Exam Code: VCAP5-DCD Number : VCAP5-DCD Passing Score : 800 Time Limit : 240 min File Version : 38.8 http://www.gratisexam.com/ Exam Code: VCAP5-DCD Exam Name: VMware Certified Advanced Professional 5 - Data Center Design (VCAP5-DCD) Sections 1. Active/Passive Discovery Methods 2. Best Practices 3. Design Phases & Qualities 4. Entity Relationship Diagram 5. Project Factors 6. Predictive/Adaptive 7. RTO/RPO 8. Storage 9. Network 10. AutoDeploy 11. High Availability

Upload: others

Post on 12-Dec-2021

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Exam Code: VCAP5-DCD

Exam Code: VCAP5-DCD

Number: VCAP5-DCDPassing Score: 800Time Limit: 240 minFile Version: 38.8

http://www.gratisexam.com/

Exam Code: VCAP5-DCD

Exam Name: VMware Certified Advanced Professional 5 - Data Center Design(VCAP5-DCD)

Sections1. Active/Passive Discovery Methods2. Best Practices3. Design Phases & Qualities4. Entity Relationship Diagram5. Project Factors6. Predictive/Adaptive7. RTO/RPO8. Storage9. Network10.AutoDeploy11.High Availability

Page 2: Exam Code: VCAP5-DCD

Actualcerts

QUESTION 1DRS rules can help satisfy availability concerns within a cluster; however, if used extensively, they may cause aperformance issue with vCenter.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:DRS rules can be extremely useful for a number of reasons, such as redundancy, network bandwidth, andperformance management. However, if they are used extensively, functionality such as DPM may become lesseffective (that is, hosts will not be able to power off due to rules and will use more power than required).

Chapter 4, Management/Platform Design

QUESTION 2You are reviewing a VMware vSphere 5 cluster design. The system is designed to run DPM in fully automatedmode. DPM in fully automated mode ____ evacuate all templates when placed into standby mode.

A. willB. will not

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:DPM will not move powered-off virtual machines or templates. A real-life workaround is to turn off fullyautomated DRS for these machines on a case-by-case basis and register them to a specific host in the clusterfor deployment usage.

Chapter 4, Management/Platform Design

QUESTION 3Has the configurable option "Failure Detection Time" in VMware HA has been removed in vSphere 5?

A. No. It is an advanced setting.B. Yes. It is no longer needed due to additional storage checks in the VMware HA isolation response process.

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:vSphere 5 will use datastore heartbeats in a disaster. Thus, this setting is no longer available or supported inVMware vSphere 5.

Chapter 4, The Importance of vMotion, VMware HA, and Fault Tolerance

QUESTION 4

Page 3: Exam Code: VCAP5-DCD

You are designing a VMware HA cluster. In vSphere 5, VMware HA will take cluster resource fragmentation intoaccount and ask DRS to defragment the cluster, if required.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:In VMware vSphere 5, this HA functionality is fully automated and does not use any specific custom settingswith regard to reservations or slot sizes. VMware HA functions can request DRS to migrate workloads acrossthe system in multiple rounds of vMotion tasks. This can help defragment the cluster and restart VMs that havebeen affected by a failed host. Chapter 4, The Importance of vMotion, VMware HA, and Fault Tolerance

QUESTION 5A guest VM should be sized using ____________. (Choose two)

http://www.gratisexam.com/

A. minimum applications specificationsB. initial workloadC. anticipated workloads

Correct Answer: ACSection: (none)Explanation

Explanation/Reference:Explanation:Allocated resources are shown in the guest operating system and are not guaranteed. The amount depends onthe unreserved resources available at the time. Assuming no functionality issues, you can configure aproduction application to be guaranteed its projected workload, and the system should deliver. Without areservation, there is potential for a performance impact if there is contention.

Chapter 5, Virtual Machines--From the Design Perspective

QUESTION 6You are a VMware consultant working at a small managed services company. The company has won acontract with a large company, Company A, to host its test and dev. platform, with the chance on annual reviewto host the production platform.

Although you have been engaged early in the project due to business requirements, the budget for the projecthas already been combined with that for another DR project for another company, Company B.

The thought process for this decision is that, if needed, the test systems from Company A have a lowerrequirement in the unlikely event of Company B having a DR event.

All the items have been bought and are to be delivered. Your role is to take the equipment provided and

Page 4: Exam Code: VCAP5-DCD

construct, develop, and implement a scalable working vSphere platform.

The following requirements are stated:

Company A's test machines must be provided with sufficient resources for BAU.Company B's systems must be made available with minimum impact to Company A.The RTO for Company A is seven days, with an RPO of one month.Company B's RTO is 1 hour, and its RPO is 15 minutes.

Using a shared infrastructure in this way is a risk to the project.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:The technical design process enables the platform designer to work in a methodical way and with others withsimilar objectives. A risk is an object that could prevent the delivery of the project requirements.

Chapter 1, The Technical Design Process

QUESTION 7You are a VMware consultant working at a small managed services company. The company has won acontract with a large company, Company A, to host its test and dev. platform, with the chance on annual reviewto host the production platform.

Although you have been engaged early in the project due to business requirements, the budget for the projecthas already been combined with that for another DR project for another company, Company B.

The thought process for this decision is that, if needed, the test systems from Company A have a lowerrequirement in the unlikely event of Company B having a DR event.

All the items have been bought and are to be delivered. Your role is to take the equipment provided andconstruct, develop, and implement a scalable working vSphere platform.

The following requirements are stated:

Company A's test machines must be provided with sufficient resources for BAU.Company B's systems must be made available with minimum impact to Company A.The RTO for Company A is seven days, with an RPO of one month.Company B's RTO is 1 hour, and its RPO is 15 minutes.

The use of a shared infrastructure used in this way is a constraint to the project.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:An item from the current state analysis that would restrict or change a design choice is potentially a constraint.These factors can limit the design and in some cases prevent the realization of the project vision.

Page 5: Exam Code: VCAP5-DCD

Chapter 1, The Technical Design Process

QUESTION 8A current state analysis is a project phase that is carried out to ensure that an architect understands thecomplete environment at the beginning of a project.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:A current state analysis gives an architect a way to examine the road ahead. Any oversights at this stage couldhave major implications for the project later on. By ensuring that the current state analysis is completedthoroughly, you can prevent many potential problems.

QUESTION 9The difference between the beginning of a project and the vision is also known as the ____________.

A. current state analysisB. gap state analysisC. upstream relationshipD. downstream relationship

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:By reviewing the current configuration of a system and mapping the final status of components as described inthe vision, the business identifies the gap between the two. A gap state analysis is a review of the items ortasks that are required to progress between the stages. Such an analysis is useful in creating milestone plans,implementation orders, and so on.

QUESTION 10The analysis of the difference between the beginning of a project and the vision is also known as the currentstate analysis.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:By reviewing the current configuration of a system and mapping the final status of components as described inthe vision, the business identifies the gap between the two. A gap state analysis is a review of the items ortasks that are required to progress between the stages. Such an analysis is useful in creating milestone plans,implementation orders, and so on.

Page 6: Exam Code: VCAP5-DCD

QUESTION 11A gap state analysis is a review of the items or tasks required to progress from the current environment to thevision.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:By reviewing the current configuration of a system and mapping the final status of components as described inthe vision, the business identifies the gap between the two. A gap state analysis is a review of the items ortasks that are required to progress between the stages. Such an analysis is useful in creating milestone plans,implementation orders, and so on.

QUESTION 12A component relationship diagram can be used to establish impact analysis.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:In an upstream relationship, a logical object or component has a dependency on other items in the solution. Forexample, a service running on an application server requires an Active Directory user account to beauthenticated. The application service must be started after the Active Directory service. Therefore, theapplication server has an upstream relationship with the Active Directory service.

