MONTHLY PROGRESS OF THE FOREST CASES - AUGUST 2012 WESTERN REGION – I WORK AREA:- ON GOING / NEW PROJECT Forest cover Status WRSS – V 15.575 71.6450 Dahanu DTEPA area 2.289 10.5294 NOC issued from FDCM Nagpur on 02.04.09 15.245 70.1270 Jawahar 14.074 64.6319 Thane 0.88 4.0480 FDCM area Thane NOC issued by FDCM, Nagpur on 09.04.10 11.117 51.1382 Ali bag Thane Raigarh Sl. No. Name of the Project/Line State/ Forest divn. Length in KM Area in Ha A) Vapi - Navi Mumbai 400KV D/C (129.1km) M/s JSL. LOA dtd 28.12.07. Sch.Comp -Dec'09. Anticipated Comp.- Dec-2012. Rs. 5 Lacs deposited with DTEPA on dtd. 05.03.10. towards Social cost. Additional Social Cost of Rs.3 lacs deposited dated 21.09.2011 FDCM area Dahanu The combined proposal of Thane, Dahanu,Jawahar & Alibag div. forwarded by CCF, Thane to Addl. PCCF/ NO, Nagpur on 22.06.11. After scrutiny, some queries from CCF, Thane on 12.09.11.Replied on 19.04.2012 . Addl querries regarding Pvt. Forest asked to CCF thane on dt.05.06.2012. Replied on Dt. 09.07.12. . . After scrutiny and approval at PCCF, Nagpur, Proposal recommended to Pr. Secretary (Forest), Mumbai on Matheran Eco zone Matheran ESZ forest proposal accepted & minutes of meeting issued on 15.08.10. The proposal cleared in State Wildlife Board on 28.06.11. Recommendations of SBWL submitted to MOEF, Delhi on 08.08.11. Meeting of NBWL held on 14.10.11 But due to shortage time, our proposal could not be discussed & will be discussed in next meeting, next meeting of NBWL awaited,10 months over since last meeting . Petition to CEC/ Hon'ble Supreme Court submitted on 03.11.10 by CC, ESMD. Hearing is held on 19.1.11.CEC wants recommendation of NBWL for preparation of their report . 2.405 km / 11.063 Ha. 5.94 km / 27.324 Ha

Upload: dilip-kumar

Post on 28-Oct-2014

102 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: ESM Progress Report - 30.08.2012 - Latest Revision

Page 1 of 34

MONTHLY PROGRESS OF THE FOREST CASES - AUGUST 2012 WESTERN REGION – I

WORK AREA:- Sh. Jebakar James GM (Project-II)

ON GOING / NEW PROJECT

Forest coverStatus

WRSS – V

15.575 71.6450 Dahanu

DTEPA area

2.289 10.5294NOC issued from FDCM Nagpur on 02.04.09

15.245 70.1270 Jawahar

14.074 64.6319 Thane

0.88 4.0480NOC issued by FDCM, Nagpur on 09.04.10

11.117 51.1382 Ali bag

Thane

Raigarh

Sl. No.

Name of the Project/Line

State/ Forest divn.

Remarks / Responsibility Center

Length in KM

Area in Ha

A)

Vapi - Navi Mumbai 400KV D/C (129.1km)M/s JSL. LOA dtd 28.12.07. Sch.Comp -Dec'09.Anticipated Comp.- Dec-2012.

Rs. 5 Lacs deposited with DTEPA on dtd. 05.03.10. towards Social cost. Additional Social Cost of Rs.3 lacs deposited dated 21.09.2011

D.S. Bhajekar, AGM, Boisar/ 9422811705

FDCM area Dahanu

FDCM area Thane

The combined proposal of Thane, Dahanu,Jawahar & Alibag div. forwarded by CCF, Thane to Addl. PCCF/ NO, Nagpur on 22.06.11. After scrutiny, some queries from CCF, Thane on 12.09.11.Replied on 19.04.2012 . Addl querries regarding Pvt. Forest asked to CCF thane on dt.05.06.2012. Replied on Dt. 09.07.12. . . After scrutiny and approval at PCCF, Nagpur, Proposal recommended to Pr. Secretary (Forest), Mumbai on 21.08.2012

Matheran Eco zone

Matheran ESZ forest proposal accepted & minutes of meeting issued on 15.08.10. The proposal cleared in State Wildlife Board on 28.06.11. Recommendations of SBWL submitted to MOEF, Delhi on 08.08.11.Meeting of NBWL held on 14.10.11 But due to shortage time, our proposal could not be discussed & will be discussed in next meeting, next meeting of NBWL awaited,10 months over since last meeting .Petition to CEC/ Hon'ble Supreme Court submitted on 03.11.10 by CC, ESMD. Hearing is held on 19.1.11.CEC wants recommendation of NBWL for preparation of their report .

2.405 km / 11.063 Ha.

5.94 km / 27.324 Ha

Page 2: ESM Progress Report - 30.08.2012 - Latest Revision

Page 2 of 34

Forest coverStatus

Sl. No.

Name of the Project/Line

State/ Forest divn.

Remarks / Responsibility Center

Length in KM

Area in Ha

FRA

05/14 Wada, Bhiwandi & Kalyan,

Total 59.18 272.1195

Gujarat Portion

0.032 0.1472 Valsad

1.624 7.4704 Valsad

Total Gujarat = 1.656 7.6176

Total Gram Sabhas involved 39. Total 22 /39 NOC's received : NOC from 5 balance villages grampanchayat to be obtained (wada& vikramgarh)

14/15 Talasari-3/3, Dahanu-5/6 & VikramGarh-6/6

N.C.Rameshan CM(Tl) Boisar Ganesh Khorate JT 8275039204

Thane(Jawahar, Wada) proposal to be subitted to ADC jawhar for his certificate

M.N.Boro-Mgr. 9869404579 Jadhv AE 9403770388 M.N.Boro-Mgr. 9869404579 Vijay kotangale AE 9403964743

05/10 Ambarnath and Panvel , Brajesh Gawai Engr.9869080229

1st stage Approval accorded on 23rd Feb. 2010.Payment deposited at Gandhi Nagar on 28.06.10.CA = ` 1,17,384/-.NPV = `. 85,376/-.2nd stage & final approval has been issued by RMOEF, Bhopal on 16.08.10.

Rameshan,CM 9422811694

The proposal cleared in SAG on 09.12.12 & forwarded on 16.01.12 to MOEF for approval.MOEF Approved case on 01.05.2012. . Demand for Rs.2,45,468/- and for Rs.10,36,800/- received towards medicinal tree plantation. Payment made. Demand note from DCF valsad for tree cutting and strip plantation-, Rs 2,45,468 DD for cost toward tree cutting/ lopping/ trimming etc.. and Rs 10,36,800 for cost toward strip plantation deposited with SBI Gandhi Nagar, Gujarat on 09/08/12 in the a/c of Nodal Officer, FCA, Gujarat. . Collector valsad certificate for FRA compliance - NOC and undertaking etc. to be submitted to DCF for C/s of translated copy on this week and further to Collector office.

Page 3: ESM Progress Report - 30.08.2012 - Latest Revision

Page 3 of 34

Forest coverStatus

Sl. No.

Name of the Project/Line

State/ Forest divn.

Remarks / Responsibility Center

Length in KM

Area in Ha

DNH Portion.

0.138 0.6348 UT/DNH,

Total DNH = 0.138 0.6348

B) M.S.

5.746 26.432 Ali bag

C)

i)

ii)

MS

6.43 41.11 Pune

0.63 4.06 Junnar

Total 7.06 45.17

FRA

IEER Details IEAR Report finalized.

D) Mundra UMPP

i)

11.979 54.965 Dahanu

N .C. Rameshan, CM 9422811694

1st stage Approval accorded on 23rd March. 2010.Payment against Demand note deposited at Silvasa on 23.06.10.CA = ` 2,15,045/-.NPV = ` 5,99,740/-.2nd stage approval has been issued by RMOE&F, Bhopal on 18.08.10.

LILO of Lonikhand (MSEB)- Kalwa (MSEB) 400kv tr. line at Navi Mumbai (9.21 Km).M/s JSLLOA dtd 28.12.07 Sch.Comp -March'10. Anticipated Comp.- Dec-2012.

1st stage approval accorded by RMOEF on 02.06.10Following payments deposited with DFO, Alibag :-i. CA :- Rs 3783691/- on 21.06.10.ii. NPV :- Rs 19295360/- on 21.06.10.iii. Medicinal Plantation :- Rs. 5,04,441/- on 18.12.10.iv. Additional CA, as per revised rate :- Rs.33,11,612/-

CM, Navi Mumbai 9422811694

2nd stage & final approval has been issued by RMOE&F, Bhopal on 18.05.11.

SRSS-XVII, (SOUTH - WEST INTERCONNECTOR) -(765 KV Solapur-Pune Line part of krishnapatnam UMPP)

765 kV Raichur-Solapur TL (WR-I Portion)-45kms

765 kV S/C Solapur-Pune TL- (S/C-136 Km+ D/C-27 Km) NOA dated 26.06.2012 M/s JV of Isolux and Karamtara SC: June-14

The Forest proposal has been prepared & submitted to Forest Deptt. on 03.03.10. . Total number of village involved are nine.DCF( now CF), Pune is nominated as combining officer.After attending all queries CCF, Pune forwarded the proposal to APCCF/ NO, Nagpur on 14.12.11.After scrutiny, APCCF/ NO asked some queries on 23.02.12 and CCF, Pune replied the details on 11.07.12. . Proposal under scrutiny with NO. Revised route to avoid forest being explored.

M.S.Nakhre CM 9422811696/ R Wadhva Mgr.9403777804

NOC's obtained and Collector's certificate issued.

D.S. Bhajekar, AGM, Boisar/

9422811705

Navsari- Boisar 400kV D/C Line Length-281 Km/ 105 Km -WR- I (90 Km D/C + 15 Km M/C) LOA Dtd. 24.03.11.M/s L &T.SC. - May -13.

Forest proposal submitted on 02.09.11 to concern forest division. DCF, asked Powergrid to submit all documents/ NOC's & FRA to process the proposal. Tree enumeration & collection of Village maps completed. Site inspection of ACF being pursuaded.

site inspections completed-25/7/12 2 subdivision: ACF inspection completed. CA LAND IDENTIFICATION in progress

Page 4: ESM Progress Report - 30.08.2012 - Latest Revision

Page 4 of 34

Forest coverStatus

Sl. No.

Name of the Project/Line

State/ Forest divn.

Remarks / Responsibility Center

Length in KM

Area in Ha

0.74 3.404 Jawahar

0.64 2.944 FDCM, Dahnu

FRA

13.359 61.313Part - C

1

MS

0 0 Wardha Noc taken

0 0 Nagpur Noc taken

22.6 151.465 Wadsa

0.85 5.715 Brahma puri

FRA

Total 23.45 157.18

D.S. Bhajekar, AGM, Boisar/

9422811705

Navsari- Boisar 400kV D/C Line Length-281 Km/ 105 Km -WR- I (90 Km D/C + 15 Km M/C) LOA Dtd. 24.03.11.M/s L &T.SC. - May -13.

site inspections completed-21/6/12 ACF inspection completed proposal forwarded to DCF jawhar for inspection and forwarding to consolidated officer (DCF Dahanu) . CA area - to be finalised.

application dated 2/09/2011, area statement along with Map/village map etc. submitted to Divisional Manager/FDCM, Dahanu and they visited the spot subsequently. Tree ennumeartion carried out in the area by Range i/c . RFO /DM inspection to be carrid out . As asked , area demarcation has been done. Site forwarded the required details to Divisional Manager /FDCM at Dahanu. Contacted DM/FDCM of 20/06/12 and assured the document/report to be sent RM/Nasik by 1st week on 5th July due to ongoing audit at DM Office. Report and details yet to be submitted to RM/Nasik, under follow up. - Report to be forwarded. . DM FDCM dahanu has to forward the proposal to Regional Manager FDCM Nasik . . Area for CA has to be identified

Target Dates: ( To CCF - 15-09-2012 To NO - 30-09-2012 ) (NO to Stage Govt & MOEF - October 2012 ) (1st stage - December 2012) (2nd Stage - Feb 2013) . N.C.Rameshan 9422811694 Y D Naik Engr. 9423762504 Ganesh Khorate JT 8275039204

FRA- 6/14 NOC's obtained Talasari, Dahanu & Palghar tehsils involved. All the gramasabha meeting conducted, under follow up.

