experimental evaluation of tendon stress in externally prestressed … · 2018. 10. 10. ·...
TRANSCRIPT
VOL. 13, NO. 18, SEPTEMBER 2018 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences ©2006-2018 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
4840
EXPERIMENTAL EVALUATION OF TENDON STRESS IN EXTERNALLY
PRESTRESSED COMPOSITE ULTRA HIGH PERFORMANCE
CONCRETE-STEEL GIRDER
Abdul Mutlib I. Said
1 and Larah Riyadh Abdulwahed
2
1Department of Civil Engineering, College of Engineering, University of Baghdad, Baghdad, Republic of Iraq 2University of Baghdad, Baghdad, Iraq
E-Mail: [email protected]
ABSTRACT
Experimental programmed was carried out to investigate the influence of external prestress on composite steel I-
girder decks.This program included fabricating and testing twelve scales down 1/4, were designed according to AASHTO
LRFD 2012 standard specification. Each girder was test as simply supported with span of 3.90m and classified in six
groups. The first and second groups consist of two girders have a concrete compressive strength of 50 MPa. The third and
fourth groups consist of two girders of concrete compressive strength of 70MPa. The fifth and sixth groups consist of two
girders of concrete compressive strength of 90MPa.In all groups; the girder has straight eccentricity and deviator at the mid
span. The applied loaded incrementally up to failure under the action of two point loads for each increment of load. The
prestressing force in strand of diameter (12.7 mm) in the girders of group (1, 3and 5) was (9) Ton (stress equal to 918 MPa
= 0.493 fpu) applied after setting the superimposed dead load on RC deck slab, while in group (2,4and 6) was (7) Ton
(stress equal to 714 MPa = 0.384 fpu). The variables in the experimental investigation were the compressive strength of the
concrete (50, 70, and 90 MPa), level and path of the prestressing force and their paths straight or deviator (80, 120, 160 and
200 mm), with or without deviator and the magnitude of the applied prestressing force (7 Ton and 9Ton). The percentage
increase in stress in external prestress strand from ultimate stress in strand (fpu=1860 MPa) after applying two point loading
were rang from (0.16 to 0.39 fpu of strand).
Keyword: external prestress, composite section, compressive strength.
1. INTRODUCTION
The research work carried out in strengthening or
rehabilitation of existing structures is enormous and covers
various types of elements that are commonly used in
engineering construction [1] and [2]. External prestressing,
initially developed for bridges, is now becoming popular
and applicable for a variety of structural systems [3].
Batchelor and Setya (1971) [4] tested four composite
steel-concrete beams to investigate their general behavior
under static instantaneous and short-term sustained loads.
Three beams were respectively prestressed to 0.7, 0.8 and
0.9 of the specified yield stress of the external prestressing
strands, while the fourth beam was tested without external
prestressing to work as a reference beam. The effects of
the amount of prestressing force, shrinkage, creep and
cracking on the performance of these beams were
investigated. The tests revealed that higher flexural
stiffness and ultimate load capacity were obtained for a
composite steel-concrete beam prestressed with a higher
level of external prestressing force. Chen and Gu (2005)
[5] investigated the ultimate moment and incremental
tendon stress of steel-concrete composite beams
prestressed with external tendons under positive moment.
The load was exerted to the test specimen with a 500 kN
hydraulic jack by a loading beam. It was shown that the
external prestressing increased the yield load and the
ultimate resistance of the composite beams as well as
reducing the deflection at serviceability state. Mousa
(2015)[6] the research is an experimental and theoretical
investigation of using external prestressing technique in
strengthening an existing girder bridge. The experimental
program consists of twelve composite steel-concrete post-
tensioned model girders. Each girder was tested as simply
supported with a span of 3 m and loaded incrementally up
to failure under the action of two point loads. Results of
the experimental investigation showed appreciable
enhancement in the load carrying capacity of the
investigation externally prestressed model girders as
compared to that of the nonprestressed reference girder.
The girders of group one showed percentage increase in
the ultimate load of 7.14%, 36.90% and 45.24% for
prestress force 1 Ton, 3Ton and 5Ton respectively.
