ep!469west!erregulla!! seismic!groundtruthingsurvey …...west erregulla seismic ground truthing...

11
EP 469 West Erregulla Seismic Ground Truthing Survey SUMMARY

Upload: others

Post on 07-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

 

 

 

 

 EP  469  West  Erregulla    

Seismic  Ground  Truthing  Survey  

 

SUMMARY      

   

West Erregulla Seismic Ground Truthing Survey

Summary

Document  Number:  16012-­‐REP-­‐001     Page  2  of  11      

 

CONTENTS  

 

1.   INTRODUCTION .................................................................................................. 3  

2.   OBJECTIVES ........................................................................................................ 3  

3.   SCOPE ................................................................................................................. 3  

4.   SURVEY METHODOLOGY .................................................................................. 3  

5.   SURVEY RESULTS .............................................................................................. 4  

5.1   Access Tracks ...................................................................................................................... 4  

5.2   Source Lines ......................................................................................................................... 4  

6.   SUMMARY OF ACTIONS AND OUTCOMES ...................................................... 4  

LIST  OF  TABLES  

Table  1:  Actions  and  Closeout  from  Seismic  Ground  Truthing  Survey  ........................................................  4  Table  2:  Actions  and  Closeouts  from  Cultural  Heritage  ...............................................................................  7  

 

APPENDICES  

Appendix  A:  Seismic  Ground  Truthing  Survey  Map  ...................................................................................  11  

   

 

West Erregulla Seismic Ground Truthing Survey

Summary

Document  Number:  16012-­‐REP-­‐001     Page  3  of  11      

1. Introduction Warrego   Energy   PTY   Ltd   (Warrego)   undertook   a   Seismic   Ground   Truthing   Survey   at   West   Erregulla  within   Exploration   Permit   (EP)   469   between   21  May   and   2   June   2014.     The   Seismic   Ground   Truthing  Survey  was  conducted  by  wkc  and  KD.1  Pty  Ltd  on  behalf  of  Warrego  to  provide  survey  data  to  aid  in  the  upcoming  3D  Seismic  Survey  Program.  The  West  Erregulla  Field  is  located  approximately  300km  north  of  Perth,  and  50km  south-­‐east  of  Dongara,  in  the  Northern  Sandplains  region  of  Western  Australia.  

2. Objectives The  objectives  of  the  Seismic  Ground  Truthing  Survey  are  summarised  below:  

• Scout  all  north-­‐south  seismic   source   lines  and   three  east-­‐west   receiver/access   lines  within  Vacant  Crown  Land.    Any  line  deviation  to  remain  clear  of  avoidance  zones;  

• A   reasonable   photographic   record   and   notes   assembled   to   assist   in   planning   and  preparation   for   line   clearance/mulching   activities,   receiver   deployment   (nodal   system  deployed  manually  on  foot),  and  the  3D  seismic  survey  acquisition  which  will  follow;  

• Agreed/committed   buffer   zones   around   environmentally   sensitive   areas   and   potential  cultural  heritage  (avoidance  areas);  

• All  source  lines  and  three  access  track  lines  to  be  reviewed  and  mapped  to  3.5m  width;  and  • Produce  revised  pre-­‐plot  data.  

3. Scope The  scope  of  this  document  is  to  summarise  the  outcomes  of  the  Seismic  Ground  Truthing  Survey  in  preparation  for  the  3D  Seismic  Survey  Program.  

4. Survey Methodology The  methodology   involved   the   setting  up  of   a  GPS   receiver   to   log   static   data  on  an  existing  point.    A  second   GPS   receiver   then   simultaneously   logs   data   on   new   station   for   a   minimum   of   30   minutes,  depending   on   the   length   of   the   baseline.   After   post   processing   the   data   to   obtain   accurate   baseline  information,  a  position  can  be  determined  for  the  unknown  station.  

Line  scouting  was  carried  out  using  the  Real  Time  Kinematic  (RTK)  GPS  method.  This  consisted  of  a  base  receiver  setup  on  a  known  control  station  and  rover  receiver  connected  via  UHF  radio  link.  Through  the  UHF  radio  modem  the  base  receiver  broadcasts  the  base  position  and  GPS  data  measured  at  the  base  directly  to  a  radio  modem  connected  to  the  roving  GPS  receiver  enabling  the  rover  to  initialise  (resolve  satellite   cycle  ambiguities).  Once   initialised   the   roving   receiver   can   compute   its  own  position  within  a  few  centimetres.  

