Existing Guidelines Vs Proposed Guidelines
Clause
Existing Guidelines
Clause Proposed Guidelines Remarks / Reference
1.0 General :
The vendor approval policy shall be applicable
for approval of STM, vendor registration, de-
listing and re-instatement of status for vendors
for Small Track Machine and P. Way Measuring
Tool.
1.0 Purpose:
The vendor approval policy Guideline shall be applicable for
approval of Small Track Machines (STM), vendor
registration, Validity extension, de-listing and re-instatement
of status for vendors or any other issue related to Small
Track Machines and P. Way Measuring Tools.
Partially Modified to suit
requirement.
2.0 Scope:
2.1
This guideline covers the items for which vendors are
approved, during fresh registration, renewal of
registration, Up gradation from Part-II to Part-I, Down
gradation from Part-I to Part-II, Delisting from Part-I
/Part-II and new machine/machine under trial. All
approvals are granted based on the recommendations of
Small Track Machines Committee (STMC) duly
approved by Railway Board.
Scope added. In line with
other Directorate
Guidelines.
2.2 This guideline also covers the items recommended by
Small Track Machines Committee (STMC) and
subsequent approval by Board or any other issue related
to Small Track Machine and P.Way Measuring Tool.
2.0 Definitions: 3.0 Definitions:
2.1 Primary Vendor: The vendor who manufactures
the STM as per RDSO specification of its own
and supplies the same to Railways directly.
3.1 Primary Vendor: The vendor who manufactures the STM as
per RDSO specification of its own and supplies the same to
Railways directly.
2.2 Sub-Vendor: Vendor to whom primary vendor
out-sources the parts of the item or from whom
the primary vendor procures the item for supply.
Item supplied by the sub vendor will form part
3.2 Sub-Vendor: Vendor to whom primary vendor out-sources
the parts of the item or from whom the primary vendor
procures the item for supply. Item supplied by the sub
vendor will form part of the bill of material of the primary
of the bill of material of the primary vendor.
vendor.
3.0 Abbreviations:
RDSO : Research Designs and Standards
Organisation.
TMM Dte : Track Machines and Monitoring
Directorate
EDTM /RDSO : Executive Director/Track
Machines RDSO
STM : Small Track Machines
STR : Schedule of Technical Requirements
Tool : Permanent Way (track) measuring tool
QAP : Quality Assurance Plan
OEM : Original Equipment Manufacturer
AMC : Annual Maintenance Contract
NABL : National Accreditation Board for
Testing and Calibration Laboratories.
4.0 Abbreviations:
RDSO: Research Designs and Standards Organisation.
TMM Dte : Track Machines and Monitoring Directorate
EDTM /RDSO : Executive Director/Track Machines RDSO
STM : Small Track Machines
STMC: Small Track Machines Committee
STR : Schedule of Technical Requirements
Tool : Permanent Way measuring tool
QAP : Quality Assurance Plan
OEM : Original Equipment Manufacturer
AMC : Annual Maintenance Contract
NABL : National Accreditation Board for Testing and
Calibration Laboratories.
Same as existing
guideline para 3.0
4.0 Policy for vendor approval: 5.0 Guideline Policy for vendor approval: To incorporate new ON-
LINE procedure.
4.1 Development of various Small Track Machines
and P-way measuring tools by RDSO is
undertaken either,
i) as per decision of competent authority
ii) Firms offer to do development free of cost.
5.1 Development of various Small Track Machines and P-way
measuring tools by RDSO is undertaken either,
i) as per decision of competent authority
ii) Firms offer to do development free of cost.
iii) On receipt of on line application.
4.2 The firm shall either be a sole manufacturer or
importer/ agent.
5.2 The firm shall either be a sole manufacturer or importer/
agent.
Same as existing
guideline para 4.2
4.3 Starting from 1st Dec 2010, the process of
vendor registration has been made on-line. No
paper based applications shall be accepted by the
directorate.
5.3 Starting from 1st Dec 2010, the process of vendor
registration has been made on-line. No paper based
applications shall be accepted by the directorate.
OEM should only be considered for registration at RDSO
and name of Indian firm/ partner/ representative as
appointed by OEM should be mentioned below: the OEM in
the vendor Directory clearly indicating their status i.e.
“Indian firm/ partner/representative”.
Same as existing
guideline para 4.3
Vigilance SI no. 10/12
dated 17.12.12
4.4 Provision of application forms and other
documents: Vendors seeking registration for Small Track
Machines and Tools items shall register online
on the RDSO website.
5.4
5.4.1
5.4.2
Procedure for vendor approval during
online submission of application form-
For Vendor approval (Vendor Registration), TMM
Directorate shall follow following procedure.
Items for which Vendor Approval is Undertaken by
TMM Directorate: TMM Directorate shall process fresh registration as well as
renewal of registration of vendors for the items mentioned in
document TM-D-7.1-2. The items in TM-D-7.1-2 can be
deleted / included as per the instructions on the subject from
Railway Board/approval of competent authority.
i. Vendor seeking registration for item(s), controlled by
TMM Dte, shall apply for registration online through RDSO
website www.rdso.indianrailways.gov.in.
ii. Firm shall follow following route to reach online
application form –
www.rdso.indianrailways.gov.in Vendor Interface Online
Vendor Registration Civil Directorates Select
Directorate TMM DTE and follow.
iii. Vendors shall take adequate care to fill in the details in
the boxes provided (Vendors may use PDF format of on-line
application form available in Help Instructions for study
purpose). Vendor shall furnish factual data in Application
Para Modified as per
existing procedure laid
down in ISO.
Copy of TM-D-7.1-2
enclosed.
5.4.3
5.4.4
5.4.4.1
Form, which shall be verified during the course of vendor
registration/assessment.
Uploading of documents along with Online Application: Vendor shall upload following documents-
a. QAP as per the standard format
b. Self compliance of specification
c. Copy of ISO certificate (if available)
d. Copy of Digital Signature Certificate
e. Copy of latest Electricity bill bearing factory address
f. Copy of Factory license for SSI/NSIC
g. Copy of Ownership of the factory
(Lease/partnership Deed or Memorandum of Article
of Association).
(If the original is in other than Hindi/English
language, translated copy of the notarized document
shall be attached)
*only first two pages & last two pages shall be
scanned and sent.
h. Copy of the receipt of Bank on payment of charges
through RTGS
(Note: Vendor must ensure that all these
documents are properly uploaded).
Additional documents to be submitted during
assessment:
Undertaking for Infringement of IPR-
All the vendors shall submit an undertaking signed by
vendor on ‘Infringement of Patent Rights’. The undertaking
shall be as under-
Indian Railways shall not be responsible for
infringement of Patent Rights arising due to similarity
in design and development of this item and any other
5.4.4.2
5.4.4.3
5.4.4.3.1
5.4.4.3.2
5.4.4.3.3
factor not mentioned herein which may cause such a
dispute. The entire responsibility to settle any such
dispute lies with vendor. Signed copy in original to be
submitted at the time of field assessment.
Declaration of Confidentiality of submitted documents –
Vendor must classify their documents confidentiality
declaration such as-
This document and its content are the property of M/s
XYZ (name of vendor) or its subsidiaries. This
document contains confidential propriety information.
The reproduction, distribution, utilization or the
communication of this document or any part thereof,
without the express authorization is strictly prohibited.
Indian Railways/RDSO is granted rights to use, copy
and distribute this document for the use of inspection,
operation, maintenance and repairs etc. Signed copy in
original to be submitted at the time of field assessment.