2. EXPERIMENTAL PROGRAM
2.1 Manufacturing of the models
The experimental tests were conducted on model
simply supported steel - concrete composite girders. All
models had similar dimensions and in fact they were
selected to be 1/4 scale of the prototype composite bridge
girder, the properties of the model girder section are given
in Table-1 considering three different cases. The
compressive strength 𝑓𝑐′of 50 MPa (Case1), 70 MPa (case
2) and 90 MPa (Case 3). Each model composite test girder
included Steel beam HEA 160 and concrete deck slab of
cross section 300mm x 55mm reinforced with welded wire
fabric WWF (gauge 150mm x 150mm and ϕ 6mm) and
two rows of ϕ 8mm diameter studs (height 40mm) spaced
80mm in transverse direction and the spaced in the
longitudinal direction from the end of the girder are at
50mm at 1200mm, 100mm at 750mm c/c as shown
Figure-1.
VOL. 13, NO. 18, SEPTEMBER 2018 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences ©2006-2018 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
4841
Table-1. Properties of the model girders equivalent steel section.
Case I - Composite with 𝒇𝒄′=50, n=6
Ad2
(mm4)
d (mm)
C.G to NA
Iᵒ (mm
4)
A×Yb
(mm3)
Yb(mm)
centroid
to bottom
A
(mm2)
Size
(mm) Member
1070259.937
1573403.177
19289091.15
27.26236
-44.2376
-115.738
9720
1203052
9720
212400
61104
6480
147.5
76
4.5
1440
804
1440
160 × 9
6 × 134
160 × 9
section HEA160
Top flange
Web
Bottom flange
9658073.882 59.26236 693229.2 493625 179.5 2750 50 × 55
Slab concrete
equivalent to steel
300/n=50
31590828.15 1915721.2 773609 6434 Summation 𝑌𝑏̅̅̅̅ = 120.2376 mm, I NA= 33506549 mm
4, slab width = 300,n =
𝐸𝑠𝐸𝑐
Case II - Composite with𝒇𝒄′=70, n=5
Ad2
(mm4)
d (mm)
C.G to NA
Iᵒ (mm
4)
A×Yb
(mm3)
Yb(mm)
centroid
to bottom
A
(mm2)
Size
(mm) Member
735192.4764
1922897.641
20876079.07
22.59536
-48.9046
-120.405
9720
1203052
9720
212400
61104
6480
147.5
76
4.5
1440
804
1440
160 × 9
6 × 134
160 × 9
section HEA160
Top flange
Web
Bottom flange
9836156.298 54.59536 831875 592350 179.5 3300 60 × 55
Slab concrete
equivalent to steel
300/n=60
3337032549 2054367 872334 6984 Summation 𝑌�̅�=124.9046 mm, I NA= 35424692 mm
4,
Case III - Composite with𝒇𝒄′=90, n=4.5
Ad2
(mm4)
d (mm)
C.G to NA
Iᵒ (mm
4)
A×Yb
(mm3)
Yb(mm)
centroid
to bottom
A
(mm2)
Size
(mm) Member
568800.568
2142804.826
21830198.18
19.87462
-51.6254
-123.125
9720
1203052
9720
212400
61104
6480
147.5
76
4.5
1440
804
1440
160 × 9
6 × 134
160 × 9
section HEA160
Top flange
Web
Bottom flange
9865925.039 51.87462 924213.1 658100.9 179.5 3666.3 66.6×55
Slab concrete
equivalent to steel
300/n=66.6
34407728.61 2146705.1 938084.9 7350.3 Summation 𝑌�̅�=127.6254mm, INA = 36554434 mm
4
VOL. 13, NO. 18, SEPTEMBER 2018 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences ©2006-2018 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
4842
Cross section
(b) Details and distribution of shear connector for Bridge model.
Figure-1. Model steel - concrete composite girder used in experimental tests.
2.2 Concrete mixes Three concrete mixes were designed and prepared
for constructing the reinforced concrete deck slab of the
composite model beams. Mix (1) was high strength
concrete while mix (2) was a high strength concrete and
mix (3) was ultra-high compressive strength concrete [7],
[8] and [9]. The mix properties of the constituents by
weight for these three mixes are listed in Table-2.
Table-2. Properties of the three types of concrete mixes used in deck slab.