In a downstream relationship, a logical object or component does not have a dependency on other items in thesolution. For example, say that a multisite web server crashes. The web tier hosting multiple websites willcrash; however, the downstream objects such as the database server will continue to function. Backendprocesses that are dependent on the downstream objects from the web servers can continue to function.

QUESTION 13A logical diagram may contain ____________. (Choose two)

A. relationship informationB. Data flow informationC. IP addressesD. vendor information

Correct Answer: ABSection: (none)Explanation

Explanation/Reference:Explanation:A logical diagram can be used to show service components and how they relate to each other. A logicaldiagram is a high-level diagram that is independent of the hardware used for the solution.

Page 7: Exam Code: VCAP5-DCD

QUESTION 14A project vision _______________.

A. is the required endpoint of a project--the purpose for completing the processB. can be achieved after several iterations of a project life cycleC. both of these are correct

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:The project vision indicates the final state the platform should be in. It is the business-led objective, whichprovides value and incorporates the infrastructure qualities.

QUESTION 15Vendor-best practices can be used to guide ______________.

A. configuration and design choices in the absence of project requirementsB. configuration and design choices in addition to project requirementsC. both these answers are correct

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:A best practice is normally based on experience with a successful implementation. By using theseconfigurations, known issues could possibly be avoided. Best practices should not replace project requirementsbut can be used as a starting point, as long as the project requirements are satisfied.

QUESTION 16You are planning a vSphere 4.1 to 5.0 upgrade. The production datastores are 6 TB. Each datastore consist ofthee extents of 2 TB and is currently 65% full. The operations team would like to keep the system as close tothe current configuration as possible. The upgrade process also requires as little service impact as possible. Inaddition, you wish to use storage I/O control as soon as possible, due to a mission-critical business applicationrequirement. Which of the following would be the correct approach?

A. Create a new VMFS 5 datastore of 6 TBEnable storage I/O controlMigrate the VMs using storage vMotionConfigure storage I/O shares as required

B. Upgrade the VMFS 3 datastoreEnable storage I/O controlConfigure storage I/O shares as required

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:When a datastore with VMFS v3 is upgraded with extents to VMFS v5, the logical attributes and extents are notchanged. Storage I/O control cannot be used with datastores composed of extents.

Page 8: Exam Code: VCAP5-DCD

QUESTION 17A logical diagram does not include ____________.

A. high-level components and how they relate to the solutionB. detailed information regarding the components, such as model of systems, IP addresses, and

configurations

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:A logical diagram can be used to show service components and how they relate to each other. A logicaldiagram is a high-level diagram that is independent of the hardware used for the solution. It shows componentsand relationships. In this example, the diagram would should the number of datastores, size, and logic, such asreplication and other settings.

QUESTION 18You are working as a platform designer for a large hosting provider. You are considering the scalability of asolution that is projected as 50 hosts and 1,500 virtual machines. A VCSA is a project requirement. Which ofthe following is true?

A. The VCSA will scale to 5 hosts and 50 VMs and thus is a risk to project scalability.B. The VCSA can be configured to use a remote SQL database to meet project scalability.C. The VCSA should be configured to use a remote DB2 or Oracle database.

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

A VCSA is a premade virtual machine. Due to the size of the system and the local DB2components, the systemis limited in support. However, if you expand the virtual machine resources and deploy a remote database, theVCSA can scale out to the vCenter standard limitations.

QUESTION 19A host has four dual-port network cards. What is the maximum number of vSwitches that can be integrated withthe physical network, assuming that network redundancy is not a requirement?

A. 8B. 4C. 64D. 512

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:An ESXi physical NIC can be assigned to only one vSwitch at a time. For example, a host with five NICs canhave a maximum of five vSwitches that can link to the outside world.

QUESTION 20

Page 9: Exam Code: VCAP5-DCD

How do you understand and predict the resources available for VMware HA to meet specific projectrequirements?

A. Configure the appropriate admission control policyB. Disable admission control policy

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:An admission control policy tells VMware HA how to calculate the resources it needs to reserve for a cluster. Ituses a combination of memory and CPU reservation configuration or, if no configuration exists, a default lowreservation.

QUESTION 21VMware HA can protect application corruption issues by using VM monitoring functionality.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:VM monitoring is the function whereby a virtual machine is restarted when the virtual machine heartbeat hasstopped (such as with a blue screen of death on a Windows machine). The machine is simply restarted on thesame host (that is, not migrated). However, the system would lose data from the point of corruption.

QUESTION 22During a vCenter outage caused by a host power issue, a member of the operations team created anemergency guest VM by connecting directly to one of the hosts. The cluster was enabled for VMware HA at thetime of the vCenter outage. In the event of further problems in the datacenter, is the newly created VMprotected by HA?

A. YesB. No

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:The vCenter manages the update of the VMware HA protected list. When you add a machine while the vCenteris out of service, the list will not be updated.

QUESTION 23When designing a system for VMware HA functionality, which of the following considerations is not an impact tothe design?

A. The size of the hostB. The number of hostsC. Application compatibility with VMware platforms using HA

Page 10: Exam Code: VCAP5-DCD

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:The simplicity of VMware HA is one of the many design benefits. If an application or guest virtual machine isrunning on a vSphere platform, the system is compatible from a high level with VMware HA. It is purely anautomated restart from a functionality perspective.

QUESTION 24The method of guest VM backup can have an effect on the size of datastores used in a vSphere platform.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:The RTO and RPO requirements and available hardware used in a solution can impact the size of datastoresby limiting the amount of data that can be practically restored. This amount of data is the max size of thedatastore.

QUESTION 25You have been sent a query regarding a platform you have just designed and implemented. Following amaintenance window where VMware HA was disabled, the VMware HA settings were lost. How would youprevent this issue?

A. Back up the vCenter database and restore it if the problem reoccurs.B. Instruct the team to use the Host monitoring tab functionality.C. Instruct the team to use the VM monitoring tab functionality.

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:Disabling the vSphere HS cluster settings will change the entire configuration of the cluster from the HSperspective. If the Host Monitoring checkbox is selected, it will allow the configuration to remain; however, theisolation response or outage response will not occur.

QUESTION 26VMware HA in vSphere 5.0 cannot survive more than five primary host failures. Thus, hosts should bephysically placed in different racks, where possible, to avoid substantial impact.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Page 11: Exam Code: VCAP5-DCD

Explanation/Reference:Explanation:This was true for VMware HA solutions prior to version 5. vSphere 5 can withstand multiple failures and uses amaster/slave topology with a reelection process.

QUESTION 27A guest VM has an 8 GB allocated to it. What is the size of the swap file?

A. 8 GB minus the reservationB. It depends on the limit configuration.C. 8 GB

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:The size of the swap space is the maximum amount of allocated memory that could be reallocated to anotherVM in the event of contention. This is expressed as the size of configured memory minus the reservation.

QUESTION 28Which of the following settings could be utilized when performing a performance test on an application server?

A. CPU LimitsB. Share ValuesC. Reservations

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:To accurately understand the resource allocation, and compare against other tests in a virtual or physicalplatform, an administrator can guarantee resources.

QUESTION 29How many vApps can a guest virtual machine be placed into?

A. 1B. 64C. 8D. 12

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:A vApp is a logical container of guest virtual machine objects. The use of a container provides the ability to usekey management functionality, which can dramatically help a virtualized platform. Automation allows lots of VMsto be managed by fewer staff. Although vApps can be nested, a single virtual machine can be defined in onlyone vApp.

QUESTION 30

Page 12: Exam Code: VCAP5-DCD

vApp startup order can be configured to work with VMware Heartbeat status.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:A vApp is a logical container of guest virtual machine objects. The use of a container provides the ability to usekey management functionality, which can dramatically help a virtualized platform. Automation allows lots of VMsto be managed by fewer staff. The virtual machine Heartbeat is part of the VMware tools service. Otherapplication services can be made a high priority or a parent of the VMware Tools service; in this case, onstartup, waiting for the VMware tools service to start before starting the next guest virtual machine in the vAppwould assume that the application service has started successfully.

