estimating activity time & cost
TRANSCRIPT
© 2012 Dr. Kenneth F. Smith, PMP
ESTIMATING ACTIVITY
TIME & COST
1 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
AFTER IDENTIFYING ACTIVITIES
& SEQUENCING THEM
ACCURATELY ESTIMATING ACTIVITY DURATIONS
& TIMING
IS THE NEXT IMPORTANT ASPECT OF
PROJECT SCHEDULING
2 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
“I hate to criticize, but you’ve only been employed here
for two days and you’re already three weeks behind in
your work.”
3 Critical Path Method
© 2014 Dr. Kenneth F. Smith, PMP 4 Project Management
Fundamentals
RISK ANALYSIS
Phase II
1. Activity Time Estimating
2. Decision Tree Analysis of
5 major risks
with focus on Probability & Impact on
Overall Project
Schedule & Budget
© 2012 Dr. Kenneth F. Smith, PMP
ESTIMATING ACTIVITY DURATIONS
• TIME is fundamental to all Projects
• Most Project Managers focus on managing
TIME
• Most Project Management Software focuses on
TIME
• Control of time is often used to control costs
5 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 6 Critical Path Method
Key Concepts
“Touch-time” = The amount of direct on-the-job
working time needed to perform an Activity
“Waiting (Idling) time” = Time when an Activity is on-
going (i.e. started, but not yet finished) but with nothing
happening
“Elapsed time” = Touch time plus Waiting time
“Opportunity time” = Waiting time when – if given the
resources – productive work could be done on the
activity, or another task, or activity on another project.)
© 2012 Dr. Kenneth F. Smith, PMP 7 Project Management Fundamentals
In many project working environments –
particularly matrix organizations where
equipment and personnel resources are
shared, outsourced and/or team members
are often concurrently assigned to
support multiple projects that are
otherwise beyond the control of
individual project managers –
Touch time for an activity may be as little as
10% of Elapsed time!
© 2012 Dr. Kenneth F. Smith, PMP 8 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 9 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 10 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 11 Critical Path Method
Thus, in most Program and Project situations massive amounts of
Opportunity time exist
Since the Project Schedule (time plan)
defines the Project Budget (money over time)
Effective time management is critical
© 2012 Dr. Kenneth F. Smith, PMP
Estimating Project Duration & Costs is not
Easy
Estimating as Accurately as possible is
important, but
• Time/Cost/Quality affect each other
• Estimating Methods affect accuracy
• How much detail do you need?
– Top Down
– Bottom up
• In the Real World, Estimates and Actuals are
usually different
12 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Types of Estimate
• Concept oriented (Rough order of magnitude)
– High level definition
– Requirements not fully defined
– Accuracy of -25% to +75%
– Informal techniques used
• Function oriented (budgetary estimate)
– Requirements are well defined
– Accuracy of -10% to +25%
• Implementation oriented (definitive estimate)
– Accuracy of -5% to +10%
13 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Estimation Methods and
Techniques
• Analogous (i.e. based on similar
projects, or processes; usually Top
Down)
• Parametric Modeling (i.e. “Rule
of Thumb” formulas or ratios)
• Detailed (Bottom up)
14 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Analogous by components; based on
familiarity with similar projects
Computer
Project
100 %
30 % 10 % 60 %
5 % 10 % 10 % 5 %
System Testing Computer
Software
Computer
Hardware
Hardware
Design
Built
Hardware
Testing
Facility
Hardware
Testing
Software
Design
Software
Codes
10 %
Tests Design
Usually by allocating available
time durations, or percentages
to each level
15 Critical Path Method
50 weeks
15 weeks 30 weeks 5 weeks
5 weeks 10 weeks 15 weeks
2.5 weeks 2.5 weeks 5 weeks 5 weeks
20 % 30 %
© 2012 Dr. Kenneth F. Smith, PMP
Parametric Modeling
Parametric modeling uses key project characteristics (parameters) in a mathematical model to predict project costs.
Examples:
In software development, the number of lines of code to predict cost.
In construction, use the per- square meter of living space to estimate cost.
16 Critical Path Method
Furthermore, “contractors estimate the cost of corruption in the construction process at P125 per square meter.
It’s worse in mining, where one Tsinoy has been overheard grumbling that he is being asked to fork out P200 million for a permit.”
[Reported by Ana Marie Pamintuan in her Opinion column: Sketches “Business
Costs” The Philippine Star, 1 July 2013.]
© 2012 Dr. Kenneth F. Smith, PMP 17
Critical Path Method
“Pork Barrel”
Priority Development Assistance Fund (PDAF)
Under the PDAF System in the Philippines:
Each Congressional Representative gets 70 million pesos
(approximately US$1.75 million ) 30 million pesos per annum for “Soft” Projects – i.e.
