ESD.36J System & Project Management

Dynamics of Project Performance

System Dynamics and Project Management

Lecture #19, SD Class 7 & 8? (11/6/00)

Copyright © 2003 James M. Lyneis

Page 2: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Typical project dynamics ...

Project Staffing

Typical Plan

... Result in schedule &/or budget overrun

TimeCopyright © 2003

9/23/03 - ESD.36J SPM James M. Lyneis 2

Page 3: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-What can we do to avoid/minimize in ...

� … project preparation (design) √

� … project planning √ – except overlap/concurrency

� … risk management � … change management � … execution and adaptation

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 3

Page 4: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Strategic Process & Organization Issues

� Waterfall vs. spiral vs. adaptive vs. …? � Autonomous (dedicated) integrated product

team vs. functional? � System vs. modules? � How much phase overlap and concurrency? � How much to subcontract, make vs. buy?

How do we assess what is right for our project?

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 4

Page 5: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

What are the pros and cons of above alternatives in the context of the model framework?

� Direct impacts of alternatives (one-off vs. dynamic) -­� Scope

� productivity

� quality

� rework discovery

� strength of productivity and quality effects

� ...� Secondary impacts (assessed via simulation)

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 5

Page 6: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-How do we know these values?

� First time, you don’t ==> make educated guesses. Remember -­� Better than mental models alone � Can do sensitivities – e.g., how bad would

the scope increase have to be before Spiral was not helpful for this type of project

� Once project finishes, can get a good estimate of the impact for use in future planning

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 6

Page 7: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

General Conclusions re. Process and Teaming

� An iterative development process and/or integratedproduct team can improve performance if projectconditions would otherwise cause significantundiscovered rework

� The benefits of these approaches increase with theuncertainty (risk) in the development, i.e., the amountof potential rework

� Cautions -- alternatives may … � … not help for truly “exogenous” changes � … involve additional scope, or � … involve short-term implementation costs (for new

processes/tools/structures) which may negate the benefits of the alternatives

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 7

Page 8: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

Topics+

-

• Planning – A look at issues in overlap and concurrency

• A System Dynamics View of Risk Management

• A Systems Dynamics View of Change Management and Dispute Resolution

• A System Dynamics View of Execution and Adaptation

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 8

Page 9: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Strategic Process & Organization Issues

� Waterfall vs. spiral vs. adaptive vs. …? � Autonomous (dedicated) integrated

product team vs. functional?� System vs. modules?� How much phase overlap and

concurrency? � How much to subcontract, make vs. buy?

How do we assess what is right for ourproject?

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 9

Page 10: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Reducing Project Duration, The Plan ...

Traditional project

Overlap phases

Compress each phase

Planned Duration

Phase 1

Phase 1

Phase 2

Phase 2

Phase 1

Phase 2

Copyright © 2003 - ESD.36J SPM James M. Lyneis

Page 11: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Phase Overlap & Concurrency: More Overlap ...

Pros Cons

Copyright © 20039/23/03 - ESD.36J SPM James M. Lyneis 11

Page 12: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Phase Overlap & Concurrency: More Overlap ...

Pros

� Speed development by starting downstream phases before upstream finished � ... �

Cons � Requires more resources at peak overlap � Executing downstream work before upstream is ready reduces productivity � Executing downstream work with partial or incorrect information creates potential quality problems � ….

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 12

Page 13: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

Ph

+

-Reducing Project Duration, The Pitfalls ...

Traditional Projects Rarely Meet Plan Because of Rework

Traditional project

Overlap phases

Compress each phase

ase 2

Planned Duration Actual

Phase 1

Phase 1

Phase 2

Phase 1

Phase 2

Rework Rework

Copyright © 2003- ESD.36J SPM James M. Lyneis

Page 14: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

n Actual

Phase 2 ReworkRework

+

-Reducing Project Duration, The Pitfalls ...

And simply overlapping phases often creates more rework because

Traditional project

Overlap phases

Compress each phase

Planned Duratioincompleteness and undiscovered errors in upstream work cause errors in downstream work.

Phase 1

Phase 1

Phase 2

Phase 1

Phase 2 More Rework?

