EU: Project Billing and Change Management
Tamara Mekhantseva [email protected]
Senior Analyst, Projects module
![Page 2: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/2.jpg)
2/34
Timing
Day One
Monday June 24, 2019
Day Two
Tuesday June 25, 2019
• 9 AM -11 AM PT• 9 AM -11 AM PT
![Page 3: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/3.jpg)
3/34
Agenda
Project integration with General Ledger
Project billing: combined billing rule,
billing rates for time and material billing
Pro forma invoices, correction of a pro
forma invoice
Configuring project invoices, modifying
billing rules
Labor cost rates: project time tracking &
expenses
Credit memo workflow
Change management: change orders to
budget and commitments
Day 2Day 1
Project budget structure
![Page 4: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/4.jpg)
4/34
• All the attendees except for the training
instructor are muted
• If you have a question
▪ Raise your hand
▪ Write the question
to the chat
RingCentral Platform
![Page 5: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/5.jpg)
5/34
25 June 2019
Time (PDT) Content
9.00 AM – 10.40 AM Training session
10.40 AM – 11.00 AM Q&A, survey
![Page 6: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/6.jpg)
6/34
Session Rules
• All attendees must be in Mute mode
• Polling questions will be asked at random moments, without advance notice (CPE credits)
• If you have a question, enter it in Chat and click Raise Hand
• For each Lesson:▪ Discuss the scenario presented
▪ Highlight key points, terminology and best practices
▪ Each student performs the exercise individually:
▪ Open Acumatica instance by clicking the link that you have received from Acumatica Training team. Select the tenant name you’ve been provided with. Please raise hand in case you do not have a personal tenant.
• Final Exam (certification) through Acumatica University
• Please fill in the evaluation survey at the end of the session
• The session will be recorded and be posted on Acumatica Open University. Our Training team will provide you with the link after the session is published
![Page 7: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/7.jpg)
7/34
Project Accounting Intermediate: Day 2 learning objectives
At the end of the session you will:
▪ Know how to work with project change orders to the project budget and project
commitments
▪ Be able to enter time activities against a project
▪ Learn how to group billable items by different invoices
▪ Be able to process a credit memo against a project
![Page 8: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/8.jpg)
8
![Page 9: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/9.jpg)
9/34
Change Management
![Page 10: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/10.jpg)
10/34
Change Management: Configuration
CS100000 PM301000
![Page 11: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/11.jpg)
11/34
Change Management: Configuration
PM101000
PM203000
![Page 12: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/12.jpg)
12/34
Change Management: Change order entry
PM308000
PM301000
![Page 13: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/13.jpg)
13/34
Change Management: Change order status flow
![Page 14: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/14.jpg)
14/34
Change Management: Change order release and effect on project budget
Cost and Revenue Budget
• Budgeted CO Quantity = The total quantity of released change orders that updated the project
balance by the key.
• Budgeted CO Amount = The total amount of released change orders that updated the project
balance by the key.
• Revised Budgeted Quantity = Original Budgeted Quantity + Budgeted CO Quantity
• Revised Budgeted Amount = Original Budgeted Amount + Budgeted CO Amount
Revenue Budget only
• Pending Invoice Amount = Completed (%) * Revised Amount - Actual Amount - Draft
Invoices Amount
![Page 15: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/15.jpg)
15/34
Change Management: Change order release and effect on project commitments
Update / Reopen
• Order Qty. = previous Order Qty. + change order commitment line Quantity
• Open Quantity = Order Qty. - Qty. On Receipts
• Ext.Cost = previous Ext. Cost + change order commitment line Amount
• Open Amount = Ext.Cost - Received Amount
New Line
• Order Qty. = change order commitment line Quantity
• Ext.Cost = change order commitment line Amount
New Document
• Order Date = the earliest date of the grouped lines
• Description = ‘Change Order #’ + CO Reference Nbr.
• Requested Date of a line = Order Date of the change order
![Page 16: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/16.jpg)
16
![Page 17: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/17.jpg)
17/34
L6: Change Orders to Budget: Learning objectives
• Review the change management process in Acumatica 2019R1
• Configure and enter change orders to project budget
• Freeze project budget
• Process a change order altering project budget
![Page 18: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/18.jpg)
18
![Page 19: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/19.jpg)
19/34
L7: Change Orders to Commitments: Learning objectives
• Review project commitments
• Freeze project commitments
• Configure and enter change orders to project commitments
• Process a change order affecting project commitments
![Page 20: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/20.jpg)
20
![Page 21: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/21.jpg)
21/34
Labor Cost Rates
![Page 22: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/22.jpg)
22
![Page 23: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/23.jpg)
23/34
L8: Time Cards and Time Activities for Projects: Learning objectives
• Configure Acumatica ERP for time tracking
• Maintain time reporting for projects
• Set up labor cost rates
• Enter time activities and time cards for the project
• Approve and release time activities
![Page 24: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/24.jpg)
24
![Page 25: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/25.jpg)
25
![Page 26: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/26.jpg)
26/34
L9: Configuring Project Invoices: Learning objectives
• Create groups of invoices
• Group billable items by different parameter
• Bill project tasks separately
• Bill project tasks by different billing rules
![Page 27: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/27.jpg)
27
![Page 28: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/28.jpg)
28/34
L10: Modifying Billing Rules: Learning objectives
• Alter billing rules
• Regenerate pro forma invoices
![Page 29: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/29.jpg)
29
![Page 30: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/30.jpg)
30/34
L11: Credit Memo Workflow: Learning objectives
• Process project billing corrections with the help of credit memos
![Page 31: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/31.jpg)
31
![Page 32: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/32.jpg)
32/34
Share your feedback on the training
Please, fill out your survey!
https://www.surveymonkey.com/r/onlinesessions2019
![Page 33: EU: Project Billing and Change Management - Acumatica · 2019. 7. 1. · Project integration with General Ledger Project billing: combined billing rule, billing rates for time and](https://reader035.vdocuments.net/reader035/viewer/2022071600/613d0f3c84584d0a6f5b45fb/html5/thumbnails/33.jpg)
33/34
Resources
▪ More information on product, training, release announcements, newsletter subscription, webinars, etc.:
▪ https://portal.acumatica.com/
▪ Contact Acumatica Education Team: [email protected]
▪ Open access to training materials and videos: https://openuni.acumatica.com/
▪ Product ideas:http://feedback.acumatica.com/
▪ Technical blog: http://asiablog.acumatica.com/