    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 1

    Volum e 1 Ex ec ut ive summ ary

    Contents

    Executive summary ........................................................................................................ 3Stage 2 approval criteria ................................................................................................ 5Stage 2 Submission structure map ................................................................................ 7

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    2/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 2

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    3/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 3

    Exec ut ive summ ary

    We are pleased to submit the draft stage 2 submission for Witton Park High School

    (WP) and New East Blackburn Learning Community (NEB). The solutions for New

    East Blackburn (incorporating Crosshill School) and Witton Park (incorporating

    Newfield pupils) provide flexible and inspiring environments in meeting the LA SfC and

    vision and the schools design briefs. The LEP has continued to challenge and support

    colleagues from the schools and LA during the design process to deliver a robust

    educational vision.

    The schemes are affordable, based on the agreed TUPE transfer proposals for

    catering and grounds staff at Witton Park. These facilities offer excellent value formoney, with more for less having been achieved in comparison with the sample

    schools and external benchmarks.

    The final stage 2 submission will be made on 7th September following the completion

    of the funding competition and receipt of full planning permission on the 26th August.

    We are committed to supporting Blackburn with Darwen LA to achieve its aims of

    transforming learning, communities and lives and we look forward to working with you

    through the Financial Close period to achieve them together. Whilst FC is scheduled to

    occur on 27th November 2010, we will work with the LA and supply chain to achieve an

    earlier close.

    Transforming learning

    As 100% new build PFI schools, the new WP and NEB schools will raise the

    aspirations of all those living and working in the surrounding communities. They will be

    beacons of learning and community, welcoming and highly visible in their respective

    communities in Blackburn, which students, parents, families and members of the

    surrounding communities can proudly call their own.

    Each of the spaces provide fully integrated design solutions able to function flexibly in

    traditional, transitional or transformational (3 Ts) layouts. The integrated strategy

    incorporates FFE, ICT, M&E and architectural layout to ensure maximum flexibility and

    usability of space.

    The ICT infrastructure will facilitate anytime/anywhere learning. The bespoke ICT

    design solutions respond to the requirements of the schools and meet the LA output

    specification. The solutions include a 1:2 pupil device ratio which includes an

    appropriate mix of fixed and mobile devices, and a 1:1 teacher/HLTA device ratio as

    all teachers and HLTAs will receive a new laptop. There will be further opportunities to

    refine and develop the final ICT solution for the school during the baselining exercise

    which will take place 6 9 months before the school opens (i.e. from January March

    2012).

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    4/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 4

    Transforming communities

    We recognise that these brand new state-of-the-art facilities will be invaluable to the

    neighbourhoods and communities they serve. With this in mind, the stage 2 designs

    have been developed to truly embrace the concept of community use. The new

    community out-of-hours entrance/reception areas and additional lifts ensure that all the

    sporting facilities (sports hall, activity studio, fitness suite, changing rooms including

    showers and toilets, hygiene rooms/ disabled change and PE classrooms) will be

    available for community use independently of the remaining buildings and during the

    school day if required. It is expected that the full range of facilities will be open to the

    community, and the zoning capability in the design will enable controlled and secure

    access to all appropriate areas of the schools.

    We have enjoyed many conversations with the schools and others about community

    use and how the new school will work with partners from other agencies. This has

    been challenging for all involved and we are continuing to respond to the changing

    political and economic climate to ensure that these facilities really can support

    community use out of school hours, and when possible, during the school day.

    In terms of working with partners from other agencies, the stage 2 designs have

    dedicated multi-agency rooms, with a separate access and ICT and WC facilities. We

    are committed to continued working in partnership with the LA, stakeholders and the

    school to ensure that the management arrangements of the facilities truly maximise

    community use and opportunities for partnership working. Our aim has been tomaximise the opportunities for multi-agencies to work in partnership with the school to

    meet, for example, the Every Child Matters (ECM) agenda.

    Transforming lives

    There will be significant spend within the local economy and opportunities for local

    people to benefit from local labour opportunities. The LEP is committed to a minimum

    of 25% of the cost of the new build to be spent locally. This will include further

    commitments to local labour, local apprenticeships, work experience for local students

    and support for local businesses to become part of the Balfour Beatty Education (BBE)

    supply chain.

    441 apprenticeship weeks will be provided on site during the construction phase, and

    a further 150 FM apprenticeship weeks, and 270 ICT apprenticeship weeks during the

    operational phase. This will provide local young people with the opportunity to learn

    more about key trades in a structured local apprenticeship placement.