Education, Health & Social Services – and another 40 million pesos for “Hard” – i.e. infrastructure Projects.
Each Senator gets 200 million pesos (approximately US$5 million )
100 million pesos per annum for “Soft” Projects, and another
100 million pesos for “Hard” Projects.
“The scuttlebutt is that the commission received by erring legislators ranges
from 20% to 30% for Hard projects . . . and 60% to 70% for Soft projects – as
evidenced by the ghost foundations that are the target of the current expose.”
Dean Andy Bautista My Four Centavos
The Philippine Star, Saturday August 10, 2013, Opinion page 12
© 2012 Dr. Kenneth F. Smith, PMP
Detailed (Bottom Up) Items &/or
Components
Overseas trip
preparation
$1,000
Accommodation
& Transportation
Personal
Belongings
Travel
Documents
Passport Visas Clothing Other Items
Plane ticket Hotel Car Rental
&/or Taxis
$1,000 $750
$2,750
$1,000 $750
$1,750 $500
$150 $350
$5,000
Add Up Estimated
item Costs at
each level
18 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
How to Prepare a Project Schedule
– Identify Activities & Milestones (WBS)
– Prepare Network diagram (CPM)
– Estimate the level-of-effort (staff-hours) to
complete the activities
– Translate effort into duration (working time)
– Convert working time to calendar time
– Identify “Critical Path” & Slack/Float
– Assign staff to work on activities
19 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Estimating Activity Times,
& Ultimately Project Duration
IMPLEMENTATION PLANNING
& SCHEDULING
20 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Time estimates are typically Over-optimistic for one or
more principal reasons:
CLIENT DRIVEN The Client establishes the project
completion deadline before technical analysis,
consultation or project management feedback
CONTRACTOR RESPONSE In order to be “Fully
Responsive” Contractors (Project Managers) accept
the Client’s deadline to hopefully win the contract
Project Activity Duration Estimating
& Scheduling
21 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
After technical analysis Contractors either
• Arbitrarily “Cut and Paste” activity time estimates
to fit the Client’s pre-determined schedule.
• Use a standard ‘Beta Distribution’ “PERT 3 time” or
a “Triangular Distribution” 3 time estimating
method to compute an “Earliest Expected Time”
but in either case, tend to favor the “Optimistic
Time” over the computed Earliest Expected Time, or
the Most Likely Time estimate in “Cutting and
Pasting” their final schedule proposal.
However, IMPLEMENTATION experience is that even
the computed Earliest Expected Time, and the “Most
Likely Times” are over-optimistic & unrealistic!
Project Activity Duration Estimating
22 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Who Provides the Best Estimates?
• Those Accountable
for the work (i.e. First
Line Supervisors)
• Those who know the
work (Senior
Technical Specialists)
• Those who Actually
do the work
(Journeymen)
23 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 24 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 25 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 26 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 27 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Who IMPOSES the WORST TIME
Estimates on Project Managers and
First Line Supervisors?
• HIGH LEVEL EXECUTIVES!!
– MARKETING DEPARTMENT PERSONNEL
• COMPANY CONTRACT NEGOTIATING
DEPARTMENT
CUSTOMERS!
Moreover, usually, none of the above have
any detailed knowledge or experience as
to what is involved or how long it actually
takes to do the work!
28 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 29 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 30 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 31 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
The Dilbert cartoon illustrates the problem faced by
project estimators, as well as some of the terms
commonly used in planning:
• Optimistic
• Most Likely
• Pessimistic,
• Earliest Expected, &
• Realistic
Times
32 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
RISK QUANTIFICATION
Determining
Risk Events &
Risk Tolerance
33 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Triangular Distribution Technique
A 3-time probability-based
time estimating technique
sometimes used to estimate
activity durations when there
is uncertainty about their
time durations
te
= O + M + P
3
i.e. a Simple Average
or “Mean”
of the range of
possibilities
34 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Triangular Distribution
Activity Duration Estimate
Optimistic + Most Likely + Pessimistic
3
Example:
Optimistic time is 10 weeks
Pessimistic time is 35 weeks
Most likely time is 15 weeks
10+ 15 + 35 = 60
3 3
te = 20 weeks Earliest Expected Time
With a 50% probability of being accurate.
