ESTATE OFFICE
STANDARD OF PROCEDURE
& GUIDELINES
ESTATE OFFICE
UNIVERSITI BRUNEI DARUSSALAM
Contents:1. Estate’s Mission, Vision and Objectives
2. Organisation Structure
3. Assigned Positions
4. Scope of Works
5. New Developmental Projects
Scope of Works
Guideline for National Development Projects
6. Work Flow Process for Quotation / Tender Projects
7. Guidelines for Payment Process - CAGE
8. Guidelines for Building Standards – Piawai Brunei Darussalam (PB12) Building Guidelines and
Requirements
9. Maintenance Works – Term Contracts / Facilities Management Estate’s Helpdesk System
• Work Flow Process for Term Contract
• Time Frame Work Flow Process
• Sample of Work Request / Work Done by relevant Contractors to be submitted to Estate Office
• Sample of Work Order issued by Estate Office
10. Facilities Management Services
• Scope of Work
• Work Process
11. Audio Visual
12. Labour Services
13. Logistic Services
14. Administration – Filing system
MISSION, VISION AND OBJECTIVES
Building and Engineering division who are responsible of streamlining and
monitoring of the maintenance and development of all
Universiti Brunei Darussalam’s building infrastructure.
The office of Estate intends to provide a service professionally with efficient, quality and costeffective.
To be a recognised office with outstanding achievement levels in managing UBD buildinginfrastructure physical development, Facilities Management and Maintenance system adapting toISO standard and to convert conventional to sustainable buildings.
MISSION:
VISION:
MISSION, VISION AND OBJECTIVES
OBJECTIVES:
• To achieve the best quality with continous improvement efforts which are needed to be emphasized on innovation, quality and the process to meet the goals of the organisation.
• To take action within 24 hours of complaints lodged by end-users with the facilities of Term Contract / Facilities Management.
• To conduct Preventive Maintenance on assigned schedules.
• To ensure that all development projects are to be implemented on schedule, within resources and goals that had been set.
MISSION, VISION AND OBJECTIVES
OBJECTIVES:
• To ensure maintenance works of the buildings, infrastructure, Mechanical and Electricial areplanned, managed and monitored accordingly as well as systematically.
• To ensure all assets are maintained and recorded accordingly as well as systematically.
• To ensure all basic maintenance of building facilties are done promptly and adopting the costeffective way.
• To ensure all upgrading works are executed accordingly with proper application via WE Helpdesk
system and to manage works efficiently as well as works executed are within the job specifications using open quotation / tender.
Housekeeping
Painting Services
Roofing
SCOPE OF WORK
BUILDING MAINTENANCE AND SERVICES SIGNS AND GRAPHICS
ELECTRICAL AND MECHANICAL SERVICES
Repairs
Interior Design
Renovation and Remodeling
Road Maintenance
Plumbing Services
Sewerage
Labels
Banners
Billboards
Nameplates
Notice Boards
Building Signages
Display Boards
Air Conditioning Maintenance and Services
Elevator Maintenance & Services
Lighting Maintenance & Services
Electrical Work
Mechanical Repairs
Telecommunication
Fire System
CCTV
Access Barriers
AUDIO VISUAL SPACE MANAGEMENTPLANNING AND DEVELOPMENT
Provide AV Facilities to new and existing infrastructure
Loan for Staff & Students
Provide AV Logistic Events
AV Maintenance
Room Allocation
Furniture Supply & Management
Renovation & Space Changes
Campus Planning
Supervision of New Building Projects
