equipment and piping 1
TRANSCRIPT
-
7/29/2019 Equipment and Piping 1
1/83
EQUIPMENT & PIPING LAYOUT
N.Todkar
-
7/29/2019 Equipment and Piping 1
2/83
It is very appropriate to say that the
Equipment and Piping layout design is an ART andnot a SCIENCE. There is not a single formula
available for the design of Equipment and Piping
layout. The equipment layout design can be asrational as the mathematics of fluid flow but with
the language of projective geometry. Mathematics
is abstract; geometry is visual. All engineeringcourses have mathematics; few have the subject of
projective geometry but none has layout design
-
7/29/2019 Equipment and Piping 1
3/83
However, systematic methods and procedures
can be developed from engineering principles,
specifications, practical engineering know-how,and just SIMPLE COMMON SENSE.
During the planning stages, the Piping
Engineer could meet with simple ideas that can
effect substantial cost savings. Let us take apractical example to it.
-
7/29/2019 Equipment and Piping 1
4/83
Fig.1.1a
-
7/29/2019 Equipment and Piping 1
5/83
Fig. 1.1b
-
7/29/2019 Equipment and Piping 1
6/83
The design must take constructibility,
economics, safety, quality and operation intoaccount. All these should be achieved within the
shortest schedule and will demonstrate the
technical capacity along with creative talent and
common sense approach to problem solving.Although the tools to achieve these goals have
changed from pencil and paper to computer
graphics, the responsibilities of the Piping
Engineer remains the same.
-
7/29/2019 Equipment and Piping 1
7/83
Design for Constructibility
Ten Commandments:
Keep It Straight and Simple
Keep Its Structures Simple
Keep Its Specification Simple
Keep It Shop Standard Keep Its Standard Simple
Keep It SameSize
Keep It Square and Squatty
Keep Its Support Simple
Keep Its Schedule Sacred
Keep Its Site Suitable
-
7/29/2019 Equipment and Piping 1
8/83
The mechanical design and development of the
plant has three major steps viz.
2.1 Equipment layout design2.2 Conceptual layout design
2.3 Piping layout design
The plant layout can be the biggest cost saver inchemical plant design next to the Process and
Equipment design. Money wasted or saved can be
substantial between alternate layouts. In addition to
capital cost, the plant layout also influences theoperating and maintenance cost. These are long term
benefits that affect profitability.
-
7/29/2019 Equipment and Piping 1
9/83
Incorrectly established plant layouts can have
serious impact on safety and operability. If thelayout do not have enough room, the plant will be
overcrowded, and unsafe and difficult to operate
and maintain. On the other hand, an overly
generous layout results in unnecessary highcapital investment.
-
7/29/2019 Equipment and Piping 1
10/83
-
7/29/2019 Equipment and Piping 1
11/83
-
7/29/2019 Equipment and Piping 1
12/83
UP
UPROOM
TERRACE
DUCT
OPEN SPACE
LIFTUP
UP
6500
6000650025003000
3500 500011 2 3 4 5 6 7 8 9 10 11 12 13
5000 5000 5000 5000 5000 5000 5000 4500 4500 2200
FED
C
B
A
C-4101T-4116
T-4104T-4107
C-4203
T-4211T-4121
R-4126R-4109T-4122T-4125T-4123T-4124
T-4114UPUP
F-4211H-4211P-4008T-4216R-4206H-4212
H-4212
R-1402 C-4201T-4213R-4202R-4201UPUP LIFT
SECOND MEZZ. FLOOR PLAN AT EL. 19.20.40M. N
T-4104C-4102
C-4103
ECP/15
ECP/15
-
7/29/2019 Equipment and Piping 1
13/83
Equipment layout is an extension of the
conceptual layout in more detailed manner. In
the same way as the P&I diagrams are thebasic documents of chemical engineering
design, equipment layout is the basic
document of mechanical engineering design.
This is a composite mechanical engineeringdesign, coordinating the design information to
produce construction drawings.
