estates division flying start - estates induction

31
Estates Division Flying Start - Estates Induction

Upload: eugene-goodwin

Post on 21-Jan-2016

242 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Estates Division Flying Start - Estates Induction

Estates Division

Flying Start - Estates Induction

Page 2: Estates Division Flying Start - Estates Induction

ESTATES DIVISION FORUM

Agenda 

1. The Estate 2. Estates Division

3. Estates Current Major Project

4. Estates Future Projects

5. Questions

Page 3: Estates Division Flying Start - Estates Induction

1. The Estate - Aldwych Campus

1 Kingsway

30 Campus Buildings

12 Halls of Residence

2 Pubs

17 acres of sports ground

Page 4: Estates Division Flying Start - Estates Induction

1. The Estate - Halls of Residences

BA - Bankside

CS - Carr Saunder

GH - Grosvenor House

HH - High Holborn

NH – Northumberland Av

RA - Rosebery

PA - Passfield

BW - Butlers Wharf

Page 5: Estates Division Flying Start - Estates Induction

1. Estate – Sports Ground

7 LSE Mens Football Teams1 LSE Womens Football Team3 LSE Mens Rugby Teams2 LSE Womens Rugby Teams7 LSE Womens Netball Teams2 LSE Cricket Teams

Windsor Avenue, New Malden, Surrey, KT3 5HB

Train Station: Berrylands

Page 6: Estates Division Flying Start - Estates Induction

2. Estates Division

PROPERTIES - ACQUISITION / 

DISPOSALS

SPACE PLANNING

CAP DEVCAPEX WORK/LTM

FM / MAINTENANCE

Page 7: Estates Division Flying Start - Estates Induction

2. Estates Division -  Management Structure

Page 8: Estates Division Flying Start - Estates Induction

2. Estate Division – Properties

• Acquire, Dispose Manage all aspects of the LSE Property Portfolio 

• Provide valuation and investment advice for all Schools purposes

• Strategic Planning• Landlord and Tenant Relationship building• Deliver a platform for School’s Performance• Enable the Schools Student experience

Page 9: Estates Division Flying Start - Estates Induction

2. Estate Division – Space Planning

• Manage the allocation and space planning of the Estate in line with the School's priorities and Strategic Vision

• Develop space norms• Office and Learning Space Planning• Relocations & Move Management• Strategic Planning

Page 10: Estates Division Flying Start - Estates Induction

2. Estates Division – Space Planning [Major]LRB - 5th Floor – Relocation of HR and Finance

• HR move from Sardinia House

• Finance re-located from Aldwych House

• Refurbishment of the 5th floor LRB

Timetable:• Strip out Aug 14• Refurb Sept – Dec 14 • Move Dec/Jan 15

Page 11: Estates Division Flying Start - Estates Induction

2. Estates Division – Space Planning [ Major]Sardinia House -  Phases 3 & 4

Proposed 6th floor layout 

• Phase 3: Refurbishment of 5th & 6th floors and half of 4th floor to accommodate decant of the Economic History dept from East Building  

• Lift replacement works being carried out at the same time • Construction: August to December and occupation in March 2015 

• Phase 4: Adapt part of 1st, 2nd and 3rd floors [ex HR space] to accommodate decant of the International History dept from East Building  

• Construction: Jan – Mar 15 and occupation in March 2015 

Page 12: Estates Division Flying Start - Estates Induction

2. Estates Division – Space Planning [Minor]Tower 3 – Levels 3 & 4 – ERD - Office Refurbishment

Programme August – December 2014Work Minor office refurbishment to rationalise 

floor layout and workstation positions on Level 4.Level 3 refurbishment followed byoccupation by Conferences and Events team.

Page 13: Estates Division Flying Start - Estates Induction

2. Estate Division – Capital Development

• Estates Strategy – Major/ Minor Developments• New Work Requests – Works requested & paid for by 

Departments (or internal funds)• Minor Works – Minor Alterations• Long Term Maintenance [LTM] – Building Elements that 

have reach end of life e.g. roofs, lifts• Planned/Recurrent Works– Flooring and Decoration• Compliance Works – Asbestos, Fire Risk Assessments, 

Legionella Remedials, Fixed Wire Testing Remedials

Page 14: Estates Division Flying Start - Estates Induction

2. Estates Division – CapEx Projects – Aldwych Campus

SU Shop SU Building  -SAW Parish Hall

Page 15: Estates Division Flying Start - Estates Induction

NAB20 Kingsway

2. Estates - CapEx Projects – Aldwych Campus [Contd]

The Women’s Library

Page 16: Estates Division Flying Start - Estates Induction

Towers

2. Estates - CapEx Projects – Aldwych Campus [Contd]

32 LIF

Lifts, Toilets

Page 17: Estates Division Flying Start - Estates Induction

2. Estates Division – CapEx Projects – Halls of ResidencesHigh Holborn – Student Rooms Butlers Wharf  -

Student Rooms & Communal Space

Passfield – External Renovation

Page 18: Estates Division Flying Start - Estates Induction

Replace gas boiler

Replace lift controls

BMS upgrades

Replace distribution boards

Refurbish WC facilities to stair B and at CON

Replace boilers Replace AC Condensers

Replaced Garrick AHU package unit

BMS upgrade in basement

Install Salto locks

Repair windows ventilation actuators

Install zip heaters under wash hand basins

Replace all carpet on GF

New fire alarm system on LG & GFs

Sump pump repair

Replacement of roof plant.