Information for Classifying Allied/Sister Concerns-
In order to enable the railway administration to ascertain
whether the firm/company is an allied/sister concern of any
other firm/company, the firm/company applying for
registration/renewal shall furnish the following information
duly certified by a charted accountant along with registration
form-
Addresses
Addresses of offices and manufacturing works
For proprietorship
Name of any other firm, already registered for the same
item with RDSO, owned by him.
For Partnership Firms
a) Name of all the partners in case of partnership firm
b) Name of those partners who are also partners in any
5.4.4.3.4
5.4.4.4
5.4.4.5
other firm already registered for the same item with
RDSO along with the relationship and profit ratio.
For Companies
a) Name of all directors
b) Name of those directors who are Directors in any
other companies already registered for the same item
with RDSO along with the relationship and
shareholding. Signed copy in original to be submitted at
the time of field assessment.
In all above cases, vendor must give Name and
Designation of the Officials to whom all the
communication is to be made, E-Mail ID and Mobile
number and other contact numbers.
Undertaking giving for information to RDSO for any
changes in entities and information submitted during
registration, at any time after approval is accorded. (Signed
copy in original to be submitted at the time of field
assessment).
Scanned signed copy of Undertaking against Cartel
information as per the online application form for
registration (Signed copy in original to be submitted at the
time of field assessment).
4.5 Vendors who are foreign firms manufacturing
machines/tools or their authorized
agents/representative based in India and having
no manufacturing facility in India shall full-fill
the following requirements:
a) Firm shall have adequate infrastructure in
India for getting the type test done and for
assembling of components wherever
necessary
5.5 For approval of Imported Machine:
i) The registration under this procedure shall be granted to
the firm or its authorized agent / representative based in
India. The Indian firm/partner/representative if any will be
treated as sales representative of OEM subject to having
valid MOU or Agreement with OEM.
ii) Authorized agents / representatives shall produce an
authorization letter from the foreign manufacturer in original
indicating the equipment’s name and model number for
b) Firm shall have suitable repair/service
support set up in India for after sales
service and AMC.
c) Firm shall maintain a suitable inventory of
required spares in India.
d) Firm shall possess written authorization
from the principal / OEM regarding
supply of the item(s) to Indian Railways
full-filling of the above conditions.
e) The item must be suitable for Indian
environmental conditions.
f) In case of more than one authorized
importer/agent, each one shall apply
separately.
which they are authorized to conduct business in India.
The validity of MOU/agreement should be verified by
RDSO from OEM at the time of granting approval.
iii) In case of more than one authorized agent/
representative, each one shall apply separately.
iv) Firm shall have necessary infrastructure in India for
getting the acceptance tests done.
v) Firm shall have suitable repair / service support set up in
India. Component level maintenance shall be carried out in
India. Railway will only interact with the approved
Authorized agents / representatives. Firm shall maintain a
suitable inventory of modules/ sub-assemblies in India and
the turnaround time for repair of a module/ sub assembly
shall be less than one month.
A paragraph should be mentioned in vendor directory that
Railway while placing order should re-verify the validity of
MOU/Agreement with OEM.
Approval for an imported machine will be accorded for
original machine along with all fittings and fixtures without
any modification/change
(i) Imported machines include all fitments, attachments,
accessories as imported.
(ii) The consignee should check import authenticity
of imported machines. Some of the documents
that may be relied upon are
(a) Original equipment manufacturer test certificate
(b) Bill of lading
(c) Bill of entry
(d) Original packing slip etc.
Normally part indigenization shall not be permitted. In case
supplier wants to indigenize any part he should approach to
RDSO with details of transfer of technology approved from
OEM and the case shall be dealt as afresh as per para 7.0.
4.6 (i) The item for which approval is sought, shall
normally meet the requirement of RDSO
specifications. However any deviation, not
affecting its performance on Indian Railways
may be considered by the Standing
Committee on Small Track Machines
(STMC). The manufacturer should have a
QAP and should maintain all the necessary
records of implementation of Quality
Assurance Plan (QAP). Minimum
requirements should be prescribed in the
detailed guidelines to be issued by RDSO.
(ii) Minimum following documents shall be
maintained with proper records by the firm
regarding implementation of Quality
Assurance Plan (QAP), if available.
a) Organization chart emphasizing quality
control setup.
b) Qualification of key personnel and the
manpower deployed in quality control
department.
c) Process flow chart indicating stages of
manufacturing process for individual product
and / or for a family of product if the process
is same.
d) Quality Assurance System-Inspection and
Testing plan. This shall cover the following:
i) Incoming Material
ii) Process control
iii) Product control
iv) System control
v) Gauging scheme- in the format for each
5.6 Preparing & submission of Quality Assurance Plan
(QAP) during fresh registration: (a) The firm shall upload QAP for the applied item along
with fresh registration form. QAP in triplicate needs to be
submitted at the time of field assessment of the firm.
(b) QAP shall be prepared as per the guidelines, available on
RDSO website (www.rdso.indianrailways.gov.in
Directorate Track Machines and Monitoring Vendors
Guidelines for Vendors Development and
Approval (Small Track Machines/P.Way Measuring Tools).
Section‘0’ Revision sheet
Section‘A’ Organization Chart
Section‘B’ Qualification and experience of Quality
Control personnel
Section C’ Process flow chart/description of
manufacturing process
Section‘D’ Details of sub-assemblies/components
manufactured in house and outsourced.
Section E’ Quality Assurance System-Inspection and
Testing plan. This shall cover the
following:
i) Incoming Material
ii) Process control
iii) Product control
iv) System control
v) Gauging scheme- in the format for each
operation gauges shall be mentioned, if used.
vi) Internal inspection.
vii) Source of procurement for raw
materials.
Section‘F’ Calibration of testing measuring equipment.
Same as existing but
rearranged.
operation gauges shall be mentioned, if used.
vi) Internal inspection.
vii) Source of procurement for raw materials.
viii) System of calibration of testing and
measuring equipment.
The QAP thus prepared following the above
minimum points shall be got approved by
RDSO.
Section‘G’ System of maintaining the date of customer
complaints/warranty failures.
Section H’ Any additional information firm wishes to
submit.
(c) QAP covering complete information as above must be
given in the form of single document indicating name of the
firm and page no. ‘x’ of ‘y’ on each page. Each page should
be signed by Quality Control in-charge. The approved QAP
must be a controlled document and a quality record of ISO
Quality Control System of the vendor (if applicable). A
certificate to this effect shall be provided along with the
QAP by the vendor.
(d) The QAP shall be provisionally approved by the officer
carried out the capability assessment and final approval shall
be given by Executive Director/TM. This will be subject to
review/upgradation by RDSO in the light of fresh data &
experience.
4.7 Vendor shall preferably possess valid ISO
9001:2000 certificate for his works address,
covering the items for which he seeks
registration with RDSO.
5.7 Vendor shall preferably possess valid ISO 9001:2008
certificate for his works address, covering the items for
which he seeks registration with RDSO.
Same as existing
guideline para 4.7
4.8 It is desirable to possess valid digital signature
and the firm shall submit the following details:
a) Name of the Certifying Authority
b) ID of the holder of Digital Certificate
c) Date of issue of Digital Certificate
d) Validity of Digital Certificate
5.8 Vendor shall possess valid digital signature and the firm
shall submit the following details:
a) Name of the Certifying Authority
b) ID of the holder of Digital Signature Certificate
c) Date of issue of Digital Signature Certificate
d) Validity of Digital Signature Certificate
Same as existing
guideline para 4.8
4.9 The testing facilities and measuring equipment
which are available in house shall be duly
calibrated by a government test house or other
agencies of national standards, accredited by
NABL.
5.9 The testing facilities and measuring equipment which are
available in house shall be duly calibrated by a government
test house or other agencies of national standards, accredited
by NABL.