Raipur P.S – Wardha 765kV D/C. # ILine length -367 Km.NOA Dtd. 19.09.11. (in 3 parts)M/s KPTL, M/s L&T, M/s Gammons. SC: Aug -13

Survey Package awarded to M/s Patange & associates on 10.08.11.Route alignment approved on 13.10.11. . .

Target Dates: ( To DCF - 25-08-2012 To CF - 15-10-2012 To NO - 15-11-2012 ) . (NO to Stage Govt & MOEF - 31/12/2012 ) (1st stage - February 2013) (2nd Stage - March 2013)

Proposal submitted on 31/05/2012. Route alignment revised to reduce forest Proposal resubmitted on 10.08.2012 Tree enumeration,CA Land etc to be completed-21/08/12 to -31/08/12

10/16 NOC's obtained. . SDM Brahmapuri forwarded letter to collector Chandrapur on date 14.08.2012 for issue of certificates under FRA.

S.K. Dambhare, AGM, Bvt / 9422811689 B. Kumar, CM. 9403777802 B.L.Kumare Mgr.9423762543

Page 5: ESM Progress Report - 30.08.2012 - Latest Revision

Page 5 of 34

Forest coverStatus

Sl. No.

Name of the Project/Line

State/ Forest divn.

Remarks / Responsibility Center

Length in KM

Area in Ha

Part - D

1

24.3963 163.455 Wadsa Proposal submission likely by 10/09/2012

0.98 6.566 Brahma puri Brahmapuri DCF on date 24.08.2012.

2.69 18.023 Bhivapur

28.0663 188.044 FRA 05/14 NOC's obtained.

Part - E

1

D.S. Bhajekar

5.516 25.3736 Dahanu,

7.5 34.5 FDCM Dahanu

13 60 Jawahar

3.76 16.7 Nashik (E) Case submitted on 10.08.2012

0.296 1.1782 Nasik (west) Case submitted on 10.08.2012

1.93 8.811 FDCM /Nashik Case submitted on 10.08.2012

Raipur Pooling Station – Wardha 765kV D/C # II NOA date 14-03-2012Line Length-380Km.Part-I- 190 Km.M/s Aster & Deepak.Part-II- 190 Km.M/s Gammon. SC: Nov 2014

Route alignment approved on 03.07.12. Detailed survey is being carried out under main package. Application submitted to Collector Chandrapur & Gadchiroli on Dt.07.06.12 & 08.06.12. . .

Target Dates: ( To DCF - 10-09-2012 To CF - 31-10-2012 To NO - 30-11-2012 ) . (NO to Stage Govt & MOEF - Jan-2013 ) (1st stage - March 2013) (2nd Stage - May 2013)

B. Kumar, CM. 9403777802 B.L.Kumare Mgr.9423762543

Nagpur Forest proposal submitted to DCF, Nagpur on date 23.08.2012

Aurangabad (PG) –Boisar 400kV D/C (Quad). M/s. Ranjeet Singh and M/s. Deepak cablesLine length-336.7Km SC: May 2014

Route alignment approved- 27.04.12. Detailed survey completed by M/S deepak Cables/KCL (as M/S Fatangle backed out)

Proposal likely to be submitted by 18-08-2012. case submitted 18.08.12, matter appraised to DyCF.

Target Dates: ( To DCF - 31-08-2012 To CF - 31-10-2012 To NO - 15-11-2012 ) . (2nd Stage - May 2013) NC Rameshan,CM Sh.Sharma Mgr./ Y D Naik Engr. 9423762504

FDCM Official agreed to visit site for area identification on 14-08-2012. case submitted to FDCM Ltd , 06/08/2102, AM/ FDCM Ltd visited the spot along with his staff on 14/08/12, promised to start demarcation /identification/measurement of each section/and further tree enumeration wef 22/08/2012. M/s Deepak has to deploy their gang since the M/s KCK is not in picture ( backed out)

case Submitted on 06.08.12. All the gramasabha meeting taken up ( except 3) under follow up.

S R Sharma CM 9422811700 Sandeep Bhitre Sr.E.9423959590

Page 6: ESM Progress Report - 30.08.2012 - Latest Revision

Page 6 of 34

Forest coverStatus

Sl. No.

Name of the Project/Line

State/ Forest divn.

Remarks / Responsibility Center

Length in KM

Area in Ha

FRA

32.002 147.2092

Part - F

1

7.7 35.55

FRA 7 Gram sabhas - Applications Submited.

2

34.0299 228

Thane

Junnar

FRA

Aurangabad (PG) –Boisar 400kV D/C (Quad). M/s. Ranjeet Singh and M/s. Deepak cablesLine length-336.7Km SC: May 2014

Application given for FRA to all tehsils. Gramsabhas details under collection.- Nasik District: - Total 9 - Dahanu - 16 gramasabha involved under Vikramgarh/Jawhar/Mokhada Tahsil. Village marking under progress.

Padghe – Padghe (PG) 400kV D/C (Quad) Line Length- 25 km LOA Dtd. 13.02.12.M/s Shyama Power. SC- Feb, 2014

Survey Package -M/s Geoinfoysis Technologies, on dt. 19.10.11.Route alignment submitted on dt 07.08.2012 - Under approval .Detailed survey to start by 14th and likely to be completed by 20th. Forest proposal to be submitted by 31-08-2012.

( To DCF - 31-08-2012 To CCF - 15-10-2012 To NO - 30-11-2012 ) (NO to Stage Govt & MOEF - 31-01-2013 ) (1st stage - March 2013) (2nd Stage - April 2013) M.M.Mehandle 9422811701 M.N.Boro Mgr. 9869404579 Ranjeet Thamke

Aurangabad (PG) - Padghe (PG) 765kV D/C line.Line Length - 300 Km (Not yet Awarded)

Survey Package awarded to M/s Geoinfoysis Technologies, on 19.10.11. Route alignment approved on 16.05.2012 Detailed survey yet to start. Being the same survey agency priority given to Padghe-Padghe line. . Forest area to be identified . . Proposal likely to be submitted by 30-09-2012.

Target Dates: ( To DCF - 30-09-2012 To CF - 31-11-2012 To NO - 15-12-2012 ) . (2nd Stage - 31-01-2013) M.Mehandle/ M N Boro Mgr. / Ranjit Thamke Engr.

N Rao Mgr./ Ritesh Mendhe SE 9423077740

FRA-Details being collected approx 11 Gramsabhas' identified.

Page 7: ESM Progress Report - 30.08.2012 - Latest Revision

MONTHLY PROGRESS OF THE FOREST CASES - AUGUST 2012 WESTERN REGION – I

WORK AREA:- Sh. A.K Sinha GM (Project-I)

ON GOING / NEW PROJECTSl. No. Forest cover Status

Length in KMArea in Ha

A WRSS-VC.G

Nil DurgNil Rajnand-gaon

3.34 15.37 Khairagarh

M.S.17.59 80.91 Gondia

4.35 20.00 FDCM, Gondia.Total 21.94 100.91

FEAR

Name of the Project/Line

State/ Forest divan.

Remarks / Responsibility Center

400 KV D/C Raipur Wardha (370.484 KM) - M/s L & T :- a) G-3 Package :-182 Km. LOA Dtd 25.04.08. Sch. Comp. - July 2010 b) G-4 Package :-184.4 Km. LOA Dtd 25.04.08. . Trg. Dt.- Dec-2012.

1st Stage approval is accorded by RMOEF on 31.05.10.Following payments have been deposited.i) NPV, deposited on 10.08.10 --Rs.89,42,039/-.ii) CA, Deposited on 10.08.10-- Rs.24,49,841/-.iii) Med. pltn on 26.10.10 --------Rs 79680/- .iv) Cost of vehicle on 03.11.10- Rs. 9,77,055/-. (for RMoEF office, Bhopal)2nd stage & Final approval issued on 09.03.11 by RMOEF, Bhopal.Cost of tree cutting amounting to Rs. 7,86,986/- deposited to DFO, Khairagarh on 11.04.11. Approval of tree cutting accorded on 05.05.11. Tree cutting in foundation area completed. DFO, Kairagarh asked on 15.09.11 for deposition of following additional amounts.> Rs. 2,44,945/- towards CA .> Rs. 7963/- towards medicinal plantation.Total amount deposited= Rs. 2,52,953/- on 23.09.11

The proposal is forwarded by Mantralaya, Mumbai on 19.05.11 to MOEF, Delhi with copy to RMOEF, Bhopal.FAC held on 26.08.11. Proposal accepted by members in principle but comments has been asked from National Tiger Conservation authority (NTCA), Delhi. FAC minutes of meeting signed on 28.09.11.NTCA submitted their recommendation to MOEF, on 21.12.11.The proposal again discussed in FAC, held on 27.12.11 & cleared for approval of MOEF. N. Delhi. Ist stage approval issued on 30.04.12. (i) NPV Rs.7.875 Cr. = 23/05/12(ii) CA Rs.5.61 Cr. = 23/05/12(iii) Wildlife mitigation Plan cost Rs.21 lakhs = 5/06/12(iv) Medicine plantation scheme Rs 2,71,02,113/- = Dt: 20/07/12(v) FRA Compliance/NOCs' Completed – 12/07/12(vi) Cost of Inspection vehicle Rs. 7,50,000/- Deposited on Dt: 20/07/12(vii) FDCM Rs. 7, 40,57,894/- Deposited on Dt:26.07.12(viii) Tree Cutting Charges Rs.12,21,026/- Deposited on Dt:17.08.12Grand Total Amount Rs. 24,01,18,021/-

Atul Shrivastava, DGM, T/L Durg 9425293997

Compliance report recomended from N.O (APCCF) NGP to AIG (Forest) MOEF New Delhi on date 24.08.2012

FEAR finalized on 11.11.09. MOEF Approved the proposal on 18.04.2012 .

Page 8: ESM Progress Report - 30.08.2012 - Latest Revision

B 'DVC- Project BilaspurChampa

0.94 6.02 Rev.FKorba

0.88 5.63 PF3.49 22.34 Orange F

11.22 71.81 Rev.FJashpur

1.77 11.30 RF4.65 29.77 PF1.19 7.65 OF3.81 24.36 Rev. F

Dharamjaygarh

5.57 35.65 RF2.31 14.79 PF1.45 9.26 OF9.73 62.29 Rev. F

Total 47.01 300.86

FRA

Tr line in CG associated with IPP ChhattisgarhPART-B

C) 3.81 25.51 Raigarh

FRA

D)

JaspurKorbaDharamjaygarh

163.80

FRA FRA after registration of proposal.

Ranchi TL- Bilaspur 765 KV S/C (299.25 KM) - M/s L & T :- LOA Dtd 10.09.08. Trg Comp. - Feb-2013

Proposal cleared in FACs held on 26.08.11 / 27.01.12./15.05.2012 Site inspection conducted on 29-30/06/2012 by AIG MOEF. Inspection ok . Report under preparation by AIG MOEF.1st Stage Approval to be issued.

CC- ESMD

FRA -Compliance/NOCs'being Completed for issue of Collectors certificate. Total 14/39 NOC's obtained.

