Agenda
ESBN Meter Project Update
RM259 Update
Feedback on Atos Contract
Smart Update (Elaine Sexton)
I-SEM Update (Jim Long)
3 esbnetworks.ie
ATOS Transition
Atos contract is up and running. Are Suppliers happy with
Service?
Comment @ January 2018 ..
“As far as we are concerned, all is going well with any wrinkles
hopefully addressed. I would however appreciate any feedback
from suppliers in case there are issues that are causing concerns”.
Gary McQuoid Client Executive Atos NI
m: +44077333 12759
Smart Metering Project – IGG Update
Thursday 3rd May 2018
Elaine Sexton, SMART Project
5 esbnetworks.ie
SMART
Agenda
• ESBN SMART Project
o Phased Approach
o Overview & Milestones
• Market Release Schema v12.00.00
o Scope
o Milestone Plan
o Progress
o Governance
• Future IGGs
o Implementation Details
o Cutover/Contingency Planning
6 esbnetworks.ie
ESBN SMART - Phased Approach
2019 2020 2024
Phase 1 Phase 2 Phase 3
2022
Market Release 1
(April 19)
Market Release 2
(December 20)
Market Release 4
(December)
2018
• Procure, build & test new solution
• Two Market Schema releases to facilitate
Smart Metering (non -Smart MCRs also incl)
• Daily collection & processing of interval data.
• The opportunity for Suppliers to offer new
Time-of-Use based tariffs
• Enable remote operation
of the service switch in
Smart Electricity Meters
• Smart Pre-Payment
services with secure
remote de-
energisation/energisation
• Advanced meter alerts &
events
• Gas Meter integration
• Commence installation of
gas smart meters
• In-Home Channel (HAN)
• In-Home Displays for real-
time customer information
250K Smart Meters safely installed by
December 2020 1 million Smart Meters
installed by 2022Remaining Smart
Meters installed by
end of 2024
20232021
Market Release 3
(December)
2017
7 esbnetworks.ie
ESBN SMART - Overview & Milestones
SMART
Drop High Level Scope Planned Go-Live Comment
0 RMP Extranet:
• MCR1176
• MCR1179
Sunday 25th April 2018 • Successfully Delivered
1 SAP IS-U Unicode Conversion August Bank Holiday 2018 • No Market Design Changes
• Market Assurance
2 Deployment & Logistics Q4 2018 • Updates provided at Smart ILG
3 Market Release v12.00.00
• MCRs
• SMART Enablement for Meter
Installation
• Technical Upgrades
Easter Weekend April 2019 • Significant body of work
• Market Assurance
• IPT
4 AMI Procurement & Enablement Q4 2019 • Updates provided at Smart ILG
5 Deployment Contractor Q4 2020 • Updates provided at Smart ILG
6 Market Release v13.00.00
• SMART MCRs
• Other Market Changes (TBC)
Dec 2020
(TBC-Prioritisation Process)
• Market Assurance
• IPT
* CoBLCR changes will be raised as required
8 esbnetworks.ie
Market Release Schema v12.00.00 - OverviewElement Changing Comment
Market Design
Documentation• ESBN SMART supporting RMDS in providing additions to the Retail Market Design:
o 11 new Standard Profiles - (MCR1167)
o 25 new Burn Hour Calendars - (MCR1167)
o Effective wattage for every lamp type will be published by ESBN (MCR1167), CoBLCR
changes as needed
TIBCO\Supplier EMMAs • Schema changes in both jurisdictions
Schema• ROI – Schema Changes 3 Data Codes are being modified to include additional or updated values:
o ‘RejectReasonCode’ - 9 new values (MCR0175)
o ‘CustomerServiceDetailsCode’ - 3 new values for ROI CoBL – 2 of which
will be added to schema (MCR1173)
o ‘LoadProfileCode’ – 11 new values (MCR1167)
• NI – Schema Changes - Covered by ReMCoWG/CDA
ROI Webforms• Webforms for ROI will need to be changed to accommodate the new Customer Service Special
Needs Details.