The  prospect  area  was  scouted  to  map  fences,  gates,  tracks,  potential  cultural  heritage  avoidance  areas  and   any   infrastructure   pertinent   to   crew   operations   and   safety   utilising   the   Trimble   Yuma   tablet   and  

West Erregulla Seismic Ground Truthing Survey

Summary

Document  Number:  16012-­‐REP-­‐001     Page  4  of  11      

MapInfo   software.  Using   this   information   combined  with   that   supplied  by  Warrego  accurate  prospect  maps  could  be  generated.  

5. Survey Results The  Seismic  Ground  Truthing  Survey  scouted  approximately  160  km  of  access  track  and  source  lines  and  a  map  indicating  the  results  of  the  survey  is  provided  in  Appendix  A.  

A  discussion  of  the  results  of  the  survey  is  provided  below.  

5.1     Access  Tracks  

Personnel  scouted  three  receiver  lines  R1000,  R1054  and  R1171  that  are  planned  to  be  mulched  and  utilised  as  access  tracks.  Small  detours  were  placed  along  them  in  order  to  avoid  flora  and  rocky   terrain.   Scouting   of   these   three   lines   and  what  was   seen  while   traversing   source   lines  indicated   no   notable   offsets   from   design   should   be   required   on   receiver   lines.   It   can   be  expected   that   with   hand   carrying   equipment   in   to   the   specific   stations   around   rocky  breakaways  some  problems  will  be  encountered  with  successfully  planting  receivers.  

5.2   Source  Lines  

Numerous   flora   buffer   zones   and   rocky   terrain   around   breakaways   require   detours   to   be  scouted   to   find   alternate   routes   for   the   source   lines.   Where   possible   station   offsets   were  maintained  on  design  and  the  detours  only  used  for  access  purposes.    

6. Summary of Actions and Outcomes During   the  Seismic  Ground  Truthing  Survey   there  were   several   areas   that   required   further   review  and  the  outcomes  are  discussed/resolved  in  the  table  below.  

Table  1:  Actions  and  Closeout  from  Seismic  Ground  Truthing  Survey  

No.   Action   Closeout  

1   Open  Eucalyptus    

Scouting  of  all  possible  options  was  not  undertaken  due  to  time   constraints   and   particularly   seeing   the   likelihood   of  some   options   was   low.   If   further   definition   could   be  provided  such  as  vibe  access  without  mulching,  vibe  access  with  mulching  if  outside  buffer  zone  from  trees  or  method  of   defining   individual   stands   of   trees   that   can   be  worked  past  as  opposed  to  blanket  classifying  the  area  as  a  forest,  these   options   could   be   quickly   reviewed   again   by   the  

Open   Eucalyptus   occurs   as   patches  throughout   the   survey   area   and   a   10m  buffer  has  been  implemented.    

 

West Erregulla Seismic Ground Truthing Survey

Summary

Document  Number:  16012-­‐REP-­‐001     Page  5  of  11      

Seismic  Line  Pointer  managing  the  mulching  crew.  

2   Unidentified  Eucalyptus  S5009  station  1180  to  1179    

Eucalyptus   found   of   a   different   species   to   the   existing  defined  Open  Eucalyptus  Forest  areas.  Whether  defined  as  a   Forest   or   not   they   are   larger   than   3m.   The   ground   is  sparsely  covered  with  grass,  mostly  bare  soil  so  no  clearing  is  required  to  traverse  vibes  through  the  area  and  reverse  back  out.  Utilising  the  natural  gap.  If  not  allowed  to  use  the  gap   it   would   most   likely   result   in   offsetting   the   line   in  excess   of   80m   west   outside   the   grid.   Offsetting   east  requires   a   greater   offset   than   the   gap   and  would   require  mulching  to  weave  around  3m  trees.  

The   route   will   avoid   open   eucalypt   forest  and  trees  larger  than  3m.  A  10m  buffer  has  been   implemented   around   open   Eucalypt  forest  and    source  line  S5009  adjusted.  

3   Over  stated  Open  Eucalyptus  S5018  station  1142  to  1152    

Desktop  provided  Open  Eucalyptus  mapping  would  appear  to   have   included   chest   high   dense   shrubs   with   sparse  scattering  of  Eucalyptus.    

Open   Eucalyptus   occurs   as   patches  throughout   the   survey   area   and   a   10m  buffer  has  been  implemented.    

 

4   Access   into  Desktop  mapped  Open  Eucalyptus  Area  S5018  south  from  station  1164    

Sparse   Eucalyptus   with   waist   high   shrubs   that   would  require  mulching.   If   mulcher   access   could   be   approved   a  considerable   distance   could   be   achieved   close   to   design  but  the  vibes  would  still  be  required  to  return  via  the  same  route  as  access  isn’t  possible  out  to  50181152.  

