  • 7/27/2019 Estimation Sample

    1/14

    No Particulars Qty Unit Rate Amount

    1

    Earthwork for foundation

    Excavation for foundation in earth, soil of all types, sand,

    gravel and soft murum including removing the excavated

    materials upto a distance of 50 metres beyond the building

    area and lift upto 1.50 metres, stacking and spreading as

    directed including dewatering unless provided elsewhere,

    preparing the bed for the foundation and necessarybackfilling, ramming, watering complete excluding shoring

    and strutting.

    42.9 m3 58.3 2,501.07

    2

    PCC for foundation:

    Providing and laying in situ cement concrete for mix 1:4:8

    of trap metal for foundation and bedding including bailing

    out water manually, formwork, compacting and curing.

    (Cement: 3.40 bags per cu.m)

    12.9 m3 1788.3 23,015.42

    3

    Brick work in foundation and plinth

    Providing second class Burnt Brick masonry with

    conventional/I.S. type bricks in cement mortar 1:6 in

    foundations and plinth of inner walls/in plinth external walls

    including bailing out water manual- ly, striking joints on

    unexposed faces, raking out joints on exposed faces and

    watering Complete.

    26.1 m3 1140.0 29,754.00

    4

    DPC

    Providing and laying damp-proof course 20 mm thick 1:2:4

    cement concrete layer and bitumen using cement with

    water proofing compound. (Cement : 0.256 bag per sq.m)

    14.9 m2 66.2 987.70

    5

    Brick work in super structure

    Providing second class Burnt Brick masonry with

    conventional/I.S. type bricks in cement mortar 1:6 in

    foundations and plinth of inner walls/in plinth external walls

    including bailing out water manual- ly, striking joints on

    unexposed faces, raking out joints on exposed faces and

    watering Complete.

    45.8 m3 1900.0 86,925.00

    6

    RCC

    Providing and casting in situ cement concrete M-20 of trap

    metal for R.C.C. pile caps as per detailed designs and

    drawings including bailing out water manually, centering,

    formwork, compacting, finishing and curing. (Excluding

    steel reinforcement) (Cement: 7.20 bags per cu.m)

    9.5 m3 1140.0 10,879.70

    7

    Roof Plastering:

    Providing internal cement plaster 6 mm thick in a single

    coat in cement mortar 1:2 without neeru finish to concrete

    or brick surfaces in all positions including scaffolding,

    curing complete.

    75.5 m2 1230.0 92,840.40

    8

    Ceiling plastering:

    Providing internal cement plaster 12 mm thick in a singlecoat in cement mortar 1:3 without neeru finish to concrete

    or brick surfaces in all positions including scaffolding,

    curing complete. (Cement: 0.140 bag per sq.m)

    63.5 m2 94.6 6,010.88

    9

    Wall Plastering:

    Providing internal cement plaster 12 mm thick in a single

    coat in cement mortar 1:4 without neeru finish to concrete

    or brick surfaces in all positions including scaffolding,

    curing complete. (Cement: 0.110 bag per sq.m)

    317.8 m2 89.4 28,407.74

  • 7/27/2019 Estimation Sample

    2/14

    10

    Floor plastering:

    Providing and laying cement concrete flooring 20 mm thick

    with 1:2:4 cement concrete laid to proper level and slope in

    alternate bays including compaction, filling joints, marking

    lines to give the appearance of tiles of 30 cm x 30 cm or

    other size, laid diagonally/ square, etc., finishing smooth

    (with extra cement) in any colour as directed and curing

    complete. (Cement: 0.146 bag per sq.m)

    60.0 m2 92.0 5,520.00

    11

    Colour Washing

    Providing and applying, plastic emulsion paint of approved

    quality, colour and shade to old and new surface in three

    coats including scaffolding, preparing the

    surface.(excluding primer coat). complete.

    317.8 m2 27.3 8,674.85

    12

    Painting

    Providing and applying two coats of lead/zinc base oil

    paint/bituminious paint of approved colour and shade to

    new wood work and fibre boards including preparing the

    surface,knotting,scaffolding if necessary, excluding primer

    coat complete.

    31.6 m2 32.3 1,020.36

    13

    Steel

    Providing steel reinforcment for RCC, including centeringand shuttering, calculated at 1% by volume of the RCC and

