measures are identified in the EIA and in
the EMP of EIA report and relate primarily to those activities in which there are
measurable environmental emissions (air quality, water quality and noise, etc).
These activities are drawn together in the Environmental Monitoring Plan (EMoP),
which describes in detail the purpose of each monitoring activity and the
methodology to be employed (including the approach, parameters to be measured,
survey locations, frequency and other information).
12
Environmental Monitoring Plan for Construction Phase of Khulna 150 MW PPP to
225 MW CCPP is given below:
Table 01: Monitoring Result of SPM, SOx & NOx (July to December, 2017)
SL.
NO
SAMPLING
LOCATION
DATE SPM
3/ mg
SOx
3/ mg
NOx
3/ mg
REMARKS
1 Residential Area
12.07.2017 112 20 23 Result is within limit
North side of
combined cycle
power plant
122 22 25 Result is within limit
2
Residential Area
05.08.2017 112 ND ND Result is within limit
North side of
combined cycle
power plant
112 ND ND Result is within limit
3 Residential Area
21.09.2017
136 ND ND Result is within limit
North side of combined cycle power plant
136 ND ND Result is within limit
4 Residential Area
17.10.2017
121 21 22 Result is within limit
North side of combined cycle power plant
124 20 21 Result is within limit
5 Residential Area
19.11.2017 125 21 20 Result is within limit
North side of combined cycle power plant
126 24 25 Result is within limit
6 Residential Area
18.12.2017 118 20 20 Result is within limit
North side of combined cycle power plant
118 20 21 Result is within limit
Bangladesh
Standard
- 200 80 100
13
Table 02: Monitoring Result of Underground & Surface Water (July to December,
2017)
Sl. No.
Date: Underground Water
Parameters
Bangladesh Standard
Present value Remarks
1.
10.10.2017
Arsenic (As) 0.05mg/L 0.001mg/L Result is
within limit.
Temperature 20-300C 270 Result is
within limit.
1
10.10.2017
Surface Water
(Industrial)
Quality
parameters
Bangladesh
Standard
Present value Remarks
TSS 150mg/L 115mg/L Result is within limit.
Table 03: Monitoring Result of Noise Level (July to December, 2017)
SL. NO.
SAMPLING LOCATION
DATE TIME NOISE LEVEL (dBa)
REMARKS
1 Plant Area
09.07.2017
10:30 am 61 Result is within limit
2 Residential Area
11:00 am 45 Result is within limit
3 Khulna Bidyut Kendra High School
11:45 am 43 Result is within limit
4 Plant Area 12.08.2017 10:00 am 63
Result is within limit
5 Residential Area
10:30 am 44
Result is within limit
6 Khulna Biddut Kendra High School
11:15 am 42
Result is within limit
7 Plant Area 12.09.2017 10:00 am 63 Result is within limit
8 Residential Area
10:30 am 43 Result is within limit
9 Khulna Biddut Kendra High
11:00 am 44 Result is within limit
14
School
10 Plant Area 12.10.2017 11:00 am 62 Result is within limit
11 Residential Area
11:30 am 42 Result is within limit
12 Khulna Biddut Kendra High School
12:15 am 42 Result is within limit
13 Plant Area 13.11.2017 10:00 am 64 Result is within limit
14 Residential Area
10:30 am 42 Result is within limit
15 Khulna Biddut Kendra High School
11:15 am 45 Result is within limit
16 Plant Area 17.12.2017 10:00 am 61 Result is within limit
17 Residential Area
10:30 am 44 Result is within limit
18 Khulna Bidyut Kendra High School
11:15 am 44 Result is within limit
Bangladesh Standard For Industrial Area 75(dBa) & Residential Area 55
(dBa) in Day time
Social Issues:
NWPGCL conduct CSR activities at khulna B L. college near the Khulna 225 MW
CCPP area. NWPGCL donated 50 (Fifty) lac taka for established a medical center
of student of khulna B L college from CSR fund (Annex 1).
6.0 CONCLUSION AND RECOMMENDATION
The environmental monitoring report consists of Semiannually environmental
monitoring reporting based on identified parameters in EIA during construction
phase. But this power plant already produced power to national grid from 26
June, 2016. But project period is up to December, 2017. During construction
activities all of the mitigation measures have been taken following ADB
Environmental Safeguard Policy 2009, IFC/World Bank Thermal Power Plant
Guideline 2008 and DoE, Bangladesh guideline and suggestive and
recommended measures in the EIA. Finally it can be concluded that the project
has no detrimental impact for short period on the environment in terms of
ambient air, ambient noise and water during the period from July to December,
2017.
15
ANNEX-1