expansion of an existing power system - a study

100
Scholars' Mine Scholars' Mine Masters Theses Student Theses and Dissertations Spring 1989 Expansion of an existing power system - a study Expansion of an existing power system - a study Suresh Arunachalam Follow this and additional works at: https://scholarsmine.mst.edu/masters_theses Part of the Electrical and Computer Engineering Commons Department: Department: Recommended Citation Recommended Citation Arunachalam, Suresh, "Expansion of an existing power system - a study" (1989). Masters Theses. 4627. https://scholarsmine.mst.edu/masters_theses/4627 This thesis is brought to you by Scholars' Mine, a service of the Missouri S&T Library and Learning Resources. This work is protected by U. S. Copyright Law. Unauthorized use including reproduction for redistribution requires the permission of the copyright holder. For more information, please contact [email protected].

Upload: others

Post on 18-Apr-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Expansion of an existing power system - a study

Scholars' Mine Scholars' Mine

Masters Theses Student Theses and Dissertations

Spring 1989

Expansion of an existing power system - a study Expansion of an existing power system - a study

Suresh Arunachalam

Follow this and additional works at: https://scholarsmine.mst.edu/masters_theses

Part of the Electrical and Computer Engineering Commons

Department: Department:

Recommended Citation Recommended Citation Arunachalam, Suresh, "Expansion of an existing power system - a study" (1989). Masters Theses. 4627. https://scholarsmine.mst.edu/masters_theses/4627

This thesis is brought to you by Scholars' Mine, a service of the Missouri S&T Library and Learning Resources. This work is protected by U. S. Copyright Law. Unauthorized use including reproduction for redistribution requires the permission of the copyright holder. For more information, please contact [email protected].

Page 2: Expansion of an existing power system - a study

EXPANSION OF AN EXISTING POWER SYSTEM - A STUDY

BY

SURESH ARUNACHALAM, 1959 -

A THESIS

Presented to the Faculty of the Graduate School of the

UNIVERSITY OF MISSOURI - ROLLA

In Partial Fulfillment of the Requirements for the Degree

MASTER OF SCIENCE IN ELECTRICAL ENGINEERING

Earl F. Richards ( Advisor)

1989

Approved by

T5810Copy 199 pages

Duke E. Tweed

Darrow F. Dawson

1;L"~:y;£George W. Zobrist

Page 3: Expansion of an existing power system - a study

11

ABSTRACT

An existing paper mill is being expanded to increase its installed capacity.

Concurrent expansions will be increasing the electrical demand by 40 - 50 MVA.

The expansion also includes the addition of DC drives. The existing system has to

be used effectively while additional equipment may be added to cater the load

increase.

Load flow study with various single line diagram configurations has been

carried out to find the required solution. A harmonic analysis was also carried out

on the suggested new system to install the required filters and capacitor banks.

Page 4: Expansion of an existing power system - a study

ill

ACKJ\O\VLEDG:\1EN1-'S

The author is indebted to Dr. Earl F. Richards of the Electrical Engineering

Department for his guidance, encouragement and support throughout the course of

stay in UMR and during the course of this investigation.

The author also wishes to thank Dr. Duke Tweed of Union Electric Company,

S1. Lou is, Dr. George Zobrist of Computer Science Department and Dr. Darrow

Dawson for agreeing to be in the committee and for putting this thesis together.

The author is greateful to Simons Eastern Consultants Inc., Atlanta, Georgia

and Champion International Corporation, Bucksport, Maine for their timely

assistance.

My special thanks extend to Rakesh, Jay, and my wife Raji who extended

unlimited moral support at aft times.

Page 5: Expansion of an existing power system - a study

IV

TABLE OF CON1'E0:TS

Page

ABSTRACT ii

ACKNOWLEDGMENTS iii

LIST OF ILLUSTRATIONS vii

LIST OF TABLES viii

I. INTRODUCTION .

II. STAGE-WISE MILL LOAD GROWTH 3

A. EXISTING MILL OPERATING LOADS 3

B. LOAD GROWTH ASSOCIATED WITH PLANT EXPANSIONS 3

C. NO.4 PAPER MACHINE LOADS 4

D. NEW NO.3 TURBINE GENERATOR 12

E. ESTIMATED MVAR FLO\tV 12

III. LOAD FLOW-STUDY 13

A. OBJECTIVES 13

B. ASSLJMPTIONS FOR THE LOAD FLOW STUDY 14

1. System Impedance Data 14

2. 13.8 kV And 7.2 kV System Configurations 14

3. Retrofit Of Cooling Equipment Of Transformer B 16

4. Sharing Of Loads Between Transformers A And B 16

5. No.2 Generator Reactive Capability Curve 17

6. LJtility Tie Transformer Taps 17

C. DETAILED ANALYSIS OF LOAD FLOW CASES 17

1. Case No.1, Stage 3 Loads 17

2. Case No.2, Stage 3 Loads 21

3. Case No.3, Stage 3 Loads 23

Page 6: Expansion of an existing power system - a study

v

4. Case No.4, Stage 3 Loads 24

5. Case No.5, Stage 3 Loads 25

6. Case No.6, Stage 3 Loads 27

7. Case No.7, Stage 3 Loads 31

8. Case No.8, Stage 3 Loads 35

9. Case No.9, Stage 3 Loads 41

1G.Case No. 11, Existing Loads 41

11. Case No. 12, Stage 1 Loads 41

12.Case No. 14, Stage 2 Loads 41

13. Case No. 15, Stage 3 Loads 42

D. GENERAL CONCLUSIONS DRAWN FROM THE LOAD FLOWCALCULATIONS 44

IV. HARMONIC ANALYSIS STUDY 48

A. INTRODUCTION 48

B. HARMONICS DUE TO RECTIFIERS LOADS AND RESONANCES 49

C. SIX-PULSE RECTIFIERS 50

D. FILTER RE/\CTORS 51

E. CAPACITOR RATINGS 55

V. SYSTEM MODELING FOR HARMONIC ANALYSIS STUDY 57

A. IMPEDANCE DIAGRAM 57

B. SVJITCHI~~G CONDITIONS 59

C. DETAILS OF THE DIGITAL COMPUTER HARMONIC STUDY ... 59

1. Part-I 59

2. Part-II 60

VI. DISCUSSION OF THE STUDY RESULTS 62

A. FREQUENCY SCAN ' 62

B. TOLERANCES ON CAPACITORS AND REACTORS 67

C. TOTAL HARMONIC DISTORTION 67

Page 7: Expansion of an existing power system - a study

VI

D. HARMONIC CURRENT FLOW 69

E. CONCLUSIONS 79

VII. CAPACITOR BANK CONTROL 80

A. INTRODUCTION 80

B. CONTROL STRATEGY 80

C. INTERLOCKING REQUIREMENTS FOR 13.8 KV CIRCUITBREAKERS 82

VIII. RESULTS 84

A. FINDINGS 84

B. RECOMMENDATIONS 87

BIBLIOGRAPHY 89

VITA 90

Page 8: Expansion of an existing power system - a study

Figure

2

3

4

5

6

7

8

9

LIST OF ILLUSTRATIOl\:S

Single Line Diagram Without New Utility Tie Transformer .

Single Line Diagram With New Utility Transformer .

Load Flow Study - Impedance Data .

Load Flow Diagram - Base Case I .

Location of Tie Transformer G And Filters .

Equivalent Circuit for Harmonic Analysis .

Impedance Diagram with Equal 5th and 7th Filters .

Irnpedance Diagram for Unequai 5th and 7th Filters .

Capacitor Bank Breaker Control Logic Diagram .

V11

Page

10

11

15

20

47

53

58

78

81

Page 9: Expansion of an existing power system - a study

\'111

LIs~r OI~ TABLES

Table Page

LOAD FLOW STUDY STAGEWISE LOAD GROWTH ESTIMATE NO.1 5

II LOAD FLOW STUDY STAGEWISE LOAD GROWTH ESTIMATE NO.2 6

III LOAD FLOW STUDY STAGEWISE LOAD GROWTH ESTIMATE NO.3 7

IV LOA,D FLOW STUDY STAGEWISE LOAD GROWTH ESTIMATE NO.4 8

V LOAD FLOW STUDY SUMMARY OF LOAD GROWTH 9

VI ESTIMATED POWER FACTORS 12

VII

VII I

BASE CASE 1 CHANGE CASES 1A TO 1D

BASE CASE 2 CHANGE CASES 2A TO 2C

19

22

IX BASE CASE 3 CHANGE CASES 3A AND 3B 24

x

XI

BASE CASE 4 CHANGE CASES 4A TO 4C

BASE CASE 5 CHANGE CASES 5A TO 5C

27

29

XII BASE CASE 6 CHANGE CASES 6A AND 6B 30

XIII BASE CASE 7 CHANGE CASES 7A TO 7D 32

XIV PEf=<CENTAGE TRANSFORt\1ER LOADINGS FOR NORMAL AND UPSETCONDITIONS NO.1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34

XV BASE CASE 8 CHANGE CASES 8A TO BE 37

Xv"! BASE CJ,SE 8F 38

X\/ll PERCEt-~TAGE TRA~~SFORMER LOADING NORMAL AND UPSETCONDITIONS NO.2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 39

XVIII BASE CASE 11,12 AND 14 43

XIX BASE C.l\SE 15 .... ~ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 45

XX HARMONIC CURRENT-IN STATIC CONVERTER INPUT PER UNIT OFFUNDAMENTAL CURRENT 52

XXI SWITCHING CONDITONS WITHOUT NEW UTILITY TRANSFORMER .. 60

XXII

XXIII

SUMMARY OF FREQUENCY SCAN CASES NO.1

SUMMARY OF FREQUENCY SCAN CASES NO.2

63

64

Page 10: Expansion of an existing power system - a study

IX

XXIV FREQUENCY SCAN CASES RESONANT HARMONIC FREQUENCIES INMULTIPLES OF FUNDAMENTAL RHO FACTORS NO.1. . . . . . . . . . . 65

XXV FREQUENCY SCAN CASES RESONANT HARMONIC FREQUENCIES INMULTIPLES OF FUNDAMENTAL RHO FACTORS NO.2. . . . . . . . . . . 66

XXVI MAXIMUM HARMONIC CURRENT DISTORTION IN PERCENTAGE OFFUNDAMENTAL 69

XXVII DESCRIPTION OF STUDY CASES FOR TWO EQUAL 5TH AND 7THHARMONIC FILTERS 71

XXVIII SUMMARY OF CAPACITOR BANK LOADINGS EQUAL 5TH AND 7THHARMONIC FILTERS NO.1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72

XXIX SUMMARY OF CAPACITOR BANK LOADINGS EQUAL 5TH AND 7THHARMONIC FILTERS NO.2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73

XXX DESCRIPTION OF STUDY CASES FOR TWO UNEQUAL 5TH AND 7THHARMONIC FILTERS 75

XXXI SUMMARY OF CAPACITOR BANK LOADINGS UNEQUAL 5TH AND 7THHARMONIC FILTERS NO.1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76

XXXII SUMMARY OF CAPACITOR BANK LOADINGS UNEQUAL 5TH AND 7THHARMONIC FILTERS NO.2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77

Page 11: Expansion of an existing power system - a study

I. Il'TROI)UC~rION

A load flow and harmonic analysis study of the electrical distribution system

has been conducted at Champion International Corporation, Bucksport, Maine.

Concurrent expansions in this paper manufacturing plant are expected to

increase the demand on the 13.8 kV system from 82 to 124 MVA. The demand on

the 7.2 kV buses (20 rviVA) is not expected to change. The purpose of the study is

to determine the electrical system's ability to reliably serve these loads.

Load flow calculations predict the voltage level on each major bus under

normal load flow conditions and the initial voltage drop on each bus if a major

source is suddenly removed from service. The calculations also show the flows of

megawatts and megavars throughout the system.

This study addresses load flow situations on the 7.2 and 13.8 kV buses when

the total electrical demand will be 135 MVA. Additional load flow situations are

included for a new utility tie transformer, new capacitor banks, and various bus tie

arrangements. Also included are load flow situations for three incremental

increases in electrical demand. Load flow calculations on 480 and 2400 volt buses

are excluded from the scope of this study.

Resonant conditions can occur when capacitor banks are used in a

distribution system having dc drives or rectifier loads. Resonance by the rectifier

generated harmonics can overload the capacitors and result in nuisance fuse

operation. A harrnonic analysis study V'/as conducted to ascertain these harmonic

resonant conditions and properly size the filter reactors and capacitor banks.

A harmonic analysis study models the distribution system on a digital

computer, based on the system impedance, rectifier loads and calcu lated

harmonic currents injected on the rectifier buses. The system's responses to

Page 12: Expansion of an existing power system - a study

2

harmonics from fundamental to 30th are calculated to determine the resonance

conditions. Harmonic current flow analyses in the various elements of the

distribution system, capacitor banks and filter reactors are then made. A number of

switching conditions representative of the plant's normal operation and also

operating conditions under a source outage are considered. The study was

conducted with equal 5th and 7th harmonic filter banks, with one 5th harmonic

filter, and with unequal 5th and 7th harmonic filters to ascertain the optimum

loading on the filter banks and to limit the total harmonic distortion on the 115 kV

and 13.8 kV buses.

Page 13: Expansion of an existing power system - a study

3

II. STAGE-\VISE l\1ILL, LOAD GROWTI-I

A. EXISTING MILL OPERATING LOADS

The existing mill operating loads have been estimated ·using meter readings

and the utility company power bills. The data used represent the mill's typical

operating conditions and reflect the maximum operating loads that can occur in

the existing distribution system.

8. LOAD GROWTH ASSOCIATED WITH PLANT EXPANSIONS

The loads associated with projects currently in progress are estimated in

three stages:

Stage 1:

-- TMP and groundwood modifications

-- New No.3 turbine generator

-- No.8 supercalender winder

Stage 2:

-- No. 6A and 68 supercalenders

-- Supercalender pulper

-- No.6 supercaiender winder

Stage 3:

Page 14: Expansion of an existing power system - a study

4

-- NO.4 paper machine rebuild

-- Refiner motors added to bus D (10,000 HP)

Table I through Table IV show the stage-wise load growth of plant loads.

Table V is a summary of this load development.

All of the load growth is taking place on systems served by the 13.8 kV buses.

