ethiopia - alemgena - butajira road project completion report

39
AFRICAN DEVELOPMENT FUND PROJECT COMPLETION REPORT ALEMGENA-BUTAJIRA ROAD FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA TRANSPORT DIVISION, 2 INFRASTRUCTURE DEPARTMENT-NORTH, SOUTH & EAST REGIONS April 2007

Upload: phamhanh

Post on 12-Feb-2017

245 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Ethiopia - Alemgena - Butajira Road Project Completion Report

AFRICAN DEVELOPMENT FUND

PROJECT COMPLETION REPORT

ALEMGENA-BUTAJIRA ROAD

FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA

TRANSPORT DIVISION, 2 INFRASTRUCTURE DEPARTMENT-NORTH, SOUTH & EAST REGIONS

April 2007

Page 2: Ethiopia - Alemgena - Butajira Road Project Completion Report

EQUIVALENTS AND ABBREVIATIONS CURRENCY EQUIVALENTS

Appraisal (August 1998) 1 UA = ETB 9.29435 PCR (April 2007) 1 UA = ETB 13.20220

WEIGHTS AND MEASURES

1.00 meter (m) = 3.281 ft. 1.00 kilometre (km) = 0.621 mile 1.00 square kilometre (km2) = 0.386 square mile (mi2) 1.00 hectare (ha) = 2.471 acres 1.00 kilogram (kg) = 2.205 lbs.

FISCAL YEAR : 7th July – 6th July

ABBREVIATIONS AADT = Annual Average Daily Traffic ADB = African Development Bank ADF = African Development Fund DFID = Department for International Development (U.K.) EIRR = Economic Internal Rate of Return ERA = Ethiopian Roads Authority EU = European Union GDP = Gross Domestic Product GOE = Government of Ethiopia (Federal Democratic Republic of Ethiopia) GTZ = Deutsche Gereuschraft fur Technische Zusammenarbeit (Germany) HDM = Highway Management and Development Tool ICB = International Competitive Bidding IDA = International Development Association (World Bank) IRI = International Roughness Index JICA = Japanese International Cooperation Agency LICB = Limited International Competitive Bidding LLCB = Limited Local Competitive Bidding NDF = Nordic Development Fund PCR = Project Completion Report RF = Road Fund RFA = Road Fund Administration RSDP = Road Sector Development Program ROW = Right-of-Way UA = Unit of Account VOC = Vehicle Operating Cost VPD = Vehicles per day

Page 3: Ethiopia - Alemgena - Butajira Road Project Completion Report

TABLE OF CONTENTS No. of Pages Project Matrix i Basic Project Data ii-iv Executive Summary v-vii 1. INTRODUCTION 1 2. PROJECT OBJECTIVE AND FORMULATION 2 2.1 Project Objective 2 2.2 Project Description 2 2.3 Formulation, Evaluation and Approval 2 3. PROJECT EXECUTION 2 3.1 Effectiveness and Start-up 2 3.2 Project Design 3 3.3 Modifications 3 3.4 Implementation Schedule 3 3.5 Reporting 4

3.6 Procurement 4 3.7 Financing Sources and Disbursement 5 4. PROJECT PERFORMANCE AND RESULTS 6 4.1 Overall Assessment 6 4.2 Operating Results 6 4.3 Institutional Performance 7 4.4 Management and Organizational Effectiveness 8 4.5 Staff Recruitment, training and Development 8 4.6 Performance of Consultants, Contractors and Borrowers 9 4.7 Conditions/Covenants 9 4.8 Economic Performance 9 5. SOCIAL AND ENVIRONMENTAL IMPACT AND REGIONAL INTRGRATION 11 5.1 Social Impact 11 5.2 Environmental Impact 12 5.3 Regional Integration 13 6. PROJECT SUSTAINABILITY 14

Page 4: Ethiopia - Alemgena - Butajira Road Project Completion Report

7. PERFORMANCE OF THE BORROWER AND BANK 15 (Continued)

8. OVERALL PERFORMANCE AND RATING 16 9. CONCLUSIONS, LESSONS AND RECOMMENDATIONS 16

9.1 Conclusions 16 9.2 Lessons Learned 17 9.3 Recommendations 17 This report has been prepared by Messrs L. Kiggundu, Transport Engineer and K.S.H. RAO, Consultant - Transport Economist, following their mission to Ethiopia from 9th to 21thApril 2007. Any inquiries relating to this report may be referred to either the authors or to Mr. J. Rwamabuga, Division Manager, OINF.2 (Extension – 2181).

Page 5: Ethiopia - Alemgena - Butajira Road Project Completion Report

LIST OF ANNEXES

Annex No. of No. Titles Pages

1. Project Location Map 2

2. Summary Comparison of Appraisal and Actual Implementation Schedules 1

3. Economic Benefit-Cost Analysis 1

4. Performance Evaluation and Rating 4

5. Recommendations and Follow-up Matrix 1

6. Sources of Information 1

Page 6: Ethiopia - Alemgena - Butajira Road Project Completion Report

i

ETHIOPIA

ALEMGENA-BUTAJIRA ROAD UPGRADING PROJECT PROJECT COMPLECTION REPORT (PCR)

Design Team: L.Kiggundu/K. S. H Rao Verifiable Indicators Narrative Summary

(NS) Appraisal (1998) PCR (2007) Means of

Verification Assumptions

1. Sector Goal 1.1 To improve and expand the essential infrastructure with a view to support economic and social development programs.

1.1 Raise the level of road density from 21km/1000 km2 to 27km/1000 km2 by the year 2002.

1.1 Road density in 2003/04 reached a level of 33.6 km/ 1000 km2.

1.1 Annual and construction statistics from Ethiopian Roads authority (ERA). 1.2 Traffic Statistics

2. Project Objectives 2.1 Reduce road maintenance and vehicle operating costs (VOC) on Alemgena-Butajira section and to promote regional integration between Ethiopia and Kenya.

2.1 Roughness less than 3.5 IRI throughout the life of the project up to 2021. 2.2 Reduced VOC by 34% in the year 2002 when the road is opened to traffic. 2.3 Maintenance costs on the road reduced by at least 50% over the life of the project. 2.4 Commercial traffic increase at 5% p.a. up to the year 2010 and 2.1% p.a. there after. Light traffic increases at 4% p.a. till 2010 and 2% p.a. thereafter.

2.1 The current IRI of the project road is estimated at 3.2. 2.2 The VOC reduced by about 48% after opening of the road in April 2004. 2.3 Recurrent maintenance cost reduced by 56% over the life of the project. 2.4 The current rate of growth is 8% p.a for commercial traffic and 6% p.a. for light traffic which is expected to continue for next 10 years. There after the rate of growth will stabilize around 5% and 4% p.a for commercial and light traffic respectively.

2.1 Calculate VOC using HDM model. 2.2 Measure Roughness 2.3 Traffic Counts 2.4 Annual Budget of ERA

(Project Objective to Goal) 2.1 Appropriate level of competition will be maintained 2.2 Vehicle availability is sufficient to meet demand

3. Outputs 3.1 A two lane 120 km bitumen surfaced road with 7 m wide carriageway and two 1.5m shoulders from Alemgena to Butajira constructed.

3.1 120 km of bituminous road completed between Alemgena and Butajira in 2002.

3.1 120 km of bituminous road completed between Alemgena and Butajira in April 2004, with a delay of about 28 months.

3.1 Quarterly Progress reports (QPRs) 3.2 Supervision Reports (SRs) 3.3 Project Completion Report (PCR) 3.4 Audit Reports

(Output to Project Objective) 3.1 ERA will maintain the road in accordance with the maintenance action plan after its completion.

4. Activities 4.1 Project Construction a) Pre-qualification of contractors b) Issue & receipt of tenders c) Evaluation, negotiation and award of contract d) Upgrading of Alemgena- Butajira Section (120 km) 4.2 Consultancy Services a) Approval of Terms of Reference (TOR) & short-list b) Issue & receipt of Request for Proposal (RFP) c) Evaluation & approval d) Award of Consultancy services e) Commencement of services

Inputs/resources 4.1 Inputs UA million a) Upgrading 17.92 b) Supervision of works & audit 1.12 c) Contingencies Physical 1.90 Price 4.06 Total 25.00 4.2 Resources a) ADF 18.50 b) GOE 6.50 Total 25.00

Inputs/resources 4.1 Inputs UA million a) Upgrading 21.27 b) Supervision of works & audit 1.09 Total 22.36 4.2 Resources a) ADF 17.86 b) GOE 4.50 Total 22.36

4.1 Appraisal estimates 4.2 QPRs 4.3 SRs 4.4 PCR 4.5 Audited accounts 4.6 Disbursement records

(Activity to Output) 4.1 All procurement actions are on schedule 4.2 Payments for invoices are not delayed 4.3 GOE’s timely payment of counterpart local funds 4.4 Effective supervision by the Bank and consultant.

Page 7: Ethiopia - Alemgena - Butajira Road Project Completion Report

ii

BASIC PROJECT DATA

1. Country : Ethiopia 2. Project : Alemgena-Butajira Road Upgrading 3. Loan Number : 2100150000314 4. Borrower : Federal Democratic Republic of Ethiopia 5. Beneficiary : Federal Democratic Republic of Ethiopia 6. Executing Agency : Ethiopian Roads Authority A. ADF Loan Details

Description Appraisal

Actual

1. Loan Amount (UA million) 18.50 17.86 2. Service Charge 0.75% per year on amount disbursed and

outstanding. 3. Commitment Fee 0.50% per year on the un-disbursed portion

commencing 120 days after signing of the loan agreement.

4. Repayment Period 40 years 5. Grace Period 10 years 6. Repayment 1% of the principal each year from the eleventh to

twentieth year inclusive and 3% each year thereafter.

