Euclid Creek Tunnel

Community UpdateMarch 19, 2013

Page 2: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Agenda

• Project Overview• Construction Updates• Shaft Updates• Contact Info

Page 3: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Project Overview

Page 4: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Euclid Creek Tunnel: By the Numbers

• Tunnel– 24’ diameter– 7110/17,750’– 60,100,000 gallons

• ~30 near surface structures– 11 complete– 10 under construction

• Shafts: 5 total– 24’ to 60’ diameter– 185-225’ deep

• 2,440 linear feet of open cut pipe placed

• 2,110 linear feet of microtunnel complete– 240 more to go

Page 5: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Construction Updates

• New sewer, Lakeshore BoulevardEast 150th Street to (east of) Collinwood Rec.– Work completed: Sept 2013

• New sewer, St. Clair Ave. and Nottingham Rd.– Work completed: Oct 2013

Page 6: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Shaft #1Construction Staging Site

• “Mackenzie” tunneled and lined 7,125’• Operating 24/7 with regularly-scheduled

maintenance periods• Currently beneath Lake Erie

Page 7: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Project Overview2/19 3/19

2/19

Page 8: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Page 9: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Shaft #2Easterly Wastewater Treatment Plant

• Shaft 2: 80 feet excavated (30’ to rock)– Blasting last 100 feet; will begin this year

• Structure 2-2: installing final lining• Structure 2-8: installing support of excvation

Page 10: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Page 11: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

• Construction staging area– Sound wall installed along south side of

Ms. Gordon’s house– Secant pile wall installation… complete!

• Case (sub-contractor) de-mobilizing now

– Next steps?• McNally/Kiewit will deliver excavation equipment• 35’ depth

Shaft #3Beulah Park

Page 12: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

• East 156th Street• West side sidewalk still closed; replaced when feasible

Shaft #3Beulah Park

Page 13: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Shaft #3: Schedule*2013 2014

January February March April May June July Aug Sept Oct Nov Dec Jan Feb Mar April May June July AugShaft Support & Excvation Shaft Structural Work

Strs 3-2 & 3-3 (Btw Wadsworth & Gordon) Close E 156th Street Diversion Sructure E 156th Microtunneling Str 3-5 (Lakeshore & E 156th)

Non-Working HolidaysMemorial DayJuly 4thLabor DayThanksgiving DayChristmas DayNew Years Day

*Schedule subject to change

Page 14: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Shaft #3: Schedule

1/13–6/1310/13–12/131/14—8/14

4/14–8/14

4/13–3/14

8/13–11/134/13–3/14

Page 15: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Site #4Triangle Park

• Excavation work is complete at this site• Currently installing baffle drop structures• Fencing will remain throughout 2014• Completed structure in Nottingham

Page 16: Euclid creek tunnel ppt mar2013
Page 17: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Page 18: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Site #4Triangle Park

• Additional sewer installation planned– Transfer from Lakeshore Blvd. Relief Sewer to

Euclid Creek Tunnel– 66” trenchless sewer pipe, microtunneled from

Euclid Creek Pump Station to Shaft 4– $4.4 million savings, minimal impact

Page 19: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Site #5Nottingham & St. Clair

• Excavation complete of Shaft 5:225 feet excavated

• Commenced excavation of Structure 5-4

Page 20: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Page 21: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Stay Informed

• Blog– EuclidCreek.blogspot.com

• Collinwood Observer– Ads and articles

• Semi-Monthly Newsletter– E-mail distribution– [email protected] to be added to the list

Page 22: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

How to Reach Us

Social Mediafacebook.com/yoursewerdistrict@neorsd | @wallywaterdrop

Customer Service (216) 881-8247

Emergencies: NEORSD ECT Field Office(216) 268-5469

Ryan Sullivan, [email protected] Elting, [email protected]

Page 23: Euclid creek tunnel ppt mar2013

euclidcreek.blogspot.com

Next Meeting

Tuesday, April 16 (or 23), 20136:00 p.m.Cleveland Public Library,Memorial-Nottingham Branch

Save the Date!May 21 August 20June 18 September 17July 16 October 15

DateMay

Change!