Page 1: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Erik Duncan, Invenergy LLC

October 20, 2009

The Cost of Developing and Constructing Wind

Farms

Page 2: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Invenergy

2

Overview Invenergy Background Development Costs Construction Costs Key Cost Drivers Other Costs Questions

Page 3: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Invenergy

3

Invenergy - Overview U.S. company, based in Chicago, IL Over 300 employees worldwide Business model includes:

Development Construction management Financing Operation and maintenance Long-term ownership

Recognized by utilities, construction companies, and turbine manufacturers as a proven and reliable business partner

2nd Largest U.S. Purchaser of General Electric Wind Turbines (over 3,000 MW of orders between 2005 & 2010)

Largest privately-owned wind energy developer in the U.S. Six U.S. natural gas generation projects in operation or construction

(2,100 MW)

Page 4: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Invenergy

Invenergy Project Locations

Page 5: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Invenergy

Invenergy Projects

Buffalo Mountain Oliver Springs, TN

Judith Gap Wheatland Co., Montana

Page 6: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Invenergy

Invenergy Projects

Forward Energy Center Fon-du-Lac Co., Wisconsin

Spring Creek Wind Farm Logan Co., Colorado

Page 7: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Invenergy

7

Typical Development Process

Assumptions: No lengthy appeals Single year of wildlife studies

Year 1 2 3 4

Site Selection / Feasibility              

Permitting Studies /Applications                

Permitting Process              

Power Marketing                

Interconnection Studies        

Interconnection Construction                

Construction              

Page 8: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Invenergy

8

Development Costs (100 MW Project)

Item Low Mid High

Site Control 100,000 300,000 500,000

Wind Analysis 170,000 310,000 450,000

Interconnection 200,000 300,000 400,000

Envir. Studies 100,000 500,000 1,000,000

Permitting 0 500,000 1,000,000

Litigation/Appeal 0 200,000 2,000,000

Miscellaneous 450,000 800,000 1,100,000

TOTAL 1,020,000 2,910,000 6,450,000

Page 9: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Invenergy

9

Development Cost Drivers Competition Site Complexity Regulatory Environment Site-specific Permitting Issues Local Support / Opposition Appeals/Litigation

Page 10: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Invenergy

10

Construction Costs (100 MW Project)

Item Low Mid High

Wind Turbines 100,000,000 137,500,000 175,000,000

Engineering & QC 3,000,000 4,000,000 5,000,000

Erection 3,000,000 5,000,000 8,500,000

Civil 14,300,000 17,000,000 21,500,000

Electrical 15,900,000 20,000,000 23,800,000

Transmission 0 6,000,000 12,000,000

Miscellaneous 1,150,000 3,500,000 5,500,000

TOTAL 134,350,000 193,000,000 251,300,000

Page 11: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Invenergy

11

Construction Cost Drivers Turbine Costs (Demand) Site Complexity Regulatory Environment Interconnection Costs Commodity Costs

Page 12: Erik Duncan, Invenergy LLC October 20, 2009 The Cost of Developing and Constructing Wind Farms

Invenergy

12

Additional Costs (Not Included)

Multi-year preconstruction studies Construction contingencies Delay costs Transaction costs Financing costs