7.Loan Negotiation Date 4 – 6, May 1998 8. Loan Approval Date 17-06-1998 9. Loan Signature Date 21-07-1998 10. Date of Entry into Force 10-02-2000

B. Project Data

1. Project Cost

Project Cost (in UA million) Item of Cost Appraisal Actual Foreign Exchange Component 18.50 17.86 Local Cost Component 6.50 4.50 Total Cost 25.00 22.36

2 Source of Finance

In UA Million Appraisal Actual

Source of Finance

F.E. L.C. Total % F.E. L.C. Total % ADF 18.50 0.00 18.50 74.00 17.86 -- 17.86 79.87 GOE 0.00 6.50 6.50 26.00 -- 4.50 4.50 20.13 Total 18.50 6.50 25.00 100.0 17.86 4.50 22.36 100.0

Page 8: Ethiopia - Alemgena - Butajira Road Project Completion Report

iii

Appraisal Actual 3. Effective Date of First Disbursement: January 1999 08-02-2001 4. Effective Date of Last Disbursement: 31-12-2002 30-06-2005 5. Commencement of Project: July 1999 07-11-2000 6. Completion of Project December 2001 05-04-2004 C. Performance Indicators 1. Cost under-run : 10.6% 2. Time Overrun : 27 months * Slippage on Effectiveness : one year * Slippage on Completion Date : 28 months * Slippage on Last Disbursement : 30 months * Number of Extensions of Loan Validity Period : Two 3. Project Implementation Status : Completed 4. List of Verifiable Indicators and Levels of Achievement:

Score Evaluation Criterion Maximum Actual 1. Time Overruns 2. Cost Over-runs/Under-runs 3. Adherence to Contractual Conditions 4. Adequacy of Supervision and Reports 5. Operational Performance

4 4 4 4 4

1 3 2 3 3

Total Score 20 12 Average Score = 2.4 (Satisfactory)

5. Implementation Performance

* Institutional Performance : Satisfactory * Consultants’ Performance : Satisfactory * Contractor’s Performance : Satisfactory

6. Economic Internal Rate of Return (EIRR):

Appraisal : 22.10% Actual (PCR) : 22.40%

D. Missions

Project Cycle M/Y Numbers of Persons Composition Person

weeks 1. Identification 2. Appraisal 02/1998 2 T.E, T.En 4

11/2001 2 T.E, T.En 2 06/2002 2 T.E, T.En 2 12/2002 2 T.E, T.En 2 06/2003 1 T.En 1 11/2003 2 T.E, T.En 2 04/2004 2 T.E, T.En 2 11/2004 2 T.E, T.En 2

3. Supervision

06/2005 1 T.En 1 4.PCR 04/2007 3 T.E, T.En, T.Ec 5 T.E: Transport Economist, T. En: Transport Engineer, T.Ec : Transport Economist-Consultant

Page 9: Ethiopia - Alemgena - Butajira Road Project Completion Report

iv

E. Bank Loan –Disbursements (UA million)

As at Appraisal Actual Year

Amount % Share Cum. (%)

Amount % Share Cum. (%)

1999 4.60 24.87 24.87 2000 6.05 32.70 57.57 2001 6.05 32.70 90.27 3.32 18.59 18.59 2002 1.80 9.73 100.00 3.22 18.03 36.62 2003 - 6.54 36.62 73.24 2004 - 2.81 15.73 88.97 2005 - 1.97 11.03 100.00 Total 18.50 100.00 17.86 100.00

Loan Balance Cancelled UA 0.64 million

F. CONTRACTOR

Description Contractor Contract Description Construction Works for upgrading Alemgena-Butajira Road Name of the Firm China Roads and Bridges Corporation (China) Date Contract Signed 25-10-2000 Date Contract Terminated 05-04-2004 Contract Duration 1,161 days Amount ETB 229.96 million

G. CONSULTANTS Construction Supervision and Project Audit

Name

Intercontinental Consultants and

Technocrats Pvt. Ltd (India)

A.A.Broamhead Co.

Contract Description Construction Supervision Project Audit Date Contract Signed 01-09-2000 12-08-2003 Date Contract Terminated 30-04-2005 October 2005 Contract Duration 1,627 days (including

defects liability period) 600 days

Amount ETB 12.67 million ETB 0.096 million

Page 10: Ethiopia - Alemgena - Butajira Road Project Completion Report

v

EXECUTIVE SUMMARY 1. INTRODUCTION 1.1 The Government of Ethiopia (GOE) formulated, with the support and wide consultation with development partners and stakeholders in 1997, a 10-year Road Sector Development Programme (RSDP) and implemented in two phases – RSDP-I (1997-2002) and RSDP-II (2002-2007). The RSDP listed several roads and sector policy support options, which formed the basis for donor intervention in the programme. The upgrading of the Alemgena-Butajira Road was one of the high priority link roads identified by the GOE for financing by the Bank Group in the RSDP. The preparation activities for Alemgena-Butajira road were undertaken as part of Five Roads Feasibility Study financed through a Japanese Grant administered by the International Development Association (IDA). The final feasibility study (July 1997) and detailed engineering design (December 1997) formed the basis for the Bank’s appraisal report. The project road was appraised in February 1998 and an ADF loan of UA 18.5 million was approved in June 1998. 1.2 This PCR is based on the appraisal report, project files in the Bank, Borrower’s progress reports, supervision consultant’s Final Construction Report (FCR) and the Borrower’s PCR, interviews and site inspection conducted during an ADB mission to Ethiopia in April 2007. Project Objective and Description 1.3 The transport sector goal was to support economic and social development programmes taking place in Ethiopia through the removal of transport bottlenecks and upgrading the road network. The objective of the project was to improve the road transport services in the project area by reducing road maintenance and vehicle operating costs and to promote regional integration between Ethiopia and Kenya. The project, as designed at appraisal, comprised i) Construction works for the upgrading of gravel surfaced road to bitumen standard with 7m wide carriageway with 1.5m shoulders on each side for a total length of 120 km between Alemgena and Butajira; and ii) Consultancy services for a) supervision of the construction works of (i) above b) project audit services. Project Execution and Implementation Schedule 1.4 The Ethiopian Roads Authority (ERA) was the Executing Agency for the project. A consulting firm provided supervision of civil works for the road upgrading. 1.5 The road upgrading works were completed 27 months after the appraisal schedule. The slippage was due to delay in procuring the supervision consultant and civil works contractor and design modifications during the construction phase. Project Costs and Financial Resources 1.6 The total project cost at appraisal was UA 25.00 million including contingencies, net of taxes of which UA 18.50 million was in foreign exchange. The actual cost of the completed project was UA 22.36 million, which is 10.6% less than the appraisal estimate. 1.7 The project was jointly financed by ADF and GOE. The Bank was to contribute 100% of the foreign exchange cost (UA 18.50 million) and the GOE was to contribute 100% (UA 6.50

Page 11: Ethiopia - Alemgena - Butajira Road Project Completion Report

vi

million) of the local costs. Overall, the ADF was to contribute 74% and GOE 26% of the total project cost. At project completion, total disbursements under the ADF loan amounted to UA 17.86 million, about 96.5% of the approved loan amount and GOE disbursed UA 4.50 million, which was about 70 % of the appraisal estimate. Overall Assessment 1.8 In spite of delays in project implementation, a well-designed 2-lane bitumen road between Alemgena and Butajira has facilitated significant reduction in vehicle operating cost and travel time and stimulated economic development in the project influence area. Economic Performance 1.9 The traffic projection at appraisal has been revised duly reflecting current (2005) traffic count of the ERA. The current traffic on the project road has exceeded the appraisal projection by about 12.5%. The recalculated EIRR of 22.4 % (Annex 5) is higher than the EIRR estimated at appraisal (22.1%). This EIRR of 22.4% confirms economic viability of the investment as compared to the opportunity cost of capital of 10%. 2. CONCLUSIONS, LESSONS AND RECOMMENDATIONS

2.1 Conclusions

2.1.1 The overall objectives of the project have been achieved. The project has significantly reduced road transport costs (by about 48%) and travel time (by about 50%) on the Alemgena-Butajira road. 2.1.2 There was considerable delay (16months) during the procurement stage which was mainly due to the fact that Executing Agency was not well conversant with the Bank’s procurement rules and procedures. This problem has been overcome through Bank’s procurement workshops, easy access to information through the Bank’s Country Office and on-going T.A programs financed by the Bank and the World Bank. The improvement in this area is evident from the procurement activities in the subsequent Bank funded road sector projects. 2.1.3 The performance of the contractor, consultant and Borrower were satisfactory. The overall implementation of the project was found satisfactory with a rating of 2.4 out of a maximum of 4. 2.1.4 Inspection of the project road revealed that some sections exhibit raveling (loss of surfacing aggregates) leading to a poorer riding quality on these sections. There are also localized base, sub-base and surfacing failures resulting in the formation of potholes. There are high embankments without guardrails which pose a danger to motorists and pedestrians in case of accidents. The inspection further noted that the corrective measures currently employed to rectify the defects are not to the required specifications and therefore not effective. 2.1.5 There are adequate financial allocations to maintenance from the Road Fund budget for the sustainability of the project road and the only constraint is the capacity of the domestic construction industry to undertake road maintenance works.

Page 12: Ethiopia - Alemgena - Butajira Road Project Completion Report

vii

2.2 Lessons Learned

• Design modifications during project execution that increase the scope of works lead to implementation slippage. It is therefore necessary to identify all the project components at detail design stage to avoid slippage due to extension of the contract period and related additional costs (Para 3.4.2).

• The adopted design of a project assumes a maintenance regime for the road to

serve its design life. It is important to ensure that the maintenance regimes assumed during the project appraisal are adhered to, to protect the investments, (Para 4.2.1).

