executing the transformation

41
Karachi Electric Supply Company (KESC) November 2009 Executing the Transformation

Upload: tingtong1

Post on 03-Oct-2015

23 views

Category:

Documents


3 download

DESCRIPTION

KEKarachi ElectricMedia Center

TRANSCRIPT

  • Karachi Electric Supply pp yCompany (KESC)November 2009

    Executing the Transformation

  • Executive Summary

    Key Hurdles Facedy

    Key Accomplishments

    Plan Going Forward Plan Going Forward

  • Abraaj acquired a controlling stake in KESC, the integrated power utility serving Karachi, in May 2009 through KES Power (holding company)

    Executive Summary (1/3)

    The transaction officially closed on May 5, 2009: Abraaj through KES Power has already injected US$ 193 million in KESC to fund capital expenditure

    and working capital since October 2008;

    First rights issue of US$ 176 million completed on October 5, 2009:

    Transaction Update

    g p

    KES Power fully subscribed to shares along with minorities shares, which led to an increase in its shareholding from 71.50% to 72.17%;

    Government of Pakistan (GoP) fully subscribed to shares retaining 25.66% ownership;

    Second rights issue of US$ 107 million announced October 27, 2009 and expected to be completed by February 2010 (subject to SECP approval)February 2010 (subject to SECP approval)

    The restructuring plan is being spearheaded by a strong, experienced and highly motivated senior management team assembled by Abraaj, which took over operational control of KESC on September 16, 2008

    A diagnostic analysis through a comprehensive due diligence process has evolved the business strategy for Restructuring Strategy g y g p g p gy

    KESC into five distinct workstreams that are being worked at and managed contemporaneously:

    1. Generation:

    Due Diligence Findings: Old, dilapidated plants with significant capacity de-rating

    Deteriorating fuel mix

    Adverse relations with suppliers

    Initiatives: Capacity Addition: 405 MW added to the system

    Existing Capacity Improvement: 55 MW recovered from existing plants through major overhauling and maintenance of units

    220 MW and 560 MW Projects: 220 MW project fast-tracked and commissioned. Contract for 560 MW renegotiated with COD expected in April 2012

    3

  • The restructuring plan has been divided into five workstreams that are being managed contemporaneously

    Executive Summary (2/3)

    Restructuring Strategy (contd)

    Mix Optimization: Increased reliance on self-generation and diversified fuel mix

    Enhanced Efficiency: Overall efficiency improved to 32.3% and plans to increase average efficiency to over 34% by 2010

    2. Transmission & Distribution (T&D):2. Transmission & Distribution (T&D):

    Due Diligence Findings: Overloaded network due to delays in commissioning of grid stations and manual operation of system

    load

    High T&D losses due to significant theft and high technical losses

    Billing mismanagement, poor customer service, and inefficient IT infrastructure

    Initiatives: Overall plan aims to reduce T&D losses 15% increase in grid stations leading to 650 MVA increase in transformation capacity

    Proactive maintenance has led to significant reduction in network trippings and faults

    Pilot project (IBC) launched for the overall rehabilitation of the T&D network

    Focused disconnection and reconnection drive launched

    3. Human Resource:

    Due Diligence Findings: Lack of a cohesive senior management team and an inefficient organization structure

    Demoralized workforce

    No CBA (Collective Bargaining Agent) in place

    Initiatives: Hiring of top management to lead the turnaround strategy and strengthening of middle management

    Incentive schemes being created to enhance motivation levels

    A team has been identified for CBA negotiations

    4

  • Successful execution of the plan has the potential to make KESC cash positive in the next 2-3 years

    Executive Summary (3/3)

    Restructuring Strategy (contd)

    4. Stakeholder Alignment:

    Due Diligence Findings: Failure to engage various stakeholders in any form of dialogue broken relationships

    E t l ti di ti l f dibilit ith i i l d d k i i Extremely negative media perception loss of credibility with opinion leaders and key civic associations

    Initiatives: Communications strategy envisioned to align KESCs stakeholders to the Companys interests

    Marketing campaigns to communicate milestones and drive transparency in public messagingMarketing campaigns to communicate milestones and drive transparency in public messaging

    Focused CSR and internal campaigns launched to enhance public image and motivate employees

    5. Value-add Initiatives:

    Leverage of KESCs infrastructure, rights of way, and capitalizing on its two million strong customer base through collaborations with telecom, consumer and marketing companies

    Value creation through an unbundling strategy

    5

  • Senior Management Team A highly experienced team is in place to execute the restructuring strategy

    Board of Directors Internal Audit

    CEO HSE DirectorTabish Gauhar

    16 yrs in Energy Sector Abraaj KESC acquisition lead AES Regional CFO, Hubco Electrical Engineer, MBA

    Amir Zafar

    26 yrs HSE experience Masters in engineering

    COO Distribution

    Jan Abbas Zaidi

    COO G&T

    Dale Sinkler

    CSOG&T

    Arshad Zahidi

    CSODistribution

    Nayyer Hussain

    Head of CorporateStrategy

    Dr. Naveed Ahmed 20+ yrs of experience with 16 yrs in fertilizer and 18+ yrs in utility related 19+ yrs experience in 16 yrs of energy sector

