etron technology, inc....1 etron technology, inc. since 1991 month day, 2017 presented to etron...
TRANSCRIPT
1
Etron Technology, Inc. Since 1991
Month Day, 2017
Presented to
Etron Quality System Introduction and Automotive Quality Support
by
Quality Service & Customer Satisfaction Management Div.
2
This following presentation contains forward-looking
statements, which involve known and unknown risks and
are subject to uncertainties that could cause actual
performance, financial results, or operation conditions to
be materially different from those contained in the forward-
looking statements.
Except as required by law, we undertake no obligation to
update any forward-looking statement, whether as result of
new information, future events, or otherwise.
Safe Harbor Notice
Outline
◼ Etron Quality Management System
– Quality Management System
– Quality Control System
– Subcon. Management System
◼ Automotive-Grade Quality Management
3
Outline
◼ Etron Quality Management System
– Quality Management System
– Quality Control System
– Subcon. Management System
◼ Automotive-Grade Quality Management
4
Quality Management System
◼ Quality Policy– With a customer-oriented approach, all Etron employees
strive to provide premium products and services on time,
to continuously improve quality, and to achieve full
customer satisfaction
◼ Objectives / Plan– Define and deploy quantitative yearly KPI / PI goals with
quarterly management review for continuous improvement
5
Quality / Reliability Organization
CEO Nicky Lu
President Elvis Deng
RD Center
B.D. Rong, Sr. VP
Quality Service
Mgt. Dept.
Mickey Chen
Product & Quality
Assurance Center
Mickey Ken, VP
Quality / Environment
Mgt. Representative
Mickey Ken, VP
QS & CSM Div.
Lennon Chang
Package RE Dept.
J.M. Lin
Product RE Dept.
T.H. Chen
QC: Quality Control
SQE: Subcon. Quality Eng.
PKE: Package Eng.
RE: Reliability Eng.
Assy.: Assembly
QE Div.
Mickey Ken (Act.)
Subcon. Quality
Mgt. Dept.
Y.J. Lee
SQE
Sec. I
SQE
Sec. II
Customer Sat.
Mgt. Dept.
Lennon Chang
QC
Sec.
PKE
Sec.
Assy.
RE Sec.
6
Management System Certification◼ Etron quality and environment management system is
ISO9001/ IATF16949/ ISO14001/ OHSAS18001 certified
Certification Time 3rd Party Certifier
ISO-9001:1994
ISO-9001:2000
ISO-9001:2008
ISO-9001:2015
Oct. 1998
Nov. 2001
Nov. 2002
Sep. 2009
Jul. 2018
|
Jul. 2021
KEMA
KEMA
UL DQS
UL DQS
ISO-14001:2004
ISO-14001:2015
Nov. 2005
May 2017
|
May 2020
UL DQS
UL DQS
OHSAS-18001:2007 Jun. 2008
|
May 2020
UL DQS
ISO/TS-16949:2002
ISO/TS-16949:2009
IATF-16949:2016
Sep. 2009
Jul. 2010
Jul. 2018
|
Jul. 2021
UL DQS
UL DQS
UL DQSP7
Quality Systems: Searching for Excellence
- ISO9001 QMS
- Intel SSQA_Lite Supplier
1998 ~2004- ISO14001 EMS
- OHSAS18001
- Green Certificates
- Electronic Industry
Code of Conduct
(EICC)
2004 ~ 2008- TS16949:
Qualification in
2009
- Total Quality
Management (TQM)
- Continuous
Improvement
Program (CIP)
2009 ~2011
2012 ~ Now
- QCC Excellent Award
- Ishikawa Quality Award
SSQA: Standardized Supplier Quality Assessment
TS16949: Quality management system for Automotive
8
Document Control (PDM System)
On-line group signoff
in parallel
Daily summary notices
for new releases
On-line application and review for
extra-privilege of view / hard copy
On-line contract review
On-line establish/
change/void
On-line check for
signoff status
On-line view with security
level & protection Automatic distribute
production doc. to subcon.
