epri igcc engineering & economic evaluations - 2009
TRANSCRIPT
EPRI IGCC Engineering & Economic Evaluations - 2009
4th International Conference on IGCC & XtL Technologies May 18-20, 2009, Dresden, GermanyNeville Holt, George Booras, Ronald Schoff – EPRI Environment & Generation Sector
2© 2009 Electric Power Research Institute, Inc. All rights reserved.
EPRI Engineering and Economic Evaluations 2009
• Recent US Coal Plant Announcements• Impact of global economic crisis on construction costs
(Fuel prices, Commodity costs, currency exchange rates)• Summary of EPRI IGCC and PC Plant Studies• EPRI Review of Studies by Others• US has >300 GW of existing PC Plants. Close? Run and
pay for CO2 emissions? CCS Retrofit?• Where are Capital costs headed?
3© 2009 Electric Power Research Institute, Inc. All rights reserved.
Capital Cost Estimates in Press Announcements and Submissions to PUCs in 2007–09
Owner Name/Location
Net MW Technology/ Coal
Estimate Date
Reported Capital $ Million
Reported Capital $/kW
Notes/Status
AEP/Swepco
Hempstead, AR
600 SCPC/PRB Dec 2008 >2000 >3333 CPCN issued
Southern Co.
Kemper County, MS
560 Air IGCC/ Lignite +50% CCS
Dec 2008 >2200 >3930 FEED in progress
Duke Cliffside, NC 800 SCPC/Bit May 2007
2400 3000 Permitted
Duke Edwardsport, IN
630 IGCC/Bit May 2008
2350 In Service
3730 Under construction
AEP Mountaineer, WV
630 IGCC/Bit June 2007
2230 3545 On hold
Tampa Electric
Polk County, FL
630 IGCC/Bit July 2007 2013 In Service
3185 Shelved: now NGCC
Sunflower Holcomb, KS 2 x 700 SCPC/PRB Sept 2007
3600 2572 Now one 700 MW
Am. Muni. Power
Meigs County, OH
1000 SCPC/Bit & PRB
Jan 2008 2900/3300 2900/3300
Tenaska Sweetwater County, TX
600 SCPC + CCS/PRB
Feb 2008 3000 5000
4© 2009 Electric Power Research Institute, Inc. All rights reserved.
Key Drivers for Coal Plant Economics
• Coal costs– Mining and transportation costs– Expected heat rates, especially with CO2 capture
• Capital costs– Equipment and commodity escalation rates– Currency exchange rates
• Construction schedule• EPC contracting strategies• Financing availability and costs• Operating and maintenance costs
– Expected reliability and capacity factor
5© 2009 Electric Power Research Institute, Inc. All rights reserved.
U.S. Regional Coal Spot Prices
http://www.ferc.gov/market-oversight/othr-mkts/coal/othr-coal-bs-prb-pr.pdf
6© 2009 Electric Power Research Institute, Inc. All rights reserved.
Coal – US, Europe, South Africa and Australia
Coal Spot Prices Indices in Local Currencies
January 2004 - February 20092JAN2004 = 100
50
100
150
200
250
300
350
400
450
500
550
Inde
x Va
lue Central Appalachia
Newcastle, AustraliaRichards Bay, South Africa
ARA, Europe
Source: Bloomberg, Energy Information Administration.
1/04 7/04 1/05 7/05 1/06 7/06 1/07 7/07 1/08 7/08 1/09
7© 2009 Electric Power Research Institute, Inc. All rights reserved.
Metal Prices Peaked in 2008 and Have Now Reduced to 2004–06 Levels
Date March 04 March 06 March 08 August 08 April 09Price $/lb Aluminum 0.75 1.05 1.40 1.20 0.64 FerroChrome 60-65% HC 0.65 0.6 2.0 2.15 0.73 Copper 1.40 2.20 4.0 3.30 2.0 Nickel 6.0 6.1 15.0 9.0 5.0 Cold rolled Steel 0.30 0.33 0.4 0.58 0.26 Steel Rebar 0.20 0.25 0.37 0.52 0.26 Std. US Steel Plate 0.26 0.38 0.42 0.72 0.31
Source: MetalPrices.comNote that equipment prices seem to be lagging the above metal price reductions, possibly due to orders that were placed prior to the economic downturn.