• ROI Webforms affected by these changes are those associated with the following MM: 010, 013,
016, 017
ROI Extranet • MCR1173,MCR1140 & MCR1167
Downloadable Files • 3 Downloadable files changing: DOM_CUST, COMM_CUST & UNMET_CUST (MCR1173,
MCR1140, MCR1169 & MCR1167)* CoBLCR changes will be raised as required
9 esbnetworks.ie
Market Release Schema v12.00.00 – Scope
MCR Version
Number
Description Schema/
Non-Schema
MCR0175 V5.0 New Reject Reasons for Address Change Rejection Schema
MCR1173 V2.0 Vulnerable Customer Implementation in ROI of SI 463 Schema
MCR1167** V3.0 Facilitate energy efficiencies in Local Authority Public Lighting Schema
MCR1140 V3.0 Introduction of Eircodes into the Retail Market Design in Ireland Non-Schema
MCR1169 V2.0 Addition of Postal Code to two Downloadable Meter Point Details Files Non-Schema
MCR1175 V3.0 Provide Market Participant Business Reference (MPBusinessReference) for Reading Non-Schema
MCR1180 V4.0 New Registration Default Supplier Non-Schema
MCR1183 V2.0 010 Customer Validation Agreement (NI) Schema
MCR1154 V2.0 New Unmetered Tariff for NI Schema
Other Comment
Smart Enablement • SAP IS-U Enhancement Pack (8.0)
• SMART Enablement for Meter Installation
• SAP Hana
** Pending IGG approval for re-versioning
10 esbnetworks.ie
Market Release v.12.00.00 – Milestone Plan
2018 2019
Q1 Q2 Q3 Q4 Q1 Q2 Q3
Design/Build/Test
V.12.00.00 Schema Published
Jan 28th
Go Live Easter 2019
IPT Prep
Market Engagement
CRU go/no Decision
v
Other
Unicode ConversionGo live August 2018
SAP Hana
SAP IS-U Enhancement Pack (8.0)
Smart Enablement for Meter Installation
5th16th 7th 7th 4th 27th 25th 29th 3rd 8th30th
Key
IGG (Meetings & Calls)
Key Milestone
Go lives
3rd
Go Live Easter 2019
Go Live Easter 2019
Go Live Easter 2019
IPT Exec
11 esbnetworks.ie
Market Release v12.00.00 – Status
MCR Description Status
MCR0175 New Reject Reasons for Address Change Rejection
MCR1173 Vulnerable Customer Implementation in ROI of SI 463
MCR1167** Facilitate energy efficiencies in Local Authority Public Lighting
MCR1140 Introduction of Eircodes into the Retail Market Design in Ireland
MCR1169 Addition of Postal Code to two Downloadable Meter Point Details Files
MCR1175 Provide Market Participant Business Reference (MPBusinessReference) for Reading
MCR1180 New Registration Default Supplier
MCR1183 010 Customer Validation Agreement (NI) ReMCoWG/CDA
MCR1154 New Unmetered Tariff for NI ReMCoWG/CDA
Other Comment Status
Smart
Enablement
• SAP IS-U Enhancement Pack (8.0)
• SMART Enablement for Meter Installation
• SAP Hana
** Pending IGG approval for re-versioning, version numbers above will change
esb.ie
Market Release Schema v12.00.00 – Governance
Topic Channel Frequency
• Periodic Update IGG As per agreed schedule
• Participant Queries RMDS Email/Phone Ad-hoc
• Market Design
• Market Release
Timelines
• Publications
RMDS Email/Web As Required
• Market Assurance RMDS/Gemserv As Required
• Existing Governance model will be used
RMDS – Contact Details
o E-Mail: [email protected]
o Website: https://rmdservice.com
o Phone: (01) 669 2410
esb.ie
Topic MCR# Description Topic IGG Meeting
(Indicative
Dates-TBC)
Implementation
Details
MCR1167 Public Lighting ESBN Publication:
• Standard Profiles
• Burn Hour Calendars
• Effective Wattages
Aug 2018
MCR1140 Eircodes Upload mechanism and schedule
for circa 1.5 Million Eircodes
Nov 2018
MCR1180 New Registration Default
Supplier
‘Work In Progress’ items will be
discussed
Nov 2018
MCR1173 Vulnerable Customers Reconciliation with suppliers for
new codes & Rejection Reasons
Nov 2018
MCR1140
MCR1173
MCR1167
MCR1169
Downloadable Meter Point Files Samples files Jan 2019
MCR1140
MCR1173
MCR1167
RMP Extranet screenshots Samples screenshots Jan 2019
MCR1167 700 Series MMs Samples 700MMs Feb 2019
Cutover &
Contingency
Planning
All Cutover & Contingency Planning Cutover & Contingency Approach Nov 2018
Market Release Schema v12.00.00 – Future IGGs
esb.ie
Appendix
esb.ie
ROI Market Release 2019 – Schema MCRs
MCR Description Change Details Comments
MCR0175
Version
5.0
New Reject Reasons for
Address Change Rejection
Nine New code
values are being
added (I.e. AD1-
>AD9)
• Market Message (MM): 014R
• 9 New Data Codes – Appendix – MCR0175 in March deck refers
MCR1173
Version
2.0
Vulnerable Customer
Implementation in ROI of SI
463
Change existing
Code 0008 to be
valid in ROI
&
Two new code values
(I.e. 0009 & 0010)
• Market Messages (MM): 010, 013 , 016 & 017
• 3 New Data Codes for ROI CoBL, 2 of which will be added to schema – Appendix – MCR1173 in March
deck refers
• Data Code values will now be used on Extranet and Downloadable files – not the Central Market System
Codes as per current design – Appendix – MCR1173 in March deck refers
• Code 0010 should not be used at this time – it’s being introduced for future proofing and will be rejected.
