exhibit j: special factors - tep

72
Tucson Electric Power Company  CEC Application Irvington to Kino 138 kV Transmission Line Project April 2018  J1  EXHIBIT J:  SPECIAL FACTORS Describe any special factors not previously covered herein, which applicant believes to be relevant to an informed decision on its application. J.1 Introduction A public involvement program was initiated in August 2016 and continued through March 2018 to notify and inform the public, agencies, community leaders, and other affected stakeholders about the Project.  J.2 Public Involvement Program Summary Public participation is an important part of TEP’s environmental planning process.  Public involvement and communications activities were conducted as part of the Project to inform the public of the need and benefits of the Project, and to solicit public input.   The public planning process was intended to ensure effective and timely communication among TEP staff, the public, agencies, and stakeholders. TEP used several different public outreach efforts to inform the affected members of the community in the study area. Those efforts included:  Briefings with community leaders, agencies, and jurisdictions  Two stakeholder workshops  Individual stakeholder meetings  Three newsletter mailings, including comment forms  Two public open house meetings  Project telephone information line  Project email address  Projectspecific webpage on TEP’s Internet website, including an online comment form  Social Pinpoint page with ability to comment The outreach effort was designed to offer interested parties an opportunity to gain information and provide input. The public was provided the opportunity to review and comment on the Project. The various methods of communication and public interaction listed above are explained below. J.2.1 Stakeholder Briefings and Workshops In order to introduce the proposed Project, gauge the level of stakeholder concern, and identify potential issues, individual briefings were conducted with key individuals within the various jurisdictions and agencies. At these briefings, the Project’s team members explained the purpose and need of the Project, provided the Project’s description and the environmental siting process, and asked for suggestions and opinions. In return, the community leaders provided TEP with their input on public concerns and sensitive resource areas within the study area.  

Upload: others

Post on 08-Apr-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

 

J‐1  

EXHIBIT J:   SPECIAL FACTORS 

Describe any special factors not previously covered herein, which applicant believes to 

be relevant to an informed decision on its application. 

J.1 Introduction 

A public involvement program was initiated in August 2016 and continued through March 2018 to notify 

and inform the public, agencies, community leaders, and other affected stakeholders about the Project.  

J.2 Public Involvement Program Summary 

Public participation is an important part of TEP’s environmental planning process.  Public involvement and 

communications activities were conducted as part of the Project to  inform the public of the need and 

benefits of the Project, and to solicit public input.   

The public planning process was intended to ensure effective and timely communication among TEP staff, 

the public, agencies, and stakeholders. TEP used several different public outreach efforts to inform the 

affected members of the community in the study area. Those efforts included: 

Briefings with community leaders, agencies, and jurisdictions 

Two stakeholder workshops 

Individual stakeholder meetings 

Three newsletter mailings, including comment forms 

Two public open house meetings 

Project telephone information line 

Project email address 

Project‐specific webpage on TEP’s Internet website, including an online comment form 

Social Pinpoint page with ability to comment 

The outreach effort was designed  to offer  interested parties an opportunity  to gain  information and 

provide  input. The public was provided  the opportunity  to  review and  comment on  the Project. The 

various methods of communication and public interaction listed above are explained below. 

J.2.1 Stakeholder Briefings and Workshops 

In order to introduce the proposed Project, gauge the level of stakeholder concern, and identify potential 

issues,  individual  briefings  were  conducted  with  key  individuals  within  the  various  jurisdictions  and 

agencies. At these briefings, the Project’s team members explained the purpose and need of the Project, 

provided the Project’s description and the environmental siting process, and asked for suggestions and 

opinions. In return, the community leaders provided TEP with their input on public concerns and sensitive 

resource areas within the study area.  

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

 

J‐2  

In addition, TEP held  two  stakeholder workshops with  stakeholders  that had a higher  interest  in  the 

Project. The first stakeholder meeting was held on October 23, 2017 at TEP. Fifty‐two (52) individuals were 

invited, and 15 agency and organization representatives attended (see Exhibit J‐1.1 for the Stakeholder 

Meeting #1 sign‐in sheets). The first stakeholder meeting covered an overview of the project, the role of 

the Arizona Corporation Commission and Line Siting Committee in the process, and the results of TEP’s 

initial research and results of the Geographic Information System (GIS) macro‐spatial analysis. The group 

discussed opportunities and constraints for the project (see Exhibit J‐2.1 for the PowerPoint presentation 

that was used). Notes from Stakeholder Meeting #1 are located in Exhibit J‐3.1. 

The second stakeholder meeting was held on December 11, 2017 at TEP. Eighty‐four (84) individuals were 

invited and 19 agency and organization representatives attended, as well as 12 students from Southside 

Community  School  (see  Exhibit  J‐1.2  sign‐in  sheets).    The  second  stakeholder  meeting  covered  an 

overview of the project, the stakeholder role, results of the GIS micro‐spatial analysis, and next steps (see 

Exhibit  J‐2.2  for  the PowerPoint presentation  that was used). Notes  from Stakeholder Meeting #2 are 

located in Exhibit J‐3.2. 

Community leaders and other stakeholders are listed in Table 9. 

Table 9. Stakeholder List and Participation Level 

AGENCY/ORGANIZATION  NAME AREA OF 

INTEREST/TITLE Level of 

Participation 

US Elected Officials/Staff

US Senator Flake (c/o Bob Brubaker)    

Briefed 

US Senator John McCain (c/o Shay Saucedo    

Briefed  

US Congresswoman Martha McSally (c/o CJ Karamargin) 

District #2 (Congressional district) 

Briefed 

US Congressman Raul Grijalva (c/o Ruben Reyes) 

District #3 (Congressional district) 

Briefed 

 Federal Agencies     

 

Department of Defense Davis Monthan Air Force Base   Bonnie Kacey Carter 

Base Community Planner 

Email newsletters 

USFWS  Jean Calhoun Asst Field Director for So. Arizona 

Email newsletters 

State Elected Officials/Staff

Arizona Senator  Andrea Dalessandro  District 2 Briefed 

Arizona Representative  Daniel Hernandez  District 2 

Briefed 

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

 