35 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Program Evaluation & Review Technique
(PERT)
te
= O + 4M + P
6
i.e. a Weighted Average
or “Weighted Mean”
of the range of
possibilities
36 Critical Path Method
A 3-time probability-based
time estimating technique
more often used to estimate
activity durations when
there is uncertainty about
their time durations
“Beta Distribution”
© 2012 Dr. Kenneth F. Smith, PMP
PERT Method – Activity Duration
Estimate
Optimistic + (4 x Most Likely) + Pessimistic
6
Example:
Optimistic time is 10 weeks
Pessimistic time is 35 weeks
Most likely time is 15 weeks
10+(4x15)+35 = 10+60+35 = 105
6 6 6
te = 17.5 weeks, or 18 weeks (rounded up)
Earliest Expected Time
37 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
The “Triangular Distribution” Formula:
A Fundamental Flaw.
The Triangular Distribution formula to estimate Activity duration – i.e. the “Earliest Expected”
time -- is a simple average, so the same weight is given to the two extremes (i.e. best and worst cases) as the “most likely” estimate.
However, since the Optimistic and Pessimistic estimates are extremes -- by definition -- they are less likely to occur. Hence the formula and its resultant Earliest Expected Time at 50% probability computation is unrealistic!
38 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
The “PERT” Formula (Beta Distribution)
A Fundamental Flaw, & Caution
The PERT formula to estimate Activity duration – i.e. the “Earliest Expected” time -- is a weighted average that attempts to rectify the
undue bias in the Triangular Distribution.
Nevertheless, the probability of completing the Activity by the “Earliest Expected” time is still only 50%
In other words, at the outset, the Activity duration is under-estimated half of the time, so there is an equal likelihood the Earliest Expected time computed will not be met, but will be overrun.
39 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Russian Roulette “RR”
Therefore, Project Managers
who use the Standard PERT
3-Time formula to estimate
project Activity timing run a
high risk of Failure . . .
Even Worse than Playing
RUSSIAN ROULETTE !!!
40 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Russian Roulette “RR”
What is the Probability of Surviving “RR” with One Round in a Six Cylinder Chamber Revolver?
• Point the Gun at Your Head
• Spin the Chamber
• Pull the Trigger
• Probability of being killed is
1 / 6 = 17 %
Thus Probability of Surviving = 100% - Probability of Dying = 83%
41 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Russian Roulette “RR”
And the Probability
of Surviving with:
Three Rounds in
the Chamber
= 3 / 6 = 50 %
This is the same probability as
the PERT “3 time” weighted-
average estimating formula!!!
42 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Would You play Russian
Roulette with One bullet?
NO? Then why expect Project Managers
to Estimate & Schedule
Project Activities with the “PERT 3 Time Formula”
Which is the equivalent of
Russian Roulette with Three bullets?
43 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
PERT Formula — A Work-Around Solution
Ken Smith’s “Realistic Time” Strategy
1. Use the PERT beta distribution 3 time formula during the planning stage as the first step in estimating individual activity durations
2. Then add two standard deviations to the activity duration
This will adjust the likelihood of completing the activity by its scheduled time to 95%
44 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
NORMAL CURVE, RANGE, STANDARD DEVIATION,
and RELATED PROBABILITIES
X -1 SD +1 SD
-2SD +2SD
-3SD +3SD
68.26%
95.44%
99.74%
50%
-3 -2 -1 +1 +2 +3
0.13% 2.15% 13.54% 34.13% 34.13% 13.5% 2.15% 0.13%
MEAN
0 % 100% 95%
45 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
The MEAN & the Standard Deviation
• A Mean (Average) is a measure of “Central
Tendency” – i.e. the midpoint of a range of
values
• A Standard Deviation is a measure of Dispersal
from the Mean within that range – essentially the
Opposite of a Mean
• Each Standard Deviation from the mean
represents a fixed percentage
• The Probability of any value occurring in that
range is the size of its standard deviation from
the mean
46 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Dr. Ken’s prescription for
improving activity duration estimating
ter = opt + 4 ML + pess + 2 Std. Devs
6
Realistic Activity Time
Take 1 PERT
+ 2 ESD’s
47 Critical Path Method
NOTE: Very Practical, but
Not in PMBOK or PMP Exam
© 2012 Dr. Kenneth F. Smith, PMP
Basic PERT/CPM Formula
Earliest Expected Time = opt + 4 ML + pess
6
Activity Estimated =
Standard Deviation
pess - opt
6
48 Critical Path Method
Two Estimated =
Standard Deviations
pess - opt
3
© 2012 Dr. Kenneth F. Smith, PMP
Ken’s “Realistic Time” Method:
Optimistic + (4 x Most Likely) + Pessimistic + 2 SDs
6
Example:
Optimistic time is 10 weeks
Pessimistic time is 35 weeks
Most likely time is 15 weeks
10+(4x15)+35 = 10+60+35 = 105 = 17.5 weeks
6 6 6
1 SD = (35 – 10)/6 = 25/6 = 4.16 & 2 SDs = 8.33
So Realistic Time = 25.83, or 26 weeks (rounded up)
For a 95% probability of Success in attainment.