R. K. Gabel, CM, BSP. 9425409537

Raigarh P.S (Kotra) – Raigarh P.S (near Tamnar) 765kV D/C Line length -47.68 KmLOA Dtd. 08.08.11.M/s Gammons. SC- Aug-13

Route allignment approved on 12.10.11.- Forest Proposal Registered on 24.04.2012. - Tree enumeration completed on 15.06.2012 -CA scheme for 51.00 Ha forest land submitted to DFO, Raigarh on 25.07.12 by SDO Gharghoda. - Tree enumeration list (remaining for 01 range) is verified by & forwaded to DFO Raigarh on 27.07.12. Recommended from DCF to CF – 08.08.2012. Recommended by CF Bilaspur to CCF, Raipur on 22.08.2012

Target Dates: (To NO - 30-08-2012 ) (NO to Stage Govt & MOEF - 30/09/2012 ) (1st stage-30-10-2012 ) (2nd Stage-15-01-2013) . S.K. Ghosh, DGM, 9425409530 R.R. Bharaskar, CM/ 9425409538 Shukla (JE) - 0926610204

Total - 4/4 NOC obtained. FRA Compliance FRA Certificate received from Collector, Raigarh.

765 KV S/C Ranchi (New)- Korba TL. (164 km) M/s Tata Projects. (Wr-1 Portion) SC: Feb-14

Survey package awarded to M/s Pioneer on 30.9.11. -Not completed..One Route alignment approved on 18.01.12.During detailed survey it is observed that coalblocks near dharmjaygarh are encoutering in route aligment . Alternate route exploration under progress. Letter for identification of Revenue forest in Lailunga & Dharamjaygarh Tehsil submitted to respective tehsildar for further processing on 24.07.12. Proposal Registration likely to be submitted by 1st week of september. After Registration detailed survey shall commence.

Target Dates: (To NO - 15-11-2012 ) (NO to Stage Govt & MOEF - 30/11/2012 ) (1st stage-15-12-2012 ) (2nd Stage-31-01-2013) . S.K. Ghosh, DGM, Raigarh/ Sanjay Chaurasia (JE) 9424146605

Page 9: ESM Progress Report - 30.08.2012 - Latest Revision

E)

M/s KEC - ER (16 km) 13.45 94.25 Raigarh

2.04 13.65 Dharamjaygarh

4.41 29.53 Korba

TOTAL 20.51 137.44

FRA

F)

Korba Route Being revised.Katghora

9.73 65.23 Marwahi Forest Proposal submitted on 28-07-2012.

20.77 133.16

FRA

Jharsukuda Dharamjaygarh (korba) 765 kv. # I Length-69km LOA Dt: 18.01.11 M/s Tata Projects SC -June-13

Forest proposal: - Registration of forest proposal for 03 divisions done on 23/05/2012, 29/05/2012 and 08/06/2012. NOC of Revenue forest obtained -09.05.2012. CA land identified for WR area. ER in process. Route alignment being revised to avoid coal blocks in consultation with CMPDI. Revenue & RF/PF/OA Identification is under process in diverted route .

Target Dates: (To NO - 15-09-2012 ) (NO to Stage Govt & MOEF - 01/10/2012 ) (1st stage-30-11-2012 ) (2nd Stage-31-01-2013) . S.K. Ghosh, DGM, Raigarh/ V K Swarnkar, Sr. Er (9422303129) Kamal Rathore, JE (975392327)>New RF/PF/OA has been verified in

diverted route and an intimation letter submitted to DFO Raigarh for change in line route on date 13-08-2012. >DFO letter for tree enumeration in new stretches awaited.

Mr. Pradhan, Sr. Er (ER) - 09179077729

>CA Scheme complied for 27.304 hectares forest land under Dharamjaygarh Forest Division, being ratified by RFO/SDO at field level. >CA scheme signed by Deputy Ranger Chhal on date 16.08.2012

B. Sahu CM, (9425409539) Jayant Nimje, Er. Korba (09425293807)

FRA- 9/11 NOC- WR-I & 1/12 NOC- ER-I 01)FRA Certificate obtained from 06 Gram Panchayat out of 08 in new format (under Raigarh TLC) 02)FRA Certificate obtained from 05 Gram Panchayat out of 10 Gram Panchayat ( 15 Villages ) in new format ( under Gharghora Villages ) in new format (under Gharghora TLC diverted portion from ER-II) SDM Dharamjaygarh forwarded the FRA Verification letter to collector Raigarh in old format.

Korba -Jabalpur, 765 Kv D/C (140km) WR-I LOA Dt: 18.01.11 M/s Tata Projects (CG-131.161 Ha/ 20461 km) SC: June-13

Route alignment finalized on 24.11.11.Forest proposal registered with CCF/Nodal Officer, Raipur on 08.02.12. An amount of Rs. 550000/- has been deposited against registratin fees. DFO (Khatgora) & DFO (Marvahi) permitted for detailed survey on 12.3.12 & 30.3.12. Detailed survey started on 30.04.201221/37 Kms. completed.

Target Dates: (To NO - 30-09-2012 ) (NO to Stage Govt & MOEF - 15/10/2012 ) (1st stage-31-12-2012 ) (2nd Stage-31-01-2013) . . D.K.JAVERI, 9425409535 B.SAHU ,CM/ 9425409539/ Jayanth Minz, Sr. Engineer, (9425293807)

Detailed Survey completed, Forest Identification under progress, likely to be completed by first week of september.

Gramsabhas- 10/54 Marwahi - 10/14 . Katghora - 0/40 . Korba- To be identified.

Page 10: ESM Progress Report - 30.08.2012 - Latest Revision

Part - GG) 218.20 C.G

6.79 46.84 Champa24.84 171.37 Bilaspur

Total 31.62 218.20

FRA

H)

15.00 100.50 CG

+/- 800kV, 6000MW HVDC Bipole between Champa Pooling Stn – Kurukshetra (NR) 156 Km. (WR-I Portion).

31.62 (*walk over survey)Survey package awarded to M/s Pioneer surveryors on 30.9.11. Route alignment approved on 07.03.12.Detailed survey in forest is in progress. Champa collector forwarded application to SDM & SDM forwarded to Tahsildar. Tahsildar forwarded RI. Patwari verification is completed and forwarded to SDM . Letter forwarded to Collector by SDM on 29.06.2012. . NOC for Revenue forest - Bilaspur District - Received on 04.08.12. Champa District - Applied on 24.05.12 & subsequently forwarded to field level through SDM Janjgir & Tahsildar Akaltara. Field inspection completed (No revenue forest invloved) & report forwarded to Tahsildar. Tahsildar asked certain clerification from RI. Detailed survey (47Km) - 38Km in revenue forest/area having less tree density/plain area has been completed. Detail survey in hilly forest area is to be taken up after getting survey approval. Proposal Registration - Applied for registration on 07.08.2012 to CCF, Raipur.

Target Dates: (To CCF - 31-08-2012 To NO - Nov-2012 ) (NO to Stage Govt & MOEF - Dec-2012 ) (1st stage-Jan-2013 ) (2nd Stage-Oct-2013) . . S.SAHU/9425409662

S.K KAMILA, Chief Manager ( 09425293345 )

21 Gramsabhas' involved. FRA to be started after Registration/submission of proposal.

NCC Srikakulam Tr. System:

S.K. Ghosh, DGM, Raigarh/

765 KV D/C Jharsukuda- Dharamjaygarh TL - IInd CktWR-1:-110 KM

Survey Package is awarded to M/s Designer Consortium on Dt. 23.04.12Route alignment to be finalised, avoiding coal blocks.

Page 11: ESM Progress Report - 30.08.2012 - Latest Revision

MONTHLY PROGRESS OF THE FOREST CASES - JULY2012 WESTERN REGION – I

COMPLETED PROJECTSTRANSMISSION LINE PROJECTS:

A)

M.S.

(346km) 19.251 100.105 Wadsa Payments:

M. P State – 180km 8.736 45.427 NPV- Rs .9,82,26,000/-

DOCO-01.06.05. Total 145.532

128.75

Total- Rs.11,38,62,720/-

Tree felling - Rs. 24,99,419/-Final approval - 08.10.04

6.169 28.37 Wadsa

CC,ESMD

Advance Payments made :CA – Rs 30,82,000/-NPV - Rs. 2,25,61,000/-

157.12 TOTALTotal- Rs. 2,60,04,930/-

B) M.S.

4.506 23.431 Dahanu Payments :

DOCO-01.08.05. C.A. - Rs. 1,19,51,720/-5.125 17.938 Dahanu NPV - Rs. 7,62,82,000/-

DOCO-01.09.05. Dwarf - Rs. 17,68,900/-7.30 36.554 Dahanu

(31.0km)- Phase-I Final approval - 17.02.05.DOCO-01.08.05.

4.986 25.927 Dahanu (10 time plantation cost).

(86.0 km)- Phase-II 3.474 18.064 Thane.

DOCO-01.03.05. 8.460 38.92Nil Nil Jawar

Total 121.63/

AGM BOISAR

SYS. STRENGTHENING SCHEME

'400KV D/C Raipur- Chandrapur

In principle approval- 22.06.04.

Chhattisgarh state -166km

CA – Rs. 1,39,90,000/-

Brahma puri

Med. Plant.- Rs . 16,46,720/-(Revised ROW-46m)

Additional area .Case forwarded to MOEF by Secretary (F). Maharashtra on 10.01.07.Ref FLD/3606/CR/171/F-10.

Issue of approval awaited from MOEF.

Med. Plant. – Rs. 3,61,930/-

TARAPUR 3 & 4 TRANS.SYSTEM

In principal approval- 12.08.04.

Tarapur-Boisar 400KV D/C (20km) - Phase-I.

Tarapur-Boisar 220KVS/C(21.00km)-Ph-I

LILO Of Jhanor – Padge /C Line At Boisar

Total - Rs. 9,00,02,620/-

Tree Felling- Rs. 2,79,534/- DTEPA- Rs. 92, 45,345/-

Tarapur-Padge 400KV D/C

Payment towards Social Cost to DTEPA(Dec-07 )- deposited

Rs. 5.0 lacs

Add. Payment of Rs 2.5 Lacs has been deposited to DTEPA.

Page 12: ESM Progress Report - 30.08.2012 - Latest Revision

Total109.916

AGM BOISARC) SIPAT-I TR. SYS.

CG

10.267 65.700 Kawardha Payments

CKT-II. (344 km) C.A. – Rs .94.18lacsNPV – Rs.10,06,11,100/-

- Rs. 75,75,440/-9.545 61.033 ---do— (Additional amt.)

19.812 126.733 Final approval- 09.06.03.3.993

In pr. approval -18.7 05. Payment made. (Oct’05.)C.A. Rs 3,56,720/-NPV- Rs 33,54,120/-

DGM, Bilaspur

Dwarf Tree plant Rs1,78,360/-Total- Rs.38,89,200/-Final approval: 30.03.06.

Nil Nil No forest.

D)

M.P.

Sidhi East Final approval -30.06.05.2.475 12.87 PF Payments

CA- Rs. 8,80,068/- (revised )NPV- Rs. 74,64,600/-Med Plant – Rs. 2,72,187/-

2.475 12.87 Total –Rs. 86,16,855/-CG

16.364 85.09 NPV- Rs. 74,64,600/-

RF/PF Med Plant – Rs. 2,72,187/-0.9 4.68 Total –Rs. 86,16,855/- CM, Satna

3.5 18.2 Rv. F20.764 107.97

0.9 4.68 Korea

3 15.6 Payment: on 26.01.06.Nil

3.9 20.2816.954 88.1608

2.36 12.272 DGM BSP20.759 107.946840.073 208.3796

Total CG 64.737 336.63-12.2 (Excl. common land with PIL )

324.43IEER CC, ESMD

E)

Add. Payment of Rs 2.5 Lacs has been deposited to DTEPA.(REDUCE

D ROW-46m)

Sipat-Seoni 765KV S/C Ckt-I (343 km)

Ist stage approval- 03.03.03.

Chhattisgarh – 178km

Chhattisgarh – 179km

IA –10.12.03.Appd .Cost – Rs. 237.02.Crores

Kawardha '(Addl area)

Due to variation in HFL of reservoir of dam, there is a revision in small stretch of forest.

LILO of Rourkela-Raipur 400KV D/C at Raigarh (30 km)

SYSTEM STRENGTHENING SCHEME

Investment Appl.– 31.01.04.Appd .Cost – Rs 164.02 Crores. Sch Comp.- Feb’07

Vindhyachal – Korba Ckt-II 400KV S/C. (284 km )DOCO-01.06.2007

Ist stage approval - 28.01.05.