J‐3  

AGENCY/ORGANIZATION  NAME AREA OF 

INTEREST/TITLE Level of 

Participation 

Arizona Representative  Rosanna Gabaldón  District 2 Briefed 

State Agencies   

Arizona Department of Transportation   Rod Lane  District Engineer 

Email newsletters 

Arizona Department of Transportation   Rudy Perez 

Planning Program Manager Major Projects Group 

Email newsletters 

Arizona Department of Transportation  

Priscilla F. Thompson, PE 

Utility Engineering Coordinator Utility and Railroad Engineering 

Workshop 1, email newsletters 

Arizona Department of Transportation  Richard LaPierre 

I‐10, SR 210 expansion 

Workshop 1 

Arizona Game and Fish Department  Kristin Terpening  Habitat Specialist 

Workshop 1, email newsletters 

County Elected Officials/ Staff 

Pima County Chuck Huckleberry (c/o Diana Durazo)  Administrator 

Briefed, email newsletters  

Pima County  Richard Elias  Chair Briefed 

Pima County Board of Supervisors  Ramon Valadez  

District  #2 Supervisor 

Briefed 

Pima County Board of Supervisors  Steve Christy 

Briefed 

Pima County Public Works  Carmine DeBonis, Jr.  Deputy County Administrator 

Email newsletters 

Pima County Real Property Services  Tim Murphy 

Supervisor, Property Management Section 

Briefed 

Pima County  Diana Durazo  Special Projects Manager 

Coordination meetings, email newsletters 

Pima County  Sandi Garrick  Utility Liaison 

Workshop 1 & 2, coordination meetings 

Pima County Department of Transportation  Ana Olivares 

Pima County roadways 

Email newsletters 

Pima County Department of Transportation  Robert Johnson 

Pima County roadways 

Workshop 1 

Pima County Department of Transportation  Ellen Alster 

Pole finish, landscaping 

Workshop 1 & 2 

Pima County Development Services  Carla Blackwell  Land use, zoning 

Email newsletters 

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

 

J‐4  

AGENCY/ORGANIZATION  NAME AREA OF 

INTEREST/TITLE Level of 

Participation 

Pima County RWRD  Jackson Jenkins  Wastewater facilities 

Email newsletters 

Pima County RWRD  Rogelio Flores II  Wastewater facilities Workshop 1 & 2 

Pima County Parks  Robert Padilla  Parks 

Coordination meetings, email newsletters 

Pima County  Jenny Neeley   Workshop 2 

Pima County  Courtney Rose Workshop 2 

City Elected Officials / Staff 

City of Tucson  Jonathan Rothschild  Mayor Briefed 

City of Tucson  Michael Ortega  City Manager Email newsletters 

City of Tucson  Richard Fimbres   Ward #5 Councilman  Individual briefings 

City of Tucson  Guadalupe Robles Ward 5 Representative 

Workshop 1, email newsletters 

City of Tucson  Matt Pate Ward 5 representative 

Workshop 2 

City of Tucson  Daryl Cole  Transportation 

Email newsletters 

City of Tucson  Jim Rossi 

Real Estate Services, Division Administrator 

Email newsletters, coordination meetings 

City of Tucson   Scott Clark Interim Development Services Director 

Email newsletters 

City of Tucson  Steve Shields  Land Use, zoning 

Workshop 1 

City of Tucson  Andy Squire  Economic Initiatives  Workshop 2 

City of Tucson  John Beall  Land Use, zoning Workshop 2, email newsletters 

City of Tucson  Mike Graham  Public Information  Email newsletters 

Tucson Water  Dean Trammel  Water facilities 

Workshop 1 & 2 

Tucson Water  Kathryn Gerber  Workshop 2 

Tucson Water  Fernando Molina Public Information Officer 

Email newsletters 

Stakeholder Organizations 

Metropolitan Pima Alliance Amber Smith  Community 

Email newsletters 

Union Pacific Railroad Renay Robison & Brandon Block  Real Estate Manager 

Email newsletters 

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

 

J‐5  

AGENCY/ORGANIZATION  NAME AREA OF 

INTEREST/TITLE Level of 

Participation 

Kinder Morgan/EL Paso Natural Gas  Randy Kimbell 

Natural gas and petroleum pipelines 

Workshop 1 

El Paso Natural Gas  Kelley Sims  Right‐of‐way 

Email newsletters 

Kinder Morgan  A. Dianne Sidorewicz  Engineering 

Email newsletters 

Sunland Deonissa Canez‐Anderson 

Representing Sunland 

Workshop 1&2 

Southwest Gas  Erika Fund  Natural gas facilities 

Workshop 2 

Southside Community School    Health and Safety 

Email newsletters, select teachers and students attended Workshop 2 

Pima Association of Governments  Sheila Storm  Community 

Email newsletters 

Neighborhood/Community Associations 

South Park Neighborhood Association 

Sara O’Neil   Community impacts  Email newsletters, Workshop 1 & 2 

South Park Neighborhood Association 

Earl O’Neil  Community impacts  Workshop 1 & 2 

Western Hills II  Becky Ybarra‐Flores  Community impacts  Email newsletters 

Pueblo Gardens  Cynthia F.H. Ayala  Community impacts  Email newsletters 

Sunnyside  Yolanda Herrera  Community impacts  Email newsletters 

Mortimore  Patricia Smith  Community impacts  Email newsletters 

Millville  George Kalil  Community impacts  Email newsletters 

Las Vistas  Christine Curtis  Community impacts  Email newsletters 

Julia Keen  Mark Mayer  Community impacts  Email newsletters 

Fairgrounds  Roy Garcia  Community impacts  Email newsletters 

Cherry Avenue  Cheryl Strickland  Community impacts  Email newsletters 

Bravo Park Lane  Paul Fimbres  Community impacts  Email newsletters 

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

 

J‐6  

AGENCY/ORGANIZATION  NAME AREA OF 

INTEREST/TITLE Level of 

Participation 

Barrio Santa Rita Park  Angela Quiroz  Community impacts  Email newsletters 

 

J.2.1.1 Department of Defense Davis Monthan Air Force Base 

TEP met with DMAFB on September 19, 2017. DMAFB indicated that their main concern would be whether 

the project would be within DMAFB’s Inner Horizontal Surface, which has a 150‐foot ceiling that should 

not be penetrated by structures. DMAFB reviewed the three alternatives in this application and indicated 

that none of the three alternatives impacted DMAFB (see correspondence in Exhibit J‐4).  