49 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP 50 Critical Path Method
ESTIMATING ACTIVITY DURATIONS FOR SCHEDULING UNDER CONDITIONS OF UNCERTAINTY
© 2014 Dr. Kenneth F. Smith, PMP [email protected]
NOTE: The Probability of SURVIVING Russian
Roulette is 83% !
Enter Your
DESIRED
Probability
% BELOW
PERT FORMULA
Ursula Kuehn's* Worksheet to Estimate
"P" in PERT Pessimistic Time Formula
PERT
FORMULA
Dr. Ken's
REALISTIC
FORMULA
( 0 + 4 ML + P )
/ 6 "What Could Go Wrong?"
Ac
tivity # Enter O, ML & P
Time Data in
cells Below
*Integrated Cost & Schedule
Control in Project
Management. 2nd Edition.
Management Concepts
Identify Top Three Risks
P =
MURPHY's
Law:
What if
ALL
THREE
Risks
Occur!
50%
PROBA-
BILITY
95.44%
PROBA-
BILITY
99.90
OPTIMIS
TIC
TIME
MOST
LIKELY
TIME Risk 1 Risk 2 Risk 3
EXPECTED
TIME
DURATION
REALISTIC
TIME Your Time
1 4 7 9 11 13 17 8.17 12.50 15.36
2 1 10 25 11.00 19.00 24.28
3 2 4 6 4.00 5.33 6.00
4 1 2 7 2.67 4.67 5.99
5 1 2 3 2.00 2.67 3.00
© 2012 Dr. Kenneth F. Smith, PMP 51 Critical Path Method
REALISTIC TIME COMPUTATION © 2012 Dr. Kenneth F. Smith, PMP
PERT FORMULA for Estimating
Activity Duration
Dr. Ken's
REALISTIC
FORMULA
Ursula Kuehn's* Worksheet for
Estimating Pessimistic Time
( 0 + 4 ML + P ) / 6
"What Could Go Wrong?"
Ac
tivi
ty
#
Enter O, ML & P Time
Data in cells Below
50%
PROBABIL
ITY
95%
PROBABILI
TY
*Integrated Cost & Schedule Control
in Project Management. 2nd Edition.
Management Concepts
OPTIMI
STIC
TIME
MOST
LIKELY
TIME
PESSIMI
STIC
TIME
EXPECTED
TIME
REALISTIC
TIME
1 2 3
MURPHY
:
Everythi
ng
1 3 7 20 8.50 14.17 15 17 14 20
2 1 10 25 11.00 19.00
3 2 4 6 4.00 5.33
4 1 2 7 2.67 4.67
© 2012 Dr. Kenneth F. Smith, PMP
REMEDY
CONTRACTOR RESPONSE: Contractors (Project Managers)
• Conduct the Technical Analysis using the supplement to the PERT 3-time estimating approach that improves the probability of developing a more realistic time estimate
• Provide feedback to the Client ASAP -- Brief the Client to demonstrate why their deadline is unrealistic, and appeal for duration extension, or reduction in Scope of Work before submitting a bid
• If Client insists on the Original Project Completion Deadline &/or Scope, either
• Get a change order ASAP if you are the successful bidder
• Don’t Bid and consider yourself lucky you won’t have to deal with the time, cost & quality problems that will inevitably arise!
Project Activity Duration Estimating
& Scheduling
52 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
The “Critical Chain” Method (CCM)
CCM is another approach to deal with uncertainty by adding non-work time duration “Buffer” activities at various points in the Critical Path Network; and particularly just before a series of activities joins the Critical Path.
Buffer Activities on the Critical Path are
called “Project Buffers”
Buffer Activities that are not on the
Critical Path are called “Feeder Buffers”
53 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
REMEDY
CONTRACTOR RESPONSE: Contractors (Project Managers)
• Conduct the Technical Analysis using the supplement to the PERT 3-time estimating approach that improves the probability of developing a more realistic time estimate
• Provide feedback to the Client ASAP -- Brief the Client to demonstrate why their deadline is unrealistic, and appeal for duration extension, or reduction in Scope of Work before submitting a bid
• If Client insists on the Original Project Completion Deadline &/or Scope, either
• Get a change order ASAP if you are the successful bidder
• Don’t Bid and consider yourself lucky you won’t have to deal with the time, cost & quality problems that will inevitably arise!