Same as existing
guideline para 4.9.
4.10 While applying for approval to manufacture and
supply of the product, the firm shall ensure that
:-
i) All the relevant documents i.e.
drawings/specifications etc. have been purchased
from RDSO at requisite fee and studied.
ii) The required plant and machineries,
infrastructural facilities and quality systems are
available.
iii) The testing facilities and measuring
equipment which are available in house, shall be
duly calibrated by a government test house or
other agencies of national standards.
5.10 While applying for approval to manufacture and supply of
the product, the firm shall ensure that :-
i) All the relevant documents i.e. drawings/specifications
etc. have been purchased from RDSO at requisite fee and
studied.
ii) The required plant and machineries, infrastructural
facilities and quality systems are available.
iii) The testing facilities and measuring equipment which are
available in house shall be duly calibrated by a government
test house or other agencies of national standards.
Same as existing
guideline para 4.10.
5.0
(i) Charges :
The following table lists the charges for different
activities for the process of vendor scrutiny /
approval /renewal etc.
6.0 i) Charges :
The following table lists the charges for different activities
for the process of vendor scrutiny / approval /renewal etc.
Same as existing
guideline para 5.0
Annexure Annexure A
(ii) RDSO reserve the right to change the
charges/introduce additional charges without
prior notice.
ii) RDSO reserves the right to change the charges/
introduce additional charges without prior notice.
6.0
Technical capability assessment for approval :
7.0 Technical capability assessment for approval :
Same as existing
guideline para 6.0
6.1
Application and its Assessment:
Applications should be scrutinized by RDSO
within a stipulated timeframe, (45 days of the
receipt of the application) and any additional
information can be sought during this period
from the firm. The firm may be allowed to reply
within a period of 45 days. Upon due
consideration of the application and such replies,
7.1
Application and its Assessment:
Applications should be scrutinized by RDSO within a
stipulated timeframe, (45 days
from the receipt of the application) and any deficiencies/
additional information noticed during scrutiny can be sought
during this period from the firm. The firm may be allowed
to reply within a period of 45 days. If the reply is not
received within 45 days or reply is not in order show-cause
Procedure has been
modified to limit the time
of scrutiny and reply of
the firm.
the ED/TMM/RDSO would take a decision
whether on the basis of information supplied,
firm can be considered for a visit for assessment
of its capability. The visit should be undertaken
within 45 days of receipt of reply from firm and
payment of due charges, as stipulated by RDSO.
If the application and details submitted are not
found satisfactory and the application is rejected,
firm shall be advised of deficiencies giving a
timeframe (max. 6 months to comply). If the
firm reports complete compliance within the
stipulated time, the case may be reviewed with
the permission of ED(TMM)/RDSO. If the firm
fails to report complete compliance within the
above mention period, the firm will have to
apply afresh to RDSO.
notice will be given to firm with reasonable opportunity to
comply within 30 days. If reply is not received or not
satisfactory, the case will be temporarily closed. Once the
case is temporarily closed, the case can be reopened for
reprocessing with the approval of ED/TM, if the firm reports
complete compliance within six months from date of making
communication for temporary closure. If the firm fails to
reports complete compliance within the above mentioned
period, the case shall be finally closed and the firm shall be
asked to apply afresh to RDSO.
7.1.1 Closure of fresh registration case: (a) Temporary closure of fresh registration case during
scrutiny of application/field assessment stage: Director/
Joint Director-TM shall recommend for temporary closure if
there are major deficiencies in infrastructure, firm failing to
offer sample for testing in a reasonable period of time, firm
failing to comply deficiencies. The case shall be temporarily
closed, after issuing a show cause notice.
(b) Show cause notice & period of temporary closure:
Before temporary closure, the firm shall be given a
reasonable opportunity by issuing a show cause notice and
giving time of 30 days. A show cause notice shall be issued
by RDSO. File shall be closed temporarily for a period of
six months from the date of making communication for
temporary closure after approval by EDTM.
(c) Re-opening of temporary closed cases: Once the case is
temporary closed for a period of six months, no
communication will be made with the firm. The case shall
be reopened, after six months on the firm’s request,
provided firm submits complete compliance to RDSO with
Para modified to restrict
endless time of
compliance. Firms used
to give
incomplete/unsatisfactory
reply and case used to
keep on open for a long
time. In line with
QA/Civil Policy.
supporting documents and photographs, if any. On receipt of
the compliance, case shall be examined and put up for
approval of EDTM. If approved, the case shall be advised to
process further. However, if the deficiencies are again
observed after reopening, the case shall be final closed with
approval of EDTM.
(d) Final closure of case file: If firm do not comply
deficiencies and compliance is not received at RDSO within
six months period of temporary closure, case shall be final
closed and firm shall be informed. No show cause notice
needs to be issued for final closure. Once the case is final
closed, the firm needs to apply afresh for approval of the
item.
6.2
The firm shall make necessary arrangements for
the inspection related to technical capability
assessment of the firm. During the inspection,
the inspecting officials shall have free access to
all the sections of the firm’s premises.
7.2 The firm shall make necessary arrangements for the
inspection related to technical capability assessment of the
firm. During the inspection, the inspecting officials shall
have free access to all the sections of the firm’s premises.
Same as existing
guideline para 6.2
6.3
During assessment, the firm shall produce all the
documents in original in support of the
establishment of the plant & machineries of the
firm. Copies of all the relevant documents shall
also be handed over to the inspecting officials.
Supporting technical documents regarding
manufacture of the item for which approval is
being sought, shall also be checked.
7.3 During assessment, the firm shall produce all the documents
in original in support of the establishment of the plant &
machineries of the firm. Copies of all the relevant
documents shall also be handed over to the inspecting
officials. Supporting technical documents regarding
manufacture of the item for which approval is being sought,
shall also be checked.
Same as existing
guideline para 6.3.
6.4
If any deficiency is observed during assessment
in manufacturing, assembly and testing facilities
of the firm, the same shall be intimated to the
firm for making good within a stipulated period,
(6 months) which shall be verified by the
inspecting official again (within 45 days of such
7.4 If any deficiency is observed during assessment in
manufacturing, assembly and testing facilities of the firm,
the same shall be intimated to the firm for making good
within a stipulated period, (i.e. 6 months) which shall be
verified by the inspecting official again (within 45 days of
such compliance). After passage of six months, his
Same as existing
guideline para 6.4
compliance). After passage of six months, his
application will be treated as cancelled and after
that it will have to apply afresh. However, at the
request of the firm another three months can be
given by the directorate head i.e. EDTM after
satisfying himself with the merit of the case and
genuineness of the delay.
application will be treated as cancelled and after that it will
have to apply afresh. However, at the request of the firm
another three months can be given by the directorate head
i.e. EDTM after satisfying himself with the merit of the case
and genuineness of the delay.
6.5
After successful assessment of the firm, it shall
be asked to manufacture prototype samples. The
firm shall conduct testing and inspection of
prototype samples as mentioned in the
specification and drawing as a pre acceptance
test/ internal test of prototype and the results of
the same alongwith drawing of sample ( if any)
shall be submitted to RDSO.
7.5 After successful assessment of the firm, it shall be asked to
manufacture prototype samples. The firm shall conduct
testing and inspection of prototype samples as mentioned in
the specification and drawing as a pre acceptance test/
internal test of prototype and the results of the same
alongwith drawing of sample ( if any) shall be submitted to
RDSO.
Same as existing
guideline para 6.5
6.6
If the firm is already approved for a particular
product and desires to apply for approval of their
firm for “similar product” requiring same QAP
and machinery and plant, capability cum
capacity assessment of the firm can be waived
off by EDTM/RDSO after ascertaining that the
firm has enough capacity to manufacture this
item based on past record and no additional
facilities would be required for manufacture of
the item in question.