Mix Type of
concrete
Mix properties (kg/m3) W/C
ratio
Viscocrete
5930* %
Steel fiber**
%
f'c (MPa)
cylinder
strength Cement Sand silica Water
1 High strength 685 1137 23.5 246.6 0.36 1.5 0.5 50
2 High strength 770 1140 115.5 208 0.27 2.5 0.5 70
3 Ultra-high
strength 925 1000 232 222 0.24 3.5 0.5 90
*percent of cement weight
**percent of mix volume
VOL. 13, NO. 18, SEPTEMBER 2018 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences ©2006-2018 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
4843
2.3 Equivalent loads Before the application of the external prestressing
on the girders, an important criterion was satisfied to get
an exact simulation of the model composite girders with
the prototype composite girder. The equivalent loads were
applied on the model to induce the same longitudinal
bottom steel flange stress as that of the full-scale bridge
due to real self-weight and superimposed dead loads.
Concrete block450mm×300mm×100 will use as an
additional mass to satisfy the simulation requirement of
specific gravity loads. The equivalents (self-weight and
superimposed equal to3.2 kN/m) are used as addition
superimposed dead load which gives the same stress with
prototype.
2.4 Estimation prestress force Figure-2 shows a model of composite beam
subjected to externally longitudinal prestressing force
applied at a level 80 and 120 mm below its bottom flange
face represent the case of straight tendon with constant
eccentricity Figure-(2-a) represent the second case when
use the deviator at mid span at a level 160 and 200mm
below its bottom flange. Each of these two sections is of
0.45 m distance away from the nearer support. The
maximum value of the applied prestress force (Pr) in this
case from the allowable stress in concrete at top fiber at
mid span of composite beam which is calculated as
follows; (𝒏 × 𝒇𝒕= − 𝑷𝒓𝑨 + 𝑷𝒓×𝒆×𝑪𝑰 − 𝑴×𝑪𝑰 ). Tensile
stress 𝒇𝒕in the concrete is equal to 0.4√𝑓𝑐′ according to
ACI code [10] was allowed to induce in the concrete.
Eccentricity (e = 80 or 160mm + Yb') which lead that the
prestress force 𝑷𝒓 equal to (9 Ton) and for (e = 120 or
200mm+ Yb') the prestress force is (7 Ton).
a) without deviator b) with deviator
Figure-2. Location of the external prestress tendon.
2.5 Instrumentation and testing procedure
After the superimposed dead load was applied
(through the use of concrete blocks uniformly distributed
on the top of the model along its full length) the two point
loads were then applied on the model girder in successive
increments, up to failure. Thereafter the prestress tendon
was post–tensioned to the specified force required for the
test as shown in Figure-3. The concentrated load was
subjected on the test model girder specimen through a jack
of the testing machine as shown in Figure-4. After the
preparations were finished and the initial readings of the
dial gauges at mid–span and under point load were taken,
the load was applied with a loading increment rate of
about 5 kN.
Figure-3. Prestress post-tension.
Figure-4. Loading system in the testing machine.
3. RESULTS AND DISCUSSIONS
Table-3 gives a full detailed description of the
experimental results for all the tested composite girders
models of the present investigation.
VOL. 13, NO. 18, SEPTEMBER 2018 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences ©2006-2018 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
4844
Table-3. Experimental test results of the tested models.
Group Symbol Designation
e @ distance
45cm from
end span
e @mid
span by
deviator
𝒇𝒄′ (MPa)
P(kN) ∆u mid span
(mm)
∆u Under point
load (mm)
1
G1 GP9S-e80 80 80
50
210 25.43 21.44
G2 GP9D-e160 80 160 230 26.53 22.68
2
G3 GP7S-e120 120 120 215 25.88 21067
G4 GP7D-e200 120 200 235 26.94 22.82
3
G5 GP9S-e80 80 80
70
260 29.87 25.81
G6 GP9D-e160 80 160 280 33.54 29.74
4
G7 GP7S-e120 120 120 265 30.19 26.68
G8 GP7D-e200 120 200 285 34.12 30.57
5
G9 GP9S-e80 80 80
90
300 43.04 37.42
G10 GP9D-e160 80 160 320 48.31 40.03
6
G11 GP7S-e120 120 120 305 43.97 35.98
G12 GP7D-e200 120 200 325 49.55 42.69
* P = Total applied on two point load (P = 2V)
G = Girder
P9 = the value of the external prestressing force was 9 Tons
P7= the value of the external prestressing force was 7 Tons
S = Strand of prestress represents as straight line
D =Strand of prestress represents by deviator
3.1 Forces and stresses in strands of group (1and 2)
fc' =50 MPa
This group 1 and 2 consists of the four steel -
concrete composite model girders G1, G2, G3and G4
which were designated as GP9S-e80, GP9D-e160, GP7S-
e120, and GP7D-e200 respectively. Each of which was
subjected to an external prestressing force prior to the
gradual application of two–point loading up to failure.