The   route   will   avoid   open   eucalypt   forest  and   a   10m   buffer   has   been   implemented  and  source  line  S5018  adjusted.  

5   Open  Eucalyptus  S5117,  S5126  and  S5135    

After   careful   review   of   these   areas   most   show   little  possibility   for   notable   improvement   by   pushing   access  issues  into  the  Open  Eucalyptus  as  they  ultimately  result  in  the   need   of   clearing   or   boxing   vibes   into   tight   places  requiring  reversing  out.  S51171076  to  1074  would  benefit  from   access   however.   The   Vibes   could   traverse   this   area  without  mulching  being  essential  online  and  save  mulching  the  600m  detour.    

The   route  will   avoid   open   eucalypt   forest.    A   10m   buffer   has   been   implemented   and  source   lines   S5117,   S5126   and   S5135  adjusted.  

6   Encroachment  on  Priority  1  20m  buffer  S5135  station  1099  to  1100    

Blocked   by   extensive   flora   buffer   zones   and   Open  Eucalyptus   no   access   is   possible   for   S5135.   In   order   to  continue   north   the   route   has   been   woven   between   the  Open   eucalyptus   and   the   required   Priority   1   15m   buffer  zone,   but   encroaches   on   the   Warrego   self-­‐imposed   20m  

The   route  will   avoid   open   eucalypt   forest.    A   10m   buffer   has   been   implemented   and  source  line  S5135  adjusted.  

West Erregulla Seismic Ground Truthing Survey

Summary

Document  Number:  16012-­‐REP-­‐001     Page  6  of  11      

buffer.    

7   Approved   use   of   North/South   fire   break   track   for   S5144  Station  1001  to  1099  

At  the  southern  end  the  offset  from  design  is  minimal  and  would   save   the   undesirable   visual   effect   of   the   mulched  line  beside  and   frequently  crossing   the  existing   track.  The  northern   portion   is   critical   in   the   successful   navigation  through   the   extensive   flora   buffers.   The   other   positive  result  is  the  quality  of  the  track  opposed  to  a  mulched  line  and  the  3.92km  of  mulched  line  saved.    

Access   of   S5144   fire   break   has   been  approved  for  use,  as  the  use  of  this  existing  cleared   area   will   not   result   in   any  vegetation   clearing   and   therefore   an  overlap   with   flora   buffer   is   acceptable   as  long   as   there   is   no   native   vegetation  clearing  within  the  buffer  

8   Extend  R1054  1.1km  west  to  access  track    

Scouted  Routes  if  mulching  allowance  allows  extend  R1054  to  the  western  access  track  to  improve  crew  movements.  

The   proposed   extension   of   R1054  will   not  be  implemented  as  this  extends  outside  the  Exploration   Permit   and   associated   NVCP  approved  area.  

 

   

West Erregulla Seismic Ground Truthing Survey

Summary

Document  Number:  16012-­‐REP-­‐001     Page  7  of  11      

The   Ethnographic   Survey   and   the   Archaeological   Heritage   Assessment   conducted   by   the   Amangu  People,  generated  several  recommendations.    The  outcomes  are  discussed  in  Table  2  below.  

Table  2:  Actions  and  Closeouts  from  Cultural  Heritage  

No.   Action   Closeout  

Ethnographic  Survey  

1   Warrego  Energy  are  advised  that  Aboriginal  heritage  places  and   sites,   both   archaeological   and   ethnographic,   were  identified   during   the   survey   in   the   area   of   the   Sandplain  Creek  and  should  be  avoided  

Works   will   be   avoided   around   Sandplain  Creek.     A   20m   exclusion   zone   has   been  established   on   either   side   of   Sandplain  Creek.     In  addition,   two   identified  heritage  site  exclusion  areas  will  be  implemented.  

2   Warrego   Energy   are   advised   that   Sandplain   Creek   is   not  clear   of   Aboriginal   heritage   and   recommend   that   works  avoid  this  watercourse  

Works   will   be   avoided   around   Sandplain  Creek.     A   20m   exclusion   zone   has   been  established   on   either   side   of   Sandplain  Creek.     In  addition,   two   identified  heritage  site  exclusion  areas  will  be  implemented.  

3   The  potential  for  Aboriginal  heritage  sites  and  places  in  the  remainder   of   the   surveyed   area   is   considered   to   be   very  low,   and   proposed   work   program   works   may   proceed   in  these   locations   in   accordance   with   Recommendation   4  (below)  

Noted.  