The existing plant load on the 13.8 kV buses is approximately 82 MVA. The stage

wise cumulative increases are approximately as follows:

Stage 1: 17 MVA 21% increase over existing load

Stage 2: 23 MVA 28 % jncrease over existing load

Stage 3: 42 MVA 51 % increase over existing load

C. NO.4 PAPER MACHINE LOADS

The following configurations for No. 4 paper machine loads have been

considered:

-- If a new 115-13.8 kV utility transformer is not installed, the No.4 paper

rnachine loads 'vv;li be divided on 13.8 kV buses Band G. The total No.4 paper

machine load cannot be shifted to bus G without overloading transformer C. Figure

1 shows the load distribution from the 13.8 kV buses.

-- If new 115-13.8 k\/ transformer G is installed, the total No.4 paper n-13chine

load can be connected to bus G. Breaker G on bus B will become a spare. Figure

2 shows this load distribution.

Page 15: Expansion of an existing power system - a study

Ta

ble

I.L

OA

DF

LO

WS

TU

DY

ST

A.G

EW

ISE

LO

AD

GR

OW

TH

ES

TIM

AT

EN

O.1

Bu

sN

o.

Bre

ake

rE

xist

ing

loa

ds

Sta

ge

1lo

ad

sS

tag

e2

loa

ds

Sta

ge

3lo

ad

Vo

lta

ge

No

.M

Wf\l

lVA

RP.

F.M

WM

VA

Rrv

1WM

VA

RM

WM

VA

RP

.F.

DX

an

d15

.00

8.55

0.87

18.2

810

.41

18

.28

10.4

12

5.5

81

4.6

50.

87

13

.8kV

y

CT

1.20

1.15

0.72

2.21

2.18

2.21

2.18

2.21

2.1

80.

71

13.8

kVS

0.6

50.

660.

700.

650.

660.

650.

660.

650

.66

0.7

0

R2

.00

2.0

40.

702.

002.

042.

002.

042

.00

2.0

40

.70

Q5

.30

4.67

0.75

5.30

4.67

5.30

4.67

5.30

4.6

70

.75

P4

.2-0

.37

-0.9

95.

100.

265.

100.

265

.10

0.2

60

.99

8

To

tal

1.7

51.

780.

701.

751.

781.

751.

781

.75

1.7

80.

7

Bu

sC

15

.10

9.93

0.84

17.0

111

.59

17.0

11

1.5

917

.01

11

.59

0.8

3

VI

Page 16: Expansion of an existing power system - a study

Ta

ble

II.L

OA

DF

LOW

ST

UD

YS

TA

GE

WIS

EL

OA

DG

RO

WT

HE

ST

IMA

TE

NO

.2

Bu

sN

o.

Bre

ake

rE

xist

ing

loa

ds

Sta

ge

1lo

ad

sS

tag

e2

loa

ds

Sta

ge

3lo

ad

s

Vo

lta

ge

No

.M

WM

VA

RP.

F.M

WM

VA

RM

WM

VA

RM

WM

VA

RP.

F.

AB

5.0

4.1

50.

775.

04

.15

5.0

4.1

54

.05

3.4

90.

76

13

.8kV

C5.

84

.67

0.78

6.84

5.5

96.

845

.59

6.84

5.5

90

.77

D6.

25

.10

0.77

8.4

25.

718.

425.

718

.42

5.71

0.83

To

tal

17

.01

3.9

20.

772

0.2

61

5.4

520

.26

15

.45

19.3

11

4.7

90

.79

Bu

sA

BE

4.2

01

.66

0.93

4.2

01.

664

.20

1.66

4.2

01

.66

0.9

3

13

.8kV

F5

.48

3.31

0.86

8.6

85.

718.

865.

718

.86

5.71

0.8

4

1.17

1.03

0.75

1.17

1.03

1.17

1.03

1.17

1.0

30

.75

L0

.35

0.26

0.8

00

.35

0.2

60

.35

0.2

60

.35

0.2

60

.80

0\

Page 17: Expansion of an existing power system - a study

Ta

ble

III.

LO

AD

FL

OW

ST

UD

YS

TA

GE

WIS

EL

OA

DG

RO

WT

HE

ST

IMA

TE

NO

.3

Bu

sN

o.

Bre

ake

rE

xist

ing

loa

ds

Sta

ge

1lo

ad

sS

tag

e2

loa

ds

Sta

ge

3lo

ad

s

Vo

lta

ge

No.

MW

MV

AR

P.F.

MW

MV

AR

MW

MV

AR

MW

MV

AR

P.F

.

BK

2.50

2.19

0.75

4.71

4.14

4.71

4.14

4.71

4.1

40.

75

13

.8kV

To

tal

19.1

112

.80

0.83

Bu

sB

G7.

304.

000.

877.

544.

188.

194.

567.

344

.68

0.84

To

tal

21.0

012

.45

0.86

26.6

516

.98

27.3

017

.36

26.4

517

.48

0.8

4

Bu

sG

\

Ne

wS

hif

ted

7.34

4.6

80.

84

Bu

sG

Lo

ad

-.)

Page 18: Expansion of an existing power system - a study

Ta

ble

IV.

LO

AD

FL

OW

ST

UD

YS

TA

GE

WIS

EL

OA

DG

RO

WT

HE

ST

IMA

TE

NO

.4

Bu

sN

o.

Bre

ake

rE

xist

ing

loa

ds

Sta

ge

1lo

ad

sS

tag

e2

loa

ds

Sta

ge

3lo

ad

s

Vo

lta

ge

No

.M

Wfv1

\1A

RP.

F.M

WM

VA

RM

WM

VA

RM

WM

VA

RP

.F.

Ne

wS

hif

ted

1.33

1.3

50

.70

Bu

sG

Lo

ad

2.8

02

.86

9.94

10

.14

0.70

1.0

51.

071

.05

1.07

0.7

0

To

tal

3.8

53

.93

19

.66

17

.24

0.7

5

Bu

sG

wit

hn

ew

tra

nsfo

rme

r

wit

ho

ut

ne

wtr

an

sfo

rme

r3

.85

3.9

31

2.3

21

2.5

60

.70

E&

FA

,Z1

8.0

0-8

.72

-0.9

18

.00

-8.7

21

8.0

0-8

.72

18

.00

-8.7

2-0

.9

7.2

kV

00

Page 19: Expansion of an existing power system - a study

Ta

ble

V.

LO

AD

FL

OW

ST

UD

YS

Urv

1M

AR

YO

FL

OA

DG

RO

WT

H

Bu

sN

o.E

xist

ing

Lo

ad

sS

tag

e1

Lo

ad

sS

tag

e2

Lo

ad

sS

tag

e3

Lo

ad

s

wit

hn

ew

xfr

mr

wit

ho

ut

ne

wxfr

mr

MW

MV

AR

MW

MV

AR

MW

MV

AR

MW

MV

AR

MW

MV

AR

015

.00

8.55

18.2

810

.41

18.2

810

.41

25.5

814

.65

25.5

814

.65

C15

.10

9.93

17.0

111

.59

17.0

111

.59

17.0

111

.59

17.0

111

.59

A17

.00

13.9

220

.26

15.4

520

.26

15.4

519

.31

14.7

919

.31

14.7

9

B21

.00

12.4

526

.65

16.9

827

.30

17.3

619

.11

12.8

026

.45

17.4

8

G--

----

--3.

853.

4319

.66

17.2

412

.32

12.5

6

Ea

nd

F18

-8.7

218

-8.7

218

-8.7

218

-8.7

218

-8.7

2

To

tal

86.1

036

.13

100.

2045

.71

104.

7050

.02

118.

6762

.35

118.

676

2.3

5

Pla

nt

MV

A=

93

.37

MV

A=

11

0.1

3M

VA

=1

16

.03

MV

A=

134.

05M

VA

=1

34

.05

Lo

ad

PF

:=.~;

0.92

2P

F=

0.9

10

PF

=0.

902

PF

=0.

885

PF

=0.

885

\0

Page 20: Expansion of an existing power system - a study

>:FR

~,,,iR

EIF

12

/16

/22

.4M

VA

l)A

/FA

/FO

A

Z 2000

A

\r

..:;;.\JJ

....JA

rY":

.f't

\\'O

OD

GR

IND

ER

S

~ ~

7.2K

V_

_--..

L_

_-+_

_""

""'-

-_

~l

.....-E

XIS

TIN

GLO

AD

(MV

A)

~--

-rl

lJh

LLO

AD

(I,iV

A)

"15

KV

BU

SlA

500A

115K

V

XFR~v1R

G3

..

E5

4/7

2/)

~9

Of..I

VAl-;:

;~

~:;

2406

3KV

A0

O.8

P.F

IG

3C

2f'\

0H

8660

0KV

AU

O.8

5P.F

20

00

AI'

13

.8K

V , BUS

8

"A

vJA

..,

ArY

":'r

'\

XFR

MR

82

0!2

6.6

7/

37

:7M

VA

OA

/FA

/FO

A

\)..

.~

Arv

·y',

XFP,

.,4R

/1

2/1

622

'.r.

~1'1

AO

A/F

A/F

OA

BU

SA

TIE

TOTRANSFOR~w1ER

NE

'NG

BU

S

N.O

O'III

IIIBI

C?D

IEIFIC

f----

tYY

'Y"\

_--

--

N~.4

~AP~R

~let

jlO!'5

bHM!

JI

MA

CH

INE

AN

D'

CA

PA

CIT

OR

B.~NKS

[----1

PU

LPM

ILL

BO

ILE

RH

OU

SE

EQ

PT.

1759

EOPT

.[[

ill.

[[ill

29

.40

21.9

731

702

4.3

2'

NO

.5P

AP

ER

MA

CH

INE

DR

IVE

S

~ ~

';~~

XF

RM

RC

20

/29

.87

/3

7."

,3U

\/A

'O

A!F

A/F

OA

',5V

V8U

S2A

BIN

GH

AMORPI~JGTON

SE

AR

SP

OR

TO

RR

ING

TON

TOU

TILI

TYK

?Q

".._

2I

~~:~~I~

'-J

r1

6.@

j

W 2000

AV

i0

20

00

A

N.O1-

XIY

CA

PA

CIT

OR

BA

NK

SA

.ND

RE

FIN

ER

S

~ ~

l;t

r<"Y

'.

XF

RM

R0

20

/29

.87

/37

.33M

/VA

OA

/FA

FOA

I I L. Fig

ure

1.S

ing

leL

ine

Dia

gra

mW

ith

ou

tN

ew

Uti

lity

Tie

Tra

nsfo

rme

r=

Page 21: Expansion of an existing power system - a study

r

WO

OD

GR

IND

ER

S---,

20

.00

18

.00

-8.7

2

7.2K

V_

._

..1

.-

1--+

-1---

115~.\/

8U

S1A

20

.30I~-

~v'1

VA17

.01

-~l'N

11

.08

--.M

'IAR

60

0A

11

5K

V

XFR

MR

G3

\~---~~

54

/72

/J

\E

.J90

MV

A'-"

"-'

<;-..

J...,

1r

TA

'"""

"~~

2406

3KV

A6

I~~

R~I~

E,F

O.8P.F

2/H.~!;\

G2f'\

G3

OA

!FA

!rO

A

HU

S~8650

?~V,\~

~OOO

A~

~OOOA

2000

AI

13.8

KY

.,-

'" BU

SB

~ A

80

lLE

RH

OU

SE

EQ

PT.

XFR

MR

B2

0/2

6.6

7/

37

:7M

VA

OA

(FA

/FO

A

~ A

XF

RM

R!

121

622

(4M

'lAO

A/F

A/F

OA

BU

SA

20

00

A\

-r-=

:::::1

-I

I

~

BIN

GH

AM

OR

RIN

GTO

NS

EA

RS

PO

RT

OR

RIN

GTO

N

NEV

IG

BU

S 13~

~IIIIIIN.O

OII

IIII

IBIC

!DIE

IFIG

II!

!t

!!

jI~OH

MjI

NO

.4P

AP

ER

M/c

MA

CH

INE

AN

DC

AP

AC

ITO

RB

AN

KS

!!2

5,8

4P

ULP

MIL

L1

9,6

6E

OP

T1

7.2

4'

\24

.32

1~~

:7~

~XF

RM

RG

NO

.5P

AP

ER

MA

CH

INE

DR

IVE

S

20

.30

17

.01

,1

.08

115~<V

8US

2A "~~

XFRIv1f~

C2

0/2

9.8

7/

37',,

:53M

VA

OA

/FA

/FO

A

y

CA

PA

CIT

OR

BA

NK

SAr~D

REflr~ERS

29

.47

25

.58

14

.55xJ

~1

XFR

MR

02

0/2

9.8

7/

3T.3

3MV

AO

A/F

A!F

OA

Fig

ure

2.S

ing

leL

ine

Dia

gra

mW

ith

Ne

wU

tilit

yT

ran

sfo

rme

r

Page 22: Expansion of an existing power system - a study

12

D. NEW NO.3 TURBINE GENERATOR

The plant has contracted to supply 27.25 MW of power to the utility company

upon commissioning of No.3 generator. This commitment is shown as a load at

0.85 power factor connected to the 115 kV bus in the load flow diagrams.

E. ESTIMATED MVAR FLOW

The power factors assu med for the various type of loads for calcu lations of

Mvar load flows are shown in Table VI. These are the actual power factors, as

calculated from the operating conditions.

Table VI. ESTIMATED POWER FACTORS

Type of Load

Synchronous Motors

5000 HP Refiner Motors

Medium Voltage Motors Operating

at 0.8 or Lower Load Factor

480 Volt Motor Loads

D.C. Drives

Power Factor

0.9 lead

0.87 lag

0.80 lag

0.75 lag

0.70 lag

Page 23: Expansion of an existing power system - a study

13

III. LOAD FtJO\V STUDY

A. OBJECTIVES

The purpose of the load flow study is to determine active and reactive power

flows and voltages at various 13.8 kV and 7.2 kV buses. The following system

configurations were studied:

-- The existing distribution system.

-- The system at the completion of Stage 1 load growth.

-- The system at the completion of Stage 2 load growth.

-- The system at the completion of Stage 3 load growth.

-- Various system configurations and operating conditions after stage 3 load

growth.

The load flow program calculates the voltages under normal load flow

conditions and the initial voltage drop upon loss of a source.

The initial voltage drop should be limited to 10% of rated bus voltage to

ensure continuous process operations during an upset condition like sudden

outage of a source.

