excavation risk assessment sheet
TRANSCRIPT
-
8/11/2019 Excavation Risk Assessment Sheet
1/3
Natural Garden Risk Assessment Page Number 1 of 3
TASK SPECIFIC RISK ASSESSMENT SHEETTASK: EXCAVATION, PIPE LAYING AND BACKFILLING
Item
No.SIGNIFICANT HAZARDS / RISKS
PERSONS
at RISK
Beforem
itigation
HighMe
diumLow
(HML)
ACTIONS REQUIRED
TO REDUCE OR CONTROL RISKS
ACTION BY:
WHEN BY:
Afterm
itigation
HighMe
diumLow
(H
ML)
1
Electric Connection
Electric shock
Operatives
Sub-Contractor,&Visitors
Medium
All electrical tools/installations to be regularlychecked
Gloves to be worn at all times. Only trained operatives to be used. Task specific PPE should be worn.
Forman,Supervisor,Operator &
banks man
Low
2 Usage of Equipment, Excavator etc
Operatives
Sub-Contractor,&Visitors
Medium
Ensure that all equipment shall be inspectedprior to start work
Make sure that the operator is certified
Ensure the equipment are fitted with reversealarm
Ensure the availability of signal man at all theworking time.
Supervisor,
Operator &banks man
Low
3
Falls of persons /Fall of materials andTrench collapse
Operatives
Sub-
Contractor&Visitors
High
Barricade the area Ensure supervisors monitor site regularly on
excavated locations Permit system should be strictly followed.
Keep the access area cleared; keep the spoil 1meter away from the edge. Provides properaccess and egress every 30 meters, erect
hard barricades with signage. Only authorized and competent operatives that
have received the required training arepermitted to work in excavation. Allexcavations deeper than 1.2m to be batteredback or shored up / supported. Trench to bebattered or benched above 1.2m deep.
Forman,Supervisor,
Operator &banks man
Low
-
8/11/2019 Excavation Risk Assessment Sheet
2/3
Natural Garden Risk Assessment Page Number 2 of 3
Item
No.SIGNIFICANT HAZARDS / RISKS
PERSONS
at RISK
B
eforemitigation
HighMediumLow
(HML)
ACTIONS REQUIRED
TO REDUCE OR CONTROL RISKS
ACTION BY:
WHEN BY:
Aftermitigation
HighMediumLow
(HML)
Excavation support must be provided in softunsuitable ground (sheet piles, boxes etc)
4 Vehicles driving into excavated area
Operatives
Sub-Contractor
Medium
Barricade the area Provide proper signage, warning lights etc Do not allow any vehicle to excavation area
with Out proper access made Ensure all vehicle movements are minimum
2mtr away from the excavation edge
Supervisor,Operator &
banks man` Low
5PVC Cutter
Hand and fingers can cut during use
Operatives Medium Gloves should be worn all the time while using
the cutterForman,
Supervisor,Low
6Existing pipes & buried cable beingstruck
Operatives
Sub-Contractor,&Visitors
Medium
PTW to be obtained before starting the workand toolbox talk should be conducted.
Verify utility service drawings and mark theservices on the ground if any.
Identify and cordon the area in a safe method Conduct the toolbox talk before work starts. Close supervision at all times
Ensure there is no contamination of hydrocarbons,etc
FormanSupervisor,Operator &
banks man
Low
7Backfilling
Operatives
Sub-Contractor
Medium Ensure excavation is clear of operatives.
Banks man to direct JCB driver. Do not tipmaterial too close to trench. Ensure stop logsin place. Ensure PPE is worn as appropriate.Driver to ensure stability of machine at alltimes, All personnel to make themselvesknown to driver when approaching. Banksmanto warn personnel. Mirrors to be clean
Forman,Supervisor,Operator &
banks manLow
-
8/11/2019 Excavation Risk Assessment Sheet
3/3
Natural Garden Risk Assessment Page Number 3 of 3
Item
No.SIGNIFICANT HAZARDS / RISKS
PERSONS
at RISK
B
eforemitigation
H
ighMediumLow
(HML)
ACTIONS REQUIRED
TO REDUCE OR CONTROL RISKS
ACTION BY:
WHEN BY:
Aftermitigation
H
ighMediumLow
(HML)
8 Heat exhaustion and Heat StrokeOperatives
Sub-Contractor
Medium
Cold Drinking Water: must ensure clean andcold drinking water shall be provided at worksites. In any time during the summer period,
Heat Exhaustion Rooms: must set up withproper cooling devices to control heatexhaustion cases.
Summer Working Instructions/ campaigns inprogressing workforce awareness on summerworking and its precautionary measures forprotecting themselves from heat related illness
such as sun burns, heat cramps, heatexhaustion and heat stress.
Forman,Supervisor,Operatives Low
Completed by:
Name: Signature: Job Title: Date:
Jawad Ghani Office Manager 27-02-14