Energy Management and Conservation
SCOPE OF WORK
LANDCARE
Landscaping Services
Grass Cutting
Pest Control Services
Forest Rehabilitation
Accessibility
Indoor Plant Supply andNursery Management
OTHER SERVICES
Estate Outreach
Transportation
Event Logistics
Supply of Laborers
Basic Waste Management
Procurement
Management of Sports Complex
SCOPE OF WORK
ORGANISATION STRUCTURE
`
Act. Executive Engineer
Hasnan bin Hj Sawal
Senior Technical
Assistant
Norasmelee bin Yusof
ZONE 1
Building Maintenance
and Services
(Cleaning & Pest
Control)
Technical Assistant /
Supervisor
Mohd Aliff Hj Yussof
Lim Ming Siong
Sulaiman bin Ibrahim
Sports Complex
Supervisor
Hamidun bin Haji
Abdul Hamid
Senior Technical
Assistant
Ahmad bin Hj Tuah
ZONE 2
Building Maintenance
and Services (Cleaning
& Pest Control)
Technical Assistant /
Supervisor
Hj Mohd Zul-Afti bin
Hj Ibrahim
Rozaiman bin Hj Abd
Karim
Muhammad bin Hj
Tamin
ZONE 1
(M&E / Vehicle
maintenance team)
Nursery Labours
Rosni bte Ismail
Dk Maslia bte Pg
Md Yassin
Faatin Nadia
Abdullah
Clerk (Secretarial /
Financial
Rakinah bte Ghani
Saiful Nizam bin Jalil
Musri bin Hj Masri
Supervisor
(Landscape and
Nursery Labours)
Ampuan Roslan bin
Ampuan Daud
ZONE 2
(M&E / AV /
Telephone team)
Senior Technical
Assistant
Yuspdillah bin
Lipang
Senior Technical
Assistant
Lim Chee Siong
Superintendent (M&E / Vehicle Maintenance team)
Act. Head of Estate
Sr. Hjh Wan Farhani Hj Suhaili
Assistant Registrar (Administration and Finance Team)
Ahmad Raimie bin Haji Mohammad Engineer (Building team)
Technical Assistant
/ Supervisor
Mohd Fadhillah bin Mohd Azri
Juhan bin Hj Ahmad (Supervisor)
Hj Abd Mutalib bin Hj Metusin
Chief Technical Assistant
Vehicle
Maintenance
Receptionist
Hjh Zonainah bte Hj
Ahim
Chief Technical Assistant
Technical Assistant
/ Supervisor
Azrinnah bte Hj
Moksin
Naim bin Idris
Abu Bakar bin
Minggo
Supervisor
Mohd Shahrin Hj Awg Damit
Clerk Vehicle
Main
Drivers
Hashim bin Hj
Jamil
Hj Aminuddin bin
H Hj Abd Karim
Binchin bin
Tingang
Estate Helpdesk
System
Dk Wirni Suarni bte
Pg Metussin
Safety System
Building
Infrasatuture
Supervisor
Mohammad Fadhlullah bin Ramli
NEW DEVELOPMENTAL PROJECT
Scope of Work:
• To implement Master Plan planning for projects under the National Development Plan,
Maintenance Asset and UBD Tabung.
• Construction of new or extension buildings shall be executed by implementing using
Contract Procurement by engaging consultants, In-House or Design and Build from pre-
contract until post contract; including preparing and processing the Progress Payment
until Retention as well as monitoring all on-going projects.
• Preparation of Preliminary estimation cost, project brief, Write-up and tender
documents.
NEW DEVELOPMENTAL PROJECT
Guidelines for National Development Projects
Budget available through warrant.
Project Champion : MOD:
• Request for site from TCP
• Site allocation approve
• Land to be gazette to UBD by Land Department
• Project Write-up according to scope of work to request budget from JPKE (parallel process while waiting land to be gazette)
• Approve budget from JKPE
• Request for Topo from Survey Department with budget info from JPKE
• Survey Department appoint consultant to do topo graphical survey
• Claim for topo (Invoice)
• Request Warrant to use budget to pay topo
• Approval from JPKE
• PO
• PV
Guidelines for National Development Projects
Project Initiated by JKR
– DOD
• Appointment of Consultant (M&E, QS, C&S, and Architect)by MOD
• MOA with appointed consultant
• Consultant to produce design and work program based on client brief.
