ermsar 2012, cologne march 21 – 23, 2012 severe accident risk importance measures in the context...

18
ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse Electric Company

Upload: bryan-ball

Post on 18-Jan-2016

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

SEVERE ACCIDENT RISK IMPORTANCE MEASURESSEVERE ACCIDENT RISK IMPORTANCE MEASURESIN THE CONTEXT OF PRA APPLICATIONSIN THE CONTEXT OF PRA APPLICATIONS

Juan Carlos de la RosaWestinghouse Electric Company

Page 2: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

Outline

To depict a picture about how safety culture is applied in NPPs by means of the Defence-in-Depth concept.

Once the different DiD barriers are analyzed, a particular gap in the area of preventive measures in Severe Accidents is detected.

To address this issue, a new risk-oriented metrics is proposed.

This new parameter enables to track risk all through the transient developed in the NPP site.

In order to be consistent (and objective) with the current risk metrics underlying the DiD barriers, a switch from the most severe to the most frequent scenario in the SA figures-of-merit is advisable.

Page 3: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

Usually, DiD barriers are spatially considered, i.e., they are placed in a one-dimensional map and intended to meet their function just as a physical wall would.

This drawing yields a balanced, well equilibrated picture of how safety measures are spread all along the nuclear plant.

Introduction

Page 4: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

• Actually, DiD encompass all “different levels of equipment and procedures (which applies to both the design and the operation of the facility) in order to maintain the effectiveness of physical barriers”:

Introduction

Page 5: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

Barriers could also be classified according to their time-to-act:

– Three different time thresholds are usually recognized: before the event is triggered, during the event evolution, and once the event has occurred (after the event measures do not fall under the NPP site).

– In accordance with maintenance and surveillance practices, predictive, preventive, and corrective barriers are considered.

Introduction

Page 6: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

Even if not explicitly declared, in order to define a barrier, two milestones are needed: the Initial and Final Event (which by the way is the Aristotle's efficient and final cause):

– Where the barrier is coming from? What has to be challenged?

– Where the barrier is looking at? What has to be prevented?

NPP initial design and practices have been directed towards the definition of the former issues as follows:

– The Initial Events have been those of the DBAs.

– The Final Event is a set of dependent consequences undergone by the core (peak temperature, cladding oxidation) usually referred as Core Damage (CD).

Introduction

Page 7: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

With the aim of removing the bias contained in the NPP initial design regarding the set of accidents that had to be challenged, PRA tool started to be taken into account.

Thus the IE issue was tackled, switching from a subset of transients to a global perspective, where all the events could become an IE.

If the FE is extended in time from CD to the next risk milestone, i.e., a radiological release to the off-site environment (usually Release Category, RC), the state of the DiD barriers drammatically diminishes.

The key point is that almost all barriers are looking at preventing CD. Then the question arises as to what if CD is exceeded?

Introduction

Page 8: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

Corrective (active) measures in SA conditions

– Values: active components have not usually been considered to mitigate post-CD scenarios (several exceptions are found by means of backfitting designs).

– Practices: Large uncertainties overcome the current possibility of moving from guidelines to procedures (improvements are expected from research).

After the Fukushima event, several steps have been taken towards fulfilling this gap.

DiD barriers beyond CD

Page 9: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

Preventive measures in SA conditions

– Values: Only variations on the two classical L2 PRA figures-of-merit are tracked.

Only related with backfitting designs.

– Practices: No one (some exception is found in the Maintenance Rule).

The key point is that even if corrective actions are going to be taken, both by means of new SA mitigating systems, and by improving the SAMGs, a gap regarding preventive actions looking at the RC (last FE in the NPP site) will still be an issue.

DiD barriers beyond CD

Page 10: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

Preventive measures could be tackled just by giving the role currently occupied by the CDF to some of the usual SA (PRA) measures.

This way, SSCs would receive an attention proportional to their contribution to the final risk.

Then risk will be redefined in terms of the (total) RCF instead of CDF.

Currently, risk is conceived as CDF * consequences.