There are two stage of force generated in strand. The first
stage produced by the initial external prestress force of
(7or 9 Ton) and the second stage is generated when the
deflection occur due to the application of two point load.
Strain in strand has been determined by measuring the
reading of strain gauges due to the applied the loads as
shown in Figure-5. On the other hand, stresses and force in
strand are calculated. The load - force (stress) in strand for
these girders are shown in Figure-6.
Figure-5. Measurement of the strand.
VOL. 13, NO. 18, SEPTEMBER 2018 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences ©2006-2018 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
4845
Figure-6. Increment force and stress in the strands after initial external prestress force.
It can be seen from Table-4 the initial force and stress in strand and percentage increases in ultimate force in strand
Table-4. Percentage increase in ultimate force in strand.
Percentage of
increment (Force)
Final stress
MPa
Final force
kN
Initial stress
MPa
Initial force
kN
fc'
Designation Symbol
46% 1339 131.21 918 90
50
GP9S-e80 G1
33% 1219 119.45 918 90 GP9D-e160 G2
69% 1209 118.45 714 70 GP7S-e120 G3
48% 1061 103.94 714 70 GP7D-e200 G4
VOL. 13, NO. 18, SEPTEMBER 2018 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences ©2006-2018 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
4846
3.2 Forces and stresses in strands of group (3and 4)
fc' =70 MPa
This group 3 and 4 consists of the four steel–concrete composite model girders G5, G6, G7and G8
which were designated as GP9S-e80, GP9D-e160, GP7S-
e120, and GP7D-e200 respectively. Each of which was
subjected to an external prestressing force prior to the
gradual application of two–point loading up to failure.
There are two stage of force generated in strand. The first
stage produced by the initial external prestress force of
(7or 9 Ton) and the second stage is generated when the
deflection occur due to the application of two point load.
The load – force (stress) in strand for these girders are
shown in Figure-7. It can be seen from Table-5 the initial
force and stress in strand and percentage increases in
ultimate force in strand.
Figure-7. Increment force and stress in the strands after initial external prestress force.
VOL. 13, NO. 18, SEPTEMBER 2018 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences ©2006-2018 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
4847
Table-5. Percentage increase in ultimate force in strand.
Percentage of increment (Force)
Final stress
MPa
Final force
kN
Initial stress
MPa
Initial force
kN
fc'
Designation Symbol
55% 1421 139.30 918 90
70
GP9S-e80 G5
41% 1299 127.31 918 90 GP9D-e160 G6
82% 1303 127.65 714 70 GP7S-e120 G7
63% 1165 114.13 714 70 GP7D-e200 G8
3.3 Forces and stresses in strands of group (5and 6)
fc' =90 MPa
This group 5 and 6 consists of the four steel -
concrete composite model girders G9, G10, G11and G12
which were designated as GP9S-e80, GP9D-e160, GP7S-
e120, and GP7D-e200 respectively. Each of which was
subjected to an external prestressing force prior to the
gradual application of two–point loading up to failure.
There are two stage of force generated in strand. The first
stage produced by the initial external prestress force of
(7or 9 Ton) and the second stage is generated when the
deflection occur due to the application of two point load.
The load - force (stress) in strand for these girders are
shown in Figure-8. It can be seen from Table- 8 the initial
force and stress in strand and percentage increases in
ultimate force in strand.
VOL. 13, NO. 18, SEPTEMBER 2018 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences ©2006-2018 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
4848
Figure-8. Increment force and stress in the strands after initial external prestress force.
Table-6. Percentage increase in ultimate force in strand.
