ABSTRACT There are several types of retaining and stabilization structures applied to road
embankments.
The objective of this study is to describe the main criteria and procedures inherent to the
design and subsequent execution of a retaining and stabilization project, different from those
that are generally adopted at a domestically level, on the case of a confirmed slipping
embankment. The complexity associated with the employment of a retaining and stabilization
structure in response to the aforementioned circumstance, in addition to the imperative
assurance of safety conditions along the road travel routes that remain unaffected, determined
the use of various constructive solutions and application of modern technology, predominantly
within the field of geotechnical engineering.
The project under review primarily considers processes of soil stabilization/treatment,
excavation, backfilling, deep drainage and a retaining structure. The solutions adopted for the
completion of these tasks are diverse, including jet grouting technology, micropiles, containment
using big bags and the execution of pavement.
As well as the description of the completed case study, theoretical foundations are
explored in order to understand the discussed techniques. In addition to this, a qualitative
assessment is employed for the evaluation of the various adopted solutions.
A project of this type should ensure maximum safety according to the most various criteria.
For this reason an instrumentation and observation plan, relying on the use of various
monitoring instruments, is employed over and above the use of standard procedures and
search for solutions that make the necessary contributions to safety conditions.
The design of a retaining structure requires expertise in the field of soil
mechanics. Therefore, the intention is to provide the reader with a clear insight into the classical
theories used in the calculation of impulses, massif collapse models and the legislation used in
geotechnical designs of this nature.
1. INTRODUCTION This thesis describes, investigates, analyzes and explains the steps involved in stabilization
of the embankment in motorway A8 at KM92+600.Analysis is conducted from the set up of the
plan for instrumentation and observation to the re-opening of conditioned motorway.It also
presents a theoretical and practical component relative to the conceptualization of the solution
for slope stabilization. The area under study, initially supported by a gabion wall of varying
height, has been the target of instrumentation since 2009 due to the appearance of cracks in
the pavement, indicating small displacements of the embankment that once supported it.
Figure 1.1 – Aerial view of intervention area [1].
On February 9, 2010, a substantial vertical deformation was registered in the motorway
platform, intersecting the land located upstream and downstream of the gabion wall, as shown
in Figure 1.2.
Figure 1.2 – Images of high-way pavement and embankment base on February 9 2010.
1.1. Objectives
This dissertation will be describe and analyze the design criteria adopted in the
implementation and enforcement of the retaining and stabilization structure at KM92 +600 on
motorway A8. Greater emphasis will be placed on the critical analysis of the geotechnical
project. The consequences resulting from the choices made are also verified during
implantation and after work completion.
Taking into account that the retaining and stabilization structure is bound for land that was
already unstabilized, thus requiring the implementation of additional security precautions as well
as the application a constructive model, dissimilar to most conventional solutions adopted in the
retainment of road embankments, it is important to analyze and report on the whole process,
including the soil´s behavior during this process. The study highlights the importance of
instrumentation and observation plan during project execution and after implementation,
N
Gabion Wall Unstable area
3
allowing for the verification and confirmation of some parameter values, pertaining to the safety
and design of the structure. In this sense, an evaluation is carried out on deformations recorded
by various instruments, both in the surrounding buildings, as well as in the new retaining
structure.
2. ADOPTED SOLUTION The chosen solution consists of reinforced concrete wall in console type "L", based on a
curtain of jet grout columns, armed with micropiles pipes. This permits the partial removal of the
initial gabion wall, allowing relief from the burden of land where it also has the same
destabilizing effect, ensuring an excavation height in the order of 9.0 m. In order to improve the
drainage conditions, reduce the destabilizing weight of land and minimize the pulses to be
supported by the structure, a lightweight aggregate was used in the masonry area of the
concrete wall, properly wrapped in a geotextile for separation.
Figure 2.1 - Cut type of solution adopted to stabilize high-way embankment [3].
The slope stability is achieved by increasing the resistant cutting force at the foot of the
slope via the implementation of jet grout columns and microcutting. This structure is established
Scale 1:200
below the sliding surface and on a layer with good resistance characteristics, enabling the
mobilization of an effective shear strength.
An efficient drainage system is essential in this type of structures, since water causes a
serious decrease in shear strength (due to increased interstitial pressures) and a significant
increase in pulses.
3. PROCESS/CONSTRUCTION PHASING The process/construction phasing include the implementation of the different technologies
already discussed, and adopted in the project, also being subject to the critical analysis of
various factors intrinsic to each solution. The aim is to better understand their functionality and
try to increase their productivity. A brief inventory of materials and equipment used in the
different technologies is also carried out.