J.2.1.2 Arizona Department of Transportation Meeting 

TEP met with ADOT on October 12, 2017. Meeting minutes are located in Exhibit J‐5.  ADOT noted that 

Alvernon Way would become an extension of SR 210, therefore TEP excluded Alvernon Way from SR 210 

to  I‐10  from  the  alternatives  analysis.  ADOT  also  indicated  that  I‐10  improvements  would  require 

additional  right‐of‐way acquisition. The  future ADOT plans were considered  in  the development of all 

three alternatives. ADOT reviewed the three alternatives in this application and indicated that they will 

submit  their  preferences  and  concerns  following  completion  of  their  Design  Concept  Report  (see 

correspondence in Exhibit J‐6).  

 J.2.1.3 Arizona Game and Fish Department 

Kristin Terpening of AZGFD attended the October 23, 2017 stakeholder meeting and was also given an 

opportunity to review the three alternatives in this application. AZGFD has not formally commented on 

the Project at this time. 

J.2.1.4 Pima County 

TEP met with Pima County on March 13, 2017, October 18, 2017, and November 1, 2017 and numerous 

Pima County staff attended the stakeholder workshops. Pima County was also given an opportunity to 

review the three alternatives in this application and indicated that Alternative B was preferred, although 

they also recommended that Alternative B be revised to continue on I‐10 to Park and continue to the Kino 

Substation  from  there  as  for  Alternative  A,  thereby  not  using  Campbell  Avenue.  Pima  County  also 

expressed concerns related  to TEP’s standard self‐weathering steel pole  finish  (see correspondence  in 

Exhibit J‐7 for detailed comments).  

TEP  responded  to  Pima  County  that  it  had  completed  its  alternatives  analysis  and  concluded  that 

Alternative A was TEP’s preferred Alternative for the following reasons: 

It has the least impact on residential development   Is entirely in an existing corridor (road right‐of‐way)  Has superior access for construction and maintenance   Has greater room for separation from existing utilities  Is less expensive than Alternative B 

 

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

 

J‐7  

In response to Pima County’s suggested modification of Alternative B, TEP responded that this option was 

reviewed early on in the alternative analysis and found to be too difficult to construct. Due to the amount 

of existing underground utilities (4‐inch and 6‐inch gas lines, 6‐inch petroleum line, 16‐inch potable water 

main, a wastewater line, and electric distribution) located between the Costco and Walmart buildings and 

the  I‐10 right‐of‐way,  it would not be physically possible to  locate the transmission  line structures and 

maintain the required clearances to the buildings. Furthermore, the height of the Kino overpass (which is 

also part of the gateway route from the airport to the City Center) and the distance of the span required 

to cross I‐10, would require the transmission line poles to be taller in height than any other poles in the 

area.  

Lastly, in response to Pima County’s concerns related to pole finish, TEP responded that it is TEP’s standard 

to use self‐weathering steel structures for the many reasons that have been stated in previous projects. 

Most  importantly, are the additional costs associated with galvanized or painted finishes. The material 

cost of galvanized over self‐weathering steel poles would be $350,000 to $400,000 more, depending on 

the  alternative  approved  plus  the  additional  labor  costs  of  assembling  the  galvanized  poles.  Painted 

finishes also do not  last  indefinitely and have additional maintenance costs  to  repaint which can cost 

$6,800‐$14,000 per pole not including the costs to take the line out of service in order to safely paint the 

poles.    

J.2.1.5 City of Tucson 

Three City of Tucson (COT) departments reviewed the project and provided a response (see Exhibit J‐8).  

Planning and Development Services indicated that TEP would need to apply for a land use permit for the 

project.  Tucson Water indicated the need for the transmission line to remain as distant as possible from 

their  48” water main.    The  Tucson Department  of  Transportation  (TDOT)  indicated  a  preference  for 

Alternative B, as that route had the least impact to pedestrian facilities on current roadways, and provided 

the fewest sight conflicts at driveways and sidewalks. 

TEP responded to the COT that it had completed its alternatives analysis and concluded that Alternative 

A was TEP’s preferred Alternative for the reasons stated above  in the Pima County response. TEP also 

stated that if Alternative A is approved by the ACC that TEP will be able to avoid impacts to the Tucson 

Water facilities and will also coordinate closely with TDOT on the placement of poles so as not to obstruct 

line of sight or impact sidewalks and driveways (see Exhibit J‐8). 

J.2.1.6 Other Stakeholders 

Kinder Morgan/EPNG 

Kinder Morgan/EPNG participated  in  the stakeholder workshops, provided  facility data and mitigation 

requirements, and reviewed the three alternatives  in this application.   They  indicated that they prefer 

Alternative A or B because Alternative C parallels three SFPP petroleum products pipelines for the entire 

stretch along Ajo Way.   Such parallelism  in proximity would require an  induction study to determine  if 

there could be any negative impacts of the proposed powerline on those pipelines and/or their cathodic 

protection systems, and designing and installing appropriate mitigation (see correspondence in Exhibit J‐

9).  

South Park Neighborhood Association 

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

 

J‐8  

At the request of South Park Neighborhood Association, TEP also presented the project at their monthly 

meeting on January 8, 2018. The presentation materials are located in Exhibit J‐10. 

J.2.2 Newsletters/Fact Sheets 

TEP prepared and mailed three newsletters that included comment forms throughout the course of the 

project. Newsletter #1 was mailed on August 15, 2017 to 14,111 residents, business owners, landowners, 

and agency/organization representatives in the study area (Exhibit J‐11.1).  

Newsletter #2 was mailed on January 15, 2018 to 12,866 residents, business owners,  landowners, and 

agency/organization representatives in the study area (Exhibit J‐11.2). 

Newsletter #3 was mailed on March 12, 2018  to 12,735  residents, business owners,  landowners, and 

agency/organization representatives in the study area (Exhibit J‐11.3).  

The  first  two newsletters were  sent  to provide  current project  information,  status,  and  to  announce 

upcoming  public  meetings.  The  third  newsletter  provided  specific  information  regarding  the  three 

alternatives that TEP had selected to carry forward in its application, and requested input and preferences 

related to the alternatives.  