Percentage of
increment (Force)
Final stress
MPa
Final force
kN
Initial stress
MPa
Initial force
kN
fc'
Designation Symbol
74% 1597 156.51 918 90
90
GP9S-e80 G9
60% 1470 144.07 918 90 GP9D-e160 G10
102% 1448 141.94 714 70 GP7S-e120 G11
86% 1327 130.03 714 70 GP7D-e200 G12
4. CONCLUSIONS
a) The use of 8mm diameter, 40mm height, studs in two
rows along the full length of each tested simply
supported composite steel-concrete model girder was
found adequate to give full interaction between the
RC deck slab and the steel I-beam. This full
interaction was assured by the facts that no shear slip
was produced in the studs nor vertical separation
between the RC deck slab and the steel I-beam was
observed.
b) In composite steel-concrete modeled girders, no
longitudinal cracks were seen in the RC deck slab
during the whole stages of loading. This is because
the ratio of the projected length of the slab to its
thickness was small enough that prevented any action
in the deck slab.
c) The force and stress in prestress strand are increased
after subject the two point loading. Group 1, 3 and 5
were initial force and stress equal to (90 kN and 918
MPa). The final force in strand in group 1 was
reached (131.21 kN and 119.45kN), in group 3
(139.30kN and 127.31kN) and in group 5 (156.51kN
and 144.07kN).The actual stress in external prestress
strand after applied two point loading were (1339,
1219, 1421, 1299, 1597, 1470, MPa) for girders in
group 1, 3 and 5 respectively. The actual increase in
stress in external prestress strand after applied two
point loading were (421, 301, 503, 381, 679, 552
MPa) for girders in group 1, 3 and 5 respectively.
d) Group 2, 4 and 6 were initial force and stress equal to
(70 kN and 714 MPa). The final force in strand in
group 2 was reached (118.45kN and 103.94kN), in
group 4 (127.65kN and 114.13 kN) and in group 6
(141.94kN and 130.03kN). The actual stress in
external prestress strand after applied two point
loading were (1209, 1061, 1303, 1165, 1448, 1327,
MPa) for girders in group 2, 4 and 6 respectively.
The actual increase in stress in external prestress
strand after applied two point loading were (495, 347,
589, 451, 734, 613 MPa) for girders in group 2, 4 and
6 respectively.
e) The percentage increase in stress in external prestress
strand from ultimate stress in strand (fpu=1860 MPa)
after applied two point loading rang from (0.16 to
0.39 fpu of strand).
REFERENCES
[1] Daly F., Witarnawan W. 1997. Strengthening of
Bridges Using External Post-Tensioning. Conference
of Eastern Asia Society for Transportation Studies,
Seoul, Korea.
[2] Abdul MuttalibI. Said, Ali Hussein Ali AL-Ahmed
and Dhafer AL-Fendawy. 2015. Strengthening of
VOL. 13, NO. 18, SEPTEMBER 2018 ISSN 1819-6608
ARPN Journal of Engineering and Applied Sciences ©2006-2018 Asian Research Publishing Network (ARPN). All rights reserved.
www.arpnjournals.com
4849
Reinforced Concrete T- Section Beams Using
External Post-Tensioning Technique. Journal of
Engineering. 21(12): 139-154.
[3] Saadatmanesh H., Albrecht P. and Ayyub B. 1989.
Guidelines for Flexural Design of Prestressed
Composite Beams. Journal of Structural Engineering,
ASCE. 115(11): 2944-2961.
[4] Batchelor D. and Setya S. 1971. Predeflected
Composite Steel-Concrete Beams. Journal of the
American Concrete Institute. 26(1): 26-35.
[5] Chen S. and Gu P. 2005. Load Carrying Capacity of
Composite Beams Prestressed with External Tendons
Under Positive Moment. Journal of Constructional
Steel Research. 61: 515-530.
[6] Mousa M. A. 2015. Strength Investigation of Existing
Plate Girder Bridges by Post-Tension Using Scale
down Models. Ph.D. Thesis, Bagdad University, Iraq.
[7] Prabhat R. Prem, B.H. Bharatkumar and Nagesh R
Lyer. 2012. Mechanical Properties of Ultra High
Performance Concrete. World Academy of Science,
Engineering and Technology. 6(8).
[8] Michigan Tech. 2008. Ultra-High Performance
Concrete for Michigan Bridges Material Performance
- Phase I. FINAL REPORT.
[9] Graybeal B. and Hartman J. 2002. Ultra High
Performance Concrete Material Properties.
Transportation Research Board Conference, USA, pp.
1-14.
[10] ACI 318M-08. 2008. Building Code Requirements for
Structural Concrete (ACI318M-08) and Commentary.
American Concrete Institute, Farmington, Hills,
Michigan, USA. p. 473.