-
7/29/2019 Equipment and Piping 1
14/83
The essential data required for the
preparation of an Equipment Layout is as
follows:
1. PROCESS FLOW DIAGRAMS (PFD)/
PIPING AND INSTRUMENT
DIAGRAMS (P &ID)
2. PROJECT DESIGN DATA
3. EQUIPMENT SIZES AND BUILINGS
-
7/29/2019 Equipment and Piping 1
15/83
TYPES OF LAYOUTS :
Inline Layout
Similar equipment grouping
Functional equipment grouping
-
7/29/2019 Equipment and Piping 1
16/83
ARRGT-1 :: VERTICAL THERMOSYPHON REBOILER WITH FIXED TUBESHEETS
VAPOUR RETURN CONNECTION
BOTTOM TRAY OF COLUMN
TOP TUBESHEETSUPPORT LUGSHELLSIDE INLET
SUPPORT BRACKETSHELL BELLOWS EXPANSIONJOINT
REBOILER SHELL
LIQUID LEGSHELLSIDE OUTLET
BOTTOM TUBESHEETdcc
COLUMN
-
7/29/2019 Equipment and Piping 1
17/83
ARRGT-1 :: VERTICAL THERMOSYPHON REBOILER WITH FIXED TUBESHEETS
BOTTOM TRAY OF COLUMN
d cc
COLUMN
VAPOUR RETURN CONNECTION
TOP TUBESHEET
SUPPORT LUG
SHELLSIDE INLET
SUPPORT BRACKET
REBOILER SHELL
SHELLSIDE OUTLET
BOTTOM TUBESHEET
COLUMN SHELL
BELLOWS EXPANSION JOINT
-
7/29/2019 Equipment and Piping 1
18/83
ARRGT-3 :: VERTICAL FIXED TUBERSHEET REBOILER WITH INDEPEDENTSUPPORT STRUCTURE.
c
COLUMN
VAPOUR RETURN
TOP HEAD
REBOILER SUPPORTSTRUCTURE
SUPPORT LUG
LIQUID LEG
BOTTAM HEAD
SKIRT
SPRING SUPPORT
BELLOWS EXPANSION JOINT
TOP TUBESHEET
BOTTAM TUBESHEET
-
7/29/2019 Equipment and Piping 1
19/83
The following guidelines and cautions are helpful
in improving the accuracy comparisons.
i) Make comparison to as similar a
plant as possible.ii) Use similar assumptions in
analyzing both existing facilities and
new design.
iii) For outdoor installation, wherevolume has less relevance than in
and enclosed structure, rely on the
area comparison alone.
iv) For tank farm, general guidelines
dictated for fire safety reasons or
statutory requirements govern.
-
7/29/2019 Equipment and Piping 1
20/83
-
7/29/2019 Equipment and Piping 1
21/83
EQUIPMENT LAYOUT DRAWING GUIDE LINES
The following are the guidelines generally
followed while making an Equipment layout
drawing.
a) Equipment layout shall be drawn in 1:50 or
1:100 scale.
b) A0 size drawing sheet should generally be used for
equipment layout. If the area to be covered is small,A1 size can be used.
c) Place north arrow at the top right hand corner of
the sheet to indicate plant north.
d) The area above title block to be kept free forgeneral notes and reference drawings.
-
7/29/2019 Equipment and Piping 1
22/83
e) All equipments are marked with its equipment no. as
appearing in Equipment list & dimensions (diameter,
height/length etc.)f) All equipments center line are located in
plant building w.r.t. the column grid. For layout of outdoor plant /
offsite facility, the equipment shall be located by co-ordinates.
g) Conceptual layout, P & ID, vendor/fabricated equipment
drawings are to be used as basic document for preparing equipmentlayout drawing.
h) Walkways, cutouts, piperacks, floor drains, gutter, trenches,
ramp etc. if applicable should be clearly marked in the drawing.
-
7/29/2019 Equipment and Piping 1
23/83
i) For in house plant layout, the location
of staircases, lift & other utility areasshould be clearly shown.
j) In equipment layout sectional drawing, for each
equipment its top most or bottom most elevations should
be marked. k) Orientation of equipment shall be clearly marked for all
the equipments by orienting one of the major nozzles.
l) In case of reactors / tanks, the location of manhole /
handhole, SG/LG,LI etc. shall be at accessible position.
m) Equipment lifting cutout shall be marked clearly in the
drawing.
-
7/29/2019 Equipment and Piping 1
24/83
n) Equipment planned to be installed in future
shall be shown dotted.o) For heat exchangers, tube removal /
cleaning space shall be marked.
p)While locating the pumps care shall be taken to ensure
that the NPSH requirement is met.
q) General notes are written on one of the drawings (first)
and shall not be repeated on all layouts but reference
shall be given.
r) Direction of north shall be maintained same for all the
plans for the same plant / project.
-
7/29/2019 Equipment and Piping 1
25/83
s) If more than one drawing is required to cover a
specified area, then the match line shall be indicated clearlywith the reference drawings.
t) One of the general notes should specify the
absolute level of the area covered with respect to the plot.
u) The equipment load, operating or test load
whichever is maximum shall be considered for design and the
layout should indicate this along with the dynamic factor
wherever applicable. This could also be covered in table as
well.
-
7/29/2019 Equipment and Piping 1
26/83
v) For reactors with agitators, lifting beam shall be
provided for agitator removal.
w) For vendor equipments maintenance
space as recommended by them for
maintenance shall be provided.
x) Equipment layout shall also indicated the
positions of utility stations, safety shower and eye wash.y) Equipment elevation shall be so arranged to
ensure gravity flow where specified.
-
7/29/2019 Equipment and Piping 1
27/83
In terms of the equipment arrangement, the equipment
layout (unit plot plan) can basically be divided into two
configurations:
a) The grade mounted horizontal
arrangement as seen in the refineries
and petrochemical plants, and
b) The vertical arrangement found inmany chemical process industries.
-
7/29/2019 Equipment and Piping 1
28/83
Irrespective of the type of arrangement, there are certain
basic principles to be followed while locating the equipment.
Economic piping Process requirements
Common Operation
Underground facilities
Climatic conditions
-
7/29/2019 Equipment and Piping 1
29/83
-
7/29/2019 Equipment and Piping 1
30/83
-
7/29/2019 Equipment and Piping 1
31/83
-
7/29/2019 Equipment and Piping 1
32/83
-
7/29/2019 Equipment and Piping 1
33/83
TYPICAL CROSS SECTION OF AN INDOOR
PROCESS PLANT
Fig. 2.2.6a
-
7/29/2019 Equipment and Piping 1
34/83
TYPICAL CROSS SECTION OF INDOOR CHEMICAL PLANT
Fig. 2.2.6b
-
7/29/2019 Equipment and Piping 1
35/83
PHILOSOPHY OF IN-PLANT PIPING
o
o Value Location
o Electrical/Instrument Cable Trays
o Statuary requirements
o Miscellaneous
o
-
7/29/2019 Equipment and Piping 1
36/83
So, the first step in the development of pipe rack is the
generation of a line routing diagram. A line routing
diagram is a schematic representation of all process and utility
piping systems drawn on a copy of plot plan or it could beplanometric representation of the utility and process line
diagrams. Although it disregards the exact locations, elevations
or interferences, it locates the most congested area.
-
7/29/2019 Equipment and Piping 1
37/83
The pipe rack splits the plant area into convenient parts.
The pipe rack takes various shapes such as straight,L,T, and
C orU. This configuration is based on the overall arrangement
and site conditions. Based on the incoming/outgoing lines and
locations, the pipe rack is laid.
-
7/29/2019 Equipment and Piping 1
38/83
Fig. 2.3.1
-
7/29/2019 Equipment and Piping 1
39/83
Fig. 2.3.2
-
7/29/2019 Equipment and Piping 1
40/83
Fig. 2.3.3
-
7/29/2019 Equipment and Piping 1
41/83
Fig. 2.3.4
-
7/29/2019 Equipment and Piping 1
42/83
Fig. 2.3.5
-
7/29/2019 Equipment and Piping 1
43/83
Fig. 2.3.6
-
7/29/2019 Equipment and Piping 1
44/83
Fig. 2.3.7
The configuration of pipe rack is not determined while doing
-
7/29/2019 Equipment and Piping 1
45/83
g p p g
the plant layout.