Rework

Copyright © 2003 - ESD.36J SPM James M. Lyneis

Page 15: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework
Page 16: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Alternatively -- Reduce Unplanned Rework!

- ESD.36J SPM James M. Lyneis

Ph

Compress each phase

Reduce Rework

ase 2

Planned Duration Actual

Phase 1

Phase 1

Phase 2

Rework Phase 1

Phase 2

Phase 2 Phase 1

Rework

More Rework?

More Rework?

More Rework?

Rework

Rework Rework

Copyright © 2003

Traditional project

Overlap phases

Page 17: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

This is not to say that overlap or compression, if carefully planned, cannot be done …

� DSM, ICE approaches as methods for effectively planning concurrency/overlap?

� Critical chain approaches to remove padding?

� … other thoughts?

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 17

Page 18: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Note that staffing strategies, concurrency, and process (iteration) models are interrelated ...

Adapted from: Smith, Preston G. and Reinersten, Donald G., Developing Products in Half the Time, 2nd Edition, John Wiley & Sons, 1998.

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 18

Conventional staffing practices force development efforts into phases that become dominated by specific functions.

Product Concept

Time

Staffing Level

Product Introduction

MARKETING

ENGINEERING

MANUFACTURING

Page 19: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- require a more level staffing … as iteration, teaming, and/or concurrency

Adapted from: Smith, Preston G. and Reinersten, Donald G., Developing Products in Half the Time, 2nd Edition, John Wiley & Sons, 1998.

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 19

Dedicated staffing forces overlapping and cross-functional interaction.

Product Concept

Staffing Level

Product Introduction

MANUFACTURING

ENGINEERING

MARKETING

Time

Page 20: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Conclusions re. Phase Overlap

� Quality as well as “availability” is critical indetermining the readiness of starting downstreamwork phases

� In many cases, it may be better to devote staff tofinding and fixing errors than starting downstreamphases

� If downstream progress is necessary to discoveryupstream rework, careful planning and monitoring areneeded to minimize the adverse consequences ofprogressing downstream with low quality upstreaminformation

continued ...

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 20

Page 21: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Conclusions re. Phase Overlap (cont.)

� Increased phase overlap requires greater upstream and downstream communication to facilitate starting downstream work with partial information, and avoiding/finding upstream rework ==> teams that may lower productivity, but increase quality and reduce rework discovery time

� … � ...

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 21

Page 22: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Topics

• Planning – A look at issues in overlap and concurrency

• A System Dynamics View of Risk Management

• A Systems Dynamics View of Change Management and Dispute Resolution

• A System Dynamics View of Execution and Adaptation

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 22

Page 23: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Decomposition of Risk Management (from Professor Warmkessel)

Risk Identification

Risk Assessment

Risk Mitigation

Risk Tracking & Handling

Risk Management

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 23

Page 24: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- For Certain Risks, SD Can Help …

Risk Identification

Risk Assessment

Risk Mitigation

Risk Tracking & Handling

Risk Management

Identify Risks & Quantify Range of

- ESD.36J SPM 9/23/03

Direct Impacts Copyright © 2003 James M. Lyneis 24

Page 25: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- For Certain Risks, SD Can Help …

Risk Identification

Risk Assessment

Risk Mitigation

Risk Tracking & Handling

Risk Management

Identify Risks & Assess Total Quantify Range of Impact of Risks Direct Impacts Alone & In

Combination Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 25

Page 26: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- For Certain Risks, SD Can Help …

Risk Identification

Risk Assessment

Risk Mitigation

Risk Tracking & Handling

Risk Management

Design EffectiveIdentify Risks & Assess Total Mitigation,Quantify Range of Impact of Risks Including WhatDirect Impacts Alone & In

Combination To Monitor Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 26

Page 27: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Examples of Risks

� Technology – E.g., uncertain technology, technology leap

� Functionality – E.g., uncertain customer requirements

� Programmatic -­� Availability and quality of information from

others (suppliers, other projects, platforms) � Availability of staff or other resources

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 27

Page 28: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- For Certain Risks, SD Can Help …

