excavation risk assessment sheet

Upload: ibrahim-janjua

Post on 02-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Excavation Risk Assessment Sheet

    1/3

    Natural Garden Risk Assessment Page Number 1 of 3

    TASK SPECIFIC RISK ASSESSMENT SHEETTASK: EXCAVATION, PIPE LAYING AND BACKFILLING

    Item

    No.SIGNIFICANT HAZARDS / RISKS

    PERSONS

    at RISK

    Beforem

    itigation

    HighMe

    diumLow

    (HML)

    ACTIONS REQUIRED

    TO REDUCE OR CONTROL RISKS

    ACTION BY:

    WHEN BY:

    Afterm

    itigation

    HighMe

    diumLow

    (H

    ML)

    1

    Electric Connection

    Electric shock

    Operatives

    Sub-Contractor,&Visitors

    Medium

    All electrical tools/installations to be regularlychecked

    Gloves to be worn at all times. Only trained operatives to be used. Task specific PPE should be worn.

    Forman,Supervisor,Operator &

    banks man

    Low

    2 Usage of Equipment, Excavator etc

    Operatives

    Sub-Contractor,&Visitors

    Medium

    Ensure that all equipment shall be inspectedprior to start work

    Make sure that the operator is certified

    Ensure the equipment are fitted with reversealarm

    Ensure the availability of signal man at all theworking time.

    Supervisor,

    Operator &banks man

    Low

    3

    Falls of persons /Fall of materials andTrench collapse

    Operatives

    Sub-

    Contractor&Visitors

    High

    Barricade the area Ensure supervisors monitor site regularly on

    excavated locations Permit system should be strictly followed.

    Keep the access area cleared; keep the spoil 1meter away from the edge. Provides properaccess and egress every 30 meters, erect

    hard barricades with signage. Only authorized and competent operatives that

    have received the required training arepermitted to work in excavation. Allexcavations deeper than 1.2m to be batteredback or shored up / supported. Trench to bebattered or benched above 1.2m deep.

    Forman,Supervisor,

    Operator &banks man

    Low

  • 8/11/2019 Excavation Risk Assessment Sheet

    2/3

    Natural Garden Risk Assessment Page Number 2 of 3

    Item

    No.SIGNIFICANT HAZARDS / RISKS

    PERSONS

    at RISK

    B

    eforemitigation

    HighMediumLow

    (HML)

    ACTIONS REQUIRED

    TO REDUCE OR CONTROL RISKS

    ACTION BY:

    WHEN BY:

    Aftermitigation

    HighMediumLow

    (HML)

    Excavation support must be provided in softunsuitable ground (sheet piles, boxes etc)

    4 Vehicles driving into excavated area

    Operatives

    Sub-Contractor

    Medium

    Barricade the area Provide proper signage, warning lights etc Do not allow any vehicle to excavation area

    with Out proper access made Ensure all vehicle movements are minimum

    2mtr away from the excavation edge

    Supervisor,Operator &

    banks man` Low

    5PVC Cutter

    Hand and fingers can cut during use

    Operatives Medium Gloves should be worn all the time while using

    the cutterForman,

    Supervisor,Low

    6Existing pipes & buried cable beingstruck

    Operatives

    Sub-Contractor,&Visitors

    Medium

    PTW to be obtained before starting the workand toolbox talk should be conducted.

    Verify utility service drawings and mark theservices on the ground if any.

    Identify and cordon the area in a safe method Conduct the toolbox talk before work starts. Close supervision at all times

    Ensure there is no contamination of hydrocarbons,etc

    FormanSupervisor,Operator &

    banks man

    Low

    7Backfilling

    Operatives

    Sub-Contractor

    Medium Ensure excavation is clear of operatives.

    Banks man to direct JCB driver. Do not tipmaterial too close to trench. Ensure stop logsin place. Ensure PPE is worn as appropriate.Driver to ensure stability of machine at alltimes, All personnel to make themselvesknown to driver when approaching. Banksmanto warn personnel. Mirrors to be clean

    Forman,Supervisor,Operator &

    banks manLow

  • 8/11/2019 Excavation Risk Assessment Sheet

    3/3

    Natural Garden Risk Assessment Page Number 3 of 3

    Item

    No.SIGNIFICANT HAZARDS / RISKS

    PERSONS

    at RISK

    B

    eforemitigation

    H

    ighMediumLow

    (HML)

    ACTIONS REQUIRED

    TO REDUCE OR CONTROL RISKS

    ACTION BY:

    WHEN BY:

    Aftermitigation

    H

    ighMediumLow

    (HML)

    8 Heat exhaustion and Heat StrokeOperatives

    Sub-Contractor

    Medium

    Cold Drinking Water: must ensure clean andcold drinking water shall be provided at worksites. In any time during the summer period,

    Heat Exhaustion Rooms: must set up withproper cooling devices to control heatexhaustion cases.

    Summer Working Instructions/ campaigns inprogressing workforce awareness on summerworking and its precautionary measures forprotecting themselves from heat related illness

    such as sun burns, heat cramps, heatexhaustion and heat stress.

    Forman,Supervisor,Operatives Low

    Completed by:

    Name: Signature: Job Title: Date:

    Jawad Ghani Office Manager 27-02-14