• Sustainability of investments requires adequate capacity of local construction

industry to undertake routine and periodic maintenance (Paras 6.3 and 6.4).

2.3 Recommendations It is recommended that:

• The Bank and the Borrower should take the necessary care to identify all project components and review the detail designs prior to appraising the project. This would minimize possible time/cost over-runs during construction phase.

• The Borrower should ensure that the maintenance strategies assumed during the appraisal are strictly followed for ensuring sustainability of the investment

• The Borrower should expedite the on-going programs and initiate new programs to enhance the capacity of the local construction industry to take up the routine and periodic maintenance works.

• The Borrower’s staff should be encouraged to attend Bank’s procurement workshops and interact with the professional staff of the country office for information and guidance.

• To assist the Borrower in the institutional capacity building efforts, the Bank

should, in future projects, identify components for institutional capacity building.

Page 13: Ethiopia - Alemgena - Butajira Road Project Completion Report

1

1. INTRODUCTION 1.1 Ethiopia, a land-locked country, is located in the North-Eastern part of Africa and extends over a land area of 1.1 million sq. km. The country is bordered by Eritrea on the North, Sudan on the West, Kenya on the South and Somalia and Djibouti on the East. A significant part of the country is made up of high plateau and mountains. The mid-year 2005 population estimates place total population of Ethiopia at 73 million; with a growth rate of 2.5% per year. Of the total population, females constitute 49.9% and males 50.1%. The project road passes through Mirab Shewa zone of Oromiya Region and Gurage zone of Southern Nations and Nationalities and Peoples Region (SNNPR); with agriculture the mainstay of 88% rural population of the project area. 1.2 The transport system of Ethiopia comprises about 37,018 km of classified roads of which about 64% is in good condition; one railway line (780 km) connecting Addis Ababa with Djibouti; two international airports (Addis Ababa and Dire Dawa), 12 local airports & 38 air strips, river and lake transport of relatively little significance and marine shipping. Roads are the country’s dominant mode of transport accounting for more than 95% of motorised freight tonne-km and passenger-km. At appraisal, the country had a total classified road network of about 26,500 km; of which only 20% was in fair/good condition. 1.3 As a result of inadequate maintenance over long periods, Ethiopia’s road network had deteriorated to such an extent that, in 1996, about 80% of the classified roads were in poor condition; which in turn adversely affected agriculture activity by way of high transport costs, delayed evacuation and crop damage. To redress the situation, the Government of Ethiopia (GOE) formulated, with the support and wide consultation with development partners and stakeholders in 1997, a 10-year Road Sector Development Programme (RSDP) and implemented in two phases – RSDP-I (1997-2002) and RSDP-II (2002-2007). The RSDP provides the key to transport development in Ethiopia, and listed several roads and sector policy support options, which formed the basis for donor intervention in the programme. The upgrading of the Alemgena-Butajira-Hossaina-Sodo Road Corridor was one of the high priority link roads identified by the GOE for financing by the Bank Group in the RSDP. For ease of implementation, the corridor was divided into sub-sections viz. Alemgena-Butajira (120.1 km), Butajira-Hossaina (95 km) and Hossaina-Sodo (94 km). The preparation activities for Alemgena-Butajira road were undertaken as part of Five Roads Feasibility Study financed through a Japanese Grant administered by International Development Association (IDA). The final feasibility study (July 1997) and detailed engineering design (December 1997) formed the basis for the Bank’s appraisal report. The project road was appraised in February 1998 and an ADF loan of UA 18.5 million was approved in June 1998. 1.5 From 1977, when the Bank started its transport sector operations in Ethiopia, the Bank has approved 15 operations for a total of UA 311.17 million comprising 13 projects and 2 studies. Out of this portfolio, 9 projects and 2 studies have been successfully completed and one project terminated/cancelled. Currently three projects are under implementation. 1.6 This Project Completion Report (PCR) is based on the appraisal report, project files in the Bank, Borrower’s progress reports and the Borrower’s PCR, interviews and site inspection conducted during the Bank’s mission to Ethiopia in April 2007.

Page 14: Ethiopia - Alemgena - Butajira Road Project Completion Report

2

2. PROJECT OBJECTIVES AND FORMULATION

2.1 Project Objectives 2.1.1 The transport sector goal was to support economic and social development programmes taking place in Ethiopia through the removal of transport bottlenecks and upgrading the road network. 2.1.2 The objective of the project was to improve the road transport services in the project area by reducing road maintenance and vehicle operating costs and to promote regional integration between Ethiopia and Kenya.

2.2 Project Description The project at appraisal comprised the following components:

i) Construction works for the upgrading of gravel surfaced road to bitumen standard with 7m wide carriageway with 1.5m shoulders on each side for a total length of 120 km between Alemgena and Butajira; and

ii) Consultancy services for

Supervision of the construction works of (i) above

Project audit services

2.3 Formulation, Evaluation and Approval 2.3.1 The project road was identified for upgrading under RSDP-I on the basis of preliminary feasibility study of five road corridors undertaken by the Ethiopian Roads Authority (ERA). The preliminary feasibility study was updated under funding from a Japanese Grant. The outcome of the final feasibility (July 1997) and detailed engineering design studies (December 1997) reconfirmed the high priority for inclusion of upgrading of the project road under RSDP-I. 2.3.2 Following GOE’s formal request to the Bank for financing the upgrading of the project road under RSDP-I, a Bank mission consisting of a Transport Engineer and a Transport Economist visited Ethiopia in February 1998 to appraise the project. The loan conditions were negotiated and there were no issues of disagreement raised by the Bank or the Borrower concerning the project. The loan amount of: UA 18.50 million was approved on 17 June 1998, and signed on 21st July 1998. 3. PROJECT EXECUTION 3.1. Effectiveness and Start-up 3.1.1 The ADF loan for the project was approved on 17th June 1998 and the loan agreement signed on 21st July 1998 without entailing any delay. The loan was made effective on 10th February 2000 with a slippage of about one year which was mainly due to the delay in fulfilling the loan condition prior to first disbursement i.e. to assign from Ethiopian Roads Authority a Civil Engineer, whose qualification and experience are acceptable to the African Development

Page 15: Ethiopia - Alemgena - Butajira Road Project Completion Report

3

Fund (ADF), to supervise and monitor the implementation of the project. This delay, however, did not affect the project implementation as the procurement process was concluded in October 2000; about 8 months after the loan was made effective. 3.2 Project Design 3.2.1 Based on the detailed design studies, the pavement was designed for 3.0 million Equivalent Standard Axles (ESALs) for a design period of 20 years comprising a double bituminous seal surface with 19 mm and 9.5 mm aggregate on 150mm crushed stone base on 200mm natural gravel sub-base. Design speeds varied according to topography; 100 kph for flat terrain, 80 kph for rolling terrain and 50kph for mountainous terrain. It was envisaged in the initial design for the Awash Bridge to extend the sub-structure and only widen the existing decks of 7 spans to accommodate two lanes and to construct new full width decks for the remaining 4 spans. Extension works for minor drainage structures to accommodate a two-lane carriageway together with re-alignment on some sections was included in the initial contract.

3.3 Modifications 3.3.1 During the construction phase, some modifications in bridge design, realignment of certain sections, adjustment of grade of the road and modification of culverts were made. These modifications entailed extension of the contract period and additional costs. The major modification was the complete replacement of the superstructure of Awash Bridge (91.5m long with 11 spans) as it was found to be in poor condition during the implementation of the project. Significant cracks were noticed in the spans proposed for widening and the design was modified to construct a new superstructure (2-lane deck) on the entire bridge length. The originally proposed centerlines and extension/ construction of culverts at some suggested locations were not found feasible/ practicable and such structures were revised and redesigned.

3.4 Implementation Schedule 3.4.1 The Ethiopian Roads Authority (ERA) executed the upgrading works for the project road with assistance of the supervision consultant. The procurement process for the selection of the supervision consultant and civil works contractor was completed in September 2000, instead of December 1998 for consultancy services and May 1999 for civil works contractor, as planned at appraisal. The supervision consultancy contract was signed on 1st September 2000 and civil works contract was signed on 25th October 2000. This entailed a delay of 17 months. 3.4.2 Actual construction works commenced in November 2000, against July 1999 as planned at appraisal, resulting in a delay of 16months. The road upgrading works were targeted for completion by May 2003 (contract period of 30 months). However, due to the reasons listed below including the modifications/ variations to the original design (refer para 3.3 above), the civil works were substantially completed in April 2004, with a delay of 11 months:

i) Delay in initial setting out due to lack of bench marks, ii) Though the works commenced in November 2000, the subsequent

mobilization of the contractor consumed the entire dry season thereby delaying the permanent work till May 2001,

Page 16: Ethiopia - Alemgena - Butajira Road Project Completion Report

4

iii) Increase in Engineer’s facilities, earthworks and disruption caused by obstructions/right-of-way problems,

iv) Lack of knowledge of contractual matters by the Contractor’s Site Management staff during the initial stages of the contract,

v) Old equipment on site and lack of required coordinated procurement of spare parts, and

vi) Exceptional weather conditions and rainy season of 2003.

3.4.3 Thus, in all, the project implementation was delayed by 28 months comprising 17 months in the procurement stage and 11 months during actual construction phase.