The active and reactive power flows demonstrate the system capabilities and

Iirnitations in serving the plant loads. Load flow calculations can be used to

determine the changes necessary in a system to support increased load growth. A

load flow analysis will also be helpful in planning power generation strategies,

calculating system losses, and selecting the optimum taps on transformers.

Page 24: Expansion of an existing power system - a study

14

The normal load flow situation should not overload any of the system

components, such as transformers, circuit breakers or feeder cables. Upon an

upset condition, it should be possible to revert to normal operations without

excessive shutdowns and load shedding.

B. ASSUMPTIONS FOR THE LOAD FLOW STUDY

1. System Impedance Data. The system impedance data has been taken

from the available short-circuit study and the plant single line diagrams. The three

phase short circuit level and X/R ratio at the 115 kV utility system were obtained

from the utility company. Figure 3 shows the system impedance data used for the

load flow study.

2. 13.8 kV And 7.2 kV S~tem Configurations. The operating configurations of

the 13.8 and 7.2 kV systems are the same as the existing plant operating practices.

In each of these configurations it is assumed that the short-circuit levels at 13.8 kV

and 7.2 kV buses will be within the rated short circuit capabilities of the circuit

breakers installed on these buses.

Two basic configurations of the 13.8 kV distribution system have been studied

for Stage 3 load growth:

-- A new 115-13.8 kV, 20/37.33 MVA utility tie transformer is connected to bus

G. This transformer will be normally operating in parallel with existing transformer

C.

Page 25: Expansion of an existing power system - a study

55

0',

4-1

/C/P

HA

SE

500M

CM

CU

.S

PA

CE

DO~~E

DIA

.IN

TRAY

EQ

UIV

.TO

.00

74

.02

29

.04

03

---

-P

.UR

ES

ISTA

NC

E.6

44

6----

P.U

RE

AC

TAN

CE

t~OTE:

ALL

l~v1PEDANCE

DAT

,t\AR

EO

N10

0MV

AB

AS

E

UTI

LITY

.3P

HA

SE

__

SH

OR

TCIR~/U~

~c9

.98

.05

72

1755

MV

A.

.92

59

11

5K

VA

rv:r

.

.00

57

.05

7

37

0',

3-1

/e/P

HA

SE

500M

CM

AI.

SP

AC

ED

ON

ED

IA.

INTR

AYE

QU

IV.

TO.0

02

78

.00

47

2

~8.0179

.00

46d:

G3

.37

56

.14

81

24

06

3K

VA

O.8

P.F

42

0',

2-1

Ie/P

HA

SE

500~

~C~,

1S

PA

CE

ON

ED

IA.

INTR

AY

AI.

EQ

UI.

TO.0

04

73

.00

68

3

GA

/IN'~6600KVA

I\/

IE

AN

DF

o0

.85

P.F

N.e

/\

nN

.O.0

05

3.2

62

5

43

0',

3-1

/eP

HA

SE

,500

MC

MAI

.E

QU

IV.

TO.0

03

23

.00

52

9

o

N.O

.01

89

--:1

0.0

18

9~C

JxG

. 01

69

dto~

.39

65

I.3

47

1I

I.3

47

1I

.64

46

Fig

ure

3.L

oa

dF

low

Stu

dy

-Im

pe

da

nce

Da

taV

l

Page 26: Expansion of an existing power system - a study

16

-- A new 115-13.8 kV, 20/37.33 MVA transformer is not installed.

The existing operating practices for the 13.8 kV and 7.2 kV distribution

systems shown in Figure 1 are as follows:

-- Only one of the transformers E or F is connected to supply the 7.2 kV loads

on buses E and F.

-- Transformers A and B are operated in parallel, with bus tie breaker N

between buses A and B normally closed. No.2 generator is normally operated at

its rated output. Reactor tie breaker a between buses C and B is normally open. In

the present system, transferring load through the reactor tie is not required for

normal operations.

-- Buses C and D are operated in isolation, with tie breaker V between buses

C and D normally open.

3. Retrofit Of Cooling Equipment Of Transformer B. The load flow study

assumes that cooling fans and oil circulating pumps are installed on transformer B.

This equipment will permit transformer B to operate at its maximum rating. This

equipment is not presently installed.

4. Sharing Of Loads Between Transformers A And B. The per unit

impedance of transformers A and B, which operate in parallel, are not of equal

magnitude and phase angle. A trial load flow program was run to ascertain the

load sharing between these two transformers. The calculations demonstrate that

transformer B will serve approximately 63% of the total load on buses A and B.

Thus, load sharing is closely proportionate to the transformer ratings.

Page 27: Expansion of an existing power system - a study

17

5. No.2 Generator Reactive Capability Curve. A reactive capability curve

shows the MW and Mvar output of a generator at different operating points. As No.

2 generator may be operating at a reduced output of 8.4 MW, its reactive power

output will increase. As No.2 generator reactive capability curve could not be

obtained, it has been conservatively assumed to have a reactive output of 16 Mvar

at 8.4 MW.

6. Utility Tie Transformer Taps. All utility tie transformers are provided with

two 2-1/2°/~ taps above and below rated primary side voltage. The tap changers

are off-load type.

C. DETAILED ANALYSIS OF LOAD FLOW CASES

1. Case No.1, Stage 3 Loads. Base load flow conditions:

-- New 115-13.8 kV transformer is not installed.

-- No.2 generator operating at an output of 8.4 MW, 16 Mvar.

-- No.3 generator operating at its rated output.

-- Tie breakers 0 and V open; tie breaker N closed.

The following sudden upset conditions were examined:

Case 1A: Tra nsformer A out of service

Case 1B: Transformer B out of service

Case 1C: No.2 generator out of service

Page 28: Expansion of an existing power system - a study

18

Case 1D: No.3 generator out of service

The voltage drops under normal load flow and upset conditions are shown in

Table VII. The percent voltage drop under normal conditions is based on the rated

voltage. The percent voltage drop upon loss of a transformer or a generator is

based on the actual bus vortage. Afso it shou Id be noted that the voltage at bus E

and F actually increased by 4.6% under normal operating conditions. A typical load

flow digram for Base Case 1 is shown in Figure 4.

The following conclusions can be drawn from the load flow calculations:

-- Under normal load flow conditions there is a 10.1% voltage drop on buses

C and G. The voltage on bus D is depressed by 5.4% and on buses A and B by

3%. These voltage levels are unacceptable for normal plant operations.

-- Transformer C is overloaded approxirnately 14% under normal operating

conditions. 4 MVA of load on buses C and G is a transient load, occuring during

start-up or sheet breakage. Even if this load is not considered under normal load

flow conditions, transformer C may be slightly overloaded.

-- As the base load operating voltages are not satisfactory, a detailed analysis

of upset conditions is unnecessary. It is, however, seen that failure of transformer

B will impose a voltage drop of 15.46%. This voltage drop is in addition to the 3%

drop under normal load flow conditions. This means bus A and B voltages will be

depressed by approximately 18.46% below rated voltage.

Page 29: Expansion of an existing power system - a study

Table VII. BASE CASE 1 CHANGE CASES 1A TO 1D

Per Unit 0/0 Initial voltageVoltage and drop on loss of:

Bus No. 0/0 drop normal XFRMR A XFRMR B G2 G3conditions Case 1A Case 1B Case 1C Case 10

115 k\l buses 0.968 3.2 0.21 0.72 1.45 3.10I1Aand2A

13.8 kV bus 0.946 5.4 0.32 0.95 1.80 3.70

D

13.8 kV buses 0.899 10.1 0.33 1.11 2.0 4.23

C and G

13.8 kV buses 0.970 3.0 3.92 15.46 6.7 3.5

A and B

7.2 k\,l bus 1.0·~6 up by 0.20 0.76 1.34 2.86

E and F 4.6

19

Page 30: Expansion of an existing power system - a study

18

.23

-5.2

9

BU

S1A

:~1:~~

-27

.25

-T6.

t39

-73

,29

-35

.17

V=

.96

8

23

.70

12

.92

K81

N.a

.V

=.9

68

v=1

.00

06~.75

5v

.07

~

65

.33

46

.21

---

~~:~

~--

nK

B2

BU

S2

A1

15

KV

IV

=.9

68

25

.80

I2

9.7

2I

13

.92

18

.56

30

.71

7.5

9

"""'"

."""

,

:5g1~:

7~

v=1

.04

6

(NO

TE1)

18

.00

-8.7

2

18

.00

8.7

2

o (OP

EN

)

G3

__

e~8~~¥A

V=

.97

-73.

61-4

5.6

2G

22

40

63

KV

AO

.8P

.F

8.4

,.1

6

~:~~

N

18

.32

6.0

2

/ra:

~~(N

.C)

NE

\'IBU

SG <V=.89

9

25

.58

17

'81

14

.65

11

.8

t~:~~~ '"

V=

.94

6

17

.01

---

MW

FLO

W1

1.0

8---

MV

AR

FLO

WN

EG

ATI

VE

SIG

NR

EFL

EC

TSU

PW

AR

DP

OW

ER

FLO

WIN

THE

DR

AWIN

GA

LLV

OLT

AG

ES

ARE

INP

.UV

ALU

ES

NO

TE1:

EIT

HE

XFR~~R

EO

RF

ISIN

SE

RV

ICE

BA

SE

CAS

E1:

NEW

TRAN

SFOR

MER

NO

TIN

ST

ALL

ED

.G

2O

PE

RA

TIN

GAT

8.2M

WG

3O

PE

RA

TIN

GAT

FU

LL

CA

PA

CIT

Y.

Fig

ure

4.L

oa

dF

low

Dia

gra

m-

Bas

eC

ase

IN o

Page 31: Expansion of an existing power system - a study

21

Wide spread process interruptions on buses A and B can be expected. Since

the mill's boiler complex is fed from these buses, the extent of process

interruptionsmay increase. Even 115 kV utility breaker KB2 will be overloaded

under this condition.

The Stage 3 load growth cannot be served by the present distribution system,

even with No.3 generator operating at rated output.

2. Case No.2, Stage 3 Loads_" Base load flow conditions:

-- New 115-13.8 kV transformer is not installed.

-- No.3 generator operating at its rated output.

-- No.2 generator out of service.

-- Tie breakers a and V open, tie breaker N closed.

The following sudden upset conditions were examined:

Case 2A: Transformer A out of service

Case 2B: Transformer B out of service

Case 2C: No.3 generator out of service

The voltage drops under normal load flow and upset conditions are shown in

Table VIII.

The following conclusions can be drawn from the load flow calculations:

-- Under normal load flow conditions, the voltage levels at buses A, B, C, and

D are worse than the voltage levels in Case 1. The voltage on buses A and B is

depressed by 9.5% under normal load flow conditions.

Page 32: Expansion of an existing power system - a study

22

Table VIII. BASE CASE 2 CHANGE CASES 2A TO 2C

Per Unit Voltage 0/0 Initial voltage dropBus No. and % drop

normal XFRMR A XFRMR Gconditions Case 2A Case 2C

115 kV buses 0.954 4.6 0.63 3.35

1A and 2A

13.8 kV bus 0.929 7.1 0.65 3.98

D

13.8 kV buses 0.881 11.9 0.79 4.54

C and G

\ 13.8 kV buses 0.905 9.5 9.94 4.31I

A and B

7.2 kV buses 1.032 up by 0.58 3.10

E and F 3.2

-- The computer run did not converge upon loss of transformer B, and no

nleaningful results could be obtained. This indicates that there will be excessive

voltage drops, and the plant operations cannot be sustained.

Page 33: Expansion of an existing power system - a study

23

Without NO.2 generator in service, the normal voltage levels on buses A and

B will be 9.5% below rated voltage. This case demonstrates the necessity of

keeping No.2 generator in operation, to reduce voltage drops on 13.8 kV buses A

and B and to prevent overloading of transformers A and B.

3. Case No.3, Stage 3 Loads. Base load flow conditions:

-- ~~ew 115-13.8 kV transformer is not installed.

--No.2 and 3 generators out of service.

--Tie breakers 0 and V open, tie breaker N closed.

The following sudden upset conditions were examined.

Case 3A: Transformer A out of service '

Case 38: Transformer 8 out of service

The voltage drops under normal load flow and upset conditions are shown in

Table IX.

The following conclusions can be drawn from the load flow calculations:

--Excessive voltage drops occur on all 13.8 kV load buses.

--Transformers A, B, and C are overloaded.

A lack of convergence of the computer program upon outage of transformer B

indicates that there will be excessive voltage drops on most 13.8 kV buses.

Stage 3 load growth cannot be sustained by the distribution system in any of

the configurations from case 1 through case 3.

Page 34: Expansion of an existing power system - a study

Table IX. BASE CASE 3 CHANGE CASES 3A AND 38

P.U. Voltage 0/0 Initial voltage dropand % drop

Bus No. normal on loss of Trans. Aconditions Case 3A

115 kv buses 0.937 6.3 0.64

1Aand2/\

13.8 kv bus 0.910 9.0 0.88

D

13.8 kv buses 0.860 14. 0.93

C and G

13.8 kv buses 0.885 11.5 10.84

A and B

7.2 kv buses 1.015 up by 1.5 0.59

E and F

4. Case No.4, Stage 3 Loads. Base load conditions:

--- New 115-13.8 kV transformer is not installed.

--- No.3 generator out of service.

24

Page 35: Expansion of an existing power system - a study

25

--- NO.2 generator operating at its rated output of 19.25 MW -14 Mvar.

--- Tie breakers 0 and V open; tie breaker N closed.

The following sudden upset conditions were examined.

Case 4A: Transformer A out of service.

Case 48: Transformer B out of service.

Case 4C: No.2 generator out of service.

The voltage drops under normal load flow and upset conditions are shown in

Table X.

The following conclusions can be drawn from the load flow calculations:

--- This case represents the existing operating configuration of the

13.8 kV buses with stage 3 loads added. Excessive voltage drops occur

on most of the 13.8 kV buses under normal load conditions.

The stage 3 load growth cannot be served by the present distribution system.

5. Case No.5, Stage 3 Loads. Base load conditions:

---New 115-13.8 kV transformer is installed. It is connected to bus G

and operated in parallel with the existing transformer C.

---All paper machine No.4 loads are connected to bus G.

---No.2 and NO.3 generators out of service.

Page 36: Expansion of an existing power system - a study

26

---Tie breakers 0 and V open, tie breaker N closed.