QUESTION 31A guest VM has 50 GB allocated to it and a 2 GB limit. What is the size of the swap file?

A. 50 GB minus the reservationB. 48 GB minus the reservationC. 52 GB minus the reservationD. 2 GB minus the reservation

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:The size of the swap space is the maximum amount of allocated memory that could be reallocated to anotherVM in the event of contention. This is expressed as the size of configured memory minus the reservation.

QUESTION 32Application performance test cases are most accurate if based on ____________.

A. quantitative success criteriaB. vendor best practices

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:The best validation is to place a platform under a typical test of what it will be faced with in the field--forexample, having a simulated number of users go through a workflow (perhaps a website). A lot of these tasksvary with the type of application and are primarily application functionality based. In addition, platform orinfrastructure metrics are key for validation and for information to be used within the operational documentation(for example, troubleshooting guide, monitoring recommendations).

QUESTION 33An installation guide should contain _____________. (Choose two)

A. basic troubleshooting and baseline monitoring for verification purposes

Page 13: Exam Code: VCAP5-DCD

B. entry criteria or requirementsC. justifications for design choicesD. best practices.

Correct Answer: ABSection: (none)Explanation

Explanation/Reference:Explanation:An installation guide provides engineers a detailed reference and process to install and verify a solution. Allrelevant components and processes are detailed. It is also useful to include troubleshooting or known issues, ifany were experienced during the development and test phases.

QUESTION 34An implementation plan should contain _____________.

A. a milestone planB. risks, assumptions, and dependencies on the activities in the implementation planC. order

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:An implementation plan gives all members of a project team a level of understanding of the technical approachof a project, the number of phases, major tasks in each phase, and the correct order for completing the tasks.

QUESTION 35You are a VMware consultant for a large enterprise running VMware vSphere 4.1. You are reviewing theupgrade documentation created to take the company to version 5.X of the software. The upgrade has severalrequirements, including the following:

- Minimize the impact to the business applications- Do a full rollback, if required, for any issues not foreseen by the project team

You notice in the documentation that the upgrade to VMFS 5 is mentioned as being non-disruptive and havingzero impact on the technical solution. Is this technically correct?

A. YesB. No

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:In this example, a VMFS 5 upgrade cannot be rolled back without extra scratch space and without usingstorage vMotion. These things could add extra I/O load on the systems and affect the first requirement.

QUESTION 36An implementation plan is a set of instruction that provide sufficient detail for an engineer to configure or installa platform according to a physical design.

Page 14: Exam Code: VCAP5-DCD

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:An implementation plan gives all members of a project team a level of understanding of the technical approachof a project, the number of phases, the major tasks in each phase, and the correct order for completing thetasks. This documentation can be used to bring in skilled people and to judge the project stability and progressthroughout the implementation. The plan should be detailed enough for technical personnel to understand thetasks being completed but without detailing specific configuration and installation processes.

QUESTION 37A validation plan is a set of processes which prove that a project or a function of a platform has beenconfigured correctly and behaves as designed.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:A validation plan can range from a detailed test plan to high-level statements. It should not be subjective. Thebest validation is to place a platform under a typical test of what it will be faced with in the field--for example,having a simulated number of users go through a workflow (perhaps a website). A lot of these tasks vary withthe type of application and are primarily application functionality based. In addition, platform or infrastructuremetrics are key for validation and for information to be used within the operational documentation (for example,troubleshooting guide, monitoring recommendations).

QUESTION 38For effective VMware platform validation to take place, that platform should be _____________.

A. running test guest workloadsB. running workloads of projected application resource requirementsC. stress tested until failure to understand capacity

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:A validation plan can range from a detailed test plan to high-level statements. It should not be subjective. Thebest validation is to place a platform under a typical test of what it will be faced with in the field--for example,having a simulated number of users go through a workflow (perhaps a website). A lot of these tasks vary withthe type of application and are primarily application functionality based. In addition, platform or infrastructuremetrics are key for validation and for information to be used within the operational documentation (for example,troubleshooting guide, monitoring recommendations).

QUESTION 39Vendor support may prevent an application from being virtualized.

Page 15: Exam Code: VCAP5-DCD

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:Good design should meet the project requirements and consider the properties of assumed platform design.Protecting data requires that a system be available and manageable, that it have good performance, and that itbe easy to recover and be secure. In this example, if an application is not supported by the vendor, thebusiness may be unable to meet SLAs.

QUESTION 40Which of the following are the infrastructure qualities?

A. Availability, manageability, best practices, scalability, backupB. Availability, manageability, performance, recoverability, securityC. CPU, memory, network, storageD. Management, virtual machine, compute, network, storage

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:Good design should meet the project requirements and consider the properties of assumed platform design.Protecting data requires that a system be available and manageable, that it have good performance, and that itbe easy to recover and be secure.

QUESTION 41The recovery point objective is the point in time to which a system needs to be restored following a failure.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:The recovery point objective (RPO) is the point in time to which the system needs to be restored following afailure.

QUESTION 42Which of the following factors should influence the decision of whether to virtualize an application? (Choosethree)

A. Whether it is supported on a virtualization platformB. Licensing costs in a virtualization platformC. Compliance considerations (such as inability to share infrastructure due to regulations)D. Whether the software is custom and has not be widely virtualized in the field

Page 16: Exam Code: VCAP5-DCD

Correct Answer: ABCSection: (none)Explanation

Explanation/Reference:Explanation:Good design should meet the project requirements and consider the properties of assumed platform design.Protecting data requires that a system be available and manageable, that it have good performance, and that itbe easy to recover and be secure.

QUESTION 43Which of the following describes the anticipated time until a solution component may fail?

A. Recovery time objectiveB. Recovery point objectiveC. Mean time between failures

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes torestore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to whichthe system needs to be restored following a failure. The MTBF is the amount of time a component is predictedto fail and can be used with operational management or design concepts.

QUESTION 44You are a VMware platform designer at a large service provider reviewing a network design.

Two of the requirements are as follows:

- R001: All traffic must be encrypted or separated.- R002: All components must be fault tolerant.

The current design involves software-based iSCSI storage with teamed 1 GB network cards for the storagenetwork. The iSCSI network has a unique VLAN and network ID. The design ensures that a different passwordis used for each LUN.The current design meets both requirements.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:By using NIC teaming, iSCSI is configured in a fault-tolerant manner. However, it is not encrypted but isseparated; therefore R001 and R002 are satisfied.

QUESTION 45The use of software-based iSCSI storage allows encryption to be used in logical designs.

A. True

Page 17: Exam Code: VCAP5-DCD

B. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:iSCSI traffic is not encrypted by default. However, CHAP can be used with software-based iSCSI.

QUESTION 46Which of the following is a logical boundary for vMotion?

A. ClusterB. vDCC. FolderD. Resource Pool

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:By design, vMotion is possible from a logical perspective between the vDC. It is possible, however, to have astretched cluster and to not satisfy vMotion requirements. The logical boundary is limited to vDCs.

QUESTION 47You have been asked to design a system with the following VMware functionality enabled:- R001: VMware HA must be functional.- R002: VMware SRM can be used between two sites for DR processes.- R003: You must be able to see all hosts from a single pane of glass.

From these requirements:

A. A vSphere 5.0 VCSA can provide an acceptable solution.B. A vSphere 5.0 Windows-based vCenter can provide an acceptable solution.C. The requirements cannot be met.

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:The VCSA can function with VMware SRM. However, for SRM functionality, both sites require a vCenterinstallation. This would limit the choice of single-glass-pane management to Linked mode. A Linked modeinstallation requires Microsoft technology in the ADAM instance, and thus eliminates the VCSA choice.

QUESTION 48When using VMware HA, the larger the consolidation ratio, the smaller the potential impact to the business inthe event of a VMware HA event.