The instability of the slope in question had as its main external cause in the seasonal
variation of temperature and humidity conditions associated with the foundation of the gabion
wall, which led to the opening of superficial cracks and encouraged the infiltration of water into
the soil. As an internal cause, the increase in interstitial pressures is considered. Due to water
infiltration, they contribute to the reduction of shear strength. As for the intermediate cause there
is the possibility internal erosion caused by the circulation of water within the slope. The likely
combination of these causes actived a simple rotational slide, evidentiating its geometry via the
location of scaring in the crest area of the embankment and base of the slope.
Given the understanding of the constraints and correct perception of what happened a
project was put in place to stabilize the entire area affected by the sliding surface, which
intersects the land at the base of the gabion wall. Domestically, this is an innovative project,
since the jet grouting technique has rarely been used to contain an unstabilized road
embankment, thus increasing the level of interest both in its construction phase, as well as in
the final behavior of the whole retaining structure.
3.1. Work sequence
The construction phasing can be synthesized into 5 phases:
Phase 1 – Work Preparation and embankment excavation
The first phase included the completion of inspections of housing adjacent to the wall base
and removal of buried services located near the work zone. This phase also included
embankment excavation to reduce the destabilizing actions of the gabion wall and the creation
of a work platform. The reduced platform size, in accordance with need to simultaneously
maintain access to the work zone and operation of the roadway in the opposite direction,
5
conditioned the choice of constructive solutions that would determine the appeal of small and
versatile equipment.
Phase 2 – Application of provisional stabilization elements
This phase involved the placement of big bags at the slope´s base, in front of the gabion
wall, and modeling of the work platform to ensure the stabilization of the demonstrated slide.In
an initial phase big bags were only placed along the northern part of the gabion wall, however
after careful consideration of the possible security risks to housing, big bags were placed along
the entire length of the wall.
Phase 3 – Implementation of micropiles and jet grout columns
In this stage, inclined micropiles, made of metal tubing in steel, was introduced, with a
minimum sealing length of 6.0m.
The test grout columns were then put into place, with various dosages of cement. The
grout columns were subsequently implemented, consisting of a retaining curtain, guaranteeing a
phasing that minimizes the impact on the embankment stability. Finally, vertical micropiles
tubes, with 2,60m spacing were placed inside jet grout columns.
Phase 4 – Implementation of reinforced concrete wall
Phase 4 corresponds to the execution of the "L" type concrete wall, properly founded on
micropiles and jet grouting columns and the embankment implementation in the masonry area
of the wall, initially performed with sand from the big bags and subsequently with lightweight
aggregates that were properly compacted and wrapped in geotextile for separation.
This phase also covered operations relating to the partial removal of the gabion wall and
consequent reshaping of the slope. Note that the reshaping of the embankment was carried out
simultaneously to the removal of big bags.
Phase 5 – Reinstatement of high-way platform and implementation of embankment drainage
blanket
In this last phase the high-way platform is reinstated, the draining mask is based at the
bottom of the wall and the roadway is re-open to traffic, its foundation based on a biaxial
geogrid that was in turn positioned on top of the lightweight aggregates.
3.2. Gabion wall
It is essential to describe the characteristics of the gabion wall prior to project execution, as
well as quantify and qualify the type of retentention caused by the wall on the embankment built
upon the site´s natural slope during high-way construction in the year 2000.
Figure 3.1 – Images of gabion wall before (left) e after (right) intervention.
As part of the adopted stabilization solution, the gabion wall is set up under the same
conditions, since its base was not removed.
The performance of the gabion wall of gabions is of paramount in the analysis of slide
causes, to make an observation of the causes of slipping. Its main function was to support the
existing embankment, however it could not perform this efficiently.
The focus point of the critical analysis highlighted in the study for this structure lies in
investigating the conditions of the gabion wall foundation. The foundation of the wall is straight,
formed by the wall, with a support plan consisting of cleaning concrete.
3.3. Provisional embankment stabilization
The big bags were the solution to stabilize the slope on a provisional basis. These worked
by gravity and played an important role in supporting the gabion wall retaining the embankment.
They were also responsible for halting the upward mobilization of soil at the foot of the slope
due to their location in front of the inflection point of the sliding surface.
Figure 3.2 - Detail of the inflection location point on the sliding surface
7
3.4. Microcutting
The application of inclined micropiles has several benefits. In relation to the performance
technique and equipment used, its application causes minimal disturbance in the soil and
requires the use of a small and low weight drilling machine compared to other techniques. From
a structural standpoint, the micropiles present several important factors, such as competence to
operate on traction, improvement of soil properties due to the increase in lateral resistance of
the bulb seal and load transfer from the retaining structure to the competent substrate. It is
concluded that the inclined micropiles not only functions as a stabilizing element, but also as
one that provides important support for the concrete wall in case of sliding and overturning.