    In addition, our public arts strategist (Ian Banks) will work alongside the school design

    teams during the construction phase to support the selection of appropriate artist(s) to

    develop exciting public art throughout the school sites.

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    5/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 5

    St age 2 approval c r i te r ia

    In accordance with the Approval Criteria as defined in Paragraph 4.5 of the Strategic

    Partnering Agreement the LEP confirms the following:

    Approval Criteria Reference in Stage 1

    submission

    Whether the costs of the Stage 1 Approved Project are within the Target Costnotified to the LEP by the Local Authority,

    See Volume 5, FinanceResponse

    Whether it has been demonstrated that the Stage 1 Approved Project providesvalue for money in accordance with the provisions of clause 9 and against the

    targets set out in the Continuous Improvement Plan submitted by the PSP aspart of the initial procurement and establishment of the LEP (as the same may

    have been amended from time to time with the agreement of the Local Authority

    and/or the SPB) (for the avoidance of doubt, if the targets set out in theContinuous Improvement Plan or Key Performance Indicators have not been

    met, by reference to the targets that should have been met as at the date of theNew Project Final Approval Submission, then the Local Authority shall be

    entitled to treat the Approval Criteria as not having been satisfied),

    See Volume 5 FinanceResponse

    Whether the Local Authority, acting reasonably, is satisfied that the New Project

    Final Approval Submission meets all the Local Authority Requirements, and ifrelevant in respect of the New Project that the LEP is in compliance with the

    requirements of schedule 5 to the FM contract

    See Section 2 Partnering and

    Section 3 Technical

    Whether any changes or amendments to the form of the relevant TemplateProject Agreement(s) as detailed pursuant to paragraph 4.3.1 (other than for

    project specific reasons reasonably acceptable to the SPB or changesspecifically agreed by the SPB at Stage 1) have been proposed (if such changes

    or amendments have been proposed and they are not acceptable to the AffectedParticipant and PfS then the Approval Criteria in respect of this sub-paragraph4.5.4 would not have been met),

    See Volume 4, Legal andcommercial

    Whether the New Project Final Approval Submission contains all the informationrequired pursuant to paragraph 4.3 (or as otherwise agreed by the parties), and

    See Index reconciling Stage 2deliverables to this submissionabove.

    Whether the implementation of the Stage 1 Approved Project would breach anyLaw.

    Confirmed. Theimplementation of the Stage 1

    Approved Project will not

    breach any laws.

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    6/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 6

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    7/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 7

    Stage 2 Submiss ion s t ruc t ure map

    We have responded to the deliverables within volumes as follows:

    Volume Part Deliverables covered (NPAP

    reference)

    Volume 1 - Executive summary 9

    Volume 2A - Partnering (New EastBlackburn)

    1a-e and 13a

    Volume 2B - Partnering (Witton Park) 1a-e and 13a

    Volume 3A - Technical (New EastBlackburn)

    Part 1 - Design 5, 6, 14, 15

    Part 2 - New Projectdelivery

    24a, b, c, f, g, j, k, l

    Part 3 - FM proposals 4a

    Part 4 - ICT proposals 4b

    Volume 3B - Technical (Witton Park)

    Part 1 - Design 5, 6, 7, 14, 15

    Part 2 - New Projectdelivery

    24a-l

    Part 3 - FM proposals 4a

    Part 4 - ICT proposals 4b

    Volume 4 - Legal and commercial 2, 7, 13b, 21, 24d, 24e, 24hand 24i

    Volume 5 - Finance 3,8,9,10,11,12,16,17,18,19,20,22,23

    Please also refer to the deliverables matrix overleaf

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    8/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 8

    Deliverables matrix

    NPAP

    reference

    Description Location within the submission

    1a a description of the New project (to exceed no more than

    10 pages) to include a detailed commentary on how theproposal specifically meets the requirements of the LA'sstrategy for change making reference to the themes of:

    Choice Diversity and access

    Tackling underperforming schools

    Personalisation and E-learning

    Extended Schools and Integrated Services

    14-19 Agenda

    Inclusion

    To include the wider Community Benefits in all the above

    Volume 2A Partnering (New East

    Blackburn)

    Volume 2B Partnering (Witton Park)

    1b a commentary on the expected contribution of the

    proposal towards the achievement of the CollectivePartnership Targets and Key Performance Indicators

    1c a specific change management plan relating to the projectwith clear reference to the Integrated Change

    Management Strategy

    1d a statement on how lessons learnt from Stage 1 approvaland how these had been addressed at stage 2development

    1e a statement on lessons learnt from the development of

    these specific projects and how the LEP intends toaddress these in future projects.