9
Change Control Management
◼ Change Control Board (CCB) is the mechanism for
all engineering change review, approval and
implementation
◼ Necessary CCB members:
– Quality Assurance Division Head (host)
– The host determine the members according to the change
requirement
◼ Change classification are clearly defined and
documented. Will follow customer’s special
requirement if any
Ref. Doc. : Change Control Work Instruction (A10400109)
10
Internal Audit System
◼ Internal audit will be conducted at least once a year
◼ All internal auditors have been trained and certified
◼ Auditor will not self-audit their own works
◼ Internal audit results will be the input of Mgt. review meetingTechnical Document & Quality Audit Section
Technical Document & Quality Audit Section
Management RepresentativeManagement
RepresentativeAudit TeamAudit Team AuditeesAuditees
Establish the annual
audit planApprove
Establish the detailed audit schedule
Audit
Issue the nonconformity
reports
Take corrective actions
Follow up & issue audit
summary reports
Analyze audit resultsApprove & report to
management review
Technical Document & Quality Audit Section
Quality system Management
Audit TeamAudit Team AuditeesAuditees
Establish the annual
audit planApprove
Establish the detailed audit schedule
Audit
Issue the nonconformity
reports
Take corrective actions
Follow up & issue audit
summary reports
Analyze audit resultsApprove & report to
management review
11
Outline
◼ Etron Quality Management System
– Quality Management System
– Quality Control System
– Subcon. Management System
◼ Automotive-Grade Quality Management
12
Generic Production Flow (Discrete IC)
CP: Circuit Probing
FT: Final Test
PLBI: Package Level Burn-In
: QC Gating
Wafer In CP2WLBI
PLBI FT2
Marking * Lead / Ball Scan
E-Test
Baking Dry Pack
Warehouse Shipping
Assembly
Redundancy
Replacement
FT1
CP1 *CP0 *
* : Optional
13
Generic QC Engineering Chart for Discrete IC Product (#1/3)
Flow ProcessSampling
Freq.Sampling Plan Criteria Reference Record Site
1 Wafer FAB Every LotIn-line (Thin Film, Photo, Etch,
Diffusion)FAB In-line spec
Abnormal handling
procedureFAB e-Runcard FAB
8 inch: Wafer appearance: inspect
1/5 pcs & 5 sites/pc,5 dies /site
12 inch: Wafer appearance: inspect
1/5 pcs & 9 sites/pc, 9 dies /site
3 Wafer FAB Every MonthIn-line (Thin Film, Photo, Etch,
Diffusion), WAT SPCCpk >= 1.67 A10300111 (Wafer SPC) Cpk Report FAB
4 IQC Every Lot WAT data for all wafersWAT Data OOS < 3
Sites / per-wafer
A10300106 (WAT Review
and Trace)
Inspection
RecordEtron
5 Warehouse Every Lot 100%No product & quantity
error
A10400252 (Handling,
Storage Procedure)
Wafer into stock
sheetEtron
8 inch: Wafer appearance: inspect
1/5 pcs & 5 sites/pc,5 dies /site.
12 inch: Wafer appearance: inspect
1/5 pcs & 9 sites/pc, 9 dies /site.
7 WLBI Every Lot 100% Performance Production Flow CP Run Card Subcon
8CP0
(Optional)Every Lot 100% Performance Production Flow CP Run Card Subcon
9 WLBI+CP1 Every Lot 100% Performance Production Flow CP Run Card Subcon
10Redundancy
replacementEvery Lot
Replace weaknesses detected by
CP1Performance Production Flow CP Run Card Subcon
6 IPQC Every LotWafer defect sites
<3/pc
FAB
A10400244 (Wafer Visual
Inspection Spec)
Inspection
RecordSubcon
Wafer FAB Every Lot2Wafer inspection
criteria
A10400244 (Wafer Visual
Inspection Spec)FAB e-Runcard
14
Generic QC Engineering Chart for Discrete IC Product (#2/3)
Flow ProcessSampling
Freq.Sampling Plan Criteria Reference Record Site
11 CP2 Every Lot 1 wafer Performance Production Flow CP Run Card Subcon
8 inch: Wafer appearance: inspect
1/5 pcs & 5 sites/pc,5 dies /site.
12 inch: Wafer appearance: inspect
1/5 pcs & 9 sites/pc, 9 dies /site.
13Generate
Wafer MapsEvery Lot 100% No Missing Production Flow Wafer Map Subcon
14Packing /
WarehouseEvery Lot 100%
No packing error
allowed
A10400249 (Wafer
Packing spec.)