    S

    H d f COO H d M k ti & H d HR

    IPPs globally CEO positions in regional

    IPPs incl Haripur Power, Meghnaghat Power, AES Lal Pir, Pak Gen

    power sectors in project development, operations and process engineering Abraaj, Engro

    experience globally COO and President of AES

    Kazakhstan - US$ 200 m revenue group (0.5 m customers; 4,500 employees)

    consumer banking, especially risk and M&A of banking portfolios in MENASA and Europe Abraaj, Citibank, Mashreq

    Bank

    experience in the US and Pakistan with ENRON, HUB Power & other energy companies Key member of ENRON

    turnaround team

    Head ofSpecial Projects

    Zulfiqar Ali

    COO Support Services

    Jalil Tarin

    Group CFOTayyab Tareen

    Head Marketing &Communication

    Ovais Naqvi

    Head HR Management Asir Manzur

    15+ yrs in project and structured financing, private equity and risk in

    16 yrs experience with multinationals in turnarounds financial

    32+ yrs of financial restructuring experience in Pakistan & ME

    20 yrs experience in media, publishing brand management and private

    26 yrs in general management & HR managing restructuring of

    Note: CEO Chief Executive Officer; CSO - Chief Strategy Officer; COO Chief Operating Officer

    private equity and risk in MENASA and Europe Abraaj, Citibank

    turnarounds, financial management, planning and acquisitions Abraaj, Coca Cola CFO UK Chartered Accountant

    Pakistan & ME PSO, Asia Petroleum and

    PIA

    management, and private equity in the US, Europe and Gulf/South Asia region

    managing restructuring of various large enterprises Union Bank, Pak Saudi

    Bank, Mashreq Bank, Coca Cola Pakistan, SMEDA

    6

  • Executive Summary

    Key Hurdles Facedy

    Key Accomplishments

    Plan Going Forward Plan Going Forward

  • Team has managed to resolve several key issues that hindered KESCs performance. However, deep-rooted systemic issues persist which has hampered progress in key workstreams

    Key Hurdles Faced

    Circular Debt

    Over US$ 580 million in receivables from GoP and related sovereign entities ( i.e. Strategic Customers, federal and provincial bodies) are still outstanding

    This has resulted in a liquidity crisis at KESC

    Resolution of Circular Debt issue will dramatically improve KESCs liquidity crisisResolution of Circular Debt issue will dramatically improve KESC s liquidity crisis

    Power P h

    Absence of a PPA with WAPDAPPA ti ti ith NTDC h t d iftl ti i t d d t t k iPurchase

    Agreement PPA negotiations with NTDC have not progressed as swiftly as anticipated due to two key issues:

    Metering Point

    Letter of Credit

    Generation & Transmission

    Gas Supply: 220 MW plant cannot be operated at full capacity due to insufficient gas pressure Rights of Way: Two recently constructed grid stations have not been energized due to a failure to procure

    rights of way from the CDGK

    Human Highly politicized and active unions: No real strategy was in place to address CBA negotiations, etc Workforce: Concerns around lack of motivation and integrity issues involving some of the employees remain

    ResourcesWorkforce: Concerns around lack of motivation and integrity issues involving some of the employees remain

    Issue of ghost employees

    8

  • Distribution was in significant disarray at the time of takeover, with the extent of damage becoming apparent only post takeover

    Key Hurdles Faced - Distribution

    Business Operations

    Billing mismanagement and poor customer service Due to a poor billing system and inaccurate reporting of data, KESCs loss data was under reported

    Analysis at time of takeover based on reported data

    Substantial theft (c. 70% of total losses) Complex political, socio-economic and law & order situation

    No theft detection mechanism (e.g. check meters, AMRs), absence of consumer mapping

    10% of kunda areas are difficult areas (such as katchi abadis) where it is difficult to reduce theft

    Theft

    10% of kunda areas are difficult areas (such as katchi abadis), where it is difficult to reduce theft Complex meter tampering methods are used for theft

    Technical

    High system technical losses due to dilapidated network infrastructure Preventive maintenance: ad-hoc maintenance only in breakdown situations

    Uncontrolled expansion and overloading resulted in voltage fluctuations and poor customer service

    9

  • Executive Summary

    Key Hurdles Facedy

    Key Accomplishments

    Plan Going Forward Plan Going Forward

  • Key Accomplishments Since New Management Involvement

    C it t f US$ 361 illi

    Financial

    G ti

    Commitment of US$ 361 million: Will facilitate investment of over US$ 800

    million in Generation, T&D over 3 - 4yrs US$ 193 million already injected Lender relationships restored post Abraaj

    involvement and capital injection T i i & Di t ib ti

    Since Sep 08 50 MW rental power - March 2009 90 MW - November 2008 (CCPP) 90 MW July 2009 (CCPP)

    Generationj

    6 new grid stations online, 1 more in 09 New connections drive 69% increase in reconnection ratio Integrated Business Center (IBC) launched to