The following sudden upset conditions were examined:

Case 5A: Transformer A out of service

Case 58: Transformer B out of service

Case 5C: Transformer C out of service

The voltage drops under normal load flow and upset conditions are shown in

Table XI. The following conclusions can be drawn from the load flow calculations:

---The voltage on 13.8 kV buses A, 8, C, D and G will be depressed from

7.8% to 9.3% under normal load flow conditions.

---The overloading of transformers A, B, and C observed in cases 2 and

3 is removed, even with No.2 generator out of service. This is due

to shifting of all No.4 paper machine loads to bus G and the addition

of transformer G.

Addition of a new utility tie transformer solves the problem of overloading of

transformers under normal load flow conditions. However 13.8 kV bus voltages are

too low for normal plant operations when both generators are out of service. This

is primarily due to losses in the utility company's system. Plant operations will be

limited when No.2 and 3 generators are out of service. No.2 generator has a major

impact on bus voltages.

Page 37: Expansion of an existing power system - a study

Table X. BASE CASE 4 CHANGE CASES 4A TO 4C

27

P.U. Voltage 0/0 Initial voltage drop on loss of:and % drop

Bus No. normal condi- Transf. A Transf. B Gen.2tions Case 4A Case 48 Case 4C

115 kv buses 0.953 4.7 0.10 0.52 1.68

1.A and 2.A

13.8 kv bus 0.928 7.2 0.11 0.54 1.94

D

13.8 kv buses 0.880 12. 0.23 0.68 2.27

C and G

13.8 kv buses 0.951 4.9 3.89 13.99 6.94

A and B

7.2 kv bus 1.031 up by 3.1 0.09 0.48 1.55

E and F

6. Case No.6, Stage 3 Loads. Base Load Conditions

---New 115-13.8 kV transformer is not installed.

---9.5 Mvar capacitor banks are connected to buses G and B.

Page 38: Expansion of an existing power system - a study

28

---No.2 and 3 generators are out of service.

---Tie breakers 0 and V open, tie breaker N closed.

The following sudden upset conditions were examined:

Case 6A: Transformer A out of service.

Case 68: Transformer B out of service.

The voltage drops under normal load flow and upset condition are shown in

Table XII.

The following conclusions can be drawn from the load flow calculations:

---The purpose of this study was to ascertain the effects of capacitor banks on

bus voltage and transformer loadings when No.2 and 3 generators are out of

service. It is seen that the provision of 9.5 Mvar capacitor banks on buses Band G

will relieve the overloads on transformers A, B, and C, which occured in cases 2

2nd 3 The The voltage levels on the 13.8 kV buses, however, stiff remain

depressed by 7.5 to 8.3%. This is unacceptable for nornlal plant operations.

Page 39: Expansion of an existing power system - a study

Table XI. BASE CASE 5 CHANGE CASES 5A TO 5C

Per Unit Voltage 0/0 Initial voltage dropBus No. and % drop

normal XFRMR A XFRMR Gconditions Case 5A Case 5C

115 kV buses 0.941 5.9 0.43 0.64

1A and 2A

13.8 kV bus 0.914 8.6 0.44 0.77

D

13.8 kV buses 0.922 7.8 0.54 12.03

C and G

13.8 kV buses 0.907 9.3 7.6 0.77

A and B

7.2 kV buses 1.019 up by 0.39 0.59

E and F 1.9

29

Page 40: Expansion of an existing power system - a study

30

Table XII. BASE CASE 6 CHANGE CASES 6A AND 66

P.u. Voltage 0/0 Initial voltage dropand % drop

Bus No. normal on loss of Transf.Aconditions Case 6A

115 kv buses 0.951 4.9 0.63

1A and 2A

13.8 kv bus 0.925 7.5 0.65

D

13.8 kv buses 0.917 8.3 0.76

C and G

13.8 kv buses 0.925 7.5 8.10

A and B

7.2 kv buses 1.029 up by 2.9 0.58

E and F

The addition of capacitor banks will not provide adequate voltage levels on

the 13.8 kV buses when No.2 and 3 generators are out of service. Plant operations

will be limited when No.2 and 3 generators are out of service.

Page 41: Expansion of an existing power system - a study

31

7. Case No.7, Stage 3 Loads. Base load conditions:

---New 115-13.8 kV transformer is not installed.

---A 14 Mvar capacitor bank is connected to bus G and a 7 Mvar capacitor

bank is connected to bus D.

---No.2 generator operating at a minimum output of 8.4 MW - 16 Mvar.

---No.3 generator operating at its rated output.

---Tie breakers 0 and V open; tie breaker N closed.

The following sudden upset conditions were examined:

Case 7A: Transformer A out of service.

Case 78: Transformer 8 out of service.

Case 7C: No.2 generator out of service.

Case 7D: No.3 generator out of service.

The voltage drops under normal load and upset conditions are shown in

Table XIII.

Page 42: Expansion of an existing power system - a study

32

Table XIII. BASE CASE 7 CHANGE CASES 7A TO 7D

Per Unit 0/0 Initial voltageVoltage and drop on loss of:

Bus No. 0/0 drop normal XFRMR A XFRMR B G2 G3conditions Case 7A Case 7B Case 7C Case 70

115 kV buses 0.983 1.7 0.2 0.71 1.42 3.05

1Aand2.A

13.8 kV bus 0.993 0.7 0.2 0.91 1.71 3.63

D

13.8 kV buses 0.980 2.0 0.31 0.92 1.84 4.08

C and G

13.8 kV buses 0.986 1.4 3.75 14.5 6.39 3.45

A and B

7.2 kV bus 1.036 up by 0.19 0.68 1.25 2.80

E and F 3.6

Table XIV shows the percent transformer loadings based on their maximum

ratings, under normal load flow and upset conditions based on FOA ratings.

Generator outputs are shown in MW/Mvar.

Page 43: Expansion of an existing power system - a study

33

The following conclusions can be drawn from the load flow calculations:

Under normal load flow conditions, the voltages on 13.8kV buses C and G will

be depressed by 2% of rated voltage. The voltage on buses A and B will be lower

by 1.4% and on bus D by 0.7%. Table XIV shows that none of the transformers are

overloaded during normal load flow conditions. The base case, therefore,

represents a normal operating configuration capable of supporting Stage 3 loads.

Upon loss of transformer A, an initial voltage drop of 3.750/0 occurs on buses

A and B. Transformer B, however, is loaded to 117.6% of its maximum rating. By

operating No.2 generator at its rated output of 19.25 MW - 14Mvar, transformer B

loading can be reduced to 94%. Thus plant operations can be sustained upon loss

of transformer A.

Upon loss of transformer B, the initial voltage drop on buses A and B will be

14.5%, and transformer A "vill be loaded to approximately 222% of its rating.

Widespread shutdowns in the areas served by buses A and B can be expected.

This may cause mill wide process disruptions, since the boiler complex is fed from

bus B.

Upon loss of No.2 generator, buses A and B experience a initial voltage drop

of 6.39C;;o, and transformers A and 8 are slightly overloaded. Load shedding of 3-4

MVA will relieve transformers A and B of their overloads.

Page 44: Expansion of an existing power system - a study

34

Table XIV. PERCENTAGE TRANSFORMER LOADINGS FOR NORMAL AND UPSET

CONDITIONS NO.1

CASE 7A CASE 76XFRMR CASE 7 XFRMR A XFRMR B CASE 7C CASE 7DOR BASE OUT OF OUT OF G2 OUT OF G3 OUT OFGEN. NO. CASE SERVICE SERVICE SERVICE SERVICE

XFRMR A 70.70 221.7 102.3 70.9

XFRMR B 71.5 117.6 103.5 71.7

XFRMR C 87.9 87.9 87.9 87.9 89.8

XFRMR D 74.7 74.7 74.7 74.7 75.4

G2 8.4/16 8.4/16 8.4/16 8.4/16

G3 76.61/45.62 73.61/45.62 73.61/45.62 73.61/45.62 --

Bus D and buses C and G are operated as islands. A total shutdown will

occur in the process areas served by these buses if the transformer serving each

island is suddenly lost. Under norrnal running conditions transformer C has a

spare capacity of approximately 4.5 MVA, and transformer D has a spare capacity

of approximately 9 MVA. Thus, a maximum of 9 MVA of load on bus C can be

supplied from transformer D when transformer C is out of service. Thus, after a

shutdown caused by failure of transformer C or D, there is no available spare

Page 45: Expansion of an existing power system - a study

35

capacity to restore the process to rated production. Extensive load shedding will

be requ ired.

Stage 3 loads can be supported under normal load flow conditions with

capacitor banks added to buses D and G. However, widespread shutdown will

occur upon failure of transformers B, C or D. The process cannot be restored at

rated capacity with the loss of one of these sources.

8. Case No.8, Stage 3 Loads. Base Load Conditions:

New 115-13.8 kV transformer is installed and connected to bus G. This

transformer is operated in parallel with existing transformer C.

No.2 generator operating at 8.4MW - 16 Mvar output.

No.3 generator operating at its rated output.

Tie breakers 0 and V open; tie breaker N closed.

The following sudden upset conditions were examined:

Case SA: Transformer A out of service

Case 8B: Transformer B out of service

Case 8e: Transformer G or C out of service

Case 80: No.2 generator out of service

Case BE: No.3 generator out of service

Case 8F: This is an independent case. This examines the load flow conditions

when transformer D is out of service and bus tie breaker V between buses C and D

is closed.

Page 46: Expansion of an existing power system - a study

36

The voltage drops under load flow and upset conditions are shown in Table

XV and XVI.

Table XVII shows the percentage transformer loadings based on their

maximum ratings under normal load flow and upset conditions. The generator

outputs are shown in MW/Mvar.

The following conclusions can be drawn from the load flow calculations: The

13.8 kV bus voltages are within + 0.20/0 to -0.50/0 of rated voltage under normal

load flow conditions. A maximum initial voltage drop of 8.68% occurs on buses A

and B upon loss of transformer B.

Table XVII shows that transforrner A or No.2 or 3 generators can be removed

from service without overloading any of the other sources.

Page 47: Expansion of an existing power system - a study

Table XV. BASE CASE 8 CHANGE CASES 8A TO 8E

37

P.u. Voltage 0/0 Initial voltage drop on loss of:and % drop

Bus No. normal Transf. A Transf. B transf. G Gen. 2 Gen. 3conditions Case 8A Case 8B Case 8C Case 80 Case BE

115 kv buses 0.985 1.5 0.10 0.30 0.30 1.32 3.05

1A. 2;d 2i\

13.8 kv bus 0.995 0.5 0.10 0.40 0.40 1.51 3.52

D

13.8 kv buses 1.002 0.2 0.10 0.40 5.59 1.50 3.49

C and G

13.8 kv buses 1.002 0.2 2.40 8.68 0.30 5.89 3.19

A and B

7.2 kv bus 1.038 3.8 0.10 0.30 0.30 1.25 2.79

E and F

Page 48: Expansion of an existing power system - a study

Table XVI. BASE CASE 8F

Per Unit Voltage andBus No. 0/0 Drop for Normal

Load Flow Conditions

115 kV buses 1A and 2A 0.983 1.7

13.8 kV bus 0 0.972 2.8

13.8 kV buses C and G 0.972 2.8

13.8 kV buses A and 8 0.998 0.2

7.2 kV buses E and F 1.036 up by 3.6

38

Page 49: Expansion of an existing power system - a study

Ta

ble

XV

II.

PE

RC

EN

TA

GE

TR

AN

SF

OR

ivlE

RLO

AD

ING

NO

RM

AL

AN

DU

PS

ET

CO

ND

ITIO

NS

NO

.2

88

A8

88C

80

BE8

FX

FRM

RX

FRM

RA

XFR

f\/1R

BX

FR

MR

GG

2G

3X

FRM

RD

or

BA

SE

Ou

to

fO

ut

of

Ou

to

fO

ut

of

Ou

to

fO

ut

of

GE

NC

AS

ES

erv

ice

Se

rvic

eS

erv

ice

Se

rvic

eS

erv

ice

Se

rvic

e

A5

5--

16

255

84

.855

.14

0.3

B5

5.6

90

.4--

55.6

84

.85

5.7

40

.7

G5

4.5

54

.55

4.5

--5

4.5

55

.39

4.7

C5

4.5

54

.554

.51

16

.85

4.5

55

.39

4.7

GE

N8

.4/

8.4

/8

.4/

8.4

/--

8.4

/1

9.2

5

G2

1616

1616

1614

GE

N7

3.6

1/

73

.61

/7

3.6

1/

73

.61

/73

.61

--7

3.6

1/

G3

45

.62

45

.62

45

.62

45

.62

45

.62

45

.62

XFR

MR

74

.67

4.6

74

.67

4.6

74

.67

5.4

0

W \0

Page 50: Expansion of an existing power system - a study

40

If transformer B is removed from service, transformer A will experience a

62~/0 overload. If the output of No.2 generator is increased to 19.25 MW and 14

Mvar, this overload decreases to 32%. This overload can be removed by closing

tie reactor breaker 0 and transferring power from bus to bus B. Case 15 covers

this in detail.

If transformer C is suddenly removed from service, transformer G will

experience a 16.7% overload. If the tie breaker between buses C and 0 is closed,

this overload will be removed. A similar situation will occur if transformer G

suddenly is removed from service, because transformers C and G will operate in

parallel. The impact of large motor starting voltage drops when in one of these two

system configurations is not known.

As bus D is being operated as an island, a sudden removal of-transformer 0

will result in a complete shutdown of the process areas from this bus. The

process can, however, be restored by closing tie breaker V between buses C, 0

and G can be fed from any two of the three transformers, without overloading any

of these units. The impact of large motor starting voltage drops when this

configuration is not known.

A planned outage of transformer D can be made without major load loss by

opening tie breaker 0' between buses C and G. Thereafter tie breaker V between

buses C and D can be closed, and transformer D can be taken out of service.

Transformer C will supply loads on buses C and D and will be momentarily loaded

to 130~/~ of its maxirrlum rating. The tie breaker 0' between buses C and G can be

reclosed, relieving transformer C of its overload. This operation prevents

paralleling of transformers 0, C, and G. The voltage levels when only transformer

C is supplying buses 0 and C have not been calculated. Some load reduction may

be required.

Page 51: Expansion of an existing power system - a study

41

The addition of a new utility tie transformer and capacitor banks will support

the stage 3 loa-ds. Loss of transformer A, No.2 generator or No.3 generator can be

tolerated without process interruptions. Loss of other sources may result in

overloading of transformers in service or cause process interruptions. However,

appropriate switching operations may restore normal plant operations.