Wafer into stock
sheet
Subcon /
Etron
8 inch: Wafer appearance: inspect
1/5 pcs & 5 sites/pc,5 dies /site.
12 inch: Wafer appearance:inspect
1/5 pcs & 9 sites/pc, 9 dies /site.
16 Assembly Every Month
SPC reviews for Key parameter
such as Wire pull, Ball shear and
Mold Temp.
Cpk >= 1.67A10400257 (Assembly
SPC Review Spec.)
Cpk monthly
reportSubcon
17 IPQC Every Lot
MIL-STD-105E,
Normal/Single/General/ Level-II,
AQL=0.1%
Package visual
inspection criteria
A10400208 (IC Visual
Inspection Spec),
A10400246 (Subcon
Marking Requirement
Inspection
RecordSubcon
18 PLBI Every Lot 100% Performance Production Flow FT Run Card Subcon
19 FT1 Every Lot 100% Performance Production Flow FT Run Card Subcon
20 FT2 Every Lot 100% Performance Production Flow FT Run Card Subcon
12 IPQC Every LotWafer inspection
criteria
15 IPQC Every LotWafer inspection
criteria
CP Run Card Subcon
A10400244 (Wafer Visual
Inspection Spec)
Inspection
RecordSubcon
A10400244 (Wafer Visual
Inspection Spec)
15
Remark: The above flow is the Etron generic QC operation flow. The actual flow might be
different by product and need to refer to the corresponding production flow.
Generic QC Engineering Chart for Discrete IC Product (#3/3)
Flow ProcessSampling
Freq.Sampling Plan Criteria Reference Record Site
21 E-Test Every Lot
MIL-STD-105E,
Normal/Single/ General/Level-II,
AQL= 0.065%
No Bin swap allowed
A10400219 (In-process
Inspection Procedure),
A10400215 (E-Test
Inspection Spec.)
FT Run Card Subcon
22Lead / Ball
ScanEvery Lot 100%
No visual inspection
defect
A10400247 (Lead-Scan,
Tape-and-Reel Operation
Spec.)
FT Run Card Subcon
23Baking /Dry
PackingEvery Lot 100% No packing defect
A10400217 (Packing
Operation Spec.)FT Run Card Subcon
24 FQC Every Lot
MIL-STD-105E,
Normal/Single/General/Level-II,
AQL=0.1%;
By sampling plan; No
D/P, T&R or mark
permanency defect
allowed
A10400221 (Final
Inspection Procedure),
A10400208 (IC Visual
Inspection Spec.),
A10400217 (Packing
Operation Spec.)
Inspection
Record
Subcon /
Etron
25Warehouse
PreparationEvery Batch 100%
No product & quantity
error
A10400252 (Handling,
Storage Procedure)Shipping Notice Etron
26 OQC Every Batch
1. 100% inspect all residual parts.
2. Inspecting listed customer
special packing / labeling requests.
No defect allowed
A10400221 (Final
InspectionProcedure)
,A10400208 (IC Visual
Inspection Spec.),
A10400217 (Packing
Operation Spec.)
QC-10 (IC
Shipping
Inspection
Record)
Etron
16
Abnormal Handling FlowANF Issuer Lot Disposition Owner Issue Owner ANF Close
ANF: Abnormal Notice Form PC: Production Control
PUR: Purchasing MRB: Material Review Board
ANF S/N rule:
-- By Etron: #Exxxxxxx
-- By Subcon: #Sxxxxxxx
1. Issue ANF on
Etron sys.
2. Sys. inform PC
1. Issue verification
2. Lot disposition
3. Containment
1. Root cause
2. Corrective action
3. Preventive action
Need
8D report*
?
1. Release after
disposition
2. Sys. inform PC
Need
Compensation
?
PUR request for
compensation
QC
approval
Top mgr
approval
Y
Y
QC
approval
Cross-team co-sign
For lot disposition
verification
* 8D report request: 1. Customer complain due to production mis-operation
(Doc. #A10400404) 2. Production mis-operation induced product yield loss
3. Major or repeating operation problems impacting product quality or reliability
4. Operation/Process problems impacting Automotive/ Industrial/ Pachinko product or reliability
Meet
shipping criteria
?