Risk Identification

Risk Assessment

Risk Mitigation

Risk Tracking & Handling

Risk Management

Design EffectiveIdentify Risks & Assess Total Mitigation,Quantify Range of Impact of Risks Including What ToDirect Impacts Alone & In

Combination Monitor Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 28

Page 29: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

- ESD.36J SPM9/23/03 29

+

-

Copyright © 2003James M. Lyneis

Risk Identification and Quantification --Learning from Prior Projects

Model prior project(s)Quantify all deviations to project vis a vis original plan and input as time series or parametric changes

Estimate direct impactsFine tune quantification via calibration to actual data

Add to “data base” of sources and magnitude of changes to original plans

Page 30: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Specify “Direct Impacts” In Terms Of ...

� Changes in scope � Changes in quality � Effects on productivity and quality � Effects on staffing � ….

… via changes to normal parametersor via time series inputs

Indirect and total impacts aredetermined by the model

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 30

Page 31: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- Development Example – Automotive

Based on a simulation model, major sources of risk ranked interms of impact on schedule and delivered quality(Analysis of 11 projects):

1. Late information and/or changes 2. Resource availability

� Slow ramp up, lower peak, forced ramp down to meet budget � Inadequate skills mix

3. New processes, missing enablers, or new materials 4. Organization &/or geographic changes 5. Aggressive program assumptions

� Compressed timing, inadequate budget, lean allowance for prototypes

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 31

Page 32: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- For Certain Risks, SD Can Help …

Risk Identification

Risk Assessment

Risk Mitigation

Risk Tracking & Handling

Risk Management

Design EffectiveIdentify Risks & Assess Total Mitigation,Quantify Range of Impact of Risks Including What ToDirect Impacts Alone & In

Combination Monitor Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 32

Page 33: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Risk Assessment

� Set up model to represent plan (if possible)

� Using prior project data base, determine possible risks and range of impact

� Test individually and in combination

The numbers may not be accurate, but the thought process coupled with sensitivity analysis improves risk

management. Copyright © 2003

9/23/03 - ESD.36J SPM James M. Lyneis 33

Page 34: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

For Example: The “Class6” Base Case

Experience on prior projects indicates significant risk of late rework with the clarification of customer needs:

� Uncertain customer requirements cause quality problems early in the project� normal quality = .95

� all other parameters as in Homework1 Model� Assume waterfall model with functional

organization structure

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 34

Page 35: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

The Base Case Overruns ...Graph for Staff Level

20

15

10

5

0

C

C

om

ost: 26

pletion:

3 Perso

Month

n-m

38.

onths

875 (30

(115

planned)

plan)

Plan

0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60 Time (Month)

Staff Level : Class6 Waterfall People Staff Level : Class6 Plan People

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 35

Page 36: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- For Certain Risks, SD Can Help …

Risk Identification

Risk Assessment

Risk Mitigation

Risk Tracking & Handling

Risk Management

Design EffectiveIdentify Risks & Assess Total Mitigation,Quantify Range of Impact of Risks Including WhatDirect Impacts Alone & In

Combination To Monitor Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 36

Page 37: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Risk Mitigation

� Determine possible methods of mitigation for risks likely to impact this project

� Assess cost-benefit, including indirect impacts via reduced productivity and increased rework

� Implement up front, or monitor and implement pre-defined action plan

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 37

Page 38: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

For Example, Mitigating Risk From Uncertain Customer Requirements: Strategic Process & Organization Issues

� Waterfall vs. spiral vs. adaptive vs. …?

� Autonomous (dedicated) integrated product team vs. functional?

� System vs. modules? � How much phase overlap and

concurrency?

� [How much to subcontract, make vs. buy?]