7.6 If the firm is already approved for a particular product and
desires to apply for approval of their firm for “similar
product” requiring same QAP and machinery and plant,
capability cum capacity assessment of the firm can be
waived off by EDTM/RDSO after ascertaining that the firm
has enough capacity to manufacture this item based on past
record and no additional facilities would be required for
manufacture of the item in question.
Clause may be deleted as
covered in detail in
clause no. 13.
6.7
It the firm is already approved for a particular
product and desires to supply some additional
products, it shall be considered as a fresh
registration case and the same procedure will be
applicable as for fresh registration.
7.6
It the firm is already approved for a particular product and
desires to get registered for some additional products, it shall
be considered as a fresh registration case and the same
procedure will be applicable as for fresh registration.
Same as existing
guideline para 6.7
7.0 7.1
Prototype Testing:
Testing and inspection of prototype samples
shall be carried out by RDSO as per approved
RDSO specification/drawing and functional
8.0 8.1
Prototype testing:
Testing and inspection of prototype samples shall be carried
out by RDSO as per approved RDSO specification/drawing
and functional requirements. This will include the tests for
chemical composition, hardness, mechanical properties etc.
requirements. This will include the tests for
chemical composition, hardness, mechanical
properties etc. as applicable, and to be carried
out at manufacturer’s premises. In case the
testing facilities are not available with the firm,
the test shall be done from a reputed Govt.
recognized testing agency. Field trials will also
be arranged by the firm, whenever required.
as applicable, and to be carried out at manufacturer’s
premises or as mutually agreed between RDSO and the firm.
In case the testing facilities are not available with the firm,
the test shall be done from a reputed Govt. recognized
testing agency. Field trials will also be arranged by the firm,
whenever required.
During testing criteria specified in type test shall be
followed. Any additional testing as desired by RDSO may
also be carried out. If type test criteria is not mentioned in
specification test chart approved by Joint Director/Director
may be followed for this purpose.
Same as existing
guideline para 7.1
New line is added to
facilitate testing.
7.2
If the samples do not fulfill the requirement(s) as
mentioned in the specification/ drawing of the
item concerned in the testing conducted by
RDSO, the firm shall be advised to submit fresh
samples after compliance of short-comings/
deficiencies observed during testing, within a
stipulated time of (6 months). If the firm fails to
make good the deficiencies within stipulated
time the application will be rejected.
8.2 If the samples do not fulfill the requirement(s) as mentioned
in the specification/ drawing of the item concerned in the
testing conducted by RDSO, the firm shall be advised to
submit fresh samples after compliance of short-comings/
deficiencies observed during testing, within a stipulated time
of (6 months) from the date of communication of
deficiencies/short comings. If the firm fails to make good
the deficiencies within stipulated time the application case
will be rejected permanently closed.
Same as existing
guideline para 7.2.
Partial modification in
line wirh para no. 7.0.
7.3
For the tests/field trials/assessment the
concerned firm shall extend all facilities to the
inspecting team as required for completing the
tests etc.
8.3 For the tests/field trials/assessment the concerned firm shall
extend all facilities to the inspecting team as required for
completing the tests etc.
Same as existing
guideline para 7.3
7.4
After successful testing, the prototype sample
will be preserved at RDSO for a period of
minimum one year or as advised by RDSO.
There will not be any commercial obligation on
RDSO/Indian Railways.
8.4 After successful testing, the prototype sample will be
preserved at RDSO for a period of minimum one year or as
advised by RDSO. There will not be any commercial
obligation on RDSO/Indian Railways.
Same as existing
guideline para 7.4
7.5
After satisfactory completion of the tests and
field trials, the detailed reports shall be put up to
Standing Committee on Small Track Machine
who will submit its recommendations to Board.
8.5 After satisfactory completion of the tests and field trials, the
detailed reports shall be put up to Standing Committee on
Small Track Machines who will submit its recommendations
to Board.
Same as existing
guideline para 7.5
8.0
Approval:
9.0
9.1
Approval:
Competent Authority:
The specifications and vendors lists of Small Track
Machines will require approval of Add. Member (CE). ME
may duly be kept informed & new type of Small Track
Machines which are proposed for development (Trial) will
require the consent /approval of Board (ME). All the
necessary procedural, technical, record keeping and nodal
assistance shall be provided by TMM Directorate of RDSO.
The Standing Committee on Small Track Machines (STMC)
shall examine all new/existing cases as per the policy and
will submit committee recommendations to Railway Board.
After the approval of competent authority the same will be
communicated. The meeting of Standing Committee shall
be held twice in a year normally at an interval of 6 months.
The STMC shall also periodically review the usage and
utility of approved machines and give recommendations for
improving the same.
Same as existing
guideline para 8.1
8.1
Competent Authority:
The specifications and vendors lists of Small
Track Machines will require approval of Add.
Member (CE). ME may duly be kept informed &
new type of Small Track Machines which are
proposed for development (Trial) will require the
consent /approval of Board (ME). All the
necessary procedural, technical, record keeping
and nodal assistance shall be provided by TMM
Directorate of RDSO. The Standing Committee
on Small Track Machines (STMC) shall examine
all new/existing cases as per the policy and will
submit committee recommendations to Railway
Board. After the approval of competent
authority the same will be communicated. The
meeting of Standing Committee shall be held
twice in a year normally at an interval of 6
months. The STMC shall also periodically
review the usage and utility of approved
machines and give recommendations for
improving the same.
8.2
Approval for an OEM/imported machine will be
accorded for original machine along with all
fittings and fixtures without any
modification/change
(ii) Imported machines include all fitments,
attachments, accessories as imported.
(ii) The consignee should check import
authenticity of imported machines. Some
of the documents that may be relied upon
9.2 Shifted in para 4.5
are
(a) Original equipment manufacturer test
certificate
(b) Bill of lading
(c) Bill of entry
(d) Original packing slip etc.
8.3 Normally part indigenization shall not be
permitted. In case supplier wants to indigenize
any part he should approach to RDSO with
details of transfer of technology approved from
OEM and the case shall be dealt as afresh as per
para 6.0.
9.3 Shifted in para 4.5
8.4 RDSO/Indian Railway reserves the right of
rejecting any machine/firm without assigning
any reason to the firm.
9.2 RDSO/Indian Railway reserves the right of rejecting any
machine/firm without assigning any reason to the
firm.
Same as existing
guideline para 8.4
9.0
Fresh Registration for the new type of small track
machines or P.Way measuring tools:
10.0
10.1
Fresh Registration for the new type of small track machines
or P.Way measuring tools:
The vendor seeking approval for a new type of
machine/tool, which does not figure in the current list of
approved type of machines/tools, needs to apply in same
manner as applicable for developmental category/multi-
sourcing. All the procedure and steps right from submission
of application to approval by competent authority will also
be same as applicable for developmental category/multi-
sourcing except with the following differences. Para 9.1 will
be followed in these cases.
Same as existing
guideline para 9.0
9.1 The vendor seeking approval for a new type of
machine/tool, which does not figure in the
current list approved type of machines/tools,
needs to apply in same manner as applicable for
developmental category/multi-sourcing. All the
procedure and steps right from submission of
application to approval by competent authority
will also be same as applicable for
developmental category/multi-sourcing except
with the following differences:
Same as existing
guideline 9.1
9.2 The approval for new item should be given only
after the field trials and satisfactory performance
in field trials.
10.2 The approval for trial of a new type of machine/tool, which
does not figure in the current list of approved type of
machines/tools should be given only after the field trials and
satisfactory performance in field by RDSO officials.