Y
Stop shipping
N
Notify
customer
for MRB
approval
Hold MRB meeting
17
Product Identification and Traceability◼ Product Identification:
– All Etron parts are manufactured and controlled by lot, with lot ID
printed on IC top mark or chip ID for identification
◼ Traceability: – Forward: Notify customers proactively if confirmed any defect parts
shipped to minimize customer impact
– Backward: All production records are traceable by lot, with IT
supporting systems, to facilitate quick containment actions
– Manufacturing Execution System (MES) for WIP tracking / status control
– Electronic Data System (EDS) for real-time test data collection / analysis
– Oracle Enterprise Resource Planning (ERP) for lot management
– Warehouse Automatic Storage / Retrieval System (AS/RS) for lot control
– Data Retention: Production records will be preserved at least for 5
years, 15 years in electronic form with periodic backup
18
Outline
◼ Etron Quality Management System
– Quality Management System
– Quality Control System
– Subcon. Management System
◼ Automotive-Grade Quality Management
19
Subcon. Management System◼ Structure:
New subcon
qual. for AVL
15%PUR / PCService (Price)
30%PCProduction Logistic
15%EngineeringTechnical Capability
40%QAQuality System
WeightingOwnerEvaluation Items
15%PUR / PCService (Price)
30%PCProduction Logistic
15%EngineeringTechnical Capability
40%QAQuality System
WeightingOwnerEvaluation Items
• Qualified for AVL:
Total Score ≥ 60,
with each item score
≥ 60% of its
weighting
WeightingOwnerWeightingOwner
Engr. team
PC
PUR
QA
Back-end
35%
15%
15%
35%
25%PURDelivery
30%PURCost
15%DEEngineering
30%QAQuality
Front-endEvaluation
Items WeightingOwnerWeightingOwner
Engr. team
PC
PUR
QA
Back-end
35%
15%
15%
35%
25%PURDelivery
30%PURCost
15%DEEngineering
30%QAQuality
Front-endEvaluation
Items
Subcon monthly
QCDE performance
appraisal
• Improvement
actions will be
required if any
non-compliance.
Total Score ≤ 60
will be disqualified.
PC: Production Control PUR: Purchasing DE: Device Eng.
QCDE: Quality, Cost, Delivery, Engineering Service
20
Subcon. Quality Audit
◼ Subcon. Quality Audits
– Yearly subcon. quality system and operation audit
– QA on-site quality check timing:
– Yearly quality audit
– Non-periodic line audit for quality event
– WIP product operation line-check
– Audit key items checklists available
◼ Audit Corrective Action Follow-up
– Improvement progress will be followed up closely in
monthly review meeting for effective closure
– Confirm implementation in next on-site audit
21
Fab. Management Review Activity
Activity Freq. Owner Content
Engineering
Review
Meeting
Weekly DE
QA
PUR
1. Yield, QA, WIP, FA cases … etc.
2. Focus on major failure modes for defect
reduction.
3. Notify any major baseline process quality issues
proactively and share containment & CA
experience.
Executive
Review
Meeting
Monthly QA
DE
1. Review FAB baseline failure mode and
continuous improvement actions.
2. In-line & WAT SPC review.
3. Key process outlier control review.
Quality Audit Yearly QA
DE
Review QA system implementation and conduct line
audits, including equipment maintenance, particle
control and abnormal handling activities.