9. Case No.9, Stage 3 Loads. This case has similar operating conditions as

case ~~o. 7 except that a third 7 tvivar capacitor bank was added to buses A and B.

This further improves the normal operating bus voltages and limits the initial

voltage drop upon loss of transformer B on buses A and B to 8.4%, as compared

to 14.5% in 7. In all other respects the conclusions drawn from the study of case 7

apply.

10. Case No. 11, Existing Loads. Base load Conditions:

This case studies the load flow on 13.8 and 7.2 kV buses with existing plant

loads.

11. Case No. 12, Stage 1 Loads. This case studies the load flow on 13.8 and

7.2 k.V buses when stage 1 loads are applied to the distribution system without any

modifications.

12. Case No. 14, Stage 2 Loads. This case studies the load flow on 13.8 and

7.2 kV buses when stage 2 loads are applied to the distribution system without any

modifications. Now 13.8 kV bus G is in operation and is connected to bus G

through a tie breaker.

The voltage drops under normal load flow conditions are shown in Table

XXVIII.

Page 52: Expansion of an existing power system - a study

42

The following conclusions can be drawn from the load flow calculations:

Stage 1 load growth results in a maximum voltage drop of 3.4% on 13.8 kV

buses C and G. This increases to 5.8% when stage 2 loads are applied. The

voltage drop on other 13.8 kV buses is limited to a maximum of 3.1% with stage 1

loads applied, increasing to 3.70/0 when stage 2 loads are applied. Though these

voltage levels are slightly depressed, it may be possible to sustain plant

operations~ without modifications th:ough stage 2 load growth. ~Jo. 2 generator has

been assumed to be operating at its rated output and No. 3 generator out of

service. The commissioning of No.3 generator by the time stage 1 loads become

operational will improve 13.8 kV bus voltages by approximately 20/0. A further

improvement of the voltage level is possible if the utility company can maintain

rated voltage at the 115 kV buses under normal lo-ad flow conditions.

Change cases have not been considered in these configurations. However,

during normal load flow conditions none of the sources are overloaded.

13. Case No. 15, Stage 3 Loads. Base Load Conditions:

This case was examined to ascertain the load flow through the tie reactor

between buses C and B, when transformer B is out of service.

Page 53: Expansion of an existing power system - a study

43

Table XVIII. BASE CASE 11, 12 AND 14

Bus No. P.U. Voltage and % DropNormal load flow conditions

115 kv buses 1A and 2A 0.978 2.2 0.970 3.0 0.966 3.4

13.8 kv bus D 0.990 1.0 0.971 2.9 0.966 3.4

113.8 kv buses C and G 0.984 1.6 0.966 3.4 0.942 5.8

1

13.8 kv buses A and B 0.996 0.4 0.969 3.1 0.963 3.7

7.2 kv buses E and F 1.056 1.048 1.044

up by 5.6 up by 4.8 up by 4.4

BeforE~ closing tie-reactor breaker 0, bus C is isolated from buses 0 and G.

The voltage drops under this condition are shown in Table XIX.

The following conclusions can be drawn from the study result:

5.52 MVA of load is transferred through the tie reactor. This relieves

transformer A of its overload.

None of the sources are overloaded.

This configuration can be adopted to support load on buses A and B when No.

2 generator or transformer B is out of service. However, a short-circuit study of

Page 54: Expansion of an existing power system - a study

44

this configuration should be made to ascertain that none of the circuit breakers are

exposed to short circuit duties exceeding their ratings.

D. GENERAL CONCLUSIONS DRAWN FROM THE LOAD FLOW CALCULATIONS

There are no voltage drop or load flow problems on 7.2 kV buses E and F in

any of the load flow cases. The load on these buses consists of 4200HP

synchronous grinder niotors operating at a leading pO~/er factor of 0.9.

Approximately 5.3 leading Mvar is supplied to 115 kV bus 1A through transformer

E. Only one of transformers E and F is kept in service at any time. Failure of the

operating unit will shutdown the loads, however, the process can be restored by

switching in the standby transformer.

Utility tie transformers A, B, C, D, and new transformer G must be operated

on their lowest tap of 0.95 to provide a 50/0 voltage boost on the 13.8 kV side. ~~o

problems are anticipated in controlling the generation voltage of new No.3 turbine

generator or the voltage levels on 7.2 kV buses E and F. Transformer G3 can be

set on the 13.8 kV tap.

Page 55: Expansion of an existing power system - a study

45

Table XIX. BASE CASE 15

Bus No.

115 kv buses 1A and 2A

13.8 kv bus 0

13.8 kv bus C

13.8 kv bus G

13.8 kv buses A and B

7.2 kv buses E and F

P.U. Voltage and % Drop

Normal load flow conditions

0.984 1.6

0.994 0.6

0.966 3.4

1.017 up by 1.7

0.956 4.4

1.037 up by 3.7

A sudden loss of NO.3 generator will cause a voltage drop of approximately

3% to 4.7% on the 115kV buses. This drop is mainly due to increased load flow

through the utility tie transmission line impedance.

The voltage drop on the 115 kV utility bus under maximum load flow

conditions could approach approximately 6.3"io to 8% when No.2 and 3 generators

are out of operation and capacitor banks are not provided on 13.8 kV buses D and

G. This drop occurs in the utility transmission line and source impedances. The

utility 115 kV bus voltage regulating capabilities are not known. The presence of

capacitor banks on 13.8 kV buses will compensate for a portion of the lagging kvar

Page 56: Expansion of an existing power system - a study

46

and reduce the voltage drop in the utility's system under normal load flow and

upset conditions. It is, however, desirable that the utility maintains rated voltage

on the 115 kV buses under normal load flow conditions.

Two alternatives, as shown in Figure 5, for the primary side connections of

new utility tie transformer G have been considered:

Pr f r;l ,:F"y Cc' nnect ionsean bern ~3 ci e to 11 5 kV bus 1A.

-- Primary connections can be made to 115 kV bus 2A.

A primary connection of transformer G t0115 kV bus 1A is preferred. This will

ensure availability of power at 13.8 kV buses C, G and D even if one of 115 kV

buses 1A or 2A is out of service. Since No.3 generator is also connected to bus

1A, there is a direct flow of power from No.3 generator to transformer G.

If a primary connection of transformer G is made to 115 kV bus 2A a total

shutdown will occur on bus C, G, and D on a failure of 115, kV bus 2A.

Page 57: Expansion of an existing power system - a study

N.O

9

7TH

HA

RM

ON

IC

f\1.C

IN.e

N.

~_~_

IT

~.c

9I

II

.

o12

00

Ar'

lN.O

I I I I I J I

N.e

115~(\J

BU

S2A

N.O

11

5K

VO

lJS

1A

.r--

------

--·-l

~:---~-J

II

1I

1C

)G

IA

lB

G3

11

ElF

»:X

TAP

Q*T

AP

TTA

P»:X

{TA

PTA

P~(""

'"~{""

'"TA

P~{

TAP

0.9

5I

0.9

5I

0.9

5.9

51

.01

.01

.0I

•I I I I I I

N.C

o J I

10

~T

)\P

0.9

5

N.C

IN

.C

l-

N.o-

---..-

TI

0o1

20

0A

I I I I I J I I i\

~i

IC

AP

AC

ITO

R1

,,--

----

-.--

--,

~P

RO

TEC

TIO

N5T

H{

~l

AN

DC

ON

TRO

LH

AR

fAO

NIC

~~

fR

ELA

YS

(r

r----1

5T

HH

AR

M0

NIC

r----~

1'-

---1

1C\

)F

ILT

ER

1~

l@C

AP

AC

ITO

R1

-A.-

GR

OU

ND

ING

1~

1~

UN

BA

LAN

CE

I~)

I/o

SW

ITC

HI

II<

DE

TEC

TIO

N_

_1..

_7

,2t.1

VA

R(T

'fP.)

-~--

7.2

t"N

AR

-:':7.

2MV

AR

EO

UIP

I\1E

NT

I

Fig

ure

5.L

oca

tio

no

fT

ieT

ran

sfo

rme

rG

An

dF

ilte

rs~ -.

J

Page 58: Expansion of an existing power system - a study

48

IV. I-IARMONIC ANALYSIS SrrlJDY

A. INTRODUCTION

Installation of capacitor banks in a distribution system can achieve the

following objectives:

---I~lprO'''''e the system operating power factor.

---Improve the load flow situation and the operating voltage level on load

buses.

---Reduce the initial voltage drop upon loss of a major source.

---Improve the useful energy availability from generators and transformers.

---Reduce loading of cables, bus bars and other distribution system

components.

---Reduce system losses.

---Reduce voltage and current distortions on various buses when capacitors

are used with harmonic filter reactors.

Capacitors are needed on 13.8 kV bus G to support an acceptable operating

voltage level and to reduce the Mvar loading of transformer C.

Page 59: Expansion of an existing power system - a study

49

B. HARMONICS DUE TO RECTIFIERS LOADS AND RESONANCES

The No.4 paper machine dc drive loads will be connected to 13.8 kV bus G.

Thyristor drive systems produce alternating harmonic currents. The harmonic

currents generated will depend upon the following factors:

---The circuit configuration and whether any of the rectifier units are

phase-displaced from the others.

---System parameters, which determine the flow of harmonic currents in the

various elements of the distribution system.

---KVA output of the rectifier units.

---Phase retard angle of the rectifiers.

Application of capacitors in conjunction with harmonic current generating

equipment can cause resonant conditions.

There are two forms of resonances that can occur. These are series and

parallel resonances. In a series resonant circuit, the total impedance at a resonant

frequency reduces to a resistance component only. high currents can flow at the

resonant frequency. A parallel resonant circuit has high impedance at the resonant

frequency. However, high resonant currents can circulate through the capacitor

and system reactance combinations, though the exciting source current may be

small. This can overload the capacitor banks and result in nuisance operation of

the capacitor bank fuses.

Excessive harmonic currents can also cause the following undesirable effects:

Page 60: Expansion of an existing power system - a study

50

---Telephone interference

---Produce rotor overheating in turbine generators

---I ncrease system losses

---Affect operation of protective devices

---Distort voltage and current waveforms

C. S}X-PULS~ RECT1FJERS

The mill's dc drive systems have six-pulse rectifiers. They produce six pulses

superimposed on the de output for every cycle of the ac supply.

Harmonic currents in an ac supply system are given by the expression:

h == kp ± 1

where

h == order of the harnl0nic

p == number of pulses produced by the rectifier

k == any integer

(1)

(2)

Thus a six-pulse rectifier will produce 5th, 7th, 9th, 11th, 17th, 19th, etc. The

maximum magnitude of each harmonic current is given by:

Ih == IJh p.u. of the fundamental (3)

where Ih =::: harmonic current and h = order of the harmonic. Thus a 5th harmonic

can theoretically produce a current equal to 1/5th or 200/0 of the fundamental

current.

Page 61: Expansion of an existing power system - a study

51

IEEE 399-1980 recommends that the following factors be included when

modeling a power system for a harmonic analysis study:

HCF harmonic cancellation factor. This factor depends upon the

rectifier-transformer configuration. In the plant where study was conducted,

transformers are delta-wye connected and have a HCF = 1.

CRF : Commutating reactance factor. The commutating reactance will affect the

magnitude of harmonic currents.

LDF : Unit loading factor. Harmonic current output will be reduced if the rectifier is

not delivering rated output. Since the rectifiers have phase retard control, this

loading factor is not necessarily proportional to the kVA output of the rectifiers.

when these factors are included in the analysis, equation (2) is modified as

follows:

(HCF)(CR F)(LDF)Ih == h p.u. of the fundamental

The harmonic current magnitude are shown in Table XX.

D. FiLTER REACTORS

(4)

Figure 6 shows a basic system configuration utilizing capacitors on a rectifier

bus. The equivalent irnpedance diagram is also shown in this drawing. The

transformer and source impedance are in parallel with the filter impedance.

Referring to this drawing:

(5)

(6)

and

Page 62: Expansion of an existing power system - a study

52

(If)(Zf) == (ls)(Zs) (7)

where

Ih = total harmonic current injected

1= harmonic current in system elementss

If = harmonic current in filter (8)

Zf= filter impedance

Z == equivalent source impedances

Table XX. HARMONIC CURRENT IN STATIC CONVERTER INPUT PER UNIT OF

FUNDAMENTAL CURRENT

Harmonic Frequency Harmonic current inOrder (Hertz) per unit of

fundamental frequency

5 300 0.175

7 420 0.110

11 660 0.045

13 780 0.029

17 1020 0.015

19 1140 0.010

23 1380 0.009

25 1500 0.008

Page 63: Expansion of an existing power system - a study

ZfI'IiZs

)PI

STE

PD

OW

NTR

ANSF

ORM

ERR

l+

jXt

(Zt)

SOU

RCE

BUS

Ri+

jXi

(2i)

Zt

Zm

Zi

Zc

Vh

Ih

.-CU

RREN

TS

OU

RC

E

Rm+

jXm

(Zm

)

EQUI

VALE

NTM

OTO

RR

c+

jXc

(Ze

)LO

AD

FILT

ER~

REAC

TOR

CAP

.BA

NK~

TE

OU

IVA

LEN

TR

ECT.

XFR

MR

Zf

EQIU

VALE

NT

IMPE

DAN

CE

DIA

GR

AMFO

RH

ARM

ON

ICC

UR

REN

TFL

OW

SIN

GLE

LIN

ED

IAG

RAM

Fig

ure

6.E

qu

iva

len

tC

ircu

itfo

rH

arm

on

icA

na

lysi

sV

IW

Page 64: Expansion of an existing power system - a study

54

The harmonic voltage across the filter impedance equals that of the total

source impedance. This gives

(9)

and

where

(10)

ZfPs ==---

Zf+ Zsboth are complex quantities. (11 )

Ratios Ps and Pf are called "harmonic current distribution factors" or RHO

factors. A good filter will have a Pf of very close to unity for a current at its tuned

frequency. Pf will be typically around 0.995, and the corresponding Ps for the power

system will be around 0.05.

For a series resonant filter, the impedance angles of Ps and Pf will be

approximately -81 0 and +2.60 respectively.

Page 65: Expansion of an existing power system - a study

55

E. CAPACITOR RATINGS

Capacitor banks in the filter circuit are subjected to harmonic current flows.

Capacitors can fail either due to harmonic current overloading or due to the

overvoltages caused by these harmonics.