North Sarguja

South Sarguja

Ist stage appl. - 10.11.05. Final approval : 07.03.06.

(OrangeF) Rev.Forest

CA Rs2,89,97,768/-NPV Rs 27,79,57,440/-Med. Sch. Rs 41,95,802/ (paid on 27.07.06.)Total Rs 31,11,50,810/-Tree cutting cost – paid to DFO (North Sarguja) – Rs.50

Kathghora 12.272 Un demarked

IEER data sent to CC, ESMD vide IOM dated 01.09.04. IEER report to be finalized by CC ESMD.SIPAT- II TRANS.

SYSTEMInvestment Appl. – 23.08.04.Appd .Cost – Rs601.90Crores

Page 13: ESM Progress Report - 30.08.2012 - Latest Revision

E)

Sch Comp.- Aug’07.Nil Nil CG No forest involved. AGM, Raipur

F)Nil Nil MS No forest involved.

AGM B’vati

NIL Nil CG

AGM, RaipurIEER

G) CG

Korba

5.815 26.749 Rev. F.

0.8 3.68 Orange F

Total F 6.615 6 Payment Details.

8.329 38.314 Rev. F.

1.22 5.612 Orange F

1.415 6.509 PF

4.265 19.619 RFTotal 15.229 70.054

Jashpur2.541 11.688 Rev.F0.26 1.196 Orange F2.52 11.592 PF1.775 8.165 RF

Total F 7.096 32.641Bilaspur

0.64 2.944 Rev.F.Champa

1.16 5.336 Rev.FTotal 30.74 116.975 DGM, BSP

IEER

H)

M.P. Survey M/s Shyama Power (CC LOA 11.06.04.)

In principle appl. 15.11.06.

Payments deposited as :LOA dtd 08.09.06. – 3.37 21.568

RFCA = 77,10,774/-

LILO of Korba- Raipur 400KV at Bhatapara S/s WR SYSTEM STRENGTHENING Bhadravati-Chandrapur 400KV (22.75 km)

Sipat –Raipur 400KV D/C – (147.65km)

Survey -M/s Tata Projects (CC LOA 11.06.04.)

IEER data sent to CC, ESMD vide IOM dated 23.07.04.

KAHALGAON STAGE -PHASE-II

Ranchi-Sipat 400KV D/C Tr. Line (288KM- WR Portion)

Ist Stage approval issued by MOEF on 29.11.2007

M/s L&T (Part-I) LOA ref No. -C-46503-L195-3/LOA-II/1811 dtd 7.10.05

M/s JSL (Part-II) LOA ref no. - C-46502-L195-3/LOA-II/1807 dated 06.10.05

Dharamjaygarh

CA 141.404 x 2 @65825/- ha) = 1,86,15,837/-

NPV = 116456820

Tree cutting = 2782125

Payments deposited. = 137,854,782

Demand note of Rs. 2072360/- for Medical Plants, issued by Nodal officer (DFO, Korba). The payment is under progress.(Rate revised from Rs.59840/- (2006-07) to Rs. 65825/- (2007-08)Total NPV deposited Rs.116456820 /- out of which Rs.30193020/- for 38.709 Ha of Bilaspur, Korba & Champa forest area and Rs.86263800/- Final Approval issued by MOEF New Delhi dated 05.05.08

IEER Data sent to CC, ESMD on 02.02.06 for finalization of IEER report. IEER finalized (March’06)

SIPAT –II SUPPLY. TR. SYSTEM.

Seoni-Wardha 765 kv S/C(278km)ckt-I Chhindwar

a

M P State – 160km

Page 14: ESM Progress Report - 30.08.2012 - Latest Revision

NPV =1,29,40,800/-

Total = 2,06,51,574/-

DOCO 01.04.2009 Med. Plant =2,96,212/-Total = 41599360/-

DGM' Seoni

Wardha

3.896 24.934 RF M/s ATSL (135km) 0.16 1.024 PF

0.66 4.224 (Zudpi forest)

4.716 30.182

Wardha Dvn. ( 30.186 ha)

0.985 6.3 Nagpur Nagpur Dvn.(6.3 ha)

CM, WardhaTotal 5.701 36.482

I) NIL

MSBuldana Payment made on 02.03.07 as

LOA dtd 20.12.06. 0.7 3.22 RF CA - Rs 3.26lacs

NPV - Rs 19.90lacs

M/s EMC Part – I (138km).

LOA comp sch.-Sept’08

Final /II stage approval issued by MOEF on 13.11.07.

Maharashtra -118km

Ist stage approval issued dated 11.10.2007.

LOA comp sch.-Sept’08

Payment for CA & NPV deposited:

CA(60.372 ha x 66203/-) = 39,96,808

NPV = 2,56,01,420

Survey and demarcation = 17,000

Boundary Pillars = 93,600

Tree felling (2878 nos.) = 3,20,827

3,00,29,655

CA(12.6 ha x 66203/-) = 8,34,158

NPV(6.3ha x 694000) = 43,72,200

52,06,358 Total 3,52,36,013

Payment deposited with Forest Dep't. On 07.01.2008.

Cost for Med. Plant. - Rs.13,47,316/-

Final Approval issued by MOEF on 16.04.08

Wardha –Akola 400KV D/C (184km)

Survey -M/s Shyama Power (CC LOA on 11.06.04). Detailed survey completed

LOA – 02.08.06. M/s ATSL

LOA comp sch.-Aug’08 DOCO 01.04.09

Akola- Aurangabad 400KV D/C

Survey- M/s Tata Projects (CC LOA dtd 30.06.04)

(250km.) -In principle appl - 11.01.07.

M/s ATSL Part – I (110km)

Page 15: ESM Progress Report - 30.08.2012 - Latest Revision

Total - Rs 23.16lacs

LOA dtd 02.02.07.– Addl. CA - - Rs.1,00,347/-

CM, WardhaIEER

J) M.S.0.779 3.583 Pusad RF

Nil

Nil Hingoli Nil Nanded Nil Beed

K)

0.24 1.104 PF0.66 3.027 OF4.55 20.926 RF

Total (a) = 5.45 25.057

1.59 7.314 OFTotal (b) = 1.59 7.314

DGM, BSPTotal (a) + (b)= 7.04 32.371 L ) WRSS-II

SET :- AMSWardhaHingoliBeed

2.582 11.877 Pusad RF

Parbhani0.59 2.714 RF

Yavatmal

CM (Wardha)

0.96 4.416 RF0.2 0.92 C- class

0.945 4.347 E- class2.105 9.683

Total 5.277 24.274

LOA comp sch.-Dec’08

M/s pt Multifabrindo (140km)

Med.Platn. - Rs. 1,20,750/-

LOA comp sch.-Feb’09

Final approval issued by RMOEF (Dec-07)

PUBLIC CONSULTATION

PCP carried out on 25.09.04 in Seoni- Wardha line. Report submitted to CC ESMD on 12.10.04.

IEER Report finalized and submitted to the World Bank in Dec-04. (MOU Target 04-05)

(Initial Environmental

Bhadravati-Parli (PG) 400 KV D/C (387KM) - M/s L & T :- a) G-1 :-190 Km. LOA Dtd 25.04.08. Sch. Comp. - May 2010 b) G-2 :-197 Km.

1st stage Approval dtd 23.12.09 received. Following amounts have been deposited with Forest Departments.1. NPV = `32,52,150/- on 04.04.102. CA = `4,04,361/- on 04.04.103. Tree Cutting = ` 72,725/-. on 19.05.10.4. Medicinal Plant = ` 2,02,588/-.

Chandrapur

KORBA III 400 KV D/C Korba - Raipur TL (215 KM) - M/s KPT L :- LOA Dtd 10.09.08.

C G . Katghora Forest division

I st stage approval accorded by RMOEF, Bhopal on 23.11.10.Following amounts have been deposited with Forest Departments.1. NPV = ` 2,08,79,433/- on 14.01.11.2. CA = ` 1,81,28,149/- on 14.01.11.3. Medicinal Plant = ` 1,68,204/-. on 14.01.11.2nd stage approval accorded by RMOEF, Bhopal on

Bilaspur Forest div.

400 KV D/C Wardha-Parli (New) (330KM) M/s JSLLOA dtd 28.04.08Sch. Comp -March'10 .Anticipated Comp.-

-  NOC obtained -         -do--         -do-1st stage approval issued by RMOEF, on 10.03.11. Demand notes collected from following divisions & following payments are deposited on 25.03.11.Further balance payment towards CA & NPV deposited on 23.05.11.Details of Yavatmal Div. Pusad div. Parbhani Compliance

Page 16: ESM Progress Report - 30.08.2012 - Latest Revision

M) WRSS-II :- Set -AM.P

0.743 4.755 PF2.911 18.630 RF

Total (a) = 3.654 23.386

0.331 2.118 R.F

DGM, Seoni

Total (b) = 0.331 2.118Total ( c) = 0.718 4.595

Total (a+ b) = 4.703 30.099

CM, Wardha

4.65 29.760 RF0.17 1.088 PF1.035 6.624 Zudapi

Total = 5.855 37.472

0.33 2.112 PF0.05 0.320 Zudapi

Total = 0.38 2.432Total (M.S area) = 6.235 39.904

Total ( MS + MP) = 10.938 70.003

'Seoni-Wardha 765 KV S/C (2nd ckt)-268KMa) 1) M/s IVRCL :-135 Km. LOA Dtd 13.02.09. Sch. Comp. -

1st stage approval issued by RMOEF, Bhopal on 06.09.11. Amendment for ML plantation issued on 20.9.11.The breakup of total payment deposited * is as below. Chind Div. Chind. Div. Total Amt paid (South) (West)1. NPV- Rs.22468743 Rs.1700754/- Rs24169497/-(*on 17.10.11)2. CA - (Rs. 16368558 + 1636842/-) = Rs. 18005400/-(* on 25.11.11 with DFO, South)3. Med. Platn. = Rs. 977200/-

Chhindwara Dev.- South

Chhindwara Dev.- West

Revenue forest

2) M/s KEC :-133 Km. LOA Dtd 13.02.09. Sch. Comp. Feb.2011. Anticipated Comp.-Fb. 2012

Maharashtra

Wardha Division

1st stage approval accorded by RMOEF on 10.03.11.The breakup of total payment deposited is as below. Nagpur Div. Wardha Div. Total Amt paid1. NPV. ` 2021980 `38317440 `403394202. CA. `1212532 `18696525 `199090573. Diff. CA ` 17447 `2950350 `29677974. Tree Cutting. `6911 ` 1942003 `19489145. Med. plant. --

Nagpur Division

Page 17: ESM Progress Report - 30.08.2012 - Latest Revision

IEER

N) WRSS#II-set- DMP

Anuppur

1.46 6.716 RF

0.82 3.772 PF CA - Rs. 2,00,35,839/-Total 2.28 10.488

Umaria18.773 86.356 RF

Total 18.773 86.356G.Total for MP 21.053 96.844

DGM, BilaspurCGKathghora

16.593 76.329 Rev. F5.28 24.288 OF6.105 28.083 PF

Total 27.978 128.700Marwahi

DGM, ESMD, CC

1.045 4.807 PF5.21 23.975 Rev.F.

Total 6.257 28.782 G.Total for CG 34.235 157.482

IEER data pertaining to all above lines under WRSS-II Project –A ,submitted to CC ESMD on 19.01.06.

IEER report finalized on 18.12.06. (MOU TARGET 06-07)

400KV D/C Korba-Birsinghpur (226.198km) M/s SPIC-SMO.LOA dtd 01.06.07.Sch. Comp May'09.Anticipated Comp.- Nov. 2011.

1st stage Approval accorded on 2nd March 2009.

Final approval of MOEF received on 09.11.09.

Payment against Demand note dtd. 14.05.09 deposited in DFO office.