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 38

Page 39: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Automotive Development: Risk Mitigation Actions

� “Disciplined” Product Development: � Contain workscope by maximizing reuse � Focus on quality rather than early milestones � Minimize late changes � Accelerate rework discovery

� Staffing: � Get planned resources on time (“fight”, external, …) � Minimize sustained overtime � Additional and accelerated training � Colocation

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 39

Page 40: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

ESD.36J System & Project Management

A Case Example: The Peace Shield Air Defense System

Copyright © 2003 James M. Lyneis

Page 41: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-The Peace Shield Program

� Hughes (now part of Raytheon): A major US aerospace company that regularly develops large-scale air defense systems

� The problem: Frequent budget overruns resulted in lengthy claim disputes between Hughes and their customers; this contract was won competitively after being taken from another contractor in trouble

� System dynamics model was used for: � Bid support and risk assessment; � On-going project management � Post-project benchmarking and policy assessment

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 41

Page 42: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

DownstreamProgress,Availability,& Quality Effects

Upstream ReworkDiscovery Effects

Support effects

+

-

SRS Code & Unit

Integration

Mgt. & Admin.

Op. & Main/

ILS

HW Installation

Software System

Program Management Office

Customer Hardware Subcontractors Other HASI Programs

CONUS

Project Phases Software Development

Development

Top Level & Detailed

Design Test & Type II

Test

Type I Test KOSA

& ICO Test Engineering Software Support

Logistics

Downstream Progress, Availability, & Quality Effects

Upstream Rework Discovery Effects

Support effects

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 42

Page 43: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Bid Support and Risk Assessment

� Adapted model of prior CCSdevelopment

� Assessed risks associated with critical assumptions � amount of code from prior project that does

not require change and could be used as is(“liftability”)

� availability of experienced staff� vendor delays� …

� Estimated likely competitor bid Copyright © 2003

9/23/03 - ESD.36J SPM James M. Lyneis 43

Page 44: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- and how much “undiscovered rework” in “Liftability” – How much “work really done”

the “lifted” code?

Quality

Progress

Rework

Productivity

Work To Be Done

Undiscovered Rework

Known Rework

Work Really Done

“Base Case”:

80%

Discovery 20%

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 44

Page 45: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Man-Months

Liftability Most Critical and Uncertain ... Total Development Man-Months

6000

5000

4000

2000

2000

1000

0 Peace 100% of 60% of 40% of 20% of 0% of Shield lift usable lift usable lift usable lift usable lift usable Base as is as is as is as is as is

PMO

Software

System Engineering

Test

Copyright © 20039/23/03 - ESD.36J SPM James M. Lyneis 45

Page 46: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Estimate Competitor Bid

� Competitor inexperience in this type of project likely to result in unrealistically low bid � Submit a low bid, but still profitable if

managed aggressively � Carefully define work scope assumptions � Aggressively manage program to control

costs, including early emphasis on rework discovery, use of experienced staff, and management of customer expectations

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 46

Page 47: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Mitigation ...

� … concentrate early program efforts on flushing out as-yet-undiscovered rework in the lifted work, rather than steeply ramping up staff to accomplish new work

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 47

Page 48: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Project Planning: Based on Model Analyses, Adopt New Process and Organization …

� Implementation of a “teaming” structure and other improved processes (including worse before better impacts) � Upstream and downstream staff involved in design

and review for all phases � Customer participation in design reviews

� Implementation of a new staffing strategy for software engineering and coding � Delay start of downstream phase � Delay roll-off of staff from phase and assign to

rework discovery Copyright © 2003

9/23/03 - ESD.36J SPM James M. Lyneis 48

Page 49: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Peace Shield Was Very Successful ...

“In my 26 years in acquisition, this [Peace Shield Weapon System] is the most successful program I’ve

ever been involved with, and the leadership of the U.S. Air Force agrees.”

Darleen Druyun

Program Manager March-April 1996

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 49

Page 50: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Post-project benchmarking ...

1800 Past Program

1600

1400

1200

1000

800

600Peace Shield

400

200

0 0

1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002

Peace Shield

Past Program

Cumulative Effort

Staff Levels

Copyright © 20039/23/03 - ESD.36J SPM James M. Lyneis 50

Page 51: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-What caused the differences between Peace Shield and Past Program?

z Differences in work scope?

z External Conditions?

z Management policies and processes?

And how can a company learn from these differences, and therefore

z Bid better?

z Plan better?

z Manage better?

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 51

Page 52: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

The same model accurately replicated Peace Shield ...