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    9/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 9

    NPAPreference Description Location within the submission

    2 draft(s) of the relevant Project Agreement(s) identifying (if

    relevant) any and all proposed changes or amendmentsproposed to Template Project Agreement(s) as submitted

    as part of the Stage 1 Approval procedure, together withdetailed reasons for any such changes or amendments

    proposed and an analysis demonstrating value for moneyin accordance with the procedure set out at clauses [ ] to [

    ] of this Agreement;

    To Include :

    Derogations Tables

    Fully marked up schedules to the PA

    Sub contracts

    Interface Agreements

    Full suite commercial docs (changes from existingsample documentation)

    Volume 4 - Legal and commercial

    3 credit committee approval and commitment from funders

    and equity providers (if any) to the drafts referred to insub-paragraph (a)(i) and the proposals generally;

    To Include:

    Commitment from Funders (Draft) Letter of support

    Proposed Funding Terms

    Preliminary tech funders due diligence reports

    Current status & Programme for Credit Committeeapproval

    Equity Providers & Conditions

    Volume 5 - Finance

    4a details of the facilities management proposals in relationto the New Project including in compliance with Clause [ ]

    of the FM Agreement a fully developed New ProjectService Delivery Proposal (as defined by that Agreement)sufficient to satisfy the Authorities Requirements that are

    to be incorporated in any required D&B Contract;

    To Include:

    detailed FM Proposals with changes tracked tosample documentation (CPs and ARs) and reasons

    To include information on pupil engagement andinvolvement with the FM Service

    Volume 3A - Technical (New EastBlackburn), Part 3 - FM proposals

    Volume 3B - Technical (Witton Park),Part 3 - FM proposals

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    10/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 10

    NPAPreference Description Location within the submission

    4b Details of the managed ICT solution in relation to the New

    Project including in Compliance

    Confirmation that the solution for this project fits with the

    agreed area-wide solution. Also that it demonstratescontinuous improvement and innovation ( using Sample

    schemes as a baseline)

    Volume 3A - Technical (New East

    Blackburn), Part 4 - ICT proposals

    Volume 3B - Technical (Witton Park),

    Part 4 - ICT proposals

    5 detailed design solutions (RIBA level D) reflecting anintegrated approach to ICT, FM and building services and

    to be not less than that required at Final bid stage in thesample schemes in the procurement of the LEP;

    Submission to include:

    Introductory statement to explain integrated designconcept (traditional, transitional, transformation)

    Fully worked up CPs. Indicating any changestogether with rationale

    Draft derogations to Sample Schemes ARsincorporating existing developed school specific

    requirements

    Commentary on how the ICT solution for thisproject meets the transformational vision for this

    specific school.

    Demonstration of how ICT has been fully integratedinto the design of this building. (ICT overlays)

    Volume 3A - Technical (New EastBlackburn), Part 1 - Design

    Volume 3B - Technical (Witton Park),

    Part 1 - Design

    6 necessary plans and drawings for the Stage TwoApproved Project [in accordance with the required

    drawings schedule agreed with the Affected Participant]but to be not less than the usual requirements at Final Bid

    stage in the sample schemes in the procurement of the

    LEP;

    As deliverable

    Inc full drawing schedule for CPs

    Volume 3A - Technical (New EastBlackburn), Part 1 - Design

    Volume 3B - Technical (Witton Park),

    Part 1 - Design

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    11/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 11

    NPAPreference Description Location within the submission

    7 relevant detailed planning permissions and any other

    relevant planning approvals (or such lesser confirmationor information in relation to planning as may be agreed

    with the Affected Participant;

    Copy of approval letter drafts

    Copy of ANC (Authority Necessary Consents)

    Authority planning conditions

    Status of other consents

    Volume 4 - Legal and commercial

    8 a financial model including the detailed price estimates forthe Stage 1 Approved Project based on the agreed

    contractual route for the New Project (e.g. unitary chargesfor PFI Project Agreements, milestone payment profile

    under D&B Contracts, the proposed FM Service Charge inrespect of the FM Agreement and a mixture of installation

    payments and service charges for ICT Contracts)identifying any provisional sums (such as insurance costs)

    together with the proposed "Annual Value" for eachProject Agreement for the purposes of clause (b);