8© 2009 Electric Power Research Institute, Inc. All rights reserved.
Historical Currency Conversion Rates
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
2.2
Jan-02 Jan-03 Jan-04 Jan-05 Jan-06 Jan-07 Jan-08 Jan-09 Jan-10
Euro to AUDUSD to AUDUSD to EuroCAD to USD
source: http://www.oanda.com
9© 2009 Electric Power Research Institute, Inc. All rights reserved.
Source: Producer Price Index, Bureau of Labor Statistics
Copper and Copper Alloy Wire & Cable
Semi-Finished Steel Mill Products
Note that equipment price indexes seem to be lagging the commodity price reductions, possibly due to orders that were placed prior to the economic downturn.
Many Commodity Price Indexes Are Dropping
10© 2009 Electric Power Research Institute, Inc. All rights reserved.
Plant Construction Costs Are Turning Around (Source: Chemical Engineering Magazine, March 2009)
One engineering company reported that their cost estimate for an IGCC project is now ~12% lower than the original estimate
developed in October 2008
Construction Cost Indices(Source: Chemical Engineering Magazine, March 2009)
360
380
400
420
440
460
480
500
520
540
560
580
600
620
640
660
Jun-98 Jun-99 Jun-00 Jun-01 Jun-02 Jun-03 Jun-04 Jun-05 Jun-06 Jun-07 Jun-08 Jun-09
Che
mic
al E
ngin
eerin
g Pl
ant C
ost I
ndex
900
950
1,000
1,050
1,100
1,150
1,200
1,250
1,300
1,350
1,400
1,450
1,500
Mar
shal
l & S
wift
Equ
ipm
ent C
ost I
ndex
Chemical Engineering Plant Cost Index
Marshall & Swift Equipment Cost Index
11© 2009 Electric Power Research Institute, Inc. All rights reserved.
We Are in a Period of Uncertainty…
12© 2009 Electric Power Research Institute, Inc. All rights reserved.
With Current Technology CO2 Capture CostlyNo Clear Winners in Current Designs (2007 Data)
40
50
60
70
80
90
100
110
120
130
140
150
30-Y
r lev
eliz
ed C
OE,
$/M
Wh
(Con
stan
t 200
7$)
. No Capture
Retrofit CaptureNew Capture
· COE Includes $10/tonne for CO2 Transportation and Sequestration · IGCC & CCS include 10% TPC contingency for first-of-a-kind
Illinois #6 Bituminous PRB ( Western Coal)
MEA- installed initially
Installed Later
Supercritical PC
Ultrasupercritical PC
GE Total Quench
ConocoPhillips E-Gas
Average IGCC
Average IGCC
13© 2009 Electric Power Research Institute, Inc. All rights reserved.
IGCC Case Studies 2008 Process Design Basis
• Site: Kenosha, WI (600 feet/190 m elevation); clear and level• Ambient Conditions: 59°F, 14.4 psia, 60% RH
(15°C, 1.0 bara, 60% RH)• Fuels (costs as-delivered to site):
– Pittsburgh #8: 13,260 Btu/lb HHV; $2.00/MMBtu 30,800 kJ/kg HHV; $1.90/GJ
– Powder River Basin: 8,340 Btu/lb HHV; $1.80/MMBtu 19,400 kJ/kg HHV; $1.71/GJ
• Design Strategy:– Environmental: UDBS Profile #2 (SCR included in HRSG)– GT-ASU: Maximize for non-CCS; allow for CCS– CO2 Capture: Full capture retrofit (80–90%) with pre-investment– CO2 Purity: 100 ppmv total sulfur
14© 2009 Electric Power Research Institute, Inc. All rights reserved.