0

Data and Plans in mid-1993

Simulated

1991 1992 1993 1994 1995

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 52

Page 53: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- policy & risk (external) changes only … and the Past Program with management

0

Simulated

Data

1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 53

Page 54: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Programs overlayed highlight difference ...

1800 Past Program

1600

1400

1200

1000

800

600Peace Shield

400

200

0 0

1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002

Peace Shield

Past Program

Cumulative Effort

Copyright © 20039/23/03 - ESD.36J SPM James M. Lyneis 54

Page 55: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Major external differences

Peace Shield -­� Lower scope and fewer changes � Fewer vendor delays & hardware

problems � Better hiring conditions (less delay)

(Some of these are sources of risk)

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 55

Page 56: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Removing external sources of difference from the past program ...

Cumulative Effort

Past Program

External Differences Removed

1800Past Program

1600

1400

1200

1000External Removed

800

600

400

200

0 0

1 2 3 4 5 6 7 8 9 10 11 12

Copyright © 20039/23/03 - ESD.36J SPM James M. Lyneis 56

Page 57: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Removing external sources of difference from the past program ...

Cumulative Effort

Past Program

External Differences Removed

Peace Shield Schedules

1800Past Program

1600

1400

1200

1000External Removed

800

600

400

200

0 0

1 2 3 4 5 6 7 8 9 10 11 12

Copyright © 20039/23/03 - ESD.36J SPM James M. Lyneis 57

Page 58: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Management differences

Peace Shield -­� Adopted teaming structure including

customer involvement in design reviews � Different staffing strategy by phase of

work

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 58

Page 59: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Delayed Roll-off of Staff and Later Start of Downstream Phases on Peace Shield

Start of S/W Coding

Past Peace C&C Shield

0% 10% 20% 30% 40%

S/W Design Complete

Program Year Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 59

Page 60: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Peace Shield: Reduce Overlap and Unplanned Rework!

Past Project: Overlap phases

Peace Shield: Reduce duration by reducing rework in upstream phases

Planned Duration Actual

Phase 1

Phase 2

Phase 2 Phase 1

More Rework?

Rework

Rework Rework

Copyright © 2003 - ESD.36J SPM James M. Lyneis

Page 61: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Teaming, Delayed Roll-off of Staff, and Customer involvement in Design Reviews Contributed to Shorter Rework Discovery Times on Peace Shield

Rework Discovery Delay(Months)24

22

20

18

16

14

12

10

8 6 4 2 0

1 2 3 4 5 6 7 8 9 10 11

Past Program

Peace Shield

Program Year

Copyright © 20039/23/03 - ESD.36J SPM James M. Lyneis 61

Page 62: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Removing management differences ...

Cumulative Effort

Peace Shield

Past Program

External Differences Removed

Peace Shield Schedules

1800Past Program

1600

1400

1200

1000

800

600Peace Shield

400

200

0 0

1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002

Copyright © 20039/23/03 - ESD.36J SPM James M. Lyneis 62

Page 63: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Where Did The Cost Improvement Come From?

External Conditions 44%Policies & Processes 56%

Teaming & OtherImprovements

Better HiringConditions

3%

Fewer Vendor & Hardware Problems

Different Staffing Policies

More Experienced

Scope Differences & Fewer Customer Changes

19%

19%

People 24%

13%

22%

Copyright © 20039/23/03 - ESD.36J SPM James M. Lyneis 63

Page 64: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

Topics+

-

• Planning – A look at issues in overlap and concurrency

• A System Dynamics View of Risk Management

• A Systems Dynamics View of Change Management and Dispute Resolution

• A System Dynamics View of Execution and Adaptation

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 64

Page 65: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

What are differences between “changes” and “quality” problems?

� Changes represent truly unknowable,uncontrollable, exogenous impacts(often can be compensated for) � competitor introduces a new feature � ...

� “Quality” problems can be anticipatedand dealt with in the design andmanagement of the project � buffers, prototypes, process, ...