A. TrueB. False

Correct Answer: B

Page 18: Exam Code: VCAP5-DCD

Section: (none)Explanation

Explanation/Reference:Explanation:VMware HA can satisfy the majority of RTO scenarios. In general, businesses can tolerate small outages ofshorter than a few minutes. Designed correctly, HA can satisfy this requirement while providing hardware-levelprotection. Some design considerations are the restart time and impact of the outage; the fact that the moreVMs per host, the higher the consolidation ratio; and the possibly longer time to restart along with its largerimpact to the business.

QUESTION 49When deploying a vCenter solution for a vSphere design, continuous uptime is stated as a requirement.

The use of vCenter heartbeat has been agreed upon and budgeted. The design consists of two VCSAs.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:vCenter heartbeat requires a Windows-based vCenter installation, rather than the appliance.

QUESTION 50A functional requirement ____________.

A. specifies what the system should do

http://www.gratisexam.com/

B. is a detail that happens to be true but has not been tested or verifiedC. specifies how the system should behaveD. is an attribute that can prevent the completion of the project

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:A functional requirement states something the system should do (for example, the system should processtransactions). A nonfunctional requirement states how the system should behave (for example, the systemshould update its performance metrics every 5 seconds). An assumption is a detail that happens to be true buthas not been tested or verified is an assumption, and a risk is an attribute that can prevent ta project from beingcompleted.

QUESTION 51A ____________ is an iterative process used to define a technical solution.

Page 19: Exam Code: VCAP5-DCD

A. constraintB. best practiceC. logical designD. design methodology

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:A design methodology is an iterative process used to create a technical design.

QUESTION 52A ______________ design requires IP addresses and specific hardware selections.

A. conceptualB. physicalC. logicalD. None of the above

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:A conceptual design is a high-level overview of the suggested system. Logical designs show how subsystemsinterconnect or communicate. No attempt is made to select vendors or map out physical products; rather, thelogical design shows how the suggested components align together. A physical design puts specificcomponents and settings into place. It lists items such as vendor products, IP addresses, and specificcommunication protocols. A physical design is a blueprint of an architecture.

QUESTION 53Which design is created first?

A. Conceptual designB. Physical designC. Logical designD. None of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:A conceptual design is a high-level overview of the suggested system. The conceptual design is created firstand is usually the starting point for the logical design.

QUESTION 54Best practices should always be followed.

A. TrueB. False

Page 20: Exam Code: VCAP5-DCD

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:Best practices are recommendations based on practical standards collected by VMware and should always beused unless company business rules or functional requirements prevent their use.

QUESTION 55Which of the following is not a reason to use virtualization?

A. Save moneyB. Improve system performanceC. Save timeD. Make disaster recovery easier

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 56Which of the following tools can be used to gather information for a current state analysis?

A. VMware vCenter ServerB. VMware OrchestratorC. VMware Operations ManagerD. VMware Capacity Planner

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:VMware Capacity Planner records performance metrics over time to give a clear picture of the currentarchitecture's performance. This information can be used to help build a current state analysis that can be usedto help build the new virtual architecture.

QUESTION 57Information gathered during the current state analysis include the number of sites, servers, or devices; a list ofapplications and their dependencies; current usage; and known issues.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

Page 21: Exam Code: VCAP5-DCD

Data such as the following may be gathered for a current state analysis:Number of sites, servers, or devicesA list of applications and their dependenciesCurrent use and capacityKnown issues (for example, a specific piece of software is not supported in a virtualized platform, an applicationrequires certain hardware to run)Forthcoming projects and future growth plan (for example, Will extra capacity be needed soon? Is a criticalpoint in the business year approaching?)Licensing, support, and maintenance informationBusiness standards, policies, and compliance information

QUESTION 58The ___________ would not be considered a stakeholder in a design.

A. backup administratorB. project sponsorC. key application ownersD. data center manager

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:Key stakeholders should include the following:Project sponsorKey application ownersServer architecture leadsLAN/WAN architecture leadsData center managers

QUESTION 59The phrase "Lack of virtualization expertise on site" is an example of a ______________.

A. constraintB. riskC. nonfunctional requirementD. functional requirement

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:A risk is an issue that can affect the overall success of a project. A constraint is a limiting factor in a design,based on current system behavior. A nonfunctional requirement is a system behavior, and a functionalrequirement is what the system should do.

QUESTION 60The customer has decided that it will use the NAS it has in-house as its storage solution. What type of designfactor is this?

A. SLAB. RiskC. Nonfunctional requirement

Page 22: Exam Code: VCAP5-DCD

D. Functional requirement

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:The customer is stating that NFS must be used in the design. This is a form of a nonfunctional requirement.Often, nonfunctional requirements are similar to constraints.

QUESTION 61A recovery point objective (RPO) is ______________.

A. the point in time to which data has to be recovered after a failureB. the amount of time it takes to recover a system from a failureC. the plan to restore a system after a failureD. an agreement with the customer on a pre-defined level of service

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:RPO is the point in time to which the system must be restored after a failure.

QUESTION 62High Availability (HA) can prevent virtual machine downtime.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:HA restarts virtual machines when an ESXi host crashes. HA can reduce downtime, but it cannot prevent it.

QUESTION 63VMware Fault Tolerance can prevent virtual machine downtime in the event of an application failure.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:Fault Tolerance can only prevent virtual machine downtime in the event of an ESXi host crash.

QUESTION 64Which of the following is not part of the logical design?

Page 23: Exam Code: VCAP5-DCD

A. BIOS settingsB. Key component relationshipsC. Data flow diagramsD. High-level diagrams

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:A logical design shows the relationship between components, without selecting specific equipment. It shows thebasic flow of data between components, key component relationships, and high- level diagrams.

QUESTION 65Which of the following is not a component of a virtual design?

A. compute layerB. resource layerC. network layerD. storage layer

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:The components of a virtual design include the management layer, the networking layer, the storage layer, theguest VM layer, and the compute layer.

QUESTION 66What are the main types of storage? (Choose two)

A. Fiber ChannelB. local storageC. VMFSD. shared storage

Correct Answer: BDSection: (none)Explanation

Explanation/Reference:Explanation:From a VMware platform design perspective, the storage is agnostic. Logically, there are two types of storage:local and shared.

QUESTION 67Storage tiering involves ______________.

A. priority locations to migrate virtual machinesB. grouping storage to be used firstC. categorizing storage by the size of the LUNs

Page 24: Exam Code: VCAP5-DCD

D. categorizing storage based on performance to meet SLAs

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:Storage tiering categorizes LUNs by the performance they can provide to enable architects to place workloadson the appropriate storage tiers to ensure that the workloads are within the SLA standards.

QUESTION 68As a result of multiple design meetings, it has been stated that the company creating the virtual architecture willbe using a NAS device as its storage choice. There is a functional requirement to run a Microsoft application ina Microsoft Cluster Service (MSCS) environment. What is the risk in this setup?

A. The cluster will not perform well in a virtual environment.B. The cluster will take up a lot of storage space, requiring an abnormal amount of storage.C. MSCS requires raw device mappings, which cannot be created on a NAS.D. There will be excessive IOPS as a result of the cluster.

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:If the organization uses only NFS datastores, raw device mappings cannot be created. A NAS creates sharesthat accesses storage at the file level, rather than LUNs that access storage at the block level.

QUESTION 69An active passive storage array should be configured with the fixed multipathing policy.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:An active passive array will have only one active path at a time. An array like this should be configured with theMRU multipathing policy. An active-active array has multiple active paths and should be configured with round-robin or fixed-multipathing policies.

QUESTION 70Which of the following could be considered a single point of failure for storage?

A. Using RAID 5 instead of RAID 10B. Using single-port HBAs in an ESXi hostC. Using a dual-port HBA in an ESXi hostD. Not using jumbo frames

Correct Answer: CSection: (none)

Page 25: Exam Code: VCAP5-DCD

Explanation

Explanation/Reference:Explanation:Using a dual-port HBA can result in a single point of failure if the HBA malfunctions, taking out both ports. It isbetter to use two single-port HBAs.

QUESTION 71To balance IOPS and capacity within a datastore cluster, which of the following technologies should beimplemented?

A. vMotionB. High AvailabilityC. Storage I/O controlD. Storage DRS

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:Storage DRS will automatically migrate powered-on VMs to datastores within a storage cluster in order tobalance the capacity and IOPS among member datastores.

QUESTION 72HA is a disaster recovery solution.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:HA provides automatic recovery of virtual machines in the event of an ESXi host crash.

QUESTION 73Consider leaving about 20% of a datastore available for _____________.

A. larger virtual machinesB. vMotionC. snapshotsD. I/O overhead

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:About 20% of a datastore should be left unused to provide space for swap files, snapshots, storage overhead,and future growth.

Page 26: Exam Code: VCAP5-DCD

QUESTION 74Which of the following is not considered vSphere network traffic?

A. IP storageB. VM networkC. Storage vMotionD. vMotion

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:vSphere network traffic includes VM network, vMotion, IP storage, FT traffic, and management network traffic.

QUESTION 75Which type of VLAN requires no configuration of vSphere?

A. Virtual switch taggingB. VLAN trunkingC. Virtual guest taggingD. External switch tagging

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:External switch tagging applies to VLANs that are created on physical switches only. The vSphere environmentis not aware of the VLANs.

QUESTION 76In which type of VLAN does adding and removing the VLAN tag occur at the virtual switch?

A. Virtual switch taggingB. VLAN trunkingC. Virtual guest taggingD. External switch tagging

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:When VLANs are configured on a virtual switch, the VLAN tag is added to outbound traffic and removed oninbound traffic.

QUESTION 77A functional requirement ____________.

A. should be a part of the designB. is important only when you're putting together the logical design

Page 27: Exam Code: VCAP5-DCD

C. must be accounted for in the designD. is not important

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:A functional requirement is an operation the design must perform. All functional requirements must beaccounted for in the design.

QUESTION 78A physical design includes specific vendor information, IP addresses, IQN addresses, and exact wiringconnections.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:A physical design is an exact diagram of how the system is intended to be built. The technical design shouldanswer all technical questions.

QUESTION 79Private VLANs are required for the design. Which vSphere licensing edition is required?

A. EssentialsB. Enterprise PlusC. EnterpriseD. Standard

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:Private VLANs require distributed virtual switches, which are available only with the Enterprise Plus licensingedition.

QUESTION 80The vCenter Server should be deployed as a virtual machine and should be configured with fault tolerance.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

Page 28: Exam Code: VCAP5-DCD

Explanation:Fault tolerance works only with a virtual machine that uses a single virtual CPU. One of the requirements ofvCenter Server is to use at least two virtual CPUs. Using fault tolerance with the vCenter Server is notsupported.

QUESTION 81A number of factors determine how many physical adapters are needed in a host design. Which of the followingis not one of them?

A. Virtual machine sizeB. Amount of bandwidth requiredC. Security requirementsD. Hardware fault tolerance

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:Virtual machine size has no effect on the network.

QUESTION 82Which networking feature should be configured to improve storage performance?

A. Spanning Tree ProtocolB. Traffic shaping on the storage networkC. Jumbo framesD. Promiscuous mode for the storage port group

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:Jumbo frames provide a larger MTU (maximum transmission unit) that enables a typical frame to hold moreactual payload data, which can result in better storage performance.

QUESTION 83____________ can be configured to ensure that a type of traffic receives priority for bandwidth when bandwidthis congested?

A. SIOCB. NIOCC. SharesD. Reservations

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:Network I/O Control (NIOC) allows you to assign shares to different types of network traffic. The more shares atype of network traffic has, the higher percentage of the available bandwidth the traffic type will get when

Page 29: Exam Code: VCAP5-DCD

network bandwidth is completely congested.

QUESTION 84Which of the following needs to be considered when determining the amount and size of the hosts required fora virtual design?

A. Aggregate CPU and memory requirementsB. Future growthC. Number of vCPUs to be hosted per boxD. All of the above

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:When attempting to determine the host requirements of a virtual design, you need to determine aggregate CPUand memory requirements, number of virtual CPUs, number of cores available, maximum utilization, socketand core availability, and future growth.

QUESTION 85In scaling an architecture, scaling out involves ___________.

A. selecting a smaller number of large hostsB. selecting a larger number of smaller hostsC. using a combination of large and small hosts to satisfy virtual machine requirementsD. none of the above

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:Scaling out involves building your architecture using more hosts that have smaller amounts of CPU cores andmemory than what you would use in a scaled-up architecture.

QUESTION 86When selecting a compute server, the architecture should use servers that are identical in every way possible,including components and the slots the components are installed in.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:Using identical servers ensures fewer issues with vMotion and aids in managing resource utilization amongservers.

QUESTION 87When considering server consolidation, plan on running ___________ vCPUs per core.

Page 30: Exam Code: VCAP5-DCD

A. 1 to 2B. 3 to 4C. 4 to 6D. 6 to 8

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:VMware best practices recommend running 4 to 6 virtual CPUs per core.

QUESTION 88When planning on resource use for the servers, you should plan on leaving resources available for all thefollowing except __________.

A. patchingB. maintenance modeC. future growthD. log file space

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:Consider leaving extra capacity for items such as maintenance mode, upgrades, patching, and short-termsurges in resource usage.

QUESTION 89Which of the following will still function if vCenter crashes?

A. HAB. DRSC. FTD. Storage DRS

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:Although all the options listed require the vCenter Server for configuration, HA will work even if the vCenterServer crashes. For this reason, VMware recommends running the vCenter Server in a virtual machine so HAcan provide the vCenter Server availability.

QUESTION 90vCenter Server Linked mode allows you to view up to 10 vCenter Servers in a single window.

A. TrueB. False

Correct Answer: B

Page 31: Exam Code: VCAP5-DCD

Section: (none)Explanation

Explanation/Reference:Explanation:vCenter Server will allow you to view up to 10 vCenter Servers and up to 30,000 virtual machines in a singleview.

QUESTION 91When configuring HA, which admission control policy should be used?

A. Host Failure Cluster ToleratesB. CPU and Memory Percentage for FailoverC. Standby HostD. None of the above

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:CPU and Memory Percentage for Failover sets aside a percentage of the resources to be left unused in theevent of a failover.

QUESTION 92The VCSA can be configured with a small internal Oracle database that can be used to manage up to 5 ESXihosts or 50 virtual machines.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:The VCSA comes with an internal IBM DB2 database that supports up to 5 ESXi hosts or 50virtual machines.

QUESTION 93An organization is considering buying hosts that have one three-port NIC rather than buying hosts that havethree one-port NICs. Is this a good idea? Why or why not?

A. This is a good idea; one three-port NIC means fewer PCI slots.B. This is a good idea; one card is cheaper than three.C. This is not a good idea; one card translates to a single point of failure.D. This is not a good idea; three-port NICs are expensive

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:If the one three-port NIC fails, you will usually lose all three ports on the NIC. It would be a better solution to use

Page 32: Exam Code: VCAP5-DCD

three one-port NICs instead. You lose one card, and you lose only one port.

QUESTION 94During the design phase, one of the constraints listed is that because the organization is already using SQLServer 2008 in-house, a SQL Server database would have to be used for the vCenter Server. Because of theconstraint, ______________.

A. the organization would have to use VCSA since it supports SQL ServerB. the organization would have to use the Windows versions of the vCenter Server, but the database would

have to be internal to the vCenter ServerC. either the VCSA or the vCenter Server can be usedD. the Windows version of vCenter Server would have to be used because VCSA does not support SQL

Server

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:The VCSA is a Linux appliance and at this time does not support SQL Server. The Windows version of thevCenter Server would have to be used because it does support SQL Server.

QUESTION 95You have a requirement to create a three-tiered application as part of a virtual machine's design. Therequirement includes the ability to start up and shut down the tiers in a given order and to be able to ensure thatthe three-tiered application gets the resources it needs. Which would be the best option?

A. Put all the tiers in a resource pool and manage resources via the resource pool settingsB. Create a vApp and place the three tiers in it. Configure the startup/shutdown options and configure

resources via the vAppC. Ensure that all three tiers are on the same vSwitch and use the ESXi host VM startup and shutdown optionsD. Manage the three tiers as three separate virtual machines

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:Of all these options, only a vApp can offer startup, shutdown, and resource control options.

QUESTION 96You have been tasked with creating a new domain controller in the vSphere environment to replace thephysical domain controller. You are trying to determine how much memory to give the virtual machine. What isyour best option?

A. Create the VM to match the memory of the domain controllerB. Give the VM as much memory as possible to ensure optimal performanceC. Read the vendor documentation and base your memory setting on thatD. Look at the long-term memory metrics of the server and have the memory setting match the maximum

memory used by the domain controller

Correct Answer: DSection: (none)Explanation

Page 33: Exam Code: VCAP5-DCD

Explanation/Reference:Explanation:Viewing the memory performance data of the physical host can give you a solid understanding of how memoryis used on the host and gives a good indication of the amount of memory you should set up for the replacementvirtual machine.

QUESTION 97It is a best practice to give a virtual machine a single virtual CPU unless there is a compelling reason to give avirtual machine more than one virtual CPU.

A. TrueB. False

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:A majority of your virtual machines can run with a single vCPU. Unless the application specifically requiresmultiple vCPUs, try to start with one.

QUESTION 98The swap file must always be stored with the other virtual machine files.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:A virtual machine's swap file can be stored separately on a local or shared datastore. This is a good option ifyou are replicating storage to another location and do not wish to replicate files that are not needed at thereplicated site.

QUESTION 99Part of your design includes updating VMware tools and virtual hardware to a newly updated vSphere 5.1architecture. What is the best method for updating tools and hardware?

A. Manually update each virtual machineB. Don't bother updating the VMs; the new version of hardware and tools are not necessaryC. Use Update Manager to update all the virtual machines at onceD. Use Update Manager to help update the virtual machines in groups, as maintenance windows allow

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:Using Update Manager is the best way to upgrade multiple virtual machines in an automated fashion. Youwould not want to update them all at once because it would be time- consuming and would require a lot ofresources and lots of reboots. As a result, there might not be enough time to finish within a maintenance

Page 34: Exam Code: VCAP5-DCD

window.

QUESTION 100Which of the following is a good way to set a memory reservation?

A. Use reservations on all virtual machines to ensure that they are all guaranteed memory.B. Set a reservation to a virtual machine's available memory to avoid creating a swap file.C. Never set a reservation on a virtual machine.D. Set a reservation only on a critical virtual machine, with the reservation set to the minimum amount of

memory needed for acceptable performance.

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:Setting reservations should be the exception and not the rule. The reservation should be set to the minimumamount required for acceptable performance.

QUESTION 101Which type of virtual disk takes the longest to create but performs the best?

A. Thin provisionedB. Eager-zeroC. Lazy-zeroD. Flat

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:An eager-zero disk allocates and zeroes out all the block at once. While this type of disk takes significantlylonger to create, the disk performs better than the others because the other disks require the block to be zeroedout before writing to the block. Since the blocks have already been zeroed with eager-zero, that is notnecessary.

QUESTION 102All virtual machine files should always be on the same datastore.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:Some applications require different types of performance on the multiple disks they require. If this is the case, itis acceptable to put virtual disks on two different datastores that have different performance and RAID features.

QUESTION 103Which metric displays the amount of time, in milliseconds, it takes for a virtual CPU to get processing time on aphysical CPU?

Page 35: Exam Code: VCAP5-DCD

A. CPU WaitB. BallooningC. CPU ReadyD. pCPU

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:CPU Ready is a metric that can be viewed using performance charts on the Web client or the vSphere clientthat shows how long a virtual CPU had to wait for a physical CPU to become available.

QUESTION 104A validation plan does not validate _____________.

A. the designB. system functionalityC. that system requirements match the functionality of the designD. topics outside the scope of the design

Correct Answer: DSection: (none)Explanation

Explanation/Reference:Explanation:A validation plan should validate the design, should verify that the system operates in accordance with thefunctional requirements, and should ensure that all requirements are met.

QUESTION 105Which VMware tools driver is the balloon driver?

A. VMMEMCTLB. VSSC. VLanceD. None of the above

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:VMMEMCTL is the balloon driver. It is installed on any virtual machine that has VMware tools installed.

QUESTION 106Which of the following can a gap state analysis help achieve?

A. The visionB. The logical designC. A list of best practices

Page 36: Exam Code: VCAP5-DCD

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 107Which of the following tools would enable a Windows administrator to complete a state analysis of a virtualWindows 2008 Server guest machine without requiring access to the vSphere platform?

A. VMware Perfmon DLLB. resxtopC. PowerCLI monitor script

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 108Which of the following is a list of attributes that can be used as a checklist for ensuring good design thoughts?

A. The project requirementsB. The infrastructure qualitiesC. The project design choices

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 109A requirement in a server consolidation project states: "The consolidation ratio must be as high as possible."This has resulted in a lower number of larger-capacity hosts in the vSphere HA cluster.Which of the following is true?

A. The restart time of a VM could be greater than when using smaller hosts.B. The restart time of a VM could be lower than when using smaller hosts.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 110A host has three dual-port network cards. What is the maximum number of vSwitches that can be integratedwith the physical network, assuming that network redundancy is not a requirement?

A. 3

Page 37: Exam Code: VCAP5-DCD

B. 6C. 256D. 512

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 111You are a platform designer constructing a physical design from an existing approved logical design. Out of thevendor proposals, there are two proposed solutions that could be used. Which of the following options is themost important factor when making a decision?

A. Community and vendor-based best practicesB. Existing vendor relationshipsC. Project requirementsD. Project budget

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 112A validation plan is used to do which of the following? (Select all that apply.)

A. Verify the designB. Verify that the system is functionalC. Verify that the system meets requirementsD. Meet current best practices

Correct Answer: ABCSection: (none)Explanation

Explanation/Reference:Explanation:

QUESTION 113vSphere cluster functionality such as DRS and HA does not need to be part of a validation plan. This kind ofdocumentation is only concerned with guest VM workload validation, not platform-wide validation.

A. TrueB. False

Correct Answer: BSection: (none)Explanation

Explanation/Reference:Explanation:

Page 38: Exam Code: VCAP5-DCD

QUESTION 114The technical approach and order of delivery can have an impact on which of the following? (Select all thatapply.)

A. Overall delivery timeB. People resource contention (right person, right time, right task)C. Validation phase duration

Correct Answer: ABCSection: (none)Explanation

Explanation/Reference:

QUESTION 115You are a VMware architect employed to design and build application environments and the underlying platformfor a software development company. The company is using a "dev-ops" approach and has engaged with youat the beginning of the first planning meeting/pre-sprint.The software has yet to be written. However, you have some high-level specifications that are subject tochange at each of the early meetings.

The ______ is more logical for virtual machine sizing.

A. predictive sizing approach based on current softwareB. adaptive sizing approach

Correct Answer: BSection: Predictive/AdaptiveExplanation

Explanation/Reference:Explanation:There are two types of scaling approaches in virtual platforms: adaptive and predictive. Both approaches areusable; however, a designer must work out which is the best approach for each project.

The adaptive approach to guest virtual machine design is a major advantage that virtualization technologybrings to a datacenter. It allows a guest virtual machine to be created initially on a few metrics or high-levelrequirements (such as a limited budget) and scaled (that is, grown, not shrunk) through the virtual machinelifecycle. In many cases, this scaling can be performed hot/live without outage/downtime to the runningapplications.