IGCC Case Studies 2008 Financial Design Basis
• 1st Quarter 2008 costs (Foster Wheeler Italiana)• Total Plant Cost (TPC):
– TPC = Bare Erected Cost + Eng/HO Fees + Contingency (10%)• Production Cost (PC):
– PC = O&M + Consumables + Fuel + CO2 Transportation & Storage• O&M: O&M = Fixed + Variable• Consumables: Chemicals, Catalysts, Water, etc.• Fuel: Coal and Natural Gas (backup/flaring)• CO2 Transportation & Storage: $10/tonne• Carrying Charge Factor: 0.1236 (Capital Component of COE)• Constant Dollar COE:
– COE = Total Production Cost + Carrying Charges
Assumed 80% Plant Capacity Factor for All COE Calculations
15© 2009 Electric Power Research Institute, Inc. All rights reserved.
Comparison with Prior EPRI Estimates
0
1,000
2,000
3,000
4,000
5,000
6,000
Tota
l Pla
nt C
ost,
$/kW
Shell Shell CCS Shell Shell CCSUSC-PC USC-PCGE-RQ GE-CCS
PRB Bituminous Coal
Cross-hatched ranges are for corresponding cases in prior year EEE report
16© 2009 Electric Power Research Institute, Inc. All rights reserved.
IGCC Case Study Capital Cost Observations
• There is a broad overlap of cost estimates for IGCC plants both with and without CO2 capture
• Capital costs for PRB plants are 5–10% higher than for plants designed for Pittsburgh #8 coal
• The capital costs are only slightly higher than those shown in the prior EEE report (1014223, Sept. 2008)– Uncertainty bands are now more balanced at +/-
15% versus -5/+20% for IGCC and -5/+10% for PC in prior EEE report
17© 2009 Electric Power Research Institute, Inc. All rights reserved.
EPRI Review of Studies by Others
• IEA Report on Co-Production of H2 and Electric Power– Foster Wheeler adjusted capital cost estimates from 1Q 2007 to
2Q 2008 by using the following factors: Direct materials 1.21, Construction 1.33, Other costs 1.27, and EPC Services 1.33. Delivered coal cost was adjusted to 100 Eu/mt.
• GE In-House IGCC Study on CO2 Capture– Looked at adding “Carbon Island” to IGCC plants w/o capture– Evaluated different levels of capture with single or 2-stage shift
• CoP/WorleyParsons IGCC Study on CO2 Capture at High Elevation– Based on Siemens 5000F gas turbine– Evaluated performance and cost penalties for 0–90% capture
• Several IGCC papers advocate CCS designs for NGCC equivalency (~50-60% CO2 capture).
• CoP/WorleyParsons Feedstock Impact on IGCC with CO2 Capture (~50%)– Gulf coast vs. minemouth performance and cost
18© 2009 Electric Power Research Institute, Inc. All rights reserved.
Existing US Coal Plants—Pay Carbon Tax? Shut Down? Replace with New? CCS Retrofit?
• US Existing boilers >300 MW and <35 years old represent 184 GW. 90% CO2 capture applied to these units would provide a 50% reduction in US coal power CO2 emissions (~1 Billion mt/year).
• Keep running and pay for CO2 allowances or CO2 tax?• Keep running, but at reduced capacity factor (CF), and pay the CO2allowances/taxes?• Shut down—but need to replace power with new build?• New coal plant costs have risen to the point that CCS retrofits may
warrant consideration if: – Space available– FGD and SCR in place– Suitable sequestration site identified– Remaining life of existing plant renders it worthwhile
• Preliminary analysis for 600 MW SCPC suggests LCOE of retrofitted plant lower than new coal plant, and while dispatch cost higher than for new coal is still lower than NGCC at NG >5$/Mbtu.
• EPRI now conducting Multiple site specific CCS Retrofit studies
19© 2009 Electric Power Research Institute, Inc. All rights reserved.
Where Are Capital Costs Headed?
Factors leading to lower capital costs:• Commodity costs are declining from 2008 peaks• Reduced demand due to worldwide recession • Currency exchange rates (country-specific; in United
States, the dollar improved versus other currencies) Factors leading to higher capital costs:
• Need for infrastructure projects in developing nations• Increased project finance costs due to credit crisis
We are indeed in a period of great uncertainty…
20© 2009 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity