erie apron addendum no. 4
TRANSCRIPT
X:\3225600\201146.01\TECH\Bid Administration\Addenda\04\Erie Apron Addendum No. 4.doc
Page 1 of 1
Project name:
Rehabilitate and Expand Terminal
Apron Client: Erie Regional Airport Authority
Project location: Erie, PA Client representative: Kimberlie Sharrer
Project number: 3225600-201146.01 Mead & Hunt, Inc. manager: Sean Thompson
Date: March 15, 2021 Mead & Hunt Inc. phone: 517.908.3103
TO ALL BIDDERS: You are requested to make all changes and/or additions contained in this Addendum
to the Bidding Documents. Failure to acknowledge this Addendum in Proposal may result in rejection of
bid.
I. GENERAL
None
II. GENERAL QUESTIONS AND ANSWERS
A. See provided Q&A sheet attached.
III. PROPOSAL DOCUMENTS
None.
IV. DRAWINGS
A. Replace sheet C-101 Construction Safety Phasing Plan – Phase 1 in its entirety with attached C-
101 included with this addendum.
B. Replace sheet C-102 Construction Safety Phasing Plan – Phases 2 & 3 in its entirety with
attached C-102 included with this addendum.
C. Add sheet C-152 Construction Safety Phasing Details included with this addendum.
D. Revise sheet C-461 to indicate that detention bed clean outs are to be 6 inches diameter instead
of 4 inches diameter as noted.
V. SPECIFICATIONS
A. Add specification F-162 included with this addendum. B. Modify specification D-651 to exclude detention beds from camera inspection and laser profile.
END OF ADDENDUM
Addendum No. 4 Erie International Airport Rehabilitate and Expand Terminal Apron
Number Question Answer
63
How many people need badges? What is the cost?
Badged personnel may escort unbadged personnel as long as
they remain in control of the escorted individual. The cost
per badge is $75.
64
Per addendum No. 1, the response to the question 28 states, The contractor is responsible to perform the camera inspection and laser profiling. The detention beds are included.”; However, after speaking with multiple pipe inspection companies, they cannot perform inspection of the detention beds due to the maneuverability of the equipment within the facility. Can inspection be omitted for the BMP Areas?
Since the clean out openings are not large enough to
perform the inspection and maneuverability is not possible,
the detention beds will not require camera inspection and
laser profile.
65
Question 28 in addendum 1 that camera inspection and laser profile is required for the detention beds. A
company that performs these services advised that It is not possible for anyone to profile detention
systems since the camera cannot turn 90 degrees. Can this activity be officially deleted from the bidding
scope of work?
Since the clean out openings are not large enough to
perform the inspection and maneuverability is not possible,
the detention beds will not require camera inspection and
laser profile.
66
On the bid pricing sheet item #11002 duct bank 4 way 3”, where is this on the drawings? I cannot find any
of this type duct bank.
4 way 3" duct bank is not identified on the plans. However,
some duct bank sizes are unknown or have conflicting record
drawing information.
67
On Drawing E202 Detail A shows signs 4,5, and 6. There is no electric show to these signs, is this correct?
signs 4, 5, and 6 are existing signs that are proposed to have
panel replacements. Electrical connection is irrelevant to the
work and not illustrated.
68
Drawing E211, and E611 calls for 3 – 1” innerducts in each occupied 4” conduit (providing spare empty
innerduct), but on the bid form Item #11006 only has enough innerduct for the fiber optic cable, (no Sper
innerduct), What quantity should we bid? bid the quantity included on the bid form.
69
Due to the extreme vagueness, and lack of information, can you suggest an allowance of manhours to put
in the bid, so all contractors are bidding equally? This could days, or weeks, depending on what is found in
the manholes. No estimate will be made.
70
Spec Section X‐108‐B‐6 calls for patch panels as shown on drawing, none are shown, are we to assume that
the new fiber will terminate in existing patch panels?
Airport security fiber is to be fused to existing fiber at
existing box in a manhole south of Taxiway D as shown on E‐
211. The FAA cable will be terminated inside the glideslope
shelter.
71
In regard to access road restoration (at airport property or township), it has been clarified that it is the
contractors responsibility for repairs. Though, it is not possible to determine quantities of potential
damage and materials for restoration. Is it possible to add a bid item for access road restoration per cubic
yard for options of asphalt placement and millings replacement?Haul route access has been changed. See revised plans for
additional details.
72
The bid form calls out an aircraft rated inlet, triple grate w/ type 7 box. However, the revised plans do not
show this structure. Can you please provide the station for this structure? The inlet is at Sta. 4+35.
73
There are several references in the notes on the bid plans that refer to the erection of
temporary safety fencing along AOA areas. However, the fencing locations are not indicated on the
drawings. Is the temporary fencing required on this project? If so, can the locations of such fencing be
indicated on the plans?
Safety fence is not located on the plans and does not need to
be installed.
74
It is understood that all vehicles/equipment operating on the airside of the airport property will need to
display 3’x3’ orange/white flags and/or amber beacons. Will all vehicles/equipment also be required to
display placards?
vehicles shall meet the requirements of FAA AC 150/5210‐5.
this does not require placards.
75
The plans provide a detail for the runway and taxiway closure “X” markings, but do not indicate that those
markings need lighted. Note 2.18.1 on plan sheet G‐112 indicates lighted runway closure X’s. Are the
runway/taxiway closure X’s required to be lighted
closure crosses shown on Runway 2‐20 are surface painted
and not lighted
76
Note 3 on plan sheet G‐102 indicates that the contractor is to coordinate with the airport for an airport
employee gate guard at AOA access gate 4. Note 2.9.4 on plan sheet G‐111 states, “The contractor shall
not permit any unauthorized construction personnel or traffic on the project site. The contractor shall be
responsible for traffic control to and from the project site.” Is the gate guard at gate 4 to be an airport
employee or a contractor employee? If the guard is to be an airport employee, is the contractor
responsible for the guard’s wages and at what rate of paymentGate guards will be supplied by the contractor. See revised
plan sheets.
77
In regards to the placement of the concrete pavement. Is the area of concrete paving included in this
project considered mainline paving requiring slip form or machine finishing with fixed form paving? If the
concrete paving is not considered mainline paving, is the use of a bridge deck paver acceptable in
conjunction with a minimum of two immersion vibrators? If the concrete paving is not considered
mainline paving, will vibrating or roller screeds be allowed in conjunction with hand operated vibrators?
See RFI response 1. Slipe form pavers are not required due to
project size. Paving equipment shall meet requirements of P‐
501 and will be evaluated by the RPR for compliance at that
time.
78The spec’s call for either 62.4 um or 50um fiber, which fiber should be used on this project? 50 um multimode fiber should be utilized. The contractor
shall confirm exisitng fiber size prior to ordering.
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
OFZ OFZOFZOFZOFZOFZOFZ
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
RSA RSA RSA
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA
XX
XX
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
XX
XX
X
X
XX
XX
XX
XX
XX
X
X
X
X
X
X
X
X
X
X
X
X
X
C
a
n
a
d
a
ir C
R
J 2
0
0
E
m
b
ra
e
r E
R
J
-1
4
5
L
R
C
anadair C
R
J 200
Em
braer E
R
J-145LR
C
a
n
a
d
a
ir C
R
J
2
0
0
E
m
b
ra
e
r E
R
J
-1
4
5
L
R
>
>
>
>
>
>
>
>
>
>
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
TOFA TOFA TOFA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
TO
FA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
>
CONSTRUCTION SAFETY
PHASING PLAN - PHASE 1
SCT
MDB
MDB
X:\3
22
56
00
\2
01
14
6.0
1\T
EC
H\C
AD
\D
RA
WIN
GS
\G
-1
01
C
ON
ST
S
AF
ET
Y P
HA
SIN
G P
LA
N.D
WG
3/1
2/2
02
1 4
:2
8:4
9 P
M
3
00 150 300
NOT FOR CONSTRUCTION
41
3225600-201146.01
02.18.21
SHEET CONTENTS
DO NOT SCALE DRAWINGS
M&H NO.:
DATE:
DESIGNED BY:
DRAWN BY:
CHECKED BY:
ISSUED
These documents shall not be used for any purpose or
project for which it is not intended. Mead & Hunt shall
be indemnified by the client and held harmless and
defended from all claims, damages, liabilities, losses,
and expenses, including attorneys' fees and costs,
arising out of such misuse or reuse of the documents.
In addition, unauthorized reproduction of these
documents, in part or as a whole, is prohibited.
of
SHEET NO.
Mead and Hunt, Inc.
2605 Port Lansing Road
Lansing, MI 48906
phone: 517-321-8334
meadhunt.com
GENERAL NOTES:
1. THE CONTRACTOR IS RESPONSIBLE FOR PLACEMENT AND REMOVAL OF RUNWAY CLOSURE MARKINGS
AND BARRICADES. COORDINATE WITH THE RPR AND AIRPORT TO CONFIRM NOTAM'S ARE ISSUED AND
APPROPRIATE RUNWAY AND TAXIWAY LIGHTING CIRCUITS ARE DISABLED.
2. THE CONTRACTOR SHALL LOCK OUT/TAG OUT ALL ELECTRICAL CIRCUITS TO CLOSED PAVEMENTS AND
INSTALL TEMPORARY JUMPERS WHERE NECESSARY TO LIGHT OPEN PAVEMENTS. THE CONTRACTOR
SHALL PROVIDE A TEMPORARY JUMPER PLAN 14 DAYS PRIOR TO PHASE CHANGE FOR APPROVAL BY
THE RPR AND AIRPORT. ELECTRICAL LOCK OUT/TAG OUT AND TEMPORARY INSTALLATION SHALL BE
INCIDENTAL TO MOBILIZATION.
3. THE CONTRACTOR SHALL PROVIDE GATE GUARD(S) AT ALL CONSTRUCTION ENTRANCES. COORDINATE
ADDITIONAL TRAINING WITH THE AIRPORT OPERATOR.
4. THE CONTRACTOR SHALL REQUEST A SAFETY AND LIGHTING INSPECTION BY AIRPORT OPERATIONS
PRIOR TO LEAVING THE CONSTRUCTION SITE AFTER EACH WORKING DAY. THE SAFETY INSPECTION
SHALL INCLUDE THE CONDITION OF ACTIVE OPERATION AREAS ADJACENT TO THE CONSTRUCTION LIMIT,
THE CONDITION OF THE CONTRACTOR STAGING AREA AND THE SECURITY OF THE CONSTRUCTION
ENTRANCE(S). THE CONTRACTOR'S SUPERVISOR SHALL REMAIN ON SITE UNTIL THE SAFETY INSPECTION
IS COMPLETE AND ALL DEFICIENCIES HAVE BEEN CORRECTED TO THE SATISFACTION OF THE AIRPORT
OPERATIONS DEPARTMENT.
5. ACCESS TO THE SITE WILL BE FROM 12TH STREET. THE CONTRACTOR SHALL OBTAIN PERMISSION AND
PERMITS FROM PENNDOT FOR TEMPORARY CONSTRUCTION ENTRANCE. ADDITIONALLY, THE
CONTRACTOR SHALL INSTALL CONSTRUCTION ENTRANCE ROADWAY SIGNAGE AS REQUIRED BY
PENNDOT AND IN COMPLIANCE WITH MUTCD. ALL COSTS FOR TEMPORARY ENTRANCE INCLUDING
FENCE REMOVAL, TEMP FENCE, FENCE REINSTALLATION, AND HAUL ROAD ARE AT THE CONTRACTOR'S
EXPENSE EXCEPT PERMIT FEES WILL BE PAID FOR UNDER PERMITS PAY ITEM FOR ACTUAL PERMIT
COSTS WITH NO MARK UPS.
AFFECTED ACTIVE OPERATION
AREAS (AOA'S)
WORK
HOURS
SAFETY AND SECURITY
CONTRACT
TIME
CONSTRUCTION
49
1. RWY 2-20 CLOSED
1.1 OPEN TO TAXI SOUTH OF TWY D DURING
DAYTIME ONLY, LIGHTS DISABLED SO NOT
AVAILABLE FOR TAXI NIGHTTIME
2. TWY C CLOSED WEST OF HANGAR TAXIWAY
3. TWY E PERMANENTLY CLOSED
4. TERMINAL APRON PARTIALLY CLOSED
NORMAL /
UN-
RESTRICTED
PHASE
CONSTRUCT NORTHEASTERN PORTION OF TERMINAL APRON EXPANSION AS
SHOWN. BEGIN REMOVAL OF TAXIWAY E. COMPLETE TAXIWAY EDGE
LIGHTING, EDGE RESTORATION AFTER PAVING, AND PLACE HALF-RATE
MARKING ON NEW PAVEMENTS.
1
(SEE SHEET G-102 FOR CONTINUATION OF CONTRACT TIME)
RUNWAY 6-24:
RDC: C-II-2400
RSA: 500' WIDE
OFZ: 400' WIDE
OFA: 800' WIDE
RUNWAY 2-20:
RDC: B-II-VISUAL
RSA: 150' WIDE
OFZ: 400' WIDE
OFA: 500' WIDE
TAXIWAYS:
TDG: 3 ADG: III
TSA: 118'
OFA: 186'
PHASE 1
WORK AREA LIMITS
R
W
Y
2
-
2
0
T
W
Y
C
T
W
Y
D
TWY A
T
W
Y
B
T
W
Y
F
TW
Y E
CONTRACTOR SHALL ESTABLISH
TRAFFIC CONTROL TO MAINTAIN GSE
TRAFFIC ACCESS TO BAGGAGE
HANDLING AREAS
BAGGAGE HANDLING
AREAS
PHASE 1
CONTRACTOR STAGING
AND STORAGE AREA
(MAX EQUIP HT 25')
A
B
C
1. THE CONTRACTOR SHALL NOTIFY THE AIRPORT AT LEAST 5 DAYS IN ADVANCE OF WORK AND PHASE
CHANGES SO THAT THE AIRPORT MANAGEMENT CAN ISSUE A NOTAM OF CONSTRUCTION ACTIVITY.
2. ALL GATES MUST BE LOCKED OR GATE GUARD POSTED.
3. ALL CONTRACTOR PERSONNEL WORKING ON-SITE SHALL UNDERGO AIRPORT TRAINING AND HAVE AIRPORT
ISSUED BADGE.
4. MAXIMUM EQUIPMENT HEIGHT FOR THE PROPOSED WORK AREA IS 25' UNLESS OTHERWISE NOTED.
CRITICAL DIMENSIONS (TOTAL WIDTH):
D
CONTRACTOR LANDSIDE
EMPLOYEE PARKING AREA
WITHIN LONG TERM PARKING
LOT
POINT
A
B
C
D
E
F
G
H
I
DESCRIPTION
WORK AREA
WORK AREA
WORK/STAGING AREA
WORK AREA
WORK AREA
WORK AREA
WORK/STAGING AREA
WORK AREA
WORK AREA
FAA AIRSPACE AND 7460 INFORMATION
HEIGHT
AGL
25'
25'
25'
25'
25'
25'
25'
25'
25'
LATITUDE
N42° 04' 52.24"
N42° 05' 00.43"
N42° 04' 58.37"
N42° 04' 52.72"
N42° 04' 51.39"
N42° 04' 54.38"
N42° 04' 56.97"
N42° 04' 51.64"
N42° 04' 49.68"
LONGITUDE
W80° 10' 46.46"
W80° 10' 46.17"
W80° 10' 52.10"
W80° 10' 49.88"
W80° 10' 47.58"
W80° 10' 45.98"
W80° 10' 53.83"
W80° 10' 56.56"
W80° 10' 44.47"
GROUND
729'
726'
726'
729'
730'
729'
726'
730'
730'
SEE SHEETS G-101 TO G-102 FOR AIRSPACE REVIEW COORDINATES
TERMINAL
1
2
T
H
S
T
R
E
E
T
S
H
E
N
K
A
V
E
INSTALL RWY CLOSURE MARKING
AND DISABLE RWY 2-20 LIGHTING
CIRCUITS AT INITIATION OF PHASE
LEGEND
EXISTING PAVEMENTS
LIGHTED BARRICADE (PHASE IF APPLICABLE)
WORK AREA BOUNDARY
CONTRACTOR HAUL ROUTE
GROUND SERVICE EQUIPMENT (GSE) ROUTE
RUNWAY OBJECT FREE ZONE
RUNWAY SAFETY AREA
TAXIWAY OBJECT FREE AREA
1
RSA
>
OFZ
XXXXXXXXXXXXXXXXX
USCBP
02.18.21 BID SET
G-101
ER
IE
IN
TE
RN
AT
IO
NA
L A
IR
PO
RT
RE
HA
BILIT
AT
E A
ND
E
XP
AN
D
TE
RM
IN
AL A
PR
ON
44
11
W
ES
T 1
2T
H S
TR
EE
T
ER
IE
, P
EN
NS
YL
VA
NIA
H
A
N
G
A
R
T
A
X
I
L
A
N
E
TOFA
CONSTRUCT TEMPORARY
CONSTRUCTION GATE AND
FENCE.
TEMPORARY HAUL ROUTE.
REMOVE AT COMPLETION
OF THE PROJECT.
2 03.15.21 ADDENDUM 4
2
2
2
2
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
OFZOFZ OFZOFZOFZOFZOFZ
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
O
F
Z
RSA RSA RSA RSA
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
R
S
A
RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA
FA
A
FA
A
FA
A
F
A
A
FA
A
XX
XX
XX
XX
XXXXXXX
XX
XX
XX
XX
X
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
Canadair C
RJ 200
Em
braer E
RJ-145LR
Canadair C
RJ 200
Em
braer E
RJ-145LR
C
anadair C
R
J 200
E
m
braer E
R
J-145LR
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
XX
XX
XX
XX
XX
XX
X
XXXXXXXX
XX
XX
XXXX
XXXX
XX
X
X
X
X
X
X
X
X
X
X
XXXXXXXXXXXXXXXXX
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
>
>
TOFA TOFA TOFA TOFA TOFA TOFA TOFA
TOFA TOFA TOFA
T
O
F
A
T
O
F
A
>
>>
>
>
>
>
>
>
>
>
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
TOFA TOFA TOFA
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
T
O
F
A
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
XX
XX
XX
XX
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
XXXXXXX
X
X
X
X
X
X
X
X
>
CONSTRUCTION SAFETY
PHASING PLAN - PHASES 2
& 3
SCT
MDB
MDB
X:\3
22
56
00
\2
01
14
6.0
1\T
EC
H\C
AD
\D
RA
WIN
GS
\G
-1
01
C
ON
ST
S
AF
ET
Y P
HA
SIN
G P
LA
N.D
WG
3/1
2/2
02
1 4
:2
8:5
2 P
M
4
NOT FOR CONSTRUCTION
41
3225600-201146.01
02.18.21
SHEET CONTENTS
DO NOT SCALE DRAWINGS
M&H NO.:
DATE:
DESIGNED BY:
DRAWN BY:
CHECKED BY:
ISSUED
These documents shall not be used for any purpose or
project for which it is not intended. Mead & Hunt shall
be indemnified by the client and held harmless and
defended from all claims, damages, liabilities, losses,
and expenses, including attorneys' fees and costs,
arising out of such misuse or reuse of the documents.
In addition, unauthorized reproduction of these
documents, in part or as a whole, is prohibited.
of
SHEET NO.
Mead and Hunt, Inc.
2605 Port Lansing Road
Lansing, MI 48906
phone: 517-321-8334
meadhunt.com
00 150 300
RWY 6-24
AFFECTED ACTIVE OPERATION
AREAS (AOA'S)
WORK
HOURS
SAFETY AND SECURITY
CONTRACT
TIME
CONSTRUCTION
63
1. RUNWAY 2-20 CLOSED
1.1 OPEN TO TAXI SOUTH OF TWY D DURING
DAYTIME ONLY, LIGHTS DISABLED SO NOT
AVAILABLE FOR TAXI NIGHTTIME
2. TWY E PERMANENTLY CLOSED
3. TERMINAL APRON PARTIALLY CLOSED
4. USCBP AIRCRAFT PARKING POSITION RELOCATED
NORMAL /
UN-
RESTRICTED
PHASE
CONSTRUCT SOUTHWESTERN PORTION OF TERMINAL APRON EXPANSION
AS SHOWN. COMPLETE REMOVAL OF TAXIWAY E INCLUDING SAWCUTTING,
PAVEMENT REMOVAL, TOPSOIL GRADING, SEEDING AND MULCHING.
COMPLETE TAXIWAY EDGE LIGHTING AND GUIDANCE SIGN
MODIFICATIONS, EDGE RESTORATION AFTER PAVING, AND PLACE
HALF-RATE MARKING ON NEW PAVEMENTS. COMPLETE FAA FIBER OPTIC
CABLE WORK.
2
RUNWAY 6-24:
RDC: C-II-2400
RSA: 500' WIDE
OFZ: 400' WIDE
OFA: 800' WIDE
RUNWAY 2-20:
RDC: B-II-VISUAL
RSA: 150' WIDE
OFZ: 400' WIDE
OFA: 500' WIDE
TAXIWAYS:
TDG: 3 ADG: III
TSA: 118'
OFA: 186'
1. THE CONTRACTOR SHALL NOTIFY THE AIRPORT AT LEAST 5 DAYS IN ADVANCE OF WORK AND PHASE CHANGES SO THAT
THE AIRPORT MANAGEMENT CAN ISSUE A NOTAM OF CONSTRUCTION ACTIVITY.
2. ALL GATES MUST BE LOCKED OR GATE GUARD POSTED.
3. ALL CONTRACTOR PERSONNEL WORKING ON-SITE SHALL UNDERGO AIRPORT TRAINING AND HAVE AIRPORT ISSUED
BADGE.
4. MAXIMUM EQUIPMENT HEIGHT FOR THE PROPOSED WORK AREA IS 25' UNLESS OTHERWISE NOTED.
5. PHASE 2A CONSTRUCTION DURATION IS NOT CONSECUTIVE. 5 DAYS PRIOR NOTICE FOR CLOSURE OF TAXIWAY D IS
REQUIRED.
CRITICAL DIMENSIONS (TOTAL WIDTH):
INSTALL TEMPORARY LEAD-IN
LINES AT START OF PHASE 2;
AFTER COMPLETION OF PHASE 2
REMOVE TEMPORARY AND
INSTALL PERMANENT GATE
MARKINGS AND LEAD-IN LINES
FOR GATES 3 AND 5.
SCHEDULING NOTE: FINAL MARKING WORK MUST OCCUR A MINIMUM OF 30 DAYS AFTER COMPLETION OF RESPECTIVE ASPHALT PAVING, A STOP ORDER IS ANTICIPATED.
2
1. COORDINATE TEMPORARY CLOSURES ON
APRONS, TAXIWAYS, AND RUNWAYS WITH
AIRPORT OPERATIONS.
NORMAL /
UN-
RESTRICTED
COMPLETE FULL RATE MARKING OF NEW PAVEMENTS.
3
1. WORK SHALL TAKE PLACE ON A PULL-OFF BASIS. CONSTRUCTION TRAFFIC MUST YIELD TO ALL AIRCRAFT.
TOTAL CONTRACT TIME: 114 CALENDAR DAYS
PHASE 2
WORK AREA BOUNDARY
R
W
Y
2
-
2
0
T
W
Y
C
T
W
Y
D
TWY A
T
W
Y
B
T
W
Y
F
TW
Y E
CONTRACTOR SHALL ESTABLISH
TRAFFIC CONTROL TO MAINTAIN
GSE TRAFFIC ACCESS TO
BAGGAGE HANDLING AREAS
BAGGAGE HANDLING
AREAS
PHASE 2
CONTRACTOR STAGING
AND STORAGE AREA
(MAX EQUIP HT 25')
E
F
TERMINAL
1
2
T
H
S
T
R
E
E
T
S
H
E
N
K
A
V
E
G
H
REMOVE RUNWAY CLOSURE
MARKERS, REPAINT RWY
NUMERALS, AND ENABLE RWY
2-20 LIGHTING CIRCUITS
AFTER CONCLUSION OF
PHASE 2
COORDINATE ACCESS TO DIRECTIONAL BORE PIT AND EQUIPMENT
SHELTER THROUGH FAA ATCT CONTROLLED MOVEMENT AREA
WITH AIRPORT OPERATIONS
I
USCBP
PHASE 2 TEMPORARY USCBP
AIRCRAFT PARKING LOCATION
POINT
A
B
C
D
E
F
G
H
I
DESCRIPTION
WORK AREA
WORK AREA
WORK/STAGING AREA
WORK AREA
WORK AREA
WORK AREA
WORK/STAGING AREA
WORK AREA
WORK AREA
FAA AIRSPACE AND 7460 INFORMATION
HEIGHT
AGL
25'
25'
25'
25'
25'
25'
25'
25'
25'
LATITUDE
N42° 04' 52.24"
N42° 05' 00.43"
N42° 04' 58.37"
N42° 04' 52.72"
N42° 04' 51.39"
N42° 04' 54.38"
N42° 04' 56.97"
N42° 04' 51.64"
N42° 04' 49.68"
LONGITUDE
W80° 10' 46.46"
W80° 10' 46.17"
W80° 10' 52.10"
W80° 10' 49.88"
W80° 10' 47.58"
W80° 10' 45.98"
W80° 10' 53.83"
W80° 10' 56.56"
W80° 10' 44.47"
GROUND
729'
726'
726'
729'
730'
729'
726'
730'
730'
SEE SHEETS G-101 TO G-102 FOR AIRSPACE REVIEW COORDINATES
PHASE 2A
WORK AREA BOUNDARY
PHASE 2A
REPOSITION BARRICADES
TO CLOSE TWY D
PHASE 2A
REPOSITION
BARRICADES TO
CLOSE TWY D
1. TWY D CLOSED (BETWEEN RWY 2-20 & TWY F)
ALL PHASE 2 WORK WITHIN THE TWY D TOFA.
UP TO 14
DURING
PHASE 2
NORMAL /
UN-
RESTRICTED
2A
2
2A
2
2
2
2A
2A
2A
02.18.21 BID SET
LEGEND
EXISTING PAVEMENTS
LIGHTED BARRICADE (PHASE IF APPLICABLE)
WORK AREA BOUNDARY
CONTRACTOR HAUL ROUTE
GROUND SERVICE EQUIPMENT (GSE) ROUTE
RUNWAY OBJECT FREE ZONE
RUNWAY SAFETY AREA
TAXIWAY OBJECT FREE AREA
1
RSA
>
OFZ
XXXXXXXXXXXXXXXXX
TOFA
G-102
ER
IE
IN
TE
RN
AT
IO
NA
L A
IR
PO
RT
RE
HA
BILIT
AT
E A
ND
E
XP
AN
D
TE
RM
IN
AL A
PR
ON
44
11
W
ES
T 1
2T
H S
TR
EE
T
ER
IE
, P
EN
NS
YL
VA
NIA
GENERAL NOTES:
1. THE CONTRACTOR IS RESPONSIBLE FOR PLACEMENT AND REMOVAL OF RUNWAY CLOSURE MARKINGS
AND BARRICADES. COORDINATE WITH THE RPR AND AIRPORT TO CONFIRM NOTAM'S ARE ISSUED AND
APPROPRIATE RUNWAY AND TAXIWAY LIGHTING CIRCUITS ARE DISABLED.
2. THE CONTRACTOR SHALL LOCK OUT/TAG OUT ALL ELECTRICAL CIRCUITS TO CLOSED PAVEMENTS AND
INSTALL TEMPORARY JUMPERS WHERE NECESSARY TO LIGHT OPEN PAVEMENTS. THE CONTRACTOR
SHALL PROVIDE A TEMPORARY JUMPER PLAN 14 DAYS PRIOR TO PHASE CHANGE FOR APPROVAL BY
THE RPR AND AIRPORT. ELECTRICAL LOCK OUT/TAG OUT AND TEMPORARY INSTALLATION SHALL BE
INCIDENTAL TO MOBILIZATION.