The predictive approach, on the other hand, requires more planning and research, and you must know themetrics before deployment. The advantage here is that once the virtual machine has been deployed, onlyapplication maintenance is required. The application requirements are known.

Chapter 5, Design Approaches

QUESTION 116You have been asked to design a virtual machine for a new application developed in-house. The application willbe load tested before it is finally made production ready. The application developers have createddocumentation based on data flow and entity dependency. The functionality of the application is critical to thebusiness for a defined project with a client base of a maximum of 12,000 users. Which of the following scalingapproaches would best suit this scenario?

A. PredictiveB. Adaptive

Page 39: Exam Code: VCAP5-DCD

Correct Answer: ASection: Predictive/AdaptiveExplanation

Explanation/Reference:Explanation:

QUESTION 117As a designer, you must either use a predictive or adaptive approach to creating virtual machines.You cannot use a combination of the two approaches.

A. TrueB. False

Correct Answer: BSection: Predictive/AdaptiveExplanation

Explanation/Reference:Explanation:In some instances, a combination of the two approaches might be best.

QUESTION 118The VMware hot add and hot plug functionality is most useful for a(n) __________ scaling approach.

A. adaptiveB. predictive

Correct Answer: ASection: Predictive/AdaptiveExplanation

Explanation/Reference:Explanation:There are two types of scaling approaches in virtual platforms: adaptive and predictive. Both approaches areusable; however, a designer must work out which is the best approach for each project.The adaptive approach to guest virtual machine design is a major advantage that virtualization technologybrings to a datacenter. It allows a guest virtual machine to be created initially on a few metrics or high-levelrequirements (such as a limited budget) and scaled (that is, grown, not shrunk) through the virtual machinelifecycle. In many cases, this scaling can be performed hot/live without outage/downtime to the runningapplications.The predictive approach, on the other hand, requires more planning and research, and you must know themetrics before deployment. The advantage here is that once the virtual machine has been deployed, onlyapplication maintenance is required. The application requirements are known.

QUESTION 119You are a VMware technical consultant for an application development project. The system consists of amultitier application. The team consists of you, five developers, and a project manager. At the project kickoffmeeting, you are tasked with creating the servers for each stage of the development life cycle the team isusing: development, testing, staging, and production. During the meeting, you come to the conclusion that thetechnical specifications have yet to be defined or will likely change. Which of the following scaling approachesfor guest workload design would be most appropriate?

A. AdaptiveB. Predictive

Correct Answer: A

Page 40: Exam Code: VCAP5-DCD

Section: Predictive/AdaptiveExplanation

Explanation/Reference:Explanation:There are two types of scaling approaches in virtual platforms: adaptive and predictive. Both approaches areusable; however, a designer must work out which is the best approach for each project.The adaptive approach to guest virtual machine design is a major advantage that virtualization technologybrings to a datacenter. It allows a guest virtual machine to be created initially on a few metrics or high-levelrequirements (such as a limited budget) and scaled (that is, grown, not shrunk) through the virtual machinelifecycle. In many cases, this scaling can be performed hot/live without outage/downtime to the runningapplications.The predictive approach, on the other hand, requires more planning and research, and you must know themetrics before deployment. The advantage here is that once the virtual machine has been deployed, onlyapplication maintenance is required. The application requirements are known.

QUESTION 120You are working on a virtual guest design for the deployment of a critical business application. The softwarevendor has provided you with very few application requirements for projected workloads. Which of the followingscaling approaches does this describe?

A. AdaptiveB. Predictive

Correct Answer: ASection: Predictive/AdaptiveExplanation

Explanation/Reference:Explanation:There are two types of scaling approaches in virtual platforms: adaptive and predictive. Both approaches areusable; however, a designer must work out which is the best approach for each project.The adaptive approach to guest virtual machine design is a major advantage that virtualization technologybrings to a datacenter. It allows a guest virtual machine to be created initially on a few metrics or high-levelrequirements (such as a limited budget) and scaled (that is, grown, not shrunk) through the virtual machinelifecycle. In many cases, this scaling can be performed hot/live without outage/downtime to the runningapplications.The predictive approach, on the other hand, requires more planning and research, and you must know themetrics before deployment. The advantage here is that once the virtual machine has been deployed, onlyapplication maintenance is required. The application requirements are known.

QUESTION 121Which of the following type of discovery methods used in state-analysis techniques is more likely to affectapplication or server performance.

A. ActiveB. PassiveC. Both A and B

Correct Answer: ASection: Active/Passive Discovery MethodsExplanation

Explanation/Reference:Explanation:There are two types of discovery methods: active and passive. Active discovery methods can run processesthat are detrimental and can impact a system. They normally require an agent.With passive discovery methods, data is obtained in a non-impact, non-intrusive manner, with no agents.

Page 41: Exam Code: VCAP5-DCD

Obtaining and interpreting/presenting data such as this normally requires more experience.

Chapter 2, Selecting the Best Tool for the Job

QUESTION 122You are a VMware consultant who has been hired to take over a mismanaged VMware vSphere 5 platformestate. You are presented with the vCenter administrator password and given the following information.

The system has full production support from VMware.

The platform has been suffering from performance problems for two weeks.

No documentation exists.

Your role is to design and implement a platform that meets the following requirements:

- R001: Stable for current workloads- R002: Supportable by operations staff

The preferred method for information gathering in this case should be a passive discovery.

A. TrueB. False

Correct Answer: ASection: Active/Passive Discovery MethodsExplanation

Explanation/Reference:Explanation:There are two types of discovery methods:Active discovery can run processes which are detrimental and can impact a system, and normally requires anagent.With passive discovery, data is obtained in a non-impactful, non-intrusive manner with no agents. Data such asthis normally needs more experience to obtain and interpret/present.

QUESTION 123Active discovery methods require agents.

A. TrueB. False

Correct Answer: ASection: Active/Passive Discovery MethodsExplanation

Explanation/Reference:Explanation:There are two types of discovery methods: active and passive. Active discovery methods can run processesthat are detrimental and can impact a system. They normally require an agent.With passive discovery methods, data is obtained in a non-impact, non-intrusive manner, with no agents.Obtaining and interpreting/presenting data such as this normally requires more experience.

QUESTION 124Passive discovery methods may impact the platform used for monitoring.

A. TrueB. False

Page 42: Exam Code: VCAP5-DCD

Correct Answer: BSection: Active/Passive Discovery MethodsExplanation

Explanation/Reference:Explanation:There are two types of discovery methods: active and passive. Active discovery methods can run processesthat are detrimental and can impact a system. They normally require an agent.With passive discovery methods, data is obtained in a non-impact, non-intrusive manner, with no agents.Obtaining and interpreting/presenting data such as this normally requires more experience.

QUESTION 125A recovery time objective (RTO) is ___________.

A. the point to which data has to be recovered after a failureB. the amount of time it takes to recover a system from a failureC. the plan to restore a system after a failureD. an agreement with the customer on a predefined level of service

Correct Answer: BSection: RTO/RPOExplanation

Explanation/Reference:Explanation:RTO is the amount of time it must take to recover a system from failure.

QUESTION 126A multitier website has an RTO of 4 hours and an RPO of 15 minutes. The database crashes at 5 p.m. andcauses the website to be unavailable. Which of the following is true? (Select all that apply.)

A. The website must be restored by 5:15 p.m.B. The website must be restored by 9 p.m.C. At restore time, the data must be correct from at least from 4:45 p.m.D. At restore time, the data must be from at least 1 p.m.

Correct Answer: BCSection: RTO/RPOExplanation

Explanation/Reference:Explanation:

QUESTION 127An application has an SLA which states that the application must be restored within 12 hours, with no morethan 10 minutes of data loss. This means the application has an RTO of 10 minutes and an RPO of 12 hours.