    Transmission & Distribution

    90 MW July / Aug 2009 (GEJB) 40 MW October 2009 (CCPP) 90 MW December 2009 (GEJB)* Total: 450 MW

    560 MW signed and fast-tracked (US$56 million down payment made)

    Integrated Business Center (IBC) launched to control theft and improve billing and customer service: 2 more IBCs in 2009 Customer service / complaint cell

    Key Accomplishments

    o do pay e t ade)

    Azm: campaign for employee moraleCommunications

    Implementation Agreement (IA) signedGoP / Sovereign

    Voluntary accountability governance council set up Transparency: twice weekly press briefings Energy conservation campaign with CDGK Truth campaign: highlight legacy issues

    Hiring of top leadership 3,400 non-mgmt to mgmt promotions 7,000 contracts renewed improved

    Human Resources IA benefits to KESC: Removal of Discriminatory Pricing KESC treated like other DISCOs for

    purchase of power from NTDC NTDC: 650 MWs under PPA

    CSR: program kick-started , pemployee morale Review of job descriptions / benefits Adding more depth to middle mgmt Incentive schemes

    Revised tariff petition filed with Regulator. Public hearing held on Sep 7, 2009

    Note: *50% already online 11

  • Key Accomplishments Generation Overview

    Power Purchases Own Generation

    WAPDA / NTDC

    650 MW

    Bin Qasim c. 1,100 MW

    New 560 MW plant to come online by FY

    2012

    IPPSc. 415 MW

    SITE Gas Turbine c. 54 MW

    Replaced by 90 MW GEJB

    Commissioned in July 2009

    Gul AhmedTapalKanuppDHA Co-GenP i

    Korangi Town

    c. 54 MW

    Replaced by 90 MW GEJB

    Dec 2009 (50% replaced)

    PasmicAnoudOthers

    R l

    Korangi Thermal Power

    Plant c. 160 MW

    To be replaced with more

    efficient plant ~ by 2011

    Pl

    Gas Based Korangi

    Combined Cycle Plant

    - All 4 GTs have been commissioned (194 MW)

    - CC already operational -

    Rental

    Aggreko -50 MW

    (commissioned M 12 09)

    yLong-term Plan

    - Coal based power plant (1000 MW)

    - Renewable and clean energy y220 MW

    - CC already operational -Oct 2009 (205 MW)

    Mar 12, 09) energy

    12

  • Successfully enhanced KESCs dependable capacity from 1,376 MW to 1,670 MW

    Key Accomplishments Generation (1/3)

    KESC has added 405 MW of gross capacity to the system and recovered 55 MW from existing plants Overcome significant issues at CCPP to bring the project back on track Signed and executed two new fast track projects at SITE and Korangi (90 MW already online)

    Capacity Addition

    GenerationTimeline

    Jan09 Mar09 Oct09 Dec09Nov08 Aug09Jul09

    Aggreko

    25MW

    GEJenbacher

    Phase1

    30MW

    GEJenbacherPhase2

    45MW

    SmallIPPs

    17MW

    Aggreko

    25MW

    CCPP

    90MW

    CCPP40MWCCPP 90MW

    GEJenbacher

    Phase1

    60MW

    GEJenbacher

    Phase1

    45MW

    Action Gross Dependable Capacity (MW)

    405MWonline

    Existing Capacity

    Annual Maintenance performed on four units of BQPS (Unit 1,3,4 & 5)

    Major overhauling performed on BQPS Unit 6 and KTPS Unit 4

    Reduced plant tripping by 80% in the last

    p yImprovement

    1,376

    1,670

    seven months

    Recovered 45 MW at BQPS and 10 MW at KTPS

    13Basic Add-On

  • Key Accomplishments Generation (2/3)Proactive project management has prevented further delays in 220 MW project

    Existing Capacity

    GE Jenbacher: Successfully negotiated replacement at two existing sites (KGTPS and SGTPS) with 180 MW of new

    capacity using GE Jenbacher engines

    GE Jenbacher operating efficiency of 40% will add an incremental 80 MW with the same gas usageGE Jenbacher operating efficiency of 40% will add an incremental 80 MW with the same gas usage

    Contract negotiated at a very low price - full turnkey

    SGTPS plant has been fully commissioned with 90 MW brought online in August 2009

    OeKB to provide financing for KGTPS plant. COD for an additional 90 MW is expected by December 2009 with over 50% of the plant already constructed

    New Projects

    220 MW Project: Team of power and construction specialists have led a turnaround of the project and successfully commissioned all four gas turbines

    180 MW brought online in July 2009

    Steam turbine also operational in October 2009

    560 MW Project: Two months of negotiations led to a much improved and favorable contract for KESC. Further negotiations with GE & Harbin led to a reduction in supply contract costs

    R ti t d t t f 1 LC t 6 LC d d ti f th j t Renegotiated payment terms from 1 LC to 6 LCs spread over duration of the project

    Site is ready for contractor mobilization; advance payment of US$ 56 million made on April 15, 2009