All newsletters were provided in both English and Spanish. 

J.2.3 Public Open House 

A public open house was held at Mulcahy YMCA (2805 E Ajo Way, Tucson, Arizona 85713) on August 30, 

2017. 

Eighteen (18) members of the public and one (1) agency/organization representative attended the open 

house meeting. Questions asked at the meeting were  in relation to the Project need, substation siting, 

health effects, and visual effects. In addition, two written comments were received and are included in 

Exhibit J‐18 and Exhibit J‐19. The sign in sheet is included as Exhibit J‐12.1. 

A second public open house meeting was held at the same location on January 24, 2018, and was attended 

by twenty‐five (25) members of the public and three (3) agency/organization representatives. Questions 

asked at the meeting were  in relation  to the Project need, substation siting, health effects, and visual 

effects. In addition, two written comments were received and are included in Exhibit J‐18 and Exhibit J‐

19. The sign in sheet is included as Exhibit J‐12.2. 

A project fact sheet and an EMF fact sheet were prepared for additional distribution at the open houses 

and at stakeholder meetings (Exhibits J‐13 and J‐14 respectively). See Exhibit J‐15.1 for copies of posters 

on display at the first Open House meeting and see Exhibit J‐15.2 for Open House meeting #2 posters. 

TEP published newspaper notices of all public meetings in the Arizona Daily Star (English) and La Estrella 

(Spanish). Copies of the public notices and affidavits of publication are included in Exhibits J‐16.1 and J‐

16.2. 

J.2.4 Telephone Information Line 

A toll‐free telephone information line was established for the Project. The automated message, in English 

and Spanish, provided basic  information and encouraged  callers  to  leave a message  requesting more 

information or a  return call. The Project webpage address was also provided  for  the public  to access 

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

 

J‐9  

updated Project information. The telephone number was advertised in the newsletters and on the Project 

website. The information line voicemail was checked regularly (and more frequently following newsletter 

mailings and public open houses); all messages that required a response were answered by one of the 

appropriate project team members. To date a total of twelve (12) voicemails were received. All messages 

received were entered into the comment tracking database. 

J.2.5 Internet Website 

The  Internet  has  evolved  into  a  primary  source  of  information,  therefore  TEP  maintains  a  website 

featuring  their  various  projects  throughout  southeastern  Arizona.  The  site  address  is 

http://www.tep.com.  A page devoted to the Project was added to the TEP website before other public 

participation  activities  commenced,  and was updated  throughout  the planning process.    The  specific 

Project page is https://www.tep.com/irvington‐to‐kino/.   

The Project webpage was updated  regularly  to  include both  general  and  specific  information on  the 

Project, including the latest maps and the Project newsletters. After the public open house, the displays 

and graphics presented were added to the Project webpage. The webpage also allowed people to submit 

comments via an online public comment form, or to request more information, and provided the toll‐free 

project information line number. 

The online public comment form offered another method for the public to provide comments, along with 

a mechanism  to  track  and  trend  all  comments  received. The  automated  comment  tracking database 

served as a platform and universal location for storage of all Project comments. To date TEP has received 

a  total  of  44  comment  form  responses  and  13  online  responses.  Comments  submitted  through  the 

website were entered into the database (discussed below). 

J.2.6 Social Pinpoint 

Social Pinpoint is an online interactive tool that enables the community and stakeholders to give feedback 

using digital mapping. The map displayed  individual  route  segments  that  could be  linked  together  to 

provide  a  transmission  line  route  to  connect  the  existing  Irvington  Substation  to  the  proposed  Kino 

Substation. Users were asked to drag a “pin” to points on the route alternatives that they felt should be 

considered or avoided, and asked to provide comments about their chosen location.   

The tool was originally launched on January 9, 2018 and the tool was updated on March 12, 2018 with the 

three  alternative  routes. An  email was  sent out  at  this  time  to  encourage  those  that had previously 

commented and who were on the stakeholder list to use Social Pinpoint to comment on the alternatives 

(see Exhibit J‐17 for a copy of the email). The site was closed for comment on March 28, 2018. 

Eleven (12) comments were received and are included in Exhibits J‐18 and J‐19. 

J.2.7 Comment Tracking Database (Exhibit J‐19) 

At the time of preparation of the application, 84 public comments were received regarding the proposed 

Project from the various sources discussed above.  

Through the comment database, comments were sorted by jurisdiction, agency, etc., as well as by issue 

area/concern  (e.g.  health  and  safety,  project  cost,  appearance,  location,  and  miscellaneous).  This 

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

 

J‐10  

information was used to better understand the concerns of the community in regard to the Project and 

incorporate the concerns into TEP’s plans where possible.  

J.3 Public Comments Received 

A  total of 84 comments were  received and categorized. The  topics covered health, cost, appearance, 

location,  and  other.  Figure  2‐5  shows  the  percent  of  each  type  of  comment  received.  Respondents 

frequently  indicated  that  location  was  of  interest  to  them,  with  location  being  relevant  to  40%  of 

responses from the public. 

   

Figure 2‐5. Public Comments and Concerns by Topic 

TEP also kept track of the public’s preferred alternatives. Of the 84 land owners, business owners and area 

residents  who  provided  public  comment  for  the  Project,  27%  of  respondents  elected  to  vote  for  a 

preferred  alternative  route.  Figure  2‐6  depicts  the  alternative  route  preferences  indicated  by 

respondents.  Alternative  Route  A  garnered  the  most  support,  with  a  52%  share  of  the  votes  while 

Alternative Rout B received 44% of the votes, respectively.  

24%

5%

17%

40%

14%

Health

Cost

Appearance

Location

Other

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

 

J‐11  

 

Figure 2‐6. Alternative Routes Preferred by the Public 

See Exhibit J‐18 for table of comments received and proposed resolutions and Exhibit J‐19 for copies of 

comments received from the public. 

 

 

52%

44%

4%

Figure 2‐4. Alternative Routes Preferred by the Public

A

B

C

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

  

 

 

 

 

 

 

 

 

 

 

EXHIBIT J‐1 

   

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

  

 

 

 

 

 

 

 

 

 

 

EXHIBIT J‐2 

   

TitleStakeholder WorkshopIRV-Kino 138-kV Transmission Line Project

October 23, 20171:00-5:00 p.m.