Rejection reasons and associated rejection messages will be communicated at a future IGG.
• The codes will appear in confirmation messages in line with current market rules
• Modified downloadable files will be available to Suppliers from May 2019 – Appendix MCR1173 in March
deck refers
• ROI Webforms :code 0010 will be selectable, not display only as originally communicated – Appendix
MCR1173 in March deck refers
MCR1167*
*
Version
3.0
Facilitate energy efficiencies
in Local Authority Public
Lighting
Eleven New code
values are being
added
(I.e.
U13->U23)
• Market Messages (MM): 591, 700, 700W, 701 & 701W
• 11 New Data Codes & 11 New Standard Profiles – Appendix MCR1167 in March deck refers
• 25 New Burn Hour Calendars – Appendix MCR1167 in March deck refers
• Effective wattage for every lamp type will be published by ESBN (when available)
• CoBLCR changes will be raised, as needed
• Downloadable file with new data values and structure will be available to Suppliers from May 2019 –
Appendix MCR1167 in March deck refers
MCR1183 010 Customer Validation
Agreement (NI)
NI Requirements NI Schema changes are covered in ReMCoWG/CDA
MCR1154 New Unmetered Tariff for NI
** Pending IGG approval for re-versioning, version numbers above will change
esb.ie
ROI Market Release 2019 – Non-Schema MCRs
MCR Description Comments
MCR1140
Version 3.0
Introduction of
Eircodes into the
Retail Market
Design in Ireland
• Eircodes can be submitted on MMs in the existing Postal Code field : 010, 012, 012W,013 & 021
• Eircodes where available will be returned in the existing Postal Code fields on MM: 014R, 101, 101P, 101R, 102,
102P, 102R, 105, 105L, 110, 112, 112R, 112W, 114, 301, 301N& 330
• ESBN will agree schedule for mass uploads of Eircodes into the Meter Point Address Postal Code field in the Central
Market System at a future IGG.
• ESBN intend to update these in batch – mechanism and schedule to be discussed at a future IGG
• Once the Postal Code field has been populated it will be visible on the Retail Market Participant Extranet – Appendix
in March deck MCR1140 refers
Note: Existing Market Defect originally intended to go-live with MCR1187 will now be implemented alongside
this MCR.
MCR1169
Version 2.0
Addition of Postal
Code to two
Downloadable
Meter Point Details
Files
• Modified downloadable files will be available to Suppliers from May 2019 – Appendix MCR1169 in March deck
refers
• However, population of field will be determined by the Eircode upload schedule for MCR1140
• ESB Networks intend to discuss the upload schedule for these two files at future IGGs
MCR1175
Version 3.0
Provide Market
Participant Business
Reference
(MPBusinessRefere
nce) for Reading
• The Market Participant Business Reference (MPBusinessReference) on the 300MM will be populated with that from
the associated original 210MM (i.e. where it populated a periodic meter reading order)
• Read Reason 95/’Not for COS’ is the only case for which the above applies
o If the customer reading which populates the open Meter Reading Order is implausible and is estimated
populate the MPBusinessReference on the corresponding 305MM
o If the customer reading which populates the open Meter Reading Order is withdrawn populate
the MPBusinessReference on the corresponding 300WMM
MCR1180
Version 4.0
New Registration
Default Supplier
• For sites with MIC <30kVa, the Customer must now register with a Supplier
• The 010MM must be received by the Central Market system before a connection point can be energised