DE: Device Eng. QA: Quality Assurance PUR: Purchasing
22
Subcon. Management Review Activity
Activity Freq. Owner Content
Periodic
Report
Weekly,
Monthly
QA 1. Review Etron IQC LRR, assembly yield, testing
yield / correlation, SPC, Cpk reports and trend
2. Abnormal event handling (impact, disposition, root
cause, improvement actions, status)
Quality
Meeting
Monthly QA
PC
Related
Eng. Team
1. Review assembly monthly Cpk, process capability,
MRB or major quality event tracking, OCAP,
reliability monitor results
2. Quality appraisal scorecard review
Quality Audit Yearly QA
Related
Eng. Team
1. Audit quality system implementation, line process
operations, reliability monitor, environmental, supply
chain management, restricted material control,
social duty
2. Previous audit action follow-up and verification
3. Non-periodic audit will be arranged for WIP monitor,
major quality event or customer issues
LRR: Lot Reject Rate MRB: Material Review Board OCAP: Out-of-Control Action Plan
23
Summary of Etron QMS
◼ Etron’s Quality Management System is ISO/TS-16949
(now IATF-16949) certified since Sep. 2009, to meet
the most stringent automotive industry expectation
and fulfill customer-specific requirements
◼ All Etron’s subcontractors for automotive are ISO/TS-
16949 (now IATF-16949) certified to provide top-
quality service throughout the supply chain
◼ Production Part Approval Process (PPAP) package
can be prepared for targeted products upon request
24
Etron PPAP Standard Format
25
Outline
◼ Etron Quality Management System
– Quality Management System
– Quality Control System
– Subcon. Management System
◼ Automotive-Grade Quality Management
26
◼Coverage on All Products: A Series of Tests Standardized In
AEC-Q100 and JEDEC Are Performed
– Assure better Quality & Reliability to meet the automotive
requirements and standards
◼ Etron Can Support Automotive Grade-2 & Grade-3 Products
AEC-Q100 Compliance Grade-2/3
Grade 3: -40°C to 85°C; Grade 2: -40°C to 105°C
No Check Item Test MethodJEDEC
Sample Size
AEC-Q100
Sample Size
Commercial
Level
Industrial
Level
Automotive
Grade 3/Grade 2
1 EFR JESD22-A108 JESD47 1000 ea 800 X 3 Lots 0°C&70°C -40°C&85°C -40°C&85°C/-40°C&105°C
2 HTOL JESD22-A108 JESD47 77 X 3 Lots 77 X 3 Lots 0°C&70°C -40°C&85°C -40°C&85°C/-40°C&105°C
3 HTST JESD22-A103 JESD47 75 ea 45 X 1 Lot 25°C 25°C&85°C 25°C&85°C/25°C&105°C
4 Pre-Con JESD22-A113 JESD47 300 ea 231 X 3 Lots 25°C 25°C&85°C 25°C&85°C/25°C&105°C
5 TCT JESD22-A104 JESD47 75 ea 77 x 3 Lots 25°C 25°C&85°C 25°C&85°C/25°C&105°C
6 PCT JESD22-A102 JESD47 75 ea 77 x 3 Lots 25°C 25°C&85°C 25°C&85°C/25°C&105°C
7 HAST JESD22-A110 JESD47 75 ea 77 x 3 Lots 25°C 25°C&85°C 25°C&85°C/25°C&105°C
8 TH JESD22-A101 JESD47 75 ea - 25°C 25°C&85°C -
9 Latch-up JESD78 JESD47 6 ea 6 x 1 Lot 25°C 25°C&85°C 25°C&85°C/25°C&105°C
10
ESD (HBM) JESD22-A114 JESD47 3 ea 3 x 1 Lot 25°C 25°C&85°C 25°C&85°C/25°C&105°C
ESD (MM) JESD22-A115 JESD47 3 ea 3 x 1 Lot 25°C 25°C&85°C 25°C&85°C/25°C&105°C
ESD (CDM) JESD22-C101 JESD47 3 ea 3 x 1 Lot 25°C 25°C&85°C 25°C&85°C/25°C&105°C
27
Commercial Automotive Remarks
Application TV, DVD, STB, Printer,
Panel, etc.