3. THE CONTRACTOR SHALL PROVIDE GATE GUARD(S) AT ALL CONSTRUCTION ENTRANCES. COORDINATE
ADDITIONAL TRAINING WITH THE AIRPORT OPERATOR.
4. THE CONTRACTOR SHALL REQUEST A SAFETY AND LIGHTING INSPECTION BY AIRPORT OPERATIONS
PRIOR TO LEAVING THE CONSTRUCTION SITE AFTER EACH WORKING DAY. THE SAFETY INSPECTION
SHALL INCLUDE THE CONDITION OF ACTIVE OPERATION AREAS ADJACENT TO THE CONSTRUCTION LIMIT,
THE CONDITION OF THE CONTRACTOR STAGING AREA AND THE SECURITY OF THE CONSTRUCTION
ENTRANCE(S). THE CONTRACTOR'S SUPERVISOR SHALL REMAIN ON SITE UNTIL THE SAFETY INSPECTION
IS COMPLETE AND ALL DEFICIENCIES HAVE BEEN CORRECTED TO THE SATISFACTION OF THE AIRPORT
OPERATIONS DEPARTMENT.
5. ACCESS TO THE SITE WILL BE FROM 12TH STREET. THE CONTRACTOR SHALL OBTAIN PERMISSION AND
PERMITS FROM PENNDOT FOR TEMPORARY CONSTRUCTION ENTRANCE. ADDITIONALLY, THE
CONTRACTOR SHALL INSTALL CONSTRUCTION ENTRANCE ROADWAY SIGNAGE AS REQUIRED BY
PENNDOT AND IN COMPLIANCE WITH MUTCD. ALL COSTS FOR TEMPORARY ENTRANCE INCLUDING
FENCE REMOVAL, TEMP FENCE, FENCE REINSTALLATION, AND HAUL ROAD ARE AT THE CONTRACTOR'S
EXPENSE EXCEPT PERMIT FEES WILL BE PAID FOR UNDER PERMITS PAY ITEM FOR ACTUAL PERMIT
COSTS WITH NO MARK UPS.
CONTRACTOR LANDSIDE
EMPLOYEE PARKING AREA
WITHIN LONG TERM PARKING
LOT
CONSTRUCT TEMPORARY
CONSTRUCTION GATE AND
FENCE.
TEMPORARY HAUL ROUTE.
REMOVE AT COMPLETION
OF THE PROJECT.
2 03.15.21 ADDENDUM 4
2
2
2
2
G-152
CONSTRUCTION
SAFETY PHASING
DETAILS
MDB
SCT
SCT
X:\3
22
56
00
\2
01
14
6.0
1\T
EC
H\C
AD
\D
RA
WIN
GS
\G
-1
01
C
ON
ST
S
AF
ET
Y P
HA
SIN
G P
LA
N.D
WG
3/1
2/2
02
1 4
:2
8:5
4 P
M
7A
NOT FOR CONSTRUCTION
41
ER
IE
IN
TE
RN
AT
IO
NA
L A
IR
PO
RT
RE
HA
BILIT
AT
E A
ND
E
XP
AN
D
TE
RM
IN
AL A
PR
ON
3225600-201146.01
02.18.21
44
11
W
ES
T 1
2T
H S
TR
EE
T
ER
IE
, P
EN
NS
YL
VA
NIA
SHEET CONTENTS
DO NOT SCALE DRAWINGS
M&H NO.:
DATE:
DESIGNED BY:
DRAWN BY:
CHECKED BY:
ISSUED
These documents shall not be used for any purpose or
project for which it is not intended. Mead & Hunt shall
be indemnified by the client and held harmless and
defended from all claims, damages, liabilities, losses,
and expenses, including attorneys' fees and costs,
arising out of such misuse or reuse of the documents.
In addition, unauthorized reproduction of these
documents, in part or as a whole, is prohibited.
of
SHEET NO.
Mead and Hunt, Inc.
2605 Port Lansing Road
Lansing, MI 48906
phone: 517-321-8334
meadhunt.com
PERMANENT
CHAIN-LINK FENCE DETAILS
4
NOT TO SCALE
6" M
IN
.
GROUND ROD
(SEE F-162)
NO. 7 TENSION WIRE
NO. 7 TENSION WIRE
10'-0" MAXIMUM
BOTTOM RAIL
3
/8
" D
IA
. T
R
U
S
S
R
O
D
W
IT
H
A
D
J
U
S
T
M
E
N
T
HORIZONTAL BRACE
TOP RAIL
10' MAXIMUM
BRACE SECTIONBRACE POSTLINE POST TERMINAL POST
(END, CORNER, OR PULL)
CHAIN-LINK FABRIC
(#9 GAGE, 2" MESH)
3' M
IN
3' M
IN
8'
AOA SIDELANDSIDE
CHAIN LINK
TEMPORARY FENCE LINE DETAIL
1
NOT TO SCALE
BARBED WIRE LAND SIDE
FENCE POST
8' F
AB
RIC
W
ID
TH
1' MIN
8'
AOA SIDELANDSIDE
CHAIN LINK
PERMANENT FENCE LINE DETAIL
3
NOT TO SCALE
BARBED WIRE LAND SIDE
EXPANSION MATERIAL
AROUND FENCE
CONCRETE
FENCE CONCRETE FOUNDATION
FENCE POST
6" M
IN
.