• Introductions• Project Overview• Role of the Arizona Corporation Commission• TEP’s Design Philosophy• TEP’s Line Siting Process and the Stakeholder Role• GIS Spatial Analysis Overview• GIS Spatial Analysis Results

– Review of data– Results of preliminary internal modeling– Group discussion of opportunities and

constraints

Workshop Agenda

Introductions

Project Background• Annual load studies.

– Project (substation and line) need first identified in 2007.

– Included in TEP’s 10-year plan since 2007.– Now identify need for infrastructure to be in place

by 2021.• Substation site selection study started in 2016.• Bridges DRC meeting held July 26, 2017.• Public meeting held August 2017.• COT minor PAD amendment for substation site

received September 2017.• Transmission line siting study started September 2017

with collection of data and internal spatial analysis.

Project Purpose and Need• Growing demand for power in the Kino

Substation Study Area requires new substation.• New 138-kV transmission line from nearest

generation source (Irvington) to serve substation.

• Maintain reliable electric service.

• Meet future capacity requirements.

• Funding support for the Pima County Natural Open Space Park

• Ability to retire at least two lower-capacity substation in the future

Additional Project Benefits

• Approx. 4 mile long 138-kV transmission line between the new Irvington 138-kV Substation and the new Kino 138-kV Substation.

• New Kino Substation located at the southeast corner of Kino Boulevard and 36th Street.

Project Description

Focus of today’s meeting

Multiple methods of public involvement – to date • Project newsletter # 1 – mailed August 11, 2017• Newspaper advertisements – August 11 & 14• Public meeting # 1 – August 30, 2017• Project website at tep.com/projects - ongoing

Upcoming public involvement opportunities• Project newsletter #2 – December 2017• Public meeting # 2 – January 2018• Online comment tool – Social Pinpoint• Project website at tep.com/projects• Public hearing – Spring 2018

Public Outreach Methods

• Comments were received in various methods: phone calls, voicemail messages, in-person and online.

• Comments received to date: 39• Comment topics included:

– Location– Health/EMF– Appearance/Design– Cost– Other/Not identified

• The complete commentspreadsheet can be viewed at tep.com/projects

Public Comments

Arizona Corporation Commission (ACC) Line Siting Process

• The ACC sites and certificates electric transmission lines greater than 115-kV.

• Line Siting Committee reviews application and makes recommendation to the ACC.

• Project requires a Certificate of Environmental Compatibility.• ACC Responsible for reviewing:

– Total environment (fish, wildlife, plants)– Existing state, local government, and private development plans– Noise– Recreational impacts– Scenic areas, historic sites & structures, archaeological sites– Interference with communication facilities– Technical aspects– Costs– Other applicable federal and state laws

• Work within or next to existing infrastructure and corridors where practical.

• Work with landowners and stakeholders to avoid or minimize impacts to sensitive areas.

TEP’s Design Philosophy

TEP’s Line Siting Process• Identify the need for the Project.• Identify the Preliminary Study Area.• Prepare Public Notification Plan/Identify stakeholders.• Collect baseline data/conduct internal macro-level analysis.• Conduct first public/stakeholder outreach.• Identify & analyze opportunities and constraints.• Develop links and conduct micro-level analysis.• Conduct second public/stakeholder outreach.• Connect viable links into alternative routes.• Conduct impact assessment/engineering & constructability

assessment/route comparison.• Identify alternative routes to carry forward in ACC application

for a CEC.• Prepare and file ACC application.

We are here

• Review information provided.• Assist in identification of opportunities and

constraints.• Provide data if requested.• Attend stakeholder meetings.• Consult and collaborate, as needed.• Identify and explain your preferred alternative.

Stakeholder Role

GIS Spatial Analysis Overview

• Incorporates multiple weighted perspectives of influence.

• Least biased method.• Inputs data based on the perspectives of society, the

environment, and construction feasibility.• Ultimately generates optimal route corridors

graphically.• Macro-level and micro-level analysis to be

conducted.

“The process of examining the locations, attributes, and relationships of features in spatial data through overlay and other analytical techniques in order to address a question or gain useful knowledge”

GIS Spatial Analysis Overview• Collected baseline data for macro analysis including zoning, sensitive

receptors, building density, information from initial public/stakeholder outreach (such as exclusion areas).

• Conducted Preliminary engineering/constructability analysis of existing utility and transportation corridors in and near the preliminary study area and ranked the segments “1” to “4”, where “1” is worst and “4” is best. Based on:– Degree of difficulty– System constraints– Cost– Relocation/reconstruction of existing facilities– Construction timeframe

• Grouped sensitive receptors (schools, hospitals, churches, day care facilities, etc.) together and ranked as “2”.

• Grouped like zoning together and ranked:– Residential “1”– Multi Use & Planned Area Developments “2”– Commercial “3”– Industrial “4”

GIS Spatial Analysis Overview

• Macro-level data converted to GIS raster (surface) files to 10 x 10 meter squares (pixel size).

• Macro-level data processed to produce 3 models:– Utility-Road Scenario– Built Environment Scenario– Combined Scenario

• Included preliminary engineering/constructability (E/C) segment analysis, zoning, and sensitive receptors.

• E/C segments weighted 50%.• Sensitive receptors and zoning weighted 50%.• Result: Sensitive receptors and zoning influence

E/C segments.

Utility-Road Scenario

Utility-Road Scenario

• Previously ranked zoning categories weighted 50%.

• Land use density weighted 50%.• Result: Identification of potential corridor

opportunities in lower density areas.

Built Environment Scenario

Built Environment Scenario# Proposed Substations

Study Area

Exclusion Areas

Building Density-Zoning

Higher Corridor Potential

Lower Corridor Potential

• Validates results of two previous scenarios.• Utility-Road and Built Environment scenarios

combined to create a composite view.• E/C segments weighted 50%.• Built environment data weighted 50%.

Combined Scenario

Combined Scenario

Discussion of Opportunities

• Focus on opportunities.• Review E/C segments in relation to models.• Document stakeholder input.

Additional Discussion

• Unidentified opportunities or constraints?• Likes/dislikes?

