evaluate plant-wide safety of your interlock system
TRANSCRIPT
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
1/14
GCPS 2013
__________________________________________________________________________
Evaluate Plant-Wide Safety Of Your Interlock SystemPrincipal Author: Mohammed Naved Khan
Ingenero Technologies India Pvt Ltd.
Mumbai, [email protected]
Presenter: Swapnil Pathak
Ingenero Technologies India Pvt Ltd.
Mumbai, [email protected]
Co-author: Jim Brigman
Ingenero Technologies Inc.
Houston, Texas, [email protected]
Prepared for Presentation at
American Institute of Chemical Engineers
2013 Spring Meeting
9th Global Congress on Process Safety
San Antonio, Texas
April 28 May 2, 2013
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
2/14
GCPS 2013
__________________________________________________________________________
UNPUBLISHED
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
3/14
GCPS 2013
__________________________________________________________________________
AIChE shall not be responsible for statements or opinions contained
in papers or printed in its publications
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
4/14
GCPS 2013
__________________________________________________________________________
Evaluate Plant-Wide Safety Of Your Interlock System
Principal Author: Mohammed Naved Khan
Ingenero Technologies India Pvt Ltd.
Mumbai, [email protected]
Presenter: Swapnil Pathak
Ingenero Technologies India Pvt Ltd.
Mumbai, [email protected]
Co-author: Jim Brigman
Ingenero Technologies Inc.
Houston, Texas, [email protected]
Keywords: IRM, interlock relationship, interlock-process interference, holistic, isolated
information, PHA, mitigation
Abstract
Interlocks serve as important safety systems in industrial settings, where they protect
equipment from damage and employees from toxic and harmful releases from that
equipment arising out of unsafe conditions. The same safety systems can lead to damage
of process systems, if not analyzed properly. In some of the cases we encountered,initiation of interlocks in equipment caused severe damage to other equipment (due to
change in composition) or initiation of interlock caused damage to the same equipment it
was intended to protect (due to incorrect sequencing of interlocks).
The information available with the interlock design documents (like cause and effect
diagrams) is limited to the vicinity of that particular interlock. It does not give any
information about the relationship of the interlock, under study, with other processequipment or even with other interlocks (except for initiation). The relationship betweensafety interlocks and process system arises out of the behavior of the process system (e.g.
change in composition) to the actions taken by the interlock. This paper proposes how a
holistic view for these behavioral responses can be obtained by developing the IRM(Interlock Relationship Matrix). IRM is a single process document (excluding
instrumentation and logic details) that provides information on the effects of all interlocks
on each element of process system. Developing IRM is crucial in evaluating the
interlock-process interference (behavioral responses) and is beneficial in managerial
decision making to assess the likely damage to equipment and provide mitigation thereof.
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
5/14
GCPS 2013
__________________________________________________________________________
1. IntroductionInterlocks form the most critical and independent layer of safety in industrial settings.They are primarily designed for:
Equipment - protect the equipment from damage due to unsafe conditions (eg.over speed) and the resulting economic loss arising out of replacement and
downtime.
Personnel - protect the personnel from exposure to harmful and toxic materialsthat may get released from equipment damage (e.g. Seal leaks from rotating
equipment).
Plant - maintain the integrity of the plant (e.g. flare mitigation methods employedto limit the flaring during global utility failures and avoid exposure of un-burnt
hydrocarbons to the general public).
The design intention of the approaches employed for interlock systems are two-fold; first
is the isolated view to protect the equipment at hand and second is the global view tomaintain integrity of the plant. Although the approach seems to be looking fair, they
(even the global interlock system) lack in considering the interlock-process systems
relationships in designing interlock systems.
The very definition of an independent protection layer provided by interlock systems
(whether a single or global interlock) has an inherent element of relationship between
interlock actions and the behavior of process systems i.e. the actions of the interlock
system are taken independent of the responses of process system. This relationship mayor may not be relevant as far as the functions of that particular interlock is concerned, butin no case it should cause upset in other process units that could jeopardize their integrity
and cause irreparable damage. In the following sections, we will look into some of the
incidences that lead to irrevocable equipment damage as a direct result of the interlock-
process interference and we will suggest an approach as to how a holistic view for these
behavioral responses of the process systems to interlock actions can be obtained for
effective mitigation. Also the major points of differences between global interlock
systems and holistic view of individual interlock systems will be highlighted.