    $75 million letter of credit posted in favor of EPC Contractor

    R t l 50 MW t l t t ith A k t H b d & W t Wh f Rental: 50 MW rental power contract with Aggreko at Haroonabad & West Wharf Full 50 MW commissioned on March 12, 2009

    SSGC supplying gas at both sites

    14

  • Key Accomplishments Generation (3/3)New management aims to increase average efficiency of plants to over 34% by 2010

    Plant Efficiency

    Average Efficiency of Plants Average efficiency of the KESC units was

    29.0% prior to new management takeover

    New management has improved overall efficiency to 32.3% and plans to increase average efficiency to over 34% by 2010

    40%

    average efficiency to over 34% by 2010 mainly through:

    Preventive maintenance of all units

    Targeted capex

    Replacement of low efficiency plants30%

    35%

    29 0%

    34.2%

    New high efficiency generation25%Jul-08 Oct-08 Jan-09 Apr-09 Jul-09 Oct-09 Jan-10 Apr-10

    29.0%

    15

  • Key Accomplishments Project Management Case StudyFast-tracking and proactive project management of GE Jenbacher recognized by Asian Power Awards2009 two awards secured by KESC

    Project Management

    New management has brought in dedicated project management teams not only to bring the much delayed 220 MW back on track but also to add incremental capacity of 180 MW contracted through GE Jenbacher

    The 180 MW GE Jenbacher project, negotiated by the new management at extremely favorable commercial terms was completed in a record time span of 7 months and won two Asian Power awards:

    Asian Power Awards 2009 Gold award Asian Power Plant of the Year

    Asian Power Awards 2009 Silver award Best Fast-track Power Project in Asia Prior to new management takeover, the 220 MW faced several issues including: project delays of over one year,

    poor commercial terms, insufficient gas pressure, no commissioning / testing plan, no project management team, no gas pipeline

    New management has led a turnaround of the 220 MW project: Dedicated team consisting of power and construction specialists

    Construction of gas pipeline

    90 MW GE Jenbacher Plant

    SGTPS (90 MW GE Jenbacher Plant)

    Fast-track implementation of project leading to COD much earlier than expected at time of due diligence. Project fully commissioned

    Plant

    16

  • Improving and expanding the transmission network in order to enable uninterrupted power supply

    Key Accomplishments Transmission (1/2)

    New Management Initiatives:

    Under the FIP program, KESC planned to build 9 new grid stations within a certain time period. However, upon takeover only 3 of the 9 grid stations had been completed, two of which were not energized

    Capacity Addition

    New management has fast-tracked construction of grid stations: 6 new grid stations were added to the network increasing transformation capacity by 650 MVA

    3 new grid stations are in the pipeline which will add a further 490 MVA

    New power transformers at Korangi Town, RECP, Queens Road, Valika and Haroonabad grid stations have been commissionedcommissioned

    TimelinesofNew132KVHybridGrids

    D 08 M 09 M 09 M 09 J l 09 O t 09 * b*D 09

    *SubjecttoRightofWays

    KorangiSouth AirportII JailRoadAzizabadMemonGothPRLGulshaneMaymar

    Dec08 Mar09 Mar09 May09 Jul09 Oct09

    80 MVA 40 MVA 80 MVA 80 MVA 80 MVA 80MVA40 MVA

    *Feb10*Dec09

    Mehmoodabad

    80MVA

    Faulty 250 MVA auto transformer repaired, tested and energized at the KDA grid stationT 40 MVA t f i d i h d i d

    80MVA 40MVA 80MVA 80MVA 80MVA 8040MVA

    Maintenance

    80

    Two 40 MVA transformers repaired in house and energized Considerable reduction in EHT trippings due to proactive maintenance

    Maintenance

    17

  • Implementation of various initiatives and a focused capex plan has led to a reduction in transmission losses and network trippings

    Key Accomplishments Transmission (2/2)

    Loss Reduction

    Transmission Losses Transmission losses have reduced from 4.2% in September 08 to 3.0% in September 09

    Reduction in losses has been achieved through:

    Addition of capacitor banks at 35 grid stations

    Implementation of a load balancing strategy at 12 grid stations

    4.2%

    3.0%

    Sep-08 Nov-08 Jan-09 Mar-09 May-09 Jul-09 Sep-09

    Reduction in Trippings

    Number of Trips* (2007 2009) Number of Extra High Tension (EHT) and transformer trippings reduced 9% YoY in 2009

    Reduction in trippings has been achieved through:through:

    Preventive maintenance carried out at 52 grids

    114 faulty relays replaced with new ones

    1,223 1,106

    1,006

    18

    Cleaning of hardware at 135 transmission circuits,

    Rehabilitation & preventive maintenance carried out at 29 circuits

    Note: * January to October for each year

    2007 2008 2009

  • Several projects geared towards distribution reform are underway

    Key Accomplishments Distribution Overview

    Distribution Network Improvement

    Preventive maintenance being carried out on 160 feeders

    IBC Roll Out

    IBCs are the cornerstone KESCs distribution restructuring strategy

    Improved Billing Software

    A new billing software is being considered for deployment:

    Key projects planned: Laying of 281 Km of new

    feeders

    300 new transformers

    A thorough IBC roll out plan has been conceived for roll-out across Karachi

    By January 2010 25% of KESCs R&C billing will be covered by IBC

    Enhanced MIS capabilities

    Ability to detect theft patterns

    Work seamlessly with customer relationship and loss calculation software

    Protective gear on transformers

    Expansion of transformer workshop

    IBCs

    Target to cover 70% of Karachi by IBCs in 2010

    calculation software

    GIS software to be deployed, which will allow KESCs assets to be tracked through GPS

    Metering Infrastructure

    Multiple projects underway: Project to replace low quality

    meters

    HR Development

    Training modules have been developed for theft reduction:

    Including special training on

    Safety Improvements

    Head of Safety hired to oversee safety improvements

    Basic safety issues are beingmeters

    Check meter installation at transformers to track theft

    Automated new connection process

    Including special training on meter tampering

    Training of dedicated loss reduction personnel

    BOC Manager training on

    Basic safety issues are being addressed

    Safety and maintenance key performance KPI for IBCs

    Institutionalization of near

    Installation of a bus-bar system in multi-storey buildings

    g gstrategies to detect theft

    Meter Inspector training

    miss reporting standards

    Line managers being trained to impart safety training

    19

  • Major initiatives include data cleansing for more accurate information, pilot testing of loss reduction initiatives and operational reorganization for better performance and accountability

    Key Accomplishments T&D Losses (1/3)

    T&D Losses (%)

    41%

    35%38%

    43%39% 40% 39%

    37%40%

    35%32%

    26%

    32%37% 34%

    Sep-08 Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09

    Losses reported in KESC have marginally increased, but they now present a far more reliable pictureProgress KESC has spent the last 12 months working on initiatives to develop a platform for reform:

    Organization has been significantly restructured into four regions, with each region led by a DCOO

    Many initiatives including incentive plans, recovery drives, meter inspector training programs and disconnection drives have been executed to understand key issues

    Th ft d t ti i f t t i f d l t 3 000 h k t h b i t ll d

    Key Successes

    Theft detection infrastructure in progress of development, 3,000 check meters have been installed, consumers are being mapped and an energy balancing initiative is underway

    IBCs (Integrated Business Center): In April 2009, after 4 months of conceptualization, the first IBC was launched in Defence

    The concept has now been perfected and is being aggressively rolled outThe concept has now been perfected and is being aggressively rolled out

    Installation of HT capacitors: Evidence suggests that installation of HT capacitors has the potential to significantly reduce losses with capacitor bank installation

    51 capacitors (total target 250) have been installed in the system more underway

    20

  • A Kunda removal drive is being carried out across Karachi

    Key Accomplishments T&D Losses (2/3)

    The new KESC management has initiated a Kunda removal drive throughout the city. This includes: C. 2,000 disconnections daily

    Raids carried out with the assistance of Rangers / Police

    Kunda Removal Drive

    Incentive plans for employees linked to theft / Kunda reduction

    Bulk metering implemented in some areas

    Community service in the heavily infected areas

    Fatwa from religious scholars against theft of electricity

    Pi k R id I Cit L b C l Bi Q i

    Select Examples

    Pink Residency

    Entire residential complex was hooked to Kundas

    Raid conducted at the colony and now all residents have applied for

    Iqra City

    Several hundred Kundas were found in a massive apartment complex

    After much effort, building

    Labor Colony Bin Qasim

    Over 1,000 Kundas converted to regular connections

    80% of the connections are now meterednow all residents have applied for

    meters and connections are being legalized

    management has agreed to apply for new connections

    21

  • Performance improvements have been achieved through an ongoing name and shame campaign

    Key Accomplishments T&D Losses (3/3)

    Improvement in amount precovered from disconnections

    31.1%

    Improvement in units billed against theft

    19.5%

    Improvement in consumer

    reconnections22.4%

    22

  • Significant investment in distribution network has led to improvements in network reliability

    Key Accomplishments Network (1/2)

    Preventive Maintenance

    Preventive maintenance has been carried out on the most critical feeders and faults have drastically reduced post maintenance, c. 30% of KESCs worst feeders have been maintained

    Installation of jumpers to improve connection between circuits and prevent system over-heating has been completed on 55% of the affected network

    New 11-KV

    New conductors are being installed to reduce breakdowns: 40,000 conductors are on track to be installed on 160 feeders (c. 15% of network) by the end of the year

    11-KV feeders distribute electricity from grid stations to consumers: To ease system constraints and increase distribution capacity, in the last 10 months110 new

    FeedersTo ease system constraints and increase distribution capacity, in the last 10 months110 new feeders (11% increase) have been energized and 100 more are targeted to be energized by June 2010 (20% increase)

    Model Town A Model Town project to improve the network in each of Karachis towns has been launched