3.5 Reporting

3.5.1 Pursuant to the provisions of the General Conditions of the Loan Agreement on submission of reports, the ERA submitted Quarterly Progress Reports (QPRs) in Bank’s format. Five annual audit reports were also submitted. 3.5.2 The Borrower’s PCR submitted by the ERA followed the Bank’s Operation’s Manual Format for the Preparation of Borrower’s PCR. The final audit report and Management Letter were submitted to the Bank. 3.6 Procurement Consultancy Services 3.6.1 The consultant for supervision of road upgrading works was selected from a short-list of 7 consulting firms approved by the Bank in accordance with the Bank’s Rules of Procedure for the Use of Consultants. The Request for Proposal (RFP) was issued to the 7 short-listed consultants on 7th April 2000 and 5 firms submitted proposals. The Bank approved the recruitment process and the contract was awarded to the lowest evaluated bidder i.e. M/s. Intercontinental Consultants and Technocrats (ICT) of India on 1st September 2000. Civil Works Contract 3.6.2 The civil works contractor was procured through international competitive bidding (ICB) with pre-qualification in accordance with the Bank’s Rules of Procurement. Tenders were issued on 21st December 1999. Of the 6 pre-qualified firms, only five collected the bid documents and finally 3 firms submitted bids. Tenders were opened on 3rd March 2000. The Bank approved the evaluation report prepared by the Executing Agency and the contract was awarded to the lowest evaluated bidder i.e. M/s. China Road and Bridge Corporation (CRBC) of China in October 2000. The contract was signed on 25th October 2000. Audit Services 3.6.3 As per appraisal, the consultant for audit services was to be procured through limited international competitive bidding (LICB). As the amount allocated for this service was not found attractive for LICB, the Bank, at the request of the GOE, approved limited local competitive bidding (LLCB) for this component. Based on this, following Bank’s Rules of Procedure for the Use of Consultants, the Executing Agency awarded the contract, after obtaining due approval from the Bank, to M/s. A.A. Broamhead & co. on 12th August 2003.

Page 17: Ethiopia - Alemgena - Butajira Road Project Completion Report

5

3.6.4 There were no disputes or complaints during the procurement process of the three components of the project.

3.7 Financial Sources and Disbursement

Project Costs 3.7.1 Total estimated project cost at appraisal was UA 25.00 million including physical and price contingencies but net of taxes, of which UA 18.50 million was in foreign exchange. The actual cost of the completed project was UA 22.36 million, which is 10.6% less than the appraisal estimate. The cost under-run can be attributed to the competitive bids that were close to the Engineer’s estimate and a reduction of 13.1% in quantities in the original BoQ. Table 3.1 presents a comparative picture of project costs at appraisal and at completion.

Table 3.1: Summary - Appraisal versus Actual Costs (UA Million) Appraisal* Actual Actual – Appraisal Item

F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total Civil Works 17.49 6.15 23.64 17.22 4.05 21.27 -0.27 -2.10 -2.37Supervision 0.97 0.35 1.32 0.63 0.45 1.08 -0.34 -0.10 -0.24Audit services 0.04 -- 0.04 0.01 --- 0.01 -0.03 -- -0.03Total 18.50 6.50 25.00 17.86 4.50 22.36 -0.64 -2.00 -2.64Percentage Share 74 26 100 79.87 20.13 100.0 Tax 3.75 3.75

*Including physical and price contingencies Financial Resources 3.7.2 The estimated and actual expenditures (in UA terms) by source of finance are presented in Table 3.2. Of the total estimated cost of the project (UA 25.00 million) at appraisal, the ADF contribution was to be 74% (100% foreign exchange) and GOE 26% (100% local cost). At project completion, the share of ADF has increased to 79.9%. This is mainly because of the additional work attributable to design modifications during the project implementation that mainly entailed foreign exchange cost and is line with the provisions of civil works contract which required that 80% of contract amount to be paid in foreign currency. In spite of the increase in the relative share of ADF, the actual funding was within the provisions made at appraisal.

Table 3.2: Financing Plan - Appraisal versus Actual (UA million) Appraisal Actual Actual - Appraisal Source of

Finance F.E. L.C. Total % F.E. L.C. Total % F.E. L.C. Total ADF 18.50 0.00 18.50 74.0 17.86 0.00 17.86 79.9 -0.64 0.00 -0.64 GOE 0.00 6.50 6.50 26.0 0.00 4.50 4.50 20.1 0.00 -2.00 -2.00 Total 18.50 6.50 25.00 100.0 17.86 4.50 22.36 100.0 -0.64 -2.00 -2.64

Disbursement 3.7.3 The loan funds were disbursed by direct method to the contractors and consultants. The slippage in the actual loan disbursement is broadly in line with the delay in project implementation. The loan amount, as per the appraisal schedule, was to be fully disbursed during 1999-2002. But due to the delay in project implementation, the actual disbursement on the loan commenced in February 2001 and the last disbursement was in June 2005 instead of

Page 18: Ethiopia - Alemgena - Butajira Road Project Completion Report

6

December 2002. The loan balance of UA 0.64 million was cancelled. Table 3.3 presents a summary comparison between the appraisal and actual disbursement profiles of ADF funds.

Table 3.3: Appraisal Versus. Actual Disbursement Profile

(UA Million) As at Appraisal Actual Year

Amount % Share Cum. (%) Amount % Share Cum. (%) 1999 4.60 24.87 24.87 2000 6.05 32.70 57.57 2001 6.05 32.70 90.27 3.32 18.59 18.59 2002 1.80 9.73 100.00 3.22 18.03 36.62 2003 - 6.54 36.62 73.24 2004 - 2.81 15.73 88.97 2005 - 1.97 11.03 100.00 Total 18.50 100.00 17.86 100.00

Loan Balance Cancelled UA 0.64 million

4. PROJECT PERFORMANCE AND RESULTS

4.1 Overall Assessment 4.1.1 The loan covenants /conditions were appropriate and valuable to the execution of the project. The success of the project itself is evidence that the loan conditions were sensible and no more additional conditions were necessary. The Government took a long time in fulfilling the loan conditions precedent to first disbursement. This, however, did not adversely effect implementation of the project, as the procurement process itself was not concluded by the time the loan conditions were fulfilled. 4.2 Operating Results Civil Works 4.2.1 The road upgrading works were substantially completed in April 2004 and fully opened to traffic. The Bank’s PCR mission visited the project road on 11 April 2007 and noted loss of surface aggregates (raveling) on some sections of the road which could be attributed to under application of the binder or inadequate compaction during the rolling in of the surfacing aggregates. These sections exhibit a poorer riding quality as compared to the remaining sections of the road. There are localized base, sub-base and surface failures and development of pot holes due to ingress of moisture into the pavement layers. Resealing of those sections with severe aggregate loss and pothole patching has not been carried out to good quality standards and therefore the measures have not been effective. There is need for close supervision of the maintenance works to ensure compliance with the required specifications of the corrective measures. It was also noted that at one of the drainage structures and on high embankments, guardrails were not provided to protect motorists and pedestrians in case of accidents. A few locations were noted that require warning road signs where reduction of speed is necessary due to changes in road environment at critical horizontal and vertical alignments. Although the Defects Liability Period expired in April 2005, GOE indicated that the contractor had undertaken to rectify the pavement defects at no extra cost to the client.

Page 19: Ethiopia - Alemgena - Butajira Road Project Completion Report

7

Traffic 4.2.2 The Ethiopian Roads Authority conducts network wide 7-day classified traffic counts three times a year i.e. in February, July and November. Based on the three cycle traffic count data, ERA estimates annual average daily traffic (AADT) on different road sections of the national network. For the project road i.e. Alemgena-Butajira, the ERA traffic count data are available up to the year 2005. These AADT levels are presented in Table 4.1. Since the road was open to traffic in April 2004, the traffic levels have increased significantly. The AADT level which was 334 in 2003 (i.e. before upgrading) has touched a level of 424 in 2004 (first year of opening the road to traffic) and 520 in 2005; indicating an annual increase of about 25%. Further, the observed traffic level in 2005 has exceeded the appraisal traffic forecasts by about 12.5%..

Table 4.1: Traffic on Alemgena-Butajira Road (AADT – Number of Vehicles per Day)

Before Upgrading After Upgrading Type of Vehicle 2001 2002 2003 2004 2005

Car 2 5 10 16 17 L/Rover 55 53 85 96 91 S/Bus 4 12 27 69 95 L/Bus 63 63 75 84 88 S/Truck 10 11 14 18 47 M/Truck 60 56 68 78 96 H/Truck 25 23 45 39 60 T & T 7 15 10 24 26 Total 226 238 334 424 520

Source: Ethiopian Roads Authority

4.3 Institutional Performance 4.3.1 As indicated at appraisal, the ERA was responsible for execution of the road upgrading project. Project supervision and monitoring was the responsibility of the Deputy General Manager, Engineering and Regulatory Services Department of ERA. The Contract Administration Division of this Department was vested with the responsibility to implement the construction works. This division was well staffed and had adequate well qualified and experienced engineers for undertaking the job. A qualified and experienced engineer of the division was designated as Project Coordinator (PC) for the implementation of the project. The PC with the assistance of the supervision consultant was responsible for project implementation including all aspects of procurement and day-to-day supervision of the project. 4.3.2 There was substantial slippage in project implementation of 27 months, mainly delayed procurement (16 months) and additional time during construction (11 months) attributable to modifications in the original design and adverse weather conditions. In respect of procurement, the delay was attributable to i) long process in advertising GPN and SPN and pre-qualification of 6 contractors from out of 26 applicants (about 6 months) and ii) actual bidding, evaluation and contract award for civil works (about 11 months). Notwithstanding the delay, the project cost at completion was 10.6% less than the appraisal estimate and the quality of the completed road was satisfactory.