What’s Next?• Incorporate stakeholder comments.• Obtain additional data from stakeholders, if

needed.• Develop links and conduct micro geospatial

analysis.• Stakeholder Workshop #2 - December 2017.• Identify alternative routes.• Public Meeting #2 – January 17, 2018.• File ACC CEC Application Spring 2018.

TitleStakeholder Workshop #2IRV-Kino 138-kV Transmission Line Project

December 11, 20171:00-3:00 p.m.

• Introductions• Project Overview• Stakeholder Role• GIS Spatial Analysis Overview• GIS Spatial Analysis Results

–Review of data–Results of micro analysis–Group discussion of links

• Next Steps

Workshop Agenda

Introductions

Project Background• Annual load studies.

– Project (substation and line) need first identified in 2007.– Included in TEP’s 10-year plan since 2007.– Now identify need for infrastructure to be in place by

2021.• Substation site selection study started in 2016.• Bridges DRC meeting held July 26, 2017.• Public meeting held August 2017.• COT minor PAD amendment for substation site received

September 2017.• Transmission line siting study started September 2017 with

collection of data and internal spatial analysis.– Stakeholder Meeting #1 held October 2017

Project Purpose and Need• Growing demand for power in the Kino

Substation Study Area requires new substation.• New 138-kV transmission line from nearest

generation source (Irvington) to serve substation.

• Maintain reliable electric service.

• Meet future capacity requirements.

• Funding support for the Pima County Natural Open Space Park

• Ability to retire at least two lower-capacity substation in the future

Additional Project Benefits

• Approx. 4 mile long 138-kV transmission line between the new Irvington 138-kV Substation and the new Kino 138-kV Substation.

• New Kino Substation located at the southeast corner of Kino Boulevard and 36th Street.

Project Description

Focus of today’s meeting

• Review information provided.• Provide data if requested.• Attend stakeholder meetings.• Consult and collaborate, as needed.• Discuss Link preferences.• Identify and explain preferred alternative.

Stakeholder Role

GIS Spatial Analysis Overview

• Incorporates multiple weighted perspectives of influence.

• Least biased method.• Inputs data based on the perspectives of society,

the environment, and construction feasibility.• Ultimately generates optimal route corridors

graphically.• Macro-level and micro-level analysis conducted.

“The process of examining the locations, attributes, and relationships of features in spatial data through overlay and other analytical techniques in order to address a question or gain useful knowledge”

GIS Spatial Analysis Overview• Collected baseline data for macro analysis including zoning, sensitive

receptors, building density, information from initial public/stakeholder outreach (such as exclusion areas).

• Conducted Preliminary engineering/constructability analysis of existing utility and transportation corridors in and near the preliminary study area and ranked the segments “1” to “4”, where “1” is worst and “4” is best. Based on:– Degree of difficulty– System constraints– Cost– Relocation/reconstruction of existing facilities– Construction timeframe

• Grouped sensitive receptors (schools, hospitals, churches, day care facilities, etc.) together and ranked as “2”.

• Grouped like zoning together and ranked:– Residential “1”– Multi Use & Planned Area Developments “2”– Commercial “3”– Industrial “4”

GIS Spatial Analysis Overview

• Macro-level data converted to GIS raster (surface) files to 10 x 10 meter squares (pixel size).

• Macro-level data processed to produce 3 models:– Utility-Road Scenario– Built Environment Scenario– Combined Scenario

• Scenarios presented at Stakeholder Meeting #1.– Input received– Data collected

• Micro-level data: cultural resources, drainage features, locations of other utilities, utility & road standards, stakeholder preferences.

• Micro analysis ranks segments in the utility-road scenario.

• Design engineer reviewed analysis and identified Links that are constructible and ranked from engineering perspective.

• Some segments are removed.

Micro Spatial Analysis

Discussion of Links

• Focus on opportunities.• Review Links.• Document stakeholder input & Link preferences.

Additional Discussion

• Unidentified opportunities or constraints?• Likes/dislikes?

What’s Next?• Incorporate stakeholder comments.• Obtain additional data from stakeholders, if

needed.• Identify alternative routes.• Public Meeting #2 – January 24, 2018.• File ACC CEC Application Spring 2018.

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

  

 

 

 

 

 

 

 

 

 

 

EXHIBIT J‐3 

   

Tucson Electric Power Stakeholder Meeting Irvington to Kino 138kV Transmission Line Siting and Kino Substation

Projects

TEP Headquarters, 88 E. Broadway Blvd October 23, 2017

Meeting began with Renee Darling, TEP senior environmental and land use planner, providing background on the study using a PowerPoint presentation. Attendees had large scale maps available to look at findings of a land-use analysis of the study area. Dean Trammel of Tucson Water asked who did the initial analysis of the study area. Renee Darling said TEP staff worked on the analysis using engineering standards and then modified the findings to include “sensitive receptors” and other societal factors. Earl O’Neil of the South Park Neighborhood Association, asked if there are legal constraints on what choices TEP can make. Renee Darling said policy restrictions by agencies and stakeholders – such as the Arizona Department of Transportation and Union Pacific Railroad – preclude transmission lines from running parallel to highways or railroad tracks. Dean Trammel of Tucson Water asked if the lines would be aerial or below ground. They will be an average of 100 feet above ground, with flexibility to go higher where necessary. The base of power poles is below ground, with footprints approximately 10 feet in diameter. Deonissa Cañez-Anderson, an attorney with Southern Arizona Legal Aid who was retained by Sunland Garden Neighborhood Association, asked if the Kino Substation would be surrounded by a wall. Renee Darling confirmed that there will be a 10-foot wall around the facility that will feature colors and themes associated with The Bridges development where it will be located. She said the final site plan will include details of the design elements.