Car Electronics With different
product part number
Ta temperature 0~70 degree C -40~85 degree C (Grade 3)
-40~105 degree C (Grade 2)
With different
production flow,
wafer selection,
enhanced burn-in,
and testing
PPM Target < 200 ppm Target < 10 ppm
Reliability Standard &
Specification
JEDEC JEDEC
AEC-Q100
Spec Customization
Product Life 2~5 years 7~10 years
FA Priority Normal priority 24 hrs initial response
Top priority
Discussable by case
Comparison of Commercial/Automotive Grades
AEC-Q100: Quality test procedure developed by the AIAG (Automotive Industry Action Group) for IC
28
Product Level Qualification◼ Complete full product qualification before releasing for mass
production, by following AEC-Q100 and JEDEC standards
檢驗項目 檢驗條件 數量 批量 接受/退回 參考標準
Inspection
Item
Inspection
ConditionsQuantity Lot Accept/Reject
Reference
Standard
EFR >1.2*Vint, Ta=125°C 800 3Predict 0.5~1year
AECQ100-0081000DPM
OLT >1.1*Vint, Ta=125°C 77 31000H
JESD22-A10850FIT
ESD
≥±2KV (HBM)
R=1.5K-ohm, C=100pF3 1 0/1 AECQ100-002
≥±200V (MM)
R=0K-ohm, C=200pF3 1 0/1 AECQ100-003
≥±500V (CDM) 3 1 0/1 AECQ100-011
Latch-up
Vtr(+) ≥ 1.5xVcc
Vtr(-) <= -0.5xVcc
Itr(+) ≥ 100mA
Itr(-) <= -100mA
6 1 0/1 AECQ100-004
29
Note: PCT duration is 96H for BGA type product
檢驗項目 檢驗條件 數量 批量 接受 /退回 參考標準Inspection
Item
Inspection
ConditionsQuantity Lot Accept/Reject
Reference
Standard
HTST Ta=150°C, 1000hrs 45 1 0/1 JESD22-A103
Pre-condition Level III
Sum of
HAST, PCT
and TCT
3 0/1 JESD22-A113
HASTV=Vmax, Ta=130°C,
85%R.H., 2.3atm, 96Hrs77 3 0/1 JESD22-A110
PCTTa=121°C, 100%R.H.,
2.0atm, 168Hrs77 3 0/1 JESD22-A102
TCT-65°C ~ +150°C, 500Cycles
(air to air)77 3 0/1 JESD22-A104
Package Level Qualification◼ Complete full package qualification before releasing for mass
production, by following AEC-Q100 and JEDEC standards
30
◼ Product routine test after releasing for mass production, by following AEC-Q100 and JEDEC standards
Note: PCT duration is 96H for BGA type product
Routine monitor starts from the product shipment >150Kpcs/qtr
檢驗項目 檢驗條件 數量 批量 接受 /退回 參考標準Inspection
Item
Inspection
ConditionsQuantity Lot Accept/Reject
Reference
Standard
Predict 0.5~1year
1000DPM
1000H
50FIT
HTST Ta=150°C, 1000hrs 45 1 0/1 JESD22-A103
Pre-condition Level IIISum of HAST,
PCT and TCT3 0/1 JESD22-A113
HASTV=Vmax, Ta=130°C,
85%R.H., 2.3atm, 96Hrs77 3 0/1 JESD22-A110
PCTTa=121°C, 100%R.H.,
2.0atm, 168Hrs77 3 0/1 JESD22-A102
TCT-65°C ~ +150°C, 500Cycles
(air to air)77 3 0/1 JESD22-A104
AECQ100-008
OLT >1.1*Vint, Ta=125°C 77 3 JESD22-A108
EFR >1.2*Vint, Ta=125°C 800 3
Quarterly Product Reliability Monitor
31
Failure Analysis Flow
Customers Inform CE Issue FA Team Support CA Owner
Responsibility
Clarification
Claim Notice
Disposition /
Containment
Action (CA)
Contact Window,
FA Issue,
Assign Owner
Sample Return
(If needed)
Investigation /
Root Cause
Clarification
Impact review,
Notify Issuer
Notify CustomerConfirm
Implementation
Prod. Record
Tracking
& Review
Customer
Approves
for Case Closure
32
Product FA Flow Sample Return
External Inspection
& Re-Ball
Electrical Test
Go/NG Result
Good NG
PFA
(if applicable)
Define Failure
MechanismChar/Shmoo
Check
Notify CustomerEFA Report*
PFA Report
(if applicable)
Return Sample
Fail
Pass
EFA: Electrical Failure Analysis
PFA: Physical Failure Analysis
33
34
Etron 8D Report Outline
◼ Discipline 0: Plan for Solving Problem
◼ Discipline 1: Team Approach
◼ Discipline 2: Problem Description
◼ Discipline 3: Containment Action
◼ Discipline 4: Root Cause Analysis
◼ Discipline 5: Verification of Effectiveness
◼ Discipline 6: Permanent Corrective Action
◼ Discipline 7: Prevent Recurrence
◼ Discipline 8: Congratulate the Team
www.etron.com