3.5. Jet grouting
The implementation of test jet grout columns was determined with to ascertain the obtained
diameters, to visualize the appearance of columns and their geometry, and also to collect
samples for laboratory testing. These confirmed the integrity of the bodies and laboratory
determination of its resistant parameters (strain modulus and compressive strength obtained
through the simple uniaxial compression experiments at 7, 14 and 21 or 28 days).
Five JET 1 type test columns were made ("A" to "E") and distributed in two testing areas.
Figure 3.3 – Implementation of test columns in zone 1 (left) and posterior excavation (right).
The jet grouting type JET 1 ensured the specified geometrical and resistant characteristics
and minimized the impact on the behavior of all structures and infrastructure adjacent to the
work site perimeter.
The jet grouting works as an element which increases the shear strength of the sliding
surface, while also transmitting loads from the wall of reinforced concrete into the consolidated
soil. It is thus responsible for stabilization through the stitching effect of unstabilized soil, thereby
increasing soil resistance and acting on the lateral retention of soil (embankment and natural
landscape). With the aid of the micropiles that is applied inside, their performance is extended in
regards to flexion and traction.
3.6. Reinforced concrete wall
The "L" shaped reinforced concrete wall supports the embankment´s surface area and
consequently the whole high-way platform. Due to its functions, that are vital to the sound
operation of the proposed objectives, its constructive procedure and induced alterations are
described.
3.7. Drainage
The existence of a groundwater table in supported massif is a big disadvantage, since it
substantially increases the total impulse. Many accidents involving retaining walls are, in fact
related to the accumulation of water contained in the soil due to inefficient drainage systems [2].
3.8. Embankment and reinstatement of pavement
This subchapter depicts the final work phase, corresponding to the implementation of the
embankment and the subsequent opening of the roadway platform. The materials used for this
purpose are described in the following cross section (Fig. 3.5).
Figure 3.4 – Cross section (ilustration) of the applied pavement.
4. INSTRUMENTATION AND OBSERVATION PLAN (IOP) The aim of the instrumentation and observation plan (IOP) is centered on the prevention
and management of risks in projects with a strong geotechnical component. It seeks to ensure
completion of the tasks associated with performed interventions, within the defined safety and
economic conditions. The behavioral analysis of adjacent structures and infrastructure after
execution is also intended. Therefore, the IOP was defined from the analysis of the main
conditions that would deemingly be the most likely ultimately affect intervention. The analysis of
these conditions facilitated the quantification of key risks associated with this type of projects.
9
4.1. Topographic targets
Despite many targets having been placed in gabion wall, it is interesting to note that their
readings are not without many errors, however it is a good reference for the perception of soil
disturbance primarily owing to the implementation of jey grouting.
4.2. Fissuremeters
Fissuremeters are devices that measure the displacement (the plan) of a particular fissure,
over time. The applied fissuremeters were not subjected to strict monitoring conditions. With the
implementation of jet grouting to the south, in the garage vicinity, it was found that the
fissuremeters had registered a significant displacement.
4.3. Topographic marks
The topographic marks, used in measuring the surface elevation of the pavements were
sealed directly onto the high-way platform, having a protected target support with protective
cover at its upper end.
It appears that the accumulated displacements were not considered very significant. These do
not have a very disturbing influence on the instrumented area. resulting in deconfinement
phenomena caused by the slide and repair work.
4.4. Inclinometers
The horizontal displacement of the massif in depth and the high-way embankment retention
will be affected by the installation of inclinometric gutters.
The filling between the hole walls and inclinometric gutters was achieved, with material from
the deformation characteristics similar to the land and surrounding concrete. The sealing of the
fixed point at the base of the instrument was completed at a depth of approximately 3.0 m in
competent substrate (NSPT> 60 blow counts).
5. DESIGN CONSIDERATIONS The design of the retaining structure as well as the foundation and soil characteristics was
created through the computer program PLAXIS Professional V.9. This program facilitated the
calculation of structural stress and deformation during of the various project phases, proving to
be an essential tool for the effective behavioral control of the whole structure. The definition of
all parameters involved in this process is a procedure that requires a certain degree of
sensitivity and experience.
Figure 5.1- Deformed finite element mesh corresponding to the final project
In order to understand the mathematical models and calculation techniques applied in the
computer program it is essential to have some theoretical notions of soil mechanics, as well as
the knowledge of current regulations.
5.1. Safety verification (Eurocode 7)
Safety verification implies that actions be lower than resistance, with an adequate
margin. The use of Eurocode 7 allows for the adoption of an appropriate margin through
methodology that relies on partial safety factors.
In the security verification the following ultimate limit states should be considered:
Overall rupture according to surface involving entire wall [GEO];
Rupture by sliding along the base [GEO];
Rupture by overturn [EQU];
Rupture by resistance mobilization of foundation ground [GEO];
Structural Rupture in wall [STR].