2. Interlock Design InformationThe design of interlock systems starts with the development of interlock diagrams or
narratives. They provide key information as to the analysis and identification of scenarios
that can cause damage to particular equipment (initiating causes) and the actions that are
required to be taken for the protection of that equipment. They are of the following three
types:
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
6/14
GCPS 2013
__________________________________________________________________________
2.1 NarrativesNarratives provide descriptive statements for the various elements of the interlock
system. Narratives are a short description stating the primary function of the interlock,events that can lead to unsafe conditions (initiating causes) and finally actions required
by the interlock to mitigate these events. They are written in a simple but precise mannerwithout making use of detail identification tags.
2.2 Cause and Effect (C&E) DiagramC&E diagrams are the next level of detail information about the interlock. C&E diagrams
are presented in a tabular format, detailing the initiating causes and the actions taken in
the form of individual tag numbers, usually initiating causes are activation of suitable
switches due to unsafe conditions and corresponding actions taken (opening or closing a
valve). Actions taken are segregated for each initiating cause. They also provideinformation about time delays. C&E diagrams provide detail accounting of each element
of the interlock.
2.3 Logic and Ladder DiagramThe information provided in logic and ladder diagrams is specific to the instrumentationpart of interlock system. They provide the circuit diagrams of the relay logic hardware
used for the interlock system under consideration.
3. Limitations of Design InformationInterlock design information is limited to the vicinity of the particular interlock under
consideration. The actions taken (or required) are bound by the isolated view of the
equipment to be protected. They are limited in their ability to evaluate and analyze the
effect of actions taken by the interlock systems on other process systems.
The structure of the C&E and ladder-logic diagrams is incompatible with identifying and
analyzing such kind of relationships. Interlock narratives can incorporate this informationin a piece-meal fashion (similar to the way information is presented in a narrative - oneinterlock at a time), however the utility of such disintegrated information is questionable
due to the following facts
Language - The information presented in narratives is written in easy tounderstand language and hence lacks a structured and objective approach.
Lack of specific information - They are prepared usually at a stage where systemspecific detail information is not available and lot of re-work might be required to
make them consistent and compatible to receiving detail information.
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
7/14
GCPS 2013
__________________________________________________________________________
4. Need for Holistic ViewWe will discuss two incidences where interlock activation in an equipment led to severe
damage in the same or other equipment.
4.1 Incident one Activation of Interlock in Acetylene Hydrogenation Reactor ofEthylene Unit
Ethylene cracker unit was operating with an acetylene hydrogenation reactor locatedbetween fourth and fifth stages of cracked gas compressor after Deethanizer and before
the chilling train that produces tail gas (front end configuration). Tail gas, usually, is a
methane-rich stream that is used as fuel in cracking furnaces. Fuel gas system for
crackers also has backup from imported LPG to handle contingencies.
For this case, interlock was designed for shutting down, boxing up and depressurizingacetylene reactor to purge out reactive hydrocarbons from the catalyst bed and preventrunaway reactions that might cause a meltdown of the reactor. However, shutting down
the reactor also meant stopping of tail gas flow to furnaces. Thus LPG from backupsystem was lined up, which changed the calorific value of fuel to the furnaces. The
cracking furnace temperature controller was working without duty correction to account
for change in composition and, therefore, was sluggish in taking appropriate corrective
actions and closing the valves. This time gap led to increased heat input to the furnaces
which resulted in a spike in the tube metal temperatures of the coils and subsequent coil
damage. Thus to protect acetylene reactor, interlock actions lead to damage of cracking
furnace coils due to inappropriate handling of fuel gas composition change.
In this case, the behavioral response of process system to the actions of interlock was
change in fuel gas composition to the cracking furnaces. This information was not
apparently or directly visible from interlock design information.
4.2 Incident two - Activation of Total Shutdown interlock of Cracking furnace ofEthylene Unit
Cracking furnaces in Ethylene units usually have two levels of interlock shutdown in case
of upset, first is steam standby with isolation of hydrocarbon feed and operating the
firebox in hot condition and second is the total shutdown where firebox is cooled.
Usually, first interlock is designed for faster restart after a partial shutdown by sustaining
close to operating conditions inside the firebox and maintaining minimum inventory of
BFW in the steam drum. The second interlock is designed to maintain integrity of the
furnace and cool the firebox, which might be operating close to 1100 deg C, to a safe
condition. Both interlocks have different functional requirements and are designed in a
way so as to be independent of each other. However, from process point of view,
initiation of first interlock also provides the necessary time lag for controlled rate heatrelease from the firebox, by maintaining minimum firing, before the cooling down of the
firebox is initiated by total shutdown interlock.