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 65

Page 66: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Changes can impact a project in a number of direct ways:

�Added work scope �Added hours, without changes in

“scope”�Work obsoleted�Work made uncertain because of

possible changes �Late/deficient information or equipment�Diversion of management time

How much, when, how long Copyright © 2003

9/23/03 - ESD.36J SPM James M. Lyneis 66

Page 67: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework
Page 68: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Estimating Impact & Mitigation

�What is the total cost and schedule impact of the change, if mitigatingactions are not taken?�What actions will reduce the extent of

the disruption -­� Schedule relief? Slipping interim

milestones? � Additional budget? � Management actions (overtime, hiring, ...)? �Should the change be made, and how

should we be compensated (if possible)Copyright © 2003

9/23/03 - ESD.36J SPM James M. Lyneis 68

Page 69: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- Graph for Work Done

100

75

50

25

0 0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60

Time (Month)

Work Done : Class7 Changes Task Work Done : Class7 Plan Task

9/23/03 - ESD.36J SPM Copyright © 2003 James M. Lyneis 69

Page 70: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Graph for Staff Level

20

15

10

5

0 0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60

Time (Month)

Staff Level : Class7 Base People Staff Level : Class7 Changes 20-15 People

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 70

Page 71: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Impact Increases the Later the Change ...

Test

Plan

Changes, 20%@ Month 5

Changes, 20%@ Month 10

Changes, 20%@ Month 15

Finish Cost(person-mos)

30.5 119.33

31.625 143.25 (+20%)

32.2 152.35 (+28%)

32.875 161.73 (+36%) Copyright © 2003

9/23/03 - ESD.36J SPM James M. Lyneis 71

Page 72: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-… and the Larger the Change

Test Finish Cost(person-mos)

Plan 30.5 119.33

Changes, 10%@ Month 15 31.69 138.35 (+16%, 1.6X)

Changes, 20%@ Month 15 32.875 161.73 (+36%, 1.8X)

Changes, 30%@ Month 15

34.1 186.6 (+56%, 1.9X)

9/23/03 - ESD.36J SPM Copyright © 2003 James M. Lyneis 72

Page 73: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Cost impact can be mitigated ...

Graph for Staff Level20

15

10

5

0

Changes

Changes, SlipSchedule

Plan

0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60 Time (Month)

Staff Level : Class7 Changes People Staff Level : Class7 Plan People Staff Level : Class7 Changes Slip Schedule People

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 73

Page 74: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- Graph for Quality

1

0.9

0.8

0.7

0.6

Plan

Changes, pSliSchedule

Changes

0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60 Time (Month)

Quality : Class7 Changes Fraction Quality : Class7 Plan Fraction Quality : Class7 Changes Slip Schedule Fraction

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 74

Page 75: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Change Scenarios

Test Finish Cost(person-mos)

Plan 30.5 119.33

Changes 32.875 161.73 (+36%)

Changes, Slip Schedule 34.2 139.78 (+17%)

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 75

Page 76: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

ESD.36J System & Project Management

Delay and Disruption Disputes

Copyright © 2003James M. Lyneis

Page 77: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Delay and disruption

Schedule and cost growth resulting from the effects of unplanned changes or unanticipated problems.

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 77

Page 78: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

How SD in Project Management got started: Ingalls Shipbuilding vs. US Navy

� Ingalls Shipbuilding won contract for 9 LHA’s and30 DD963 destroyers in 1969 and 1970.

� Firm fixed price contract structure

� $500 million cost overrun on the programs (Ingallsand Navy agreed on $150 direct cost – the rest?)� Navy – bad management � Ingalls – D&D

� Ingalls sues Navy claiming design changescaused delay and disruption Source: Cooper, Kenneth G., 1980, Naval Ship Production: A Claim Settled

and a Framework Built. Interfaces. 10(6) (December), 20-36. Copyright © 2003

9/23/03 - ESD.36J SPM James M. Lyneis 78

Page 79: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

The big question: ‘How would the program have performed absent customer-responsible events & conditions?’