    Active financial model based on anticipated market rates(Not hard Coded) linked to proformas with supporting cost

    models for Capex (build rates) and Opex (cost model withpriced TUPE requirements)

    TAB on the model to track changes & identify the impactof changes from stage 1 to stage 2 submission

    Section 6: 2 versions with tracked changes from stage 1 &one clean version

    Demonstrate value for money in relation to ICT

    Volume 5 - Finance

    9 an explanation (together with appropriate supportingevidence) as to why the New Project Final ApprovalSubmission meets the Approval Criteria (as defined in

    paragraph 4.5 of the SPA);

    Refer to deliverable

    Volume 1 - Exec summary

    10 confirmation (or details of any requested variations to

    (with supporting justification)) of the Project ManagementFee referred in paragraph 3.1(g);

    Provide Confirmation

    Volume 5 - Finance

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    12/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 12

    NPAPreference Description Location within the submission

    11 Value for Money assessment

    Detailed report required

    Volume 5 - Finance

    12 an assessment of the progress made by the LEP againstthe value for money and Continuous Improvement Plan

    Refer to deliverable

    Volume 5 - Finance

    13a an assessment of the effect (if any) on any communitygroups and impact on stakeholders

    To include Engagement Activities

    Volume 2A - Partnering (New EastBlackburn)

    Volume 2B - Partnering (Witton Park)

    13b an assessment of the effect of third party agreements,including any potential transfer of any such employees toany LEP Party and the cost implications of such transfer;

    Provide detailed Assessment to include community

    groups and stakeholders

    Volume 4 - Legal and commercial

    14 A final report confirming compliance with the applicable

    Building Bulletins, including but not limited to:

    BB93 Acoustics

    BB100 Fire

    BB101 Natural Ventilation

    BB98 Accommodation (particularly externalprovision)

    To include Design compliance with Sport England

    Technical Derogations

    Volume 3A - Technical (New East

    Blackburn), Part 1 - Design

    Volume 3B - Technical (Witton Park),

    Part 1 - Design

    15 a final report confirming compliance with all regulationsrelating to sporting and external activity areas, includingprovision of suitable drainage and detailing any other risks

    relating to compliance with all necessary consents, e.g.

    Building Regulations and Planning, with approach tomanaging such risk.

    Detailed Report required

    Volume 3A - Technical (New EastBlackburn), Part 1 - Design

    Volume 3B - Technical (Witton Park),

    Part 1 - Design

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    13/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 13

    NPAPreference Description Location within the submission

    16 Fully completed financial and technical proformas,

    including the following sections:

    Utilities (proposed payment mechanism targets)

    Wall to Floor ratio

    Glazing ratio

    GIFA

    Complete all PfS financial + technical proformas with

    active cells (not hard coded) linked to the financial model

    Volume 5 - Finance

    17 Provision of fully rated quantities supporting the Capex, in

    a similar form to that provided for the Sample Schools.

    Fully rated quantities

    Fully completed future funding protocol

    Volume 5 - Finance

    18 A report in relation to the outline impact on FM and LifeCycle costs by comparison to the Sample schemes as

    benchmarking with competent reconciliation of anymaterial variances.

    Detailed report on movement of FM + lifecycle costs fromsample schemes

    Volume 5 - Finance

    19 FM and Life Cycle cost models in similar form to thatprovided for the Sample Schools

    Active cells (not hard coded) linked to the financial model+ priced TUPE list

    Volume 5 - Finance

    20 Detailed pricing schedules in respect of all abnormal and

    external works

    Detailed Pricing Schedules

    Rationale and breakdown explaining allocation of

    abnormals + external works in accordance with PfSguidance

    Volume 5 - Finance

    21 Proposed payment mechanism consequentialunavailability and categorized schedule of

    accommodation.

    Refer to the deliverable

    Final schedule of accommodation reconciled

    Volume 4 - Legal and commercial

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    14/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 14

    NPAPreference Description Location within the submission

    22 A report detailing the savings associated with

    incorporation of results of Legacy F&E survey. Theseresults should be verified through a FF&E survey

    conducted by the LEP during stage 2.

    As the deliverable

    Volume 5 - Finance

    23 A report detailing how the LEP intends to apply

    Guaranteed Minimum Savings to its proposals, with fullreconciliation where these do not apply.