5.1.1. Safety verification in relation to overall rupture (Bishop´s method)
Faced with the currently predicament, this is without doubt the most important check to
perform. The problem of safety in relation an overall rupture is considered the safety verification
of a slope, which involves the investigation of the project site and its vicinity. It also takes into
account the effect that the project has on its environment as well as the effect of the environent
on the current object of study.
The analysis of this problem led to the development of various analytical methods for
calculating slope stability. Of the various methods available, the problem in question will be
11
analyzed using Bishop's simplified method of slices method, which applies limit equilibrium
analysis. In order to verify safety the calculation 1 combination 2 approach was employed, a
conditioning combination when at issue is the geotechnical verification. (AC 1 - Combination 2:
A2 + M2 + R1).
Stability verification of Project in question
Note that the PLAXIS Professional V.9 performs this verification using numerical methods.
There are two basic geometries to observe: the one corresponding to the initial project phase
and to the project conclusion. The embankment is considered in drained conditions, without the
presence of water and presenting a circular surface rupture approximate to the surface
estimated in the geotechnical surveys.
The geometry considered for the final Project phase is presented in fig. 5.1.
In the division into slices is necessary to define, first, the critical points: the start and end
points of the surface, the horizontal slope transition point – inclined slope (crest of the slope)
and point of inflection of the curve. It is vital to know the tipping point where the slices to the
right of this point are unstable (negative effect) and to the left are stable (positive effect). The
slope in question has 19 slices and presents the existence of an overload in the order of 10
KN/m2 due to traffic.
Figure 5.2 - Transversal cut in embankment to be analized in fial Project phase by the simplified Bishop method.
The final values obtained from the performed calculations are presented in the following
table:
Table 5.1 - Values of Msd and Mrd obtained using the simplified Bishop method.
CA 1 - combination 2 Mrd [KN.m/m] Msd [KN.m/m]
Simplified Bishop Method 39927,68 25886,33
The resistance moment is far superior to the actuating moment, which means that the
safety condition is verified so it that there is no collapse of the embankment. This can be
confirmed through the established ratio between the resistance moment and actuating moment,
which is 1, 54. The value obtained for the final project phase represents the higher guarantee of
stability than the value usually defined in the project of about 1,5.
6. FINAL CONSIDERATIONS This type of geotechnical Project can be characterized a structure that is permanent
adjustment to geological and surrounding conditions.
It is essential to point out that all the basic elements for implementing the final project
should always be confirmed before and during execution. Therefore, it is essential to highlight
the following points:
Confirmation of the geotechnical zoning and geomechanical characteristics of the land
intervened through the continuous analysis of the same characteristics during the
execution of all the excavation and drilling tasks;
Evidence of dimensions and drainage geometries in existing drainage means to allow
the integration of the proposed drainage systems;
Need to ensure the total lengths, in tandem with the criteria for sealing the micropiles
and jet grout columns in the competent substrate;
The systematic verification of the jet grouting implementation procedures and all
parameters;
Confirmation of all the design and execution assumptions through the implementation of
the Instrumentation and Observation Plan, a proposed management tool in
geotechnical risk, allowing the analysis/prediction of the projects proactive behavior
and, consequently, the timely validation considered.
The implementation of the IOP is becoming common practice and a real asset in the
perception of the behavior of intrinsic agents carrying out a project of this type.
The reduced specificity attributed to the issue of effectiveness in the retention of gabion
walls, as well as the lack of other studies in similar fields, emphasizes the need for further
research in this area. However, it can be stated that the application of a gabion wall as a
13
retaining solution of containment should not be as comprehensive as it has to been past,
deserving further in-depth analysis and a more detailed framework.
Emphasis is placed on the difficulty in correlation between parameters that is needed in
order to obtain the characteristics proposed by the project in the implementation of the jet
grouting. Its application and consequent analysis of the test columns confirmed various
parameters mentioned in the theoretical segment of this study.
7. REFERENCES [1] Sítio da empresa Google earth: http://earth.google.com/intl/pt/ (coordenadas: N39° 29.477` W9° 5.587`), visitado em 25/02/2010.
[2] GUERRA, Nuno – Análise de estruturas geoténicas. Instituto Superior Técnico, Lisboa, 2008.
[3] PINTO, Alexandre; TOMÁSIO, Rui - Projecto de execução, solução de estabilização do aterro – Memória descritiva e justificativa. JetSJ Geotecnia Lda., Lisboa, Março de 2010.
[4] PINTO, Alexandre; TOMÁSIO, Rui - Projecto de execução, solução de estabilização do aterro – Peças desenhadas. JetSJ Geotecnia Lda., Lisboa, Março de2010.
[5] GUERRA, Nuno – Disciplina de fundações de estruturas (parte de estruturas de suporte). Instituto Superior Técnico, Lisboa.