The arrangement results from an overall plant layout, site
conditions, client requirements and above all plant economy.
The width of the pipe rack is estimated asW = (f x n x s) + A + B
f = Safety factor
= 1.5 if pipes are counted from the PFD
= 1.2 if pipes are counted from P & ID.n=Number of lines in the densest area upto the size of 450NB
s = 300mm (estimated average spacing)
= 225mm (if lines are smaller than 250 NB)
A = Additional width for
(1) Lines larger than 450 NB(2) For instrument cable tray/duct
(3) For electrical cable tray
B = Future provision
= 20% of (f x n x s) + A
1 5 TO 2M
-
7/29/2019 Equipment and Piping 1
46/83
Fig. 2.3.8
1.5 TO 2M
TYPE 15 TO 6M 1TO 1.2M
TYPE 2
-
7/29/2019 Equipment and Piping 1
47/83
5 TO 6M
TYPE 3
The Headroom normally provided is as below.
-
7/29/2019 Equipment and Piping 1
48/83
y p
Sr. Description Headroom
No. (mm)
1. Clear head room under 2200
Structures/pipe linesinside operating area.
2. Head room over rail 7000
(from top of rails)
3. Clear headroom above 7000crest of road for crane
movement.
4. Clear headroom above 600
crest of road for truck
movement.5. Clear headroom above 4500
crest of road between
process units.
-
7/29/2019 Equipment and Piping 1
49/83
P & I diagram, equipment layout, piping
specifications, equipment drawing and the vendor
requirement for proprietary equipment form the basis of a
piping layout. In areas where piping is critical, theequipment locations are fixed only after a pipingstudy is
made.
-
7/29/2019 Equipment and Piping 1
50/83
Fig. 2.3.9a
-
7/29/2019 Equipment and Piping 1
51/83
-
7/29/2019 Equipment and Piping 1
52/83
Fig. 2.3.10
-
7/29/2019 Equipment and Piping 1
53/83
Fig. 2.3.11
-
7/29/2019 Equipment and Piping 1
54/83
-
7/29/2019 Equipment and Piping 1
55/83
Fig. 2.3.13
-
7/29/2019 Equipment and Piping 1
56/83
Fig. 2.3.14
-
7/29/2019 Equipment and Piping 1
57/83
Fig. 2.3.15
-
7/29/2019 Equipment and Piping 1
58/83
Fig. 2.3.16
-
7/29/2019 Equipment and Piping 1
59/83
Fig. 2.3.17
-
7/29/2019 Equipment and Piping 1
60/83
Fig. 2.3.18
-
7/29/2019 Equipment and Piping 1
61/83
Fig 2.3.19
-
7/29/2019 Equipment and Piping 1
62/83
Fig 2.3.20
-
7/29/2019 Equipment and Piping 1
63/83
Fig 2.3.21a
-
7/29/2019 Equipment and Piping 1
64/83
Fig 2.3.21b
-
7/29/2019 Equipment and Piping 1
65/83
Fig 2.3.22
-
7/29/2019 Equipment and Piping 1
66/83
2.3.5 PIPING FOR INSTRUMENTS
Instruments,when located on piping ,will need certain
specific requirement for it to perform the duty for which it is
provided. Piping Engineer should be aware of there
requirement and should take care of the same while routing
these pipe line.
a) Flow measurement instrument need certain straight lengthupstream and downstream of the instrument.This is normally
15D on the upstream and 5D on the downstream.
b) The pipe lines in which flow meters such as magneticflowmeters ,vortex meters ,turbinemeters etc are located should
be routed in such a way that the line will be full with liquid all
the time.The pipe line should be supported on both sides of
meter.
c) Control valves are located at grade at about 500mm height to
-
7/29/2019 Equipment and Piping 1
67/83
c) Control valves are located at grade, at about 500mm height to
provide convenient access for operation and maintenance. Block
and bypass valve also form the same criteria. The standard
arrangements followed are as perFig 2.3.23. If pocketing theprocess line is unacceptable, then a permanent or mobile platform
should be planned, as access is very important. Locating control
values on the vertical line should be avoided.If is unavoidable; the
should actuator should be supported properly.The bypass should
be selected for easy operation.
d) Isolation valves for level gauges and pressure gauges shall be
made accessible. Access and space for the removal of level
controllers temperature probes ,conductivity probes,bottom flagsof the control values etc shall be provided. All primary and
secondary indicators of pressure, temperature, flow, level,
positioners etc. should be visible from the operating area.