    A t f thi j t f h b l t d i th fi t h f i tModel Town Project

    As part of this project four areas have been selected in the first phase for improvement In these areas as a result of installation of new feeders and PMTs, rehabilitation of the LT network and

    preventive maintenance of key feeders, the number of faults have reduced by 42%

    Maintenance Completed Number of Faults*

    41

    81

    38

    2030 40 50 60 70 80 90

    100

    150

    200

    250

    300

    350

    400 *

    10

    0 10 20

    New Feeders New PMTs

    LT Network

    Preventive Maint

    0

    50

    100

    Apr-09 May-09 Jun-09 Jul-09 Aug-09Feeder Trips Wire Broken Cable Faults PMT Faults

    23* Number is in thousands

  • The Rapid Response Center (RRC) was established in June 2009 to monitor distribution network performance, facilitate management oversight and ensure coordination

    Key Accomplishments Network (2/2)

    Media:RRC sends daily media

    briefing

    MIS:Hourly MIS on faults

    shared with management

    Local Govt. Liaison:Communication with local

    bodies on faults

    Rapid Response Center:Ensures coordination and

    information flow

    Information Coordination

    Operational Coordination

    Operations:Keep track of operations

    Security:Send security in case of

    p

    Keep track of operations and expedite lags

    Send security in case of mobs / attack on crews

    24

  • Increased promotional activities, safety trainings and safety audits have led to a reduction in the number of accidents / incidents in KESC

    Key Accomplishments Safety

    Safety Trainings

    2113

    1446

    2000

    2500

    Promotional Activities

    1788

    12701400160018002000

    675917

    1446

    0

    500

    1000

    1500

    397

    813

    614365

    650

    346

    43 65205

    650

    200400600800

    10001200

    Total Accidents / IncidentsSafety AuditsSafety Audits

    0

    FY 07 FY 08 FY 09 Qtr 1 FY 10Staff Trained

    0

    FY 07 FY 08 FY 09 Qtr 1 FY 10Tool Box Talk Near Miss Evacuation

    58

    39

    2840

    50

    60

    70

    437

    1047

    494600

    800

    1000

    1200

    437

    1047

    494600

    800

    1000

    1200

    7 8 62

    20

    3

    28 26

    14

    30

    10

    20

    30

    FY 07 FY 08 FY 09 Qtr 1 FY 10

    195

    437 494

    0

    200

    400

    FY 07 FY 08 FY 09 Qtr 1 FY 10

    195

    437 494

    0

    200

    400

    FY 07 FY 08 FY 09 Qtr 1 FY 10Fatal Major MinorSafety AuditsSafety Audits

    Note: Quarterly data is not annualized (FY 09 is 12 months data; Qtr 1 FY 10 is 3 months data) 25

  • Three Integrated Business Centers (IBCs) have been launched, the first one was launched in April 2009 while two more have been recently inaugurated

    Key Accomplishments IBCs

    Concept

    IBCs result in a complete turnaround of an areas operations This turnaround is achieved by consolidating commercial and technical operations, having the IBC

    perform as a profit center, workforce reorganization and through improved processes and infrastructure

    IBCsKESCs First Integrated Business Center (IBC)

    Cash Collected through Disconnections Total Collections

    2,599 3,289

    5,447

    3,057 3,790

    3,476

    2,000

    3,000

    4,000

    5,000

    6,000

    0.2 0.2 0.3 0.3 0.4 0.4 0.5 0.5

    2.9 3.8

    5.1 5.7

    5.1 4.8

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0 First IBC Performance

    0.1 0.2 0.4 0.3 0.4 0.4 0

    1,000

    0.0 0.1 0.1

    Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09Cash Recovered (US $ millions) No. of Disconnections

    0.0

    1.0

    Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09Cash Collected (US$ millions)

    26

  • In order to centralize complaint cell and provide quality 24/7 service to the consumer, KESC is investing in a state-of-the-art call centre

    Key Accomplishments 118 Call Center

    Complaint Management System

    CMS at call center tracks all technical complaints: It has a telephone database of over 1 million consumers

    To facilitate complaint tracking and monitoring, the system cleanses addresses which helps agents respond to queries and helps maintenance crews locate system faultsrespond to queries and helps maintenance crews locate system faults

    Information available to call center agents includes: Updates on failure at grids, transmission lines, distribution lines and general location failures

    Real time information on load shed schedules

    Call center representatives have been deployed at maintenance centers to train local staff

    Representatives at maintenance centers Infrastructure upgrades

    Call center software being revised to improve customer service

    Major initiatives

    Maintenance center performance monitored through regular visits

    Complaint management MIS developed

    CMS system being enhanced to deploy at maintenance centers

    New hardware to expand capacity

    Key processes developed include: Complaint management at maintenance

    center

    Process development Quality of service monitoring

    Quality monitoring cell to be established which will monitor:

    Customer service at IBCscenter

    Consumer inquiry facilitation

    Detailed process flow diagrams developed

    Customer service at IBCs

    MIS and accuracy of data reporting

    Adherence to company standards

    27

  • 461 skilled employees have been hired over the last 12 months to address resource gaps

    Key Accomplishments Human Resource (1/2)