NPV - Rs. 80889319/- + Rs. 9848232/- = Rs. 90737551/-

Total Amt deposited= 11,07,73,390/-

Cost of Medicinal plantation of Rs. 3408229/- & Rs. 413931/- deposited to DFO, Umaria & DFO Anuppur respectively on 01.02.10.AnuppurCost of tree cutting of Rs. 1st stage approval accorded on 28.07.10 by MOEF.Following payment against Demand note dtd. 12.08.10 deposited on 06.09.10 to DFO, Katghora.NPV - ` 10,00,16,721/- on 06.09.10.CA - ` 2,51,30,913/- on 06.09.10.Cost of tree cutting- Rs. 72,64244/- (Rs. 6115021- Kathghora div. & Rs. 1149223/- in Marvahi Div.) deposited on

Page 18: ESM Progress Report - 30.08.2012 - Latest Revision

FEAR

O) Mauda Tr systemi) MS

Nagpur Div

2.974 13.68 PF

ii) Part-II-60 km.NOC for DFO, Wardha obtained on 09.08.10.

P) Nil Nil No forest involvement

Q)

Nil Nil No forest involvement.

LOA dtd 22.08.07

DGM DurgIEER

(Sudarshan Telang) Mgr. ( Engg-ESM)

FEAR data has been forwarded to CC, ESMD & report forwarded Sep.09.

Mauda -Wardha 400 Kv D/C Line length 120 KmLOA Dtd. 23.03.2010.M/s Bajaj Electricals Ltd.Comp. Sch. June 11.Anticipated Comp. = Nov.2011

Part -I -60 km. Forest Proposal submitted to DCF, Nagpur on 27.09.10.

AGM, Bvt/ DGM, Engg & ESM

The proposal cleared in SAG on 08.12.12.Approval of MOEF, N. Dehli 2nd stage & Final approval issued on 23.02.12 from RMOEF, Bhopal

Parli(PG)Parli (MSEB) 400 KV D/C(7KM)EAST-WEST TR. CORRIDOR STRENGTHENING SCHEMERaigarh-Raipur 400 KV D/C-(230km)

M/s B&C and ICOMM

Sch. Comp - July'09

IEER has been finalized by CC ESMD on 15.03.07.

Page 19: ESM Progress Report - 30.08.2012 - Latest Revision

Page 19 of 34

STATUS OF ‘SAMP/RAP' - JULY -2012

State SAMP / RAP Status.

1 2 3 4 5 7 8A)

1 PUNE MIDC land M.S --- No PAP involved. Being government land.42.0

SAMP /RAP

CM, Pune2 PARLI M.S. 35

Section – 4 corrigendum notified on 19.12.06.for actually required area.

Section – 6 notifications issued 17.01.07. Rs 54.06 lacs for balance payment has been deposited for land cost

SAMP /RAP

RA 15.25 lacs Training 2.0 lacs RA Implementation - 2.0 lacs● Management Approval accorded for Implementation of RAP dated 23.03.08

RA payment made to the Land oustees on 12.05.08

NGO (Manavlok) being engaged for RAP implementation works.

Description of Work Status of work

1 10.57 lacs

2 28.07 lacs

3 12.17 lacs

4 11.07 lacs

Total = 61.88 lacs

5 3.00 lacs Payment released on 25.04.11.

Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

WRSS –II (World Bank funding)

Mr. Mohammad Hassan Sr.Social Development Specialist, World bank visited Pune substations on 5th august'2008 for RAP implementation reviewMOU TARGET (06-

07) > Community Development work - Const. of RCC road in adjoining village (Nav Lakh Umbre village) is awarded on 30.10.09. LOA Value - Rs.29,44,408/- > All community developments works completed & being handed over to Village Panchayat.

36.5(Pvt.)

Section-4 Published on 11.10.06. Payment of Rs 38.60 lacs (80% of total amount) has been released to LOA.

LOA for SES & preparation of RAP placed to M/S CMSR Hyderabad on 20.11.06. LOA Cost = Rs. 90,000/-

MOU TARGET (06-07)

·       SES survey conducted during Dec’06.

·       Draft RAP report submitted by consultant on 09.02.07. ·       RAP finalized by CC-ESMD – Feb.08. ·       Community development works approved as below:

Additional RA amount for Rs. 1261667/- approved for PAP's on dated 12.03.09 & distributed in April 09.

Due resistance of villagers, the earlier sanctioned amount of Rs. 25.73 lacs towards Community development works could not be utilized.

Finally Community Development works amounting to Rs 6155202/- was approved on 01.02.11.The finally approved Community Development works are awarded as indicated below.

AGM, Bhadra-wati

Sl. No

Awarded value in Rs.

Extension of Community Hall.

>Awarded vide LOA Dtd. 23.12.11.>Drawings approved in May-12. > Work Completed on 15-08-2012. Scheduled Completion 22-06-12

Modi. & extn. Of school Bldg.

Awarded vide LOA Dtd. 23.12.11.Scheduled Completion: 22.08.12 >Work yet to start. >Approval from CEO, Zilla Parishad Beed received. >Work Of shifting School to alternate location under progress. >Work shall start within a week after completion of shifting work.

Constn. Of RCC Road in Village

>Awarded vide LOA Dtd. 23.12.11. >Work completed on 07-07-2012 >SC-21-06-2012

Constn. Of WBM Rd. along east side s/s Boundry

Awarded vide LOA Dtd. 23.12.11.> Work Completed on 12-08-2012

Financial assistance of Rs3.00 lacs to three Mahila Bachat gut@ Rs1 lacs to each guts.

Claim for additional RA for 90 persons approved in Feb-11 & secrutinised by the committee. The documents of some persons were given to Gram Panchayat for varification.

Page 20: ESM Progress Report - 30.08.2012 - Latest Revision

Page 20 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

3 SOLAPUR (South) 16.11 ha./ M.S 15

39.79acers > Sec. -6 & 17 (urgency clause) published on 27.04.06.

SAMP/RAP

Community development works as mentioned below are completed.

Description of Work Final Cost in Rs.

1

i) Community Hall. 19,76,190.00 1519489.45

ii) Community Toilet. 17,91,126.00 1571268.75

iii) Building for Library. 3,01,942.00 275435.4

Total = 40,69,258.00 3366193.60

2

i) 12,29,889.00 1140627.82

ii) 5,39,155.00 454864.74

iii) 6,18,982.00 530654.02

iv) 10,85,461.00 813875.87

Total = 34,73,487.00 2940022.45

3 2,00,000 Installed at School on 10.12.2008

CMTotal 77,42,745/- Pune

CM, Solapur

>  Section -4 published on 13.04.06.

>  Possession taken on 24.05.06. Forest clearance obtained.

> LOA for SES & preparation of RAP placed to M/S CMSR Hyderabad on 20.11.06. LOA Cost = Rs. 1,05,000/-.> Work completed & SAMP Report finalized vide CC, ESMD dated 02.04.2007.

(MOU TARGET 06-07)

·       RA – Rs. 5.33 lacs + 1.32 for Valnabur group·    Management approval accorded for implementation of RAP by CC dated 19.07.07 .

Management approval for revised cost estimate of RAP for Rs 94.11 lacs has been Approved .

Sl. No

Awarded value in Rs.

Building Package (LOA Dtd. 13.01.09)

Road Package. (LOA Dtd. 27.10.09)

350 x 3.75 mtr wide BT Road connecting Main road to Community Hall with one culvert.

Road Work -200m, connecting Main road to SC &ST Colony road)

Road Works- 180M (BT road in Minority colony with one side Drain).

Road Works- 350M (BT road connecting SC colony to Hanuman Mandir with one side Drain)

05 Nos PC for High School

·  RA disbursement completed in September 2007.

RAP Implementation review

Mr. Mohammad Hasan Sr. Development Specialist, & Mr. Joshi, Environmental Specialist, World bank visited Pune substations on 07.04.08 for RAP implementation review

Page 21: ESM Progress Report - 30.08.2012 - Latest Revision

Page 21 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

B)

4 NAVI MUMBAI 12 M.S. nil No RAP required being Govt. land.

4.85ha.CIDCO land

C) WRSS – X 5 106.83 acre C.G

Govt. Land

Status/ progress of work

1

2 Amount deposited on 02.03.11.

3 Const. of Mangal Bhavan

4 Drilling 3 nos bore wells Work completed by 30.04.11.

5 Const. Bituminous road Work completed by 30.07.20126

WRSS – V KAWAS – II TR. SYSTEM.

CM Navi Mumbai.

In principle approval for commu. dev. works, from CC is accorded on 17.08.10.Work awarded on 13.07.11. LOA Cost 2831542/-.The status of Community Dev. Works are as below:-(i) Extn & renovation of Existing Panchayat office:-The permission to start the work received on 09.02.12. >Column up to plinth beam completed. >Plinth beam concreting 100 percent completed. >Brickwork upto lintel level 70 Percent completed.(ii) for all other works - Constn. of Toilets, Welcome gate & Pick up Shed:- Permission for clearance/ NOC of work from BDO, Panvail & Gram Panchayat, Tembhode & finalization of work location awaited & being followed.

765 kV Pooling Station Bilaspur, CG.

Land, measuring 106.83 acre allotted, on lease basis, by Additional Secretary (Revenue), Govt. of Chhattisgarh, vide letter no. F-04-29/7-1/2009/1152 Dtd. 15.06.09. The Land cost of `. 2,29,23,047/- deposited on 16.07.09. Possession of land is taken on 20.08.09. DGM

S/S,Bilaspur.

'In principle' approval for Community Development work for Rs. 46.31 lacs accorded.Mean while site submitted vide NS Dtd. 25.12.10 the revised proposal of Community Development works amounting to Rs. 67.71 lacs w.r.t earlier approved cost - Rs46.31 lacs by adding some new works as requested by Gram Panchayat, Bherrary Village. 'In principle' approval of revised community development works accorded on 21.03.11 by CC. Status of approved Community Development works in Bheas below:-

Sl. No

Details of Work including estimated / LOA cost at Bharary Village

Const. of community centre

` 1900341/- Work awarded vide LOA Dtd.03.08.11. Roof slab casted at 1st level. PCC for plinth slab completed. For 2nd level Centering completed. Brickwork completed about 90%, Outer Plastering 50% completed.Work is in progress.

Financial Assistance of ` 5 lacs towards const of traffic park at Bilaspur as requested by SP, Bilaspur.

` 6.3 lacs Work awarded on 18.01.12.RCC foundation completed. Plinth beam casted. Balance under Progress.

` 6 lacs

` 5.2 lacsConst. of over Head Tank with water supply distribution system

` 30.62 lacs Work is being taken up with PHE department , Bilaspur as a deposit work. Amount of Rs.30.62 against demand note collected from PHE Depart. Deposited to PHE on 17.08.11. Work tendered in last week of Aug. 2011. The work is being awarded in two parts.a) Cosnstructon of OHT :- But due to high quoted cost it is being retendered..b) Laying of water pipe line :- Work awarded by PHE & agency mobilized & 40% work completed, rest of the work under progress.

Page 22: ESM Progress Report - 30.08.2012 - Latest Revision

Page 22 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

D)

Kolhapur S/S M.S Land identified. Purchase process from collector initiated.

CM, Kol'pur

CM, Kol'pur

E)

7 50 acres M.S 150

South- West Inter Connector Project.

65 acresGov- 60 acresPvt.- 05 acres

>In principal approval towards Community development work ( black topping of existing WBM roads in Village- Kalamba) amounting to Rs 56.6lacs has been accorded. >The work awarded vide LOA Dtd. 15.07.09 & started on 27.07.09 & in progress. >Collection of stone aggregate for WBM road is in progress.>Bituminous Carpeting completed in 6.40 Km out of total -7 Km of road. Balnce 600m Road under progress>Laying of WBM - 75 mm thk completed in 7 Km out of 7.00 Km (revised) road (3m wide) length. >Laying of NP-2 pipe for culvert is progress. All 30 nos culverts are completed. All work completed - 29.06.2012

RAP Implementation review

Mr. Mohammad Hasan Sr. Development Specialist, & Mr. Joshi, Environmental Specialist, World bank visited Pune substations on 08.04.08 for RAP implementation review. All work completed

Krishnapattanam UMPP

765 kV / 400 KV GIS S/S at Pune

> Committee visited the three identified sites on Pune- Nagar road on 11.01.11 & recommendation for village Shikrapur has been sent to CC, Engg for approval.> After completing various formalities/ querries, Initial enquiry under Section-III held on 15.09.11 by Dy. collector, Pune. Some of land owners raised objection for acquisition of their land. According Dy. Collector advised Powergrid to submited revised land area with interested landowners. Same is submitted on 01.10.11 after getting cearance of CC- Engg. >Land acquisition shall be done through tripartite negociation by a committee nominated by Collector, Pune.> Nomination of the committee member from Powergrid side is approned on 07.10.11.> Application of nomination of Committeee for rate negotiation, submitted to collector, Pune on 11.10.11.> Collector, Pune, nominated Dy Collector (SLO), Pune for committee of rate negotiation.>Date of meeting for rate negotiation between land owners & nomimated committee finalized by Collector, Pune on 05.03.12.