The recommendations of IEEE 519-1981 and IEEE 18-1980 have been followed

to provide a normal life expectancy for the capacitor banks.

recommendations impose the following lirnits on capacitor loading:

These

-- Total rms current of the capacitor banks, including all harmonics, should not

exceed 180% of its rated current, Le.

'RSS ==

h= max

I~+ I I~h=2

(12)

where

IRSS == total current (rms)

If == fundamental current

Ih == harmonic current.

(13)

It should be noted that if the capacitor bank is loaded with only one harmonic

current, it could take 150% of the rated fundamental current at that harmonic.

-- The total kvar loading of the capacitor bank should not exceed 135% of the

nameplate rating, including loading due to all harmonics:

Total kvar(14)

Page 66: Expansion of an existing power system - a study

56

-- The rms voltage, including all harmonics, but but excluding transients should not

exceed 110% of the rated voltage.

VRSS =h= max

V2

+ I v~h=2

(15)

-- The crest voltage should not- exceed 1200/0 of the rms voltage times -12. The

harmonic voltages are arithmetically summated and added to the fundamental for

this evaluation

h= max

VSUM = Vf + I Vf

h=2

(16)

Values of IRSS, VRSS, total kvar and VSUM are calcu lated. The selection of

capacitor banks has been nlade so that none of these parameters exceed the

recommended limits under any of the modeled operating conditions of the

distribution system.

Page 67: Expansion of an existing power system - a study

57

v. SYSTEM l\10DELING FOR I-IARMO~ICA~ALYSIS STlJD)l

A. IMPEDANCE DIAGRAM

Figure 7 shows the impedance diagram of the distribution system at the

fundamental frequency for the harmonic analysis study.

The plant rectifi.er loads are con~~cted to 13.8 kV buses A, B, C, and G.

There are no rectifier loads connected to 13.8 kV bus D or 7.2 kV buses E and F.

The projected dc drive loads for No.4 paper machine and the existing rectifier

loads are represented as equivalent rectifier loads:

Buses A and B:

Figure 7.

Buses C and G:

Figure 7.

9750 KVA, 480 Volt. This load is shown as Bus 3 load in

26,000 KVA, 480 Volt. This load is shown as Bus 2 load in

1250 KVA, 550 Volt: This load is shown as Bus 1 load in Figure 7.

To simulate the worst harmonic loading conditions, the rectifier load

estimates throughout the distribution system have been made based upon the

naturally cooled rating the connected transformers.

The rectifier load injection buses are connected to the 13.8 kV buses A and B

and C and G through rectifier transformers of equivalent impedances.

The motor loads on each of the 13.8 kV buses are represented as equivalent

impedances M 1, M2, M3 and M4.

Page 68: Expansion of an existing power system - a study

9,0

05

7(S

OU

RC

E)

.05

70

,'5

KV

oJ

I

X~Rt,;1R

0.0

221

.40

18

1.3.

8KV

XF

RM

RC

.02

19

.402

.3

(NO

)

V

XF

RM

RG

3.0

04

8.1

48

1G

3

.00

23

2.2

30

9

BUSE

SC

AND

G

.00

53

.26

25

XFR

MR

A.0

45

0.6

51

4

BUSE

S0

AAN

D8

XFRM

R8

.02

07

.J8

03

G2~

.01

03

:?S13

.44

15

M0

H13

.8K

VI

A

XFRM

RE

.06

46

,93

78

7.2K

VB

US

ES

EAN

DF

M1

.02

42

.66

70

~~2

.23

10

1.6

97

BUS

1.5

4255

0V3

.79

5

.12

7l.

00

54

.63

27

.26

96

.031

01"'

T-r

1199

77.

2MV

A7.

2MV

ABU

S2

480V

M3

.01

85

.33

33

BUS

348

0V

.051

.46

2

~~4

.04

4,.

23

5

7TH

HARMOt~IC

FILT

ERQ

=50

8AN~<

297

50K

VA

5TH

tiAR

MO

NIC

FILT

Ef;

Q=

50BA

NKi

2600

0KV

A12

50K

VA

.02

42

----

P.U

.RE

SIS

TAN

CE

.66

70

----

P.U.REACTA~lCE

ALL

RE

SIS

TAN

CE

SA"