    Overview

    17,200 employees Ageing Management

    Senior Management: 45% are above 55

    Middl M t 30% b 55

    Departmental Split of EmployeesTransmission,

    6%

    Generation,

    Support Services,

    14%

    Middle Management: 30% are above 55

    11,500 staff Recent CBA election won by Labour Union

    Distribution, 74%

    Generation, 6%

    Hiring philosophy: to support the turnaround and business strategy i.e. modernization, customer service and growth:

    To recruit best in class talent at all levels i.e. entry, middle & senior

    Talent sources at entry Level: top tier institutions local / international

    Recruiting

    Middle / Senior Level: Power sector, Engineering & FMCG Sector, Financial Sector, with relevant experience & solid corporate business structure

    C. 60% of existing officers are in age bracket of 40-60 years, 60% of fresh hiring is in below 32 years

    Hi i b S i li ti Hi i b D t tHiring by Specialization Hiring by Department

    Engineering & Sciences,

    35%

    Other, 15%

    Distribution,

    Other Support Functions,

    31%

    Business & Financial

    Management, 50%

    Distribution, 48%

    G&T, 15%

    Security, 6%

    28

  • Development programs for employees continue to be a key focus area. Positive relationship maintained with the Unions and CBA referendum process managed smoothly

    Key Accomplishments Human Resource (2/2)

    Meetings held by CEO with various levels of employees to introduce concept of an open communication channel

    Transformation leadership sessions cascaded down to middle management (615 employees / 22 sessions) Technical programs to be conducted and certified through independent testing mechanism by Institute of

    OrganizationalDevelopment

    Technical programs to be conducted and certified through independent testing mechanism by Institute of Engineering Professionals (IEP)

    Other initiatives include: Internal Job Postings internal opportunities for qualified staff

    Introduction of Engineering Qualification Allowance

    SAP HCM Module is 75% live

    Career Progression concept for Junior Staff

    Review of HR Policies

    SAP HCM Module is 75% live

    Other functionalities being developed e.g. leave, time and health management Time / Surveillance System implementation project has been initiated

    HR Technology

    Active engagement with Union leadership Positive meetings with CBA on Charter of Demands negotiations Alignment and enrichment of jobs:

    Alignment of jobs which carry responsibilities of supervisory nature

    Industrial Relations

    Enrichment of jobs with bigger responsibilities and skills enhancement

    Introduction of Job Enhancement Allowance

    29

  • Public Relations Campaign Advertisements (1/4)

    Anti-Theft Campaign

    30

  • Public Relations Campaign Advertisements (2/4)

    Truth Campaign

    31

  • Public Relations Campaign Advertisements (3/4)

    Monthly Scorecard

    32

  • Public Relations Campaign Advertisements (4/4)

    Umeed Zone Campaign

    33

  • Executive Summary

    Key Hurdles Facedy

    Key Accomplishments

    Plan Going Forward Plan Going Forward

  • Plan Going Forward - Generation Plan

    Short TermShort Term

    GEJB 180 MW

    Estimated Cost: US$ 106 mn

    BQPS 560 MW

    Estimated Cost: US$ 460 mnEstimated Cost: US$ 200 mn

    CCP 220 MW

    135 MW online

    Estimated Cost: US$ 106 mn

    Commissioning Status

    Contractor mobilized detailed

    Estimated Cost: US$ 460 mn

    Commissioning Status

    90 MW N 08

    Estimated Cost: US$ 200 mn

    Commissioning Status

    135 MW online 45 MW to be online by December,

    2009

    Contractor mobilized, detailed design in progress

    US$ 56 million advance payment made

    COD by 2012

    90 MW Nov 08 90 MW July 09 40 MW Oct 09

    Long Term (feasibility stage)

    COD by 2012

    500 MW Coal Plant 500 MW Coal Plant300 MW Coal Plant

    OR

    35

    1 x 1,000+ MW Coal Plant

  • Plan Going Forward T&D Plan (1/2)A Comprehensive Capex plan has been developed for the T&D network

    Transmission Capex

    Transmission Metering and SCADA to improve monitoring and control

    Re-integration of SCADA with new generation and transmission assets

    Improve reliability and reduce technical losses

    New grid stations: Two new grid stations expected to be energized by December 2009

    New 132/220 kV lines

    Rehabilitation/expansion of existing network Rehabilitation/expansion of existing network

    Distribution Capex

    Distribution Theft reduction program:Capex p g

    Including check meters, replacement meters and automatic meter readers (AMRs)

    Installation of HT and LT Aerial Bundle Cable (ABC)

    System improvement and expansion to improve reliability and meet demand growth. System Improvement proposals being executed and budgeted for 2009-10p p p g g

    Billing system being upgraded to industry standards

    Introduce geographic information system (GIS) for asset identification and efficient customer handling

    Installation of power factor corrective devices for voltage stabilityp g y

    Rehabilitation of distribution system through installation of 11 kV feeders and distribution transformers, and change in system design philosophy

    36

  • T h i l L R d ti St t

    which ties into the long term strategy of the company

    Plan Going Forward T&D Plan (2/2)

    Technical Loss Reduction Strategy

    Initiatives Long term strategy

    Load flow study (SINCAL/CYMDIST) Set up team in KESC for regular load flow studies