CM, T/L Pune

> Meeting chaired by Dy. Collector, Pune, held on 05.03.12. But rate could not be finalized.> Meeting , chaired by Collector, Pune, again held on 27.03.12. Collector, Pune offered some rate to Land oweners for which they asked some time to take their decision.> Mean while Collectror Pune, asked Powergrid to deposit the cost towards land measurement,same has been deposited. Measurement completed on 22.05.2012. Demarkation on field under progress. After demarkation file has been sent to Collector Pune. On the basis of this, collector has prepared the Note and forwaded to Divisional Comm. Pune on 29.06.2012.

SAMP/ RAP implementation Status

> As the land acquisition is being done through consent award, SES is not being carried out.

Page 23: ESM Progress Report - 30.08.2012 - Latest Revision

Page 23 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

8 765 kV S/s at Sholapur 55 acres M.S

F)

9 M.S 63

DGM, A'bad> As the award is a consent award, SES survey is not being carried out.

DGM, A'badG

>18 lac(2/3 part of the total Land cost) deposited to State Govt.Land acquisition is in progress. >Joint measurement of site Completed on 27.02.09.>Section-4 notification issued on 28.04.09. >Section-6 notification issued on 23.07.09.>Award for Land approved by Collector on dated 24.02.2010.>Final award dtd. 23.03.10 issued except for village road of Zola Parishad through the Land. Presently the case is with Rural & Water Resource Ministry at Mumbai.After Conts & handing over of Alternate road, the area of land under existing vollage road ( with in S/S land) will be handed over to Powergrid.> Diversion of area under exisiting village road:- Clearance from Ministry for transfer of land received on 17.11.11.Clearance from Zila Parisad received on 02.01.12 for constuction of Alternate Road. Cost estimate for Rs. 9702247/- for Conts. of alternate road approved on 19.12.11. NIT issued on 17.01.12 & Work awarded on 20.04.2012.>SES completed by M/s CMSR. Final Report submitted by Consultant at site on 01.12.10 & is accepted by Power grid. LOA Cost = 1,80,00/-.> Management approval of rehabilitation plan accorded on 26.07.11.> Disbuersement of RA completed.

Sh. CM, Solapur

Mundra Ultra Mega Power Project

● Pre Investment Approval for Rs 10 Cr. accorded by BOD 206 the MOM dtd 05.03.08.

1200KV Aurangabad S/S

Private land 243.49 acres (98.54Hect.) Govt Land 28.96 acres (11.72 Hect)

> Site for S/S is finalized. Govt. Land:-> Land measurement of Government land - 11.72 Ha. has been done. > Demand note for Rs.1,74,22,500/- for Govt. Land raised by Collector, Aurangabad (on 11.08.10), deposited on 26.08.10.> Possession letter of Govt. Land (11.72 Ha.) has been received from the Collector, Aurangabad on date 05.10.10 & possession taken on 07.10.10.

Private Land:->Rs. 2,05,67,645/- deposited with Revenue Department on 18.12.09 towards 66% of Land cost.> Notification for acquiring land has been published by Collector, under section -4 - urgency clause section-17, on 10.11.10. >Representation was made by land owner for giving prevailing market rate & for arranging a joint meeting with Power grid , headed by Collector, Aurangabad .

> Meeting was held on 01.02.11 at Collector office.> Collector has finalized a rate- ` 15 lacs per acre towards Land Compensation. An additional amount of ` 4.95 lacs per acre to be paid by Power grid as RA Package.> Collector has also informed that the above proceeding will be done in the form of Land Sale proceeding between Power Grid & Land Owner & not as per Land acquisition act in view of the previous land acquisition problems in Aurangabad earlier.> In view of above, the proposal accorded by Competent authority (CMD) on 24.03.11 for with drawl of Land acquisition proceedings & for taking in possessing of above land through execution of registered sale deed with individual land owner as advised by Collector. > Execution of sail deed (total- 79 nos) are started from 05.05.11.78 nos of sale deed has been executed. Balance one is under process.> Refond of Rs. 1,99, 64,685/- received from Collector, aurangabad on 12.08.11.> The Balance sale deed - 01 no. executed on 30.12.11. Now all 79 nos of sale deed executed. & mutation of land in fovour of Power Grid is completed.

SAMP/ RAP implementation Status

Trans. System for Phase -I Generation Projects in Orissa - Part-B

Page 24: ESM Progress Report - 30.08.2012 - Latest Revision

Page 24 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

10 C.G 138765/400 KV Korba Pooling Station

182.41 Acre(11.53 Acre - Govt Land170.88 Acre - Private Land.)

> Application for Land acquisition submitted on 24.07.10 for Private Land & on 07.08.10 for Govt. Land.Private Land Acquisition :-> Demand note for 10% Service Charge/ Processing Fees ( Rs. 42,15,563/-) for Private land received on 02.11.10 & deposited on 08.11.10.>Notification under section -4 for private land published on 26.11.10.> Approval for Section-6 accorded by Collector Korba on 27.12.10.> Notification under Sect.VI has been published on 18.01.11 & subsequently notice for section -9 has also been issued .> Public hearing of Section-9 completed on 16.02.11. Compilation of objections received from PAPs completed. > An amount of Rs. 1,00,00,00/- (Advance) deposited with revenue (Land acquisition) department in March 2011 vide Demand Note No. - 494/SDM/Revenue/Land acquisition 2011/Korba dated 08.03.11 > Notice of compensation of land owners are prepared & put to SDM, Korba.> Proposal of land forwarded to Collector, Korba by SDM, Korba on 28.05.11.> Collector, Korba recommended the proposal to Commissioner,Bilaspur, on 03.06.11.> Commisioner, Bilaspur approved the award of land on 28.06.11.

CM (Bilas-pur)

> An amount of Rs. 5,85,34,051/- (Compn.+S.Charge) deposited with revenue (Land acquisition) department on 15.07.2011 vide demand note Ref. No. 1255 dated 05/07/2011.> Payment Distribution to the land owners is under process. 95% copensation distributed. Balance compensation could be distributed due some internal problems & non availability of concern land owners. Efferts are being made.> However possession of land is handed on 06.09.11.

Page 25: ESM Progress Report - 30.08.2012 - Latest Revision

Page 25 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

I

11 C.G 67

Govt. Land Acquisition :- >Govt Land acquisition case reached to SDM Korba from Tehsil office Bhaisma after calculation of premium for Govt land in all three villages, on 23.11.10.>After scrutiny the case was returned back to Tehsil office, Bhaisma by SDM, Korba for taking NOC from Gram Panchayats (3 nos) & other govt. agencies. NOC from all Grampanchyat & other departments are received .> Land proposal compiled at Tehsil office, Bhaisma & forwarded to SDM, Korba on 28.08.11.> Land proposal forwarded to Add. Collector on 10.09.11 by SDM,Korba.>Add. Collector asked some qurreries from Tehseldar, Bhaisma on 14.10.11 & after attending asame, tproposal forwarded to Commissioner, Bilaspur on 13.11.11.> Commissioner, Bilaspur againg asked some querries like NOC from mining Department, Comments on Suprimcourt dicision on Govt. Land from Add.Collector, Korba on 26.11.11 & same are forwarded to SDM, korba on 03.12.11.> NOC from mining department received on 30.1.12 & comments on Superimcourt decision is under preparation at SDM Korba office.

D.K .JAVERI (CM KORBA)

SAMP/ RAP implementation Status

> Proposal for engaging SES agency approved on 19.01.11. > LOA placed to M/s. Mittsoo Solutions Pvt. Ltd., New Delhi, on 08.06.11. Awarded value Rs.4,60,000/- ( Combined package- 765/400 KV - Korba S/S & Champa S/S).> After incorpation of necessary information, final detailed report forwarded to ESMD, CC on 11.01.2012. > Management approval for RAP report accorded by Compitent authority on 27.03.12.> Approval of disbursement of RA to PAPs is processed on 28.3.12 & approved on 28/03/2012. Disbursement of RA 90% Completed. >R&R Works estimated for 1.80 crore. D.K .JAVER

I ,CM (KORBA)

Trans. System associated with IPP Generation Projects in Chhattisgarh

765/400 KV Raigarh-1 (Tamnar) S/S.

119.28 Acre(1.75 Acre - Govt Land ( out of which 1.491 Revenue forest land) +117.53 Acre - Private Land.)

Govt. Land Acquisition :->Application for Land acquisition submitted on 1st week of Nov. 10..> NOC from Gram Panchayat & other govt. agencies are received by SDM, Gharghoda, on 26.03.11 & under scrutiny at SDM, Gharghoda office.>Some land (0.219 Ha.) identified as forest land. Accordingly case has been registered at DFO Raigarh for diversion of land on 25.04.11 > Proposal of balance land (1.531) submitted to Collector, Raigarh for approval on 23.04.11. > After scrutiny of proposal of balance land (1.531acre) at Collector office, it is found that 1.2acre land is also belongs to Forest. The information forwarded to DFO, Raigarh on 20.05.11. > The proposal for 1.2 acre land is being submitted to CCF, Raigarh for case registration & incorporation with earlier proposal for diversion of land. The total forest land is 1.2+0.291= 1.491acre of out 1.75 acre govt. land. > Letter for NOC for diversion of revenue forest land has been forwarded to SDM Gharghoda office from collectorate office on 29.06.2011 which is being pursuaded.

Sh. P.C . Sastry DGM (Raigarh)/

Sh. P. Biswas,CM, (Raigarh)

> DFO, Raigarh asked RFO, Tamner for field varification of forest land on 20.08.11.Field varication done on 12.10.11 & report submitted on 22.11.11.>NOC from Gram Sabha of associated villages (Barpali & Bhendra) received on 28.12.11 & 3.02.12 respectively & submitted to Collector, Raigarh for issuance of NOC towards revenue forest land. > The above NOC issued by Collector, Raigarh on 02.02.12 & submitted to Forest Departm,ent.> After compilation of documents,the forest proposal submitted to DFO, Raigarh on 17.02.12.> DFO, Raigarh recommended the proposal to CF, Bilaspur on 05.03.12 & same recommended to CCF, Raipur on 19.03.12.

Page 26: ESM Progress Report - 30.08.2012 - Latest Revision

Page 26 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

CM, Raigarh

-do-12 C.G 276

CM, Raigarh

CM, Raigarh

Private Land Acquisition :->Application for Land acquisition submitted on 21.10.09 for Private Land.>Demand note for 10% Service Charge/ Processing Fees ( Rs. 95, 82,424/-) & 80 % compensation amount (Rs. 7,66,62,593/-) for Private land received on 12.10.10 & deposited on 09.11.10.> Gram Sabha held on 24.12.2010 for associated villages -Barpali & Bhendra.> Letter by SDM, after approval of Collector, Raigarh, for publication under Section -IV & XVII issued on 22.01.11.>Notification under Sec. - IV & XVII pulished on 29.01.11 in local news papers & Gazzette notification is published on 25.02.11.