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
8/14
GCPS 2013
__________________________________________________________________________
For the case under consideration, in order to maintain minimum BFW inventory for first
shutdown, the trigger was set at significantly low-level point. This resulted in activationof both interlocks with minimum time delay resulting in rapid cooling of firebox. The
coke layer deposited inside the coils has very different coefficient of expansion than coilmetallurgy leading to unequal contraction and subsequent mechanical failure of coils.
The incident gives the interlock interference or dependence that may be sometimes
necessary due to process behavior. Design information of both interlocks, when observed
in isolation, was sufficient to perform their designated tasks. However without a holistic
view of looking at them, integrity of the equipment was jeopardized.
With the above-discussed instances, it is evident that sole reliance on interlock design
information to provide the hindsight necessary to avoid damage to other equipment is
insufficient. It requires a holistic view, encompassing all individual interlock systems, tostudy the interlock-process relationship for each element of the process system to better
understand these relationships rather than piece-meal and isolated interlock designinformation.
One can argue that global interlock systems responsible for maintaining the integrity of
the entire plant can take care of these relationships. We think that such a system ispractically infeasible. The reasoning starts with the very definition of an interlock which
states that it is the actuation of the initiating causes that triggers the interlock responses
irrespective of the process. For global interlock systems to take care of interlock-process
relationships, all the elements of the process system must be allowed to trigger them
(along with the upsets in global utility networks).
Another approach could be to trigger specific interlock systems put in place to protect
these relationships. The practicality of such an interlock system is bound to fail becauseof two reasons. First the investment required in putting up these extra interlock systems
or triggers is huge as the permutations and combinations of initiating causes from all
process elements is gigantic. Second it can lead to loss of earnings and operationalprudence due to the higher cost of production for increased number of instances of
unsteady plant operation due to spurious activations.
5. IRMWe propose to develop IRM as a tool to give the necessary holistic view forunderstanding the interlock-process relationship. IRM is an acronym for InterlockRelationship Matrix. It is the final outcome of the study for evaluation of interlock
actions and is a single document that shows the effect of actions of each interlock
systems on all elements of the process system.
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
9/14
GCPS 2013
__________________________________________________________________________
It is prepared in a tabular format with interlock systems arranged in rows and process
system elements arranged in columns. A typical IRM is shown in Table 1 for referencelayout.
Table 1. Typical IRM Layout
Elements of Process
System
Element 1 Element 2 Element 3 Element 4 ...
Interlock Systems
Interlock 1
Interlock 2
Interlock 3
...
The effect of each interlock action is documented in the corresponding column for
process elements. For example, if the actions of Interlock 2 change the feed compositionof Element 3, then change in feed composition is typed in cell corresponding to
Interlock 2 and Element 3.
IRM should include only those effects of interlock actions that have the potential to causesignificant damage to process elements. This will avoid ambiguity and redundancy of
information. Populating IRM with all effects of interlock actions reduces the utility of thetool. Existing safeguards should also be considered for evaluating the potential damage to
the equipment. If damage is possible after considering existing safeguards, only then IRM
should be updated with the relevant effect. For earlier example, it can be analyzed
whether change in feed composition can cause damage to the equipment if it is not
corrected (by the absence of density or composition meter) for changed composition.
However, reference of existing safeguards, for effects that have potential for damage, can
be made in IRM to ensure and document that the analysis of the interlock actions has
been conducted.
6. Why IRMThere are generic approaches available for evaluating hazards for process system. They
can be studied under two categories: Software Evaluation and PHA.
6.1 Software evaluation techniquesThese techniques include Software Systems Hazards Analysis like Fault/Event TreeAnalysis, Failure Mode and Effects Analysis, Software Failure Mode, Effects, and
Criticality Analysis, etc. They are deemed to analyze and identify whether software
system components' operation or failure (functioning or lack of functionality) could result
in hazards for process systems. It begins when the components are designed sufficiently,
and is updated as their design matures to take care of the potential hazards.
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
10/14
GCPS 2013
__________________________________________________________________________
Functional difference between these analyses and IRM is that they are more concerned
with the effects of software (interlock) systems on process elements in case the softwaregoes rogue and malfunctions (lack of functionality). Moreover, the analysis of
components' operation (functionality) on process systems is unable to understandinterlock-process relationship as it is concerned only for segregating and avoiding
intermixing interlock (safety actions) and process (control actions) systems.