9.3 For new items, initially only broad functional
requirements should be issued from RDSO for
10.3 For new items, initially only broad functional requirements
should be issued from RDSO for the development of the
Same as existing
guideline para 9.3
the development of the product on trial basis and
after satisfactory performance of the equipment
thus procured, regular technical specifications
should be drawn. The functional requirement
may not be sent to Board for approval. Only
detailed technical specifications after
development of the item may be sent to Board
for approval to be given at the level of AM (CE).
product on trial basis and after satisfactory performance of
the equipment thus procured, regular technical specifications
should be drawn. The functional requirement may not be
sent to Board for approval. Only detailed technical
specifications after development of the item may be sent to
Board for approval to be given at the level of AM (CE).
9.4 After due deliberation, STMC will recommend
the initial approval for trial only, proposing some
of the zonal Railways to procure and use the new
item alongwith suggested trial quantities and the
period of trial before regular adoption. The
performance report of the new type of
machine/tool will be submitted by the zonal
Railways after predefined period and use.
Performance Report shall be submitted with the
approval of SAG officer nominated to deal STM
and under the signatures of an officer not below
the rank of JAG. The performance report will be
put up to Standing Committee on Small Track
Machine who will deliberate and submit
recommendation to Railway Board for its regular
use or otherwise.
10.4 After due deliberation, STMC will recommend the initial
approval for trial only, proposing some of the zonal
Railways to procure and use the new item along with
suggested trial quantities and the period of trial before
regular adoption. The performance report of the new type of
machine/tool will be submitted by the zonal Railways after
predefined period and use. Performance Report shall be
submitted with the approval of SAG officer nominated to
deal STM and under the signatures of an officer not below
the rank of JAG. The performance report from at least one
Zonal Railway will be required for upgradation from Trial
order to Regular use. The performance report will be put up
to Standing Committee on Small Track Machine who will
deliberate and submit recommendation to Railway Board for
its regular use or otherwise. The vendor thus approved will
be listed as Part-I directly in current list of approved type of
machines/tools. If Trial of a machine is not completed
within five years from the date of initial approval, it would
be considered that the machine of no use to Railway and it
will be dropped from the list of new machines.
Same as existing
guideline para 9.4
Performance from only
one Zonal railway will
suffice in case of New
Machine.
10.0:
Validity of approval
11.0
11.1
Validity of approval:
The approval shall generally be given up to validity of
existing Approved List of Vendors or for a period of three
year whichever is less.
Extension of approval, generally for 03 years shall be
examined and recommended by Small Track Machine
Committee (STMC) after due deliberation of applications,
As per STMC
recommendation
10.1 The approval shall generally be valid for two
years. Extension of approval, generally for 2
years shall be examined and recommended by
Small Track Machine Committee (STMC) after
due deliberation of applications, performance,
usages and utility.
performance, usages and utility. However, if meeting of
STMC could not be conducted or its minutes are not
approved by Railway Board, EDTM/RDSO is empowered to
extend the validity up to three months from the date of
expiry of existing approval.
To facilitate supply of
machines if STMC could
not be conducted.
10.2
For extension, the firm should apply at least
three months before the expiring of the existing
approval.
11.2 For extension, the firm should apply at least three months
before the expiring of the existing approval. If application is
received at RDSO before two months in advance of the
expiry of validity, it shall be processed. Otherwise firm will
be temporarily de-listed from the date of expiry of existing
validity. However EDTM may review the delay in
submission of application on case to case basis and consider
the application for grant of validity extension.
Language modification.
Modified to limit the time
line of granting
extension.
NEW 11.3 If the firm is temporarily delisted on account of Late
application received, and its application is received within
Three months from the date of Existing approval, It shall be
processed and will be put up to next STMC meeting for
consideration. Till the approval is given, the firm will
remain temporarily delisted.
Modified to limit the time
line of granting
extension.
10.3 After six months from the expiry of the earlier
approval, the vendor will be permanently de-
listed from the approved list and will have to
apply afresh.
11.4 After Three months from the expiry of the earlier approval,
the vendor will be permanently de-listed from the approved
list and will have to apply afresh.
Same as existing
guideline para10.3
10.4 During validity period of approval, if the firm
doesn’t participate in tenders invited by zonal
railways, RDSO officials shall inspect the firm’s
premises, for the purpose of further extension of
the validity period of approval in case the firm
has applied for the same.
11.5 During validity period of approval, if the firm doesn’t
participate in tenders invited by zonal railways, and on
enquiry by RDSO, the firm shall furnish the reasons for not
participation. The case will be put up to STMC for
deliberation.
Same as existing
guideline para10.4
11.0
Change of Specification:
12.0 Procedure to introduce new specification/or change
existing specification:
11.1
In order to improve the quality and /or
performance of the approved machine/tool,
whenever a need arise for a major change in
specification/schedule of technical requirement
12.1.1
Draft specification to be displayed on website: (a) Whenever there is a proposed new introduction or
change of procedure/specification/Drawing or any other
aspects having relevance in the manufacturing and quality of
As per QM-G-7.1-3
Clause no 4.19
As per QM-G-7.1-3
Clause no 4.19.1
As per QM-G-7.1-3
or any other aspects in view of the
RDSO/Railway, the suggested changes shall be
informed to the vendor(s) by the RDSO.
Already approved vendor(s) shall be required to
comply with changes within the time frame
specified by RDSO. Also the applicant vendor
seeking fresh approval shall be required to
comply with all the changes before the approval
is granted.
12.1.2
12.1.3
the product, the draft copy of newly introduced
document/changed document shall be put up on the RDSO
website requesting for comments by the vendors or other
external bodies or persons for a duration of at least one
month.
(b) It is to be ensured that contact details must be clearly
available to the users of the website for sending comments.
(c) All comments and suggestions collected at the end of this
period should be deliberated and decisions should be taken
recording the reasons for acceptance/ rejection of the
suggestions and comments.
(d) These deliberations shall be put up on the website along
with final acceptable copy of the document for a period of
fifteen days. After which these shall be removed from the
website and shall be filed.
Communication to approved vendors and meeting for
discussion on draft: (a) Whenever there is a change in
procedure/specification/Drawing or any other aspects having
relevance in the manufacturing and quality of the product,
the draft copy of the revised document shall be provided to
all the approved vendors by the Directorate controlling these
documents.
(b) A meeting to discuss the ramifications of changes
proposed shall be convened by the directorate and all
approved vendors should be invited for discussions. Minutes
of such meetings shall be recorded and uploaded to the
website and retained there for a period of fifteen days.
Approval & Issue of revised documents:
The documents shall be finalized after approval of
competent authority and will be issued after addressing all
comments received against the draft documents and those
recorded in the meeting minutes. Copies of the final revised
Clause no 4.19.2
12.1.4
12.1.5
12.1.6
& approved documents shall be given to the approved
vendors free of cost.
Date of enforcement The date from which the revised specification is to be
enforced is to be decided by the directorate head, keeping in
view the time reasonably required by the existing vendors to
comply with the changed provisions and shall be mentioned
in the Specification. Also, if necessary, some specific
clauses may be made effective from different dates and the
same shall be mentioned against the respective clauses in the
specification
Time Frame To be Given to Existing approved Vendors
for Switching Over from Old Specifications to New
Specifications- A 12 months time will be given to all
Existing approved vendors to switch over form old
specifications to new specifications. In this transition period,
so as to have a continuous supply of machines, both versions
of the machines will be accepted/continued.
Compliance to Changes by the vendors: The already approved vendor shall be required to comply
with above mentioned changes on a written time-bound
basis. However, the applicants seeking fresh approval shall
be required to comply with all the changes before the
approval is granted
12.2 Procedure to introduce the machine of higher version in
lieu of lower version.