Ellen Alster of Pima County Department of Transportation asked how tall the structures associated with the transmission line will be. TEP said poles will be 100 feet tall while other associated structures will be approximately 60 feet high. Randy Kimbell of Kinder Morgan/El Paso Natural Gas noted that there is a 10-inch natural gas pipeline below ground at Country Club and Michigan Street. Roy Flores of Pima County Wastewater added that his agency has facilities below ground throughout the study area, some located on the centerline of roads, others on roadway shoulders and on private property. PC Wastewater will share information with the TEP study team. Robert Johnson of Pima County Department of Transportation asked if the line will allow for other utility uses or solely be for the electrical transmission line. TEP said that, unlike lower voltage lines, the 138kV line is not required to share with other utilities such as cable, but can allow it on a case-by-case basis. Deonissa Cañez-Anderson noted a study that indicated pregnant women should not be exposed to electromagnetic fields (EMFs) generated by high-power transmission lines. TEP responded that “thousands of studies” have been conducted on the health effects of EMFs and that there is no conclusive evidence of harmful effects. All electrical devices emit EMFs and their strength diminishes to “zero” depending on how much is being emitted and how far they travel before reaching people. The 138kV lines are 100 feet above ground to eliminate concern about ill effects. Earl O’Neil asked how TEP can traverse “prohibitive areas” noted on the study area map, including interstates and railroad tracks. TEP noted that crossings of highways and railroad tracks are allowed, but running lines parallel to them is not. Mr. O’Neil noted that 36th Street is used by oversized and over-height vehicles that are required to exit I-10 to avoid low overpasses and that some vehicles require traffic signals and other overhead utility lines to be lifted. He suggested that TEP’s line should not interfere with that use of 36th Street.

Steve Shields of the Tucson Planning and Development Services Department, noted that residential development is planned for the area southwest of Kino Parkway and Park Avenue. Question was asked about the value of avoiding circuitous routes for the transmission line. Ed Beck of TEP said that the Arizona Corporation Commission, which must approve the line siting plan, does consider the cost associated with less-direct routes to prevent those expenses from being passed on to rate payers. Roy Flores suggested to other stakeholders that they drive routes followed by existing 138kV lines to see what visual impacts those lines have. Earl O’Neil asked where lines taking energy from the substation to customers would be aligned. TEP said that is not yet known because the data to determine those routes would come out of decisions made in this study.

Opportunities/Constraints

Country Club/Michigan – Kinder Morgan has natural gas pipe (Kinder Morgan can send information)

Pima County Wastewater facilities located throughout study area (Roy Flores, PCWW to send files)

Keep in mind roads used for “heavy loads” and oversized trucks – along 36th

Vertical clearance of poles – Run by ADOT

Ajo – Need to follow-up with City of Tucson Department of Transportation to see if any constraints along Ajo

Park/36th is residential area

Kino Sports Park has plans for expansion

Questions

Was a sensitivity analysis done? Are there legal constraints? Tucson Water: Will the t-line be above ground or below? Will there be a wall around the substation? What is the pole diameter? How do you cross “grey” areas? -90 degree crossings OK

What options are there other than road right-of-way? Would underground be considered? Existing 138kV’s near residential area? When will the preliminary design be ready to share?

Parking Lot

Siting of Kino substation

10-year plan

DRC/monumentation/design

EMF

Phase II of project

Diagram of existing 138kV, etc.

Tucson Electric Power Stakeholder Meeting 2 Irvington to Kino 138kV Transmission Line Siting and Kino Substation

Projects

TEP Headquarters, 88 E. Broadway Blvd December 11, 2017

Meeting began with Renee Darling, TEP senior environmental and land use planner, providing background on the study using a PowerPoint presentation. Attendees had large scale maps available to look at the proposed links. Discussion of Links - All Deonissa: Is the transmission line going to go through any residential areas? Renee: We are trying to figure that out today. This is why we meet with stakeholders and host public meetings. With their help we decide which pieces of the puzzle we use. At some point the line will go through a residential area. We are working with Pima County to purchase the land for the substation. We look at analytics to come up with options. Deonissa: Is the substation going to be the same size as the Irvington substation? Renee: No, it won’t be as large. The Irvington substation has multiple components that this new substation will not have. The poles will be no higher than 14’ tall. D: Is there a substation of similar size I can drive by to compare? R: The one of similar size is currently being built at Orange Grove and La Canada on the southwest corner. Christina (engineer for project): The new substation will only take 3 to 5 acres while the Irvington substation is over 400 acres. R: We can provide model/simulation. There will be a decorative wall, landscaping, nice entrance that matches the Bridges development. Ellen Alster, Pima County: Will they be galvanized poles? Ed Beck: Inside the substation would be galvanized but others are self-weathering steel. Deonissa: What is galvanized? Renee: Not shiny. D: Can they be galvanized as to not create an eye sore? R: Self-weathering steel is preferred because it is low cost and low maintenance, however, comments will be taken into consideration when submitting to the Arizona Corporation Commission (ACC). Courtney Rose, Pima County: How is this project being funded? Joe Barrios: Rates are included in monthly bill as part of scheduled maintenance. Before moving forward everything must be approved by ACC.

Deonissa: Requested teacher from Southside Community School speak. Renee: Accepts. Anjelica: 5th grade teacher at Southside Community School brought her two daughters Jackie (Kinder) and Jasmine (3rd grade). School is right across from proposed substation. Most students reside east of proposed substation. Worried about potential harm of substation. Daughter has brain tumor and has received the maximum amount of radiation allowed. Worried about radiation. Very opposed to substation and transmission lines going through school and neighborhoods. Renee: We will do an EMF (electromagnetic field) study after we have defined a proposed transmission line. A: When will the EMF study take place? R: Once we have defined a proposed transmission line route. School is about 1000 feet from substation. The substation will be about 300x500 feet total. All information is disclosed in ACC report. Deonissa: Is it feasible for 36 and 37 to connect by I-10 to avoid residences? Renee: Yes, these are options. 39 up to 40 have been excluded due to ADOT construction Jenny Neeley: So there is a 46kV on the north side just across from new substation? Renee: Jenny Neeley: Can we do the transmission line on 36? Renee: There are a lot of residences, we would have to bury the distribution on 36th and have to allow users (cable, etc.) to use 46kV. Transmission line cannot be buried. There would be a double circuit line a lot closer to residences. Burying distribution is more expensive. Line 1: Residents would prefer buried line Ed Beck: We would have to dig up the road. Depending on input from stakeholders, cost, construction, etc. sometimes it makes more sense to co-locate. Renee: Macro and Micro analysis are broken down by side of the road. We can put back options we’ve eliminated at this stage if necessary. Line 2: What about street lights and the new development in that area? Renee: These have been considered and are in conversation. There is a 15” and 8” clay line in the road Right of Way. R: May require an easement but we aren’t at that point yet. Line 3: Red area least preferred. Goes by the ball fields, hospital and Kino Sports Complex. Garrick: How high is pedestrian bridge? Renee: I’m not sure. Line 36-39: ADOT does not allow lines parallel to Right of Way North side of I-10.