• Design Presentation (max 3 months)
• Approved Design by MOE
• Tendering process by DOD
• Evaluation Process by DOD – with client knowledge
• Approval by LTK/LTN according to project value
• LOA by DOD to approved contractor
• Bankers and Insurance by Contractor
• Possession of Site
• Project Implementation
• Payment done by DOD
– Progress payment (monthly)
» EOT (if any)
» VO (if any)
– Penultimate payment
– Retention Money (7.5% of contract sum for project above 150K and 5% of contract sum below 150K)
• Payment done by DOD
– Progress payment (monthly)
» EOT (if any)
» VO (if any)
– Penultimate payment
– Retention Money (7.5% of contract sum for project above 150K and 5% of contract sum below 150K)
• Loose Furniture requirement and specification by client request
• Tendering by MOE
• Evaluation by MOE/Client
• Award to successful Vendor by MOE LTK (itemized/ package)
• Furniture supplied and received
• Invoice by Vendor receive
• Application of Warrant to JPKE by MOE
• Approval of Warrant
Guidelines for National Development Projects
• Loose Furniture requirement and specification by client request
• Tendering by UBD
• Evaluation by UBD
• Award to successful Vendor by MOE LTK (itemized/ package)
• Furniture supplied and received
• Invoice by Vendor receive
• Application of Warrant to JPKE by MOE
• Approval of Warrant
– DBS & DTS
• JKR team to produce design and work program based on client brief.
• Design Presentation (max 3 months)
• Approved Design by UBD
• Tendering process by DOD
• Evaluation Process by DOD – with client knowledge
• Approval by LTK/LTN according to project value
• LOA by DOD to approved contractor
• Bankers and Insurance by Contractor
• Possession of Site
• Project Implementation
Guidelines for National Development Projects
UBD – in house – Design and Build
• Prepare Tender Document
• Prepare Tender Notice for advert – open tender – LTK
• Tendering process by UBD and LTK, MOE
• Evaluation Process by MOE to LTN through LTK
• Approval by LTN
• LOA by UBD to approved contractor
• Bankers and Insurance by Contractor
• Signing Contract
• Design Presentation
• Approve design by UBD
• Seek approval from other relevant government authorities
• Proceed Working Drawing
• Possession of Site
• Project Implementation
• Invoice Receive
Guidelines for National Development Projects
• Payment done by UBD
– Request Warrant for payment based on Claim / S-Curve
– Progress payment (monthly) through PO and PV
» EOT (if any)
» VO (if any)
– Penultimate payment through PO and PV
– Retention Money (7.5% of contract sum for project above 50K and 5% of
contract sum below 50K)
Guidelines for National Development Projects
WORK FLOW PROCESS FOR
QUOTATION / TENDER
PROJECT
no
< $50,000.00 In-House 1 Month
> $50,001.00 LTN / LTK
Approval
Issue Cert. of Site Possession
Work in Progress /
Progress Payments
yes yes
Warning Notice
Changes no no
no
Warning Notice yes no
no yes
yes no
yes
no
yes
Penultimate Payment no
yes
Acceptance no
no
yes
Site Poss. issued within 1 day
Issue Cert. Progress Payment after Contract
Signing for Tender project
Assessment min.of 2 weeks
P.O issued within 1 day
LOA issued within 2 days
Issue Cert. of Practical Completion within 1
day
Preparation Tender not exceeding 1 Month /
Quotation not exceeding 2 weeks
Project
Estimate Within
Budget
Advertisement
Assessment &
Recommendation
Isuue P.O
Fund
Request
Tender Document
Bill Of Quantities
Issue LOAContract Starts
Work Commences
Apply VO Changes Delay
Non Compliance Rectification Works
Acceptance
Warning for
Apply EOT
Practical Completion Inspection
Notice to MC
Non Completion Acceptance
Non
Compliance
Termination
Non Compliance
Defect Liability Period Starts
Money
Retention
Money
Retention
Release
Final Notice of Defects
Making Good Defects
Final Inspection
yes
Issue Cert. of Non Completion within 1 day
Application of EOT /V.O min. of 2 weeks for
approval
Penultimate P. to be processed not
exceeding 3 months
Quotation: 6 months DLP
Tender: 9 months DLP
Terminate Contract
LAD
Imposed
Acceptance
Contract Ends
Defect Liability Period Ends
GUIDELINES FOR PAYMENT PROCESS
All payment invoices to be processed must be attached with relevant documents accordingly as below:
A. Progress Payments:
• Progress Payment Certificate
• Progress photograph
• Letter of Award
• *Work Order for Facility Management / Term Contracts
( Every progress payments must be deducted of 10% of progress work submitted for both quotation
or tender projects)
B. Penultimate Payment:
• Penultimate Payment Certificate
• Progress Photograph
• Laporan Kerja Siap
• Certificate of Practical Completion
• Certificate of Site Possession
• Letter of Award
• *Work Order for Facility Management / Term Contracts
( Every progress payments must be deducted of 10% of progress work submitted for
both quotation or tender projects).