Whenever there is a proposal to introduce the machine of
Higher version in lieu of Lower version, all existing
approved vendors of Lower version machine will be
informed about the proposal and a copy of specification of
Higher version machine will be provided to them free of
cost.
A time period of twelve months shall be given to all existing
As per Board approval
dated 19.08.2013
approved vendors of Lower version machine to develop the
machine as per higher version specification.
In this transition period of twelve months, both versions of
the machines with existing lower version specification as
well as machine with higher version specification are to be
continued /accepted so as to have a continuous supply of
machines.
11.2 If any approved vendor intends to modify or
bring a major change in specification/schedule of
technical requirements or any other aspects for
improvement, the changes/modifications shall be
intimated to RDSO with time-frame for
materializing of such changes. The
changes/modifications shall be verified by
RDSO by conducting fresh type test as decided
by EDTM/RDSO.
12.3 If any approved vendor intends to modify or bring a major
change in specification/schedule of technical requirements
or any other aspects for improvement, the
changes/modifications shall be intimated to RDSO with
time-frame for materializing of such changes. The
changes/modifications shall be verified by RDSO by
conducting fresh type test as decided by EDTM/RDSO.
Same as existing
guideline para11.2
11.3 Fresh product sample testing shall necessarily be
done whenever there is a major change in
design, manufacturing process or specification.
This testing shall normally be done in firm’s
premises.
12.4 Fresh product sample testing shall necessarily be done
whenever there is a major change in design, manufacturing
process or specification. This testing shall normally be done
in firm’s premises or as decided by RDSO as mutually
agreed.
Same as existing
guideline para11.3
11.4 All such cases of change in specification shall
be deliberated in ensuing meeting of standing
Committee on Small Track Machines for review
and necessary recommendation.
12.5 All such cases of change in specification shall be deliberated
in ensuing meeting of standing Committee on Small Track
Machines for review and necessary recommendation.
Same as existing
guideline para11.4
NEW 13.0
Change of Engine/Motor or any Other major
component of the machine
If the firm is already approved for a particular Machine and
desires to change engine/Motor of the machine which can
affect functionality of the machine or cost of machine in
substantial manner, then following cases can be considered-
There have been cases
where Vendors may want
to change engine/motor.
Earlier there was no such
procedure for the same.
13.1 13.1.1 13.1.2 13.1.3 13.1.4 13.2 13.2.1
Case-1 –OEM of Engine /motor is same but
manufacturing/production/assembling country is
changed- If the firm is already approved for a Machine with
particular engine/Motor of a OEM and desires to change
engine/Motor of different manufacture/origin country with
same OEM and same model, Then-
(i)The firm has to submit a Certificate from OEM that the
engine/Motor has same specifications whether
manufactured/produced/assembled in any other country
(give names) and performance parameters are same and not
affected in any way.
(ii) Certificate of Self Compliance from the Firm with full
details of Engine/motor changed that their machine meets all
parameters as per existing specifications and functionality of
machine is not affected by changing the engine/motor.
(iii) Engine/Motor matching test certificate from OEM if
applicable.
Above documents will be scrutinized by RDSO within a
stipulated timeframe (45 days from the date of receipt at
RDSO) and after having satisfied, the firm will be advised
about prototype testing which will be carried out as per Para
no. 8.0.
Till the firm is approved with changed
engine/motor/component, it will continue to supply machine
with existing approved engine/motor/component.
If approved, the above case will not affect the Status of the
Firm and status will remain same as part-I/Part-II/Trial
Order as the case may be. Otherwise Para no. 8.2 will be
followed.
Case-2- OEM of Engine /motor is same but model has
been discontinued/upgraded- If the firm is already approved for a Machine with
particular engine/Motor of a OEM and desires to change
engine/Motor different model with same OEM, due to
13.2.2 13.2.3 13.2.4 13.3 13.3.1
existing model discontinued/upgraded, Then-
(i)The firm has to submit a Certificate from OEM that the
existing model of engine/Motor has been
discontinued/upgraded.
(ii) Certificate of Self Compliance from the Firm with full
details of Engine/motor changed that their machine meets all
parameters as per existing specifications and functionality of
machine is not affected by changing the
engine/motor/component due to existing model of
engine/Motor/Component has been discontinued/upgraded.
(iii) Engine/Motor matching test certificate from OEM if
applicable.
Above documents will be scrutinized by RDSO within a
stipulated timeframe (45 days from the submission) and
after having satisfied, the firm will be advised about
prototype testing which will be carried out as per Para no.
8.0.
Till the firm is approved with changed
engine/motor/component, it will continue to supply machine
with existing approved engine/motor/component.
If approved, the above case will not affect the Status of the
Firm and status will remain same as part-I/Part-II/Trail
Order as the case may be. Otherwise Paa no. 8.2 will be
followed.
Case-3- OEM of Engine /motor was having Joint
venture/Technical collaboration/Partnership/or any
other shareholding with other Firm/Company and they
are separated/bifurcated- If the firm is already approved for a Machine with
particular engine/Motor of a OEM which was having Joint
venture/Technical collaboration/Partnership/or any other
shareholding with other Firm/Company and they are now
separated-
(i)The firm may continue with engine/motor manufactured
13.3.2 13.3.3 13.3.4 13.3.4
by its principal technology provider of the Joint
venture/Technical collaboration/Partnership/or any other
shareholding however it has to submit a Certificate from its
principal technology provider that they were the principal
Technology provider and the existing Joint
venture/Technical collaboration/Partnership/or any other
shareholding with other firm/company is broken and the
model of engine/Motor now manufactured under their Brand
Name has same specifications and performance parameters
are same and not affected in any way .
(ii) Certificate of Self Compliance from the Firm with full
details of Engine/motor/component changed that their
machine meets all parameters as per existing specifications
and functionality of machine is not affected by changing the
engine/motor/component.
Above documents will be scrutinized by RDSO within a
stipulated timeframe (45 days from the submission) and
after having satisfied, the firm will be advised about
approval.
Till the firm is approved with changed
engine/motor/component, it will continue to supply machine
with existing approved engine/motor/component.
The above case will not affect the Status of the Firm status
will remain same as part-I/Part-II/Trial Order as the case
may be.
However if the firm desires to change
engine/motor/component manufactured by other than its
principal technology provider, the case will be dealt as the
case will be dealt as Fresh/New registration case and firm
shall be accorded Part-II status with new
Engine/motor/components.
Case-4- OEM of Engine /motor is changed
13.4 13.4.1 13.5 13.5.1
If the firm is already approved for a Machine with
particular engine/Motor of a OEM and wants to change the
engine with different OEM, then-
(i) It will be treated as Fresh/New registration case and firm
shall be accorded Part-II status for same machine the new
Engine/motor/components.
However, QAP and machinery and plant, capability cum
capacity assessment of the firm can be waived off by
Directorate head. Sr. ED/ED will have to ascertain that the
firm has enough capacity to manufacture this item based on
past record and no additional facilities would be required for
manufacture of the item.
(ii) The charges as applicable are to be paid by the firm.
Case-5- Firm wants to supply similar machine with
two/more type of Engine/motor/components-
If the firm is already approved for a Machine with
particular engine/Motor of a OEM and wants to supply
similar machine with two/more type of
Engine/motor/components with different OEM, then-
(i) The firm will continue to be approved in same status with
existing engine/motor. However the case of additional
engine/motor will be treated as Fresh/New registration case
and firm shall be accorded Part-II status for same machine
with new Engine/motor/components.
