  • 8/13/2019 Event Centre Program - Thunder Bay, 2012

    1/1

    The ongoing discussion to replace the Fort

    William Gardens has gained significant

    momentum in the past three years.

    The consulting team, using a broad-based

    Site Evaluation Matrix, is recommending the

    Downtown/Waterfront site because it offers the

    greatest short- and long-term benefits, and is

    solidly anchored in a downtown core, a trendthat is becoming the norm in other mid-size

    Canadian cities.

    Overall, the development and operation of the

    Event Centre is concluded to impart substantial

    benefit within Thunder Bay, including:

    $148.3 million to $149.4 million in total

    economic benefits (direct and indirect

    impact) during the construction of the

    facility, along with between $79.0 million

    to $79.6 million in employment income

    growth, 1,120 to 1,130 person years of

    employment, and $17.2 million to $17.4

    million in direct tax revenue to the federaland provincial governments.

    $10.8 million to $16.8 million in annual

    economic benefits (direct and indirect

    impact) during the facilitys operations,

    including $4.6 million to $5.4 million

    annually in employment income growth,

    265 to 380 person years of employment

    annually, and $3.4 million to $4.6 million

    annually in direct tax revenue to the federal

    and provincial governments.

    In addition, the operation of the Spectator

    Arena and Conference Centre components are

    estimated to attract numerous new events,

    along with conference delegates and other

    visitors to Thunder Bay to attend the various

    conferences, meetings, trade shows and

    spectator events held at the Event Centre.

    Hosting such events is projected to result

    in approximately $6.1 million in new visitor

    spending within Thunder Bay annually, as well

    as assist the City in enhancing the revenues it

    receives from its North Core Parkade, where

    an additional $91,800 to $129,600 in annual

    revenue is projected.

    RECOMMENDED SITEThe Downtown/Waterfront:

    scored higher in the Site Evaluation Matrix

    (79.7 compared to 63.1 for Innova)

    is consistent with general consensus that

    Downtown North is the entertainment district

    or precinct

    will be a critical element in the transformation

    of the historic downtown Port Arthur, similar

    to many precedents in both Canada and the

    United States

    combined with Prince Arthurs Landing, will

    create a unique synergy as a destination for

    residents and visitors and attract national

    and international attention

    PROJECTED COST

    Event Centre Facility including

    site works & pedestrian overpass $92.6 million

    200-stall Parking Structure 7.2 million

    Facility fit up including public art

    & relocation of Hydro substation 6.3 million

    TOTAL PROJECTED COST $106.1 million

    PROPOSED FUNDING

    Citys Renew Thunder Bay (RTB)* $33.0 million

    Parking Structure Debenture 2.4 million

    Federal & Provincial Governments 55.7 million

    Private Equity 15.0 million

    TOTAL CAPITAL FUNDING $106.1 million

    *$25 million is in place in RTB Reserve Fund

    WHATS NEXT?Subject to Councils approval of the Phase 2 Feasibility Study on November 26, the proposed

    next step will see the development of a Project-Ready Plan including detailed facility plan

    and financial/business plan (Phase 3).

    Proposed Phases Anticipated Timing

    Phase 3 - Detailed Facility Development and

    Financial Plan/Business Plan [Project-Ready Plan] 2013Phase 4 - Confirmation of Funding and Business Partners 2013-2014

    Phase 5 - Detailed Design and Construction 2014-2016