Page 1: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Exterior Restoration and Rehabilitation of Thompson Hall

Presented By:

University of New Hampshire

Goody Clancy

Shawmut Design and Construction

Page 2: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Today’s Agenda

• Team Introductions

• Project Description

• Pre-construction / Construction Schedule

• Preliminary Logistics

• Occupant Concerns / UNH Department Concerns

and Issues / Fire, Police and Life Safety

Page 3: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

University of New Hampshire

Thompson Hall Project Team

Brenda Whitmore, Project Manager

Douglas Bencks, University Architect

Paul Chamberlin, Executive Director, Facilities Design and

Construction

Page 4: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Goody Clancy

Thompson Hall Project Team

• Jean Carroon, Principal

• Lisa Howe, Project Manager

• Beth Sitterly, Architectural Conservator

• John Wathne, Principal

(Structures North Consulting Engineers, Inc.)

Page 5: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Project Description

Page 6: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction
Page 7: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Shawmut Design and Construction

Thompson Hall Project Team

Lee Dellicker, Vice President/Partner

Carl Jay, Director of Historic Preservation

Ryan Lynch, Project Manager

Dave Hayden, Site Superintendent

Steve Kanavich, Senior Estimator

Tim Leblanc, Director of Safety

Page 8: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Occupied Renovation Philosophy

Shawmut Design and Construction brings a very different attitude

to managing construction within occupied environments. We

consider ourselves guests in your institution and instill

this sense of respect with every subcontractor and individual

worker on site.  We firmly believe that what goes on “outside

the construction fence” is just as important as the actual

construction process. We have developed a job site culture with

our superintendents and subcontractors that every person needs to

demonstrate the highest level of sensitivity to the

operational environments .

Page 9: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Project Schedule

• June 2004 – August 2004: Design Development

• August 2004 – October 2004: Final Design

• November 2004 – March 2005: Final Planning

and Subcontractor Procurement

• March 2005 – December 2005: Construction

Page 10: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Preliminary Logistics

• Project Safety

• Subcontractor I.D. Program

• Site Signage

• Communication Methods

Page 11: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Guard Shack

Covered Walkway

Gate

Tree Protection

Emergency Meeting Location

Dumpster

Gate

2 nd Staging Area

Dimond Library

Murkland

Emergency egress routes-

Maintain clear access at

all times

TO BE APPROVEDTO BE APPROVED

Staging with cover to maintain walk way at

porte cochere

Page 12: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

“By acceptance of the Contractor Badge, all personnel have acknowledged the worker decorum policy set forth for this project along with the requirements detailed in the General Requirements

Rider of all subcontracts. If any worker fails to adhere to these policies or behaves inappropriately while on the University of

New Hampshire’s campus, We Reserve The Right to remove any worker from the project.”

Subcontractor I.D. Program

Page 13: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Site Signage

Construction

Vehicles

ONLY

Construction

Deliveries

NEXT GATE

HARD HAT AREA

Authorized Personnel

ONLY

Page 14: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Communication

Page 15: Exterior Restoration and Rehabilitation of Thompson Hall Presented By: University of New Hampshire Goody Clancy Shawmut Design and Construction

Questions?