    Focusing on Capex & Opex

    Volume 5 - Finance

    24 a timetable and method statement setting out the stages

    and timescales for the period between achieving Stage 2Approval (as defined in paragraph 4.5(b)(i)) and the

    execution of the relevant Project Agreements (or each of

    the Project Agreements, if more than one) and how therelevant New Project will be delivered which shall include

    (but not be limited to):

    Volume 3A - Technical (New East

    Blackburn), Part 2 - New Projectdelivery

    Volume 3B - Technical (Witton Park),Part 2 - New Project delivery

    24a proposals for the effective management of the

    construction programme;

    Volume 3A - Technical (New East

    Blackburn), Part 2 - New Projectdelivery

    Volume 3B - Technical (Witton Park),

    Part 2 - New

    24b proposals for the decanting of pupils (where a necessarypart of the solution) so that teaching and learning is notdisrupted;

    Volume 3A - Technical (New EastBlackburn), Part 2 - New Projectdelivery

    Volume 3B - Technical (Witton Park),

    Part 2 - New

    24c proposals for the migration from the current ICT service to

    the new managed ICT service which minimises anydisruption to Educational Services and to pupils teaching

    and learning; In addition a Commentary on themanagement of the transition from interim/core service to

    the full BSF service with emphasis on service continuity

    from an educational perspective.

    Volume 3A - Technical (New East

    Blackburn), Part 2 - New Projectdelivery

    Volume 3B - Technical (Witton Park),

    Part 2 - New

    24d confirmation that risks in relation to asbestos, latentdefects ground conditions and/or contamination, if any,

    have all been fully addressed in the draft(s) of the relevant

    Project Agreement(s), priced and are now at the LEPsrisk;

    Volume 4 - Legal and commercial

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    15/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 15

    NPAPreference Description Location within the submission

    24e confirmation that title to the relevant Site(s) issues have

    been resolved and the LEP and any funders are satisfiedwith the same;

    Volume 4 - Legal and commercial

    24f an assessment as to how any benchmarking or markettesting within the New Project will coincide with any other

    Approved Projects;

    Volume 3A - Technical (New EastBlackburn), Part 2 - New Project

    delivery

    Volume 3B - Technical (Witton Park),Part 2 - New

    24g an assessment as to the savings to be generated acrossthe New Project and any Approved Projects with the

    introduction of the New Project particularly on ProjectCompany operational costs, staff costs, lifecycle

    replacement and maintenance and operation of services;

    Volume 3A - Technical (New EastBlackburn), Part 2 - New Project

    delivery

    Volume 3B - Technical (Witton Park),

    Part 2 - New

    24h an explanation as to how the LEP will address and dealwith any existing contractual arrangements that may affect

    the delivery or operation of the New Project;

    Volume 4 - Legal and commercial

    24i confirmation of proposed changes to this Agreement (if

    any);

    Volume 4 - Legal and commercial

    24j details of the nominated Project Service Providers and

    sub-contractors together with evidence and explanation ofthe benchmarking and Market Testing undertaken by the

    LEP in relation to the New Project and their fully worked

    up sub-contracts and any related interface agreements;

    Volume 3A - Technical (New East

    Blackburn), Part 2 - New Projectdelivery

    Volume 3B - Technical (Witton Park),

    Part 2 - New

    24k a completed risk register for the New Project showing thepotential risks identified in relation to the delivery of the

    New Project the occurrence of which are capable of

    adversely affecting the time for completion, cost and/orquality of the New Project, the probability of such risksoccurring and a financial estimate of the most likelyconsequences of each risk occurring together with the

    prioritisation of all continuing risks and an action plan in

    respect of, and risk owners for, all risks prioritised asserious risks;

    Volume 3A - Technical (New EastBlackburn), Part 2 - New Project

    delivery

    Volume 3B - Technical (Witton Park),Part 2 - New

  • 8/8/2019 Exec Summary Joint Draft Stage Submission

    16/16

    Blackburn with Darwen and Bolton Local Education Partnership

    New East Blackburn Learning Community and Witton Park High School

    Page 16

    NPAPreference Description Location within the submission

    24l any externally sourced and warranted surveys,

    investigations and associated reports that are reasonablynecessary to ascertain (in relation to projects involving the

    construction of buildings) information as to the nature,location and condition of the relevant land (including

    hydrological, geological, geotechnical and sub-surfaceconditions) together with information relating to

    archaeological finds, areas of archaeological, scientific ornatural interest and (in relation to the refurbishment of any

    existing buildings) information on the condition and qualityof existing structures and, in particular, the presence ofany latent defects;

    Volume 3A - Technical (New East

    Blackburn), Part 2 - New Projectdelivery

    Volume 3B - Technical (Witton Park),Part 2 - New