Boiler conversion to gas

Structural survey of internal ceilings

Remedial upgrades following refurbishment

Replace UPS batteries

Basement water penetration remedials

Repairs to terraced seating panels

Install Salto LocksReplace distribution boards

Install Salto Locks

Replace boilerReconfigure WCs

Replace boiler

LSE Campus

 KEY 

Main Campus

LSE Owned Buildings

Centre BuildingsRedevelopment

Leased Buildings

Works level of disruption

Disruptive

Unsightly

Minimum

Disruption

2. Estates Division - Annual LTM Works

Page 19: Estates Division Flying Start - Estates Induction

2. Estates Division – Carbon Management Programme - RE:FIT

• BOUYGUES was appointed to develop and implement energy saving measures to 11 buildings. 

• Works planned to start in August 2014 to finished in March 2015

      Key figures:• Total project cost: 

£1,987,372• Projected energy 

savings:  3,095,308 kWh per annum, i.e. 11% reduction against AY 2011-12

• Projected financial benefits: £255,890 per annum

• Simple payback: 7 years

Page 20: Estates Division Flying Start - Estates Induction

2. Estate Division – FM Services

• Maintenance: reactive and planned maintenance      of current facilities• Cleaning: daily cleaning and bin collection• Ancillary FM Services: blinds/windows/pest control• Sustainability: carbon reduction/waste management• Security: crime reporting, access, emergencies• Post Room: delivery of internal/external mail• Portering: removal/relocation of heavy items & 

confidential waste

Page 21: Estates Division Flying Start - Estates Induction

WORKING TOGETHER TO MAKE THE CAMPUS A BETTER PLACEIf you need a repair or notice a fault with our facilities, e.g. lights not working, dripping taps, leaks, blocked toilets/sinks, , trip hazards, broken locks, lift out of service, unsafe practice etc.:

PLEASE CONTACT ESTATES HELP DESK OR REPORT IT TO ANY MEMBER OF THE ESTATES STAFF

Estates Help Desk - Mon-Fri 8.30am-4.30pm ☎ emergency: ext. 2444, communal phones dial #6244; DD: 020 7831 8713 ☎ general enquiries: ext. 7956 or ext.6415✉: email: [email protected]; Estates web Service Request Formwww.lse.ac.uk/EstatesDivision/HelpdeskAndServices/HelpdeskSecurity: ☎ Out of hours: ext. 2000

Where possible we will assist you, if we cannot – we will tell you why. All jobs are prioritised based on merit and subject to emergencies, workload & staff availability.

2. Estate Division – FM Services - Help Desk

Page 22: Estates Division Flying Start - Estates Induction

Buildings being demolished:

• East Building

• The Anchorage

• Clare Market

• St Clements: core & eastern wing

Buildings being demolished are coloured purple

3. Estate Division – Current Major Project  Centre Building Redevelopment [CBR]

Page 23: Estates Division Flying Start - Estates Induction

New public square at the heart of the LSE

3. Estate Division – Current Major Project  Centre Building Redevelopment [CBR]

Page 24: Estates Division Flying Start - Estates Induction

Creating a new LSE landmark building & public square Improving facilities for staff and students

3. Estate Division – Current Major Project  Centre Building Redevelopment [CBR]

Page 25: Estates Division Flying Start - Estates Induction

CBR will be a 13-storey tower with an adjoining 6-storey block facing Houghton Street and a new public square leading to the Library

3. Estate Division – Current Major Project  Centre Building Redevelopment [CBR]

Page 26: Estates Division Flying Start - Estates Induction

3. Estate Division – Current Major Project  Centre Building Redevelopment [CBR]

Page 27: Estates Division Flying Start - Estates Induction

Construction traffic route is via Clare Market. The blue is traffic into the site; green shows traffic exiting the site. No vehicles will reverse.

3. Estate Division – Current Major Project  Centre Building Redevelopment [CBR]

Page 28: Estates Division Flying Start - Estates Induction

Access via Grange Court and the Towers steps may be restricted for short periods while STC is demolished but will be reopened as soon as practicable and safe. 

3. Estate Division – Current Major Project  Centre Building Redevelopment [CBR]

Page 29: Estates Division Flying Start - Estates Induction

4. Estate Division – Future Major Project  44 Lincoln’s Inn Fields [44LIF]

Page 30: Estates Division Flying Start - Estates Induction

4. Estate Division – Future Major Project  44 Lincoln’s Inn Fields [44LIF]

Page 31: Estates Division Flying Start - Estates Induction

ESTATES DIVISION

 

Questions?