Project Activity Duration Estimating
& Scheduling
54 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
A NOTE ON PROBABILITY
• A Risk Event could still occur Despite a Low Probability
and
• A Risk Event might not occur Despite a
High Probability
There are No Guarantees !!!
55 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Team Exercise - Estimating
• Upgrade your CRITICAL PATH NETWORK based on the WBS plus any new information & feedback
• Estimate [“Best Guess!”] Time Durations for each Activity and Task in the WBS independently,
• USE a STANDARD DURATION TIME UNIT THROUGHOUT
• Do not attempt to Schedule the overall Project WBS]
56 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Team Exercise - Estimating
• Add Time Estimates to your Activities
• Schedule your Critical Path Network
• Prepare it for Presentation
57 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Team Exercise - Estimating
• Upgrade your WBS based on new information & feedback
• Estimate [“Best Guess!”] Resource Requirements and Costs for each Component, Activity and Task in your WBS
• Estimate [“Best Guess!”] Time Durations for each Activity and Task in the WBS independently, using the PERT formula. [NOTE: Do not attempt to Schedule the overall Project WBS]
• Prepare a Resource Register with the Estimated
Costs and Estimated Duration for each item in the
WBS
58 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Calendar Time
Elapsed time
– Accounts for all time, not
just time spent on the
project
Working time
– Time spent working on
the project; Synonymous
with productive time
59 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Usefulness of CPM & PERT
In planning:
it forces the project staff to carefully identify the tasks to be undertaken
Precisely determine the relationships of the tasks to each other
Allows planners to do “what-if” scenarios to determine the impact of task slippages
Helps to create more realistic estimates of project schedules
60 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Key Time Estimating Issues that can be Explored
with the
CRITICAL PATH CONCEPT
• Calculating Realistic durations and timings -- Earliest & Latest -- for Activities & Milestones
• Determining reasonable deadlines
• Identifying “Hurry up & wait” and “Wait & hurry up” Activities
• Parallel Scheduling of Selected Activities to speed up project implementation
• Fast Track Facilitation
• Identifying Merge/Burst Points
• Identifying “bottle neck” Activities
• Performing “What if” simulations for forward planning
61 Critical Path Method
© 2012 Dr. Kenneth F. Smith, PMP
Critical Path Network with three buffers added
applying the Critical Chain method
A
B
D
G
C
E
F
H
I
J Z
2
4
2 3
3
5
4 1 1
5
6
4 3
3
4
19
16
12
11 8
11
12
5 2
5
4
8
2
0 7
2
2
7
8
8
16
6
5
4 20
6
62 Critical Path Method
9
3
Feeder Buffer
Project Buffer
3 15 1
© 2013 Dr. Kenneth F. Smith, PMP Project Management Fundamentals Slide 63
Applying the Decision Tree / Risk
Breakdown Structure Technique
in RISK ANALYSIS Phase II
Estimating PROJECT
Schedule Buffer &
Budget Contingencies, &/or
Management Reserves
# 1-8 Decision Tree Analysis
Template In Tool Kit
Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP
Decision Tree / Risk Breakdown Structure to Analyze the Probability of up to Five Sequential Risk Tiers
Etc., etc.,
resulting in
32 separate
different
possible
outcomes
for Five
Sequential
Risks
1
Risk
2
Risks
3
Risks Each of
which
affect the
schedule
and budget
in different
ways!
2 possible
outcomes 4 possible
outcomes 8 possible
outcomes
Slide 64
Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP
Exponential Contingency / Management Reserve Needed to address the Cascading Effect of Additional Risks
Likely to be Encountered
# Risks Encountered
Sc
ale
o
f C
on
tin
ge
ncy L
eve
l
to
a
dd
re
ss th
e in
cre
asin
gly
co
mp
ou
nd
e
ffe
ct
0 5 3 4 2 1
2
4
8
16
32
The Cumulative
Impact of
“Murphy’s Law”
“If anything can go
wrong, it will, and at the
worst possible time”
A Computer Program is needed to
handle all the possibilities and
outcomes
Slide 65
© 2012 Dr. Kenneth F. Smith, PMP
Revisit your Project Network and
update activity Durations based on
risk analysis data
Then add buffers
Team Activity
66 Critical Path Method
Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP
Develop a Time-Scaled Gantt/Bar
Chart from the CPM Network Data
67
Ac
tiv
itie
s &
Mile
sto
nes
Time
Executive Level Review of Implementation Plan
Milestone
Summary
Project Management Fundamentals © 2013 Dr. Kenneth F. Smith, PMP
TEAM EXERCISE
68
Prepare a GANTT/BAR CHART
for your Project’s
MAJOR ACTIVITIES & MILESTONES