However, QAP and machinery and plant, capability cum
capacity assessment of the firm can be waived off by
Directorate head. Sr. ED/ED will have to ascertain that the
firm has enough capacity to manufacture this item based on
past record and no additional facilities would be required for
manufacture of the item.
(ii) The charges as applicable are to be paid by the firm.
12.0 Type of vendor list:
14.0 Type of vendor list:
Same as clause no 12.0
12.1
Track Machine & Monitoring Directorate shall
maintain a master list of approved vendors in
two categories
(i) for regular supply (i.e. for Part-I & Part-II)
and
(ii) for trial orders
14.1 Track Machine & Monitoring Directorate shall maintain a
master list of approved vendors in two categories
(i) for regular supply & Development order (i.e. for Part-I &
Part-II) and
(ii) for New machine/Machine under trial
12.2 The vendors approved and included in Part-I are
for regular supply and are eligible for getting an
order for full quantity of the tender whereas the
vendors approved and included in Part-II are for
developmental order and eligible for getting an
order for a part quantity (upto 20%) of the tender
quantity as per the extant rules of store tendering
system.
14.2 The vendors approved and included in Part-I are for regular
supply and are eligible for getting an order for full quantity
of the tender whereas the vendors approved and included in
Part-II are for developmental order and eligible for getting
an order for a part quantity as per stores procurement policy
as amended time to time.
Recommendation of
STM Standing
Committee
Vig .Cell SI no. 0lof
9/2013
13.0
Withholding / Suspension of approval of the
vendor:
15.0 Withholding / Suspension of approval of the vendor:
13.1
Suspension and de-listing of approval of the
vendor:
a. Performance reports/Complaints from
Users/Adverse Performance Report:
Upon receiving such an adverse report from
zonal railways which must be issued with the
approval of SAG officer nominated for looking
after STM and signed by an officer not below the
15.1 Suspension and de-listing of approval of the vendor:
a. Performance reports/Complaints from Users/Adverse
Performance Report:
Upon receiving such an adverse report from zonal railways
which must be issued with the approval of SAG officer
nominated for looking after STM and signed by an officer
not below the rank of JAG, RDSO shall investigate the
Same as clause no 13.1
rank of JAG, RDSO shall investigate the matter
and undertake inspection of the defective/under
performing machine/tool duly notifying the
vendor.If the defects/under performance are
established during the inspection, ED/TMM will
be competent to suspend the vendor from
approved list and will inform all Zonal railways
besides placing such suspension on website. The
deficiencies shall be notified to the vendor for
rectification within a stipulated time of 6 months.
If the vendor fails to rectify the deficiencies
satisfactorily, RDSO will put up the case to Small
Track Machine Committee (STMC) for delisting.
All cases of adverse performance reports and
vendors under suspension shall be reviewed by
STMC in their meeting and wherever necessary,
appropriate recommendations shall be given.If the
vendor rectifies the deficiencies/takes requisite
corrective action within stipulated period,
suspension can be revoked by EDTMM/RDSO.
b. Suspension/delisting may also be
initiated by RDSO after serving a show cause
notice seeking time bound reply and considering
the response of the firm to the notice in case of
other non- conformities as per extant vendor
approval policy of RDSO. However, all such
cases shall be put up in ensuing meeting of
Standing Committee on Small Track Machine for
their review and necessary recommendation for
continuation of suspension or de-listing etc.
matter and undertake inspection of the defective/under
performing machine/tool duly notifying the vendor.If the
defects/under performance are established during the
inspection, ED/TMM will be competent to suspend the
vendor from approved list and will inform all Zonal railways
besides placing such suspension on website. The
deficiencies shall be notified to the vendor for rectification
within a stipulated time of 6 months. If the vendor fails to
rectify the deficiencies satisfactorily, RDSO will put up the
case to Small Track Machine Committee (STMC) for
delisting. All cases of adverse performance reports and
vendors under suspension shall be reviewed by STMC in
their meeting and wherever necessary, appropriate
recommendations shall be given. If the vendor rectifies the
deficiencies/takes requisite corrective action within
stipulated period, suspension can be revoked by
EDTMM/RDSO.
b. Suspension/delisting may also be initiated by RDSO
after serving a show cause notice seeking time bound
reply and considering the response of the firm to the
notice in case of other non- conformities as per extant
vendor approval policy of RDSO. However, all such
cases shall be put up in ensuing meeting of Standing
Committee on Small Track Machines for their review
and necessary recommendation for continuation of
suspension or de-listing etc.
13.2 Deletion of vendors name from approved list
(i) The vendors can be de-listed from
approved list by competent authority in
case of one or more of the below
mentioned conditions considering the
15.2 Deletion of vendors name from approved list
(i) The vendors can be de-listed from approved list by
competent authority in case of one or more of the
below mentioned conditions considering the
seriousness & nature of deficiencies and its effects
Same as clause no 13.2
seriousness & nature of deficiencies and its
effects on quality of products:
a. Major non-compliance of the QAP.
b. Deficiencies/non-functioning of major
machinery & Plants affecting the
quality.
c. Premature withdrawal of
support/collaboration by the collaborator.
d. During course of time, if the
specification is amended and the vendor is
not
upgrading/providing the additional
requirements within a specified time
frame.
e. Any other situation leading to adverse
effect on the quality of production.
f. The entire factory or part of it is reported
closed/shut down/lockout.
g. Information provided by the firm is
found to be incorrect.
h. The vendor is black listed/or business
dealing is banned by Govt. of India or
its offices on communication by the
Board.
i. If at any time after approval, some
machinery is found deficient without
intimation to RDSO, firm’s approval
will be withdrawn immediately.
(ii) De-listing shall be communicated in
writing to the vendor. All concerned as
per distribution of the vendor list shall also
be advised.
on quality of products:
a. Major non-compliance of the QAP.
b. Deficiencies/non-functioning of major machinery &
Plants affecting the quality.
c. Premature withdrawal of support/collaboration by the
collaborator.
d. During course of time, if the specification is amended
and the vendor is not upgrading/providing the additional
requirements within a specified time
frame.
e. Any other situation leading to adverse effect on the
quality of production.
f. The entire factory or part of it is reported closed/shut
down/lockout.
g. Information provided by the firm is found to be incorrect.
h. The vendor is black listed/or business dealing is banned
by Govt. of India or its offices on communication by the
Board.
i. If at any time after approval, some machinery is found
deficient without intimation to RDSO, firm’s approval will
be withdrawn immediately.
(ii) De-listing shall be communicated in writing to the
vendor. All concerned as per distribution of the vendor list
shall also be advised.
15.3 a) Preface/lnstructions/lnformation given at the beginning of
vendor directory issued by RDSO should contain the
following:
"If due to any oversight/Typographical error /any other
reason, a vendor has been wrongly placed in Part I or
Part-II for a particular item without actually being
issued approval certificate by RDSO, then vendor
should immediately:
i) Inform RDSO about the wrong status
ii) The vendor should not accept any purchase order or
P.O. quantity more than that allowed for Part-II (as
the case may be) from Railways against the wrong
status. In case, it is found that vendor has taken more
order quantity against wrong status without having. a
valid certificate for that status (Part I/Part II)
stringent action of permanent delisting shall be taken
besides other legal action.
iii) In case of accident etc. on this account i.e. taking
orders for an item for which he is not approved or
taking more order quantity than allowed as per his
actual status the firm shall also be taken up against
relevant provisions of IPC for causing accidents
/injury to passenger etc".
b) In Approval Certificate following should be added:
Approval shall be withdrawn and firm permanently
delisted in case of following:
i) Taking purchase order or taking P.O. quantity more
than that allowed for Part-II(as the case may be )
against wrong status (i.e. Part-II / Part-I) in vendor
Vigilance note no.