Whereas, in the case of IRM, it analyzes the effects of interlock actions on process
element considering that software (interlock) system has fulfilled its functionality and
there is no sharing of functions from either side. It is not intended to find any design fault
in software (interlock) systems but to evaluate and understand the probable responses of
process system to software (interlock) system actions.
6.2 PHA
PHA techniques include operational and process hazards analysis like HAZOP, LOPA,
HAZAN, etc. These techniques use guidewords in combination with process parametersto evaluate deviation scenarios from normal operation and verify the utility of existing
safeguards. If the existing safeguards are not sufficient, new safeguards are suggested.
Safeguards can include interlocks, process control, alarms, relief valves, operating
procedures, etc.
Key difference between PHA and IRM is that PHA considers only the process parameters
as the potential causes for deviation and subsequent consequences. To mitigate such
consequences, PHA provides the scope for defining actions required by a safety system.
However, it does not evaluate the actions of a safety system like an interlock as probablecauses of deviation.
IRM fills this gap of analyses of actions of an interlock as potential causes of deviationfor the process elements and gives insight to unearth latent harmful events of interlock
actions.
7. Developing IRMIRM can be developed in a structured way such that the aftereffects of interlock actions
can be analyzed under the considerations of core parameters critical to the industrial
setting. This approach will avoid ambiguity and subjectivity.
Simple IRM layout discussed in Table 1 can be modified to include critical parameters as
shown in Table 2.
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
11/14
GCPS 2013
__________________________________________________________________________
Table 2. Typical IRM Layout with critical parameters (cp)
Elements of Process
System
Element 1 Element 2 Element 3 Element 4 ...
Interlock Systems
Interlock 1
cp1: cp1: cp1: cp1: ...
cp2: cp2: cp2: cp2: ...
cp3: cp3: cp3: cp3: ...
... ... ... ... ...
Interlock 2
cp1: cp1: cp1: cp1: ...
cp2: cp2: cp2: cp2: ...
cp3: cp3: cp3: cp3: ...
... ... ... ... ...
Interlock 3
cp1: cp1: cp1: cp1: ...
cp2: cp2: cp2: cp2: ...
cp3: cp3: cp3: cp3: ...
... ... ... ... ...... ... ... ... ... ...
For the refining and petrochemical industry, critical parameters are pressure, temperature,
flow and composition. Other parameters like chemical reaction, liquid level, etc. can be
evaluated from these four parameters. Each action of an interlock system should be
evaluated with respect to above four parameters for understanding the relationship with
each process element.
We will prepare IRM for the two incidents discussed in Section 4 as case study (Table 3
and 4). These tables will form a subset of the overall IRM for the plant.
Table 3. IRM for interlocks and equipment involved in Incident 1
Elements of Process
System
Cold box Cracking Furnace
Interlock Systems
Front End Acetylene
Reactor shutdown
interlock
Pressure: no change, cold box is
boxed up
Pressure: no change, OSBL
pressure controller is designed for
backup
Temperature: no effect, temperature
will rise gradually due to ambient
heating
Temperature: no effect
Flow: no flow to cold box resulting
in loss of tail gas and H2
Flow: flow of tail gas will be
replaced by LPG
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
12/14
GCPS 2013
__________________________________________________________________________
Elements of Process
System
Cold box Cracking Furnace
Interlock Systems
Composition: no effect on cold boxstreams composition
Composition: methane-rich tail gaswill be replaced by propane-butane
rich LPG increasingly thevolumetric calorific value, no heat
value correction available. Likely
to increase firing duty due to
sluggish temperature control of
furnace coils.
Table 4. IRM for interlocks and equipment involved in Incident 2
Elements of Process
System
Cracking Furnace
Interlock Systems
First shutdown
interlock of Cracking
Furnace
Pressure: no change in firebox and furnace coil pressure
Temperature: firebox temperature is maintained at lower level by
minimum firing.
Flow: less flue gas flow due to low firing
Composition: NA
Second shutdown
interlock of Cracking
Furnace
Pressure: firebox pressure will rise to ambient due to unavailability of ID
fan
Temperature: firebox temperature will reduce rapidly to ambient due to
fuel gas shutdown. Controlled rate heat release is required to avoid rapid
cooling by maintaining minimum firing conditions (first shutdown
interlock) for some duration or stopping flue gas instantly by closing the
damper. However, neither the duration of firebox operation under first
shutdown is sufficient, nor the damper will close to allow controlled rate
heat release and avoid thermal shock. Likely damage to coils.