Customer-Responsible Events & Conditions Total Program Labor (Equiv. People)

Real Program

l i

l ion Time

ii

i

le

l

l

i i l

l

i

ll

Work Quality to Date

Scheduled Comp et on

Time

Expected Comp et Availabil ty

of Prerequis tes

Perce ved Progress

Schedule Pressure

Out-of-Sequence Work

Mora

Expected Hours at

Comp et

Hours Expended

to Date

Skill & Experience

Hiring

Equiva ent Staff on Project

Staffing Requested

Progress

Rework Discovery

Turnover Organ zat onaSize

Changes

Staff

Productivity Quality

Added Work Obso eted

Work

Overt me

Time Remaining

Work To Be Done

Undiscovered Rework

Known Rework

Work Rea y Done

As-Built Data

StartingProgram

Conditions ion

TIME

Company Actions

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 79

Page 80: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-One simple, extreme solution

The first thing we do,let’s kill all the lawyers …

William ShakespeareHenry VI, Part 2, IV. ii.

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 80

Page 81: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

All changes from plan (both customer and company) are specified in terms of their direct impacts on the project:

�Added work scope �Added hours, without changes in “scope” �Work obsoleted �Work made uncertain because of possible

changes �Late/deficient information or equipment �Diversion of management time

How much, when, how long Copyright © 2003

9/23/03 - ESD.36J SPM James M. Lyneis 81

Page 82: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Answering the big question is a three-step process

� Step 1: Use the program simulationmodel to re-create history with thecustomer-responsible events & conditionsincluded

� Step 2: Remove the customer-responsible events & conditions and re-simulate the program

� Step 3: Analyze the differences betweenthe two program simulations – they comprise and explain the total customer-responsible cost & schedule growth.

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 82

Page 83: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Step 1: Re-creating program history (including customer claim items)

Program Labor Total Fab, Assy, Inst'n Mgmt. & Support Design Flight Test

Equi

vale

nt P

eopl

e (h

undr

eds) Dash

are Aed linesircraft

Program data

TIME

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 83

Page 84: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Step 2: Remove customer claim items and resimulate

Customer-Responsible Events & Conditions Total Program Labor (Equiv. People)X

l i

l ion Time

ii

i

le

l

l

i i l

l

i

ll

Simulation Model

Work Quality to Date

Scheduled Comp et on

Time

Expected Comp et Availabil ty

of Prerequis tes

Perce ved Progress

Schedule Pressure

Out-of-Sequence Work

Mora

Expected Hours at

Comp et

Hours Expended

to Date

Skill & Experience

Hiring

Equiva ent Staff on Project

Staffing Requested

Progress

Rework Discovery

Turnover Organ zat onaSize

Changes

Staff

Productivity Quality

Added Work Obso eted

Work

Overt me

Time Remaining

Work To Be Done

Undiscovered Rework

Known Rework

Work Rea y Done

As-Built Data Absent Customer Items

Starting Program

Conditions ion

TIME

Company Actions

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 84

Page 85: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Step 3: The claim is the difference between the simulations...

Program Cumulative Labor Hours As Built Data Absent Customer Items

Labo

ur H

ours

(mill

ions

)

Budget hours

Cust.-driven labor growth

It would have needed...

Actual

87 88 89 90 91 92 93 94 95 96

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 85

Page 86: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Actual vs. Would-Have for Ingalls

LHA Program StaffingAnnual Staffing (Person Years)

0

20

40

60

80

100

120

140

160

Actual History Would-Have Been

1969

1970

1971

1972

1973

1974

1975

1976

1977

1978

1979

1980

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 86

Page 87: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

…which includes the added delay and disruption costs stemming from customer changes

Full Impact of

Unplanned Events &

Conditions: $447M

& Disruption from $300M

$147M

$53M

Direct Cost of

0

Cum

ulat

ive

Prog

ram

Cos

ts$M

illio

n

Original Budget

Start Date Scheduled

Actual History

Cost of Unanticipated Delay

Customer Changes

Customer Changes

Overruns caused by Ingalls

Actual End Date End Date

US Navy initially acknowledged only the direct costs their changes caused – a small portion of the total $500M budget overrun

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 87

Page 88: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Ingalls was even able to quantify specific sources of cost growth

% Impact on Cost Growth for the LHA Program

Reduced Drawing Inadequate Loss of Quality Skill Level Learning Out-of-Sequence Work

6% 3% 3% 29% Delayed/ReducedQuality of PriorConstruction

14%

Other Labor Impacts Excessive Schedule

22% Pressure 23%

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis

Source: Analysis of Delay and Disruption in the LHA and DD Programs, June 1978, table 5.5 (after p134).