Page 20: Ethiopia - Alemgena - Butajira Road Project Completion Report

8

4.4 Management and Organizational Effectiveness

4.4.1 ERA was designated as the executing agency at appraisal responsible for project implementation. The ERA, headed by a General Manager, has three departments namely, i) Engineering and Regulatory Services, ii) Operations and iii) Human Resources & Financial Management. A Deputy General Manager heads each of these three departments. While the broad structure of the ERA has remained the same, designations of some top management of ERA have changed. For example, the General Manager is now Director General and Deputy General Managers heading the three departments are now designated as Deputy Director Generals. Further, the Engineering and Regulatory Services Department has been reorganized into five divisions namely, a) Planning & Programming Division, b) Construction Contract Implementation Division, c) Network Management Division, d) Engineering Procurement, Design & Technical Services Division and e) District Engineering Divisions. Further, the Right-of-way (ROW) unit is now placed under Construction Contract Implementation Division to minimize delay relating to ROW issues and to fast track implementation of projects. 4.4.2 ERA is the apex body responsible for overall planning, construction, maintenance and management of the country’s trunk road network and major link roads. The Board of Directors of ERA has the authority to approve the award of all contracts. The Rural Road Authorities (RRAs) of respective Regional Governments are vested with the responsibility for the construction and maintenance of rural/regional roads. The RRAs function as autonomous agencies under respective management boards. The ERA has a Rural Roads Technical Support Branch to provide the needed technical assistance and training support to RRAs. 4.4.3 Within the above organizational set up, the ERA is functioning effectively as is evident from the successful completion of a number of programs/ projects including Phase 1 (1997-2002) and Phase 2 (2002-2007) of the Road Sector Development Program (RSDP). At the time of the PCR mission, negotiations for Phase 3 of the RSDP were underway with the World Bank. However, problems like paucity of professionals and staff turn-over (refer para 4.5.1) sometimes cause slippages in project implementation.

4.5 Staff Recruitment, Training and Development

4.5.1 During February 1998 (i.e. at appraisal), the ERA had 15,732 employees of which 4% were professionals. Women employees constituted 3.8% of the total; of which only 14% were professionals. Currently, ERA has about 13,000 employees comprising 5,545 permanent and the rest contract & seasonal staff. The reduction in the total staff strength of ERA as compared to 1998 level is mainly due to restructuring and establishment of District Road Maintenance Contractor Units (DRMCs). There are a number of vacant positions at engineer/ senior engineer levels. In spite of concerted efforts for filling these vacancies, ERA is finding it difficult to get qualified personnel. Another issue of concern is that the ERA is loosing professionals to private sector due to better packages. 4.5.2 ERA has two training institutes (one each at Alemgena and Ginchi) for undertaking on-the-job training programs for all levels of its professionals. In addition, for enhancing the institutional capability of Road Agencies advanced training courses in overseas institutions are also organized with funding from the ADF, World Bank, JICA, EU and DFID. The in-

Page 21: Ethiopia - Alemgena - Butajira Road Project Completion Report

9

house training activities of ERA are complemented through Technical Assistance (T.A.) under donor funding in the areas of transport economics, contract management, bridge engineering, etc. Further, programs are underway with funding from NDF, GTZ and Ireland for enhancing the institutional capacities of RRAs in the areas of transport planning, contract administration and capacity building. The on-going T.A. activities funded by the World Bank and ADF include extensive on-the-job training in ERA; short/long term overseas training to enhance ERA’s capability in Human Resource Management, Contract Administration, Design Review, Project Planning and Procurement.

4.6 Performance of Consultants, Contractors and Executing Agency Consultants

4.6.1 The quality of the supervision was generally good. Due attention was paid to procedure and to detail. A full complement of staff was maintained on site at all times to monitor the Contractor’s site activities. These included a resident engineer, an assistant resident engineer, a senior pavement/materials engineer, a structural engineer, a highway engineer, a surveyor, a claims expert, inspectors of works and laboratory technicians. The inputs of the site personnel helped to produce a final product with the required specifications. 4.6.2 The consultant maintained a good working relationship with executing agency in the supervision of the project. Relations with the Contractor were strained at times due to delay in issuance of final detailed design drawings to achieve good progress.

Contractor

4.6.3 Overall the contractor’s performance was satisfactory despite delay in mobilization, poor co-ordination of procurement of the required resources and high turn-over of site management personnel. Due to consciousness of meeting targets and production of good quality of work, the contractor took steps to improve his activities on site. Executing Agency(EA) 4.6.4 The ERA was the executing agency for the project and dealt with all technical and management issues relating to the project and served as the contact for the Bank in terms of project related coordination. 4.6.5 The ERA maintained a close working relationship with the supervising consultant during the course of project implementation. Further, the ERA contributed to the project by assigning a qualified and experienced engineer, as coordinator of the project in accordance with the loan conditions precedent to the first disbursement. 4.7 Conditions/Covenants 4.7.1 The GOE fulfilled all the conditions precedent to the entry into force of the Loan Agreement. However, there was a delay of about 12 months in fulfilling the loan conditions precedent to the first disbursement. This delay however did not affect the implementation schedule of the project.

Page 22: Ethiopia - Alemgena - Butajira Road Project Completion Report

10

4.8 Economic Performance Appraisal Expectations 4.8.1 At appraisal, economic viability of the investment on upgrading the project road was assessed using a “with” and “without” project scenario approach. The assessment of economic viability was based on Economic Internal Rate of Return (EIRR). The vehicle operating costs (VOC) and various road maintenance interventions underlying the economic analysis were calculated using Highway Design and Maintenance model (HDM-III). The analysis was conducted using January 1998 prices, assuming a 3-year construction period (1999-2001) followed by 12-month defects liability period. A 20-year analysis period (2002-2022) was assumed. For the project road, the base year (1998) traffic level was 328 AADT comprising 18.2% light vehicles, 9.4% medium vehicles and 72.4% heavy vehicles. Based on the base year traffic levels, observed growth trends of population, Gross Domestic product (GDP), etc., the traffic projections were made for each year of the 20-year design period. The average annual growth rates adopted were: 4.5% for light vehicles and 3.6% for medium & heavy vehicles. The projected traffic was estimated to reach 385 AADT by 2002 (year of completion of upgrading) and 762 AADT by 2022 (last year of the design period). 4.8.2 The project cost included capital cost (excluding price contingency and transfer payments) of upgrading works (UA 20.94 million) and road maintenance (periodic and routine) cost. The benefits for the project consisted of saving in vehicle operating cost (VOC), travel time and road maintenance cost resulting from the improved surface condition. Based on the comparison of economic costs and user benefits under “with” and “without” project scenarios, Economic Internal Rate of Return (EIRR) for the project road was 22.1%. With this level of EIRR, the investment was considered economically viable.

Recalculation of Economic Internal Rate of Return (EIRR) 4.8.3 According to the latest traffic count data of ERA, the average annual daily traffic (AADT) on project road for 2005 was 520 AADT comprising 37% light vehicles, 21% medium and 42% heavy vehicles. The current traffic level has exceeded the expected traffic levels for the year 2005 as at appraisal (462 AADT) by about 12.5%, which is mainly due to developments in trade and industry in the project influence area (PIA) facilitated by the upgraded road. However, the share of heavy vehicle traffic is low now (42%) as compared to the appraisal estimate (72.4%). This factor has a negative impact on level of savings in VOC as compared to appraisal scenario. 4.8.4 Available traffic count data since the completion of the upgrading of the road has indicated an increasing trend, the average annual growth being about 25%. This is a very high growth rate and cannot be sustained over a long-term horizon of 20 years. An analysis of traffic growth on similar upgraded roads in Ethiopia has indicated an average annual growth of about 6% for light vehicle and 8% for heavy vehicle traffic. Based on Ethiopian experience, these growth rates are assumed up to 2015 beyond which the annual growth has been assumed to stabilise at 4% for light vehicles and 5% for heavy vehicles. 4.8.5 For recalculation of EIRR, the economic costs have been revised in the light of actual construction costs and economic benefits have been updated in line with the observed growth in traffic since the completion of the project roads. The economic analysis was carried out in July 2005 prices by converting the financial costs into economic terms. The actual cost of construction at completion net of taxes and duties but including the real increase in construction

Page 23: Ethiopia - Alemgena - Butajira Road Project Completion Report

11

cost was UA 22.36 million. The actual economic cost of construction and supervision, and likely road maintenance costs (based on the appropriate maintenance intervention strategies) as well as the benefits emanating from the revised traffic forecasts (in terms of savings in VOC and travel time) formed the basis for reworking the EIRR. The HDM-IV model has been used to calculate VOC and EIRR. 4.8.6 Based on the above, the revised EIRR for the project road which works out to 22.4%, confirms the economic viability of the completed project (Annex 3). The revised EIRR is slightly higher than the appraisal EIRR (22.1%). The revised EIRR would have been much higher than the appraisal EIRR but for the lower share of heavy vehicle traffic currently on the road vis-à-vis the appraisal forecasts (42% versus 72.4%) and higher economic cost of upgrading (UA 22.36 million at completion versus UA 20.94 million at appraisal). If allowance were made for these two factors, the revised EIRR would be 28%. 5. SOCIAL AND ENVIRONMENTAL IMPACT 5.1 Social Impact 5.1.1 The current travel time from Alemgena to Butajira has reduced by about 2.5 hours i.e. about 50% reduction in travel time. The weighted average vehicle operating cost per vehicle km (v km) during 2005 (for a traffic level of 520 AADT) reduced from ETB 4.977 (without upgrading) to ETB 2.549 (with upgrading) i.e. reduction of ETB 2.428 per v km - about 48% reduction in VOC. With the assumed periodic and routine maintenance activities, this level of reduction, on the average, will be sustained till the end of the useful life of the project. 5.1.2 The direct positive impact of reduction in VOC is that the frequency of public transport has increased significantly. For example, as per ERA traffic data, during 2000 (i.e. prior to the upgrading) only 7 small bus and 63 large bus trips per day were observed on the project road. This frequency has increased to 95 trips per day for small buses and 88 trips per day for large buses in 2005 i.e. one year after opening of the upgraded road to traffic. This fact was confirmed by the project beneficiaries. Further, the transport operators have passed on the benefits of reduction in VOC to the passenger in terms of reduction in real tariffs. In this context it may be mentioned that in the project road corridor the road transport tariffs on paved roads are about 10-20% less as compared to the ones on gravel roads as brought out in Table 5.1.

