eskom’s coal fleet operations and the challenges this presents
TRANSCRIPT
Eskom’s coal fleet operations and the challenges this presents
IEA CCC – October 2018
Sumaya Nassiep
South Africa – Electricity Overview
2
Power crisis in 2007 saw the start of electricity blackouts due to demand exceeding
supply capabilities. This combined with rapidly aging electricity supply infrastructure
reduced available capacity by ~20%.
Costs associated with building new capacity, maintaining infrastructure and pressure
to “keep the lights on” have resulted in significant increases in electricity costs over
the past five years.
Electricity generation, transmission &
distribution undertaken by State
Owned Utility, Eskom.
Eskom produces >90% of SA’s power
and approx. 80% of the power within
the SADC region
Government launched an Integrated Resource Plan in 2010, with a revised draft
released in August 2018, with the objective of establishing SA’s long term electricity
demand (2030) and how this should be met (i.e. energy mix).
4
South Africa’s Integrated Resource Plan
Draft IRP 2018 estimates an
additional 35GW of electricity
would be required by 2030.
Based on GDP growth of 4.6%
over 20 years.
IRP 2010-2030 not only seeks to
provide a sustainable affordable
future energy supply but also
focuses on job creation and
achieving the 34% reduction in
GHG emission – Paris
Agreement
Renewable Energies will
comprise 20 GW of new
capacity planned.
5
~~
South Africa - Eskom Grid Map
Current Installed Nominal
Generation Capacity ~44GW;
15 Base Load Coal Fired PS
1 Nuclear Power Station
6 Pumped Storage PS
4 OGCTs PS
1 Renewables (Wind)
Solar PV for self consumption
>32000km of Transmission lines
Electricity distribution by Eskom &
187 municipalities
Actual available supply capacity
due to UCLF, PCLF and OCLF
stands at ~35GW
New capacity construction
>8GW coal
South African Electricity Consumption, Challenges& Mitigations
6
Challenges:
• Escalating Electricity Costs
• Periodic Load Shedding
• Increasing UCLF
• Decreasing EAF
• Poor Primary Energy Quality
• Increasing cost of operation
• Increasing Environmental
pressures
Caused by:
• Growth (Population, dev.)
• Inadequate Energy Planning
• Inadequate PE contracting
Mitigating Measures:
• Introduced IDM programme
• Stepped up maintenance
• Reviewing QA of PE
• New build >8GW
Eskom Operational Performance 31/03/2018
7
• Current YTD EAF ~ 74% * Severe Coal Supply Challenges*
• Decreasing Coal Quality * PE costs increased by ~14.5% in Q1 FY19
Eskom’s Installed Capacity & Challenges
8
• Coal will remain the country’s main source of base load power until 2030
• Decommissioning of units may start as early as 2019 if demand continues to reduce.
• Coal availability, quality and price amongst the biggest challenges faced
• Increased need for HELE technologies to meet GHG emission targets.
• IPP take or pay contracts
• Tariff increases 19% requested vs 5% granted by National Energy Regulator
Eskom System Status Report @ 10/10/2018
10
UCLF Main Contributors (MCs): Boiler Tube Failures (FAE), Turbine Fault on Gen Stator
Partial Losses MCs: Poor Coal Quality (Load losses, FFP DP low, Poor Vacuum, ID/FD
Eskom R&D Focus – Coal & Clean Coal
11
Investigation activities underway to support the above:
• The main objective of ensuring sustainable coal use on new and existing plants by:
Identifying and assessing green field sources and fines for future Eskom applications;
Understand the impacts associated with the introduction of new coal technologies in
Eskom, both positive and negative (risks);
Provide implementation strategies to mitigate against coal related risks.
• Review existing reserves to identify new sources
• Develop cost effective methods to remove stone, hence improve qualities
• Consider fine coal as a reserve and develop methods of combusting coal in power station.
• Improve analytical methods to ensure that quality of coal is determined in real time – be
proactive not retroactive.
• In depth analyses of the impact of coal quality on power station so we can manage
accordingly (ETAPRO/online analysers)
Existing Coal Fleet
Eskom R&D Focus – Coal & Clean Coal
12
• South African targets a decarbonized electricity system by 2050 – expressed in it
Intended Nationally Determined Contributions (Paris Accord, 2015)
• Investigating HELE technologies to enhance environmental performance
• Focus on gasification, carbon capture and control
• Refer to additional Eskom Clean Coal Grand Challenge overview and 5 year focus
attached to email sent
Clean Coal – target to decarbonized electricity by 2050 (INDC)
Thank you
Sumaya Nassiep
General Manager (Acting)
Eskom Research Testing & Development
South Africa
Email: [email protected]
Tel: +27 11 629 5353
Mobile: +27 82 563 7429