-
7/29/2019 Equipment and Piping 1
68/83
e) Rotameters shall be placed on vertical line and the inlet
should be from the bottom of the instrument.
f) Thermowell shall be located on the pipe line of required
size.Instrument hook up shall be reffered for the requirement.
g) Enough operating and maintance occur shall be considered
while locating any instrument.
-
7/29/2019 Equipment and Piping 1
69/83
Fig. 2.3.23
-
7/29/2019 Equipment and Piping 1
70/83
Fig. 2.3.24
-
7/29/2019 Equipment and Piping 1
71/83
The requirement as per the following shall be
adhered to
a) The Factories Act 1948.
b) The Petroleum Act 1934 & The Petroleum
rules 1976.
c) The Static and Mobile Pressure Vessels
(unfired) Rules 1981.
d) The Gas Cylinders Rules 1981.
e) The Indian Boiler Regulations 1951.
f) Development control rules by the State
Industrial Development Corporation.
-
7/29/2019 Equipment and Piping 1
72/83
BFW
TANK
ECONOMISER
BFW
HP DOSING
BFWLINE
BOILER FEED
WATER PUMP
DOSING TANK
DOSING PUMP
PI
MAINSTEAM
MANIFOLD
CONSUMER
ST
Y
ST
TO ATMOS.
(TYP)
LG LG LG LG
BLOW DOWN
DRAIN
BLOW DOWN TANK
NOTE:-
PIPE LINESTHE PURVIEW OF IBR SHOWN WITH THICH LINES.
IBR SCOPE
IBR SCOPE
-
7/29/2019 Equipment and Piping 1
73/83
2.3.8 CRITICAL EXAMINATION TECHINIQUE
The quality of the equipment and piping layout can be
established by the Critical Examination Technique where you
ensure that all the following parameters are well addressed
a) It is process adequate?b) It is operator friendly?
c)It is construction clear?
d)Has adequate maintenance access provided?
e)How to evacuate in case of emergency?f)Has safe fire fighting access provided?
g)Standard practices where applicable has been adopted?
h)Is the piping arrangement aesthetic ?
i)Is supporting arrangement adequate and aesthetic ?
j) Is piping adequately flexible ?
-
7/29/2019 Equipment and Piping 1
74/83
Pumps rarely influences the plant layout except where a
common standby for two services or multiple duty pumps
might dictate the process equipment arrangement. But the
pumps can never be treated as an independent entity, but to betreated as part of the piping system which affects the
performance even if the basic selection is faultless.
-
7/29/2019 Equipment and Piping 1
75/83
The design of equipment and piping configuration
affect the energy used and capital cost of pumps. Hence,
economy of piping and structures along with ease of
operation and maintenance are the principal aim whilearranging the pumps.
-
7/29/2019 Equipment and Piping 1
76/83
The primary goal in locating the pump is to minimize the
piping configuration while satisfying the performance and
flexibility requirements as well as allowable loads that may
be subjected to the nozzles.
Mechanical or Chemical Engineers can no longer consider
the pump as an independent entity, but to be treated as a part
of the Piping System.
-
7/29/2019 Equipment and Piping 1
77/83
Fig. 3.1.1a
-
7/29/2019 Equipment and Piping 1
78/83
Fig. 3.1.1b
-
7/29/2019 Equipment and Piping 1
79/83
Fig. 3.1.2
-
7/29/2019 Equipment and Piping 1
80/83
Fig. 3.1.3
-
7/29/2019 Equipment and Piping 1
81/83
-
7/29/2019 Equipment and Piping 1
82/83
-
7/29/2019 Equipment and Piping 1
83/83