> Proposal for notification of land under Section - VI, approved by Collector, Raigarh on 30.03.11. Notification published in Local news papers on 7 & 8.04.11 & in Gazzette on 06.05.11.> Notices to land owners under section IX issued on 20.05.11 & public hearing completed on 25.05.11. Objections raised by land owners are being replied.> Objection under section -IX resolved. > Award prepared & forwarded to Collector, Raigarh by SDM, Gharghoda on 20.9.11.> Collector Raigarh asked some clarification from SDM, Gharghoda, on 07.10.11 & attended. > Award of land of Bhendra village & Bartali Village issued on 22& 26.11.11 respectively.> Demand note for difference amount ( balance 20% Compensation) for village Bhendra : 72,75,889.00 & for village Barpali : 1,28,59,517.00 deposited at Collectrate Raigarh on dt.09.01.12.> 75 % of Dispersement of Land compensation to Land owners completed & balance is under progress.> Possession of Land of Village Bhendra & Village Bartali given on 27.01.12 & 10.02.12 respectively by Revenue Department

SAM/ PAP implementation Status

>Proposal for engaging SES agency approved on 21.01.11. >LOA placed to M/s SENES, Nioda, UP on 12.05.11. Awarded value- ` 5,59,772/- ( combine package- Raigarh-1, 2 & existing).> final draft report submitted by consultant forwarded to ESMD CC on 31.01.12 for comments.

765/400 KV Raigarh-2 (Kotra) S/S with provision of +/- 600 KV, 4000MW HVDC terminal).

259.18 Acre(73.5 Acre - Govt Land185.68 Acre - Private Land.)

Govt. Land Acquisition:->Application for Land acquisition submitted on 09.09.10. > All NOCs from Grampanchayat & other govt. agencies are collected & proposal forwarded to Collector on 28.02.11 & Same are forwarded to Commissioner Raigarh, by Collector on 28.03.11.> The proposal returned by Commissioner, Raigarh for revision of rates, applicable to new financial year on 07.04.11.> Collector, Raigarh also asked clarification from Revenue Secretary, Raipur on regarding allotment of Govt. land to Power Grid which is reserved for Public use & banned by Superimcourt. Clarification awaited.> Mean while Govt land proposal forwarded to Commissioner office Bilaspur from Collector office Raigarh on 26.07.2011.> Govt land proposal returned from Commissioner office Bilaspur to Collector office Raigarh regarding some queries in NOC on 01.08.2011. > Queries clarified by Collector, Raigarh on 05.08.11 to Commissioner, Bilaspur.> Proposal is forwarded to Revenue Secretary, Raipur on 08.08.11 & is cleared in IDC (Inter Department Committee) on 29.08.11.> Out of 73.92 Acre of Govt. Land, 66.66 Acre Land awarded on 30.9.11 & Demand note of Rs 2,41,83,864 along with yearly lease rent of Rs. 28,88,054/- deposited on 25.11.11. Award of balance land is in process.> Possession of Land taken on 19.01.2012.

Private Land Acquisition :-> Application for Land acquisition submitted on 07.10.09 for 172.37 Acre Land. Supplementary proposal for 20 Acre of Land submitted on 15.12.2010.> Demand note for 10% Service Charge / Processing Fees (Rs.1,23,75,445) & 80 % compensation amount (Rs. 9,90,03,563/-) for Private land received on 30.09.10 & 23.08.10 respectively & deposited on 08.11.10.>Meeting among villagers, District authority & Power grid officials held on 23rd Dec. for rate negotiation & MOM received.>An amount @ Rs.12 Lacs per acre asked by the villagers & recommended by Collector.

Page 27: ESM Progress Report - 30.08.2012 - Latest Revision

Page 27 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

CM, Raigarh

CM, Raigarh13 C.G 100

> Approval for the above agreed rate has been received from CC on 23.1.11 & confirmed to Collector (Raigarh) on 29.01.11.> Notification under Section-IV & XVII for 172.37 Acre Pvt. Land on 31.12.2010 approved on 31.12.10 by Collector Raigarh & same published in local news papers on 10.01.11 and in official gazette on 21.01.11.> Notification & publication of section -6 approved by Collector, Raigarh on 10.03.11 & same published in Local news papers on 15 & 16.03.11 and in Gazette on 01.04.11.> Notices to land owner under section IX issued on 20.04.11 & Public hearing completed by 05.05.11.Objections raised by land owners are resolved.>Award of land under section XI is in process.> Award of Village - Patel pali- Land is awarded& possession is taken on 20.10.11 .> Award of Village - Tarkela- Land awarded on 31.10.11. Balance compensation payment (20%) - Rs. 2,33,68,660/-, is deposited on 17.11.11. Possession of land has been taken on 19.01.12.> Award of Village -Bansiya- Land awarded on 07.11.2011. Balance compensation payment (20%)- Rs1,45,62,200/-, is deposited on 28.11.11. 85 % Compensation has been distributed & balance distrubution will be done after rectification of record. Possession of land has been taken on 19.01.12.

SAMP/ RAP implementation Status

>LOA placed to M/s SENES, Nioda, UP on 12.05.11. Awarded value- ` 5,59,772/- ( combine package- Raigarh-1, 2 & existing).> final draft report submitted by consultant forwarded to ESMD CC on 20.01.12 for comments.> RA payment not required as additional compensation of Rs 12 lacs per acre paid during tripartite negociation. Only Community Development works shall be carried out. > Estimate of Rs. 1.003 crore for community development works approved. For management approval note sent to CC-ESMD on 02.07.2012.

765/400 KV Champa S/S with provision of +/- 800 KV, 6000MW HVDC terminal).

270 Acre (157 .8

Acres- Govt. & 113

Acre- Pvt.)

Government Land Acquisition:->Govt.Land awarded on 30.9.11.Private Land Acquisition:-> Land owners details along with list of affected PAPs are prepared. Proposal of land is prepared & submitted to SDM (Tamgarh) & SMD ( Janjgire) on 24.06.11 & 26.06.11 for approval for publication of Sec-4 & Section -17.> Payment towards Demand note for Rs. 8,44,21,000/- towards 80% Land Compensation & 10% sercive charges, deposited on 11/12.08.11 to State Government.> Section -IV published in official guzzette on 25.08.11. > Two no. of gramshabha involved. Gramshabha of both the villages done & proposal is cleared. > Section VI isuued on 25.11.11 & pulished in local news papers on 27.11.11.> Public hearing under section -IX held on 03 & 06.01.12 for both villages.> Compensation amount of Land owners approved by state govt. are not accepted by them. They are demanding compensation on higher rate/ market rates. > Collector, Janjgir- Champa formed a district level committeee on 16.03.12 inclding Power grid representative for finalisation of rate.> one meeting held on 28.04.12. land owners insisting for job per PAF.Negosation in process.meeting being to be held by colector .

DGM (Bilas-pur)- SS

SAMP/ RAP implementation Status

> Proposal for engaging SES agency approved on 19.01.11. >LOA placed to M/s. Mittsoo Solutions Pvt. Ltd., New Delhi, on 08.06.11. Awarded value Rs.4,60,000/- ( Combined package- 765/400 KV - Korba S/S & Champa S/S).> Cosultant visited the site on 10.11.11 for collection of data from PAPs & under process. 75 % data collection is completed.

DGM (Bilas-pur)- SS

Page 28: ESM Progress Report - 30.08.2012 - Latest Revision

Page 28 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

14 C.G 22

15 C.G 150

16 49 Acre M.S

Extension of existing 400/220 KV S/S Raigarh.

8.87 Acre( Private Land.)

Private Land Acquisition :-> Application for Land acquisition submitted on 18.11.09 for Private Land.> Demand note for 10% Service Charge/ Processing Fees ( Rs. 3,90,009/-) & 80 % compensation amount (Rs.39,00,093/-) for Private land received on 05/07/10 & deposited on 22.10.10. > Letter by SDM, after approval of Collector, Raigarh, for publication under Section -IV & XVII issued on 22.01.11.>Notification under Sec. - IV & XVII polished on 29.01.11 in local news papers & Gazette notification published on 18.02.11.> Notification under Sec.- VI published in lacs news papers on 24 & 25.03.11 and in Gazette on 01.04.11.> Notices to land owner under section IX issued on 20.04.11 & Public hearing completed by 04.05.11. Objections raised by land owners are resolved.> Award of Land prepared & forwarded to Collector, Raigarh on 02.02.12 for approval . > Award of Land of Kotra & Jampali Village approved on 15.02.12 & 13.03.2012.> Demand note for balance cost of Rs. 14,75,000 towards Village Kotra deposited on 16.03.12 & that for Village Jampali fo Rs. 28,88,054/- collected on 20.03.12. Award approved and demand issued on dt .30.04.2012.

Sh. Mayank Singh CM,

RaigarhSAMP/ RAP implementation Status

>Proposal for engaging SES agency approved on 21.01.11. >LOA placed to M/s SENES, Nioda, UP on 12.05.11. Awarded value- ` 5,59,772/- ( combine package- Raigarh-1, 2 & existing).> final draft report submitted by consultant forwarded to ESMD CC on 20.01.12 for comments.

Sh. P.C. Sastry,DGM

(Raigarh )/ Sh. Mayank

Singh, CM, (Raigarh)

765/400 KV Raipur (Durg) S/S

140.47 Acre(4.42 Acre - Govt Land136.05 Acre - Private Land.)

Govt. Land Acquisition :- > Application submitted to Collector Durg on 27.01.11.> Measurement of land has benn done by Tehsildar. > Recommendation for allotment of land is under process at Collector, Durg.> Tehseldar, Dhamdha has asked on 30.05.11 for submission of NOC from various government agencies like PWD, Forest, Mining, Education, Health, PHE etc. as per new guidelines befor allotment of land.> Proposal of land allotment forwarded to Collector Durg on 25.07.11by SDM, Dhamdha.> Collector, Durg asked some clarification from SDM, Dhamdha, on 15.09.11 & clarification forwarded to Collector, Durg on 16.10.11. > The proposal is approved on 05.11.11.> Order for allotment of land issued on 20.11.11. > Demand note for land cost - Rs. 47,52,898/- collected on 03.12.11 & Payment deposited on 19.12.11 with State Government. > Land handed over to Powergrid.Private Land Acquisition :-> Total amount deposited towards land cost & compensation is Rs 13,92,27,542/-> Order for possession of land has also been issued on 23.06.11. > Land handed over to Power Grid on 25.06.11.

DGM (Durg)

SAMP/ RAP implementation Status

> SES work awarded to M/s SENES, Nioda, UP on 06.09.11. > Detailed draft report for review, submitted by consultant on 29.12.11. After secrutiny the report is forwarded to CC, ESDD, on 24.02.12 for further comments & approval.> Management approval for RAP report accorded by Compitent authority on 27.03.12.> Approval of disbursement of RA to PAPs is approved on 28.03.2012.Disbursement of RA 90% completed.

DGM (Durg)

765/400 KV Padge Substation.

>3no Site identified. > Above identified sites are not found suitable & new site is being searched.> Four nos. new sites are again identified. Nominated Committee visited the site on 22.09.11. > The proposal of site selection for site selection is approved on 12.10.11. & Site at Village-Karanjoti , Taluka- Bhiwandi, Dist-Thane is identified.> Appilication submitted to Collector, Thane on 10.10.11 for procurement of land on urgent basis.> Oder issued on 16.11.11 by collector, Thane for Committee formation for rate negotiation.> During meeting, held on 08.12.1, between land owners & committee members for rate negotiation, landowners strongly protested against purchase of land.> Due to protest of land owners, Collector, Thane advised to identify new land.> New land identified & proposal submitted to Collector, Thane on 24.01.12.> Meeting taken by SDO, Bhivandee on 23.02.12 with Land owners in presence of nominated committee. Land owners accrded their consent.> Meeting called by Collector, Thane on 27.03.12 for rate negotiation with land owners. Collector announced final rate of Rs. 35 Lacs per Acre. However Land owners insisted for rate of Rs. 40 Lacs per Acre.> Further negation being taken up by Collector, Thane.

AGM, Boisar

Page 29: ESM Progress Report - 30.08.2012 - Latest Revision

Page 29 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

17 MS

18 MS

765 /400 KV Dhule Substation

132 Acre (Pvt. Land)

Not finaliz-

ed

> 3no Site identified. >Committee visit done on 3.01.11. >Recommendation approved on 18.02.11.> Investment approval is awaited.> Land acquisition process is yet to be taken up.