JDR

EA

CTA

NC

ES

ARE

ON10

0MV

ABA

SEAT

60H

ERTZ

~~~,

,~..1

2I~.1J

,~1

4AR

EEQ

UIV

ALE

NT

~,10

TOR

LOA

0S

Fig

ure

7.Im

pe

da

nce

Dia

gra

mw

ith

Eq

ua

l5

tha

nd

7th

Filt

ers

(J)

00

Page 69: Expansion of an existing power system - a study

59

B. SWITCHING CONDITIONS

The switching conditions shown in Table XXI were initially identified for the

harmonic analysis study. The following symbols are to be noted:

C - closed In - in service

o - open Out - out of service

transformer on Bus G. As the study progressed, it became evident that it will not

be necessary to study all the conditions initially identified in Table XXI. The effect

of adding a new tie transformer to bus G was included in the study. Each of the

switching conditions studied, and the study results, are described in detail in

Chapter 6.

c. DETAILS OF THE DIGITAL COMPUTER HARMONIC STUDY

The computer program used conducts the harmonic analysis in two parts:

1. Part-I. A rectifier is assumed to be a harmonic current generator which

'injects' higher frequency currents into the system. Current is injected one

frequency at a time to find the system response. Then currents at all other

frequencies are injected. This identifies the resonant conditions in the system at a

particular frequency. A graph of frequencies and the corresponding harmonic

current distribution factors are obtained. These data are also shown in tabular

form.

Page 70: Expansion of an existing power system - a study

60

Table XXI. SWITCHING CONDITONS WITHOUT NEW UTILITY TRANSFORMER

Case Capacitor G2 G3 BreakersNo. Banks

5th 7th V J M 0

IN IN IN IN 0 C C 0

2 IN IN IN OUT 0 C C 0

3 IN IN OUT OUT a c c 0

4 IN IN IN IN 0 C 0 0

5 IN IN IN IN 0 0 c C

6 IN IN OUT IN 0 C C C

7 OUT IN IN IN 0 C C 0

8 IN OUT IN IN 0 C C 0

2. Part-II. Harmonic currents and voltages in the selected system

configurations are calculated for the injected harmonic currents. The magnitude of

harmonic current and voltage distribution on each of the 13.8 kV buses, capacitor

banks, and utility system are calculated.

The resulting VSUt·J1, total capacitor Kvar loadings, VRSS, IRSS, and total

harmonic distortion are calculated to evaluate the harmonic duties on the

capacitors and effectiveness of the filter reactors.

Page 71: Expansion of an existing power system - a study

61

The computer calculations include the following:

---A listing of the circuit elements along with impedance values, tolerances,

load currents and voltages.

---A tabulation and graphical representation of the harmonic distribution

factors and phase angles.

---/1. tabulation of the harrnonic currents and voltages in the identified buses.

---Totalized quantities of VSUM, THO, VRSS, IRSS and Kvar loading on the

identified buses.

Page 72: Expansion of an existing power system - a study

62

VI. DISCUSSION OJ~ THE STUI)Y RESlJLTS

A. FREQUENCY SCAN

A frequency scan is made from 60 Hz to 1,800 Hz (fundamental to 30th

harmonic) to identify t~e location of resonant frequencies. The per unit harmonic

impedances of the major components of the distribution system are also

calculated.

The switching conditions considered for frequency scan are shown in Table

XXII and XXIII.

A brief summary of the resonant frequencies and the distribution factors is

shown in Table XXIV and XXV.

The following conclusions can be drawn from the study results:

---The resonant conditions of cases 1AF, 1SF, 1CF show that the system

response is identical whether the harmonic injection source is placed at rectifier

group 1,2 or 3. Thus the rest of the study was conducted with harmonic injection

only at rectifier group 1.

---Cases 1AF, 2AF, 3AF show that harmonic distribution factors are high at 5th

and 7th harmonics. Tuning reactors are necessry to reduce RHO factors at these

rectifier generated frequencies.

---Resonances at frequencies higher than 7th harmonic do not occur in the

distribution system.

---The capacitor banks should not be operated with the 5th harmonic filter out

of service,though they can be operated without the 7th harmonic filter.

Page 73: Expansion of an existing power system - a study

Ta

ble

XX

II.S\UMt\~ARY

OF

FR

EQ

UE

NC

YS

CA

NC

AS

ES

NO

.1

CA

SE

NO

.HAR~J10NIC

INJE

CT

ION

BR

KR

AT

V

SW

ITC

HIN

GC

ON

DIT

ION

SB

RK

RN

O.2

GE

NB

RK

RH

RE

AC

TO

R0

XF

RM

RG

5T

H7

TH

HA

RM

ON

ICH

AR

MO

NIC

FIL

TE

RF

ILT

ER

AN

DC

AP

.A

ND

CA

P.

1l,

FR

EC

T1

OP

EN

CL

OS

EO

UT

OP

EN

NO

---N

OR

EA

CT

OR

1B

FR

EC

T2

OP

EN

CL

OS

EO

UT

OP

EN

NO

---7

.2M

VA

R

1C

FR

EC

T3

OP

EN

CL

OS

EO

UT

OP

EN

YE

S

2A

FR

EC

T1

OP

EN

CL

OS

EO

UT

OP

EN

YE

SN

OR

EA

CT

OR

/7.2

MV

AR

3A

FR

EC

T1

OP

EN

CL

OS

EO

UT

OP

EN

YE

S7

.2M

VA

RN

O

4A

FR

EC

T1

OP

EN

CL

OS

EO

UT

OP

EN

YE

SR

T4

.7R

T7

.2

7.2

MV

AR

7.2

MV

AR

0'­

l~

Page 74: Expansion of an existing power system - a study

Ta

ble

XX

III.

SU

MM

AR

YO

FF

RE

QU

EN

CY

SC

AN

C.f\

SC

SN

O.2

C,A

.SE

NO

.H

AR

MO

NIC

INJE

CT

ION

BR

KR

AT

V

SW

ITC

HIN

GC

ON

DIT

ION

SB

RK

RN

O.2

GE

NB

RK

RH

RE

AC

TO

R0

XF

RM

RG

5Tf-·

f7

TH

HA

RM

ON

ICH

AR

MO

NIC

FIL

TE

RF

ILT

ER

AN

rJC

AP

.A

ND

CA

P.

5A

FR

EC

T1

OP

EN

CL

OS

EO

UT

OP

EN

NO

RT

4.7

RT

7.2

7.2r

\J1V

AR

7.2

MV

AR

6A

FR

EC

T1

OP

EN

CL

OS

EO

UT

OP

EN

NO

NO

RT

7.2

7.2

MV

AR

I

7A

FR

EC

T1

OP

EN

CL

OS

EO

UT

OP

EN

YE

SR

T4.

7N

O

7.2

MV

AR

8A

FR

EC

T1

OP

EN

OP

EN

OU

TC

LO

SE

NO

RT

4.7

RT

7.2

7.2

MV

AR

7.2

MV

AR

~

Page 75: Expansion of an existing power system - a study

65

Table XXIV. FREQUENCY SCAN CASES RESONANT HARMONIC FREQUENCIES IN

MULTIPLES OF FUNDAMENTAL RHO FACTORS NO.1

RECT. CAP 1 CAP 2CASE BUS 5th 7th XFRMR C XFRMR G3NO. AT HARMONIC HARMONIC

1AF RECT 1 4.5/9.159 4.5/9.159 4.4/14.344 4.4/1.584

5/2.315 5/2.315 5/2.894 5/9.320

(NO FILTER) (NO FILTER)

1BF RECT 2 4.5/9.159 4.5/9.159 4.4/14.344 4.4/1.584

5/2.669 5/2.669 5/2.894 5/0.320

(NO FILTER) (NO FILTER)

1CF RECT 3 4.5/0.381 4.5/0.381 4.5/0.608 4.4/0.097

(NO FILTER) (NO FILTER)

2AF RECT 1 5.7/10.691 5.7/10.691 5.7/18.802 5.7/2.076

5/1.615 5/1.615 5/3.691 5/0.408

(NO FILTER) (NO FILTER)

3AF RECT 1 8.1/20.978 REMOVED 8.1/18.273 8.1/2.018

7/2.961 7/3.454 7/0.381

(NO FILTER)

Page 76: Expansion of an existing power system - a study

66

Table XXV. FREQUENCY SCAN CASES RESONANT HARMONIC FREQUENCIES IN

MULTIPLES OF FUNDAMENTAL RHO FACTORS NO.2 &part2. &part3.

RECT. CAP 1 CAP 2CASE BUS 5th 7th XFRMR C XFRMR G3NO. AT HARMONIC HARMONIC

4AF RECT 1 3.7/7.903 6/11.237 3.8/10.705 3.8/1.183

5/0.924 7/1.200 5/0.292 5/0.032

(5th FILTER) (7th FILTER) 7/0.068 7/0.008

5AF RECT 1 3.4/10.042 5.7/9.805 3.4/12.852 3.4/1.420

5/1.051 7/1.084 5/0.184 5/0.020

(5th FILTER) (7th FILTER) 7/0.036 7/0.004

6AF RECT 1 REMOVED 4.7/15.802 4.7/12.772 4.7/1.411

5/5.095 5/3.279 5/0.362

(7th FILTER)

7AF RECT 1 4.1/7.878 REMOVED 4/6.866 4/0.758

5/0.733 5/0.234 5/0.026

(5th FILTER)

8AF RECT 1 3.9/10.106 6/10.168 3.9/6.005 3.9/1.104

5/0.896 7/1.119 5/0.147 5/0.027

Page 77: Expansion of an existing power system - a study

67

---The 5th harmonic filter alone is adequate to control the resonant conditions

in the distribution system. The use of a 7th harmonic filter is mainly to control total

harmonic distribution (THO).

B. TOLERANCES ON CAPACITORS AND REACTORS

The computer program calculates harmonic loading under various

combinations of tolerances on the capacitor banks and the filter reactors The

computer also calculates the currents calculated for each harmonic under the

worst combination of tolerances.

The following tolerances were considered:

Capacitor banks -0 to + 7.5 % Reactors ± 30/0

The specified tolerances for reactors are ± 2%. However, the harmonic

current flow study was conducted with ± 3% tolerance to allow for variations due

to installation, cable connections and manufacturing.

C. TOTAL HARMONIC DISTORTION

The total harmonic voltage and current distortions are defined as:

THD (voltage) =

THD (current) =

h= max

Iv~V2

fh=2

h=max

'Ii12fh=2

(17)

(18)

Page 78: Expansion of an existing power system - a study

68

where

Ih = harmonic current

Zh == harmonic impedance

If == fundamental frequency current

vf == fundamental frequency voltage.

(19)

(20)

(21 )

(22)

The distortion is a function of the amount of harmonic currents flowing

through the systeln. IEEE 519-1981 gives the voltage distribution limits for medium

and high voltage power systems. The following limits are specified in this

standard.

System Voltage Maximum Voltage Distortion

Medium Voltage systems:

2.4 - 69 kv 50/0

High voltage systems:

115 kv and above 1.50/0

The standard does not specify limits of current distortion. Table XXVI shows

that total harmonic current distortion on the 115 kv system should be limited to 4 0/ 0

under normal mill operating conditions.

Page 79: Expansion of an existing power system - a study

69

Table XXVI. MAXIMUM HARMONIC CURRENT DISTORTION IN PERCENTAGE OF

FUNDAMENTAL

(r) HARMONIC ORDER (FOR ODD)

oTO 11 11 TO 17 17 TO 23 23 TO 35 THO

20 4.0 2.0 1.5 0.6 5.0

20 TO 50 7.0 3.5 2.5 1.0 8.0

50 TO 100 10.0 4.5 4.0 1.5 12.0

100 TO 1000 12.0 5.5 5.0 2.0 15.0

IL

D. HARiV10NIC CURRENT FLOVV- -

Harmonic current flow has been studied under a number of switching

conditions vvith the following configurations:

---equal 5th and 7th harmonic filters, each with 7.2 Mvar capacitor

banks.

---unequal 5th and 7th harmonic filters.

---a 5th harmonic filter only.

Page 80: Expansion of an existing power system - a study

70

Table XXVII shows the harmonic current flow study cases with equal 5th and

7th harmonic filters. A sumrnary of the study results with equal 5th and 7th

harmonic filters is shown in Table XXVIII and XXIX. Harmonic current, and voltages

up to 11th harmonic are only shown in this drawing.

The following conclusions can be drawn from the study results summarized in

Table XXVIII and XXIX.

---Without harmonic filters connected to the distribution system, the voltage

distortion on 13.8 kv buses C & G will be 13.5% and 7% on the 115 kv bus. This

exceeds the permissible limits specified in IEEE 519-1981.

---The installation of 5th and 7th harmonic filters provides lower THD than a

5th harmonic filter alone.

---The computer program calculates a unit P.U. fundamental voltage in the

presence of filter reactors. This is not correct,as the presence of a filter reactor in

series with a capacitor will raise the fundamental voltage on the capacitor banks.

l-his discrepancy in the conlputer program was corrected for some of the

calculations. The computer calculations which do not allow for the rise in

fundamental frequency voltage have been identified in Table XXVIII and XXIX.

Page 81: Expansion of an existing power system - a study

Ta

ble

XX

VII

.DE

SC

RIP

TIO

NO

FS

TU

DY

CA

SE

SFO

RTW

OE

QU

A.L

5TH

AN

D7T

HH

AR

MO

NIC

FIL

TE

RS

CA

SE

5TH

7TH

FIL

TER

SW

ITH

BR

EA

KE

RS

TA

TU

SN

o.2

NO

.HARMO~~IC

HA

RM

ON

ICTUR~~ING

XF

RM

RG

EN

FIL

TE

RF

ILT

ER

FRE

Q.

G0

VM

HJ

RE

AC

TO

R

1A

RIN

IN4.

7/7.

2N

O0

0C

CC

OU

TI

2AR

ININ

4.7/

7.2

NO

00

CC

CIN

2BR

ININ

4.7/

7.2

NO

0a

cc

CIN

3A

RIN

OU

T4.

7/--

NO

00

cc

CIN

4AR

INO

UT

4.7/

--YE

S0

0c

cC

IN

5AR

ININ

4.7/

7.2

YES

00

cc

CIN

6AR

OU

TO

UT

--/-

-N

Oa

0c

cC

IN

7AR

ININ

4.7/

7.2

NO

C0

C0

CO

UT

BAR

INO

UT

4.7/

--YE

SC

0C

0C

OU

T

-~.)

Page 82: Expansion of an existing power system - a study

Ta

ble

XX

VII

ISU

MM

AR

YO

FC

AP

AC

ITO

RB

AN

KL

OA

DIN

GS

EQ

UA

L5T

HA

ND

7TH

HA

RM

ON

ICF

ILT

ER

SN

O.1

5TH

HA

RM

ON

ICF

ILT

ER

CA

SE

HA

RM

C)N

ICC

UR

RE

NT

SH

AR

MO

NIC

VO

LT

AG

ES

RS

SS

UM

RS

SKV

ARN

O.

FD

57

11F

D5

711

(V)

(V)

1A

R3

12

.92

48

.99

.89

.81

.15

5.0

05.0

03

1.0

12

1.1

65

1.2

79

82

48

2A\R

31

2.9

25

913

.110

.21

.16

.00

6.0

03

1.0

13

1.1

72

1.2

99

85

07

2B

R3

18

.72

65

.410

.19.

31

.05

.16

8.0

05

.00

31

.06

31

.22

91

.30

29

12

6

3A

R3

12

.91

73

.56

5.7

21

.61

.11

5.0

31.0

06

1.0

07

1.1

59

1.1

66

7991

4A

R3

12

.91

60

.55

0.5

15

.81

.10

6.0

24.0

05

1.0

06

1.1

41

.13

77

90

3

5A

R3

12

.919

9.1

10

.48

.41

.13

2.0

05

.00

31

.00

91

.14

21

.18

68

08

7

6A

R--

--O

UT

OF

SE

RV

ICE

----

-

7A

R3

12

.92

18

11

.69

.21

.14

5.0

06

.00

31.

011

.15

61

.22

82

07

8A

R3

12

.91

65

.34

5.3

13.7

1.1

1.0

21.0

04

1.0

06

1.1

39

1.14

179

21

-Jt~

Page 83: Expansion of an existing power system - a study

Ta

ble

XX

IX.

SU

MM

AR

YO

FC

AP

AC

ITO

RB

AN

KL

OA

DIN

GS

EQ

tJ/\

L5T

HA

ND

7TH

HA

RM

ON

ICF

ILT

ER

SN

O.2

5TH

HA

RM

ON

ICF

ILT

ER

TH

DT

HO

CA

SE

HARMO~lIC

CU

RR

EN

TS

HA

RM

ON

ICV

OL

TA

GE

SR

SS

SU

MR

SS

K'!

('.R

11

5K

VB

US

ES

NO

.F

D5

711

FD

57

11(V

)(V

)I&

VC

&G

/V

~AR

31

2.9

14

4.2

14

5.5

30

.91

.08

9.0

69

.00

91

.00

61

.17

61.

201

80

37

.03

4/.

00

7.0

47

2A

R3

12

.91

67

.61

51

.53

1.5

1.1

03

.07

2.0

09

1.0

08

1.1

93

1.2

48

16

8.0

37

/.0

07

.05

2

2B

R3

09

.61

98

.31

47

.231

1.0

2.·1

25.0

73

.01

1.0

31

.23

61

.28

58

43

6.0

42

/.0

08

.001

3A

R--

----

----

----

-0U

T0

FS

ER

VIC

E--

----

-.0

34

/.0

08

.06

5

4A

R--

----

----

----

-0U

T0

FS

ER

VIC

E--

----

-.0

43

/.0

11

.04

9

5A

R3

12

.91

11

.21

54

.32

6.9

1.0

68

.07

3.0

08

1.0

05

1.1

57

1.1

75

79

35

.04

3/.

00

8.0

37

6A

R--

----

----

----

-0U

T0

FS

ER

VJC

E--

----

-.0

7/-

-.1

35

7A

R3

12

.91

19

.41

72

.92

9.3

1.0

73

.08

2.0

09

1.0

06

1.1

72

1.21

8031

.03

9/.

00

8.0

4

BA

R--

----

----

----

-0U

T0

FS

ER

VIC

E--

----

-.0

47

/.0

11

.04

3

-J

l;.J

Page 84: Expansion of an existing power system - a study

74

---Case 2BR shows the effect of -0 to + 10% tolerance for capacitors on the

harmonic loadings. The increased tolerance detunes the filter and attracts more

harmonic current. A tolerance smaller than -0 to + 7.5% is therefore desirable. An

investigation revealed that capacitor units with -0 to + 50/0 tolerance can be

supplied.

A study of harmonic current flow with unequal capacitor banks was also

conducted. The purpose of th!s study was to optimize harmonic loadings on the

capacitor banks without exceeding current and voltage total harmonic distortions

on 13.8 and 115 kv buses. A tolerance of -0 to +5% for capacitor units was used

for this study.

A summary of the study cases with unequal 5th and 7th harmonic filters is

shown in Table XXX and the results of the study are shown in Table XXXI and

XXXII. The Figure 8 shows the corresponding impedance diagram.

The following conclusions can be drawn from the study results:

---Case 2(1 B) considers only a 5th harmonic filter with a 14.2 Mvar capacitor

bank. However,the voltage distortion on 13.8 kv buses C and G is 4.70/0.

---Case 2(GR) shows the effect of tuning frequency on the harmonic current

loading of the 7th filter. Shifting the tuned frequency of 7th harmonic filter from 7.25

to 6.6 KHz reduces harmonic current loading. However, the THO on 13.8 kV buses

C and G is increased to 4.20/0, compared to 3.4% in case 2FR.

---The harmonic loadings on the capacitor banks in all the cases are well

within the acceptable ratings of the filter banks.

Page 85: Expansion of an existing power system - a study

Ta

ble

XX

X.

DE

SC

RIP

TIO

NO

FS

TU

DY

CA

SE

SFO

RTV

VOU

NE

QU

AL

5TH

AN

D7T

HH

AR

MO

NIC

FIL

TE

RS

CA

SE

5TH

7TH

FIL

TE

RS

WIT

HB

RE

AK

ER

ST

AT

US

No.

2N

O.

HA

RM

ON

ICH

AR

MO

NIC

TU

RN

ING

XF

RM

RG

EN

FIL

TE

RF

ILT

ER

FRE

Q.

G0

VM

HJ

RE

AC

TO

R

2(1

B)

INO

UT

4.7/

--N

O0

0C

CC

IN

14.2

MV

AR

5(2

8)

ININ

4.6/

7.25

NO

00

CC

CIN

9.2M

VA

R4.

6MV

AR

2(6R

)IN

IN4.

6/6.

6N

OC

0C

CC

IN

9.2M

VA

R4.

6MV

AR

2F

RIN

IN4.

6/7.

25N

O0

0C

CC

IN

9.2M

VA

R4.

6MV

AR

-.) Vl

Page 86: Expansion of an existing power system - a study

Ta

ble

XX

XI.

SU

MM

f4.R

YO

FC

AP

AC

ITC

)RB

AN

KL

OA

DiN

GS

UN

EQ

UA

L5T

HA

ND

7TH

HA

Rr\

10

NIC

FIL

TE

RS

NO

.1

5TH

HA