Flow: no flue gas flow
Composition: NA
8. Integration of IRM with PHAA structured IRM described in Section 7 provides compatibility to integration with PHA
techniques such as HAZOP, LOPA, etc. PHA technique like HAZOP analyzes each andevery parametric deviation on process system that is applicable for an industrial setting.
For refining and petrochemical industry, the parameters include pressure, temperature,
level, flow, composition, chemical reaction, mixing, contaminants, special procedures,
etc.
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
13/14
GCPS 2013
__________________________________________________________________________
Development of IRM along with PHA study starts by identification of a subset of critical
or primary parameters out of the PHA parametric set on which other parameters depend(like pressure, temperature, flow and composition). It then incorporates and analyzes
actions of a safety system (interlock) as potential sources of deviation (in addition to theparametric deviations) for each process element (equipment or node) where the
deviations of interlock actions are evaluated under the guidance of critical parameter
subset.
9. ConclusionInterlock design information, in the form of narratives, cause and effect diagrams or
ladder/logic diagrams, is limited to the vicinity of the interlock system. It is unable to
evaluate and analyze the effect of actions taken by the interlock systems on other process
systems. This inability might result in irrevocable damage of equipment or potentialpersonnel exposure to toxic materials as evident from the two case studies presented in
Section 4. These damages can be avoided by understanding the interlock-process
relationship to gauge probable process responses to interlock actions.
The interlock-process relationship is not visible explicitly in evaluation techniques like
Software Systems Hazards Analysis (Fault/Event Tree Analysis, Failure Mode and
Effects Analysis) and PHA (HAZOP, LOPA, HAZAN). These techniques intend to
eliminate operational hazards caused by either malfunctioning of the software (interlock)
system or deviations in process parameters. However, they do not take into consideration
the probable causes that can occur in process elements after the actions of a software
(interlock) system have successfully executed.
IRM (Interlock Relationship Matrix) can overcome the isolated nature of interlock design
information by providing a holistic view of all interlock systems and process elements in
the plant (in the form of a matrix) and evaluate critical interlock-process relationship
under the guidance of critical parameters applicable for the industrial setting. It can also
fill the gap in other evaluation techniques by analyzing actions of a safety system
(interlock) as potential causes of deviation for the process elements. It provides efficientincorporation of new interlock systems or functions for existing process systems and
vice-a-versa by giving a ready platform for analyzing the interlock actions on the processsystem. IRM is a managerial decision making instrument that provides valuable
information to assess the likely damage to equipment and provide mitigation thereof.
Understanding interlock-process relationship is crucial to avoid jeopardizing mechanical
integrity of the process system by the very interlock system installed to protect them and
IRM makes it happen.
-
7/29/2019 Evaluate Plant-wide safety of your Interlock system
14/14
GCPS 2013
__________________________________________________________________________
10. References
1. Guidelines for Hazard Evaluation Procedures, 3rd edition, Center for ChemicalProcess Safety (CCPS), John Wiley & Sons, 2008.
2. Lees Loss Prevention in the Process Industries, Hazard Identification, Assessmentand Control, Volume 1, 3rd edition, Sam Mannan, Elsevier Butterworth-Heinemann,
2005.
Additional references not cited:
1. Instrumentation and Control systems, Princeton Plasma Physics Laboratory,ES&HD 5008 Section 2, Chapter 10, Revision 6, 2005.
2. Code Walk-Through, 1984, Dunn, Robert, Software Defect Removal, McGraw-Hill, Inc.
3. "Event Trees and their Treatment on PC Computers", Limnious, N. and J.P.Jeannette, Reliability Engineering, Vol. 18, No. 3, 1987.
4. "A Guide to Hazard and Operability Studies", Chemical Industry Safety and HealthCouncil of the Chemical Industries Association, Alembic House, London, UK.
5. "HAZOP and HAZAN", Klutz, T.V., Institution of Chemical Engineers, UK, 1986.6. "Nuclear Surety Design Certification for Nuclear Weapon System Software and
Firmware", Air Force Regulation 122-4, Department of the Air Force, 24 August
1987.
7. Petri Net Theory and Modeling of Systems, Peterson, J.L., Prentice Hall, 1981.8. "Procedures for Performing A Failure Mode and Effect Analysis", MIL-STD-1629A,
Department of Defense, 24 Nov 1980.
9. "Generic Techniques in Reliability Assessment, Fussel, J., Noordhoff PublishingCo., Leyden, Holland, 1976.