 

4   Warrego   Energy   are   advised   that   based   on   the   available  information  gathered  during  the  survey  YMAC  and  Amangu  did   not   identify   any   new   ethnographic   sites   or   heritage  places   within   the   areas   surveyed   outside   of   Sandplain  Creek  

Noted.    

 

5   That   Warrego   Energy   seek   to   engage   Amangu   people   to  monitor   ground   disturbing   works   or   participate   in  rehabilitation  work  in  the  area  surveyed  

Warrego   is   not   proposing   to   engage  monitors   during   the   3D   Seismic   activity.    Monitors   will   be   engaged   during   activities  involving  ground  disturbance,   for  example,  during  well  site  preparation  in  the  future.  

6   If   human   remains,   skeletal  materials   that  may  be  human,  or   materials   that   may   belong   to   a   human   grave   are  discovered   during   exploration   within   the   cleared   survey  areas,   Warrego   Energy   must   follow   the   DAA   procedures  and  stop  work  immediately,  and  the  materials  and  the  area  around   them   must   be   left   undisturbed.   The   Western  Australian  Police  must  be  informed  immediately  as  well  as  Amangu   traditional   owners,   through   their   representative,  

If   any   human   remains,   skeletal   materials  that  may   be   human  or  materials   that  may  belong   to   a   human   grave   are   discovered  activities  will  cease,  with  the  materials  and  the   area   to   be   left   undisturbed.   The  notification   process   shown   in   the   Cultural  Heritage  Management  Plan  that  are   in   line  with  the  DAA  Procedures  will  be  followed.  

West Erregulla Seismic Ground Truthing Survey

Summary

Document  Number:  16012-­‐REP-­‐001     Page  8  of  11      

YMAC,  as  soon  as  practicable  

7   It   is   recommended   that   Warrego   Energy   employees   and  contractors  executing  the  proposed  works  be   informed  of  the   contents   of   the   heritage   survey   report   and   their  obligations  under  the  AHA.  

Personnel   involved   in   the   Survey   will   be  informed   of   the   contents   of   the   Amangu  Heritage   Survey   and   obligations   under   the  Aboriginal  Heritage  Act  1972  (AHA).  

8   It   is   recommended   that   landowners   in   proximity   to  Sandplain   Creek   be   informed   of   the   contents   of   the  heritage   survey   report   and   their   obligations   under   the  AHA;  

The   landholders   in   proximity   of   Sandplain  Creek  have  been  informed  of  the  outcomes  of   the   survey   and   the   report   and   the  associated  obligations  under  AHA.  

9   It   is   recommended   that   Warrego   Energy   maintain  discussions  with  the  Amangu  people,  regarding  any  future  matters   that   may   arise   in   relation   to   the   area   surveyed,  including   any   further   proposed   excavation   or   ground  disturbance   activities   or   access   to   uncleared   proximate  areas.  

Ongoing   communications   are   being  conducted  and  recorded  with  Warrego  and  the  Amangu  people.  

Archaeological  Heritage  Assessment  

1   Warrego   Energy   is   advised   that   the   archaeological   work  area  clearance  of  the  West  Erregulla  PDA  is  complete.  

The   proposed   access   tracks   and   deviations   have   been  cleared.   The   area   of   the   PDA   that   extends   over   private  paddocks   has   also   been   cleared.   Two   heritage   restriction  zones   (TRHRZ-­‐AMA14-­‐01   and   TRHRZ-­‐AMA14-­‐02)   were  identified  during  a  targeted  search  of  the  creek  line  in  the  northern  part  of   the  PDA  and  are  not  clear.  As  a  result  of  this,   the   Amangu   Traditional   Owners   request   further  heritage  work  to  be  done  in  areas  of  the  PDA  that  extend  over  the  crown  land  and  within  in  the  100  m  buffer  of  Sand  Plain   Creek.   Warrego   is   advised   that   the   existing   creek  crossings  and  existing  firebreaks  are  clear.  

Noted.  

Works   will   be   avoided   around   Sandplain  Creek.     A   20m   exclusion   zone   has   been  established   on   either   side   of   Sandplain  Creek.      

2   Warrego   Energy   is   advised   that   there   is   a   deviation   on  proposed   access   track   A   and   that   only   this   deviation   has  been  cleared.  

A  section  of  the  proposed  access  track  A  was  not  surveyed,  and   is   subsequently   not   clear.   As   such   an   alternative  deviation  has  been  cleared.  Warrego  Energy  is  advised  that  should   the   deviation   provided   not   be   suitable,   further  heritage  work   is   required   to   complete   the   section   of   the  original  access  track  or  assess  an  alternative  access  track.  