GROUND ROD
(SEE F-162)
NO. 7 TENSION WIRE
NO. 7 TENSION WIRE
10'-0" MAXIMUM
BOTTOM RAIL
3
/8
" D
IA
. T
R
U
S
S
R
O
D
W
IT
H
A
D
J
U
S
T
M
E
N
T
HORIZONTAL BRACE
TOP RAIL
10' MAXIMUM
BRACE SECTIONBRACE POSTLINE POST TERMINAL POST
CHAIN-LINK FABRIC
(#9 GAGE, 2" MESH)
3' M
IN
3' M
IN
8' F
AB
RIC
W
ID
TH
1' M
IN
TEMPORARY
CHAIN-LINK FENCE DETAILS
2
NOT TO SCALE
2 03.15.21 ADDENDUM 4
Erie International Airport Item F-162 Chain-Link Fence Erie, PA Rehabiliate and Expand Terminal Apron AIP No. TBD F-162-1 Addendum 04
Item F-162 Chain-Link Fence
DESCRIPTION
162-1.1 This item shall consist of furnishing and erecting a chain-link fence in accordance with these specifications, the details shown on the plans, and in conformity with the lines and grades shown on the plans or established by the RPR.
MATERIALS
162-2.1 Fabric. The fabric shall be woven with a 9-gauge galvanized steel wire in a 2-inch (50 mm) mesh and shall meet the requirements of ASTM A392, Class 2. or the fabric shall be woven from a 9 gauge aluminum-coated steel wire in a 2-inch (50 mm) mesh and shall conform to the requirements of ASTM A491.
162-2.2 Barbed wire. Barbed wire shall be 2-strand 12-1/2 gauge zinc-coated or aluminum-coated wire with 4-point barbs and shall conform to the requirements of ASTM A121, Class 3, Chain Link Fence Grade or ASTM A121, Class II.
162-2.3 Posts, rails, and braces. Line posts, rails, and braces shall conform to the requirements of ASTM F1043 or ASTM F1083 as follows:
Galvanized tubular steel pipe shall conform to the requirements of Group IA, (Schedule 40) coatings conforming to Type A, or Group IC (High Strength Pipe), External coating Type B, and internal coating Type B or D.
Posts, rails, and braces, with the exception of galvanized steel conforming to ASTM F1043 or ASTM F1083, Group 1A, Type A, or aluminum alloy, shall demonstrate the ability to withstand testing in salt spray in accordance with ASTM B117 as follows:
External: 1,000 hours with a maximum of 5% red rust.
Internal: 650 hours with a maximum of 5% red rust.
The dimensions of the posts, rails, and braces shall be in accordance with Tables I through VI of Federal Specification RR-F-191/3.
162-2.4 Gates. Gate frames shall consist of galvanized steel pipe and shall conform to the specifications for the same material under paragraph 162-2.3. The fabric shall be of the same type material as used in the fence.
162-2.5 Wire ties and tension wires. Wire ties for use in conjunction with a given type of fabric shall be of the same material and coating weight identified with the fabric type. Tension wire shall be 7-gauge marcelled steel wire with the same coating as the fabric type and shall conform to ASTM A824.
All material shall conform to Federal Specification RR-F-191/4.
162-2.6 Miscellaneous fittings and hardware. Miscellaneous steel fittings and hardware for use with zinc-coated or aluminum-coated steel fabric shall be of commercial grade steel or better quality, wrought or cast as appropriate to the article, and sufficient in strength to provide a balanced design when used in conjunction with fabric posts, and wires of the quality specified herein. All steel fittings and hardware shall be protected with a zinc coating applied in conformance with ASTM A153. Barbed wire support arms shall withstand a load of 250 pounds (113 kg) applied vertically to the outermost end of the arm.
162-2.7 Concrete. Concrete shall have a minimum 28-day compressive strength of 3000 psi (2670 kPa).
Erie International Airport Item F-162 Chain-Link Fence Erie, PA Rehabiliate and Expand Terminal Apron AIP No. TBD F-162-2 Addendum 04
162-2.8 Marking. Each roll of fabric shall carry a tag showing the kind of base metal (steel, aluminum, or aluminum alloy number), kind of coating, the gauge of the wire, the length of fencing in the roll, and the name of the manufacturer. Posts, wire, and other fittings shall be identified as to manufacturer, kind of base metal (steel, aluminum, or aluminum alloy number), and kind of coating.
CONSTRUCTION METHODS
162-3.1 General. The fence shall be constructed in accordance with the details on the plans and as specified here using new materials. All work shall be performed in a workmanlike manner satisfactory to the RPR. The Contractor shall layout the fence line based on the plans. The Contractor shall span the opening below the fence with barbed wire at all locations where it is not practical to conform the fence to the general contour of the ground surface because of natural or manmade features such as drainage ditches. The new fence shall be permanently tied to the terminals of existing fences as shown on the plans. The Contractor shall stake down the woven wire fence at several points between posts as shown on the plans.
The Contractor shall arrange the work so that construction of the new fence will immediately follow the removal of existing fences. The length of unfenced section at any time shall not exceed 300 feet (90 m). The work shall progress in this manner and at the close of the working day the newly constructed fence shall be tied to the existing fence.
162-3.2 Clearing fence line. Clearing shall consist of the removal of all stumps, brush, rocks, trees, or other obstructions that will interfere with proper construction of the fence. Stumps within the cleared area of the fence shall be grubbed or excavated. The bottom of the fence shall be placed a uniform distance above ground, as specified in the plans. When shown on the plans or as directed by the RPR, the existing fences which interfere with the new fence location shall be removed by the Contractor as a part of the construction work unless such removal is listed as a separate item in the bid schedule. All holes remaining after post and stump removal shall be refilled with suitable soil, gravel, or other suitable material and compacted with tampers.