Anjelica: Isn’t that the best option since there are no residences? Renee: Yes. Earl: What are you considering private property (on map)? Renee: businesses, not residential. This would affect parking lots, minor effects which would require an easement application. ###: What is the probability of going west on Ajo? Renee: Adds 2 miles to length of line but not impossible. Ellen: Why is Kino Blvd eliminated? Renee: It considered scenic. 41: Following off-ramp, hard to obtain. ADOT is OK with crossings but not parallels. Ed Beck: Costs is considered upon approval. Deonissa: What is TEP’s preference in the transmission line route? Renee: None. Ed Beck: If we could, it would be the straightest and cheapest route but that isn’t practical or possible. D: What is the best method for comment? R: Written comment is best because there is no interpreting. D: Is the AZ Corp. Comm. application due in January? R: No, that is the 10-year plan which doesn’t affect this project. This project will need to be completed by 2021 to meet demand of growth in area. D: Is Kino/36th placement of substation set in stone? R: Waiting for minor PAD approval, substation approval waiting for local jurisdiction Andrew: Irvington 21, 22, 24, 10, 9, 12, 33, 2, Why are we not talking about these links? Renee: We are working our way down the map and not there yet. Renee: There is no federal nexus required. Ellen: Repairian disruption for substation? R: minimal disruption, maybe 2-3%. Pima County is planning on building a park with STEM playground, trails, etc. but there is no funding for that right now. Teacher: If substation is built, will there be a park there? R: Yes. Deonissa: Question about substation size in relevance to land. Renee: The land is from the Kino ROW to edge of dense green area. Can send footprint. Approx 3.5 acres. Large dirt area (on map) are for new developments: Kino park expansion, gateway from airport, commercial development. Which will create significant increase in power needs

Deonissa: Line 22, 25, 24, 10, 9, 32, 33 are a good option R: adds 2 miles but not impossible Teacher: Why pick route 13 if it’s right through the park? Renee: It’s on the edge of the park Teacher: Most of our residents are in that area a lot Is it easier to make curved lines or right angles? Ed: Right angles, fewer poles What is the approximate cost of each pole? Tangents are $10-15k, depending on height others can be $20-50k. Ellen: Have you thought of colored poles. BLM did a study regarding cost-effectiveness of colored poles. Renee: Can you send me that study? (Ellen to send) Ed: In the past, painted poles don’t hold up in Tucson. They fade or paint peels off and cost to paint over is expensive. Ellen: They used a powder-coated paint. Deonissa: Do you have a cost of powder-coated poles? Ellen: No. Earl: What is the height of these poles? Ed: 75-80 ft Courtney Rose: Are the alternative routes surveyed? Renee: Yes, Class 1. Can send those maps.

LINK

1. Power lines on both sides—is there another option? Co-location opportunity? Bury lines?

2. New development on west side Street lights P.C. WW existing facilities

3. Height of pedestrian bridge?

36, 37, 38, 39 – Good option to go along freeway (I10) 41 – Why not go through Kino? Has been identified as “scenic” 21, 22, 25, 24 – Makes sense 32, 33 – Development plan could change Power-coated poles (Ellen, Pima County to share info from BLM) Cultural info (send to Courtney, Pima County)

Tucson Electric Power Company   CEC Application Irvington to Kino 138 kV Transmission Line Project  April 2018 

  

 

 

 

 

 

 

 

 

 

 

EXHIBIT J‐4 

   

From: CARTER, BONNIE K CIV USAF ACC 355 CES/CENPPTo: Darling, Renee; Aguda, CeliaCc: [email protected]; GERMANOS, NICHOLAS M GS-13 USAF ACC 355 CES/CEN; FROSCH, JARED C GS-12

USAF ACC 355 CES/CENP; TORIELLO, MICHAEL R GS-13 USAF ACC 355 CES/CDSubject: [EXTERNAL E-Mail] RE: Irvington to Kino Newsletter #3 and Alternatives Map for reviewDate: Thursday, March 8, 2018 6:03:43 PM

Ms. Darling

We have reviewed the TEP proposed 130KV transmission line routes from the new substation at Kino and 36th . They are not within or adjacent to our installation boundary. Therefore, we find all three routes to have no negativeimpact on DMAFB mission. We are curious, will the transmission line be buried or overhead lines?

V/r

B. Kacey Carter, Civ USAF = =Base Community Planner355th Civil Engineer Squadron/CENPPDavis-Monthan AFB [email protected]

-----Original Message-----From: [email protected] [mailto:[email protected]]Sent: Thursday, March 8, 2018 1:42 PMTo: [email protected]; [email protected]: [email protected]: [Non-DoD Source] Irvington to Kino Newsletter #3 and Alternatives Map for review

Hello,

Tucson Electric Power (TEP) is encouraging stakeholders to help identify the preferred route for the proposedIrvington to Kino 138 kV transmission line to connect the Irvington Substation located at East Irvington Road andSouth Contractor’s Way to the planned Kino Substation at South Kino Parkway and East 36th Street. TEP has completed its alternatives analysis and selected 3 alternative routes. Attached is the final project newsletter thatincludes the 3 alternative maps. Please review this information and let us know:

1. Any issues that are important to you in evaluating the transmission line alternatives.

2. Whether there is an alternative you prefer and why.

TEP will use additional input received by March 28, 2018 to select a preferred route from these alternatives. TEPwill include all three alternatives and all input received from public meetings, in writing, and through onlinecomment tools, in its application to the Arizona Corporation Commission for a Certificate of EnvironmentalCompatibility, which we expect to file in April 2018.

Additional information is available at TEP’s website at: https://www.tep.com/irvington-to-kino/

<https://www.tep.com/irvington-to-kino/>

Please let me know if you have any questions or need additional information. Thank you,

Renee Darling

Senior Environmental & Land Use Planner Tucson Electric Power Company Land Resources – RC131

3950 E. Irvington Road

Tucson, AZ. 85714-2114

520-884-3642 Fax [email protected] <mailto:[email protected]>