Table 5.1: Comparative Tariffs on Paved and Gravel Roads in Ethiopia Road Type Reduction on Paved Roads Type of Service

Paved Gravel ETB % 1. Passenger (Ethiopian Birr/Passenger Km) 1.1 Inter-urban Large Bus 0.0920 0.1150 0.0230 20% 1.2 Small Bus 0.1500 0.1720 0.0220 13% 2. Freight (Ethiopian Birr/Tonne km) 2.1 Liquid Cargo 0.3446 0.3962 0.0517 13% 2.2 Dry Cargo 0.4000 0.4400 0.0400 9% 2.3 Small Truck 0.4500 0.5500 0.1000 18%

Source: Base Line Survey and Monitoring Indicators for Poverty Impact Evaluation, Final Report (April 2005)

5.1.3 The upgraded road has also facilitated easy and cost effective access to markets. This has increased the awareness of farmers regarding market trends and enhanced their

Page 24: Ethiopia - Alemgena - Butajira Road Project Completion Report

12

bargaining power. The farmers have now formed associations and are able to command better prices for their produce in major markets like Addis Ababa, Nazareth and Ziway. For instance, as indicated by the Agricultural and Rural Development Bureau of Meskan Woreda, in Butajira area the current farm gate prices are: Birr 280/qtl for wheat, Birr 500/qtl for teff, Birr 260/qtl for maize and Birr 500/qtl for beans. The corresponding farm gate prices before upgrading of the road were: Birr 80/qtl (wheat), Birr 200/qtl (teff), Birr 50/qtl (maize) and Birr 180/qtl (beans). The increased farm gate prices, easy access to extension services, seeds, fertilizers, etc. are also contributing to the increase in production levels. 5.1.4 The improved road has a major catalytic role in the socio-economic development of its influence area. A number of new developments e.g. horticulture farms, industries (food processing, textiles, corrugated iron sheets, etc.), hotels, shopping centers are visible along the road corridor. As a result, the number of skilled work force that is attracted to the areas within the road corridor is increasing. Further, according to Butajira Municipal Administration, about 26 private investors have taken land on lease and are planning to set up industries, private schools and colleges, health centers, clinics, pharmacies, petrol stations, etc. The upgraded road has also contributed to considerable increase in small/petty trade along the road which is essentially managed by the rural poor/women. This activity has created additional employment for the rural poor. 5.1.5 During construction phase, about 100,000 skilled and unskilled person-days of employment per year was generated. Women workers constituted about 24% of the total work force. On the average, about ETB 300 per person were paid monthly as wages to labour. In addition, routine maintenance activities for the upgraded road is likely to generate about 120,000 unskilled person-days of employment; of which share of women will be about 20%. 5.1.6 The national policy of Ethiopia on HIV/AIDS emphasizes the participation of government agencies as well as non-governmental organizations (NGOs) and the community at large to assume responsibility to carry out HIV/AIDS prevention and control campaign. Realizing the magnitude of the problem and in response to the national policy, the ERA, as part of World Bank funded RSDP, has taken initiatives to address the HIV/AIDS challenges in the road sector in Ethiopia. The Environmental Monitoring & Safety Branch (ESMB) of ERA is responsible for guidance, supervision and coordination HIV/AIDS prevention activities. In addition, the contractor, as part of the civil works contract, regularly undertook the HIV/AIDS awareness program that included the distribution of pamphlets to the work force and lecture talks by the local doctors to which road side communities were also invited. Further, a clinic was established and operated in the construction camp and proper sanitary conditions were maintained at the living quarters for the labourers. 5.1.7 Notwithstanding the significant positive benefits of the upgraded road, the project beneficiaries along the road corridor with whom the mission interacted during the site visit have expressed concern about the increasing number of road accidents mainly due to speeding. The GOE is putting in place various strategies and programs, as part of the National Road Safety Activities under the aegis of National Road Safety Committee (NRSC).These strategies and programs include a) strengthening legal provisions relevant to traffic safety, b) implement stringent drivers’ training, testing and licensing procedures, c) implement defensive driver training for professional drivers, d) strengthen road safety responsibilities in transport associations and organizations, e) control unsafe usage of freight vehicles for passenger transport, g) pedestrian awareness creation programs and g) traffic

Page 25: Ethiopia - Alemgena - Butajira Road Project Completion Report

13

safety education for children. In this context it may be mentioned that pilot programs implemented in Eastern Shewa Zone within the above strategy framework have shown very encouraging results in as much as the total accidents in the zone in September 2006 have decreased by about 40%, fatality by 48%, serious injury by 54%, light injury by 56% and property damage by 34% as compared to September 2005.

5.2 Environmental Impact

5.2.1 The project road is not situated in or close to environmentally sensitive areas. Since the project entailed upgrading of the existing gravel road to paved standard, the Environmental Impact Assessment (EIA) undertaken as part of the feasibility study concluded that the environmental impacts due to the upgrading would be minimal and only of temporary nature. As such these can be easily controlled to acceptable levels by appropriate mitigation measures and good construction practices. 5.2.2 During the site visit, the mission noted that the contractor had fully reinstated all borrow areas and detours to their original state and to the satisfaction of the executing agency and local communities. Some stretches of detours in villages and towns (e.g. Awash, Lemon, Suten, Bui, etc) were left to serve as village roads at the request of local administrations. The project camp site 1 (Melka Kunture) was handed over to local administration for opening a new primary school. 5.2.3 The road upgrading has brought with it a number of positive environmental impacts (benefits) such as i) reduction in dust, ii) improved surface water drainage, iii) improved drainage system, iv) control of vegetation growth under culverts/ bridges and v) reinforcement of structures. 5.2.4 The Government of Ethiopia paid a total of ETB 9.97 million to people whose properties were affected by the project on account of ROW related issues mentioned at item vi) of para 3.4.2.

5.3 Regional Integration 5.3.1 The upgraded road forms an alternative route to Kenya through Sodo leading to Cairo-Gaborone Trans-African Highway (TAH). The road from Butajira to Sodo is being upgraded to bitumen standard. When the road from Sodo to Kenya Border (Moyale) is upgraded to bitumen standard, the project road corridor can serve in the long-term as an alternative transit route to Kenya with potential to promote regional integration ultimately resulting in enhanced social, cultural and economic development activities between Ethiopia and Kenya. 6. PROJECT SUSTAINABILITY 6.1 Full benefits of investment on the road upgrading will be realized only if the asset is preserved in a good serviceable condition through out the design life of the project. This requires carrying out routine and periodic maintenance on time as per the specified standards. Needless to say, such regular maintenance activities require steady and secured financing. Recognizing the crucial role of maintenance in preserving the assets, as agreed during the RSDP donor meeting (1996), GOE established the Road Fund (RF) in March 1997. The objectives of RF are to finance maintenance works of the Road Agencies and to provide

Page 26: Ethiopia - Alemgena - Butajira Road Project Completion Report

14

sources of fund for road safety measures and programs. The RF is overseen by the Road Fund Board (RFB), an autonomous public authority, and comprises representatives of Federal Government (4), Regional States & Municipalities (6) and private transport sector stakeholders (4). 6.2 The RF revenues comprise levy on fuel consumption, vehicle license fees, overloading fines and central government budgetary allocation. To widen the revenue base other prospective road tariffs can be fixed as necessary. The RF revenue, allocations and actual transfers to different road agencies during the period 2000/01 to 2004-05 are presented in Table 6.1.

Table 6.1: Road Fund Regular Budget Allocation and Actual Transfers

(ETB Million)

Budget Allocation Fiscal Year

Road Fund Revenue

ERA RRA Munici- palities Total

Actual Transfer

2000/01 355.80 169.75 48.50 24.25 242.50 162.49 2001/02 346.40 178.50 51.00 25.50 255.00 233.55 2002/03 341.91 178.50 51.00 25.50 255.00 246.01 2003/04 516.65 208.25 59.50 29.75 297.50 286.28 2004/05 534.97 216.13 83.12 33.25 332.50 423.96

Source: Road Fund Administration 6.3 The RF follows the broad budget allocation pattern of 70% to Federal Roads (ERA), 20% to Regional Roads and 10% to selected municipalities. During the 5-year period (2000/01 – 2004/05), the RF budget allocations were about 60% to Federal Road Network (ERA), 20% to Regional Roads and 10% to selected municipalities, on the average. According to Table 6.1, the collected RF revenues are in excess of the allocations/actual transfers made to different road agencies indicating that the current maintenance program is constrained by the existing capacity of the domestic construction industry. 6.4 The GOE has already initiated some policy measures and programs for encouraging and enhancing the capacity of local construction industry. A 5-year District Maintenance Organization (DMO) Capacity Building Project was launched in 2001 to strengthen maintenance. To achieve the objectives, the DMOs have been split into District Engineering Divisions (DED) and District Road Maintenance Contractors (DRMC); the DEDs responsible for the management function of determining the local maintenance priorities and monitoring performance of DRMCs. The purpose of the split is to transform and equip DRMCs to undertake cost effective road maintenance and prepare them eventually to compete with the private sector on equal commercial terms. As a result, the DEDs are now contracting out maintenance work to the DRMCs and are preparing pay certificates. The DRMCs have their own accounts and payroll and are responsible for their own staff recruitment. It is also planned that equipment and facilities will be leased on a full replacement basis to DRMCs. The GOE has reconfirmed its commitment for achieving the commercial entity stage by the DRMCs by introduction of term maintenance contracts for a period of 2-3 years on limited sections of the road network; participation in routine maintenance with planned scaling up in the coming years along with private domestic contractors. The GOE is currently awarding

Page 27: Ethiopia - Alemgena - Butajira Road Project Completion Report

15

about 40% of the periodic road maintenance works to private sector and this share is expected to increase progressively to 100%. 6.5 As a result of the DMO project, the road maintenance capacity has increased significantly, though still not adequate. Prior to DMO project, the entire maintenance work used to be handled by ERA’s Force Account Unit which did not have the required capacity. Now with the restructuring of ERA’s Force Account Unit into DED and DRMC and injection of additional capacity in the local private sector construction industry, there is a quantum increase in the available domestic road maintenance capacity. 6.6 To ensure that the future road maintenance works will be taken up as per schedule, the GOE has prepared a Maintenance Action Plan (MAP-4) for the period 2004/05 – 2009/10. As per the MAP-4, the size of the maintainable part of road network is estimated at 65%. Table 6.2 gives the total maintenance need for the network in maintainable condition and RF revenues for next three years of MAP-4. The figures set out in Table 6.2 indicate that adequate funding availability for ensuring the sustainability of the road network.