Page 89: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-The Navy’s starting position

“If you think you’re going to get 10 cents from us with this black box hocus-pocus simulation model, you’re nuts.”

But after a review by MIT System Dynamics Professors …

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 89

Page 90: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

How it all got started: Ingalls Shipbuilding vs. US Navy

� Case settled out of court for $447 million

� Model-generated analysis was the basisfor $200-300 million of the claim. Source: Cooper, Kenneth G., 1980, Naval Ship Production: A

Claim Settled and a Framework Built. Interfaces. 10(6) (December), 20-36.

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 90

Page 91: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Since the beginning ...

� More than 30 contract disputes � In excess of $4 billion in dispute, with

average recovery of 75% vs. 40% withtraditional methods

� All disputes have settled out of court,avoiding lengthy litigation

� More than 75 proactive applications � In excess of $25 million in consulting

fees � Conservatively saved clients $5 billion

on cost and schedule performance Copyright © 2003

9/23/03 - ESD.36J SPM James M. Lyneis 91

Page 92: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Why has system dynamics been so successful?

�Transparent and logical cause-effect structure � Facilitates discussion with adversaries � Focuses discussion on assumptions, rather than

outcomes �Highly validated model -­

� Accurate re-creation of project history (essentialfor allocating costs to causes)

� Concurrence of project managers that structureand behavior are right

� Use of models for managing other projects � Reasonableness of behavior under a wide range

of conditions Copyright © 2003

9/23/03 - ESD.36J SPM James M. Lyneis 92

Page 93: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Why has system dynamics been so successful? (cont.)

�“What-if …” capability -­� What “would-have” happened � Project future consequences � Demonstrate management reasonableness

and impact mitigation

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 93

Page 94: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Topics

• Planning – A look at issues in overlap and concurrency

• A System Dynamics View of Risk Management

• A Systems Dynamics View of Change Management and Dispute Resolution

• A System Dynamics View of Execution and Adaptation

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 94

Page 95: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

Selected Issues in Execution & Adaptation

� Managing Risks and Changes: � Schedule adjustments � Staffing strategies

A Strategic View – Deciding in advance the best way to handle problems if

they arise

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 95

Page 96: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

In the face of a projected schedule overrun, is it better to slip as soon as you know it or wait and see if corrective actions will help?

Copyright © 20039/23/03 - ESD.36J SPM James M. Lyneis 96

Page 97: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

- Graph for Staff Level 20

15

10

5

0

No Slip

Slip Early (and all along)

Slip Late

0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60 Time (Month)

Staff Level : Class7x Base People Staff Level : Class7x Slip Late People Staff Level : Class7x Slip Early People

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 97

Page 98: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Graph for Cumulative Effort Expended

400

300

200

100

0

Slip Early (and all along)

No Slip

Slip Late

0 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60 Time (Month)

Cumulative Effort Expended : Class7x Base Month*Person Cumulative Effort Expended : Class7x Slip Late Month*Person Cumulative Effort Expended : Class7x Slip Early Month*Person

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 98

Page 99: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Conclusions

� If project priorities favor cost over schedule, it’s better to slip the schedule early rather than wait until the damage is done. [Note: if rework creation is high enough, not slipping early can make the project finish later!]

� Use buffers early.

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 99

Page 100: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-

ESD.36J System & Project Management

Staffing Strategies

Copyright © 2003James M. Lyneis

Page 101: ESD.36J System & Project Management · ESD.36J System & Project Management ... Reducing Project Duration, The Pitfalls ... Traditional Projects Rarely Meet Plan Because of Rework

+

-Selected Staffing Issues

� Should staff be added to a late project (Homework 4 question)? � Unless new staff are 100% productive from

day 1, adding staff increases cost; � And, can make project later if the quality hit

is large enough � Should you start with the expected full

team, or staff up gradually?

Copyright © 2003 9/23/03 - ESD.36J SPM James M. Lyneis 101