A. TrueB. False

Correct Answer: BSection: RTO/RPOExplanation

Explanation/Reference:

Page 43: Exam Code: VCAP5-DCD

Explanation:The RTO is the amount of time until a crashed application should be back online. The RPO is the toleratedamount of data loss.

QUESTION 128An application has an SLA which states that the application must be restored within 12 hours, with no morethan 10 minutes of data loss. This means the application has an RTO of 12 hours and an RPO of 10 minutes.

A. TrueB. False

Correct Answer: ASection: RTO/RPOExplanation

Explanation/Reference:Explanation:The RTO is the amount of time until a crashed application should be back online. The RPO is the toleratedamount of data loss.

QUESTION 129You are VMware architect working at a large enterprise where a new VMware platform is being installed.

Based on conversations with the business, you establish that the RTO requirement is 8 hours, and the RPOrequirement is 15 minutes. After months of successful use, the system crashes at 4 p.m.To meet the project SLA, _____________. (Choose two)

A. the application must be brought online and be accessible to users by midnight.B. the application must be brought online and be accessible to users by 4:15 p.m.C. when the application is brought online the data must be from a version as of 3:45 p.m.D. when the application is brought online the data must be from a version as of 8 p.m. the night before.

Correct Answer: ACSection: RTO/RPOExplanation

Explanation/Reference:Explanation:The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes torestore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to whichthe system needs to be restored following a failure.

QUESTION 130Active discovery methods may impact the platform used for monitoring.

A. TrueB. False

Correct Answer: ASection: Active/Passive Discovery MethodsExplanation

Explanation/Reference:Explanation:There are two types of discovery methods: active and passive. Active discovery methods can run processesthat are detrimental and can impact a system. They normally require an agent.With passive discovery methods, data is obtained in a non-impact, non-intrusive manner, with no agents.

Page 44: Exam Code: VCAP5-DCD

Obtaining and interpreting/presenting data such as this normally requires more experience.

QUESTION 131VMware Capacity Planner is an example of a(n) __________ discovery tool.

A. activeB. passive

Correct Answer: BSection: Active/Passive Discovery MethodsExplanation

Explanation/Reference:Explanation:There are two types of discovery methods: active and passive. Active discovery methods can run processesthat are detrimental and can impact a system. They normally require an agent.With passive discovery methods, data is obtained in a non-impact, non-intrusive manner, with no agents.Obtaining and interpreting/presenting data such as this normally requires more experience.

http://www.gratisexam.com/

QUESTION 132Which quality of a good design deals with backup and restoration?

A. AvailabilityB. ManageabilityC. PerformanceD. Recoverability

Correct Answer: DSection: Design Phases & QualitiesExplanation

Explanation/Reference:Explanation:Recoverability deals with recovering from a component or system outage with minimal data loss, in accordancewith an organization's RTO and RPO.

QUESTION 133When designing a storage platform, which of the following should be considered as part of the overall design?

A. CapacityB. I/O requirements of the applications to be supportedC. Disk latency toleranceD. Growth rateE. All of the above

Correct Answer: ESection: StorageExplanation

Page 45: Exam Code: VCAP5-DCD

Explanation/Reference:Explanation:A storage platform logical design requires in-depth analysis of factors that can affect applications. In the case ofstorage, aspects that relate to the physical layer--such as the amount of usable space required for services; thesize, number, and speed of disks; and how fast the data is being produced--could have a substantial impact tothe storage platform.

Chapter 4, Storage Design - The Logical & Physical Approaches

QUESTION 134You are working on a hybrid cloud project, where production applications (yet to be fully developed) are to bedeployed. Which of the following is a project requirement?

A. The production data must be in the UK at all times.B. The hosting partner provides sufficient resources without over commitment to support application load.C. The hosting provider meets uptime expectations.D. The development team provides the software on time.

Correct Answer: ASection: Project FactorsExplanation

Explanation/Reference:Explanation:A requirement is a definable and measurable project item. It must be part of the delivery, and its removalcannot be justified.

Chapter 2, Definitions of Key Terms

QUESTION 135You are a virtualization consultant working on a DR project. You have proposed a solution that uses SANreplication technology to replicate production virtual machine files. This meets the cold standby requirement.

Which of the following could be a design constraint?

A. The hardware currently being used in the datacenter is out of support.B. The company is undecided about the choice of centralized storage to be used in the enterprise.C. The company is at the end of year 1 of a 3-year contract for the point-to-point link between Site A and SiteD. This link is currently 10 MB.

Correct Answer: CSection: Project FactorsExplanation

Explanation/Reference:Explanation:An item from the current state analysis that would restrict or change a design choice is potentially a constraint.Such factors can limit a design and in some cases prevent the realization of a project vision.

Chapter 2, Gathering Information and Spotting the Gaps

QUESTION 136A project vision in some cases may not be achieved due to constraints, risks, and other project factors.However, a project vision is required to guide a project throughout the life cycle.

A. True

Page 46: Exam Code: VCAP5-DCD

B. False

Correct Answer: ASection: Project FactorsExplanation

Explanation/Reference:Explanation:The technical design process enables a platform designer to work in a methodical way and with others whohave similar objectives. The vision is the endpoint--the environment or situation whereby the business wouldideally like to be following the process.

Chapter 1, The Technical Design Process

QUESTION 137Only a software vendor develops a standard process or configuration.

A. TrueB. False

Correct Answer: BSection: Best PracticesExplanation

Explanation/Reference:Explanation:A best practice is based on experience with delivering a solution. A new product will have limited best-practiceinformation except for vendor- or vendor-partner-based recommendations. The longer a technology is used in acommunity, the more potential success; therefore, best practices may be recommended by non-vendor-relatedpeople. It is up to a designer to validate this information rather than ignore it straightaway.

Chapter 6, Validation, Thoughts, and Processes

QUESTION 138At a late stage in the software development life cycle of a production application developed in- house, anunfortunate issue was identified when the application was deployed to the production vSphere cluster. Theproduction core stacked switch has capacity issues, and this is having a serious impact on all applications forwhich the switch is providing network services. Within the test system, the application works as intended in thesingle test VLAN and with a single-host configuration.

Which of the following could be tried to help in this situation, from a vSphere perspective? (Choose two)

Case Study Title (Case Study):You are the technical designer for a vSphere platform transformation project. After conducting SME interviewsand using various platform information-gathering methods, you have created a high-level design document.

This document specifies the following:

Requirements:

R1. The solution must not have a single point of failure.R2. Production applications must not have an outage of more than 10 seconds.R3. Data must be based in the UK.R4. There is a 7-year retention policy for contracts.R5. Applications should support existing and developing workloads for the next 3 years' growth.

Spec of servers:

Web 1 vCPU, 2 GB RAM, 100 GB storage

Page 47: Exam Code: VCAP5-DCD

App 1 vCPU, 4 GB RAM, 100 GB storageDB 2 vCPU, 16 GB RAM, 750 GB storage

A. Redevelop the application for a virtual platformB. Place the application into a single-vApp networkC. Add DRS rules to keep network traffic within the same host, where possibleD. Configure network I/O control

Correct Answer: CSection: (none)Explanation

Explanation/Reference:Explanation:If you limit the application traffic to a specific dedicated network (that is, a separate VLAN) and using enforcedDRS affinity rules, the application traffic will not traverse the ESXi host's physical network interfaces. This willensure that the impact of the application is minimized, while also ensuring that the application itself is notlimited. The application servers already have vCPU settings. This suggests that the system has already beingvirtualized in both types of environments. Network I/O control could be useful in the event of contention, but therole of a designer would be to plan to prevent contention where possible; other options would be morebeneficial. In addition, Requirement 5 specifies that the system should work with workloads over the next3years. Network I/O control would suggest contention very early in the platform history.

Chapter 4, Network - Logical and Physical Design to allow applications to flow

http://www.gratisexam.com/