MIMS ESPACIO
Events, Daily Works, and Projects
INDEPENDENCE DAYOn August 15th, Mims Espacio celebrated Independence day with it’s fellow residents. Flag hoisting was followed with musical recitals all as well as instrument playing by the children of the complex.
BOREWELL PUMPThe borewell pump fix suffered an electrical line cut which was fixed easily. A suggested recommendation is to maintain a back up pump in cases where extended maintenance will be required.
DIESEL GENERATOR DOORThe DG Door hinge was fixed.
STP PUMPThe submersible STP pump burnt out and a new one was installed.
DG ANNUAL MAINTENANCE CONTRACTA new AMC was signed at a lower rate for the DG.
Newsle t t e r
August 15, 2012
DG Door Hinge Borewell pump fix
MIMS ESPACIO NEWSLETTER! PAGE2
FIRE EXTINGUISHERSTwo additional Fire extinguishers have been added to the facility. Two more are being considered
FINGER PRINT ATTENDANCE SYSTEMA attendance system using fingerprint authentication for permanent staff is being added to the guard room, gratis, and is undergoing testing.
NEW STAFF RESTROOM FACILITIESA restroom was built for Espacio staff to the right of the drive way entrance. All visiting and permanent staff are expected to use the new facility.
LANDSCAPINGOld vegetation was removed and new plants have been added. Please welcome the new Ficus and Cypress trees to the complex.
SECURITY CAMERASSecurity video monitor is being moved from the Gym to the guard house to facilitate better threat awareness.
PARTY HALL, LOUNGE, AND GYM REMODELING
The club facilities at Espacio are all being remodeled. Resident and owner forbearance is highly appreciated during the remodeling.
WATER PROOFINGParty hall, Party hall terrace and verandah were waterproofed.
GARAGE SAFETY FEATURESAddi t iona l sa f e ty f ea ture s in the underground parking facilities are being researched and quotes have been requested from various vendors.
ESPACIO VOLUNTEERSAs owners and residents please feel free to contribute in any way towards the improvement of the community space.
ACCOUNTSSome rough accounts have been included at the end of this newsletter for the readers perusal.
New staff restroom New Submersible STP Pump
New Landscaping
Club Facilities Remodeling
MIMS ESPACIO NEWSLETTER! PAGE3
AccountsLabour Borewell repair-Imtiaz 2000
Labour charges-Debris 3000
Labour charges-Satish-Servant Toilet 6000
Labour charges-Servant Toilet 4000
Labour Charges-Tea 500
Labour Charges-weekly payment 14800
Labour Charges-Welding-Servant Toilet
1000
Labour Charges(Basha) 1000
Labour Charges(Carpentry work) 500
Labour Charges(Debris) 10000
Labour charges(Gym room breakage) 4000
Labour Charges(Imtiaz) 10000
Labour charges(Night work) 800
Labour Charges(Plumbing work) 3600
Labour Charges(Skylight) 5000
Labour charges(Weekly Payment) 30150
Labour Total 96350
MIMS ESPACIO NEWSLETTER! PAGE4
AccountsRaw Material
Cement Sand Bricks Purchases 1650
Cement bags 10720
Sand Purchase 17000
White Cement 7303
Cement Sand Total
36673
Electrical Fitting CCTV Adopter 600
CFL Bulbs 3373
Earthing cable at gym 22000
Emergency Lights 780
Electrical Fitting Total
26753
Flooring Advance-tiles 1000
Chemicals for marble 2745
H.V.Stone 15000
Marble laying 30000
Marble Purchases 195000
Tiles 6440
Flooring Total 250185
Plants Plants purchase 52900
Plants Total 52900
Plumbing Plumbing Items 7931
Plumbing Total 7931
Water Proofing Karnataka Engg 25000
Water Proofing 12000
Water Proofing Total
37000
Wood Purchase of Wood 7500
Wood Total 7500
Raw Material Total
418942