The cost of removing and disposing of the material shall not constitute a pay item and shall be considered incidental to fence construction.
162-3.3 Installing posts. All posts shall be set in concrete at the required dimension and depth and at the spacing shown on the plans.
The concrete shall be thoroughly compacted around the posts by tamping or vibrating and shall have a smooth finish slightly higher than the ground and sloped to drain away from the posts. All posts shall be set plumb and to the required grade and alignment. No materials shall be installed on the posts, nor shall the posts be disturbed in any manner within seven (7) days after the individual post footing is completed.
Should rock be encountered at a depth less than the planned footing depth, a hole 2 inches (50 mm) larger than the greatest dimension of the posts shall be drilled to a depth of 12 inches (300 mm). After the posts are set, the remainder of the drilled hole shall be filled with grout, composed of one part Portland cement and two parts mortar sand. Any remaining space above the rock shall be filled with concrete in the manner described above.
In lieu of drilling, the rock may be excavated to the required footing depth. No extra compensation shall be made for rock excavation.
162-3.4 Installing top rails. The top rail shall be continuous and shall pass through the post tops. The coupling used to join the top rail lengths shall allow for expansion.
Erie International Airport Item F-162 Chain-Link Fence Erie, PA Rehabiliate and Expand Terminal Apron AIP No. TBD F-162-3 Addendum 04
162-3.5 Installing braces. Horizontal brace rails, with diagonal truss rods and turnbuckles, shall be installed at all terminal posts.
162-3.6 Installing fabric. The wire fabric shall be firmly attached to the posts and braced as shown on the plans. All wire shall be stretched taut and shall be installed to the required elevations. The fence shall generally follow the contour of the ground, with the bottom of the fence fabric no less than one inch (25 mm) or more than 4 inches (100 mm) from the ground surface. Grading shall be performed where necessary to provide a neat appearance.
At locations of small natural swales or drainage ditches and where it is not practical to have the fence conform to the general contour of the ground surface, longer posts may be used and multiple strands of barbed wire stretched to span the opening below the fence. The vertical clearance between strands of barbed wire shall be 6 inches (150 mm) or less.
162-3.7 Electrical grounds. Electrical grounds shall be constructed at 500 feet (150 m) intervals. The ground shall be accomplished with a copper clad rod 8 feet (2.4 m) long and a minimum of 5/8 inches (16 mm) in diameter driven vertically until the top is 6 inches (150 mm) below the ground surface. A No. 6 solid copper conductor shall be clamped to the rod and to the fence in such a manner that each element of the fence is grounded. Installation of ground rods shall not constitute a pay item and shall be considered incidental to fence construction. The Contractor shall comply with FAA-STD-019, Lightning and Surge Protection, Grounding, Bonding and Shielding Requirements for Facilities and Electronic Equipment, paragraph 4.2.3.8, Lightning Protection for Fences and Gates, when fencing is adjacent to FAA facilities.
162-3.8 Cleaning up. The Contractor shall remove from the vicinity of the completed work all tools, buildings, equipment, etc., used during construction. All disturbed areas shall be seeded per T-901.
METHOD OF MEASUREMENT
162-4.1 No direct payment.
BASIS OF PAYMENT
162-5.1 No direct payment.
REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM International (ASTM)
ASTM A121 Standard Specification for Metallic-Coated Carbon Steel Barbed Wire
ASTM A153 Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A392 Standard Specification for Zinc-Coated Steel Chain-Link Fence Fabric
ASTM A491 Standard Specification for Aluminum-Coated Steel Chain-Link Fence Fabric
ASTM A824 Standard Specification for Metallic-Coated Steel Marcelled Tension Wire for Use with Chain Link Fence
ASTM B117 Standard Practice for Operating Salt Spray (Fog) Apparatus
Erie International Airport Item F-162 Chain-Link Fence Erie, PA Rehabiliate and Expand Terminal Apron AIP No. TBD F-162-4 Addendum 04
ASTM F668 Standard Specification for Polyvinyl Chloride (PVC), Polyolefin and other Organic Polymer Coated Steel Chain-Link Fence Fabric
ASTM F1043 Standard Specification for Strength and Protective Coatings on Steel Industrial Fence Framework
ASTM F1083 Standard Specification for Pipe, Steel, Hot-Dipped Zinc-Coated (Galvanized) Welded, for Fence Structures
ASTM F1183 Standard Specification for Aluminum Alloy Chain Link Fence Fabric
ASTM F1345 Standard Specification for Zinc 5% Aluminum-Mischmetal Alloy Coated Steel Chain-Link Fence Fabric
ASTM G152 Standard Practice for Operating Open Flame Carbon Arc Light Apparatus for Exposure of Nonmetallic Materials
ASTM G153 Standard Practice for Operating Enclosed Carbon Arc Light Apparatus for Exposure of Nonmetallic Materials
ASTM G154 Standard Practice for Operating Fluorescent Ultraviolet (UV) Lamp Apparatus for Exposure of Nonmetallic Materials
ASTM G155 Standard Practice for Operating Xenon Arc Light Apparatus for Exposure of Nonmetallic Materials
Federal Specifications (FED SPEC)
FED SPEC RR-F-191/3 Fencing, Wire and Post, Metal (Chain-Link Fence Posts, Top Rails and Braces)
FED SPEC RR-F-191/4 Fencing, Wire and Post, Metal (Chain-Link Fence Accessories)
FAA Standard
FAA-STD-019 Lightning and Surge Protection, Grounding, Bonding and Shielding Requirements for Facilities and Electronic Equipment
FAA Orders
5300.38 AIP Handbook
END OF ITEM F-162