    7850 kg/m3

    749.2 kg 24.0 17,980.14

    Lumpsum

    Doors 2.0 nos 5000.0 10,000.00

    Windows 4.0 nos 4500.0 18,000.00

    Shelves 2.0 nos 3800.0 7,600.00

    15 Total 350,117.27

    16 Electrification ( 8% of total cost ) 28,009.38

    17 Miscellaneous ( 8% of total cost ) 28,009.38

    18 Net Total 406,136.04

    19 Profit (10 % of net total) 40,613.60

    20 Gross total 446,749.64

    14

  • 7/27/2019 Estimation Sample

    3/14

    No Particulars No L B H Q Explanation

    1 Earthwork in escavation

    1.1 Long walls 2 11.70 1.10 1.00 25.74 11.7=? (write how important values are calculated)

    1.2 Short walls 3 5.20 1.10 1.00 17.16 5.2=?

    Total 42.90

  • 7/27/2019 Estimation Sample

    4/14

    No Particulars No L B H Q Explanation

    2 Plain Cement Concrete

    2.1 Long walls 2 11.70 1.10 0.30 7.72 (write how important values are calculated)

    2.2 Short walls 3 5.20 1.10 0.30 5.15

    Total 12.87

  • 7/27/2019 Estimation Sample

    5/14

    No Particulars No L B H Q Explanation

    3 Brick masonry I class 1:6 for foundation

    3.1 Long walls -First footing 2 11.40 0.80 0.20 3.65 (write how important values are calculated)

    3.2 Long walls - Second footing 2 11.30 0.70 0.10 1.58

    3.3 Long walls - Third footing 2 11.20 0.60 0.10 1.34

    3.4 Long walls - Fourth footing 2 11.10 0.50 0.10 1.11

    3.5 \-do- Plinth wall above footing 2 11.00 0.40 0.80 7.04

    3.6 Short walls - First footing 3 5.50 0.80 0.20 2.64

    3.7 Short walls - Second footing 3 5.60 0.70 0.10 1.183.8 Short walls - Third footing 3 5.70 0.60 0.10 1.03

    3.9 Short walls - Fourth footing 3 5.80 0.50 0.10 0.87

    3.10 \-do- Plinth wall above footing 3 5.90 0.40 0.80 5.66

    Total 26.10

  • 7/27/2019 Estimation Sample

    6/14

    No Particulars No L B H Q Explanation

    4 Damp proof course 2.5 cm

    4.1 Long walls 2 11.00 0.40 8.80 (write how important values are calculated)

    4.2 Short walls 3 5.90 0.40 7.08

    4.3 Deduct for door sills 2 1.20 0.40 -0.96

    Total 14.92

  • 7/27/2019 Estimation Sample

    7/14

    No Particulars No L B H Q Explanation

    5 Brick masonry I class for superstructure

    5.1 Long walls 2 10.90 0.30 4.20 27.47 ??

    5.2 Short walls 3 6.00 0.30 4.20 22.68 ??

    5.3 Deduct for door opening 2 1.20 0.30 2.10 -1.51

    5.4 Deduct for window opening 4 1.00 0.30 1.50 -1.80

    5.5 Deduct for shelf opening 2 1.00 0.20 1.50 -0.60

    5.6 Deduct for lintels over door 2 1.50 0.30 0.15 -0.14

    5.7 Deduct for lintels over windows 4 1.30 0.30 0.15 -0.235.8 Deduct for lintels over shelves 2 1.30 0.30 0.15 -0.12

    Total 45.75

  • 7/27/2019 Estimation Sample

    8/14

    No Particulars No L B H Q Explanation

    6 Reinforced Cement Concrete

    6.1 Roof 1 11.10 6.80 0.12 9.06 ?

    6.2 Lintels over door 2 1.50 0.30 0.15 0.14

    6.3 Lintels over windows 4 1.30 0.30 0.15 0.23

    6.4 Lintels over shelves 2 1.30 0.30 0.15 0.12

    Total 9.54

  • 7/27/2019 Estimation Sample

    9/14

    No Particulars No L B H Q Explanation

    7 Roof Plastering

    7.1 Plastering over roof 1 11.10 6.80 75.48 ?

    Total 75.48

  • 7/27/2019 Estimation Sample

    10/14

    No Particulars No L B H Q Explanation

    8 Ceiling plastering

    8.1 Big Room 1 6.00 4.00 24.00 ?

    8.2 Small Room 1 6.00 6.00 36.00 ?

    8.3 Long outside projection 2 11.10 0.10 2.22

    8.4 Short ourside projection 2 6.60 0.10 1.32

    Total 63.54

  • 7/27/2019 Estimation Sample

    11/14

    No Particulars No L B H Q Explanation

    9 Wall plastering

    9.1 Long walls outside 2 10.90 4.20 91.56 ?

    9.2 Short walls outside 2 6.60 4.20 55.44 ?

    9.3 Inside small room long side 2 6.00 4.20 50.40

    9.4 Inside small room short side 2 4.00 4.20 33.60

    9.5 Inside bing room 4 6.00 4.20 100.80

    9.6 Deduct for door opening 2 1.20 2.10 -5.04

    9.7 Deduct for window opening 4 1.00 1.50 -6.009.8 Deduct for shelf opening 2 1.00 1.50 -3.00

    Total 317.76

  • 7/27/2019 Estimation Sample

    12/14

    No Particulars No L B H Q Explanation

    10 Floor plastering

    Big room 1 6.00 6.00 36.00 ?

    Small room 1 4.00 6.00 24.00 ?

    Total 60.00

  • 7/27/2019 Estimation Sample

    13/14

    No Particulars No L B H Q Explanation

    11 White washing of walls

    same as wall plastering 317.76 ?

  • 7/27/2019 Estimation Sample

    14/14

    No Particulars No L B H Q Explanation

    12 Painting of doors/windows

    12.1 Doors 2 1.20 2.10 2.25 11.34 ?

    12.2 Windows 4 1.00 1.50 2.25 13.50 ?

    12.3 Shelves 2 1.00 1.50 2.25 6.75

    Total 31.59