RM

ON

ICF

ILT

ER

CA

SE

HA

RM

ON

ICC

UR

RE

NT

SH

AR

MC

)NIC

VO

LT

AG

ES

RS

SS

UM

KV

AR

NO

.F

D5

711

FD5

711

(V)

(V)

2(1

B)

60

8.6

18

0.9

83.7

29

.41.

05.0

63

.021

.00

51

.05

21

.14

21

.05

41

52

39

2(F

R)

41

5.2

19

8.2

27

.41

3.9

1.05

.10

3.0

1.0

03

1.05

51.

169

1.11

110

907

5(2

8)

41

5.2

17

9.9

3111

.71.

05.0

93

.011

.00

31,

054

1.16

1.0

93

10

82

4

2(G

R)

41

5.2

21

1.3

26

.81

5.6

1.0

5.1

09

.01

.00

41

.05

51

.17

61

.12

510

971

-.) 0\

Page 87: Expansion of an existing power system - a study

Ta

ble

XX

XII

.SU

MM

AR

YO

FC

AP

AC

ITO

RB

AN

KLC'A[)I~JGS

UN

EQ

UA

L5T

HA

ND

7TH

HA

RM

ON

ICF

ILT

ER

SN

O.2

5TH

HAR~v'ONIC

FIL

TE

R

CA

SE

HA

RM

ON

ICC

UR

RE

NT

SN

O.

FD5

711

HARMO~JIC

VO

LTA

GE

SFD

57

11

TH

DT

HD

RS

SS

UM

RS

SK

VA

R11

5KV

BU

SE

S(V

)(V

)I&

VC

&G

/V

2(1

8)

---O

NL

Y5T~,

FIL

TE

RIN

ST

AL

LE

D--

.OO

?

.027

2(F

R)

201.

756

.617

4.6

24.5

1.02

.056

.129

.012

1.02

91.

227

1.36

5532

.006

.026

5(2

8)

201.

?47

.519

7.5

20.8

1.02

.047

.146

.01

1.03

11.

231

1.42

556

53.O

O?

.034

2(G

R)

202.

478

.610

2.4

20.4

1.02

3.0

78.0

76.0

11.

029

1.19

61.

193

5293

.006

.029

.047

.039

.034

.042

-J

-.J

Page 88: Expansion of an existing power system - a study

.00

57

(SO

UR

CE

).0

57

01

15

KV

XFR

MR

0.0

221

.40

18

1J.8

KV

XFR

MR

C.0

219

.40

23

(NO

)V

XFR

MR

G3

,00

48

.14

81

G3 U

.00

23

2.2

30

9'j'

BUSE

SC

AND

G

.00

53

.26

25

XFR

MR

A.0

45

0.6

51

4

BUSE

S0

AA

ND

8

XFR

MR

8.0

20

7.3

80

3G

2

0.01

03

.00

16

.44

15

.13

13

IM

0H

0J

,3,8

KV

I

XFR

MR

E.0

64

6.9

37

8

7.2K

VB

US

ES

EA

ND

F

M1

.02

42

.66

70

t.~2

.23

'01

,69

7

BUS

,.5

42

55

0V

·J.

79

5

.031

011

997

.01

37

l,0

06

8.6

838

.34

25

TT

6.91

MVA

RBU

S2

.

480V

tvL3

.01

a5

.333

.3

BUS

348

0V

.051

.46

2

~,i4

.04

41.

235

-0TO

+10

%±J/~

TOLE

RA

NC

E:

CA

P.

RE

AC

.

9750

KV

A

1250

KV

A26~OOKVA

5TH

HARM

ONIC

CHAN

GED

TOFI

LTE

R5T

HH

AR

MO

NIC

Q=

50

FILT

ER

BAN

K1

(CAS

E2C

R).0

242

----

P.U

,RE

SIS

TAN

CE

.66

70

----

P.U

.RE

AC

TAN

CE

ALL

RE

SIS

TAN

CE

SAN

DR

EA

CTA

NC

ES

ARE

ON10

0MV

ABA

SEAT

60

HER

TZM

1,M

2,M

3,M

4A

RE

EO

UIV

ALE

NT

MO

TOR

LOA

DS

Fig

ure

8.Im

pe

da

nce

Dia

gra

mfo

rU

ne

qu

al

5th

an

d7

thF

ilte

rs-J

00

Page 89: Expansion of an existing power system - a study

79

E. CONCLUSIONS

A 5th harmonic filter with a 9.2 Mvar capacitor bank and a 7th harmonic filter

with a 4.6 Mvar capacitor bank provides acceptable bank loading. The harmonic

voltage and current on the 13.8 and 115 kV buses under various switching

conditions are below the limits specified in IEEE/ANSI standards.

Page 90: Expansion of an existing power system - a study

80

VII. CAPi\CITOR BA~K CONTROL

A. INTRODUCTION

The selection of appropriate controls for the capacitor bank switching should

be based upon ease of system operation, reliability and maintainability. The

following types of controls can be considered:

---'Joltage control : A simple voltage relay may be used to switch the

capacitors 'on' if the voltage drops to a present level and switch the capacitors

'off' above a second present level.

---Current control: The capacitors are connected to the system during heavy

load. This control is similar to the voltage control, except that current level sensing

is adopted to switch the capacitors 'on' and 'off'.

---VAR Control: The control determines the Mvar loading at a given point in

the system. The control is thus responsive to power factor of the load also.

--·-VAR conlrol is recomnlended for control of the capacitor banks due to its

obvious merits.

B. CONTROL STRATEGY

A logic diagram of the var control of the capacitor bank breaker is shown in

Figure 9. The main features of this control are described below:

---The Mvar loading of bus G is converted into a 0-1 mA signal through a var

transducer. A summation current transformer is used to add the input currents in

the 2000 AMPS tie breaker and the future 2000 AMPS utility transformer tie

breaker.

Page 91: Expansion of an existing power system - a study

--IB

-J

...P

BU

SUND[F~VOlTACE

TRIP

IRI

_~

LOC

AL9

-B

TR

IPC

AP

AC

ITO

R

B-

.~

OR

.--~

cor~TROL

BR

KR

.----

OR

----

I

rI

"rI~..E

(Ir.-

L..\

YT

RIP

0r.

'l",'-J'~""

',

1-

10

l.llli

)

RE~lor

E-_

_I<

[Y~JT

ERLOCI

<~_~

'''------a'~

08

68

Rt.S

t.TTO

·CLO

SE~

~S6

RES

ETC

AP

AC

ITO

RA~\JD

I~J

CO

NTR

OL

8RK

R.

---

"EY

~,nE

RLOC

KI

_..

J

5TH

CAP

ACIT

OR

rUS

EFA

ILU

RE

OV

ER

VO

lTA

CE

REL

AY(B

US

)

GROUI~O

FAU

LTR

ELA

Y

C'lE

RC

UR

RE

Nl

~:ELAY

BU

SD

IFF

ER

EN

llAL

REL

A.Y

7TH

CA

PA

CIT

OR

FUS

EFA

ILU

RE

..I

SU

MM

ATI

ON

TRA

NS

tOR

ME

RS

TRA

NS

MIT

IER

,-30

0SE

CTI

ME

DEL

AYI

Ij

TIM

ED

ELAY

TOB

US

P.T

S\

lOW

-HIG

HC

UR

REN

TC

ON

TRO

LLER

TOC

.TZO

OO

ATI

E8R

KR.

\~

TOC

.i2

00

0A

G-

TRA

NS

FOR

ME

RTI

E8R

KR

.

AUTO

CLOS

E

52C

SRE

MO

TED--~

CLOS

E

Fig

ure

9.C

ap

aci

tor

Ba

nk

Bre

ake

rC

on

tro

lL

og

icD

iag

rgm

z

Page 92: Expansion of an existing power system - a study

82

---A high-low current controller output activates two time-delays, adjustable

1-300 seconds, to prevent repeated switching of the capacitor banks on transient

loads. The low set point, after a present time-delay, trips the capacitor breaker.

Similarly, the high set point, after a present time-delay, closes the capacitor

breaker.

The voltage on 13.8 kV Bus G rise approximately 5.6 % upon energizing the

capacitor banks. The high set point VIii I be controlled so that the voltage on 13.8 kV

bus G is approximately 2% below rated voltage when the capacitors are

energized. A time delay is provided to prevent the capacitor banks from being

energized within 5 minutes of tripping.

The filter reactors introduce sufficient impedance in the capacitor bank circuit

to limit the magnitude of switching currents. Abnormal notching in the 13.8 kV

supply voltage upon energizing the capacitor banks is not expected.

c. INTERLOCKING REQUIREMENTS FOR 13.8 KV CIRCUIT BREAKERS

The installation of a new tie transformer will introduce additional interlocking

requirement, to limit fault currents to levels within the short-circuit rating of the

13.8 kV circuit breakers. Though this is a matter of detailed design, these

interlocks are briefly described as follows:

Transformer D, C, and G secondary tie breakers should be so interlocked that only

two of these transformers can be operated in parallel at any time.

Interlocks should be provided to ensure that reactor-tie breaker 0 on bus B is

closed only if:

---No.2 generator or transformer B is out of service

Page 93: Expansion of an existing power system - a study

83

---Tie breaker 0' between buses C and G is open-

---Tie breaker V between buses D and C is open

It is important to note that a detailed short-circuit study will be required to

ensure that none of 13.8 kV circuit breakers are exposed to short circuit currents

exceeding their ratings.

Page 94: Expansion of an existing power system - a study

84

VIII. RE.SlJLTS

A. FINDINGS

The existing system will be able to serve a load growth of approximately 17

MVA associated with stage 1 of the plant expansions. However, the voltage taps on

the primary side of the utility tie transformers serving the 13.8 kV load buses will

have to be set 1;) their lovvest setting. Some of the unit substations served by the

13.8 kV buses may require primary side tap changes to compensate for below

normal voltage levels. If No.3 generator is operating at rated output concurrent

with stage 1 load growth, tap changes on unit substations will be minimized.

The distribution system should be able to serve a fLirther load growth of

approximately 6 MVA associated with Stage 2 of the plant expansions. However,

pr:rnary side tap changes on some unit substations may be required to

compensate for below normal voltage levels. With No. 3 generator operating at

rated output, the voltage on 13.8 kV buses C and G will be approximately 3.8

pE'rCt~nt below rated voltage. The other 13.8 kV buses will be approximately 1.4 to

1.7 percent below rated voltage. The utility tie transformers will not be overloaded

during normal operations.

'The distribution system will not be able to serve the load growth associated

with Stage 3 of the plant expansions. The normal voltage levels on the 13.8 kV

buses will range from 3.0 to 10.1 percent below rated voltage, even with generator

~~os. 2 and 3 in operation. These voltage levels are not appropriate for continuous

plant operations.

It will be possible to serve the load growth of Stage 3 with the addition of a 7

Mvar capacitor bank to bus D and two 7 Mvar capacitor banks to bus G. The sizes

of the capacitor banks will require a series reactor to form a filter for harmonic

Page 95: Expansion of an existing power system - a study

85

currents. The capacitor banks v/ill improve the voltages on the 13.8 kV buses to

acceptable levels and permit the mill to operate at the rated capacity. However,

this system has serious limitations. Upon failure of a major source, like

transformer B, C or D, widespread shutdowns will occur. The process cannot be

restored to rated production due to lack of reserve capacity in the system.

A new 20/37.33 MVA utility tie transformer, connected to 13.8 kV bus G and

operated in parallel with transformer C, will improve normal operating voltage

levels on the 13.8 kV buses. However, the capacitor banks described above will

still be required. They are needed to provide acceptable operating bus voltages

and limit the initial voltage drops upon loss of a source..The addition of a new

transformer offers the following advantages:

---The entire No.4 paper machine load can be fed from 13.8 kV bus G.

VJithout the new transformer, the No.4 paper machine will be fed from buses B

and G.

__v,.; sudden loss of transformer A, or generator No.2 or 3, should not cause a

!l1ajor process disruption. Loss of utility tie transformers B, C or G may result in

overloading of other sources in service. However, appropriate switching operations

olay perrrdt plant operations a1 the rated output.

---Since bus D is operated as an island, a sudden loss of transformer D will

result in a shutdown of the loads served by this bus. The process can be restored

by closing bus tie breaker V between buses C and D.

It will be necessary to operate No.2 generator with an output of atleast 8.4

MW and 16 Mvar to support the load growth of Stages 1, 2 and 3. The load flow

calculations demonstrate that excessive voltage drops will be experienced on 13.8

kV buses A and B when No.2 generator is out of service.

Page 96: Expansion of an existing power system - a study

86

There are no voltage problems associated with 7.2 kV buses E and F. The

loads on these buses remain unchanged through Stage 3 load growth. These

buses serve the grinders.

The results of the harmonic analysis study indicate that:

---Tuning reactors are required with the capacitor banks. Without tuning

reactors the harmonic loadings on the capacitor banks will be excesstve.

---Various switching conditions may result in resonance at the 5th and 7th

harmonic frequencies.

---Resonance at frequencies higher than 7th harmonic does not occur.

---One 5th harmonic filter is adequate to control resonant conditions in the

distributed system. However, the use of the 5th and 7th harmonic filters gives a

lower total harmonic distortion (THD) on the 155 kV and 13.8 kV buses. With 5th

and 7th filters the THO on these buses is within the specified limits in ANSI/IEEE

Standard 519.

---Without the use of filters, the THO on 115 kV and 13.8 kV buses will exceed

the specified limits in ANSI/IEEE Standard 519. Although the primary objective of

in~tallation of capacitor banks is to have an acceptable voltage level on load flow,

'~he filter banks also limit the THO, both current and voltage, on 115 kV and 13.8 kV

buses. Cleaner voltage and current waveforms will result in lower harmonic losses

in the distribution system.

---Unequal 5th and 7th harmonic filters give optimum capacitor bank loadings.

The following additional power systems studies are required to confirm that

the new utility tie transformer and the loads can be safely added to the distribution

system and that the system wiil reliably serve the loads:

Page 97: Expansion of an existing power system - a study

87

---5 hort-circu it study.

---Initial voltage drop due to large motor starting on selected buses.

---Load flow study extended to selected 480 and 2400 volt buses.

B. RECOMMENDATIONS

Contingent upon conlpletion of the power system studies, the following are

the possible solutions:

---Install a new 115-13.8 kV, 20/37.33 MVA utility tie transformer on 115 kV bus

1A. The transformer should be connected to 13.8 kV bus G and normally operated

in parallel with transformer C.

---Install fans and oil circulating pumps on utility transformer B, to permit

operation at its maximum MVA rating.

---Utility tie transformers A, 8, C, D and G should be operated on their lowest

primary tap. Transformers E and F should be operated on the + 2.5% tap.

Transformer G3 can be operated on the 13.8 kV tap.

---Operate NO.2 generator at 8.4 MW and 16 Mvar output and NO.3 generator

at its rated output concurrent with Stage 1 load growth.

---Install 5th harmonic and 7th harrnonic filters on the 13.8 kV buses C and G.

The 5th harmonic filter should have a 9.2 rv1var capacitor bank. The 7th should

have 4.6 Mvar capacitor bank. These filters will be controlled by a single circuit

breaker on bus G.

Page 98: Expansion of an existing power system - a study

88

---The distribution system can be operated without the 7th harmonic filter. The

system should not be operated without the 5th harmonic filter. However, both

filters should be operated during normal operations to provide reactive power for

13.8 kV buses C and G.

---Install interlocking on the utility tie transformer 13.8 kV circuit breakers and

bus tie circuit breakers as outlined in chapter 5.3.

---Conduct a short-circuit study on each of the major 0.48, 2.4 and 13.8 kV

buses. This study should compare the available fault currents with the short-circuit

current ratings of the system's switching devices and cables.

---Conduct large motor starting studies on selected buses, to determine initial

voltage drops for various system operating conditions.

---Conduct load flow studies on selected 480 and 2400 volt buses, where

voltage drop problems are anticipated.

Page 99: Expansion of an existing power system - a study

89

BIBIJOGRAPIIY

1. "National Electric Code," - 1988

2. "IEEE Recommended Practice For Electric Power Distribution for Industrial

Plants," STD 141-1976

3. Stagg and EI-Abiad "Computer Methods In Power System Analysis,"

. McGraw-Hili Book Company, 1968

4. John E. Harder and Elton L. Parker "Important Considerations For Capacitor

Applications In The Pulp and Paper Industry," IEEE Transactions of Power

Apparatus and Systerns, Vol. 10, pp 32-43, 1982.

5. "American National Standard for Shunt Power Capacitors," ANSI C55.1, IEEE

"-10.18.

6. D. D. Shipp "Harmonic Analysis For Power Systems Supplying DC Drives,"

IEEE/L6S Pulp and Paper Conference Vol. 7, pp 182-187, 1978.

Page 100: Expansion of an existing power system - a study

90

vrrA

Suresh Arunachalam was born on May 28, 1959, in India. His elementary

education was obtained through the Indian Public School System. He graduated

from the Sengunthar High School, Erode, India in 1976 and obtained the

Pre-University education from Chikkaiah Naicker College, Erode, India in 1977.

In 1977, the author enrolled as a student at P.S.G College of Engineering,

Coimbatore, India, graduating in May, 1982 with a degree of Bachelor of

Engineering in Electrical and Electronics.

From 1982 May to 1986 April, the author was employed in Seshasayee Paper

and Boards Ltd., Erode, India as Project Engineer with experience primarily in

Industrial Power Distribution. In June of 1986, he entered the University of

i\1issouri-Rolla as a full-tirne student. He is a member of IEEE Power Society and

Registered Professional Engineer in Tamil Nadu, India.