The   ground   Truthing   Survey   investigated  the   on   the   ground   aspects   of   the   original  ‘access   track   A’   and   the   proposed  deviation.  Assessment  of  terrain  issues  and  access   was   incorporated   into   the  refinement  of  this  line.    .  

3   Warrego   Energy   is   advised   to   engage   at   least   2  monitors   Exclusion   zones  have  been   included  at   the  

West Erregulla Seismic Ground Truthing Survey

Summary

Document  Number:  16012-­‐REP-­‐001     Page  9  of  11      

for   all   clearing   and   ground   disturbing   works,   and   works  along  Sand  Plain  Creek.  

The   presence   of   Amangu   Traditional   Owner  representatives   as   monitors   is   advised   so   that   any  subsurface  cultural  material  that  may  be  unearthed  during  works   is   managed   appropriately.   Additionally,   cultural  material  may  be  unearthed  during  vegetation  clearance  as  dense   vegetation   limited   ground   visibility   in   parts   of   the  PDA.  

known  cultural  heritage   sites  and  Warrego  will  engage  the  Amangu  people  should  any  new  sites  be  identified.  

It   is   noted   that   native   vegetation   clearing  will   not  be  undertaken  as   such,  but   rather  mulching   which   will   not   disturb   the  vegetation  root  stock  or  top  soil.  

4   All   Warrego   Energy   employees   and   contractors   working  within  the  PDA  should  be  made  aware  of  the  location  and  boundaries   of   all   not   cleared   areas   identified   therein   and  be  clearly   instructed  to  restrict  access  and  works   to  areas  that   Warrego   Energy   has   clearance   to   utilise.   It   is  recommended   that   Warrego   Energy   employees   and  contractors  are  briefed  fully  on  their  obligations  in  regards  to   heritage   places   and   objects   under   the   Act,   and   attend  cultural  awareness  training  if  available.  

It   is   an   offence   to   disturb   an   Aboriginal   heritage   place  without  prior  written  permission  to  do  so  under  s16  or  s18  of   the   Act.   Financial   penalties   may   be   applied   against  individuals   or   corporations   who   disturb   a   heritage   place.  S18   of   the   Act   details   the   statutory   provision   for  applications  to  be  made  to  the  Minister  to  utilise  areas   in  which   Aboriginal   heritage   places   may   exist.   Approval   to  utilise  areas   in  which  Aboriginal  heritage  places  may  exist  is  subject  to  evaluation  by  the  ACMC  and  the  conditions  of  the  Act.  

Personnel   involved   in   the   Survey   will   be  informed   of   exclusion   zones   of   the   known  cultural   heritage   sites   and   the  requirements  and  obligations  under  AHA.      

5   It   is   recommended   that  Warrego  Energy  and   the  Amangu  Traditional   Owners   cooperatively   develop   a  comprehensive   Cultural   Heritage   Management   Plan  (CHMP).  

In   order   to   establish   a   framework   for   the   mitigation   of  project   impacts  upon  heritage  places   throughout  Amangu  country,   it   is   recommended   that  Warrego  Energy  and   the  Amangu   Traditional   Owners   cooperatively   develop   a  CHMP.   This   CHMP   should   include   a   comprehensive   stop-­‐works   procedure   that   addresses   the   management   of  subsurface  cultural  and  skeletal  material.  

Warrego  has  developed  a  Cultural  Heritage  Management  Plan  that  will  be  reviewed  by  the  Amangu  Traditional  Owners.  

6   If  Warrego  Energy  proposes  to  alter  the  type  of  works  or  to  expand   the   program   of   works,   either   in   size   or   scale,  

Ongoing   communications   are   being  conducted  and  recorded  with  Warrego  and  

West Erregulla Seismic Ground Truthing Survey

Summary

Document  Number:  16012-­‐REP-­‐001     Page  10  of  11    

beyond   that   cleared   during   the   heritage   assessment,   it   is  advised   that   further   consultation   with   the   Amangu  Traditional   Owners   is   undertaken   prior   to   the  commencement  of  works.  

Warrego  Energy  is  advised  that  only  the  areas  subjected  to  heritage  assessment  are  clear  for  works  to  proceed.  Should  the   program   of   works   expand   in   size   or   scale,   extend  beyond  existing  creek  crossings  and  existing  firebreaks,  or  should   the  proponent  wish   to   conduct  a  different   type  of  works,  the  Traditional  Owners  will  need  to  be  engaged  for  further  heritage  assessment.  

the  Amangu  people.  

 

   

West Erregulla Seismic Ground Truthing Survey

Summary

Document  Number:  16012-­‐REP-­‐001     Page  11  of  11    

Appendix  A:  Seismic  Ground  Truthing  Survey  Map