Table 6.2: Road Maintenance Need and Road Fund Revenue (ETB Million) Maintenance Need Year

Federal Regional Municipalities Total Road Fund Revenue

2007-08 461.4 155.0 78.8 695.2 765.2 2008-09 461.3 175.0 82.7 719.0 818.8 2009-10 521.3 190.0 86.8 798.1 876.1

Total 1444.0 520.0 248.3 2212.3 2460.1 Source: Road Fund Administration 6.7 The sustainability of the project road is ensured by the DED of the Alemgena Maintenance District. The DED has contracted out maintenance work of the project road to DRMC and supervising the works and instructing the DRMC regarding the remedial measures where the maintenance works were not meeting the specified standard. Further, the contractor (M/s CRBC) that carried out upgrading works has committed to carry out the necessary remedial works, as per the time schedule to be submitted to ERA. 7. PERFORMANCE OF THE BORROWER AND THE BANK 7.1 The upgrading of the project has reduced road transport costs over the project corridor and also stimulated economic development. Throughout project implementation, the Borrower ensured timely availability of the required counterpart funds. The present condition of the road is overall satisfactory with the exception of some sections that exhibit loss of surfacing aggregates resulting in a poorer riding quality on these sections plus localized potholes due to base, sub-base and surfacing failures. 7.2 During project implementation, the Bank supervised the project through 8 field missions in which technical and disbursement issues were discussed and problems resolved. The Bank responded within reasonable time to the problems arising from project execution. Overall the performance of the Borrower and the Bank was satisfactory. The rating for the Bank's performance is 2.67 out of a maximum of 4 indicating satisfactory level of performance.

Page 28: Ethiopia - Alemgena - Butajira Road Project Completion Report

16

8. OVERALL PERFORMANCE AND RATING 8.1 Project completion was delayed by some 27 months when compared to Appraisal forecast. This delay in completion was due to a number of reasons outlined in Section 3.4. 8.2 In accordance with the implementation performance indicators (Annex 4), the overall assessment of implementation performance and project outcome are satisfactory with a rating of 2.4 and 2.76 respectively out of a maximum of 4. 9 CONCLUSIONS, LESSONS AND RECOMMENDATIONS

9.1 Conclusions

9.1.1 The overall objectives of the project have been achieved. The project has significantly reduced road transport costs (by about 48%) and travel time (by about 50%) on the Alemgena-Butajira road. 9.1.2 There was considerable delay (16months) during the procurement stage which was mainly due to the fact that Executing Agency was not well conversant with the Bank’s procurement rules and procedures. This problem has been overcome through Bank’s procurement workshops, easy access to information through the Bank’s Country Office and on-going T.A programs financed by the Bank and the World Bank. The improvement in this area is evident from the procurement activities in the subsequent Bank funded road sector projects. 9.1.3 Delayed mobilization of the contractor and design modifications during construction phase resulted in 11 month slippage in project completion. 9.1.4 The performance of the contractor, consultant and Borrower were satisfactory. The overall implementation of the project was found satisfactory with a rating of 2.4 out of a maximum of 4. 9.1.5 Inspection of the project road revealed that some sections exhibit raveling (loss of surfacing aggregates) leading to a poorer riding quality on these sections. There are also localized base, sub-base and surfacing failures resulting in the formation of potholes. There are high embankments without guardrails which pose a danger to motorists and pedestrians in case of accidents. The inspection further noted that the corrective measures currently employed to rectify the defects are not to the required specifications and therefore not effective. 9.1.6 There are adequate financial allocations to maintenance from the Road Fund budget for the sustainability of the project road and the only constraint is the capacity of the domestic construction industry to undertake road maintenance works. 9.2 Lessons Learned

• Design modifications during project execution increase the scope of works and lead to implementation slippage. It is therefore necessary to identify all the project components at detail design stage to avoid slippage due to extension of the contract period and related additional costs (Para 3.4.2).

Page 29: Ethiopia - Alemgena - Butajira Road Project Completion Report

17

• The adopted design of a project assumes a maintenance regime for the road to serve its design life. It is important to ensure that the maintenance regimes assumed during the project appraisal are adhered to, to protect the investments, (Para 4.2.1).

• Sustainability of investments requires adequate capacity of local construction

industry to undertake routine and periodic maintenance (Paras 6.3 and 6.4).

9.3 Recommendations It is recommended that:

• The Bank and the Borrower should take the necessary care to identify all project components and review the detail designs prior to appraising the project. This would minimize possible time/cost over-runs during construction phase.

• The Borrower should ensure that the maintenance strategies assumed during the appraisal are strictly followed for ensuring sustainability of the investment.

• The Borrower should expedite the on-going programs and initiate new programs to enhance the capacity of the local construction industry to take up the routine and periodic maintenance works.

• The Borrower’s staff should be encouraged to attend Bank’s procurement workshops and interact with the professional staff of the country office for information and guidance.

• To assist the Borrower in the institutional capacity building efforts, the Bank

should, in future projects, identify components for institutional capacity building. A matrix of recommendations is presented in Annex 5.

Page 30: Ethiopia - Alemgena - Butajira Road Project Completion Report

Annex 1 (Page 1 of 2)

ALEMGENA-BUTAJIRA ROAD UPGRADING PROJECT: PROJ ECT COM PLETION REPORT

PROJECT LOCATION MAP

This map was provided by the African Development Bank exclusively for the use of the readers of the report to which it is attached. The names used and the borders shown do not imply on the part of the Bank and its members any judgment concerning the legal status of a territory nor any approval or acceptance of these borders.

Page 31: Ethiopia - Alemgena - Butajira Road Project Completion Report

Annex 1 (Page 2 of 2) ALEMGENA-BUTAJIRA ROAD UPGRADING PROJECT: PROJ ECT COM PLETION REPORT

PROJECT LOCATION MAP

This map was provided by the African Development Bank exclusively for the use of the readers of the report to which it is attached. The names used and the borders shown do not imply on the part of the Bank and its members any judgment concerning the legal status of a territory nor any approval or acceptance of these borders.

Page 32: Ethiopia - Alemgena - Butajira Road Project Completion Report

Annex 2

Ethiopia: Alemgena-Butajira Road Upgrading Project – Project Completion Report (PCR)

H D M - 4 Economic Indicators Summary

HIGHWAY DEVELOPMENT & MANAGEMENT

Study Name: Alemgena - Butajira Upgrading Project

Run Date: 25-04-2007

Currency: Ethiopian Birr (millions)

Discount Rate: 10.00%.

Alternative

Present Value of

Total Agency Costs (RAC)

Present Value of Agency Capital Costs (CAP )

Increase in Agency

Capital Costs ( C)

Decrease in User Costs

( B)

Net Exogenous

Benefits ( E)

Net Present Value (NPV = B + E - C)

NPV/Cost Ratio

(NPV/RAC)

NPV/Cost Ratio

(NPV/CAP)

Internal Rate of Return (IRR)

Base Case 16.164 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 With Project DBST 218.759 213.271 202.595 617.218 0.000 414.623 1.895 1.944 22.4 (1) 1. Figure in brackets is number of IRR solutions in range -90 to +900

HDM-4 Version 1.2

Page 33: Ethiopia - Alemgena - Butajira Road Project Completion Report

Annex 3

Ethiopia: Alemgena-Butajira Road Upgrading Project – Project Completion Report (PCR) Economic Cost-Benefit Analysis (Comparison of “With” and “Without” Project Situations)

(ETB Million – At 2005 Price Level) Increase in Road Agency Costs Savings in Road User Costs