    Reduce system overloading by network expansion Installation of new power lines and transformersp g

    Results of load flow study have been shared; team aims to regularly update the study with new data

    SCADA1 implementation Sped up SCADA implementation by identifying

    gaps and ensuring smooth implementation

    p

    System rehabilitation Rehabilitate existing system (grids, feeders,

    conductors etc)

    Projects to balance system voltage profile Installation of capacitors, conductors etc

    Non-Technical Loss Reduction Strategy

    SCADA is expected to be installed by December 2009 (already 56 grid stations connected)

    Installation of capacitors, conductors etc

    Optimization & system reliability improvement

    Launched IBCs to reform and modernize the distribution function

    Restructured KESCs operations into four differentregions with Deputy COOs leading each region

    Single point responsibility for customer service, maintenance, billing and service delivery in each IBC

    Tools to detect and prevent theft (energy balancing)Installation of AMRs2 on 11 KV feeders check

    Initiatives Long term strategy

    g p y g g Have installed 3,000 check meters all across Karachi

    to detect theft

    Revenue Protection Department is being significantly upgraded for theft detection

    City wide Kunda removal drive in progress

    Installation of AMRs2 on 11 KV feeders, check meters on distribution transformers and bus-bar meters to monitor theft in multi-storey buildings

    Specific projects to target loss reductions Training of loss reduction personnel Organization restructuring of distribution networkOrganization restructuring of distribution network

    into regional profit centers

    Collection strategy to improve cash flow Replacement of faulty metersNotes:

    1 Supervisory Control and Data Acquisition2 Automatic Meter Readers 37

  • Overall plan includes restructuring Distribution on lines of IBC, addressing compensation & benefits issues and implementing a performance management system

    Plan Going Forward Human Resource

    Strategic Alignment

    To ensure functional initiatives are aligned with the business plan, a system of Key Action Areas (KAAs) for the top leadership team have been agreed

    Each functional head has responsibility to deliver his/her KAAs and these are monitored and updated on a quarterly basis

    Senior levels of the organization have already been restructured Distribution business is to be remodeled along the lines of IBC Organization

    Restructuring

    quarterly basis

    These are being cascaded down by the leadership to their teams

    Significant manpower changes will be phased as following: Internal Hiring (IJP): a transparent process of selecting existing employees for the new restructured

    organization. Four IBCs have already been selected this way

    Management Trainees: for specific areas of Generation, Transmission, Distribution, Finance, HR etc will be based on predefined positions

    Restructuring

    will be based on predefined positions

    Compensation & Benefits

    Inconsistencies to be addressed and align the work force to ensure a motivated, performance driven organization

    Performance Management: To be implemented for 2010 based on company objectives and drive variable pay and promotionsy

    Other Areas

    Policies & Procedures: Current approach stems from government service rules which have been in place since pre-privatization. These need to be re-aligned with industry best practices. Some policies have been modified, yet there is need for further changes in many cases

    SAP HR: To be properly utilized

    38

    SAP HR: To be properly utilized

    HR Team Restructuring: Improved service delivery to be achieved through a redesigned HR team. This will include a specific team for Disciplinary Cases

  • Overall Framework for KESCs Marketing and Communications Department

    Plan Going Forward Public Relations (1/3)

    1. Creating a marketing ecosystem.

    2. Creating an FMCG best-in-class operating process, based on global best practice.on global best practice.

    3. Creating a mass communication tonality. This is a political campaign, not a brand readjustment.campaign, not a brand readjustment.

    4. Driving multiples strands: from brand and media, to the social role as the bedrock.social role as the bedrock.

    5. Driving media efficiency. Creating the look and tone of a professionally run, confident, customer-facing utility.p o ess o a y u , co de t, custo e ac g ut ty

    39

  • Core goals of KESCs Marketing and Communications Department

    Plan Going Forward Public Relations (2/3)

    Brand Challenges Business Supportg pp

    Reverse media hostility Align media on our business to

    ensure transparency

    Advisory on consumer insight Integrated Business Center (IBC)

    launchesensure transparency

    Gain consumer trust and confidence Ensure good and responsible

    citizenship

    launches

    Public and internal safety Address theft and collecting issue

    citizenship

    Leverage sports and football to change brand image

    Revamp KESCs brand design

    Showcase KESC employees Energy conservation Unite people within KESC Revamp KESC s brand design

    Sow the right seeds with consumers for tomorrow

    Showcase business achievements

    40

  • A five step plan has been developed to drive forward the envisioned Azm (Resolve) Campaign

    Plan Going Forward Public Relations (3/3)

    Employee Research

    1 Understand and segment KESC employees and benchmark track-able

    metrics

    Internal Azm: Launch Campaign

    2

    Explain Azm and how employees can play their partp g

    AzmChampions

    3

    Cascade messages, incite change and collect real Azm storiesChampions

    Azm Stories

    4

    Spread compelling stories that further amplify the Azm causeAzm StoriesCampaign

    5

    Spread compelling stories that further amplify the Azm cause

    Azm Star Awards

    Recognize and celebrate success

    41