DGM, Auranga-bad

Expansion of 765 KV Hyderabad & Jabalpur Bays at Wardha 765/ 400/ 220 KV S/S.

40.1 Acre (Pvt. Land)

12 (PPF)

> Application for land acquisition submitted on 22.06.11 to Collector, Wardha & came forwarded to Land acquisition Officer for further action.> Land measurement done on 03.09.11 & being submitted to Land acquisition Officer.> A committee of six members, head by Collector Wardha, members - Land acquision officer, Town planner & Powergrid representatives-3 nos, nominated on 28.07.11 for negotiation of rate per Hac. from land owners for consent award.> One meeting held on 01.10.11 in which land owners demanded Rs. 25 Lacs per Hac. & not agreed by the committee & asked the land owner to rethink.> During HOD meeting on 14.10.11, it is decided to acquire the land under land acquisition act.> An application to this effect, is given to Collector, Wardha, on 19.10.11 to issue section IV & VI. > Accordingly Powergrid representative met Collector, Wardha on 30.11.11. Collector Wardha advised that Land acquirement through land acquisition will be time taking & it will be better to follow the procedure as per GR Dtd. 04.08.10 i.e by Consent award.

Sh. Patanjali SharmaCM, Wardha S/S

> A meeting of Nominated committee members with land owners for rate finalization, held on 19.12.11 & rates were negotiated.> MOM of negotiated rates were signed by Powergrid representative on 12.01.12 & submitted to other members of Committee for signature.> Above MOM finally signed by all other members by 31.03.12 & submitted to Collector, Wardha on 02.04.12 for onward submission to Commissioner, Nagpur. Matter is under followup.

SAMP/ RAP implementation Status

> As the land acquisition is being done through consent award, SES is not being carried out.

ESM, RHQ, NGP

Page 30: ESM Progress Report - 30.08.2012 - Latest Revision

Page 30 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

COMPLETED PROJECTS

A)

1 BOISAR MS NIL Possession of land taken over on 01.04.03. AGM

No RAP required being Govt. land. Boisar

B) SIPAT- I TR SYSTEM

AGM, Seoni.

1 SEONI

MP 58 Land acquired in Dec. 2004. RA = Rs 1745961/-

RAP- Development Works

Description of Work Status of work

1

2 753044/-

C) SIPAT-II TR.SYSTEM

2 BHATAPARA 30.38 C.G 212.82 (Govt.)

27.56 (Pvt)

Management approval - 18.05.07. RA – Rs.5,73,928/-

Rs.7,09,737/-

Payments disbursed – March, 2008.

Community Development works :-Description of work Actual cost in Rs.

1 1119350

2 Construction of Bus shelter 99991

Total = 1219341Date of completion of work = 25.06.09

TARAPUR 3 & 4 TR. SYSTEM

47 (Govt. Land)

135.38(131.33 Pvt.+ 4.05 Govt.)

SES done by M/s Xavier institute of Development Action & Studies, Jabalpur, M.P. LOA Cost = Rs. 1,90,000/-.

Sl. No

Awarded value in Rs.

Construction of Lavatories in Village Lugharwara & Simaria. (20 nos)

Development of one no. tube well at Village Simaria & Lugharwara.

394381/-

131404

10 Nos. Lavatory at Simriya village & 5 nos. at Lugharwara village has been completed & handed over to concerned Gram Panchayat.Retendering of work of supply & installation of one hand pump at Lugharwara near Laboratory site & Simaria, are process. Tender opened on 03.12.10 and under finalization. Due to high quoted rate of L1, the tender has been canceled on 18.06.11 Now the possibility for takling up above work through PHE department, Seoni, as deposit work is being explored.

Construction of WBM Road in Village Lugharwara & Simaria (600 mtr).

400 mtrs WBM road of Lugharwara village & 230 mtrs WBM road of Simaria village are completed & handed over to Gram Panchayat.

SAMP /RAP REPORT

SES - M/s Center for Management & Social Research Hyderabad. RAP report finalized. Ref: CC: ESMD: WR: 07 dt.24.01.07. LOA Cost- Rs. 95,000/-

Addle RA –Rs. 1,35,809/-(vulner’ble )

Sr No

Repairing of existing connecting road to village & betterment of main road.

Mgr. BHATA-

PARA

Page 31: ESM Progress Report - 30.08.2012 - Latest Revision

Page 31 of 34

State SAMP / RAP Status.Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

D)

3 RAIGARH 39.61 (Pvt) --do-- 225SAMP/ RAP' REPORT

Description of work Actual Cost in Rs.

01. Bus shed 10649502. 290132

03. Playground development 31384 CM, Raigarh

Total = 428011

E) SIPAT-II SUPPLEMENTARY SYSTEM

4 WARDHA 85.00 M.S. 22 Possession of land taken on 23.08.06 from MIDC. (34.414ha)Govt.Land

SAMP REPORT

MOU TARGET(05-06) RA – Rs 3.62lacsVocational training– Rs 1.00 lacs Implementation of RAP Rs. 0.50lacs Contingent Rs. 1.00 lacs RA disbursement completed in September, 2007.

Vocational Training given to PAPs at Krishi Kendra, Wardha.

(Sudarshan Telang)

Mgr. (Engg- ESM)

VINDHYACHAL –III TR. SYS.

SES-M/s Utkal University Bhuvaneshwar RAP report finalized on 31.03.06.by CC ESMD.(MOU Target 05-06). LOA Cost - Rs. 1,91,000/-.

·       Management approval accorded for RAP on 18.07.07.·       R. A. amount- 19.52lacs·   The following Community development works were approved & completed on 31.10.06.

Sr. N0

Infrastructure development of school-

·       RA Disbursement completed September, 2007.

· SES-M/s CMSR Hyderabad & Draft report submitted by consultant, in Dec’04. LOA Cost - Rs. 1,05,000/-

·  SAMP report finalized and submitted to World Bank in Dec’04.

RAP Implementation review

Mr. Mohammad Hassan Sr.Social Development Specialist, World bank visited Wardha on 04.08.08 for RAP implementation review

Mr. Mohammad Hassan Sr. Development Specialist, & Mr. Joshi, Environmental Specialist, World bank visited Wardha on 09.04.09 for RAP implementation review. S. Patanjali

Sharma ,CM, (Wardha)

Page 32: ESM Progress Report - 30.08.2012 - Latest Revision

STATUS OF ‘SAMP/RAP' - JULY -2012

State SAMP / RAP Status.

1 2 3 4 5 7 8A)

2 PARLI M.S. 35

Section – 4 corrigendum notified on 19.12.06.for actually required area.

Section – 6 notifications issued 17.01.07. Rs 54.06 lacs for balance payment has been deposited for land cost

SAMP /RAP

RA 15.25 lacs Training 2.0 lacs RA Implementation - 2.0 lacs

RA payment made to the Land oustees on 12.05.08NGO (Manavlok) being engaged for RAP implementation works.

Description of Work Status of work

1 10.57 lacs

2 28.07 lacs

Sl. No.

Name of the Sub station

Land in Acres

Nos of PAPs

Respty. Center

WRSS –II (World Bank funding)

36.5(Pvt.)

Section-4 Published on 11.10.06. Payment of Rs 38.60 lacs (80% of total amount) has been released to LOA.

LOA for SES & preparation of RAP placed to M/S CMSR Hyderabad on 20.11.06. LOA Cost = Rs. 90,000/-

MOU TARGET (06-07)

·       SES survey conducted during Dec’06.·       Draft RAP report submitted by consultant on 09.02.07. ·       RAP finalized by CC-ESMD – Feb.08. ·       Community development works approved as below:

● Management Approval accorded for Implementation of RAP dated 23.03.08

Additional RA amount for Rs. 1261667/- approved for PAP's on dated 12.03.09 & distributed in April 09.Due resistance of villagers, the earlier sanctioned amount of Rs. 25.73 lacs towards Community development works could not be utilized.Finally Community Development works amounting to Rs 6155202/- was approved on 01.02.11.

AGM, Bhadra-wati

Sl. No

Awarded value in Rs.

Extension of Community Hall.

>Awarded vide LOA Dtd. 23.12.11.>Drawings approved in May-12. > Work Completed on 15-08-2012. Scheduled Completion 22-06-12

Modi. & extn. Of school Bldg.

Awarded vide LOA Dtd. 23.12.11.Scheduled Completion: 22.08.12 >Work yet to start. >Approval from CEO, Zilla Parishad Beed received. >Work Of shifting School to alternate location under progress >Work shall start within a week after completion of shifting work.

Page 33: ESM Progress Report - 30.08.2012 - Latest Revision

3 12.17 lacs

4 11.07 lacs

Total = 61.88 lacs5 3.00 lacs

B)

4 NAVI MUMBAI 12 M.S. nil No RAP required being Govt. land.4.85ha.

CIDCO land

C) WRSS – X 5 106.83 acre C.G

Govt. Land

Status/ progress of work

1

2

AGM, Bhadra-wati

Constn. Of RCC Road in Village

>Awarded vide LOA Dtd. 23.12.11. >Work completed on 07-07-2012 >SC-21-06-2012

Constn. Of WBM Rd. along east side s/s Boundry

Awarded vide LOA Dtd. 23.12.11.> Work Completed on 12-08-2012

Financial assistance of Rs3.00 lacs to three Mahila Bachat gut@ Rs1 lacs to each guts.

Payment released on 25.04.11.

Claim for additional RA for 90 persons approved in Feb-11 & secrutinised by the committee. The documents of some persons were WRSS – V KAWAS

– II TR. SYSTEM.

CM Navi Mumbai.

In principle approval for commu. dev. works, from CC is accorded on 17.08.10.Work awarded on 13.07.11. LOA Cost 2831542/-.The status of Community Dev. Works are as below:-(i) Extn & renovation of Existing Panchayat office:-The permission to start the work received on 09.02.12. >Column up to plinth beam completed. >Plinth beam concreting 100 percent completed. >Brickwork upto lintel level 70 Percent completed.(ii) for all other works - Constn. of Toilets, Welcome gate & Pick up Shed:- Permission for clearance/ NOC of work from BDO, Panvail & Gram Panchayat, Tembhode & finalization of work location awaited & being followed.

765 kV Pooling Station Bilaspur, CG.

Land, measuring 106.83 acre allotted, on lease basis, by Additional Secretary (Revenue), Govt. of Chhattisgarh, vide letter no. F-04-29/7-1/2009/1152 Dtd. 15.06.09. The Land cost of `. 2,29,23,047/- deposited on

DGM S/S,Bilaspur.

'In principle' approval for Community Development work for Rs. 46.31 lacs accorded.Sl. No

Details of Work including estimated / LOA cost at Bharary Village

Const. of community centre

` 1900341/- Work awarded vide LOA Dtd.03.08.11. Roof slab casted at 1st level. PCC for plinth slab completed. For 2nd level Centering completed. Brickwork completed about 70%.Work is in progress.

Financial Assistance of ` 5 lacs towards const of traffic park at Bilaspur as requested by SP, Bilaspur.

Amount deposited on 02.03.11.

Page 34: ESM Progress Report - 30.08.2012 - Latest Revision

3 Const. of Mangal Bhavan

4 Drilling 3 nos bore wells

5 Const. Bituminous road Work yet to be started

6

(Sudarshan Telang) Mgr. (Engg- ESM)

DGM S/S,Bilaspur.

` 6.3 lacs Work awarded on 18.01.12.RCC foundation completed Balance under progress.

` 6 lacs Work completed by 30.04.11.

` 5.2 lacs

Const. of over Head Tank with water supply distribution system

` 30.62 lacs Work is being taken up with PHE department , Bilaspur as a deposit work. Amount of Rs.30.62 against demand note collected from PHE Depart. Deposited to PHE on 17.08.11. Work tendered in last week of Aug. 2011. The work is being awarded in two parts.a) Cosnstructon of OHT :- But due to high quoted cost it is being retendered..b) Laying of water pipe line :- Work awarded by PHE & agency mobilized & work under progress.