• * Final Variation Order (if applicable)
• *Extension of Time (if applicable)
C. Retention Payment
• Retention Payment Certificate
• Letter of Award
• *Final Defects Certificate
• *Work Order for Facility Management / Term Contracts
• * Final Variation Order (if applicable)
• *Extension of Time (if applicable)
GUIDELINES FOR PAYMENT PROCESS
GUIDELINES FOR BUILDING STANDARDS –
All building standards are referred from PIAWAI BRUNEI DARUSSALAM
(PB12) BUILDING GUIDELINES AND REQUIREMENTS
• To convert Conventional to Sustainable buildings in UBD by implementing Carbon free as well as Energy Efficient materials for renovation and new construction works.
• Estate Office have initiated reduction of Energy Consumption since September 2016 by switching off Air-Conditioning system (AHU) from 5:00pm until 6:00am and will be switched
off every Friday and Sunday except certain buildings that require constant cooling for eg, Laboratories.
• All Air-Conditioning’s temperature have been set to 23 degree.
GUIDELINES FOR BUILDING & CIVIL AND MECHNICAL AND ELECTRICAL
MAINTENANCE WORKS:
Term Contracts / Facilities Management
ESTATE OFFICE HELPDESK SYSTEM
Estate Helpdesk
Track
Simplify
Interact
Retrieve
ESTATE OFFICE’S HELPDESK SYSTEM
ESTATE HELPDESK SYSTEM
• This system allows UBD students and staff to drop any complaints or requests on any estate related matters.
• It simplifies the way complaints or requests which can be tracked, interacted and retrieved complaint easily via a single thread (ticket).
• Estate Office will be able to track, monitor, record any activities within the system and will be integrated with the Work Request / Work Order that will be issued for Term Contact works.
• The system is divided into sections for end-user wish to choose their complaints/requests such as Building & Civil, Mechanical & Electrical, Labor, Cleaning services, Pest control, Transportation, Landscaping & Grass cutting and Logistics.
• Upon submitting complaints / requests, Ticket Tracking ID will be automatically sent to end- users email to track, interact and retrieve.
• Estate Helpdesk’s focal person will reply end-users as soon as possible within 24 to 48hrs and if expected ticket may take additional time, helpdesk system will update by sending end-user a notification email.
• Duration period from ticket submitted to payment processed will be 10 working days.
1. Complaints / Request by Enduser
2. Estate Helpdesk
3. Forwarded to relevant Estate Team
4. Forwarded to relavant Contractor
5. Contractor to inspect & issue Work Request
6. Approved WR – Issue Work Order
7. Work completed and contractor to submit WO to Estate
8. Estate to inspect and verify WO
9. Contractor submit invoice
10. Estate to process Progress Payment
1 Day
1 Day
1 Day
1-3 Days
2 Days
3 Days
1 Day
TIME FRAME WORK FLOW
PROCESS
Resolved works
informed by Estate team to
Helpdesk FP
FACILITIES MANAGEMENT SERVICES
Facilities Management Services
Facilities Management (FM) is an “integrated approach to operating, maintaining, improving
and adapting the buildings and infrastructure of an organization in order to create an environment that strongly supports the primary objectives of that organization”. (Barret and Baldry (20
03) in Facilities Management – Towards Best Practice).
The Contractor is to manage the scope of works and services under the UBD FM Contract. Thescope ranges from supply of resources to the overall management of the entire scope of workin any instances the Contractor must ensure that HSE, Quality, Planning, Logistics, Documentat
ion and records and all aspects of Commercial service are managed professionally in accordance with the Client’s needs.
Scope of Work
General building and civil engineering maintenance works including alterations and additions to existing buildings.