Normal+Diverted Year Capital Recurrent Special

MT VOC MT Time NMT

Accidents Net

Exogenous Benefits

Net Benefits

2001 40.627 -0.780 0.000 -4.126 -0.168 0.000 0.000 0.000 -44.140 2002 39.316 -0.794 0.000 -13.636 -0.521 0.000 0.000 0.000 -52.679 2003 79.943 -0.922 0.000 -15.657 -0.575 0.000 0.000 0.000 -95.253 2004 58.538 -0.933 0.000 -17.269 -0.659 0.000 0.000 0.000 -75.533 2005 0.000 -1.036 0.000 55.138 1.539 0.000 0.000 0.000 57.714 2006 0.000 -1.075 0.000 59.702 1.665 0.000 0.000 0.000 62.441 2007 38.144 -1.572 0.000 64.840 1.802 0.000 0.000 0.000 30.070 2008 0.000 -0.886 0.000 72.089 1.952 0.000 0.000 0.000 74.928 2009 0.000 -0.933 0.000 78.564 2.111 0.000 0.000 0.000 81.609 2010 0.000 -0.984 0.000 85.588 2.282 0.000 0.000 0.000 88.853 2011 0.000 -1.038 0.000 93.199 2.466 0.000 0.000 0.000 96.702 2012 0.000 -1.095 0.000 101.409 2.663 0.000 0.000 0.000 105.168 2013 0.000 -1.157 0.000 110.260 2.874 0.000 0.000 0.000 114.292 2014 0.000 -1.224 0.000 119.812 3.099 0.000 0.000 0.000 124.134 2015 0.000 -1.271 0.000 126.990 3.259 0.000 0.000 0.000 131.520 2016 20.469 -1.321 0.000 134.499 3.425 0.000 0.000 0.000 118.775 2017 0.000 -1.373 0.000 142.406 3.600 0.000 0.000 0.000 147.379 2018 0.000 -1.427 0.000 150.778 3.781 0.000 0.000 0.000 155.986 2019 0.527 -1.484 0.000 159.463 3.972 0.000 0.000 0.000 164.393 2020 0.000 -1.544 0.000 168.455 4.168 0.000 0.000 0.000 174.167 2021 0.000 -1.607 0.000 177.765 4.375 0.000 0.000 0.000 183.748 2022 20.469 -1.674 0.000 187.218 4.589 0.000 0.000 0.000 173.011 2023 0.000 -1.743 0.000 197.167 4.813 0.000 0.000 0.000 203.723 2024 -21.842 -1.816 0.000 208.338 5.047 0.000 0.000 0.000 237.043

Economic Internal Rate of Return (EIRR) = 22.4%

Page 34: Ethiopia - Alemgena - Butajira Road Project Completion Report

ANNEX 4

Page 1 of 4

GOVERNMENT OF ETHIOPIA ALEMGENA-BUTAJIRA ROAD UPGRADING PROJECT

PROJECT COMPLETION REPORT Performance Rating Scale and Evaluation Criteria 1. Rating Scale

X > 3 Highly satisfactory

2 < X < 3 Satisfactory

1 < X < 2 Unsatisfactory

X < 1 Highly unsatisfactory

Where X is the value assigned to a performance variable. Classification: Implementation performance is considered satisfactory if the average value of X is > 2. 2. Evaluation Results

Component Indicators Score(1-4)

Remarks

1. Adherence to time schedule 1 Upgrading of 120 km completed 28 months behind the appraisal schedule.

2. Adherence to cost schedule 3 Despite implementation slippage and modifications to the original design during the construction phase, the actual cost at project completion was 10.6% less than the appraisal estimate.

3. Compliance with covenants 2 Delay of 12 months in fulfilling the conditions precedent to first disbursement.

4. Adequacy of monitoring & evaluation and Reporting

3 All Reports submitted on time.

5. Satisfactory Operations (if applicable)

3 VOC, travel time and transport tariffs decreased.

TOTAL 12 Overall Assessment of Implementation Performance

2.4

Satisfactory

Page 35: Ethiopia - Alemgena - Butajira Road Project Completion Report

ANNEX 4 Page 2 of 4

GOVERNMENT OF ETHIOPIA ALEMGENA-BUTAJIRA ROAD UPGRADING PROJECT

PROJECT COMPLETION REPORT

FORM BP 1

BANK PERFORMANCE

Component Indicators

Score

(1 to 4)

Remarks

1. At Identification 3 The project was a component of the RSDP-I of the GOE. The related studies were financed under a Japanese Grant in 1997.

2. At Preparation/Appraisal 2 The project costs were backed by detailed design. 3. At supervision 3 Most of the problems were resolved in time and adequate

measures taken. Overall assessment of Bank Performance

2.67 Satisfactory

Page 36: Ethiopia - Alemgena - Butajira Road Project Completion Report

ANNEX 4 Page 3 of 4

GOVERNMENT OF ETHIOPIA ALEMGENA-BUTAJIRA ROAD UPGRADING PROJECT

PROJECT COMPLETION REPORT FORM PO 1

PROJECT OUTCOME

No.

Component Indicators

Score (1 to 4)

Remarks

1 Relevance and Achievement of Objectives

i) Macro-economic policy 3

A comprehensive macro-economic policy is in place.

ii) Sector Policy 3 Integrated transport sector policy is in place.

iii) Physical (incl. Production) 2 120 km upgraded to bitumen standard road as planned at appraisal.

iv) Financial 3 Counterpart funds paid on time.

v) Poverty alleviation, social & gender

3 Additional employment opportunities created for rural poor including women.

vi) Environment 2 Better drainage and reduction in soil erosion.

vii) Private sector development 2 Private sector investment and small/petty trade increased along the road corridor.

viii) Other (Specify) 2 Institutional Development (ID) i) Institutional framework incl.

Restructuring 3 Created Road Fund and Ethiopian Roads Authority.

ii) Financial and Management Information Systems including Audit Systems

3 FMIS is in place and audit reports were submitted on schedule.

iii) Transfer of Technology iv)

Staffing by qualified persons (incl. Turnover), training & counter-part staff

2 ERA is losing qualified staff to the private sector which is not entirely adverse as the expertise is within the country.

Page 37: Ethiopia - Alemgena - Butajira Road Project Completion Report

Annex 4 Page 4 of 4

GOVERNMENT OF ETHIOPIA

ALEMGENA-BUTAJIRA ROAD UPGRADING PROJECT PROJECT COMPLETION REPORT

FORM PO 1 PROJECT OUTCOME

3

Sustainability

Score

Remarks

i)

Continued Borrower Commitment

3

Borrower has shown commitment to road maintenance by establishing a dedicated Road Fund.

ii)

Environmental Policy

3

A comprehensive environmental policy in place.

iii)

Institutional Framework

iv)

Technical Viability and Staffing 3 Provision for training of staff to higher university degrees through donor financed programs.

v)

Financial viability including cost recovery systems

3

An effective cost recovery system is in place in the form of fuel levy, etc which is transferred to Road Fund for road maintenance and development activities.

vi)

Economic Viability 3 The project had an EIRR of 22.1% at appraisal.

vii)

Environnemental Viability 3 All the environmental mitigation measures undertaken, as recommended.

viii) O&M facilitation (availability of recurrent funding, foreign exchange, spare parts, workshop facilities etc.)

4

Economic Internal Rate of Return 3 Indicates viable rate of return of 22.4% at PCR>10% (cost of capital)

TOTAL 47

Overall Assessment of the Outcome

2.76 Satisfactory

Page 38: Ethiopia - Alemgena - Butajira Road Project Completion Report

ANNEX 5

ALEMGENA-BUTAJIRA ROAD UPGRADING PROJECT: PROJECT COMPLETION REPORT RECOMMENDATIONS AND FOLLOW-UP MATRIX

Main Findings & Conclusions Lessons Learned/ Recommendations Follow-up Actions Responsibility Formulation & Project Rationale: The project was a component of the RSDP-I of the GOE. The related pre-feasibility study was financed by the GOE 1996 and the feasibility and detailed design studies were financed in 1997 under a Japanese grant.

In spite of detailed design study completed in December 1997, modifications to the original design were made during the construction phase, which indicates that the project components were not fully identified and the detail design was not properly reviewed before approval by ERA. This could be due to the lack of required capability within ERA and points to need to strengthen ERA with design review capability either by training the existing engineers or recruiting engineers with required skills.

The ERA and the donor partners have recognized the problem. To address this aspect the on-going TA programs financed by the World Bank and ADB are providing extensive on-the-job training in ERA, among other things, in contract administration, design review, project planning and procurement.

GOE/ADB/other Donors

Project Implementation: 1. Time overrun mainly due to procurement delays and modifications to the original design during construction.

GOE should ensure that project components are fully identified and the designs thoroughly reviewed and updated prior to project appraisal. On the Bank’s part, it should ensure review and update of designs and cost estimates.

Such actions at the time of project appraisal would, to a large extent, ensure timely project completion within the budget.

GOE / ADB

Compliance with Loan Conditions & Covenants: 1. All the loan conditions fulfilled and reports submitted.

--------

----------

----------

Performance Evaluation & Project Outcome: The overall project performance rating was satisfactory and the project objective was achieved.

For effective and efficient implementation of projects, adequate care should be taken at the time of project preparation and appraisal to ensure that the project components are identified in full and the designs reviewed.

GOE should endeavor to follow the recommendations for implementation of future projects.

GOE

Sustainability: There is a risk that due to the limited capacity of the domestic construction industry, routine and periodic may not be adequately implemented.

GOE is to expedite the implementation of DMO Capacity Building Project to provide requisite capacity to the local construction industry for undertaking the planned road maintenance works.

GOE to assess, on a regular basis, the capacity requirements of the local construction industry and initiate appropriate programs to enhance its capacity so that the road maintenance program is not hindered.

GOE

Page 39: Ethiopia - Alemgena - Butajira Road Project Completion Report

ANNEX 6

GOVERNMENT OF ETHIOPIA ALEMGENA-BUTAJIRA ROAD UPGRADING PROJECT

PROJECT COMPLETION REPORT

SOURCES OF INFORMATION

1. Borrower's Project Completion Report on Alemgena-Butajira Road Upgrading Project (September 2005), Ethiopian Roads Authority, (The Borrower's PCR is on the file with OINF.2)

2. Engineer’s Final Completion Report, ICT (India), 2005

3. Appraisal Report on Alemgena-Butajira Road Upgrading Project May 1998. 4. Monthly and Quarterly Progress Reports 5. Project Audit Reports

6. Civil Works Contract Document, ERA 7. Consultants Services Contract, ERA 8. Project Files.

9. Five Roads Feasibility Study, 1997

10. Road Sector Development Programme II (RSDP II) 11. Overview of the Road Safety Activities in Ethiopia

12. Base Line Survey and Monitoring Indicators for Poverty Impact Evaluation, Final Report (April 2005)