The problem is that consequences can be very low in many situations where CD has been considered, whether because of conservatism assumption in the PRA model or because damage has been arrested.

LERF / LRF as an issue

Page 11: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

In order to set down the main category stated in the NRC R.G. 1.174, LERF, an agreement is held where the Spanish NRC and NPP utilities come together and adequately specify this release category. R.G. 1.174 says that

LRF is defined as LERF but at 24 hours.

LERF / LRF as an issue

This qualitative statement is converted to numbers considering a 3% volatile threshold

This qualitative statement is converted to numbers considering a 12 hours period

Page 12: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

LERF / LRF shortcomings (1/3):

– Very low frequency scenarios: the associated risk value will not likely be the highest one... bear in mind that when considering SA, a low consequence means always a high consequence, thus the second risk equation term should not be the most advisable way to identify the highest risk sequences.

– Many of these scenarios are unreasonable considering the current SOA of containment phenomena and IPE analysis, thus in a near future most of them could be neglected.

– Regulation: very low values; in the most of cases, nothing must be done once L2 PRA has been submitted.

– L2 PRA has been conceived as a back-end analysis, i.e., it only focuses on containment SSCs.

LERF / LRF as an issue

Page 13: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

LERF / LRF shortcomings (2/3):

– Biased!

• Same design philosophy than DBA: the worst scenario must be addressed (LBLOCA was discovered not to be the issue).

• But the worst case could have a negligible probability (first term of risk concept): like SBLOCA, Reactor & Turbine Trip, SBO, etc., other less severe scenarios have a much higher frequency, and therefore they should be addressed the first (in many PRA models all LBLOCA sequences are truncated).

• The conclusion is that a switch in SA analysis is needed, just the same undergone in accidents concerned with CD after PRA outcomes started to be accounted for: risk should be a frequency-driven concept.

LERF / LRF as an issue

Page 14: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

LERF / LRF shortcomings (3/3):

– Timing vs Actions:

• Sequences falling under LERF/LRF figures-of-merit are usually the result of a few terms contribution (Boolean equation representing containment failure means the failure of just a small set of actions): this could be seen in terms of the number of DiD barriers that are present in each sequence

• These contributions do not usually depend on human or mechanical actions (considering that Level 2 is a back-end analysis).

• Therefore, the more rapid evolves a sequence the less can be done, both regarding recovery actions or human actions.

LERF / LRF as an issue

Page 15: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

The key points are the followings:

• LERF is not the best tool to track the highest risk sequences related with NPPs accidents.

• Currently, the regulator (and therefore the utility) would probably skip the most useful information about how to deal with SA.

• LERF/LRF should be replaced by RCF: frequency should be the point, not consequence (as this is almost an inelastic term within the field of SA).

LERF / LRF as an issue

Page 16: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

Taking up the two issues mentioned above, a risk measure index is generated by extending the Fussel-Vesely measure factor to the SA scenarios, by means of weighting their contribution from CD to RC:

New metrics for tracking SA in preventive actions

STF

PDSRCfPDSBEMCSf

iFV jjlc

ljij

))(());((

)(

*

Page 17: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

A concern has been raised about the underlying basis of the DiD barriers.

DiD barriers usually rely on arguments related with preventing Core Damage by means of either deterministic assumptions or CDF.

Even if SA mitigating systems are going to be taken into consideration, a gap related with preventive actions looking at SA will still be an issue.

Conclusions (1/2)

Page 18: ERMSAR 2012, Cologne March 21 – 23, 2012 SEVERE ACCIDENT RISK IMPORTANCE MEASURES IN THE CONTEXT OF PRA APPLICATIONS Juan Carlos de la Rosa Westinghouse

ERMSAR 2012, Cologne March 21 – 23, 2012

Typical L2 PRA figures-of-merit have several shortcomings that make them not suitable for being implemented in SA preventive actions. The point is to use a frequency-driven parameter (as the total RCF).

A new metrics based on an extension of F-V index has been proposed, allowing to identify what are the main contributors to risk since the early beginning to the last end of the accident (thereby performing a front-end analysis).

Conclusions (2/2)