Minor new works of building and civil engineering nature.
Maintenance, repairs, alterations and minor new additions to electrical and mechanicalsystem installations.
Maintenance, repairs, alterations and minor new additions to air-conditioning and ventilation system installations and refrigeration equipment.
Maintenance, repairs, alterations and minor new additions to fire alarm, fire protection and suppression system installations;
Maintenance, repairs and minor new additions to lift installations;
Scope of Work
Maintenance, repair and minor new additions to Security and access control system installation
Maintenance of Vehicles
Civil engineering works including general repairs, maintenance and ad-hoc alterations
associated with roads, car parks, storm water drains, foul drains, service tunnel, etc.
Waste management works.
Pest control works.
Landscaping and Grass cutting works.
Cleaning and housekeeping works.
Minor structural repair works.
Waterproofing works
FM Work Process
UBD Estate / End User
Helpdesk
FM / QS Consultant approval
UBD Estate approval
AUDIO VISUAL
WORK
PROCESS
FOR AUDIO
VISUAL
EQUIPMENT
LOANING
Process 1:
Timeline: 5 working days + days depending on the duration of loaning the equipment.
Timeline: 5 working days + days depending on the duration of loaning the equipment.
Note:
• The loaning period is depending on the type of equipment being loaned.• A demo will be shown by the technical staff on using the equipment upon
collection of equipment.• As part of the loaning term, client’s UBD card will be hold by Estate office upon
collection of equipment and will be returned back to the client once the equipment is return back to Estate Office.
• Client will be fully responsible for the equipment once collected from Estate Office.
Thus, late charges and penalty cost will be charged to the client if the equipment is return later than the actual date or if the equipment is damage or loss during the loaning period.
• Penalty cost will also be charged to client if he/she does not show up to collect the requested items.
• Any further enquiries, client can always interact through our Estate Helpdesk System or drop off to Estate Office.
WORK
PROCESS
FOR AUDIO
VISUAL
EQUIPMENT
LOANING
Process 1:
WORK
PROCESS
FOR AUDIO
VISUAL
SERVICES
FROM
ESTATE
OFFICE
Process 2:
Timeline: 7 days (excluding the number of days of the event)
LABOUR SERVICES
Timeline: 8 days (excluding number of days of the event)
WORK
PROCESS
FOR
LABOUR
SERVICES
LOGISTIC SERVICES
Timeline: 11 – 17 days (Excluding number of days of the event)
WORK
PROCESS
FOR
LOGISTIC
SERVICES
ESTATE OFFICE
UNIVERSITI BRUNEI DARUSSALAM
WORKPLACE INSPECTION REPORT
Inspected by:
Team:
Zone:
Date:
Department/
Faculty
Room
No.
Scope of Complaint
Designated
Contractor for
Corrective
Action
Status
Date
Inspected by (Signature): Approved by (Head of Zone):
---------------------------------------- _________________________________
Note:
1. Report MUST be submitted to respective Head of Zone (STA) for approval
MAXIMUM OF TWO (2) DAYS from the inspection day.
2. Once approved by Head of Zone, report will be submitted to Helpdesk and
for contractor to take action accordingly.
HOE/WFS’ April 2019
Work place Inspection Report
• All Estate’s staff must use the Workplace Inspection Report during any inspection.
• Report must be submitted to respective Head of Zone (STA) for approval.
• Maximum of TWO (2) days from inspection day.
• Once approved by Head of Zone, report will be submitted to Estate Helpdesk and for respective Term contractor to take action (issue Work Request) Estate staff to prepare Bill of Quantities and issue Quotation/Tender.
ADMINISTRATION:
Filing System
Document recieved
• receiver to stamp received date
Send to Head of Estate
• for review and signature
• to be copied after signature
Filing (original)
• file based on quotation number/project file/title of project
RKN
(Rack 3)
Log In / Log Out system
Focal person:
Nizam
Term Contracts
(Rack 4)
Log In / Log Out system
Focal person:
Rakinah
Project File
Personnel
(Rack 1 & 2)
Log In / Log Out system
Focal person:
Rakinah
WORK FLOW PROCESS
FOR
QUOTATION / TENDER
PROJECT