europe - project controls · eva europe geneva 2009 geneva school of business administration haute...

14
eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EUROPE 2009 WAS JOINTLY ORGANISED BY PARTNERS GOLD SPONSORS © 2009, CERN, HEG, AUTHORS - THIS MATERIAL IS PROVIDED COURTESY OF EVA EUROPE 2009, THE EUROPEAN ORGANISATION FOR NUCLEAR RESEARCH(CERN), THE GENEVA SCHOOL OF BUSINESS ADMINISTRATION (HEG) AND THE AUTHORS. ALL RIGHTS RESERVED. THE CONTENTS MAY NOT BE REPRODUCED WITHOUT PERMISSION OF THE AUTHORS AND EVA EUROPE.

Upload: others

Post on 02-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

evaeuropeGENEVA 2009

Geneva School of Business Administration Haute école de gestion de Genève

EVA EuropE 2009 wAs jointly orgAnisEd by pArtnErsgold sponsors

© 2009, CErn, HEg, AutHors - tHis mAtEriAl is proVidEd CourtEsy of EVA EuropE 2009, tHE EuropEAn orgAnisAtion for nuClEAr rEsEArCH(CErn), tHE gEnEVA sCHool of businEss AdministrAtion (HEg) And tHE AutHors. All rigHts rEsErVEd. tHE ContEnts mAy not bE rEproduCEd witHout pErmission of tHE AutHors And EVA EuropE.

Page 2: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

Earned Value

Measurement

Earned Value ManagementFundamental PrinciplesOlivier Lazar, Msc., MBA, PMP

Page 3: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

Earned Value Measurement (EVM)Definition

“…Technique...integrates project Scope, Cost and Schedule measures to help the project management team

assess project performance.”PMBOK® Guide, 2008

Page 4: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

EVM History

EVM emerged as a financial analysis specialty in United States Government programs in the 1960s on DoD’s programs (Polaris missiles…)EVM was not limited to the DoD for long. It was quickly adopted by the National Aeronautics and Space Administrationalso received greater attention by publicly traded companies in response to the Sarbanes-Oxley Act of 2002

Page 5: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

EVM Objectives and Benefits

Going beyond 2 dimensional project assessment (Cost vs Allocated Budget) by integrating Technical Achievement monitoringExactly measure “What did we get for the money we spent?”Anticipate rather than ReactProvide Vision over the project from Now to CompletionEasy to use, to report and to analyze

Page 6: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

Earned Value Principles

EVM Measures:1. Planned effort (Planned Value – PV) – Baseline

Person-days estimated at current dateCumulative cash flow of project

2. Actual effort (Actual Cost – AC)Person-days expended at current dateIf measuring cost, use “committed” cost

3. Scope achievement (Earned Value – EV)Percent of work (scope/deliverables) accomplished

EVM Analyzes:Current status vs baseline (variance)Estimate to complete (Effort & Duration) (Baseline estimate x index – actual effort)Corrective actions (if needed)

Page 7: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

Earned Value Illustrated (S-Curve)C

ost

Time

Budget At Completion (BAC)Performance Measurement Baseline

Data Date

Planned Value (PV)

Actual Cost (AC)

Earned Value (EV) = BAC x Physical %

Cost Variance = EV - AC

Schedule Variance = EV - PV

Actual Time Variance

Estimate to Complete (ETC = BAC – EV)

Estimate At Completion (EAC = AC + ETC)

Performance Indexes:- SPI (Schedule): EV / PV- CPI (Cost): EV / AC

Page 8: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

Earned Value Calculations

1. Planned Value (PV) = [(BAC/Project Duration) x Elapsed time units]2. Actual Cost (AC)3. Earned Value (EV) = BAC x Physical % Complete4. Cost Variance (CV) = EV - AC5. Schedule Variance (SV) = EV - PV6. Cost Performance Index (CPI) = EV / AC7. Schedule Performance Index (SPI) = EV / PV8. Estimate at Completion (EAC) = AC+ETC9. Estimate to Compete (ETC) = BAC – EV10. To Complete Performance Index (TCPI) = (BAC-EV)/(EAC-AC)

Acronyms, see PMBOK® Guide

Page 9: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

What does these PI’ tell us?

Of course, about the current status… But… It’s too late anyway!

Highlight the trendsPredict deviationsEvaluate resources

About the Quality of the Project PlanIs the initial estimate accurate?Deviation can highlight a problem with the accuracy of the initial plan

• About how realistic is an objective…• The TCPI will tell you… when used with CPI…

Microsoft Excel Worksheet

Page 10: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

CV SV PROJECT STATUS

Over-achieving and underspending

No action needed (unless spending customers’ money is an issue!)

( + ) ( + )

Over-achieving, but overspent for the achievement

Money being wasted, e.g. unnecessary overtime?

( - ) ( + )

( + ) ( - )

Under-achieving on the project, but overachieving for the spend

Team performing well but under-resourced

( - ) ( - )

Under-achieving, and overspending for the achievement

Team under-resourced and under-performing

1

2

3

4

1 Cost

Time

Cost

Time

3

2 Cost

Time

4 Cost

Time

Interpretation and Analysis

PV: Budgeted CostAC: Actual CostEV: Earned Value

Page 11: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

Difficulties and Limitations

Consolidation issues:

If a consolidated indicator is green, get a look at the details. Some difficulties can be masked by over well-performing activities of workpackages.

So called « Support Activities » (1FTE, 100% rate, long term)

AC = PV, SPI and CPI correlated

Data’s time consistency (costs and % at same Data Date)

Lack of Planning (“Failing to Plan is Planning to Fail” Ika, 2006)Difficult to obtain a stable and consistent Baseline

Cultural Issues

Earned Value Management is NOT addressing Quality

Page 12: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

Progress Measurement

Progress measurement : difficulties to define a precise and accurate way of estimate the work performed

Existing ways of measurement:Physical % Complete (ex. 42.5% of task)Defined Steps (25/25/30/20)0/100Custom % Complete (n/y, ex. 20/80)Level of Effort (EV=PV) eg. Management tasks

Page 13: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

ReferencesISO/WD 21500, International Organization for Standardization, to be published. Project Management – Guide to Project Management.ISO 10600, International Organization for Standardization, 1997. Quality Management – Guidelines to Quality in Project Management.American National Standard Institute, 1998. ANSI/EIA 748 EVMS Standard.AACE, Association for Advancement of Cost Engineering, 1956 – 2002. Project Management Using Earned Value, Gary C. HumphreysHumphreys & Associates, 2002.PMI® , Project Management Institute, 2005. Practice Standard for Earned Value Management.PMI®, Project Management Institute, 1996-2008. A Guide to the Project Management Body of Knowledge.Sarbanes-Oxley Act, 2002.Office of the Secretary of Defense & National Aeronautics And Space Administration, 1962. DOD & NASA Guide PERT COST.

Page 14: europe - Project Controls · eva europe GENEVA 2009 Geneva School of Business Administration Haute école de gestion de Genève EVA EuropE 2009 wAs jointly orgAnisEd by gold sponsors

That’s all Folks!

Olivier [email protected]+41 78 936 00 62