9/2013 dated 01.05.2013
directly for an item due to over site / typographical
error by RDSO for which approval certificate has not
been issued by RDSO.
ii) Tampering of documents based on which
approval/upgradation/renewal.
14.0 Re-Instatement of status of vendor de-listed:
Once the firm is de-listed, the firm shall be
considered for re-instatement treating it as fresh
approval and the procedures as followed for
fresh approval shall be applicable after satisfying
following:
a) The firm applies after complying the
deficiencies.
b) The request for re-instatement shall be
considered only after a period of one year
from the date of de-listing.
c) The case shall be considered as for fresh
approval and the procedures as followed
for fresh approval shall be applicable.
d) After being satisfied with the above
criteria, the case shall be put up to
ensuing meeting of Standing Committee
on Small Track Machine for its
consideration and recommendation.
16.0 Re-Instatement of status of vendor de-listed:
Once the firm is de-listed, the firm shall be considered for
re-instatement treating it as fresh approval and the
procedures as followed for fresh approval shall be applicable
after satisfying following:
a) The firm applies after complying the deficiencies.
b) The request for re-instatement shall be considered
only after a period of one year from the date of de-
listing.
c) The case shall be considered as for fresh approval
and the procedures as followed for fresh approval
shall be applicable.
d) After being satisfied with the above criteria, the case
shall be put up to ensuing meeting of Standing
Committee on Small Track Machine for its
consideration and recommendation.
Same as clause no 14.0
15.0 Up-gradation of vendor’s status from Part-II
to Part-I:
(i) The vendors who are in Part II shall be
upgraded to Part-I list only after compliance of all
the following conditions-
a) The vendor has applied in writing to
RDSO for up-gradation from Part-II to
Part-I.
b) The vendor shall have supplied minimum
17.0 Up-gradation of vendor’s status from Part-II to Part-I:
(i) The vendors who are in Part II shall be upgraded to
Part-I list only after compliance of all the following
conditions-
a) The vendor has applied in writing to RDSO for up-
gradation from Part-II to Part-I.
b) The vendor shall have supplied minimum specified
quantity as laid down. For the items already
approved, these quantities are specified by TMM
Same as clause no 15.0
specified quantity as laid down. For the
items already approved, these quantities
are specified by TMM Dte.. Small Track
Machine Committee (STMC) shall review
these quantities from time to time and
submit its recommendations for changes,
if any.
c) A minimum period of 12 months has
elapsed from the date of first successful
supply to zonal railway before
consideration by STMC committee.
d) No adverse report attributable to
unsatisfactory quality/workmanship or
performance of the product has been
received from the Railways and assessed
prima facie substantiated by RDSO till
time of consideration for up-gradation or
such report, if any, has been disposed off
after satisfactory compliance.
e) Approval of firm is still valid.
After being satisfied with the above criteria, the
case shall be put up to ensuing
meeting of STMC for its deliberations and
recommendations to Railway Board.
Dte.. Small Track Machines Committee (STMC)
shall review these quantities from time to time and
submit its recommendations for changes, if any.
c) A minimum period of 12 months has elapsed from
the date of first successful supply to zonal railway
before consideration by STMC committee.
d) No adverse report attributable to unsatisfactory
quality/workmanship or performance of the product
has been received from the Railways and assessed
prima facie substantiated by RDSO till time of
consideration for up-gradation or such report, if any,
has been disposed off after satisfactory compliance.
Performance Report from minimum two zonal
railways will be required for this purpose. However if
the qualifying quantity as per Para no. 17.0/(i)/b is
one number, then the performance Report from only
one zonal railways will be sufficient for this purpose.
e) Approval of firm is still valid.
f)
After being satisfied with the above criteria, the case shall
be put up to ensuing meeting of STMC for its deliberations
and recommendations to Railway Board.
16.0 Change in name of the vendor: 18.0 Change in name of the vendor: Same as clause no.16.0
New If a firm intends to change name of the firm, Inspection of
the machine will be stopped immediately till following -
16.1
If a firm intends to change name of the firm, it
shall make available an undertaking by the new
firm for liability of the old firm, resolution by
Board of Directors, partnership deed etc. which
will be scrutinized by RDSO / Lucknow. In this
connection inspection of the firm may also be
carried out by RDSO/Lucknow, if considered
necessary.
18.1 If a firm intends to change name of the firm, it shall make
available an undertaking by the new firm for liability of the
old firm, resolution by Board of Directors, partnership deed
etc. which will be scrutinized by RDSO / Lucknow. In this
connection inspection of the firm may also be carried out by
RDSO/Lucknow, if considered necessary.
Same as clause no 16.1
16.2 If change of name is done as a result of
bifurcation of the existing works premises, in
addition to checking of documents , re-
assessment will also be carried out by RDSO
official before effecting the change in name of
firm.
18.2 If change of name is done as a result of bifurcation of the
existing works premises, in addition to checking of
documents , re-assessment will also be carried out by RDSO
official before effecting the change in name of firm.
Same as clause no 16.2
16.3
The same policy as mentioned above shall also
be applicable in case of the change in name of
the production co-units of the approved vendor,
the approved vendor shall be responsible for
necessary formalities and submission of for new
location related documents.
18.3 The same policy as mentioned above shall also be applicable
in case of the change in name of the production co-units of
the approved vendor, the approved vendor shall be
responsible for necessary formalities and submission of for
new location related documents.
Same as clause no 16.3
16.4
Competent authority shall grant approval for
change of name and necessary change of name
shall be advised to all copy holders of vendor’s
list.
18.4 Competent authority shall grant approval for change of
name and necessary change of name shall be advised to all
copy holders of vendor’s list.
Same as clause no 16.4
17.0
Change of location/address of works/firm:
19.0 Change of location/address of works/firm:
Same as clause no 17.0
17.1
On receipt of request from the vendor for
change of work-site, the RDSO official shall
verify that.
19.1 On receipt of request from the vendor for change of work-
site, RDSO official shall verify that-
Same as clause no 17.1
17.2
The office of Works, Plant, establishment etc.
has been totally shifted.
19.2 The office of Works, Plant, establishment etc. has been
totally shifted.
Same as clause no 17.2
Note:
Vendors on approved list will inform Executive Director, Track Machine & Monitoring Directorate of RDSO regarding changes in
correspondence address, telephone numbers, Fax Nos. and E- mail at the earliest.
********************************************
17.3
The Machinery & Plants have been totally
shifted, set up and commissioned.
19.3 The Machinery & Plants have been totally shifted, set up
and commissioned.
Same as clause no 17.3
17.4
The testing and laboratory facilities have been
shifted totally setup and commissioned.
19.4 The testing and laboratory facilities have been shifted totally
setup and commissioned.
Same as clause no 17.4
17.5
The certificate from Small Scale Industries /
registrar of companies or equivalent authority is
available for new location of works.
19.5 The certificate from Small Scale Industries / registrar of
companies or equivalent authority is available for new
location of works.
Same as clause no 17.5
17.6
The name of the firm is same. 19.6 The name of the firm is same.
Same as clause no 17.6
17.7
Certificate for power connection from State
Electricity Board is available.
18.7 Certificate for power connection from State Electricity
Board is available.
Same as clause no 17.7
20.0
NEW Empowerment of EDTM- ED/TM is empowered to consider any deviations /
discrepancies in procedure laid down above on case to case
basis and merit of the case by giving specific remarks.
However, the deviations so considered shall not violate the
vendor approval procedure. The items which are not covered
in this document ED/TM may decide the procedure to be
followed giving specific remarks.
To address any
unforeseen circumstances
which may arise as
special case.